Tutorial 6.0 (A) 3 Hours
Tutorial 6.0 (A) 3 Hours
1. (a) System Development Life Cycle is a set of activities carried out to develop an information system.
(i) Identify the first two phase in the System Development Life Cycle. [2 marks]
=Planning, Analysis
(ii) System analyst performs two major activities in the design phase. State these two (2) activities.
[2 marks]
=Acquire hardware and software. Develop all of the details design of the new or modified information
system.
(iii) Describe briefly the purpose of the implementation phase. [2 marks]
=Constructing the new or modified system and then deliver it to the user.
2. (a) Rahilah works as a system analyst in Azan Company. She is required to upgrade the company’s
information system in order to solve various problems faced by users. One of her tasks is to construct
interview among users of the system.
(i) Identify the phase in System Development Life Cycle based on the given scenario. [1 mark]
=Analysis.
(ii) List two (2) major activities in the phase mention in 2(a)(i). [2 marks]
=Process modelling, Object modelling
(b) Based on the following statements, identify the phase of System Development Life Cycle. [2 marks]
Statement Phase
3. (a) System Development Life Cycle (SDLC) contains five phases. Refer to DIAGRAM 1 below.
Maintenance
(ii) Describe one (1) activity performed in each phase X and Y. [2 marks]
X Y
Database design. Design the database upon the Train users. Training involving showing users
data dictionary that developed during the exactly how they will use the new hardware and
analysis phase. software in the system. Training methods are
included one-on-one sessions, classroom-style
lectures, and web-based training.
4. (a) Identify the first and the third phase in System Development Life Cycle. [2 marks]
=Planning, Design
(b) Identify the phase of System Development Life Cycle for each of the following statements:
(i) Miss Linda acquires all the hardware and software needed for the development of the student
information system. [1 mark]
=Design.
(ii) Mr. Tony forms a development team for the project. [1 mark]
=Planning
(iii) Dr. Mustafa needs to conduct a study of the project in order to determine if development system should
continue. [1 mark]
=Analysis
5. (a) Give two (2) importance of System Development Life Cycle. [2 marks]
(b) System development often consists of five phases that should follow three general guidelines group
activities into some phases, involve the users and define standards. Each phase consists of some activities
that take place throughout system development. Give one (1) activity for each phase. [2 marks]
Phase Activity
Planning ● Review project request
Analysis (i) Perform detailed analysis
6. (a) There are five phases of the System Development Life Cycle (SDLC) which are planning, analysis, design,
implementation and maintenance. Describe system analysis and system design phases. [4 marks]
=System analysis consists of two major activities, conduct a preliminary investigation, and perform detailed
analysis. System design phase consists of two major activities, acquire hardware and software, and develop all
of the details design of the new or modified information system.
7. (a) List the five (5) phases of a system development life cycle. [5 marks]
=Planning, Analysis, Design, Implementation, Maintenance
(b) Identify which phase of a system development life cycle involved testing the program of the system.
[2 marks]
=Implementation.
9. (a) Identify the step of System Development Life Cycle (SDLC) for student information system based on activity
below: [5 marks]
10. (a) The total number of phases in System Development Life Cycle is five (5) including planning and analysis. List
the other three (3) phases. [3 marks]
=Design, Implementation, Maintenance
11. (a) List and explain two (2) activities involves during the analysis phase.
Activity 1: Process Modelling
Explanation of Activity 2: Combines the data with the processes that act on that data into a
single unit called an object
(b) State the most suitable phase during system development life cycle (SDLC) in the following table.
[3 marks]
Activity Phase
System Prototyping Design
Monitor System Performance Maintenance
Create Data Flow Diagram Analysis
12. (a) Identify the phase in the System Development Life Cycle based on the following conversation among the
system development team members. [4 marks]
13. (a) State the software development life cycle (SDLC) phases based on activities listed below. [4 marks]
(b) Identify the IT positions involved in the IS development based on the roles and responsibilities given below.
[2 marks]
14. Give one (1) main activity of the following specified phases in the software development life cycle (SDLC).
[2 marks]
Analysis Implementation
Conduct a preliminary investigation Develop programs
15. There are four conversion strategies that can be used to migrate from an existing system to a new one.
a) Briefly describe two (2) conversion strategies. [4 marks]
b) Various tests should be performed on a newly developed system. Name two (2) types of tests and describe
their purposes. [4 marks]
Type of Test Purpose
Unit test Verifies that each individual program or object works
by itself
Systems test Verifies that all programs in an application work
together properly
16. Specify the appropriate phase of System Development Life Cycle (SDLC) for the following tasks: [14 marks]
17. Determine the System Development Life Cycle (SDLC) phase based on the following activities: [5 marks]
Activities SDLC Phase
Writing the actual code Design
Provide live support to end users Maintenance
The thought of the idea for the project Planning
Study the system and gather business requirements Analysis
Develop a storyboard Planning
18. There are five (5) phases of System Development Life Cycle (SDLC). State the appropriate phase starting from
A to D in the box given.
[4 marks]
Planning
…………………………………………….
Analysis Analysis
………………………………………… …………………………………………
Implementation Design
…………………………………………
19. Determine the System Development Life Cycle (SDLC) phase based on the following activities in developing a
website. [6 marks]
Activity SDLC Phase
20. (a) Identify and state the suitable step of System Development Life Cycle for the following statement. [5 marks]
Ali is preparing project management plan and others planning documents to start his Planning
project
Chua is preparing to start up the system that has been planned half a year ago Implementation
Roslan transforms all details requirement into a complete detail system Design
Sani involves in a department which eliminates errors in the system during its working Maintenance
life
Advantages Disadvantages
Improve the monitoring and control of large Increase the cost and time of the development.
projects.
Assure the reliability, maintainability and quality Performance of the system cannot be tested before the
of the developed solution or software. completion of the coding.
(c) Various tests should be performed on the newly developed system. Name four (4) types of testing. [4 marks]
Types of Testing
1. Unit test
2. Systems test
3. Integration test
4. Acceptance test
22. Matahari College decided to develop an information system that involves maintaining databases and generates
results of students in the college. The system also needs to produce reports such as reports on performance of
students for every semester, statistics of students that were dismissed and etc. Currently all activities involving
results of students, producing reports and maintaining students’ data and are done manually.
(b) Determine three (3) consequences of not executing the analysis phase in System Development Life Cycle
(SDLC). [3 marks]
=Cannot identify the problem. Designing the system that does not follow the requirements given by the
client.
NOTE:
❖ Terms
➢ Report = Fixability study