Petronas Technical Standards: Geotechnical Engineering For Onshore Facilities
Petronas Technical Standards: Geotechnical Engineering For Onshore Facilities
Petronas Technical Standards: Geotechnical Engineering For Onshore Facilities
PTS 11.13.01
April 2019
FOREWORD
PETRONAS Technical Standards (PTS) has been developed based on the accumulated knowledge,
experience and best practices of the PETRONAS group supplementing National and International
standards where appropriate. The key objective of PTS is to ensure standard technical practice across
the PETRONAS group.
Compliance to PTS is compulsory for PETRONAS-operated facilities and Joint Ventures (JVs) where
PETRONAS has more than fifty percent (50%) shareholding and/or operational control, and includes
all phases of work activities.
Contractors/manufacturers/suppliers who use PTS are solely responsible in ensuring the quality of
work, goods and services meet the required design and engineering standards. In the case where
specific requirements are not covered in the PTS, it is the responsibility of the
Contractors/manufacturers/suppliers to propose other proven or internationally established
standards or practices of the same level of quality and integrity as reflected in the PTS.
In issuing and making the PTS available, PETRONAS is not making any warranty on the accuracy or
completeness of the information contained in PTS. The Contractors/manufacturers/suppliers shall
ensure accuracy and completeness of the PTS used for the intended design and engineering
requirement and shall inform the Owner for any conflicting requirement with other international
codes and technical standards before start of any work.
PETRONAS is the sole copyright holder of PTS. No part of this document may be reproduced, stored
in a retrieval system or transmitted in any form or by any means (electronic, mechanical, recording or
otherwise) or be disclosed by users to any company or person whomsoever, without the prior written
consent of PETRONAS.
The PTS shall be used exclusively for the authorised purpose. The users shall arrange for PTS to be
kept in safe custody and shall ensure its secrecy is maintained and provide satisfactory information to
PETRONAS that this requirement is met.
Table of Contents
1.0 INTRODUCTION ............................................................................................................... 4
1.1 SCOPE ............................................................................................................................ 4
1.2 GLOSSARY OF TERMS..................................................................................................... 4
1.3 SUMMARY OF CHANGES ............................................................................................... 5
2.0 GEOTECHNICAL DESIGN APPROACH.................................................................................. 6
2.1 GENERAL ........................................................................................................................ 6
2.2 DEVELOPMENT OF SUBSURFACE PROFILES................................................................... 6
2.3 FOUNDATION LOADS AND GEOTECHNICAL DESIGN ..................................................... 6
2.4 DESIGN CONSIDERATIONS FOR EARTHQUAKE .............................................................. 6
2.5 EFFECT OF FOUNDATION WORKS ON ADJACENT STRUCTURES.................................... 6
3.0 SHALLOW FOUNDATIONS................................................................................................. 7
3.1 GENERAL ........................................................................................................................ 7
3.2 DESIGN CONSIDERATIONS ............................................................................................. 7
3.3 STABILITY REQUIREMENTS ............................................................................................ 8
3.4 FOUNDATIONS ON HARD GROUND, ROCK, OR CEMENTED SOILS ................................ 8
4.0 DEEP FOUNDATIONS ........................................................................................................ 9
4.1 GENERAL ........................................................................................................................ 9
4.2 PILE DESIGN ................................................................................................................... 9
4.3 PILE MATERIAL ............................................................................................................. 12
5.0 EARTHWORK ................................................................................................................. 14
5.1 GENERAL ...................................................................................................................... 14
5.2 SLOPES ......................................................................................................................... 15
5.3 GROUND IMPROVEMENT ............................................................................................ 17
5.4 DEWATERING SYSTEM ................................................................................................. 19
6.0 RETAINING WALLS ......................................................................................................... 20
6.1 GENERAL ...................................................................................................................... 20
6.2 GRAVITY WALLS ........................................................................................................... 20
6.3 EMBEDDED RETAINING WALLS ................................................................................... 20
6.4 DRAINAGE SYSTEMS .................................................................................................... 21
7.0 BIBLIOGRAPHY............................................................................................................... 22
APPENDIX 1: PILES INSTALLATION AND TESTING ......................................................................... 24
APPENDIX 2: MAINTAINED LOAD TEST PROCEDURE (EXAMPLE) .................................................. 28
1.0 INTRODUCTION
This PTS provides the minimum technical requirements on geotechnical and foundation
engineering for onshore facilities.
1.1 SCOPE
The scope of this PTS is covering shallow foundation, deep foundation, earthwork design
and retaining structures.
No Term Definition
The value of the gross loading intensity for a particular
Ultimate bearing
1 foundation at which the resistance of the soil to
capacity
displacement of the foundation is fully mobilized
The maximum allowable net loading intensity at the
base of the foundation, taking into account the
Allowable bearing
2 ultimate bearing capacity, the amount and kind of
capacity
settlement expected and the ability of the structure
to accommodate this settlement
The load which the pile (or foundation) is designed to
3 Working load
carry
The maximum load to be transferred by the
4 Design load foundation or pile, according to the design of its
superstructure
Load(s) that is in motion, that may vary with time in
5 Dynamic load
magnitude and direction
Repeated or fluctuating stresses, strains, or stress
6 Cyclic load
intensities on structural components
Table 1.1: Specific Definition of Terms
No Abbreviation Description
1 FOS Factor of Safety
This PTS 11.13.01 (April 2019) replaces PTS 11.13.01 (December 2018).
2.1 GENERAL
This PTS provides minimum requirements for allowable stress design based on BS 8004:1986.
Unless otherwise agreed by Owner, LRFD method based on AISC can be adopted for the
purpose of geotechnical design approach.
Geological desk study shall be performed to determine the profiles and variability of the soil
strata, the groundwater pressures in the various strata and other factors interacting with the
proposed work or structure. Reference shall be made to PTS 11.11.01.
Loading on foundation shall be derived in accordance with PTS. 11.10.01 taking into account
distribution, direction and eccentricity of the loads. Geotechnical design shall be in accordance
with BS 8004 or approved equivalent. Geotechnical design of coastal structures shall be in
accordance with BS 6349 or approved equivalent. FOS used shall be as specified in this PTS.
Unless otherwise requested by Owner, BS EN 1997 shall be adopted for geotechnical design.
Reference shall be made to PTS 11.10.02 for seismic hazard assessment and BS EN 1998-1 or
approved equivalent for seismic resistance design.
ii. Estimation of the effect on and the response of these buildings, structures and
services as a result of foundation works
iii. Proposals of the preventive measures, monitoring scheme and contingency plans
to be undertaken before and during construction
3.1 GENERAL
Shallow foundation in the context of this PTS shall include foundations that are placed directly
on the ground surface without embedment and embedded foundation with a maximum depth
of less than the shortest plan dimension. This include strip, pad and raft foundations.
i. An adequate structurally sound bearing stratum shall be reached under the area
of the foundation
ii. Below the zone where shrinkage and swelling due to seasonal weather changes
iii. Below the zone in which problem may be expected from frost
Ultimate bearing capacity shall be calculated taking into account the distribution of stresses
in the subsoil. Refer to BS 8004 or equivalent codes for bearing capacity calculation.
A minimum FOS of 2.0 shall be adopted with respect to the ultimate bearing capacity provided
soil investigation have been performed. Additional relevant loading test shall be performed
for purpose of storage tanks as required by Owner. FOS of 1.5 can be considered for
temporary structures if risk can be demonstrated to be ALARP.
3.2.4 Settlement
Total and differential settlement of the structure shall be calculated and to consider all
components of settlement i.e. immediate, primary consolidation and secondary consolidation
settlements. Refer to BS 8004 or equivalent codes for settlement calculation.
ii. For building and other structures: 25mm total settlement and 12.5 mm
differential settlement
For foundation supporting sensitive structure or equipment e.g. tank, special equipment,
vibratory machineries, etc. the total and differential settlement shall be as per requirement
from the manufacturer (if more stringent than the above) or as specified by Owner.
