CRITICAL PATH

WEEKLY 19
ID Task Task Name Duration Start Finish Jul '18 Aug '18 Sep '18 Oct '18 Nov '18 Dec '18 Jan '19 Feb '19 Mar '19 Apr '19 May '19
Mode 08 15 22 29 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20 27 03 10 17 24 03 10 17 24 31 07 14 21 28 05
1 Construction 591 days Sun 15/07/18 Sun 15/03/20 15/07 15/03

2 Phase 1 (As 1- 11; 20.725 m2) 286 days Sun 15/07/18 Tue 30/04/19 15/07 30/04

3 PEKERJAAN PERSIAPAN 286 days Sun 15/07/18 Tue 30/04/19 15/07 30/04

4 Site management, Site Office, dll (sesuai BQ) 286 days Sun 15/07/18 Tue 30/04/19
5 PEKERJAAN BANGUNAN UTAMA 286 days Sun 15/07/18 Tue 30/04/19 15/07 30/04

6 PEKERJAAN TANAH, PONDASI & STRUKTUR 249 days Sun 15/07/18 Sun 24/03/19 15/07 24/03
BETON

8 Indikator Pile 14 days Sun 15/07/18 Sat 28/07/18


9 Test Pile/Loading test 16 days Sun 29/07/18 Mon 13/08/18
10 Pondasi Pancang (diesel + drop hammer) 61 days Tue 14/08/18 Sun 14/10/18
91 Phase 2 (As 12- 21; 21.330 m2) 378 days Sat 15/09/18 Tue 15/10/19 15/09

92 PEKERJAAN PERSIAPAN 153 days Wed 01/05/19 Tue 15/10/19 01/05

93 Site management, Site Office, dll (sesuai BQ) 153 days Wed 01/05/19 Tue 15/10/19
94 PEKERJAAN BANGUNAN UTAMA 339 days Sat 15/09/18 Fri 06/09/19 15/09

95 PEKERJAAN TANAH, PONDASI & STRUKTUR 284 days Sat 15/09/18 Fri 12/07/19 15/09
BETON

97 Indikator Pile 14 days Sat 15/09/18 Fri 28/09/18


98 Test Pile/Loading test 16 days Sat 29/09/18 Sun 14/10/18
99 Pondasi Pancang (diesel + drop hammer) 75 days Mon 15/10/18 Sun 30/12/18
160 Phase 3 (As 22- 33; 25.430 m2) 439 days Sat 15/12/18 Sun 15/03/20 15/12 15/03

161 PEKERJAAN PERSIAPAN 152 days Wed 16/10/19 Sun 15/03/20 15/03

162 Site management, Site Office, dll (sesuai BQ) 152 days Wed 16/10/19 Sun 15/03/20
163 PEKERJAAN BANGUNAN UTAMA 432 days Sat 15/12/18 Sun 08/03/20 15/12 08/03

164 PEKERJAAN TANAH, PONDASI & STRUKTUR 308 days Sat 15/12/18 Tue 05/11/19 15/12
BETON

166 Indikator Pile 14 days Sat 15/12/18 Sun 30/12/18


167 Test Pile/Loading test 33 days Mon 31/12/18 Sat 02/02/19
168 Pondasi Pancang (diesel + drop hammer) 85 days Sun 03/02/19 Sun 28/04/19
169 Pekerjaan Pondasi Pile Cap 75 days Fri 22/02/19 Tue 07/05/19
170 Pekerjaan Retaining Wall (dpt) 100 days Fri 22/02/19 Sat 15/06/19
174 Pekerjaan Kolom 90 days Fri 22/02/19 Wed 22/05/19
181 PEKERJAAN SLAB LANTAI VAS MEZZANINE 125 days Mon 18/03/19 Sat 03/08/19 18/03

182 Pekerjaan kolom mezzanine 70 days Mon 18/03/19 Sun 09/06/19


183 Pekerjaan balok mezzanine 85 days Sat 20/04/19 Sat 27/07/19
184 Pekerjaan slab mezzanine 85 days Sat 20/04/19 Sat 27/07/19
185 Pekerjaan tangga VAS Mezzanine (2 unit) 7 days Sun 28/07/19 Sat 03/08/19
186 PEKERJAAN ARSITEKTUR 183 days Sun 08/09/19 Sun 08/03/20 08/03

187 Pekerjaan Dinding 100 days Sun 08/09/19 Mon 16/12/19


189 Pekerjaan Pintu dan Jendela 110 days Sun 29/09/19 Thu 16/01/20
191 Pekerjaan Plafon 110 days Sun 13/10/19 Thu 30/01/20
192 Pekerjaan Keramik 100 days Sun 27/10/19 Mon 03/02/20
194 Pekerjaan Sanitary 100 days Sun 10/11/19 Mon 17/02/20
206 PEKERJAAN EKSTERNAL 273 days Sun 16/06/19 Sun 15/03/20 15/03

207 PEKERJAAN BANGUNAN UTILITAS 67 days Thu 09/01/20 Sun 15/03/20 15/03

208 Disposal Area 67 days Thu 09/01/20 Sun 15/03/20


209 maintenance Room 67 days Thu 09/01/20 Sun 15/03/20
210 Pallet Room 67 days Thu 09/01/20 Sun 15/03/20
211 PEKERJAAN INFRASTRUKTUR 273 days Sun 16/06/19 Sun 15/03/20 15/03

212 Pekerjaan Pagar BRC 120 days Sun 16/06/19 Mon 14/10/19
217 Lapis Perkerasan (Loading Dock) 150 days Thu 15/08/19 Sun 12/01/20
218 Pekerjaan pedestrian 100 days Tue 15/10/19 Wed 22/01/20
219 Pekerjaan area parkir 110 days Tue 29/10/19 Sat 15/02/20
220 Pekerjaan Taman/Penghijauan 25 days Sun 16/02/20 Wed 11/03/20
221 Pekerjaan Whell Stopper 25 days Sun 16/02/20 Wed 11/03/20
222 Pekerjaan Tiang Bendera 9 days Sat 07/03/20 Sun 15/03/20
223 Pekerjaan Dock Leveler Uk. 2110 x 2119 mm 40 days Thu 23/01/20 Mon 02/03/20
228 PEKERJAAN PROVISIONAL SUM 245 days Sat 13/07/19 Sat 14/03/20 14/03

231 PEKERJAAN DOCK LEVELER 52 days Thu 23/01/20 Sat 14/03/20


232 PEKERJAAN RUBBER BUMPER 52 days Thu 23/01/20 Sat 14/03/20
234 Hand Over Phase 3 0 days Sun 15/03/20 Sun 15/03/20

PROJECT WH 14 Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
DELTA SILICONE 3- CIKARANG Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress