NZSEE14 Aninthaneni Conceptualdevelopmentoflowlosssystem
NZSEE14 Aninthaneni Conceptualdevelopmentoflowlosssystem
NZSEE14 Aninthaneni Conceptualdevelopmentoflowlosssystem
net/publication/299043876
CITATIONS READS
10 25,024
2 authors, including:
Rajesh P Dhakal
University of Canterbury
346 PUBLICATIONS 3,000 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Rajesh P Dhakal on 20 March 2016.
1 INTRODUCTION
In modern world, concrete has dominated the construction sector because of its availability and
material properties. Concrete structures are constructed in two ways: cast-in-situ and precast. Precast
concrete structures can be defined as structures where majority of structural components are
standardized and produced in concrete yards away from the site and then transported to the site for
assembly. Precast concrete construction is being adopted in many countries for its potential
advantages. The performance of precast structural system in resisting lateral loads depends on the
behaviour of connections. The implementation of innovative ideas for connecting precast elements
together, and subsequent verification through experimental procedures, has resulted in significant
advances for the precast concrete industry in seismic regions of the world in the past two decades. For
example, in New Zealand precast concrete has been used in moment resisting frames since the 1980s
(Park 1990).
Structural behaviour of precast structures differs from monolithic cast-in-situ concrete structures.
From a general point of view, there are two alternatives to design precast structures. One choice is the
use of precast concrete elements interconnected predominantly by hinged connections, whereas the
other alternative is the emulation of monolithic RC construction. The emulation of the behaviour of
monolithic RC constructions can be obtained using either ‘‘wet’’ or ‘‘strong’’ (dry or partially dry)
connections. A ‘‘wet’’ connection between precast members uses cast-in-place concrete or grout to fill
the splicing closure. Precast structural systems with wet connections must then comply with all
requirements applicable to monolithic RC constructions. A ‘‘strong’’ connection is a connection, not
necessarily realized using cast-in situ concrete, that remains elastic while designated portions of
structural members undergo inelastic deformations under the design actions (Bournas et al 2013).
1
Generally “strong” dry connections are achieved with use of dowels or anchor rods, steel billets, steel
plates, and steel angles. Many researchers have proposed dry connections with different configurations
and experimentally validated and found that these systems can be considered as semi-rigid
connections which primarily depend on dowel action for force transfer from beam to column (Elliott et
al 2003, Mohamed 1992 & Negro et al 2012). To the authors’ knowledge, there is limited research in
the development of precast system with strong rigid dry connection.
The present research is focused on development of sustainable demountable precast RC frame
building system using “strong” dry connections consisting of steel angle or steel tube, stiffened steel
plates and pre-tensioned high strength frictions grip (HSFG) bolts. The main advantages of the
proposed sustainable precast frame building system are:
1. Quick to construct: Building system without use of cast-in-situ concrete, site formwork, and
can be erected in quick time.
The proposed system doesn’t need any cast-in-situ concrete; the connections between floor-
floor, floor-beam, beam-column and column-foundation are made using steel elements (i.e.
stiffened steel angle or steel tube) and pre-tensioned high strength bolts. This system can be
erected in quick time which leads to significant reduction in overhead project cost and
increased financial return due to earlier occupancy of the building.
2. Simple system: Building system is simple to analyse, design and construct.
No specialist knowledge is required in the analysis, design and construction of the proposed
precast frame building system. As the precise elements and connections to be used in the
system are simple and have been used in industry for several years, general builders can easily
erect the proposed system without much difficulty. In addition, the system does not require
very precise construction and fabrication tolerance.
3. Demountable: Building system can be demounted at any time during the life span of building.
The connections between the precast elements of the frame building are made such that the
building can be easily demounted when/if needed without damaging the components. The
proposed system enables financial savings through dismantle and reuse (rather than demolish).
