Project Schedule - (Line Protector) & Update - 240718
Project Schedule - (Line Protector) & Update - 240718
Project Schedule - (Line Protector) & Update - 240718
No Description
Note: We shift existing Metal Forming Line machines ONLY after the new machines trial done & success !
Remarks
I PO Received & DP
1.1 PO Received Nadirman 14/12
1.2 DP 30% again Bank Guarantee Nadirman Wk-3 19/12
II Purchase & Complete design
2.1 Complete Design and Review Hengki/ Akhirman 5-6 Weeks
- Design and details
2.2 BOM List Review and getting quotation from Vendor Hengki/ Andri/ Akhirman 5-6 Weeks
- Uncoiller, Strengter, Rolling M/C and Feeder
Waiting LM Gui
2.3.3 Electrical parts 6-8 Weeks Slide Guide
Completed
2.4 FABRICATION Zaimuddin/ Udin/ Jamal 6-8 Weeks
2.4.1 Conveyor after cut-1
Completed
2.4.2 Plate Stacker
Completed
2.4.3 Plate P&P
Completed
2.4.4 Engraving
3.4 MACHINE INSTALATION & INTEGRATION AT CT Hengki/ Andri/ Deny/ Udin 6-8 Weeks
3.4.1 Mechanical Instalation 6 Weeks
3.4 2 Electrical Instalation 6 Weeks
HARI RAYA
METAL PROTECTOR – AUTOMATION LINE Planning
Detail Plan Actual
Delay
24 25 26
1 Mechanical - Setup
1.1 Moving mc from VEB to CT Akhirman / Deni
2 Electrical Setup
2.1 Termination Electrical Team
June July
WW 26 WW 27 WW 28 WW 29 WW 30
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
August
WW 30 WW 31 WW 32 WW 33 WW 34
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
WW 34 WW35
S S M T W T F
25 26 27 28 29 30 31