The document outlines the schedule for a sample construction project from August 2022 to February 2023. It details the activities and timelines for project engineering, procurement, construction, and commissioning. The schedule involves multiple sub-activities for each phase and indicates timelines for completion across quarters.

Uploaded by

Rinku Mandal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views1 page

Sample

The document outlines the schedule for a sample construction project from August 2022 to February 2023. It details the activities and timelines for project engineering, procurement, construction, and commissioning. The schedule involves multiple sub-activities for each phase and indicates timelines for completion across quarters.

Uploaded by

Rinku Mandal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Office Builkding Construction SChedule 20-Jul-22 15:20

Activity ID Activity Name BL1 Start BL1 Finish BL1 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
tr001 Sample Project1 01-Aug-22 15-Feb-23 169d 02-Mar-23, tr001 Sample Project1

tr001.1 Milestone 01-Aug-22 15-Feb-23 169d 02-Mar-23, tr001.1 Milestone

A1000 Project Start 01-Aug-22 0d Project Start, 01-Aug-22 A


A1010 Completion of BE 28-Sep-22 0d Completion of BE,
A1020 completion of DE 14-Nov-22 0d completion of DE,
A1030 Completion of Project 15-Feb-23 0d Completion of Project,
tr001.2 Engg 12-Aug-22 14-Nov-22 80d 21-Nov-22, tr001.2 Engg

tr001.2.1 BE 12-Aug-22 28-Sep-22 40d 05-Oct-22, tr001.2.1 BE


A1040 be of A 12-Aug-22 16-Sep-22 30d be of A
A1050 be of b 19-Aug-22 22-Sep-22 30d be of b
A1060 be of c 25-Aug-22 28-Sep-22 30d be of c
tr001.2.2 DE 17-Sep-22 14-Nov-22 50d 21-Nov-22, tr001.2.2 DE
A1070 De of A 17-Sep-22 21-Oct-22 30d De of A
A1080 De of b 23-Sep-22 27-Oct-22 30d De of b
A1090 De of c 11-Oct-22 14-Nov-22 30d De of c
tr001.3 Proc 22-Oct-22 19-Dec-22 50d 26-Dec-22, tr001.3 Proc

tr001.3.1 PO 22-Oct-22 01-Dec-22 35d 08-Dec-22, tr001.3.1 PO


A1100 PO of A 22-Oct-22 08-Nov-22 15d PO of A
A1110 PO of b 28-Oct-22 14-Nov-22 15d PO of b
A1120 PO of c 15-Nov-22 01-Dec-22 15d PO of c
tr001.3.2 Supply 09-Nov-22 19-Dec-22 35d 26-Dec-22, tr001.3.2 Supply
A1130 Supply of A 09-Nov-22 25-Nov-22 15d Supply of A
A1140 Supply of b 15-Nov-22 01-Dec-22 15d Supply of b
A1150 Supply of c 02-Dec-22 19-Dec-22 15d Supply of c
tr001.4 Const 22-Oct-22 10-Feb-23 95d 25-Feb-23, tr001.4 Const

tr001.4.1 Civil work 22-Oct-22 30-Dec-22 60d 14-Jan-23, tr001.4.1 Civil work
A1160 CW of A 22-Oct-22 25-Nov-22 30d CW of A
A1170 CW of b 26-Nov-22 30-Dec-22 30d CW of b
A1180 CW of c 15-Nov-22 19-Dec-22 30d CW of c
tr001.4.2 Mechanical work 26-Nov-22 04-Feb-23 60d 20-Feb-23, tr001.4.2 Mechanical work
A1190 MW of A 26-Nov-22 30-Dec-22 30d MW of A
A1200 MW of b 31-Dec-22 04-Feb-23 30d MW of b
A1210 MW of c 20-Dec-22 23-Jan-23 30d MW of c
tr001.4.3 Electrical work 20-Dec-22 10-Feb-23 45d 25-Feb-23, tr001.4.3 Electrical work
A1220 EW of A 20-Dec-22 05-Jan-23 15d EW of A
A1230 EW of b 24-Jan-23 10-Feb-23 15d EW of b
A1240 EW of c 12-Jan-23 30-Jan-23 15d EW of c

tr001.5 Trial & Commissioning 10-Feb-23 15-Feb-23 5d 02-Mar-23, tr001.5 Trial & Commissioning
A1250 Trial & Commissioning of A,B&C 10-Feb-23 15-Feb-23 5d Trial & Commissioning of A,B&C

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities