SCR Projects Targeted Non Targeted June 2021

Download as pdf or txt
Download as pdf or txt
You are on page 1of 126

INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work : Manoharabad – Kothapalli (151.36


km) (PB No. 09 of 21-22)
Super Critical /Critical : Hon’ble PM laid the
Foundation Stone on 07.08.2016
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 151.36 Kms
Year of Sanction 2016-17
Rs. 1981.04 Crores
Anticipated Cost (Cr)
(Original Sanc. 1160.47 Cr. + 213.26 Cr. MM )
601.55 Cr
Up to date expenditure (Cr)
(Cap. 441.32Cr + SF.99.95Cr + Dep.60.28Cr)
Length commissioned (Km) 31.071 Kms
Land acquisition required in Ha. Scope Acquired Balance
Telangana State 1079.816 703.116 376.700
Forest Land in Diversion in Ha. Scope Diverted Balance
Telangana State 2.200 2.200 0.000
Major Bridges nos 21
Minor Bridges Nos 159
Limited Height Subways & Road under
104
bridges
Stations 14
Physical progress 39%
TDC of complete project 2024-25
SCOPE OF COMPLETE PROJECT
Total %
SN Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 138.310 47.73 34.51%

2 Hard rock cutting (Lakh Cum) 0.935 0.00 0.00%


To be
3 Imp Bridges 1 executed in 0
Phase-III
4 Major Bridges (Nos.) 25 9 36.00%
5 Minor Bridges (Nos.) 159 65 40.88%
6 LHS/RUB (Nos.) 104 41 39.42%
7 ROB (Nos.) 20 6 30.00%
8 Track Linking (Km) 151.36 33.071 21.85%
9 Stations Bldg.(Nos.) 14 4 28.57%
ISSUES PENDING WITH STATE GOVERNMENT

SN Issue Present status


Requisition for land acquisition submitted for entire
1. Land Acquisition project. As on date, Out of total scope of land
acquisition i.e., 1082.01 Ha, 705.316 Ha has been
acquired. Balance land of 376.70 Ha is to be expedited
by Govt., of Telangana, at the earliest.
Telangana State Govt’s share towards the project cost
(1/3rd Share) work out to be Rs. 311.46 Crores (Excl.
2. Any Other issues Cost of Land). As on date, State government had
deposited Rs. 150 Crores only towards their share of
project cost. State Government is to be pursued for
the deposition of balance share in project cost i.e., Rs.
161.46 Crores.
PHASE-WISE PLANNING TO COMMISSION THE PROJECT
Planning of commissioning :

Length in Km
S.No. Name of section planned for TDC
commissioning (Km)
Manoharabad - Gajwel CRS
1 31.071 Mar, 2020
authorization received on 19.06.2020
2 Gajwel - Kodakandla 11.529 Dec, 2021
3 Kodakandla - Siddipet * 32.60 Mar, 2023
4 Siddipet - Sircilla * 37.15 Mar, 2024
5 Sircilla - Kothapalli * 39.01 Mar, 2025

*Subject to handing over of land & deposition of 1/3rd share by Telangana Govt.

Year wise commissioning


20-21 21-22 22-23 23-24 24-25
31.071 11.529 32.60 37.15 39.01
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work : Munirabad - Mahabubnagar New


line - DEVARAKADRA - KRISHNA 65.74 KM
Section (TELANGANA portion by SCR)

Super Critical /Critical : Targetted


Munirabad - Mahabubnagar New line
DEVARAKADRA - KRISHNA 65.74 KM Section (TELANGANA portion by SCR)

Map of the Project


SALIENT FEATURES OF PROJECT – SCR Portion
Length of the Project (Km) 65.74 km
Year of Sanction 1997-98
Anticipated Cost (Cr) 907.71
Up to date expenditure (Cr) 1740.00
Length commissioned (Km) 39.822
Land acquisition required in Ha. Scope Acquired Balance
Telangana 109 109 -
Forest diversion. In Ha Nil
Imp Bridges nos 1
Major Bridges nos 1
Minor Bridges Nos
Limited Height Subways & Road 48
under bridges
Stations 3
Physical progress 70 %
TDC of complete project 2022-23
SCOPE OF COMPLETE PROJECT

Total %
SN Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 26 20 77
2 Hard rock cutting (Lakh Cum) - - -

3 Imp Bridges 1 1 100

4 Major Bridges (Nos.) 1 1 100

5 Minor Bridges (Nos.)


48 47 98
6 LHS/RUB (Nos.)

7 Track Linking (Km) 65.74 39.822 61


8 Stations Bldg.(Nos.) 3 1 34
ISSUES PENDING WITH STATE GOVERNMENT

S Issue Present status


N

• nil
1. Land Acquisition

• Nil
2. Forestry
clearances

3. Any Other issues Canal Crossing- Br. N.o. 40B: Span-1x6.0x5.0m RCC Box (Barrel
Length-388m) – 60% Completed.
Balance work is in progress and it will be completed with the co-
ordination of officials of Irrigation Dept., / Telangana State, as it is
Irrigation Canal crossing.
Munirabad - Mahabubnagar New line -
DEVARAKADRA - KRISHNA 65.825 KM Section
(TELANGANA portion by SCR)
Planning of Commissioning (KSN-DKC) – SCR part
Likely Month &
Km planned for Name of sections for which likely month & year of
Year of
commissioning (Km) commissioning has been given in Col no.2
commissioning
(1) (2) (3)
Devarakadra - Jaklair
28.345 Commissioned CRS authorisation received on 27.10.16.
First train flagged of by Hon’ble MR on 25.03.2017
Jaklair - Makthal
11.477 Commissioned CRS authorisation received on 05.06.2020.
First train run on 23.08.2020.

13.305 Nov, 2021 Maganur - Makthal

13.170 2022 - 23 Krishna - Maganur

Year wise commissioning


20-21 21-22 22-23 23-24
11.477 13.305 13.17 -
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work : Bhadrachalam Road - Sattupalli


(NewLine)
Super Critical /Critical : Coal Project & Targetted
BHADRACHALAM ROAD - SATTUPALLI NEW BG LINE (54.10KM)
• Sanctioned in 2010-11
• DE sanctioned in 2016-17 (Mar,2017)
• Cost of the Project : 704.31 Cr
• Revised Cost (Feb 2020) : 927.94 Cr

BETHAMPUDI • Cost Sharing :


(9.74 KM) • Land : By Railways
KOYAGUDEM • Project cost : By M/s SCCL & Rlys
BHADRACHALAM ROAD • Figuring in “PRAGATI” of PMO
(6.004 KM) (0.00 KM)

CHANDRUGONDA • Target: 2021 - 22


(23.60 KM) •BDCR – Chandrugonda (Upto 23.60 Km)
Aug’ 2021 ( Subject to EHT modification)
BHAVANNAPALEM
(39.25 KM)
•Chandrugonda– Sattupalli (Upto 29.60 Km) –
Dec’ 2021 ( Subject to EHT modification)
SATTUPALLI
KAZIPET (53.20 KM) •BG 2021-22: EBR(IF) : 100.00 Cr

KONDAPALLI

VIJAYAWADA
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 54 kms
Year of Sanction March 2017 Rev. Estimate Feb 2019
Anticipated Cost (Cr) Rs. 927.94 cr.
Up to date expenditure (Cr) Rs. 627 Cr. As on 31-05-2020
Length commissioned (Km) --

Land acquisition required in Ha. Scope Acquired Balance


Telangana State 354 344 10
Forest Land 8.42 8.42 --
State
Forest diversion. In Ha
Scope Ha , diverted Ha, bal. Ha
Imp Bridges nos ---
Major Bridges nos 10 Nos
Minor Bridges Nos 44 nos
Limited Height Subways & Road
48 Nos
under bridges / Road Over Bridge
Stations 4 Nos. ( 1 Exg)
Physical progress 79%
TDC of complete project DEC - 2021
SCOPE OF COMPLETE PROJECT
Total %
Sn Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 71.30 65 91
2 Hard rock cutting (Lakh Cum) 0.50 0.45 90

3 Imp Bridges -- --

4 Major Bridges (Nos.) 10 8 80%

5 Minor Bridges (Nos.) 44 40 90

6 LHS/RUB/ROB (Nos.) 48 33 69

7 Track Linking (Km) 54 17 31


8 Stations Bldg.(Nos.) 4 3 75
ISSUES PENDING WITH STATE GOVERNMENT
SN Issue Present status

1. Land Acquisition
1) Handing Over of 10 Ha. Land.
This land is mainly required for Land acquisition is under different stages. It is expected to get
ROB/RUB approaches and for all land by June’ 2021
extra formation width.

2. Forestry clearances All forest land taken over.


A. From TS TRANSCO Dept
3. Any Other issues
1) Shifting 220/132 KV HT crossings (6 Nos)
2) Shifting 440 kv EHT crossings (1 No) - (Already entire
amount deposited with TRANSCO) – Progress of shifting need
to be expedited as it is effecting construction works.
B. From TS R & B Dept
1. ROB 7 at SH & ROB 50 at NH crossing, Approaches
executed by State R&B Authorities. (80% amount already
deposited. R & B to expedite progress. )
Progress of approaches is only around 50%. Further this
work is held up due to land acquisition issues in approaches
(LA in approaches is being dealt by R&B authorities)
PHASE-WISE PLANNING TO COMMISSION THE PROJECT

Planning of commissioning :

Sn Name of Section Length in Km TDC


MM/YY
1. BDCR – Chandrugonda 23.60 Aug’ - 21
2. Chandrugonda - Sattupalli 29.60 Dec’ - 21

Year wise commissioning


20-21 21-22 22-23 23-24
-- 54 -- --
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work :Akanapet-Medak New Line

Super Critical /Critical : Targetted


SALIENT FEATURES OF PROJECT
Length of the Project (Km) 17.20 Kms
Year of Sanction 2014-15
Anticipated Cost (Cr) Rs. 205.26 Crores (Original Sanc. 117.75 Cr.)
158.41 Cr (SF. 21.59 Cr + EBR(IF). 58.51
Up to date expenditure (Cr)
Cr. + Cap. 40.90Cr + Dep.37.41Cr)
Length commissioned (Km) 0.00 Kms
Land acquisition required in Ha. Scope Acquired Balance
Telangana State 152.620 151.600 1.020
Forest Land in Diversion in Ha. Scope Diverted Balance
Telangana State 9.685 0.000 9.685
Major Bridges nos 3
Minor Bridges Nos 36
Limited Height Subways & Road
15
under bridges
Road Over Bridges 1
Stations 4
Physical progress 90%
TDC of complete project January, 2022
SCOPE OF COMPLETE PROJECT
Total %
SN Item Progress
Scope Progress

1 Earthwork (Lakh Cum) 17.550 16.900 96.30%


2 Hard rock cutting (Lakh Cum) 1.690 1.500 88.76%
3 Imp Bridges 0 - -
4 Major Bridges (Nos.) 3 1 33.33%
5 Minor Bridges (Nos.) 36 36 100%
6 LHS/RUB (Nos.) 15 15 100%

7 ROB (Nos.) 1 0 0%

8 Track Linking (Km) 17.20 16.00 93.02%


9 Stations Bldg.(Nos.) 4 2 50%
ISSUES PENDING WITH STATE GOVERNMENT

SN Issue Present status


Requisition for land acquisition submitted for entire
1. Land Acquisition project. Balance land of 1.02 Ha is to be expedited by
Govt., of Telangana, at the earliest.
Total scope of diversion in forest land is 9.685 Ha.
2. Forestry Stage-I Clearance has been obtained for 9.685 Ha on
clearances 23.09.2015. Application for Stage-II clearance has
been submitted on 06.08.2019. Stage-II clearance yet
to be expedited.
Telangana State Govt’s share towards the project cost
(50% Share) work out to be Rs. 102.63 Crores. As on
3. Any Other issues date, State government had deposited Rs. 61.75
Crores only towards their share of project cost. State
Government is to be pursued for the deposition of
balance share in project cost i.e., Rs. 40.88 crores.
PHASE-WISE PLANNING TO COMMISSION THE PROJECT

Planning of commissioning :

Length in Km
S.No. Name of section planned for TDC
commissioning (Km)

1 Akanapet - Medak 17.20 January’22

Year wise commissioning


20-21 21-22 22-23 23-24 24-25
0.00 17.20 -- -- --
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work : Proposed Third line with


electrification between Balharshah - Kazipet
stations (201.04 Km.) excluding already sanctioned
length of 33.42 kms between Mandamarri and
Raghavapuram stations (PH:Doubling)

Super Critical /Critical : Coal Project & Targetted


Proposed Third line
with electrification
between Balharshah
- Kazipet stations
(201.04 Km.)
excluding already
sanctioned length of
33.42 kms between
Mandamarri and
Raghavapuram
stations
(PH:Doubling)
SALIENT FEATURES OF PROJECT
201.04 Km. excluding already completed length of 33.42
Length of the Project (Km)
kms between Mandamarri and Raghavapuram stations
Year of Sanction 2015-16
Anticipated Cost (Cr) 2063.03 Cr
Up to date expenditure (Cr) 1481.97 Cr
Length commissioned (Km) 30.508 km
Land acquisition required in Ha. Scope Acquired Balance
State 1: Maharashtra 0
State-2:Telangana 19.24 2.75 16.49
Forest diversion. In Ha
Scope Ha Diverted Ha Bal. Ha
State 1: Maharashtra 31.98 31.98 0
State-2:Telangana 24.7539 0 24.7539
Imp Bridges nos 3
Major Bridges nos 23
Minor Bridges Nos 245

Limited Height Subways & Road under bridges -

Stations 24
Physical progress 65%
TDC of complete project 03/24
SCOPE OF COMPLETE PROJECT
Mandamarri - Balharshah section (CE/C-VI/SC Portion)

SN Item Total Scope Progress % Progress

1 Earthwork (Lakh Cum) 20 13 65%

2 Hard rock cutting (Lakh Cum) 0.20 0.10 50%

3 Imp Bridges 2 0 35%


(Work in Progress)

4 Major Bridges (Nos.) 11 8 73%

5 Minor Bridges (Nos.) 138 102 74%

6 LHS/RUB (Nos.) -

7 Track Linking (Km) 115 20 18%

8 Stations Bldg.(Nos.) 14 9 65%


Name of Project: Proposed Third line with electrification between Balharshah - Kazipet stations (201.04 Km.) excluding
already sanctioned length of 33.42 kms between Mandamarri and Raghavapuram stations (PH:Doubling)

ISSUES PENDING WITH STATE GOVERNMENT


Mandamarri - Balharshah section (CE/C-VI/SC Portion)

SN Issue Present status

1. Land Acquisition
• Requisition for LA for 0.40Ha submitted under RFLARR (Telangana
Amendment) Act, 2016 on 13.08.2020 and 31.05.2021.Under pursuance
with State Government Revenue department.
2. Forestry clearances • Forest & Wildlife Clearances in 24.7539 Ha in the State of Telangana:
• Stage -1 Forest Clearance obtained from MOEFC&C on 19.06.2019 and
Formal approval for Wildlife Clerance obtained on 20.04.2020.
• Demand notice from DFO/Kaghaznagar, DFO/Asifabad &
DFO/Bellampally issued on 25.07.2020.
• Administrative Sanction obtained and Payment made to Forest
Department on 02.09.2020.
• Compliance Report Submitted to forest Department on 14.09.2020
• Working Permission obtained on 15.01.2021 from PCCF, Telangana for a
period of 1 year subject to conditions. MoU/Agreement with Forest
Divisional Officers of Kaghaznagar, Asifabad and Bellampally processed
recently. Work recommenced. Stage-II clearance is pending due to
NTCA observations by NBWL which are infeasible for implementation at
site as expressed by Railway (User Agency) and referred through PCCF
to Member Secretary, NBWL vide RC No.15033/2018-WL-1 of dt:
05.01.2021 and also to the Asst.Inspector General of
Forests(MoEF&CC), GOI, of dt:22.03.2021.
3. Any Other issues
PHASE-WISE PLANNING TO COMMISSION THE PROJECT
Mandamarri - Balharshah section (CE/C-VI/SC Portion)
Planning of commissioning :

TDC
SN Name of Section Length in Km
MM/YY

1 Manikgarh - Wirur 17.93 Km 06/21

2 Wirur - Makudi 12.89 Km 12/21

3 Asifabad - Bellampalli 24.28 Km 06/22

4 Bellampalli - Mandamari 9.40 Km 08/22

5 Balharshah - Manikgarh 6.91 Km 03/23

6 Makudi - Asifabad 43.84 Km 08/23

Year wise commissioning

20-21 21-22 22-23 23-24

- 30.82 40.59 43.84


SCOPE OF COMPLETE PROJECT (CE/C-II/SC Portion)