3.3.1 General
Overturning 1.5
Sliding 1.5
Buoyancy* 1.1
Table 3.1: Shallow foundation stability requirements
NOTE(S): *Against buoyancy, only permanent dead loads shall be considered
3.4.1 General
From the site investigation and geological assessment, the rock below the foundation shall be
verified to be free from any unknown discontinuities. The foundations shall not be constructed
on weak layers e.g. fault zones, rock decomposition, rock fracturing etc.
The top level of bearing rock shall be defined in the design and the encountered rock mass
during construction shall be further evaluated to ascertain the design assumption.
The structure shall not be founded partly on sound rock and partly on soil or weak rock.
For the backfilling underneath foundation, the backfilling material shall have a similar stiffness
as the rock underneath or other part of foundation.
For foundation on rocks or cemented soils, the following engineering parameter shall be
evaluated for the design purpose: -
A minimum FOS of 2.0 shall be adopted with respect to the ultimate bearing capacity provided
soil investigation in rock have been performed.
4.1 GENERAL
Deep foundation shall be selected over shallow foundation when poor soil condition is
subjected to a design load resulting in low bearing capacity and excessive settlement.
Normally piled foundation is used as deep foundation.
Refer to Appendix 1 for pile selection and advantages and disadvantages of various pile types.
Minimum FOS of 2.5 for ultimate pile capacity shall be adopted provided soil investigation and
pile load test are performed.
For skin friction or bond strength in rock, minimum socket depth shall be 2.5m. Pile shall not
be terminated in boulders.
Refer to section 4.2.5 for negative skin friction, 4.2.8 for tension pile and 4.2.10 for laterally
loaded pile.
Based on BS 8004, allowance of 75mm should be considered in pile group design of pile caps
to ensure position of the individual piles is still within the tolerable limit.
For precast pile, structural pile capacity can be obtained from manufacturer. For bored pile or
micropile, structural pile capacity shall be determined by calculation.
Pile working load is the load which pile is designed to carry. It shall be adopted based on
geotechnical capacity and shall not exceed structural capacity. This shall be verified based on
verification test.
Prior to finalize the pile design, a pilot pile program should be performed to verify the design
length.
Pile spacing, length and size shall be designed based on pile working load.
Where pile is driven into cohesive soil that is subjected to settlement, the negative skin friction
resulted under this condition shall be calculated.
i. Ultimate friction between soil and pile shaft over the full depth of the settling
layers
Pile settlement shall be calculated and the acceptance shall be based on pile load test results.
Refer to section 4.6 in this PTS.
Pile group-effects shall be checked when the centre-to-centre spacing are of less than 3 times
the diameter of the piles as specified in BS 8004.
In such case the bearing capacity and settlement pile group shall not be taken as the
summation of bearing capacity of single piles within the group. A group reduction factor
determined by recognized foundation engineering principles shall be applied to the total
allowable load carrying capacities of any group of piles.
i. Individual piles
The ultimate pulling capacity of an individual pile shall be calculated and the pile
rise shall be predicted as a function of the load.
The working load i.e. design load minus the (submerged) pile weight - under static
conditions shall include FOS of minimum 2.5 with respect to the ultimate capacity
provided soil investigation has been performed.
Where piles are subjected to dynamic loads which are cyclic in nature, the pile response to
the loads shall be studied.
When piles are subjected to this load, the following shall be given careful attention;
ii. The influence of cyclic loading on the axial stiffness of the pile-soil system
The degradation factor of the piles shall be determined. The sum of static and cyclic load
should be kept below 75% of the pile ultimate capacity to avoid large cumulative settlements.
