Project Charter
Project Charter
Project Objectives:
Project Requirements:
1. Purchase licenses for Windows 11 for all 200 computers in the office.
2. Ensure that all necessary software and applications are installed on the new
operating system.
3. Provide training to employees on the use of Windows 11.
4. Transfer all files and data from Mac OS to Windows 11 without data loss.
5. Ensure that all hardware components are compatible with Windows 11.
The scope of this project is to migrate 200 computers in an office from Mac OS to
Windows 11. The project includes purchasing licenses for Windows 11, installing
necessary software and applications, transferring data from Mac OS to Windows
11, providing training to employees on the use of Windows 11, and ensuring that
all hardware components are compatible with the new operating system. The
project does not include purchasing new hardware components.
MOSCOW:
Must have:
Migrate 200 computers from Mac OS to Windows 11
Install necessary software and applications
Transfer data from Mac OS to Windows 11
Provide training to employees on the use of Windows 11
Ensure hardware components are compatible with Windows 11
Should have:
Minimize disruption to office operations during the migration process
Ensure all applications used by employees on Mac OS are available on
Windows 11
Could have:
Purchase new hardware components if required
Won’t have:
Purchase new hardware components
Project Methodology:
The project methodology we will use is the Agile methodology. Agile is a flexible and
iterative approach that allows us to adapt to changes and feedback throughout the
project. The Agile methodology will allow us to work closely with stakeholders to ensure
their needs and requirements are met. It also promotes collaboration, communication,
and continuous improvement.
1. Project Initiation
Define project objectives and scope
Identify stakeholders
Develop project charter
2. Planning
Identify software and application requirements
Purchase Windows 11 licenses
Develop migration plan
Develop training plan
3. Execution
Install Windows 11 and necessary software and applications
Transfer data from Mac OS to Windows 11
Provide training to employees
4. Monitoring and Control
Monitor progress and identify risks
Manage project changes
5. Closure
Conduct lessons learned audit
Close out project
Risks Table:
Risk Likelihood Impact Mitigation Strategy
Hardware compatibility Conduct a hardware inventory to identify potential issues and test
issues High Medium compatibility prior to migration
Software compatibility Identify all necessary software and applications and ensure
issues High Medium compatibility with Windows 11
Employee resistance to Provide training and support throughout the process to ensure
change Medium High employees feel comfortable with the new operating system
Technical issues during Conduct thorough testing and have a backup plan in place in case of
migration High High technical issues
Ensure that the project team has the necessary resources, including
Insufficient resources High Medium personnel and equipment, to complete the project successfully
At the end of the project, we will conduct a lessons learned audit to identify areas of
success and areas for improvement in the project. We will gather feedback from
stakeholders, including employees and third-party vendors, to identify what worked well
and what could have been done differently. The lessons learned audit will help us
improve our processes and approach for future projects.