Kazipet-Raghavapuram
Total %
SN Item Progress
Scope Progress

1 Earthwork (Lakh Cum) 21.99 17.10 77.76


2 Hard rock cutting (Lakh Cum) - - -

3 Imp Bridges 1 - 50

4 Major Bridges (Nos.) 12 10 83

5 Minor Bridges (Nos.) 107 107 100

6 LHS/RUB (Nos.) - - -

7 Track Linking (Km) 81.4 45.8 56.27


8 Stations Bldg.(Nos.) - - -
Name of Project: (CE/C-II/SC Portion)
ISSUES PENDING WITH STATE GOVERNMENT

SN Issue Present status

1. Land Acquisition Land acquisition between HSP –KZJ required for commissioning of
3rd line. Money deposited with State Govt. Joint Inspection with
state govt completed. Land to be handed over By District Collector
Warangal (Urban)

Nil.
2. Forestry clearances

3. Any Other issues


1. ROB @ LC 1 @km 362/21-23 between KZJ-HSP to be
commissioned before commissioning of 3rd line due to
difference in grades of 3rd line, byepass line and up & DN lines
at LC portion. Tenders of both railway portion & approaches
finalized.
(CE/C-II/SC Portion)
Details of Issues and updated status if any

1. Shifting of existing utilities of S&T and Trd departments in a length of 5 km between


Hasanparthi - Kazipet .Earth work in cutting to be taken up in this length.

2. Important Bridge No.66 on Manair River with 27x18.30m (clear span) PSC Girders: All
PSC girders 54 Nos. Casting completed and 32 Nos launched up to May 31st. Further
works are in Progress. Due to covid pandemic the work slowed down.

3. ROB @ LC 1 @km 362/21-23 between KZJ-HSP to be commissioned before


commissioning of 3rd line and bye-pass line due to difference in grades of between
these lines. Tenders finalized for construction of ROB (Railway portion) and its
approaches (state govt Portion) .
(CE/C-II/SC Portion)
Bisgursharif-Uppal(18.192KM)

Total %
SN Item Progress
Scope Progress

1 Earthwork (Lakh Cum) 4.82 4.56 94.6


2 Hard rock cutting (Lakh Cum) - - -

3 Imp Bridges - - -

4 Major Bridges (Nos.) 2 2 100

5 Minor Bridges (Nos.) 24 24 100

6 LHS/RUB (Nos.) - - -

7 Track Linking (Km) 18.192 12 65.96


8 Stations Bldg.(Nos.) 3 3 100
(CE/C-II/SC Portion)
Uppal-Hasanparthi(11.77KM)
Total %
SN Item Progress
Scope Progress

1 Earthwork (Lakh Cum) 3.33 2.5 75


2 Hard rock cutting (Lakh Cum) -- -- --

3 Imp Bridges -- -- --

4 Major Bridges (Nos.) 4 2 50

5 Minor Bridges (Nos.) 18 16 88.9

6 LHS/RUB (Nos.) -- -- --

7 Track Linking (Km) 11.77 0 0


8 Stations Bldg.(Nos.) 1 1 100
(CE/C-II/SC Portion)
Potkapali-Bisgursharif(10.42KM)

Total %
SN Item Progress
Scope Progress

1 Earthwork (Lakh Cum) 6.29 5.9 93.8


2 Hard rock cutting (Lakh Cum) -- -- --

3 Imp Bridges 1 - 50

4 Major Bridges (Nos.) -- -- --

5 Minor Bridges (Nos.) 9 9 100

6 LHS/RUB (Nos.) -- -- --

7 Track Linking (Km) 10.42 1.2 11.5


8 Stations Bldg.(Nos.) -- -- --
(CE/C-II/SC Portion)
Hasanparthi-Kazipet(12.12KM)

Total %
SN Item Progress
Scope Progress

1 Earthwork (Lakh Cum) 3.06 2.37 77.45


2 Hard rock cutting (Lakh Cum) -- -- --

3 Imp Bridges -- - --

4 Major Bridges (Nos.) 2 2 100

5 Minor Bridges (Nos.) 18 18 100

6 LHS/RUB (Nos.) -- -- --

7 Track Linking (Km) 12.12 0 0


8 Stations Bldg.(Nos.) -- -- --
(CE/C-II/SC Portion)
Phase wise planning to commission
the project
Name of section Length in km TDC

Bisgursharif - Uppal 18.33 Sep 2021

Potkapalli - Bisguir sharif 10.42 2022 - 23


Uppal - Hasanparti 11.77 11.77 2022 - 23
Hasanparthi - Kazipet Jn 12.12 2023 - 24

Year wise commissioning

20-21 21-22 22-23 23-24

- 18.33 22.19 12.12


INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work : Guntur-Guntakal Doubling(PH:14)

Super Critical /Critical : Additional Throughput


Enhancement Project & Targetted
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 401.47
Year of Sanction 2016-17
Anticipated Cost (Cr) 3631.08
Up to date expenditure (Cr) 1209.64
Length commissioned (Km) 67.814
Land acquisition required in Ha. Scope Acquired Balance
AP 192.48 13.89 178.59
Forest diversion. In Ha State
Scope 64.11 Ha , diverted 0 Ha, bal.
64.11 Ha
Imp Bridges nos 1
Major Bridges nos 63
Minor Bridges Nos 492
Limited Height Subways & Road
under bridges 10
Stations 43(CROSSING)+4(HALT)
Physical progress 41%
TDC of complete project 2024-25
SCOPE OF COMPLETE PROJECT
Total %
SN Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 48.45 24.91 51.41
2 Hard rock cutting (Lakh Cum) 2.05

3 Imp Bridges 1 1 60

4 Major Bridges (Nos.) 63 20 31.74

5 Minor Bridges (Nos.) 492 172 34.95

6 LHS/RUB (Nos.) 10 5 50.00

7 Track Linking (Km) 401.47 72 17.93


8 Stations Bldg.(Nos.) 43 14 32.56
Name of Project: Guntur-Guntakal Doubling
ISSUES PENDING WITH STATE GOVERNMENT
SN Issue Present status
GNT dist: Requisitions submitted = 230.80 Acres for 29 villages. 11.275 acres of land handed over
1. Land
.PN issued for 9 villages between July’19 & Dec’19. SIA exempted for the entire stretch. An
Acquisition: amount of 41.192 cr. was deposited with DC/Guntur. Requested DC/Guntur to instruct concerned
Andhra to speed up the process of land acquisition on priority.
Pradesh Prakasam dist: a) Between Nallapadu - Donakonda section: Requisitions submitted for 36.50
State acres on 25.05.2018. Joint inspection already completed with Revenue authorities for 6 villages
Government. for land acquisition. SIA exempted for the entire stretch. An amount of 3.07 cr. was deposited
with RDO/Ongole & RDO/ Kandukur. Requested DC/Prakasam to instruct concerned to speed up
the process of land acquisition on priority.
b) Donakonda - Nandyal section: Total extent of 90.81 Ac. Requisitions submitted for 90.81 Ac to
District Collector. Joint survey completed in all 20 villages. 13 villages DD published. 7 villages
Draft Notification issued. Required funds 11.55 Cr deposited to collector, Prakasam district.
Kurnool dist: DKD-NDL section : Requisitions submitted for 5.74 Ac to DC / Kurnool on
31.05.2021.No action from Revenue deptarment inspite of serval recommended, state
government to expedite.
Kurnool & Anantapur dist: Land acquisition (42.7 Hectares of Private land & 8.2 Hectares of
Forest land) process is delaying much (around 1-2years). As part this project, Rs.4.4 Cr were
deposited to State Government against part of required land (15.9 hectares) on Nov’2019 and
land yet to be handed over as on date.
DKD-NDL section: Total 27.21 Ha of Forest land / Wild life DGPS survey data submitted to PCCF
2. Forestry
GNT for uploading purpose.
clearances

3. Any Other
issues
Planning of Commissioning
Km planned for Likely Month & Year of Name of sections for which likely month & year of
commissioning (Km) commissioning commissioning has been given in Col no.2
(1) (2) (3)
6.996 Nov, 2020 Nallapadu - Perecherla
8.414 26.11 Dec, 2020 2020 – 21 Pendekallu - Edduladoddi
10.70 Dec, 2020 Donakonda - Gajjelakonda
11.285 Gundlakamma - Kurichedu
12.95 Kurichedu - Donakonda
13.19 64.355 Gajjelakonda - Markapur
2021 – 22
12.47 Markapur - Tarlupadu
14.46 Edduladoddi - Maddikera
13.67 13.67 JBK-Somidevapalli
19.82 Munumaka - Savalyapuram
32.34 63.86 2022 – 23 Tarlupadu - JBK
11.70 Maddikera - Guntakal
18.74 Satalur - Munumaka
23.03 67.88 2023 – 24 Savalyapuram - Gundlakamma
26.11 Somidevipalle - Diguvametta
41.92 Diguvametta - Nandyal (EPC) (includes 2 tunnels)
40.00 117.74 2024 - 25 Nandyal - Bethamcherla (EPC)
35.82 Bethamcherla - Dhone
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work : KZJ-BZA 3 L(PH:14)

Super Critical /Critical : Additional Throughput


Enhancement Project & Targetted
INDIAN RAILWAYS

Name of Work- KZJ-BZA 3 L(PH:14)


( Kazipet – Kondapalli Stations 3rd line )

Super Critical /Critical : Additional Throughput


Enhancement Project & Targetted
Name of Project: Kazipet - Vijayawada 3rd line, 219.64 km (PH: 14 Doubling) S C Railway
BZA – KI: CE/C-II/SC Mob No. 9701372112

KI – KZJ: CE/C-IV/SC Mob No : 9701372114


SALIENT FEATURES OF PROJECT
Length of the Project (Km) 202.15
Year of Sanction Feb - 2017
Anticipated Cost (Cr) 1952.68
Up to date expenditure (Cr) 152.76
Length commissioned (Km) Nil

Land acquisition required in Ha. Scope Acre Acquired Balance

State 1 AP 11.01 0 11.01


State-2 Telengana 190.432 0 190.432
State - Nil -
Forest diversion. In Ha
Scope Ha , diverted Ha, bal. Ha
Imp Bridges nos 3
Major Bridges nos 15
Minor Bridges Nos 322
Limited Height Subways & Road
5
under bridges
Stations 24
Physical progress 27%
TDC of complete project 2024-25
SCOPE OF COMPLETE PROJECT

Total %
SN Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 26.73 4.88 18%
2 Hard rock cutting (Lakh Cum) - - -

3 Imp. Bridges 3 3 55%

4 Major Bridges (Nos.) 15 2 10%

5 Minor Bridges (Nos.) 322 68 22%

6 LHS/RUB (Nos.) 5 2 40%

7 Track Linking (Km) 228.75 10.5 4.6%


8 Stations Bldg.(Nos.) 24 6 25%
ISSUES PENDING WITH STATE GOVERNMENT

SN Issue Present status

1. Land Acquisition • Proposals submitted , Joint Measurements


partly completed and as per the advise of
Revenue Authorities, an amount of Rs
19.19 Crore has been deposited to the
state govts. Further Record work is in
progress.
2. Forestry clearances • No Forest Land involved

3. Any Other issues Nil


Name of Project: Kazipet - Vijayawada 3rd line, 219.64 km
(PH: 14 Doubling) S C Railway
Planning of Commissioning
Km planned for Likely Month & Year of Name of sections for which likely month & year of
commissioning (Km) commissioning commissioning has been given in Col no.2
(1) (2) (3)
9.08 July, 2021 Kondapalli - Rayanapadu - North West Block Hut

7.87 Sep, 2021 Kondapalli - Cheruvumadhavaram


45.76
16.50 Nov, 2021 Cheruvumadhavaram - Errupalem

12.31 Feb, 2022 Chintalpalli - Warangal

8.41 North West Block Hut - Vijayawada

22.10 47.71 2022 - 23 Errupalem - Motumari

17.20 Nekkonda - Chintalpalli

22.30 Motumari - Chintakani


61.08 2023 - 24
38.78 Chintakani - Dornakal

54.71 54.71 2024 - 25 Dornakal - Nekkonda


INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work :
Vijayawada (19.50 km) & Kazipet (10.65 km) – Bye
Pass Line – PB 41 of 2021-22

Super Critical /Critical : Critical


Bye pass at Kazipet (PH: 15 Doubling) S C Railway

2022-23 10.65 Km
SALIENT FEATURES OF PROJECT Bye pass at Kazipet

Length of the Project (Km) 19.50 Km


Year of Sanction 2019
Anticipated Cost (Cr) 125.14
Up to date expenditure (Cr) 27.35
Length commissioned (Km) Nil
Land acquisition required in Ha. Scope Acquired Balance
Telangana 7.80 Nil 7.80
Forest diversion. In Ha Nil
Imp Bridges nos Nil
Major Bridges nos 3
Minor Bridges Nos 32
Limited Height Subways & Road
Nil
under bridges
Stations Nil
Physical progress 16.0 %
TDC of complete project Feb/2023
SCOPE OF COMPLETE PROJECT
Bye pass at Kazipet

Total %
SN Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 5.50 3.74 68
2 Hard rock cutting (Lakh Cum) -

3 Imp Bridges -

4 Major Bridges (Nos.) 3 3 100

5 Minor Bridges (Nos.) 33 31 94

6 LHS/RUB (Nos.) - - -

7 Track Linking (Km) 19.5 0 0


8 Stations Bldg.(Nos.) - - -
ISSUES PENDING WITH STATE GOVERNMENT
Bye pass at Kazipet

S Issue Present status


N

• Land acquisition is under process. Total extant of land is 7.80 Ha


1. Land Acquisition
Land is essential to take up earth work in a length of 8 km
between Hasanparthi - Kazipet. Amount for land deposited in
June 2020. State Govt has to give the possession of the land.

• Nil
2. Forestry
clearances

• Nil
3. Any Other issues
PHASE-WISE PLANNING TO COMMISSION THE PROJECT
Bye pass at Kazipet
Planning of commissioning :

Sn Name of Section Length in Km TDC


MM/YY
1 Hasanparthi – Kazipet 10.58 02/23
2 Kazipet – Warangal 8.92 02/23

Year wise commissioning


20-21 21-22 22-23 23-24
19.50
Bye pass at Kazipet
Details of Issues and updated status if any

S. Issue Status
No
1 Shifting of Shifting of existing utilities of S&T and Trd
existing utilities departments in a length of 5 km between
of S&T and TrD. Hasanparthi - Kazipet & 2km length between
Kazipet – Warangal. Earth work in cutting to be
taken up in this length.

2 ROB @ LC 1 ROB @ LC 1 @km 362/ 19-21 between KZJ-


HSP to be commissioned before
commissioning of bye-pass line due to
difference in grades of Bye-pass line and UP &
DN lines at LC portion. GAD approved.
Railway Portion Tender finalised on 27.5.21.

ROB : Approaches Tender under finalisation


by State Govt.
Bye pass at Kazipet

EFFORTS MADE TO RESOLVE THE ISSUES

Assistance required

ASSITANCE REQUIRED FROM TELANGANA STATE GOVT.


FOR EARLY HANDING OVER OF THE LAND.
Bye pass at Vijayawada (PH: 15 Doubling) S C Railway

2021-22 5.01 Km
2022-23 16.57 Km
SALIENT FEATURES OF PROJECT Bye pass at Vijayawada
Length of the Project (Km) 21.58Kms
Year of Sanction 2019
Anticipated Cost (Cr) 495.514
Up to date expenditure (Cr) 37.86
Length commissioned (Km) 0
Land acquisition required in Acres Scope Acquired Balance
Andhra Pradesh 78 Nil 78
Forest diversion. In Ha Nil
Imp Bridges nos 2
Major Bridges nos 4
Minor Bridges Nos 18
Limited Height Subways & Road 9
under bridges
Stations 3
Physical progress 8%
TDC of complete project 02/23
SCOPE OF COMPLETE PROJECT Bye pass at Vijayawada
Total %
SN Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 10.14 0.6 6
2 Hard rock cutting (Lakh Cum) - - -
GAD under
3 Imp Bridges 2 0
finalization
GAD under
4 Major Bridges (Nos.) 4 0
finalization
GAD under
5 Minor Bridges (Nos.) 18 0
finalization
GAD under
6 LHS/RUB (Nos.) 9 0
finalization
7 Track Linking (Km) 27 - 0
8 Stations Bldg.(Nos.) 3 In Progress 10
ISSUES PENDING WITH STATE GOVERNMENT
Bye pass at Vijayawada

SN Issue Present status

1. Land LAND REQUIRED FOR TWO RORs FOR A LENGTH OF


4Km. Indent already submitted . PN issued for 2Km.
Acquisition
And further record work is in progress. For Balance
2Km. Joint measurements works are in progress.