As a minimum requirement it shall be analysed whether the cyclic character of the load
requires reducing of the maximum allowable load when both of the following two conditions
apply:
i. Maximum (peak) load is more than 75% of the allowable static load
ii. Peak to peak load cycle is more than 50% of the maximum load
The following shall be taken into account when performing the analysis;
ii. Stiffness of the pile, ratio of pile (equivalent) diameter to the length
All foundation system founded on thick soft compressible soil layer shall be designed to take
into consideration the possible lateral soil movement due to consolidation process. The
eccentric load induced by possible out-of-tolerance installation of load and/or piles shall be
analyzed and taken into consideration in designing the foundation system.
Pile lateral load capacity shall be determined by considering two different failure mechanisms:
i. Structural failure of the pile due to yielding of pile material or shear failure of the
confining soil due to yielding of soil.
For piles spaced less than eight times the pile width apart, group effects shall be considered.
Before installation of driven piles driveability analysis shall be carried out to investigate the
feasibility of installing the piles with the proposed hammer to ensure that the piles will not
experience structural failure. Risks of pile damage or misalignment due, for example, to
boulders or sloping surfaces shall be assessed. For this purpose, wave analysis method which
represent the soil-pile model is recommended.
In some cases, piles may become exposed to aggressive environment, tidal action (wetting
and drying) due to soil or groundwater condition, for example due to high contents of acid,
sulphates or chlorides, or due to soil oxidation etc.
The following protective measures (separately or in combination) should then be considered:
ii. Application of steel piles with coating of (the relevant part of) the pile surface
4.2.13 Heave
Driving a relatively large number of pile in a relatively small area where the sub-soil consists
of predominantly saturated stiff cohesive soil would potentially be subjected to heaving of
piles which have already been driven.
When such condition is encountered while performing the soil investigation, care shall be
taken into considering the potential tension in the piles induced by the heave action.
Preboring may be applied in this circumstances to reduce the effect from heaving if necessary.
i. General
The design shall take into account all loading conditions, including pile driving,
handling/pitching and transport.
The design shall comply with BS8004 and BS8110 or approved equivalent.
The steel reinforcement shall be designed in such a way that the crack width of
the concrete will remain less than 0.2 mm under all loading conditions. The total
minimum percentage of reinforcement shall be 1.5%.
The maximum slenderness ratio of pile, L/D shall not exceed 100.
The design shall be such that the crack width of the concrete will remain less than
0.05 mm under all loading conditions.
Concrete for cast in-situ piles shall have minimum compressive strength of 40N/mm2 at 28
days. Detail concrete and quality monitoring requirement, shall comply with PTS 11.15.03.
When steel tubular piles are used, the material of the piles shall be of steel grade S355 in
accordance with BS 5950 or approved equivalent.
If these pile are to be driven into rock formation, the bottom tip of the piles shall be
strengthened by means of providing pile shoes either external or internal.
The manufacturing of these piles shall be under close supervision by a third party qualified
inspector internationally accredited and shall be in accordance with BS 5950 and BS 4360 or
approved equivalent.
For application on jetty structure, corrosion protection of the steel pile shall be provided by
a cathodic protection system for the section under water and protective coatings on section
in the splash zone and above in accordance with PTS 15.20.03.
5.0 EARTHWORK
5.1 GENERAL
For Health, Safety & Environment (HSE) requirement related to excavation for brownfield and
greenfield work, reference shall be made to PTS 18.52.18.
Before performing earthwork activities such as excavation, cut, fill, ground improvement,
dewatering etc., a site investigation shall be carried out with reference to PTS 11.11.01.
5.1.2 Excavation
Bottom of all excavations pit shall be levelled and well rammed to receive the permanent
structures.
In the case of groundwater head is higher than the bottom level of an excavation, the stability
of the bottom shall be checked. For permanent excavations the bottom stability shall be
maintained with a minimum FOS of 1.2.
Stability of embankment slope for an excavated pit shall in accordance with PTS 18.52.18.
Slope analysis shall be performed to consider a possible surcharge imposed due to excavated
material stored near the top of the slope and, it shall meet the required FOS. If temporary
shoring is required, it shall be properly designed and maintained.
For excavation exceeding 1.5m depth, the slope shall be designed and engineered by
competent person and endorsed by Professional Engineer in accordance to PTS 18.52.18.
Embankments and filled areas shall be designed to have adequate stability against shear
failure and to ensure that any deformation is within acceptable limits.
The strength, deformation and moisture susceptibility of fill material shall be established by
means of:
The Contractor shall demonstrate the suitability of the proposed soil fill material before on-
site application.
The stability of slope and settlements of a fill or embankment shall be evaluated as in section
5.2.
5.2 SLOPES
i. Engineering
The design of slopes shall be in accordance with BS 6031 or approved equivalent.
FOS for slope stability shall be:
Condition Minimum FOS Remarks
Consist of Natural Slope
Temporary Slopes 1.0 during Excavation with
sufficient Drainage
Provide adequate
drainage system and
Permanent Slopes 1.4
slope protection to
prevent slope erosion.
Table 5.1: Engineering Slope Stability
For slope in remote and extreme environment and where impact damage to facilities
is ALARP, then slope stability can meet minimum FOS of 1.2.
Slope stability assessment and slope repair for existing pipeline route in mountainous
region shall be carried out in accordance with PTS 11.12.05.
iii. Seismic
If applicable the design shall consider the seismic effects on slopes. The analyses
of seismic effects on a slope shall include but not limited to:
a) Horizontal and vertical ground accelerations
b) Increasing of pore water pressures
c) Potential of liquefaction
Exposed slope surfaces subjected to potential erosion shall be protected by the following
methods.
For temporary protection:
i. Cover with canvas or tarpaulin sheet from top to toe of the slope.
NOTE(S): *Where applicable, the risk of fire to be considered in selection of long term slope surface protection method.
Drainage system shall be ensured adequate and water flows properly to discharge outlet in
order to avoid water entering slope body and reduce soil strength gradually which could
jeopardize stability of slope.
Slope located near seasonal streams or Permanent River shall be adequately protected against
erosion.
The stability of a slope shall be monitored regularly over a minimum period completion of that
slope. As a minimum, a monthly visual inspection for sign of defects i.e. cracks and
deformations shall be carried out. For major works, monitoring should comprise
measurements of pore water pressure (e.g. by installation of piezometer), settlements (e.g.
by level survey) and horizontal displacements (e.g. by inclinometer), tension cracks (e.g.
extensometer), inclination (e.g. tiltmeter), rainfall data (rain gauge).
5.3.1 General
Ground improvement can be done separately or combination by the following methods not
limited to:
iii. Preloading
v. Stone column
The method selected shall be based on settlement criteria, bearing capacity and stability.
The compaction procedure for fill shall be specified depending on the compaction
criteria and on the following:
a) The origin and nature of the material
b) The placement method
c) The placement water content and its possible variations
d) The initial and final thickness of the lift
e) The local climatic conditions
f) The uniformity of compaction
g) The nature of underlying ground
A trial compaction shall be performed at the site using the intended material and
compaction equipment. This allows the determination of the compaction
procedure (method of placement, compaction equipment, layer thickness,
number of passes, adequate techniques for transportation, amount of water that
shall be added) to be followed. A trial compaction may also be used to establish
the control criteria.
For general fill, the minimum compaction shall achieve a minimum of 90%
Maximum Dry Density (MDD).
For structural fill, the minimum compaction shall achieve a minimum of 95%
Maximum Dry Density (MDD).
iii. Preloading
While performing the preloading, the actual settlements amount of the original
ground shall be monitored. For major works, monitoring of pore water pressure
in the compressible soil layers shall be performed.
The manufacture of plastic drains and PVD is subject to approval by the Owner.
The following are the general requirement for all types of vertical drains:
a) To discharge the excess water, the top of the vertical drains shall be
placed in a free draining (sand) layer of at least 0.6 m thickness.
b) The vertical drains shall penetrate the compressible soil layers to be
drained.
c) The drains shall be installed to a maximum depth of 1.0 m above the top
of the water-bearing layer below those compressible layers.
d) Care should be taken with regard to possible long term effects on the
groundwater quality.
Water may be removed from the ground by gravity drainage, by pumping from sumps, well
points or bored wells. The scheme adopted will depend on:
ii. The characteristics of the project: e.g. excavation depth and extent of dewatering.
The design of dewatering system shall consider all the risks generally associated with
dewatering activities but not limited to the following:
i. Soil and slope stability and soil erosion due to dewatering activities.
ii. Soil contamination. Whether contamination exists in the project area prior to
commencement of construction or is caused by dewatering activities.
vii. Risks associated with failure of dewatering system and/or disposal methods.
The following data from Site Investigation shall be made available prior to design a dewatering
system:
6.1 GENERAL
All retaining structures shall be designed to ensure an asset that is fit for purpose and
guarantees long-term performance. There are 2 types of retaining structures e.g. gravity walls
and embedded retaining walls.
Other methods of retaining earth such as soil nailing (anchorage), mechanical stabilized earth
(MSE), reinforced slope etc. should be considered based on cost and practicality.
Gravity walls are walls of stone or plain or reinforced concrete with base footing with or
without a heel, ledge or buttress, e.g. reinforced concrete wall, gabion retaining wall,
reinforced concrete crib wall, etc. Design of these structures shall be in accordance with BS
8002 or approved equivalent.
The minimum FOS for bearing capacity is 2.0 and overturning and sliding shall be at least 1.5.
Embedded retaining wall is a walls of steel or reinforced concrete which can be designed in
cantilever or supported by anchorages or struts. Example of these walls are sheet pile wall,
diaphragm wall (slurry wall), contiguous pile wall, secant pile wall, etc. The design shall be in
accordance with BS 8002 or approved equivalent.
vi. Yielding stress or cracking occurs in any cross section of the wall
The FOS of at least 1.5 to be adopted for each failure mechanism which depend on other
design requirements and the type of anchoring structure. Assessment on the deformations of
each part of the retaining structure shall be performed.
If there is any drainage system designed for retaining structure, the following conditions shall
be applied:
ii. Access shall be designed and provided for the drainage maintenance work
7.0 BIBLIOGRAPHY
Slope Stability Assessment And Slope Repair For Existing Pipeline PTS 11.12.05
Route In Mountainous Region
INTERNATIONAL STANDARDS
Standard Test Method for High-Strain Dynamic Testing of Deep ASTM D4945
Foundations
Standard Test Method for Low Strain Impact Integrity Testing of ASTM D5882
Deep Foundations
Specification For High Tensile Steel Wire And Strand For The BS 5896:1980
Prestressing Of Concrete
1.0 CONSTRUCTION
1.2 Supervision
The piling work shall be supervised by Owner and/or his representatives. No supervision work
shall be carried out by the piling contractor. Pile installation and tests shall be carried out only
in the presence of authorized supervisor.
1.3 Tolerances
At all stages of pile installation, the pile shall be adequately supported and restrained by
means of leaders, temporary supports or other guide arrangement to maintain position and
alignment. No concrete pile shall be subjected to high stress when being placed into the
required position.
For the pile cut off at or above ground level, the maximum permitted deviation of pile center
from the center-point shown in the drawings shall be 75mm in any direction and shall be
within two (2) percent of plumb for the total length of the shaft.
For pile group, pile installation should start from the center of pile group. For pile driving at
slope surface, pile installation shall be started from the higher side.
Jetting of ground and pre-boring shall not be carried out without prior approval of the Owner.
Jetting and/or pre-boring are not permitted in those layers from which in accordance to
geotechnical design, the pile will derived static resistance, which consist of positive shaft
friction and/or end bearing. In any circumstance, jetting shall not be permitted for piles
subjected to lateral loads.
Where pre-boring is allowed it shall be carried out only if the diameter of pre-bore is
sufficiently less than the diameter of working pile to prevent reduction of the stiffness of the
lateral soil support. The Contractor shall exercise care while carry out jetting and/or pre-
boring for raking piles to prevent the pile from being out of alignment.
Pile Driving Record shall be submitted once the piling work completed. The record shall report
of any issues encountered during the piling work such as Problematic Pile, Deviation of Design
Length (Either Short or Lengthy) or any pile facing difficulty during driving. The pile driving
record should include the following information:
- Description of equipment, type size and maximum energy of hammer, stroke of hammer
and frequency of blows.
- Date of pile manufacture.
- Date and time of the driving.
- Pile data (length, working load, size and number / location of piles as shown on the
drawing.
- Penetration resistance (blows per unit penetration or set per blow) and embedment depth.
- Levels with respect to Datum (elevation of pile top, elevation of pile tip and grade/bottom
elevation at the time of pile driving)
- Sequence of installation of the piles.
- Replacement of the cushion material in the driving cap.
- Occurrence of plugging of pen end piles.
- Date and time of testing.
- Sequence of testing (end of driving or beginning of restrike)
2.1 General
The minimum number of pile points that shall be subjected to load test is:
i. Compression pile: One (1) percent of the total number of pile points with
minimum of 3 nos. of pile tests or as instructed by Owner.
ii. Other types of pile (eg. tension pile, laterally loaded pile): Two (2) percent of
the total number of pile points with minimum of 3 tests or as instructed by
Owner.
The number of test may be reduced if satisfactory results is obtained at for the same pile type
at geotechnically similar location by Owner’s approval.
In addition, minimum 10% of installed piles shall be tested for integrity using low strain test i.e.
Pile Integrity Test (PIT) in accordance with ASTM D5882.
Requirement for high strain dynamic test i.e. Pile Dynamic Analyzer (PDA) test, Statnamic Load
Test shall be performed and approved by Owner. This test shall be in accordance with ASTM
D4945. Where full load test is not feasible to be carried out e.g. due to site constraint, this test
may be conducted as alternative.
The selection of pile to be tested shall be decided by the Owner. The first installed pile shall
be tested. At least two (2) tests shall be performed before completion of half of the total number
of piles. It is recommended that the test pile locations are located closest to soil
investigation points that have been carried out.
The maximum test load on a pile shall be twice the Working Load.
The load shall be applied in increment of 25% of the working load, up to the working load and
appropriately smaller thereafter, until a maximum test load of twice the working load is
reached. Each increment of load shall be applied as smoothly and as expeditiously as possible.
Settlement readings and time observations shall be taken before and after each new load
increment.
A time-settlement graph shall be plotted to indicate when the rate of settlement of 0.05 mm
in 15 minutes is reached. A further increment of load shall be applied when this rate of
settlement is achieved, or until a minimum time of 2 hours has elapsed, whichever is later.
The process shall be repeated until the maximum test load is reached.
The maximum test load shall then be maintained for a minimum of 24 hours, and time-
settlement readings shall be taken at regular intervals, as for the earlier load stages.
The test load shall then be decreased in four (4) equal stages, and time-settlement readings
shall be as specified aforesaid, until the movement ceases. At least 60 minutes interval shall
be allowed between the unloading decrements.
During testing, if the result from each measuring devices differs by more than 20%, the
Contractor shall release the load and recheck the arrangement of the load cell and redo the
load test.
Settlement readings shall be made immediately after and before every load increment is
applied or removed.
All equipment to be used for load test shall be subject to approval of the Owner and
experienced operators/supervisors shall be present full time for the duration of each pile test
programme to ensure that the loading sequence and period of maintaining load are strictly
followed. During the pile load test, all records shall remain available for inspection by the
Owner. Within three (3) days of completion of any pile load test, complete records shall be
submitted to the Owner.