Objectives

The document introduces different types of formwork systems and common site practices for formwork construction. It aims to provide hands-on experience for students to design and fabricate formwork for placing concrete. It also covers different types of metal falsework and critical issues in their design and construction when supporting formworks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
47 views17 pages

Objectives

The document introduces different types of formwork systems and common site practices for formwork construction. It aims to provide hands-on experience for students to design and fabricate formwork for placing concrete. It also covers different types of metal falsework and critical issues in their design and construction when supporting formworks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

Objectives

◼ To introduce different types of formwork


system and common site practices of
formwork construction
◼ To provide ‘hands-on’ experience for
students to design and fabricate formwork
for placing concrete.
◼ To appreciate different types of metal
falsework; and the critical issues in design
and construction of falsework in supporting
formworks

1
Formwork & Falsework _ OT-03

BCS Stream

Website: - http://158.132.155.107/bcu/
Learning Outcome _ OT-03
After the end of this training lesson, you will be able to
know

◼ location and functions of Kicker and Pocket


◼ formwork for concrete cast in-situ
◼ formwork for pre-cast concrete unit
◼ types of form tie
◼ hand tools safety
◼ woodworking machines safety
◼ practices on production of formwork
3
Training flow _ OT-03
◼ e_Lecture 80 minutes

◼ Demonstration 30 minutes
◼ Hands-on practice 50 minutes
◼ Reflection 20 minutes

Total: 180 minutes

4
Location and functions of
Kicker and Pocket
https://www.cedd.gov.hk/filemanager/eng/content_72/GS_2006
Edition_VOLUME_2_26Feb07.pdf _ (CEDD, GS vol.2, Sec14,
Page14.12&13, Clause14.29 (3)(7) )

◼ Formwork shall be firmly supported and individual


panels shall be rigid. Joints between formwork
panels, stop ends and adjoining concrete shall be
tight and shall not permit grout loss. Gaps shall be Kicker
sealed with gaskets, filler, sealant or tape before
the application of release agents.

◼ If required for cleaning or inspection, temporary


openings shall be provided in the formwork.
Temporary openings shall not be cut in any
formwork without the approval of the Engineer.

Pocket 5
Formwork for cast-in-situ
◼ The form is erected on site in location.

◼ Inspection is very important in all stage formwork


and should consist of checking the various forms, to
ensure sufficiently strong and rigid enough.

◼ The checking should be included all part of formwork


i.e. wedges, braces and ties etc.

◼ The size, level, plumb and alignment also be check


time to time.

◼ Falsework, scaffolding and working platform are the


main accessories.
6
Formwork for cast-in-situ

7
Precast concrete form
◼ Precast concrete usually has to be made within fine limit of accuracy
and to a high degree of finish.

◼ Precast units have to fit and easily install when delivery on site.

◼ The mould boxes have therefore to be carefully made to permit these


standards in casting.

◼ For mass production purpose, it is necessary to be able to strike a


mould when the concrete is in a vary green state, both to permit early
re-use of the forms and to enable the finished article to be cleaned
down when in a workable state.

◼ Its panel or unit should come square away from the concrete face and
not side off it.

◼ Hinge, tenon and easy bolt shall be used for joint of erection.

◼ The placing direction is always different from the design on site. 8


Precast concrete form
https://www.housingauthority.gov.hk/en/business-partnerships/resources/prefabrication-in-housing-blocks/index.html

Precast Concrete installation


https://www.youtube.com/watch?v=qcmv4nzD_hA (00:30 to 02:50)
9
Precast concrete facade installation

10
Types of form tie
Form tie (tie bolt) to through the two pieces of wall form panels and tie them together,
which acts in tension due to pressure from elevated height difference of fresh concrete.
Lot of types can be adopted from the market, e.g. …..
對拉螺絲
FORM TIE

膠杯孔
TIE BOLT HOLE
膠套筒
PVC SLEEVE

11
Types of form tie
FIBERGLASS TIE ROD
對拉螺絲
FORM TIE

花籃螺絲
TURNBUCKLE TIE

膠杯
PLASTIC CONE

12
Working Safely with
Hand Tools (in face to face session)
https://www.labour.gov.hk/eng/public/content2_8d.htm

13
Basic woodworking machinery
(in face to face session)
https://www.labour.gov.hk/eng/public/os/A/WWMR.pdf
There is a high risk of accident from the use of woodworking machinery.
In spite of improved safeguards, many people using these machines are
injured each year.
The facts show that injuries from these accidents are invariably more
serious than those caused by ordinary machinery and a great many of the
victims suffer from permanent incapacity.
The Factories and Industrial Undertakings (Woodworking Machinery)
Regulations lay down standards of safety measures for woodworking
machinery and impose duties on proprietors to protect persons operating
the machinery. At the same time, the Regulations also place a legal
obligation on persons employed to use the guards and safety devices
provided.

https://www.youtube.com/watch?v=v2ixRV9VBkU&app=desktop
(00:00 to 02:22) 14
Basic woodworking machinery

15
Training assignment
In the video: Basic woodworking machinery https://www.youtube.com/watch?v=v2ixRV9VBkU&app=desktop

please state the mistakes of the operator?


1. …..
2. …..
3. …..
4. …..

◼ to use MS Word
◼ to submit the file to Blackboard for teacher’s
comment 16
Hands on practice (exercise 3)
(for 3 sessions)

◼ For production hands on practice and safety session of Group


Project, please refer to further notice from the PolyU
◼ You must bring your own Safety Shoes and Long Trousers along
to IC workshop for practice training

In the workshop area:


◼ 1st: Please divided into several groups (about 5 per group)
◼ 2nd: Each group of you to take an Exercise Sheet

◼ 3rd: To design the formwork, estimate materials, cut


materials and fabricate the formwork

17