2. Forestry
NOT REQUIRED.
clearances

Any Other
3. issues NIL
PHASE-WISE PLANNING TO COMMISSION THE PROJECT

Planning of commissioning :

S Name of Section Length in Km TDC


No MM/YY
1 BZA North Cabin - Gundala 5.01 Feb 22
2 Gundala - Mustabada 6.55 Feb 23
3 BZA North Cabin- Rayapadu 10.02 Feb 23

Year wise commissioning


20-21 21-22 22-23 23-24
0 5.01 16.57
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work : AKOLA- KHANDWA GC Project

Super Critical /Critical : Targetted


������� �������������
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 173.59km
Year of Sanction 2008-09
Anticipated Cost (Cr) 2584.90 Cr
Up to date expenditure (Cr) 896.306 Cr
Length commissioned (Km) 43.50 Kms
Scope Acquired Balance
Land acquisition required in Ha.
138.132 Ha 33.50 Ha 104.632 Ha
State 1-MH 68.23 Ha 33.50 Ha 34.73 Ha
State 2-MP 69.902 Ha 0 69.902 Ha

State-MP
Forest diversion. In Ha
Scope-21.446Ha , diverted-0 Ha, bal.-21.446 Ha

Imp Bridges nos 1


Major Bridges nos 46
Minor Bridges Nos 312
Limited Height Subways & Road
65
under bridges
Road over bridges 2
Stations 17
Physical progress 35%
Can be fixed after getting forest and wildlife
TDC of complete project
clearance for Melghat Tiger Reserve.
SCOPE OF COMPLETE PROJECT

Total
Sl.No. Item Completed % Progress
Scope
1 Earthwork (L.Cum) 109.01 47.12 43.22

2 Sub Grade(SQ2/SQ3)(L.Cum) 19.34 5.64 29.16

3 Blanketing (L.Cum) 8.08 2.06 25.50

4 Imp Bridges 1 1 100

Completed-2
5 Major Bridges (Nos.) 46 10
Progress-8

6 Minor Bridges (Nos.) 312 75 24.04

7 LHS/RUB (Nos.) 65 37 56.92

8 ROBs (Nos) 2 Progress-1 42

9 Track Linking (TKm) 175.43 43.50 24.80

10 Stations Bldg.(Nos.) 17 5 29.41


ISSUES PENDING WITH STATE GOVERNMENT

SN Issue Present status

1. Land Acquisition AMX-KNW Section: 1) Land acquisition in 18 villages


is under process in Khandwa and Burhanpur districts.
Revenue Dept. to hand over the land early.
2) Application for diversion of 21.446 Ha of forest
land between GUX-AMX station submitted. Forest
Dept. of M.P. to hand over the land early.

2. Forestry clearances AOT-AMX Section: Forest and Wild Life clearances are
required.

3. Any Other issues NIL


PHASE-WISE PLANNING TO COMMISSION THE PROJECT

Planning of commissioning :

TDC
S No Name of Section Length in Km
MM/YY
Commissioned
1. Akola-Akot 43.50
on 15-10-2020.
2. Amlakhurd-Khandwa 54.50 March 2023
3. Akot-Amlakhurd 77.43 ---

Year wise commissioning (km)


20-21 21-22 22-23 23-24
43.5 54.50
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: NADIKUDI – SRIKALAHASTI


NEW BG LINE, 308.70 Km
(PH -11, New lines)

Super Critical /Critical – Non Targeted


SALIENT FEATURES OF PROJECT
Length of the Project (Km) 308.70 Km
Year of Sanction 2016
Anticipated Cost (Cr) 4000
Up to date expenditure (Cr) 1477.50 Cr. (Rly: 1471.50 Cr + State: 6.00 Cr)
45.85 kms, CRS Authorization received on
Length commissioned (Km)
dt:20.03.20 and Commissioned on dt:14.06.2020
Land acquisition required in Ha. Scope Acquired Balance
State 1(Andhra Pradesh) 1092.62 492.31 600.31
State – Andhra Pradesh
Forest diversion. In Ha Scope-118.76 Ha , Diverted-Nil Ha,
Bal.-118.76 Ha
Imp Bridges nos 2
Major Bridges nos 94
Minor Bridges Nos 266
Limited Height Subways & Road
148
under bridges
Stations 33
Physical progress 35%
TDC of complete project 03/2025
SCOPE OF COMPLETE PROJECT

SN Item Total Scope Progress % Progress

1 Earthwork (Lakh Cum) 351.31 149.37 42.51%

Hard rock cutting (Lakh


2 12.40 2.73 22.01%
Cum)

3 Imp Bridges 2 In progress 5%

4 Major Bridges (Nos.) 94 23 24.46%

5 Minor Bridges (Nos.) 266 113 42.48%

6 LHS/RUB (Nos.) 148 72 48.64%

7 Track Linking (Km) 341 52 15.24%

8 Stations Bldg.(Nos.) 33 5 15.15%


Name of Project: NADIKUDI-SRIKALAHASTI NEW BG LINE PROJECT
ISSUES PENDING WITH STATE GOVERNMENT
SN Issue Present status
AP State Govt. - 1. Land being handed over by State Govt. is not covering the targeted sections fully.
1. Land Hence, State Govt. has to extend cooperation duly handing over the land covering the entire section
Acquisition for taking up the work. District -wise Issues are mentioned as under :
DC, Guntur Dt. AP state - Allocating and disbursing an amount of Rs 11 Cr. towards uploaded bills of
Mukkellapadu, Chintalacheruvu and Inavolu villages of Guntur district by State Govt. of AP(finance
dept.) to achieve Railway Board target of 2021-22.
DC, Prakasam Dt. AP state – 1.Allocating and disbursing an amount of Rs 11.85 Cr. towards
uploaded bills of Darsi & Podili villages of Prakasam district by State Govt. of AP(finance dept.). 2.
Uploading of bills in Sankhavaram and Peramgudipalli villages of Prakasam district by RDO,
Kandukur.
DC, Nellore Dt. AP state- 1. Approval of awards and uploading of bills in Apparaopalem (Atmakur
mandal) and Perumallapadu(Chejerla Mandal) villages of Nellore district by District Collector,Nellore
and RDO, Atmakur for completion of Penna and Boggeru bridges(long lead items). 2. Handing over of
land from Venkatagiri to Obulayapalle(80 km) 3. Disbursal of an amount of Rs.50 lakhs to DFO,
Nellore towards tree extraction and enumeration charges by State Govt. of AP(finance dept.).
2. Forestry
• Forest Land stage-II clearance to be expedited
clearances

3. Any Other
amount of Rs 1228.80 Cr is outstanding from the Sate Government of AP as part of
50%An project cost share. It has deposited Rs. 6 Cr so far ., ( Rs 1138.35 Cr, Overdue.
issues
Funds to be released immediately for taking up further works.)
 Works are kept in abeyance due to non deposition of funds from AP state Govt.
PHASE-WISE PLANNING TO COMMISSION THE PROJECT

Planning of commissioning :
Sn Name of Section Length in Km TDC
MM/YY
1 New Piduguralla - Savalyapuram, CRS 45.850 2019-20
Authorisation received on 20.03.20 and
Commissioned on 14.06.2020
2 Gundlakamma - Darsi 26.68 2022 - 23
3 Venkatagiri – Alturupadu (15.25Km) & Darsi – Kanigiri 67.55 2023 - 24
(52.30 Km)
4 Kanigiri - Pamuru (35.36 Km) & Alturupadu – 78.61 2024 - 25
Venkatapuram (43.25 Km)
5 Venkatapuram - Obulayapalle (21 Km) & Obulayapalle – 90.23 2025 - 26
Pamuru (69.23 Km)

Year wise commissioning


21-22 22-23 23-24 24-25 25-26
Nil 26.68 Km 67.55 Km 78.61 Km 90.23 Km
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: KADAPA-BANGALORE


NEW BG LINE (260.00 KM)

