Service Report: Rate Me

1. CIMB Bank technicians performed an installation and commissioning service at the CIMB Bank Akademi Nazir Razak building. 2. The technicians updated the building's Battery Monitoring System and Hawkeye DCMS version 2.0 to integrate new equipment, including four UPS units and six CRAC units. 3. Over 992 monitoring points across four UPS units were successfully added to the BMS. An alarm on one 80kVA UPS was found to be a true alarm. 4. The technicians completed graphic and data configuration updates in the Hawkeye 2.0 system to support the new equipment. Testing and handover to the client was planned for February 21.

Uploaded by

Isaac azhar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views2 pages

Service Report: Rate Me

1. CIMB Bank technicians performed an installation and commissioning service at the CIMB Bank Akademi Nazir Razak building. 2. The technicians updated the building's Battery Monitoring System and Hawkeye DCMS version 2.0 to integrate new equipment, including four UPS units and six CRAC units. 3. Over 992 monitoring points across four UPS units were successfully added to the BMS. An alarm on one 80kVA UPS was found to be a true alarm. 4. The technicians completed graphic and data configuration updates in the Hawkeye 2.0 system to support the new equipment. Testing and handover to the client was planned for February 21.

Uploaded by

Isaac azhar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

SERVICE REPORT

(Doc. No. PWS-TSD-PSR-001-00)

Company Name : CIMB BANK BERHAD (AKADEMI NAZIR Seq. Number : SR02021
RAZAK BLOCK G) Type of Service : Installation & Commisioning
Customer Address : Lot 60, Jln Ayer Hitam, Kawasan Institusi Type of Charges : Chargeable
Bangi, 43000 Bandar Baru Bangi, Selangor,
Malaysia Time In : 20-02-2023 22:00:00
Time Out : 21-02-2023 4:45:00
Completed By : ALIFF AIZAZ AZHAR, MOHD FARID BIN
BAMBANG PURNOMO, Wong Xian Qi
Completed By (Others) : -

Nature Fault / Reported : Hawkeye DCMS version 2.0 migration with new equipment integration. Ups, crac & BMS
Problem
Action Performed / : Update CIMB Bangi

Implemented Battery Monitoring System

1. BMS Graphic for Hawkeye 2.0 below done binding

• BMS Bank 1&2 UPS 1B-80 kVA =248 points = Successful Online

• BMS Bank 1&2 UPS 2B-80 kVA =248 points= Successful Online

• BMS Bank 1&2 UPS 1A-200 kVA =248 points= Successful Online

• BMS Bank 1&2 UPS 2A-200 kVA=248 points= Successful Online

Total= 992 Points

2. Alarm on BMS UPS 1B -80 kva is true Alarm. We already alert SELESA to look into this alert & they confirm the Unit got alarm
.

Hawkeye version 2.0

1. OLD database data is working find on hawkeye 2.0.

2. Graphic & DATA is pooling on old database on hawkeye 2.0.

3. Asset threshold rectification a 100% done.

4. Graphic condition rectification 100% done.

5. Print screen graphic for Hawkeye Version 2.0 – 100%

6. All 4 units UPS reillo Hi-Level are online & in good condition.

7. All 6 units CRAC vertiv Hi level is online & in good condition.

8. All 4 unit of BMS Hilevel is online & in good condition.

9. Tomorrow SELESA will bring the SMS GSM Gateway & we will configure the alarm for testing Hawkeye 2.0

10. Most probably on 21 FEB 2023 we will T&C & handover to SELESA

Remarks : Most probably on 21 FEB 2023 we will T&C & handover to SELESA
Checklist (if available) : -

Rate Me

This is to certify that the system(s) has/have today been routine inspected and/or serviced and is working and to our/my satisfaction

Authorised Customer

Wed 22 Feb 2023 1:00 AM

Nelson
Customer Comment (Opt.) : -

/