Untitled
Untitled
TABLE OF CONTENTS
TABLE OF FIGURES
TABLE OF ATTACHMENTS
The objective of design verification is to confirm that designs conform to all design requirements
and criteria.
Prior to using this procedure, the extent of design verification is determined by following TFC-
ENG-DESIGN-C-52. This determination supports the graded approach by selecting design
verification based on aspects of the design, such as cost, complexity, and important to safety.
If the extent of design verification was determined to be more than checking, then design
verification is conducted in accordance with this procedure.
The acceptable methods of Design Verification in accordance with this procedure are:
The design inputs have been evaluated and verified for their impact on the design
The design meets the applicable requirements for environmental, quality, health, safety,
and performance.
2.0 IMPLEMENTATION
This procedure is effective on the date shown in the header. Design verification documents that
have been prepared or are in process may continue according to the previous revision. Refer to
TFC-ENG-DESIGN-C-25 for other implementation considerations such as document numbers,
reviews, approvals and document release.
3.0 RESPONSIBILITIES
(7.1.2)
Design verifications, with the possible exception of testing, are performed by the Design Agent.
There are several individuals within the design agency that may be involved in design
verification. Each of these individual roles is described in the following sections.
Design Verification Manual Engineering
Document TFC-ENG-DESIGN-P-17, REV E-0
Page 3 of 15
Issue Date January 14, 2020
The Design Originator (also considered the Design Agent) is responsible for:
Ensuring design verification occurs only at the appropriate design and project phases.
Preparing, assembling, and submitting the design verification packages to the design
verifier.
If qualification testing is to be performed, verifying that a formal test plan has been
established in accordance with TFC-PRJ-SUT-C-01 (or TFC-ENG-DESIGN-C-18 for
technology development)
Maintaining their independence by not providing input to the design that they are
verifying
Filling out the Design Verification Record form (SPF-023), available on the SmartPlant
Form website
Ensuring unverified designs, or unverified portions of the design are identified and
controlled with a TBD/HOLD in accordance with TFC-ENG-DESIGN-C-25.
Not have immediate supervisory responsibility for the individual performing the design
(design originator).
Not have performed the original design development, including supporting calculations
completed, in conjunction with the activity being verified.
Not have specified a singular design approach or ruled out certain design approaches for
the design being verified.
Not have established the design input for the particular design being verified.
The Design Authority may perform the verification provided the Design Authority meets the
requirements of the items above.
4.0 PROCEDURE
This section continues from the point where TFC-ENG-DESIGN-C-52 directs that this
procedure be used to perform, or document Design Verification.
To document that vendor provided designs have been design verified by the vendor, proceed to
Section 4.7.
Design Verification must be performed prior to releasing the final design, or a portion of the
final design for:
Procurement
Manufacture
Construction
Use by another design organization
Turnover to Operations (Final Design).
Except where this timing cannot be met, such as when insufficient data exist, in which case
design verification will be performed at a later date.
Design Verification Manual Engineering
Document TFC-ENG-DESIGN-P-17, REV E-0
Page 5 of 15
Issue Date January 14, 2020
In all cases, the design verification must be completed prior to relying upon the component,
system, structure to perform its function.
Although it is not preferable, the need may arise to release the design, or a portion of the design
before design verification can be performed.
If the DRCM contains project related (non-design) requirements, only design requirements shall
be considered for design verification.
Design verification is performed in the context of all engineering documents that represent or
support the final design, or the portion of the final design being verified. These must be
available to the design verifier. The design verifier may be provided the documents as hard
copies, or a list of the documents if they are easily retrievable (e.g. SmartPlant® Foundation ) by
the design verifier.
For designs where portions of the design have previously been verified, the design verifier must
have access to both the previously verified design documents, and the design verification
package used for the previous verification.
For evaluation of new technologies for suitability of deployment, the only design information
available may be performance and functional criteria (TFC-PLN-90 and TFC-ENG-DESIGN-C-
34).
All documents that establish or flow down design requirements, inputs, or criteria, such
as:
Modification Travelers
Specifications
Design Verification Manual Engineering
Document TFC-ENG-DESIGN-P-17, REV E-0
Page 6 of 15
Issue Date January 14, 2020
All documents that describe, depict, or implement the design, such as:
All supporting documents that analyze, assess, or qualify or otherwise support the
design, such as:
Calculations
Technical Evaluations
Reports
Previously verified design documents, and the associated design verification package.
The acceptable methods of design verification used to satisfy the requirements of this procedure
are:
Section 5.0 provides definitions of these different types of design verification. Attachment A
provides guidance on selection of the design verification method.
In some cases, it may be appropriate to combine more than one design verification method to
ensure all aspects of a design are adequately verified.
Qualification testing is most frequently used when an aspect of the design cannot be verified
analytically. However, in some cases analytical verification is possible, qualification testing may
be the preferable method for verification. This is especially true when aspects of a design are
extremely difficult or time consuming to verify analytically.
Reviewer comments should only identify inadequate or missing design inputs (requirements), or
identify requirements or criteria not met. The reviewer’s comments may explain why
requirements are not met when necessary for clarification. However, the comments shall NOT
provide proposed solutions or resolutions other than “meet requirement.” The comment should
indicate how the requirement is not met (e.g., the load stress is higher than the allowable stress
for the material)
Design Verification Manual Engineering
Document TFC-ENG-DESIGN-P-17, REV E-0
Page 7 of 15
Issue Date January 14, 2020
Otherwise, documenting and resolving comments for all Design Verification methods is
performed in accordance with the Review Comment Record process in TFC-ENG-DESIGN-C-
52.