Super Critical /Critical – Non Targeted


KADAPA – BANGALORE NEW LINE

50 % Phase 1
cost sharing by AP Govt.
in SCR portion
Phase 2

RAYACHOTI

Phase 3

MADANAPALLI ROAD

Phase 4

Madagatta

Executed by South Western


Railway.
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 260.00
Year of Sanction 2008-2009
Anticipated Cost (Cr) 2968.65
Up to date expenditure (Cr) 350.89
Length commissioned (Km) 21.80

Land acquisition required in Ha. Scope Acquired Balance

Andhra Pradesh 1248.26 163.104 1085.155


Karnataka 83.45 0 83.45
State Scope Diverted Balance
Forest diversion. In Ha A.P 56.04 0 56.04

Imp Bridges nos 0


Major Bridges nos 43
Minor Bridges Nos 242
Limited Height Subways & Road
74
under bridges
Stations 26
Physical progress 8.5%
TDC of complete project 2026-27
SCOPE OF COMPLETE PROJECT

Total %
SN Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 124.89 20 16.01
2 Hard rock cutting (Lakh Cum)

3 Imp Bridges 0 0 0

4 Major Bridges (Nos.) 43 4 9.3

5 Minor Bridges (Nos.) 242 38 15.7

6 LHS/RUB (Nos.) 74 20 27

7 Track Linking (Km) 209.49 21.8 10.4


8 Stations Bldg.(Nos.) 26 3 11.54
Name of Project:
ISSUES PENDING WITH STATE GOVERNMENT

SN Issue Present status


• Revenue authoritiesadvised Railways to
1. Land Acquisition
give approval for acquisition of Pvt. land
through consent award in lieu of general
award.
• state government is not coming forward to
share 50%-50% cost of the total project.

Reqision submitted for acquisition of 56.04


2. Forestry clearances
hactares of forest land.Uploading of
authenticated maps in web portal completed.
Stage 1 clearance in Kadapa district may be
given early to start the work.
3. Any Other issues
PHASE-WISE PLANNING TO COMMISSION THE PROJECT

Planning of commissioning :

TDC
Phase Name of Section Length in Km
MM/YY
COMMISSIONED
1 KADAPA-PENDLIMARRI 21.80
ON APRIL 2017
2 PENDLIMARRI-RAYACHOTI 79.20 -
3 RAYACHOTI-VAYALPADU 53.56 -
MADANAPALLI RD-
4 54.56 -
MADAGATTA
MADAGATTA- KOLAR( SWR
5 45.53 -
PORTION)

Year wise commissioning


20-21 21-22 22-23 23-24
• Railway to add sections as per planning of
commissioning /Phases

KM planned for Likely Month and Name of the section


commissioning Year of
commissioning

21.30 April, 2017 Kadapa-Pendlimarri section


commissioned in April ,2017.

12.46 2022-23 Pendlimarri-Nandimandalam


29.46 2023-24 Vayalpadu-Kona
26.00 2024-25 Rayachoti-Kona
60.27 2025-26 Madanapalle-Madaghatta
66.24 2026-27 Nandimandalam-Rayachoti
Targets could be achieved ,If land is handed over and timely deposit of funds by state Govt.
INDIAN RAILWAYS
South Central Railway

Name of Work: Bye pass at WADI (PH:15)


S.C.Railway

Super Critical /Critical: Additional Throughput


Enhancement Project & Non Targeted
JN:
I
AD
W 12

PR
NOT TO SCALE
12 O.
ISL

I JN:
12
AN
D
PF
.
12
12

WAD
0
5 .0 0
7 .8
0
5 .3

G
SIDIN
12

12
12
12
12

12
N.
ST

12
12
H
RT
NO
AR

SUL
LW

SEC LLI (K
0
NA

5 .0
0

EHA
7 .8
0
5 .3

5.00
UND M:9.

7.80
5.30
12

ERA 18)

12
12
12

BAD
12
12

12

12
12
PROPOSED CONSTRUCTION OF WADI BYEPASS
BETWEEN NALWAR AND SULEHALLI STATIONS.
SALIENT FEATURES OF PROJECT
Year of Sanction 2015-16
Month & year of Final San April-2016

Anticipated Cost (Cr) 273.05 Cr(70.19RU,43.57GY,159.29 WADI)

Up to date expenditure (Cr) 57.81 Cr


Length commissioned (Km) NIL

Project falling in (Railway) South Central Railway

Project falling in (States) Andhra Pradesh & Karnataka


Length of Complete Project (Km) 31.60 Kms
Physical progress 21.17%

TDC of complete project 2022-2023


Planning of Commissioning

Name of sections for which likely


Km planned for Likely Month & Year of
month & year of commissioning has
commissioning (Km) commissioning
been given in Col no.2

(1) (2) (3)

2 x 10.60 = 21.20 Kms 2022-2023 Bye pass at Wadi

NOTE: Actual targets depends on handing over of land from State Government.
SN Issue Present status

1. Land acquisition to the extent of 5.3Ha is involved in SEDAM,


Land
Kalaburagi District, Karnataka and Rs.2.00 Cr is deposited to
Acquisition: state authorities (as per their demand).
Out of 13 Acres 10 Guntas of land acquisition, 5 Acres 33
Guntas registered on 05.04.2021. Balance likely in the next
two weeks.
SCOPE OF COMPLETE PROJECT

Total %
SN Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 9.01
2 Hard rock cutting (Lakh Cum) -- -- --

3 Imp Bridges -- -- --

4 Major Bridges (Nos.) 4 0 0%

5 Minor Bridges (Nos.) 17 0 0%

6 LHS/RUB (Nos.) 3 0 0%

7 Track Linking (Km) 21.2 0 0%


8 Stations Bldg.(Nos.) 2 0 0%
Details of Issues and updated status if any :

S&T cables to be shifted. OHE masts to be removed.


Tenders for Major bridges & ROB under process.
MOU on RRI modifications to be finalized with Central Railway.
EFFORTS MADE TO RESOLVE THE ISSUES

Assistance required

1. Land acquisition to be expedite


INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: Construction of new BG line from


Nalgonda -Macherla

Super Critical /Critical – Non Targeted


Construction of new BG line from Nalgonda - Macherla

Map of the Project


SALIENT FEATURES OF PROJECT
Length of the Project (Km) 92.00
Year of Sanction Year of inclusion 1997-98
Anticipated Cost (Cr) 458.26
Up to date expenditure (Cr) 3.69
Length commissioned (Km) Nil
Land acquisition required in Ha. Scope Acquired Balance

State 1 AP -- Nil --
State-2 Telengana -- Nil --
Forest diversion. In Ha State
Scope Ha , diverted Ha, bal. Ha
Imp Bridges nos 2
Major Bridges nos 25
Minor Bridges Nos 73 including LHS/RUB
Limited Height Subways & Road
under bridges
Stations 7
Physical progress Nil
TDC of complete project Kept in abeyance as project is financially
unviable
SCOPE OF COMPLETE PROJECT

%
SN Item Total Scope Progress
Progress
1 Earthwork (Lakh Cum) 52.995 Nil
2 Hard rock cutting (Lakh Cum) --

3 Imp Bridges 2 ---

4 Major Bridges (Nos.) 25 Nil

5 Minor Bridges (Nos.)


73 Nil
6 LHS/RUB (Nos.)

7 Track Linking (Km) 92.00 Nil


8 Stations Bldg.(Nos.) 7 Nil
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: Construction of new BG Line


between Kakinada Port – Pithapuram Stations

Super Critical /Critical – Non Targeted


Construction of new BG line between Kakinada Port - Pithapuram Stations
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 21.5 kms
Year of Sanction --
Anticipated Cost (Cr) 220.29 Cr
Up to date expenditure (Cr) 2.18 Cr
Length commissioned (Km) Nil
Land acquisition required in Ha. Scope Acquired Balance
State 1 AP -- Nil --
Forest diversion. In Ha State
Scope Ha , diverted Ha, bal. Ha
Imp Bridges nos Nil
Major Bridges nos 3
Minor Bridges Nos 43
Limited Height Subways & Road 7
under bridges
Stations 2
Physical progress nil
TDC of complete project Board decided to freeze this project and kept in
abeyance
SCOPE OF COMPLETE PROJECT

SN Item Total Progress %


Scope Progress
1 Earthwork (Lakh Cum) 2.65 nil
2 Hard rock cutting (Lakh Cum) -- --

