Altaaqa Hungary Master Timeline Draft

This document outlines the tasks and timeline for completing due diligence requirements for a loan agreement from March 2019 to May 2020. Key steps include: 1. Completing buyer-side due diligence by April 18th, including signing a letter of engagement, preparing due diligence documents, and completing the buyer-side due diligence. 2. Preparing a tax memo by April 25th, including drafting the memo and completing it. 3. Fulfilling conditions precedent to signing the loan agreement by May 31st, including closing an acquisition, preparing sale-purchase agreements, conducting an energy audit, and completing legal and technical due diligence.

Uploaded by

nagymate
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views10 pages

Altaaqa Hungary Master Timeline Draft

This document outlines the tasks and timeline for completing due diligence requirements for a loan agreement from March 2019 to May 2020. Key steps include: 1. Completing buyer-side due diligence by April 18th, including signing a letter of engagement, preparing due diligence documents, and completing the buyer-side due diligence. 2. Preparing a tax memo by April 25th, including drafting the memo and completing it. 3. Fulfilling conditions precedent to signing the loan agreement by May 31st, including closing an acquisition, preparing sale-purchase agreements, conducting an energy audit, and completing legal and technical due diligence.

Uploaded by

nagymate
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019

Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
1

2 1 Completion of Buyer side DD 4 days Mon Thu 18/04/19


15/04/19

3 1.1 Signing Letter of Engagement 0 days Mon 15/04/19Mon 15/04/19 Signing Letter of Engagement

4 1.2 Preparation of Due Diligence 4 days Mon Thu 18/04/19 Deloitte - Legal
15/04/19

5 1.3 Buyer side DD completed 0 days Thu 18/04/19 Thu 18/04/19 Buyer side DD completed

6 2 Tax memo 7 days Mon Thu 25/04/19


15/04/19

7 2.1 Preparation of Tax Memo 7 days Mon Thu 25/04/19 Deloitte - Tax
15/04/19

8 2.2 Tax memo completed 0 days Thu 25/04/19 Thu 25/04/19 Tax memo completed

9 3 Conditions precedent to signing 52 days Mon Fri 31/05/19


the loan agreement 18/03/19

10 3.1 Closing of the acquisition with 30 days Tue 19/03/19 Thu 02/05/19
Electraplan

11 3.1.1 Sub division of Project Real 30 days Tue 19/03/19 Thu 02/05/19
Estate

12 3.1.1.1 Division of Csabrendek 30 days? Tue 19/03/19 Thu 02/05/19 Electraplan


property

13 3.1.2 Preparation of Preliminary 10 days Mon Tue 30/04/19


Sale-Purchase agreement for 15/04/19
real estate

14 3.1.2.1 Finalisation of Preliminary 10 days Mon Tue 30/04/19 Deloitte - Legal,Altaaqa


Sale-Purchase agreement 15/04/19

15 3.1.2.2 Preliminary Sale-Purchase 0 days Tue 30/04/19 Tue 30/04/19 Preliminary Sale-Purchase Agreement signed
Agreement signed

16 3.1.3 Preparation of Quota 10 days Mon Tue 30/04/19


Sale-Purchase Agreement 15/04/19

17 3.1.3.1 Finalisation of Quota 10 days Mon Tue 30/04/19 Altaaqa,Deloitte - Legal


Sale-Purchase Agreement 15/04/19

18 3.1.3.2 Quota Sale-Purchase 0 days Tue 30/04/19 Tue 30/04/19 Quota Sale-Purchase agreement is signed
agreement is signed

19 3.2 Other key steps 30 days Mon 18/03/19Tue 30/04/19


20 3.2.1 Bridge loan - PENDING 30 days Mon 18/03/19Tue 30/04/19 Electraplan,Greencells

21 3.2.2 Finalising technical details of 11 days Wed Fri 26/04/19 Electraplan,Greencells,Altaaqa


the project - timing subject to 10/04/19
Deloitte's technical scope
agreement

22 3.2.3 Technical details of the 0 days Fri 26/04/19 Fri 26/04/19 Technical details of the project finalised
project finalised

23 3.3 Lender's Energy audit and 43 days Thu 28/03/19 Thu 30/05/19
technical due diligence report

24 3.3.1 Site visit 1 day Thu 28/03/19 Thu 28/03/19 MVM Erbe

25 3.3.2 Data request for TDD 2 days Thu 28/03/19 Fri 29/03/19 Electraplan

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
26 3.3.3 Zero report preparation 5 days Mon 29/04/19Mon 06/05/19 MVM Erbe

27 3.3.4 Zero report hand over 0 days Mon 06/05/19Mon 06/05/19 Zero report hand over

28 3.3.5 Technical Due Diligence process15 days Mon 29/04/19Mon 20/05/19 MVM Erbe

29 3.3.6 Discussion of TDD results 5 days Tue 21/05/19 Mon 27/05/19 MVM Erbe

30 3.3.7 Update of TDD based on 3 days Tue 28/05/19 Thu 30/05/19 MVM Erbe
discussion

31 3.3.8 Lender's TDD completed 0 days Thu 30/05/19 Thu 30/05/19 Lender's TDD completed

32 3.4 Lender's Legal DD 49 days Thu 21/03/19 Fri 31/05/19


33 3.4.1 Data request for LDD 5 days Thu 21/03/19 Wed 27/03/19 Electraplan

34 3.4.2 Partial Legal DD 15 days Thu 28/03/19 Wed 17/04/19 Kinstellar

35 3.4.3 Remaining data requests 10 days Tue 23/04/19 Tue 07/05/19


handled - contracts

36 3.4.4 Finalisation of Legal DD 10 days Wed 08/05/19Tue 21/05/19


37 3.4.5 Discussion of LDD results 5 days Wed 22/05/19Tue 28/05/19 Kinstellar

38 3.4.6 Updatte LDD based on 3 days Wed Fri 31/05/19 Kinstellar


discussions 29/05/19

39 3.4.7 Lender's LDD completed 0 days Fri 31/05/19 Fri 31/05/19 Lender's LDD completed

40 3.5 Financial model preparation 36 days Tue 19/03/19 Fri 10/05/19


41 3.5.1 Scope negotiation with banks 1 day Tue 19/03/19 Tue 19/03/19 Deloitte - Financial

42 3.5.2 Scope negotation with 1 day Mon Mon Deloitte - Financial


Altaaqa 25/03/19 25/03/19

43 3.5.3 Data collection 1 day Tue 26/03/19 Tue 26/03/19 Deloitte - Financial

44 3.5.4 Discussions with client/target 1 day Wed Wed Deloitte - Financial


management 27/03/19 27/03/19

45 3.5.5 Construction of the financial 15 days Thu 28/03/19 Wed Deloitte - Financial
model 17/04/19

46 3.5.6 Presenting draft financial model5 days Mon 29/04/19Mon 06/05/19


47 3.5.7 Validation of modelling results 2 days Tue 07/05/19 Wed Deloitte - Financial
08/05/19

48 3.5.8 Finalising financial model with 2 days Thu 09/05/19 Fri 10/05/19 Deloitte - Financial
the Altaaqa

49 3.5.9 Delivery of the financial 0 days Fri 10/05/19 Fri 10/05/19 Delivery of the financial model
model

50 4 Bank internal credit proposal 15 days Mon 03/06/19Mon 24/06/19


51 4.1 Submitting of internal credit 5 days Mon Fri 07/06/19 Lenders
proposal 03/06/19

52 4.2 Corporate Credit Committee 5 days Tue 11/06/19 Mon Lenders


decisions in Budapest 17/06/19

53 4.3 Vienna/Brussels HQ Credit 5 days Tue 18/06/19 Mon Lenders


Committee decisions 24/06/19

54 4.4 Facility agreement is signed 0 days Mon 24/06/19Mon 24/06/19 Facility agreement is signed

55 5 Conditions precedent to 1st 69 days Mon Wed


disbursement 15/04/19 24/07/19

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 2
ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
56 5.1 Preparation of draft EPC 25 days Mon Wed
contract 15/04/19 22/05/19

57 5.1.1 Examining draft EPC and 5 days Mon Tue 23/04/19 Altaaqa,Deloitte - Legal,Greencells
discussion of findings with 15/04/19
Altaaqa

58 5.1.2 Localisation of EPC contract 20 days Wed Wed Deloitte - Legal


24/04/19 22/05/19

59 5.1.3 Draft EPC contract prepard 0 days Thu 23/05/19 Thu 23/05/19 Draft EPC contract prepard

60 5.1.4 Signing PV plant EPC contract 0 days Tue 25/06/19 Tue 25/06/19 25/06

61 5.2 Preparation of draft O&M 25 days Mon Wed


Contract 15/04/19 22/05/19

62 5.2.1 Examining draft O&M and 5 days Mon Tue 23/04/19 Altaaqa,Deloitte - Legal,Greencells
discussion of findings with 15/04/19
Altaaqa

63 5.2.2 Localisation of O&M contract 20 days Wed Wed Deloitte - Legal


24/04/19 22/05/19

64 5.2.3 Draft O&M contract prepared 0 days Wed Wed Draft O&M contract prepared
22/05/19 22/05/19

65 5.2.4 Signing PV plant O&M contract0 days Tue 25/06/19 Tue 25/06/19 25/06

66 5.3 Substation EPC signed 0 days Mon 24/06/19Mon 24/06/19 Substation EPC signed

67 5.4 Closing of QSPA 0 days Mon 24/06/19Mon 24/06/19 Closing of QSPA

68 5.5 Sub-station construction 0 days Mon Mon Sub-station construction contract secured and grid access is secured
contract secured and grid access 24/06/19 24/06/19
is secured
69 5.6 Positive insurance advisory 5 days Tue 25/06/19 Mon Marsh
report - NO INFO 01/07/19

70 5.7 Registration of reclassification 15 days Tue 25/06/19 Mon Electraplan


and ownership 15/07/19

71 5.8 MEKH approval of acquisition 22 days Tue 25/06/19 Wed


24/07/19

72 5.8.1 Preparation and submission of 7 days Tue 25/06/19 Wed Deloitte - Legal
request for MEKH approval 03/07/19

73 5.8.2 MEKH evaluates approval request


15 days Thu 04/07/19 Wed 24/07/19 MEKH

74 5.8.3 MEKH approval received 0 days Wed Wed MEKH approval received
24/07/19 24/07/19

75 5.9 All Project Documents are 0 days Wed Wed All Project Documents are available in form and content acceptable to the Banks
available in form and content 24/07/19 24/07/19
acceptable to the Banks

76 5.10 1st disbursement - financial close0 days Wed 24/07/19Wed 24/07/19 1st disbursement - financial close

77 6 Construction phases 173 daysMon 19/08/19Wed 29/04/20


78 6.1 Delivery Schedule - Longlead
items (arrival on site)

79 6.2 Delivery Schedule - Longlead 37 Sun 08/12/19 Mon


items (arrival on site) days? 03/02/20

80 6.2.1 Pole Delivery 6 days Mon 30/09/19Sat 05/10/19


81 6.2.2 Mounting Structure 20 days Fri 04/10/19 Mon 04/11/19
82 6.2.3 Modules 14 days Mon 14/10/19Mon 04/11/19
83 6.2.4 Inverter Station 1 day Mon 04/11/19Mon 04/11/19

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 3
ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
84 6.2.5 Combiner Box 2 days Mon 04/11/19Tue 05/11/19
85 6.2.6 HV Subst-Long Lead Delivery 51 days Tue 10/12/19 Tue 25/02/20
Equip (arrival on site)

86 6.2.6.1 Power transformer 1 day Tue 25/02/20 Tue 25/02/20


87 6.2.6.2 Instrumental transformers 1 day Tue 25/02/20 Tue 25/02/20
current and voltage

88 6.2.6.3 Circle breakers (SF6 110 - 1 day Fri 31/01/20 Fri 31/01/20
400kV)

89 6.2.6.4 Disconnectors 1 day Tue 10/12/19 Tue 10/12/19


90 6.2.6.5 MV switchgears 1 day Fri 10/01/20 Fri 10/01/20
91 6.3 Enabling Construction Phase 14 days? Mon 18/11/19Thu 05/12/19
92 6.3.1 PV Area 30 days Mon 19/08/19Tue 01/10/19
93 6.3.1.1 Topographical survey 5 days Mon 19/08/19Mon 26/08/19
94 6.3.1.2 Geotechnical analysis 5 days Mon 19/08/19Mon 26/08/19
95 6.3.1.3 Structural calculations 25 days Fri 23/08/19 Thu 26/09/19
(including contractor site
soil testing)

96 6.3.1.4 Commencement of works Tue 01/10/19


97 6.3.1.5 Access roads (layby) 10 days Mon 16/09/19Fri 27/09/19
98 6.3.1.6 Site Set Up 5 days Mon 23/09/19Fri 27/09/19
99 6.3.1.7 Fence 20 days Mon 02/09/19Fri 27/09/19
100 6.3.1.8 Site Preparation (temporary)5 days Mon 23/09/19Fri 27/09/19
101 6.3.1.9 Internal Roads 5 days Mon 23/09/19Fri 27/09/19
102 6.3.2 HV Substation 30 days Mon 19/08/19Tue 01/10/19
103 6.3.2.1 Topographical survey 5 days Mon 19/08/19Mon 26/08/19
104 6.3.2.2 Geotechnical analysis 5 days Mon 19/08/19Mon 26/08/19
105 6.3.2.3 Fondation calculations 25 days Fri 23/08/19 Thu 26/09/19
(including contractor site
soil testing)

106 6.3.2.4 Commencement of works Tue 01/10/19


107 6.3.2.5 Access roads (layby) 10 days Mon 16/09/19Fri 27/09/19
108 6.3.2.6 Site Set Up 5 days Mon 23/09/19Fri 27/09/19
109 6.3.2.7 Fence 20 days Mon 02/09/19Fri 27/09/19
110 6.3.2.8 Site Preparation (temporary)5 days Mon 23/09/19Fri 27/09/19
111 6.3.2.9 Internal Roads 5 days Mon 23/09/19Fri 27/09/19
112 6.3.3 Auxiliary Line 5 days Mon 16/09/19Fri 20/09/19
113 6.3.3.1 Topographical survey 5 days Mon 16/09/19Fri 20/09/19
114 6.3.3.2 Geotechnical analysis 5 days Mon 16/09/19Fri 20/09/19
115 6.4
116 6.5 Main Construction Phase 140 daysTue 01/10/19 Fri 24/04/20
117 6.5.1 PV Area 142 daysTue 01/10/19 Tue 28/04/20
118 6.5.1.1 Civil Works 25 days Tue 01/10/19 Wed 06/11/19
119 6.5.1.2 Ramming of piles 20 days Fri 08/11/19 Thu 05/12/19
120 6.5.1.3 Building of understructure 50 days Mon 25/11/19Fri 07/02/20

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 4
ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
121 6.5.1.4 Module Installation 35 days Mon 09/12/19Fri 31/01/20
122 6.5.1.5 Trenching works 35 days Mon 02/12/19Fri 24/01/20
123 6.5.1.6 Laying of string cables on tables
30 days Mon 02/12/19Fri 17/01/20
124 6.5.1.7 Laying of DC& MV cables 20 days Sun 15/12/19 Thu 16/01/20
125 6.5.1.8 Installation of Inverters 10 days Mon 16/12/19Fri 03/01/20
126 6.5.1.9 Connection of inverters 15 days Tue 14/01/20 Mon 03/02/20
127 6.5.1.10 Testing of DC cables 10 days Tue 14/01/20 Mon 27/01/20
128 6.5.1.11 Instalation of String 10 days Tue 14/01/20 Mon
Combiner Boxes 27/01/20

129 6.5.1.12 Connection of String 10 days Mon Fri 31/01/20


Combiner Boxes 20/01/20

130 6.5.1.13 Stationes DC connection 10 days Thu 30/01/20 Wed 12/02/20


131 6.5.1.14 Stationes MV connection 10 days Thu 30/01/20 Wed 12/02/20
132 6.5.1.15 Testing of Solar Strings 10 days Thu 30/01/20 Wed 12/02/20
133 6.5.1.16 Testing of DC cables 10 days Thu 30/01/20 Wed 12/02/20
134 6.5.1.17 Monitoring Installation 14 days Mon 03/02/20Thu 20/02/20
135 6.5.1.18 Grid Connection 5 days Mon 24/02/20Fri 28/02/20
136 6.5.1.19 Comisioning& Testing 20 days Mon 02/03/20Fri 27/03/20
137 6.5.1.20 COD 1 day Tue 28/04/20 Tue 28/04/20
138 6.6 HV Subst + Main Transformer 143 daysTue 01/10/19 Wed 29/04/20
139 6.6.1 Civil Works Land (including 25 days Tue 01/10/19 Wed
cables trenches) 06/11/19

140 6.6.2 Fondation work/structure 40 days Mon 04/11/19Fri 03/01/20


141 6.6.3 Equip Instalation (HV St + transf)
60 days Thu 09/01/20 Wed 01/04/20
142 6.6.4 Electrical Instalation (Grid 35 days Mon Fri 10/04/20
conection) 24/02/20

143 6.6.5 Comissioning and Testing 5 days Mon 13/04/20Fri 17/04/20


144 6.6.6 COD Wed 29/04/20
145 6.7 Auxiliary Line 134 daysMon 14/10/19Wed 29/04/20
146 6.7.1 Civil Works 50 days Mon 14/10/19Mon 30/12/19
147 6.7.2 Trenching works 50 days Tue 22/10/19 Wed 08/01/20
148 6.7.3 Laying of cables 21 days Sat 28/12/19 Mon 27/01/20
149 6.7.4 Testing 20 days Sat 01/02/20 Thu 27/02/20
150 6.7.5 Grid Connection 10 days Sun 01/03/20 Thu 12/03/20
151 6.7.6 Comision & Testing 21 days Sat 14/03/20 Fri 10/04/20
152 6.7.7 COD 1 day Wed 15/04/20Wed 15/04/20
153 6.7.8 Power plant (full scope) 41 days Mon 02/03/20Wed 29/04/20
154 6.7.8.1 Comision& Testing 40 days Mon 02/03/20Tue 28/04/20
155 6.7.8.2 COD Wed 29/04/20

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 5
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 6
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 7
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 8
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 9
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 10