0% found this document useful (0 votes)
68 views1 page

Work Programme Soil Investigation

This document outlines the work program for soil investigation works at two project sites - Section 11 (Lot 201) and Section 12 (Lot 2892) - over a 6 week period. The program involves mobilization of surveyors and boring teams, fieldworks including soil boring, lab testing of samples, and submission of a report. A work sequence is provided showing which boring holes (BH1, BH2, etc.) each team will work on each week, while accounting for weekends and holidays.

Uploaded by

faizal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
68 views1 page

Work Programme Soil Investigation

This document outlines the work program for soil investigation works at two project sites - Section 11 (Lot 201) and Section 12 (Lot 2892) - over a 6 week period. The program involves mobilization of surveyors and boring teams, fieldworks including soil boring, lab testing of samples, and submission of a report. A work sequence is provided showing which boring holes (BH1, BH2, etc.) each team will work on each week, while accounting for weekends and holidays.

Uploaded by

faizal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT : CADANGAN KERJA-KERJA PEMBANGUNAN G.R.I.

P KOTA PUTERI :- KERJA KERJA PENYIASATAN TANAH SEKSYEN 11 (LOT 201)

WORK PROGRAMME
1ST WEEK 2ND WEEK 3RD WEEK 4TH WEEK 5TH WEEK 6TH
25/3 26/3 27/3 28/3 29/3 30/3 31/3 1/4 2/4 3/4 4/4 5/4 6/4 7/4 8/4 9/4 10/4 11/4 12/4 13/4 14/4 15/4 16/4 17/4 18/4 19/4 20/4 21/4 22/4 23/4 24/4 25/4 26/4 27/4 28/4 29/4 30/4 1/5 2/5 3/5 4/5
MOBILIZATION :

1. Surveyor
2. Boring Team
- Team 1
Sunday (Off)

Sunday (Off)

Sunday (Off)

Sunday (Off)

Sunday (Off)

Sunday (Off)
Nuzul Quran
- Team 2

Hari Raya

Hari Raya
FIELDWORKS :

1. Surveyor
2. Boring Team
- Team 1
- Team 2

LAB TESTING

REPORT

SUBMISSION
Works Squence : Team A BH 1 BH9 BH2 BH10 BH5 BH6 BH12
Team B BH7 BH3 BH3 BH11 BH8

PROJECT : CADANGAN KERJA-KERJA PEMBANGUNAN G.R.I.P KOTA PUTERI :- KERJA KERJA PENYIASATAN TANAH SEKSYEN 12 (LOT 2892)

WORK PROGRAMME
1ST WEEK 2ND WEEK 3RD WEEK 4TH WEEK 5TH WEEK 6TH
25/3 26/3 27/3 28/3 29/3 30/3 31/3 1/4 2/4 3/4 4/4 5/4 6/4 7/4 8/4 9/4 10/4 11/4 12/4 13/4 14/4 15/4 16/4 17/4 18/4 19/4 20/4 21/4 22/4 23/4 24/4 25/4 26/4 27/4 28/4 29/4 30/4 1/5 2/5 3/5 4/5
MOBILIZATION :

1. Surveyor
2. Boring Team
- Team 1
Sunday (Off)

Sunday (Off)

Sunday (Off)

Sunday (Off)

Sunday (Off)

Sunday (Off)
- Team 2
Nuzul Quran

Hari Raya

Hari Raya
FIELDWORKS :

1. Surveyor
2. Boring Team
- Team 1
- Team 2

LAB TESTING

REPORT

SUBMISSION
Works Squence : Team A BH6 BH2 BH1 BH10 BH11
Team B BH8 BH9 BH7 BH3 BH4 BH5