3 Imp Bridges Nil --

4 Major Bridges (Nos.) 3 nil

5 Minor Bridges (Nos.) 43 nil

6 LHS/RUB (Nos.) 7 nil

7 Track Linking (Km) 21.5 nil


8 Stations Bldg.(Nos.) 2 nil
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: Kotipalli – Narasapur, 57.21 km new


BG line (PH: 11 New lines)

Super Critical /Critical – Non Targeted


KOTIPALLI-NARSAPUR NEW BG LINE (57.21KM)

• Sanctioned in 2000-01
• DE sanctioned in March 2012)
• Cost of the Project : 1045.20 Cr
• Revised Cost (Feb 2020) : 2120.16 Cr

• Cost Sharing :
• Land : By Railways
• Project cost : By M/s SCCL & Rlys
• Figuring in “PRAGATI” of PMO

• Target: ----
•Kotipalli - Narsapur 57.21 km.
•BG 2021-22: 0.00001 Cr
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 57.21 kms
Year of Sanction March 2012
Anticipated Cost (Cr) Rs. 2120.16 cr.
Up to date expenditure (Cr) Rs. 867.644Cr. As on 31.03.2021
Length commissioned (Km) --
Land acquisition required in Ha. Scope Acquired Balance
Andhra Pradesh State 368.68 162.55 206.13

Forest Land -- -- --
Forest diversion. In Ha --
Imp Bridges nos 3 Nos
Major Bridges nos 14 Nos
Minor Bridges Nos 171 Nos
Limited Height Subways & Road ROB-1
under bridges / Road Over Bridge
Stations 2 Nos. crossing station, 4 halt stations
Physical progress 41%
TDC of complete project 2024-25
SCOPE OF COMPLETE PROJECT
Total %
Sn Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 57.30 0 0
2 Hard rock cutting (Lakh Cum) 0 0 0

3 Imp Bridges 3 3 75

4 Major Bridges (Nos.) 14 0 0

5 Minor Bridges (Nos.) 171 0 0

6 LHS/RUB/ROB (Nos.) 1 0 0

7 Track Linking (Km) 57.21 0 0


8 Stations Bldg.(Nos.) 7 0 0
ISSUES PENDING WITH STATE GOVERNMENT

SN Issue Present status

1. Land Acquisition
• Joint survey is completed in 2 villages out of 17 villages.
Support of state government is crucial to complete the
balance land acquisition in time. State govt. may be
East Godavari Dist. Land advised to conduct joint survey immediately on
acquisition is required Ac. 797.19, completion on harvesting of crops.
out of this Ac. 287.84 of revenue
land handed over balanced land • An amount of Rs. 189.76 Cr is to be deposited by the govt.
Ac. 509.35 patta land is still to be of Andhra Pradesh towards 25% of Cost Sharing.
acquired.
PHASE-WISE PLANNING TO COMMISSION THE PROJECT

Planning of commissioning :

S No Name of Section Length in Km TDC


MM/YY

1. Kotipalli - Narsapur 57.21 2024-25


INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: Proposed new BG line between


Bhadrachalam Rd and Kovvur Stations ( Modified
alignment from Sattupalli to Kovvur )

Super Critical /Critical – Non Targeted


Proposed new BG line between Bhadrachalam road and Kovvur Stations
(Modified alignment from Sattupalli to Kovvur)

BHADRACHALAM ROAD - KOVVURU (151 KM) New Line


DO
RN
AK
(50 % COST SHARING by STATE GOVT., OF AP)
AL
(FOR THE LENGTH FALLING IN AP STATE)
U
JN UR
. N UG
MA
TO
BETHAMPUDI(9.74 KM)

M) STATE BORDER
.0 5K
SITAMPETA(13.40 KM) BHADRACHALLAM ROAD (3 6
STATION(0.00 KM) E
LL ) M)
IPA KM 0K ) M)
D D
6.25 5.0 KM 0K
R E ( 4 (5 5 .5
PU U LI .7 75 M)
NA AD AL (66 A( )
M) 5K
CHANDRUGONDA(23.80 KM) AP AP TA ET KM 3 )
AN L L E P 0 K 1 .
KM
GU U
MA
P
RA
O 3.0 .50 10 KM
)
RE AG I(8 87 M( M) .75
MA
( 26 D D A N D
D A M
S W A
I L L
A D (
D E ) 0 K
1 24
7.60
A M O GU 5 .6 ( 13
. 95 U K G
GU IR DI 8.7 16 EM LI (
KM URU J I LU U VA R ED M (10 RU(1 GUD P AL
BHAVANNAPALEM(39.25 KM) ) D A A U A A
TA NG AR UT AY AR
JA J AV O N G H I N N D EV
RA P C KOVVURU(151 KM)
PENUBALLI((49.55 KM)
SATTUPALLI(56.375 KM)
KAZIPET Revised take-off & alignment proposed by Govt., of Telangana

KONDAPALLI LENGTH OF COMMON ALIGNMENT UPTO CHANDRUGONDA - 23.80 KM


LENGTH IN
VIJAYAWADA PROJECT
ANDHRA PRADESH TELANGANA

BHADRACHALAM - KOVVURU 72.50 KM 78.50 KM

BHADRACHALAM - SATTUPALLI - 56.25 KM

BHADRACHALAM - KONDAPALLI 65.50 KM 61.00 KM


SALIENT FEATURES OF PROJECT
Length of the Project (Km) 151.00
Year of Sanction Year of inclusion 2012-13
Anticipated Cost (Cr) 2154.83
Up to date expenditure (Cr) 2.464
Length commissioned (Km) Nil
Land acquisition required in Ha. Scope Acquired Balance

State 1 AP -- Nil --
State-2 Telengana -- Nil --
Forest diversion. In Ha State
Scope Ha , diverted Ha, bal. Ha
Imp Bridges nos 1
Major Bridges nos 29
Minor Bridges Nos 122 including LHS/RUB
Limited Height Subways & Road
under bridges
Stations 9
Physical progress Nil
TDC of complete project Estimate yet to be sanctioned
SCOPE OF COMPLETE PROJECT

SN Item Total Scope Progress %


Progress
1 Earthwork (Lakh Cum) 97.066 Nil
2 Hard rock cutting (Lakh Cum) --

3 Imp Bridges 1 ---

4 Major Bridges (Nos.) 29 Nil

5 Minor Bridges (Nos.) 122 including Nil


LHS/RUB
6 LHS/RUB (Nos.)

7 Track Linking (Km) 151 Nil


8 Stations Bldg.(Nos.) 9 Nil
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: Proposed new BG Line between


Kondapalli – Kothagudem station ( Modified
alignment from Kondapalli to Penuballi )

Super Critical /Critical – Non Targeted


Proposed new BG line between Kondapalli Kothagudem Stations
(Modified alignment from Kondapalli to Penuballi)

KONDAPALLI - BHADRACHALAM ROAD (KOTHAGUDEM) (126.50 KM) New Line


D
O
RN
(13 % Cost Sharing by 2 State Govt's)
AK
AL U
JN UR
. NUG
MA
TO
BETHAMPUDI(9.74 KM)
)
5 KM STATE BORDER
6 .0
SITAMPETA(13.40 KM) BHADRACHALLAM ROAD 3
STATION(0.00 KM) E(
LL ) )
IP A
5 KM 0 KM ) M)
D
ED 46
. 2
5 5.0
5 KM 50K
R ( LI ( .7 . )
PU DU (66 75 KM
CHANDRUGONDA(23.80 KM) NA PA P AL A T A( K M) M ) 5
N A A T E K .3 )
A
G UL G UL A PE A OP 3 .00 .50 1 01 5 KM M)
8 7 ( )
MA RE DA A M M WA R L I( D (8 E M K M 4 .7
. 60K
N L 2
(26 DD GA D AS MI OA UD .75) 6.60 M(1 37
.95 UK GU A IR D IG 08 1 1 D E L I(1
U
KM RU U V ED (1 ( U L
BHAVANNAPALEM(39.25 KM) ) JI L DU AR AM TUR YAG
U
AP
A
TA N G
V A R U N A VA
R
JA G IN
JA ON DE
RA P CH KOVVURU(151 KM)
PENUBALLI((49.55 KM)
SATTUPALLI(56.375 KM)
KAZIPET Revised take-off & alignment proposed by Govt., of Telangana