4. Easily upgradable: Building system can be easily upgraded or strengthened.
The proposed building system can be upgraded if higher strength is required due to change of
building occupancy or change in design code/demand. Higher strength can be achieved by
replacing the weakest frame elements with bigger/stronger ones or by adding diagonal bracing
elements with little intervention (as the steel connection can be predesigned to accommodate
the bracing elements when/if needed in future).
5. Easy/fast to repair/Insurance compliant: System with easily replaceable damaged elements,
thereby making it an earthquake resilient building system and compliant to insurance policy
“like for like as when new”.
The damaged structural beams and columns in earthquakes can be easily replaced with new
one within short time (which leads to significantly less downtime loss); thereby rendering it a
definitely repairable and low loss system, despite not being a damage avoidance solution. The
damaged building can be recovered exactly to the original state (or stronger, if needed) in a
short time which leaves no room for ambiguity in terms of compliance to the common
insurance policy of “like for like as when new”.
This paper describes the conceptual development (including schematic layout) of the proposed
demountable precast frame building system, and available lateral load resisting options within the
proposed system. It also explores an analytical model for estimating the connection capacity.
2
2 PRECAST BUILDINGS AND THEIR PERFORMANCE IN CANTERBURY
EARTHQUAKES
In New Zealand, precast reinforced concrete moment resisting frames are very common since 1980’s.
In precast building systems, joints between precast elements are normally designed to emulate
monolithic construction so that the whole structure shows equivalent monolithic behaviour during an
earthquake. There are four ways of achieving equivalent monolithic behaviour in conventional precast
frames, which are shown in detail in figure 1.
Figure 1: Commonly used arrangements of Precast Members and Cast in Place Concrete for Constructing
Moment Resisting Reinforced Concrete Frames in New Zealand. (Restrepo,1992)
In system-1, the precast beam elements are placed between columns and seated on the cover concrete
of the previously cast-in-place or precast column below and/or propped adjacent to the columns. A
precast concrete floor system is placed, seated on the top of the precast beam elements and spanning
between them. Reinforcement is then placed on the top of the beams, over the precast floor and in the
beam column joint cores. The topping slab over the floor system and the beam-column joint cores is
cast-in-situ (Fib-27 2003). In system-2, the precast beams are seated on steel shims creating a
construction joint 10 to 25mm thick. Protruding column longitudinal bars pass through precast
preformed vertical holes in the beams and protrude above the beams top surface. The holes in the
precast beam elements are formed by corrugated steel ducting. The vertical ducts and the horizontal
construction joint at the bottom of the precast beams are grouted in one operation. A precast concrete
column is then positioned above the precast beam using grouted vertical laps or grouted steel sleeves
to connect the vertical column bars (Restrepo 1992).
3
In system-3, T–shaped, cruciform precast concrete elements or even multi-storey cruciform units are
used. In this arrangement the vertical column bars in the precast units are connected using grouted
steel sleeves. Cast-in-place connections of the beams for this system are identical to those employed
for System 2 (Fib-27 2003).In system-4, pre-tensioned precast concrete beam shell units are used as
permanent formwork for beams. The precast U-beams support the self-weight and construction loads
and act compositely with the reinforced concrete core when subjected to other loading in the
completed structure. Precast U-beams are generally not connected by reinforcement to the cast-in-
place concrete of the beam or column, the composite action normally comes from the bond between
the roughened inner surface of the precast U-beam and the cast-in-place concrete (Fib-27 2003).
Generally concrete moment resisting frames performed as expected in the Canterbury earthquakes.
Modern precast buildings in general did well in terms of ‘life safety’ and ‘collapse prevention’; with
the exception of two RC buildings (Uma et al, 2013). In the September 2010 Darfield earthquake,
modern precast concrete buildings reportedly behaved better apart from experiencing considerable
damage to non-structural elements and contents. However, cracking in precast flooring systems due to
beam elongation, damage to staircase elements and damage in gravity load elements due to inadequate
detailing to cater for the displacement demands were observed in some modern buildings (Uma et al
2013, Kam et al 2010 & Elwood et al 2011). In the February 2011 Christchurch earthquake, the
damage to the majority of modern buildings was technically repairable, but many of these buildings
were demolished based on financial viability of the available repair options. A full compilation of
vulnerability assessment of RC buildings in general in these earthquakes has been reported (Kam et al,
2011), but the authors are not aware of any report specific to the damage sustained by the precast
building stock.
