Jadual Pelaksanaan Pekerjaan

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

JADUAL PELAKSANAAN PEKERJAAN

Pekerjaan : RIGID JALAN NURSERY


Lokasi : SAMARA HILLS
Kontraktror : PT. FULLMOON CREATIVE LOMBOK

JUMLAH BOBOT HARI PROSENTASE


U R A I A N P E K E R J A A N HARGA (%)
(%)
(Rp.) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45

Mobilisasi & Demobilisasi 15,000,000.00 0.78 0.1 0.1 0.1 0.1 0.1 0.1 0.1 100
Air & Listrik Kerja 15,000,000.00 0.777453 0.3 0.3 0.3
Kebersihan area Kerja Sebelum dan Sesudah Pekerjaan 15,000,000.00 0.78 0.3 0.3 0.3
APD 3,000,000.00 0.16 0.1 0.1
Alat dan perlengkapan Kerja 5,000,000.00 0.26 0.1 0.1 0.1 0.1 0.1
LPA Layer, thickness = 15 m + Compaction 713,451,375.00 36.97833 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2 1.2
Wiremesh M7 1 layer - (Include Beton Decking) 508,545,375.00 26.36 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
Formwork thickness 10 cm 35,042,800.00 1.816275 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Concrete thk.10 cm (K - 300) 615,838,080.00 31.92 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Perawatan Beton ( 3 X sehari selama 7 Hari) 3,500,000.00 0.18 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0

1,929,377,630.00
100.00
Jumlah Keseluruhan (Dibulatkan) 1,929,377,000.00
Prosentase Rencana Keseluruhan 0.1 0.2 0.5 0.4 0.7 0.4 1.6 2.0 2.1 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 1.8 1.8 1.0 1.0 1.0 1.0 0.03 0.03
Rencanan Komulatif Pekerjaan - 0.1 0.3 0.8 1.2 1.9 2.4 4.0 6.0 8.1 11.1 14.1 17.1 20.1 23.1 26.2 29.2 32.2 35.2 38.2 41.2 44.2 47.2 50.2 53.2 56.3 59.3 62.3 65.3 68.3 71.3 74.3 77.3 80.3 83.4 86.4 89.4 92.4 94.2 96.0 97.1 98.1 99.0 100 100 100
Prosentase Rencana Pekerjaan - - - - - - - - - - - - - - -
Realisasi Komulatif Pekerjaan - - - - - - - - - - - - - - -
Deviasi - - - - - - - - - - - - - - -
JADUAL MATERIAL ONSITE
Pekerjaan : RIGID JALAN NURSERY
Lokasi : SAMARA HILLS
Kontraktror : PT. FULLMOON CREATIVE LOMBOK

HARI
U R A I A N P E K E R J A A N
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

Mobilisasi Tenaga dan Peralatan


- Tenaga Kerja
Alat dan perlengkapan Kerja
- Kayu Kaso
- Multiplex
- Wiremesh
- Excavator PC.20
- Vibro
- Concrete Truss Screed
- Concrete Vibrator
LPA
Concrete thk.10 cm (K - 300)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 27 28 29 30 31 32
1 2
Ra KEBUTUHAN BETON HARIAN
Pekerjaan : RIGID JALAN NURSERY
Lokasi : SAMARA HILLS
Kontraktror : PT. FULLMOON CREATIVE LOMBOK

HARI
U R A I A N P E K E R J A A N
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45

Concrete thk.10 cm (K - 300)