Article #155 Why Requests For Information (RFI) Will Always Exist On Construction Projects and Why They Need To Be Monitored Closely?

RFIs are an inevitable part of construction projects that help resolve gaps, conflicts or ambiguities in design documents. They must be carefully monitored and managed through the use of templates, workflows and a project management information system to track details, status and ensure proper circulation for response. Analyzing historical RFI data can provide insights into recurring issues to help improve future project documentation and planning.

Uploaded by

Raj Mohammad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views7 pages

Article #155 Why Requests For Information (RFI) Will Always Exist On Construction Projects and Why They Need To Be Monitored Closely?

RFIs are an inevitable part of construction projects that help resolve gaps, conflicts or ambiguities in design documents. They must be carefully monitored and managed through the use of templates, workflows and a project management information system to track details, status and ensure proper circulation for response. Analyzing historical RFI data can provide insights into recurring issues to help improve future project documentation and planning.

Uploaded by

Raj Mohammad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Article #155 Why Requests for Information (RFI) Will Always Exist on Construction

Projects and Why they Need to be Monitored Closely?


Rarely an engineering and construction project is ever delivered that did not have a Request for Information (RFI) issued
by the contractor, subcontractor, suppliers, or any other entity responsible for providing the project. RFIs are part of every
engineering and construction project and will continue to be part of it.
In most Construction Documents (agreements, drawings, specifications, and bills of quantities) developed by the
Engineer, inevitably, those documents will only adequately address some matters. There may be gaps, conflicts, or subtle
ambiguities. The Request for Information (RFI) aims to act as the project communication management process to resolve
these gaps, conflicts, or subtle ambiguities during the bidding process or early in the construction process to eliminate the
need for costly corrective measures. Should the response to the RFI lead to additional work that represents added cost or
delays to the project's scope of work, then this could lead to a change order request by the contractor.
The Effective Management of the RFI process
Like all other project management processes, managing the Request for Information (RFI), Request for Interpretation, or
Request for Clarification, the process requires a document template to be used by the project parties to raise the RFI query
and receive the answer for this query. The details of those RFIs will then be logged in a register to provide the status of
submitted, responded, and pending RFIs. In addition, there should be a documented workflow to enforce the process for
submitting, reviewing, and responding to the RFI by the contract agreement and project execution plan. The Construction
Specification Institute (CSI) has developed document templates for more construction management processes, including
Request for Information, as shown below.
How Can PMIS Improve the RFI Process?
PMWeb RFI module allows the project team member to capture all details needed to manage the RFI. Using a Project
Management Information System (PMIS) like PMWeb where the RFI Module is readily available, the RFI data will be used
to identify trends associated with the reasons for issuing RFIs, effectiveness in responding to RFIs, and the time and cost
impact resulting from those RFIs among others. The default form has fields for Project, Phase (Design, Tender,
Construction), WBS Level, RFI Reference ID, RFI Subject or Description, Reference, Status, Revision, and Revision Date,
RFI Date, Trade (Substructure, Superstructure, etc.), CSI Specification Section, Category (Structural, Mechanical,
Electrical, etc.) and Priority (High, Normal, Low). In addition, there is no limit to the additional custom fields that can be
added as attributes to the RFI using the specification section.

RFI Query, Proposed Solution, and Response


In addition, each RFI needs fields for the query or clarification, the proposed solution by the issuer or other, and the
response or answer to close the RFI. The response to the RFI could impact the project's scope of work, cost, and/or
schedule. The project schedule activity that this RFI response could impact needs to be provided for the schedule. In
addition, should the RFI has a relation with other project management processes, then the relevant documents need to be
linked to the RFI to provide those involved in responding to the RFI with the complete details of the RFI.

The RFI Specification Reference


As almost all RFIs are raised against what was included in Contract Documents, it is recommended that the issuer of the
RFI have the relevant technical specification section or sections related to the RFI. PMWeb Clauses tab allows the
organization to add all technical specification sections and then drag and drop the relevant specification section to the RFI
template. The same approach could also be made for the contract agreement clauses that have a relation or could impact
the issued RFI.
Attach All Supportive Documents
The RFI should have all drawings, specification sections, contract agreements, bill of quantity, pictures, videos, and all
other supportive documents attached to the RFI submission. Although those can be uploaded directly into the RFI, it is
recommended that all those documents be uploaded first to the PMWeb document management repository and then to
the RFI. In addition, PMWeb links project-related emails that were imported to PMWeb to the relevant RFI. In addition,
hyperlinks to external websites like those for seismic activities and building codes, among others.

Submitting, Reviewing, and Responding To RFI


PMWeb Workflow will detail the different roles in submitting, reviewing, and responding to RFIs. What is essential in
PMWeb workflow is that all possible workflow scenarios can be mapped using the conditional workflow rules and
branches. Those rules could be specific to the RFI category, CSI specification section, location, WBS level, reason, impact
on scope, cost, and schedule, among other RFI attributes or fields. This will ensure that the RFI will be distributed
appropriately and circulated among those who are part of the pre-defined RFI management process.
Suppose there is a requirement to involve project stakeholders who are either separate from the process workflow, or
stakeholders who are not part of the PMWeb authorized users. In that case, the PMWeb notification module will be used
to email the RFI and other forms and reports to be reviewed by those stakeholders.

Integrating RFI with Change Events


Should the response to the RFI result in additional cost or delays to the project milestone dates, then PMWeb allows the
authorized user to generate a Change Event that will be used to capture the impact of this RFI on the project budget as
well as the awarded contracts. This will enable tracking RFIs that could have increased the project cost or delayed the
project completion date. The change event will then become the basis for issuing a change order for the changed scope of
work.
Formal RFI Submission and Single Version of The Truth Reporting on RFI Status
In most countries in the MENA region, contract agreements and local legal requirements make a must that all RFIs and
similar other formal project communications need to be printed, signed, and submitted. PMWeb allows the organization
to design the output in any desired format for which the content will be automatically extracted from the RFI input form.
Of course, real-time RFI logs and registers can be designed in any form and format. The RFI Log could be grouped by
reason, status, and location. Similarly, the data can be sorted by those fields, RFI data, or priority level. In addition, logs
can be designed to filter reported RFIs by the same codes or any other possible fields.

Analyzing RFI Management Process


The knowledge wealth that an organization could have from capturing projects' BIG DATA in a trustworthy format can
be proven to be of great value. Since PMWeb is designed to capture data from an unlimited number of projects whether
they are active or completed, the organization can use this data to analyze and identify trends on RFI growth patterns, RFI
issued by contractors, RFI issued on projects designed by a specific consultant, RFI that resulted in change orders, RFI by
reason, RFI by specification section, and RFI by location among others.
About the Author
Bassam Samman, PMP, PSP, EVP, GPM, is a Senior Project Management Consultant
with over 35-year service record providing project management and controls services to
over 100 projects with a total value of over US $5 Billion. Those projects included
Commercial, Residential, Education, and Healthcare Buildings and Infrastructure,
Entertainment and Shopping Malls, Oil and Gas Plants and Refineries,
Telecommunication, and Information Technology projects. He is thoroughly
experienced in project management, including project management control systems,
computerized project control software, claims analysis/prevention, risk
analysis/management (contingency planning), design, supervision, training, and business
development.
Bassam is a frequent speaker on Project Management, Strategic Project Management,
and Project Management Personal Skills. Over the past 35 years, he has lectured at more
than 350 events and courses at different locations in the Middle East, North Africa, Europe, and South America. He has
written more than 250 articles on project management and project management information systems that were featured in
international and regional magazines and newspapers. He is a co-founder of the Project Management Institute- Arabian
Gulf Chapter (PMI-AGC) and has served on its board of directors for over six years. He is a certified Project Management
Professional (PMP) from the Project Management Institute (PMI), an accredited Planning and Scheduling Professional
(PSP), an Earned Value Professional (EVP) from the American Association of Cost Engineers (AACE), and a Green
Project Management (GPM).
Bassam holds a Master's in Engineering Administration (Construction Management) with Faculty Commendation from
George Washington University, Washington, DC, USA, Bachelor in Civil Engineering – from Kuwait University, Kuwait,
and has attended many executive management programs at Harvard Business School, Boston, USA, and London Business
School, London, UK.

You might also like