Design Originator 1. Using Attachment A and the DRCM (if available), identify the
method, or methods of design verification to be performed.
Design Originator 9. Provide the design verification package to the design verifier.
Design Verifier 10. Continue to the appropriate section of the procedure to perform
design verification using the method(s) identified on the DVR.
Design Verifier 1. Using the design package, and the checklist in Figure 1, perform
design verification review against the scope identified on the DVR.
Design Verification Manual Engineering
Document TFC-ENG-DESIGN-P-17, REV E-0
Page 8 of 15
Issue Date January 14, 2020
Design Originator 2. Resolve comments with the Design Verifier per Section 4.1.6.
The Design Verifier may use an alternative calculation to verify the results of a calculation
produced in accordance with TFC-ENG-DESIGN-C-10.
Design Verifier 1. Ensure a Design verification review has been performed. If not,
proceed to Section 4.3.
NOTE 1: The alternate calculation must use the same inputs and
assumptions used in the original calculation. However, the alternate
calculation must use a different analytical methodology than the original
calculation.
Design Originator 5. Resolve comments with the Design Verifier per Section 4.1.6.
Design Verification Manual Engineering
Document TFC-ENG-DESIGN-P-17, REV E-0
Page 9 of 15
Issue Date January 14, 2020
Reviews in this section identify the features, characteristics, and functions that must be verified
by testing.
Design Verifier 1. Ensure a Design verification review has been performed. If not,
proceed to Section 4.3.
2. Identify the requirements of the design that need to, or are planned to
be verified by Qualification Testing. Document these on the Design
Verification Record (DVR).
4. Verifying that a formal test plan has been established, and that will
verify the list of requirements identified on the DVR by the Design
Verifier to be verified by Qualification Testing.
5. If a test plan has not been developed, or existing test plans do not
adequately verify the requirements, exit this procedure and develop a
test plan, or revise existing test plans in accordance with the
applicable test plan procedure.
Design Verifier 8. Verify that qualification testing successfully verified the requirements
listed on the DVR.
11. Finish filling out the DVR by referencing the test reports that
document verification of the requirements.
Design Verifier 1. Complete the remaining portions of the DVR form. Attach completed
checklists used for each verification method to the DVR, and approve
the DVR.
Design Originator 3. Attach the approved DVR and any additional documentation to the
document. Ensure the Design Verifier is an approver on the
document.
4. Return to TFC-ENG-DESIGN-C-52.
This section is used to ensure that designs produced by vendors have been design verified by the vendor.
Project Engineer 1. Fill out the Design Verification Record (DVR) form (SPF form SPF-
023) for the sections applicable to vendor produced designs.
5.0 DEFINITIONS
Design Requirements Compliance Matrix (DRCM). A single point of reference for applicable
design requirements and design assumptions/Documented Safety Analysis (DSA) assumptions
(if applicable)/project technical assumptions (if applicable) that would impact design or
deployment associated with a project, and documentation of requirement compliance and
technical assumptions reasonableness and re-verification, where necessary.
represent the entire design. This evaluation verifies the adequacy of design inputs, technical
assumptions, design methods, interfaces, and outputs.
Qualification Testing. Testing (including prototype testing and proof testing) that verifies
adequacy of design under conditions that simulate the most adverse design conditions, operating
modes, and environmental conditions.
6.0 RECORDS
(7.1.5)
The record custodian identified in the Company Level Records Inventory and Disposition
Schedules (RIDS) is responsible for record retention in accordance with
TFC-BSM-IRM_DC-C-02.
7.0 SOURCES
7.1 Requirements
7.2 References
2 Have design assumptions, DSA assumptions (if applicable), and ☐ Yes ☐ No ☐ N/A
project technical assumptions (if applicable) that would impact
design or deployment associated with the project been adequately
described and are they reasonable? Where necessary, have
assumptions been identified for re-verification when the design task
has been completed (e.g., design assumptions included in design
calculations, DSA assumptions included in applicable DSA, project
technical assumptions (where applicable) that would impact design
or deployment included in the Project Execution Plan risks and
assumptions lists (if applicable), and project specific risk
management plan (if applicable))?
3 Were appropriate design or analytical methods and computer ☐ Yes ☐ No ☐ N/A
programs used?
4 Were the design or analytical inputs correctly incorporated into the ☐ Yes ☐ No ☐ N/A
design, analysis or evaluation?
5 Does the design meet the functional and performance requirements? ☐ Yes ☐ No ☐ N/A
6 Are the necessary design inputs for interfacing organizations ☐ Yes ☐ No ☐ N/A
specified in the design documents or in supporting procedures or
instructions?
7 Have suitable materials, parts, processes, and inspection and testing ☐ Yes ☐ No ☐ N/A
criteria been specified?
8 Have engineering standards (including national consensus codes ☐ Yes ☐ No ☐ N/A
and standards) and criteria been specified properly in the design?
9 Is the design in compliance with applicable regulatory requirements ☐ Yes ☐ No ☐ N/A
and/or regulatory commitments?
10 Have Human Factors in accordance with TFC-ENG-STD-01 been ☐ Yes ☐ No ☐ N/A
incorporated into the design?
Additional Comments/Issues:
Design Verification Manual Engineering
Document TFC-ENG-DESIGN-P-17, REV E-0
Page 14 of 15
Issue Date January 14, 2020