4
Figure 2: Perspective view of demountable precast frame concrete structural system
Figure 3: Steel angle connection between hollow core floor slab and precast beam
5
that although the capacity and stiffness of these connections vary significantly, they can be treated as
semi-rigid connection in analysis and design without inducing too much error. Full details of such
semi-rigid connections using mechanical connectors can be found in Fib-43. Figures 4 & 5 show the
proposed “strong” dry beam-column connection using stiffened angles or steel tube and HSFG bolts.
The bolts are pre-tensioned so that the initial moment of resistance depends on the frictional resistance
developed between steel surface and concrete surface. Such a connection offers high moment of
resistance and rotational stiffness to ensure the connection remains in elastic state while the beams
(weakest element) reach their capacity. Figure 6 shows a typical mechanical pin connection between a
gravity load resisting beam and column, which ensures that the lateral loads are shared only among the
seismic frames. This enables the precast frame building system to be built as designed so that no
surprising damage is incurred in the gravity frame connection in future earthquakes.
Figure 4: Beam-column connection system using steel angle, steel plate, and HSFG bolts
Figure 5: Beam-column connection system using steel tube, and HSFG bolts
6
Figure 6: Gravity load resisting beam connected to precast column with use of mechanical pin
Figure 7: Column-column connection, column-foundation connection using steel end plate and bolts
7
The load path in an unbraced frame with fixed base and pin base under external lateral load is shown
in figure 8. The fixed base frame offers high strength and stiffness compared to the pin base frame.
The capacity and stiffness of pin base frame can be considerably increased by addition of steel braces.
In a fixed base frame system, ground storey columns will be damaged along with beams in seismic
events, and they have to be replaced with new one after seismic events; whereas in a pin base
connection only beams (which are easy to replace) will be damaged. The qualitative comparison of
base shear capacity between unbraced frames with fixed and pin bases and braced frame with pin base
(which can be adopted as an option for new design or strengthening of a pin based frame) is shown in
figure 9.
Lateral load
: Plastic hinge
brace
Frame with pin base
Roof displacement
8
Lateral load : Simple connection
: Plastic hinge
Figure 10:Precast concrete frame with simple connections and Steel brace
9
F: frictional resistance
between steel and concrete
P P surface
µ: Coefficient of friction
F=μ*P between steel and concrete
surface
P: Pre-tension in bolt urface
d: Depth of concrete beam
MR =φ*F*d d M
MR: Moment of resistance
F=μ*P M: External applied moment
P P φ :0.9 (if slip resistance is
designed at service load)
:0.8 (if slip resistance is
designed at ultimate load)
Figure 11: Force transfer mechanism through beam end to column connection (Slip critical connection)
P P
Figure 12: Force transfer mechanism through beam end to column connection (bearing type connection)
Figure 13: Force transfer mechanism through beam end to column connection (no gap between beam & column)
10
4 APPLICATIONS
The proposed demountable frame system can be easily implemented in low to medium rise residential,
industrial and commercial buildings. Given that majority of buildings in New Zealand are low to
medium rise, the proposed system can be adopted in majority of RC frame buildings to be built in
future in New Zealand. In addition, because it is easy to demount, the proposed system is perfect for
temporary structures like sports complex, parking buildings and storage houses.
Gravity-only frames or secondary elements constructed with current practice have been observed in
recent earthquakes to have either participated as part of the lateral load resisting system or deformed in
a way similar to (and along with) the main seismic frames. Consequently, damage was inevitable in
gravity frames in contrast to the intention of the designer. The proposed system allows gravity
resisting frames to be built with mechanical pin connections to the lateral load resisting system. With
this practice, the lateral loads will be shared only among the lateral load resisting seismic frames;
thereby enabling the building system to be built (and behave) as designed which spares gravity frames
from any earthquake damage.
6 CONCULSIONS
A new precast concrete frame building system is proposed which inherently offers unique advantages
such as; quick construction, simple, demountable and reusable, easily upgradable, quickly repairable
to insurance policy compliant condition etc. The proposed system is sustainable and can be easily
implemented into practice in all RC frame buildings. It is particularly suitable for temporary structures
because the structure can easily be demounted at any time and the components can be reused in
another structure. In the proposed precast frame system, damaged structural elements after an
earthquake can be easily detached and replaced with a new one; thereby significantly reducing the
downtime and rendering it a definitely repairable and low loss solution.
11
REFERENCES:
Bournas, D.B., Negro, P. & Molina,F.J.2013. Pseudo-dynamic tests on a full-scale 3-storey precast concrete
building Behavior of the mechanical connections and floor diaphragms, Engineering Structures, 57,609-627
CPCI Deign Manual, 1996, Precast and Prestressed concrete,Canadian Presstressed Concrete Institute,Canada
Elwood, K.J., Pampanin, S. &Kam, W.Y. 2012. 22 February 2011 Christchurch Earthquake and Implications for
the design of concrete structures, Proceedings of the International Symposium on Engineering Lessons Learned
from the 2011 Great East Japan Earthquake, Tokyo, Japan, 1157-1168
Elliott, K.S.1996. Multi-storey precast concrete framed structures. Blackwell Science, Oxford.
Elliott, K. S., Davies, G., Ferreira, M. A., Gorgun ,H. &Mahdi, A. A. 2003.Can precast concrete structures be
designed as semi-rigid frames – Part 1 the experimental evidence The Structural Engineer, 81/16,14-27.
Elliott, K. S., Davies, G., Ferreira, M. A., Gorgun, H.& Mahdi, A. A. 2003. Can precast concrete structures be
designed as semi-rigid frames – Part2 Analytical equations & column effective length factors. The Structural
Engineer, 81/16, 28-36.
Fib (2003b): Seismic design of precast concrete building structures. State-of-the-art report, federation
internationale de béton, Bulletin 27, Lausanne.
Fib (2008b): Structural connections for precast concrete buildings. State-of-the-art report, federation
internationale de béton, Bulletin 43, Lausanne.
Kam, W. Y., Pampanin, S., Dhakal, R. P., Gavin, H. &Roeder, C. W. 2010. Seismic performance of reinforced
concrete buildings in the September 2010 Darfield (Canterbury) earthquakes. Bull. of New Zealand Soc. of
Earthquake Eng., 43(4), 340-350.
Kam, W.Y., Pampanin, S & Elwood, K.J.2011. Seismic performance of reinforced concrete buildings in the 22
February Christchurch (Lyttelton) earthquake, Bull. of New Zealand Soc. Of Earthquake Eng., Vol. 44, no. 4,
Dec 2011.
Mohamed, S.A.M. 1992. Behaviour of sleeved bolt connections in Precast Concrete Building Frames. PhD
Thesis,University of Southampton,UK
Negro,P.& Toniolo,G. 2012. Design guidelines for connections of precast structures under seismic actions,
European commission.
Park , R. 1990. Precast concrete in seismic-resisting building frames in New Zealand. Concrete International,
Vol.12, No.11, pp.43-57.
PCI design handbook. 2010. Precast and prestressed concrete, 7th edition,Chicago
Restrepo,J.1992. Seismic Behaviour of Connections Between Precast Concrete Elements, PhD Thesis,
Department of Civil Engineering, University of Canterbury, Christchurch, New Zealand.
Uma, S.R., Dhakal, R.P.,Nayyerloo ,M. 2013.Vulnerability assessment of Christchurch Buildings in Canterbury
Earthquakes,GNS Science Report, New Zealand.
12