KONDAPALLI LENGTH OF COMMON ALIGNMENT UPTO CHANDRUGONDA - 23.80 KM


LENGTH IN
VIJAYAWADA PROJECT
ANDHRA PRADESH TELANGANA

BHADRACHALAM - KOVVURU 72.50 KM 78.50 KM

BHADRACHALAM - SATTUPALLI - 56.25 KM

BHADRACHALAM - KONDAPALLI 65.50 KM 61.00 KM


SALIENT FEATURES OF PROJECT
Length of the Project (Km) 81.57
Year of Sanction Year of inclusion 2013-14
Anticipated Cost (Cr) 997.29
Up to date expenditure (Cr) nil
Length commissioned (Km) Nil
Land acquisition required in Ha. Scope Acquired Balance

State 1 AP -- Nil --
State-2 Telengana -- Nil --
Forest diversion. In Ha State
Scope Ha , diverted Ha, bal. Ha
Imp Bridges nos Nil
Major Bridges nos 11
Minor Bridges Nos 107 including LHS/RUB
Limited Height Subways & Road
under bridges
Stations 8
Physical progress Nil
TDC of complete project • Estimate yet to be sanctioned. Project kept
in abeyance.
SCOPE OF COMPLETE PROJECT

SN Item Total Scope Progress %


Progress
1 Earthwork (Lakh Cum) 36.91 Nil
2 Hard rock cutting (Lakh Cum) --

3 Imp Bridges 0 ---

4 Major Bridges (Nos.) 11 Nil

5 Minor Bridges (Nos.) 107 including Nil


LHS/RUB
6 LHS/RUB (Nos.)

7 Track Linking (Km) 81.57 Nil


8 Stations Bldg.(Nos.) 8 Nil
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: Proposed construction of new BG


Line between Gudur - Durgarajapatnam

Super Critical /Critical – Non Targeted


Proposed Construction of new BG line between Gudur - Durgarajapatnam

VIJAYAWADA

BAY OF BENGAL
ONGOLE

PENNAR RIVER

NELLORE
KM
50 KRISHNAPATNAM
VENKATACHALAM 4.
K UR M
LA RA KM
GUDUR JN.(GDR) I L V A .4 0
EXG.136.04 CH SA KM U 25
E
K .50 OD
PRO. Km.0.00 ND
17 E
CH
S

DURGARAJAPATNAM
C KA
V

SRIKALAHASTI
E

L
N

41.55 Km
IM G
IT IR
T

M
A
RE

A
D
N

R
I

A
IG

S
U
N

PROPOSED NEW BG LINE SHOWN IN RED


TA
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 41.55
Year of Sanction Year of inclusion 2011-12
Anticipated Cost (Cr) 761.37
Up to date expenditure (Cr) 0.52
Length commissioned (Km)
Land acquisition required in Ha. Scope Acquired Balance

State 1 AP -- Nil --
Forest diversion. In Ha State
Scope Ha , diverted Ha, bal. Ha
Imp Bridges nos 1
Major Bridges nos 11
Minor Bridges Nos 119 including LHS/RUB
Limited Height Subways & Road
under bridges
Stations 6
Physical progress Nil
TDC of complete project Project kept in abeyance
SCOPE OF COMPLETE PROJECT

SN Item Total Scope Progress %


Progress
1 Earthwork (Lakh Cum) 34.98 Nil
2 Hard rock cutting (Lakh Cum) --

3 Imp Bridges 1 NIL

4 Major Bridges (Nos.) 11 Nil

5 Minor Bridges (Nos.) 119 including Nil


LHS/RUB
6 LHS/RUB (Nos.)

7 Track Linking (Km) 41.55 Nil


8 Stations Bldg.(Nos.) 6 Nil
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: Cumbum-Proddatur NEW BG LINE


(PH: 11 NEW LINES)

Super Critical /Critical – Non Targeted


CUMBUM – PRODATTUR NEW LINE (142 Kms)
N AN

UR
D YA
L

NT
NE

GU
D HO
CUMBUM
Bestavarapeta 135.5km
Mokhagundam 126 km
lle
an apa Tatcherla 117 km
g
B ana Nallaguntla 112.2 km
Komarolu 103.50 km
Rameswaram 93.50 km
Chennamarajupalem 8.0km Vasudevapuram 84.0 km
Chitalapalli 78.5km
Porumamilla 73 km
AM

Chinnapullivedu 66.0km
UR

GUN Mallepalli 53km


AP

TA K NOSAM
AL
D
N

Vanlpenta 36.5km Mudireddipalle 43.0 km


KO

Mydukuru29.5km DOUBLE LINE BG


Chapadu17.5km
PROD DATUR
SINGLE LINE BG
TLA
G UN PA
A A
RR DR
YE KA EN I
P en GU
dl i m SB NT
arri
C A
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 142 kms
Year of Sanction Detailed Estimate not yet sanctioned by
Railway Board
Anticipated Cost (Cr) Rs. 1599.39 Cr cr.(As per DE)
Up to date expenditure (Cr) Rs. 0.0 Cr. As on 31-05-2021
Length commissioned (Km) NIL
Land acquisition required in Ha. Scope Acquired Balance
Andhrapradesh 593.05 0 593.05
Forest Land 23.47 0 23.47
Forest diversion. In Ha State
Scope Ha , diverted Ha, bal. Ha
Imp Bridges nos --
Major Bridges nos 35 Nos
Minor Bridges Nos 325 Nos
Limited Height Subways & Road 7 Nos
under bridges / Road Over Bridge
Stations 6 Nos.
Physical progress 0%
TDC of complete project Frozen / Kept in Abeyance
SCOPE OF COMPLETE PROJECT
Total %
Sn Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 109.78 0.0 0%
2 Hard rock cutting (Lakh Cum) -- -- --

3 Imp Bridges -- -- --

4 Major Bridges (Nos.) 35 0 0%

5 Minor Bridges (Nos.) 325 0 0%

6 LHS/RUB/ROB (Nos.) 7 0 0%

7 Track Linking (Km) 142.28 0 0%


8 Stations Bldg.(Nos.) 6 0 0%
INDIAN RAILWAYS

SOUTH CENTRAL RAILWAY

Name of Work: VIJAYAWADA-GUNTUR Via


AMARAVATHI NEW BG LINE (PH: 11 NEW LINES)

Super Critical /Critical – Non Targeted


VIJAYAWADA – GUNTUR Via AMARAVATHI NEW BG LINE (56.53 KM)

• Sanctioned in 2017-18
• DE not sanctioned.
• Cost of the Project : 1635.81Cr
• Revised Cost (Feb 2020) : --
• Cost Sharing : 50 %
• Land : By Railways
• Project cost : DPR not yet sanctioned.
• Target: Not yet finalised
•VIJAYAWADA – GUNTUR via AMARAVATHI
NEW BG LINE (56.53 km)
•BG 2021-22: Rs.0.00001Cr in CAP
SALIENT FEATURES OF PROJECT
Length of the Project (Km) 56.53 kms
Year of Sanction 2017-18
Anticipated Cost (Cr) Rs. 1635.81 Cr
Up to date expenditure (Cr) Rs. 2.20 Cr towards FLS as on 31-03-2021
Length commissioned (Km) --
Land acquisition required in Ha. Scope Acquired Balance

TELANGANA STATE 31 0 31
Andhra Pradesh State 385 0 385
TOTAL 416 0 416
Forest diversion. In Ha NIL
Imp Bridges nos 0 Nos
Major Bridges nos 32 Nos
Minor Bridges Nos 102 Nos
Limited Height Subways & Road 2 Nos
under bridges / Road Over Bridge
Stations 4 Nos.
Physical progress 0%
TDC of complete project --
SCOPE OF COMPLETE PROJECT
Total %
Sn Item Progress
Scope Progress
1 Earthwork (Lakh Cum) 38.95 0 0
2 Hard rock cutting (Lakh Cum) 0 0 0

3 Imp Bridges 0 0 0

4 Major Bridges (Nos.) 32 0 0

5 Minor Bridges (Nos.) 102 0 0

6 LHS/RUB/ROB (Nos.) 2 0 0

7 Track Linking (Km) 56.53 0 0


8 Stations Bldg.(Nos.) 4 0 0
PHASE-WISE PLANNING TO COMMISSION THE PROJECT

Planning of commissioning :

Sn Name of Section Length in Km TDC


MM/YY
1. Vijayawada – Guntur Via 56.53 --
Amaravathi