ESTIMATE of RCC Building Design
ESTIMATE of RCC Building Design
3. SEWERAGE SYSTEM
i) Providing laying, joining, cutting upvc pipe SN8 complete
including cost of special under bed cement concrete,
excavation complete in all respect.
• 300 mm Ø = 215 mtr. @ Rs. 2800/- mtr. Rs 6,02,000/-
• 250 mm Ø =91 mtr. @ Rs.1810/- mtr. Rs 1,64,710/-
• 200 mm Ø = 230 mtr @1180/- mtr. Rs 2,71,400/-
• 160 mm Ø= 100 mtr. @ 750/- mtr. Rs 75,000/-
Total = 44.00Mt.
Say = 44Mt.
Pumping capacity per hour = 25000Lt. OR 25.00 cum
Pumping capacity in cum per second Q = 25/60X60 = 0.006Pcum/sec
Say = 0.007
H.P of electric motor with 60% efficiency 0.007x1000x44/75x0.60 = 0.84 BHP
One no. Submersible pumping set coupled with 7.50 HP electric motor capable of delivering
420 LPM against a head of 44 Mt.
One no. Submersible pumping set (pump with motor of same capacity and size) to act as a stand-by
arrangement in case of failure of installed machinery.
RISING MAIN (DELIVERY PIPE)
Daily water supply requirement = 1,00,000
Required capacity per hour = 25000Lt.
Say = 25000
Design discharge per day = 25000x24 =6,00,000Lt.
Length of pipe from T/well to UGSR = 10Mt.
The design carrying capacity of 100mm dia G.I pipe for 6,00,000 Lt. Water/day having loss of head
2.50 Mt. in 1000 Mt. length of pipe.
Length of rising main = 30Mt.
Loss of head in rising main 10x3.50 = 0.35Mt. Say = 0.50Mt.
Provide 100mm G.I rising main from tube well to under-ground water tank.
TOTAL = 45.95Mt.
Say = 50Mt.
Sand Filtration