Critical Path-19
Critical Path-19
Critical Path-19
WEEKLY 19
ID Task Task Name Duration Start Finish Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19
Mode 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05
1 Construction 591 days Sun 15/07/18 Sun 15/03/20 15/07 15/03
2 Phase 1 (As 1- 11; 20.725 m2) 286 days Sun 15/07/18 Tue 30/04/19 15/07 30/04
3 PEKERJAAN PERSIAPAN 286 days Sun 15/07/18 Tue 30/04/19 15/07 30/04
4 Site management, Site Office, dll (sesuai BQ) 286 days Sun 15/07/18 Tue 30/04/19
5 PEKERJAAN BANGUNAN UTAMA 286 days Sun 15/07/18 Tue 30/04/19 15/07 30/04
6 PEKERJAAN TANAH, PONDASI & STRUKTUR 249 days Sun 15/07/18 Sun 24/03/19 15/07 24/03
BETON
93 Site management, Site Office, dll (sesuai BQ) 153 days Wed 01/05/19 Tue 15/10/19
94 PEKERJAAN BANGUNAN UTAMA 339 days Sat 15/09/18 Fri 06/09/19 15/09
95 PEKERJAAN TANAH, PONDASI & STRUKTUR 284 days Sat 15/09/18 Fri 12/07/19 15/09
BETON
161 PEKERJAAN PERSIAPAN 152 days Wed 16/10/19 Sun 15/03/20 15/03
162 Site management, Site Office, dll (sesuai BQ) 152 days Wed 16/10/19 Sun 15/03/20
163 PEKERJAAN BANGUNAN UTAMA 432 days Sat 15/12/18 Sun 08/03/20 15/12 08/03
164 PEKERJAAN TANAH, PONDASI & STRUKTUR 308 days Sat 15/12/18 Tue 05/11/19 15/12
BETON
207 PEKERJAAN BANGUNAN UTILITAS 67 days Thu 09/01/20 Sun 15/03/20 15/03
212 Pekerjaan Pagar BRC 120 days Sun 16/06/19 Mon 14/10/19
217 Lapis Perkerasan (Loading Dock) 150 days Thu 15/08/19 Sun 12/01/20
218 Pekerjaan pedestrian 100 days Tue 15/10/19 Wed 22/01/20
219 Pekerjaan area parkir 110 days Tue 29/10/19 Sat 15/02/20
220 Pekerjaan Taman/Penghijauan 25 days Sun 16/02/20 Wed 11/03/20
221 Pekerjaan Whell Stopper 25 days Sun 16/02/20 Wed 11/03/20
222 Pekerjaan Tiang Bendera 9 days Sat 07/03/20 Sun 15/03/20
223 Pekerjaan Dock Leveler Uk. 2110 x 2119 mm 40 days Thu 23/01/20 Mon 02/03/20
228 PEKERJAAN PROVISIONAL SUM 245 days Sat 13/07/19 Sat 14/03/20 14/03
PROJECT WH 14 Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
DELTA SILICONE 3- CIKARANG Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress