Altaaqa Hungary Master Timeline Draft
Altaaqa Hungary Master Timeline Draft
Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
1
3 1.1 Signing Letter of Engagement 0 days Mon 15/04/19Mon 15/04/19 Signing Letter of Engagement
4 1.2 Preparation of Due Diligence 4 days Mon Thu 18/04/19 Deloitte - Legal
15/04/19
5 1.3 Buyer side DD completed 0 days Thu 18/04/19 Thu 18/04/19 Buyer side DD completed
7 2.1 Preparation of Tax Memo 7 days Mon Thu 25/04/19 Deloitte - Tax
15/04/19
8 2.2 Tax memo completed 0 days Thu 25/04/19 Thu 25/04/19 Tax memo completed
10 3.1 Closing of the acquisition with 30 days Tue 19/03/19 Thu 02/05/19
Electraplan
11 3.1.1 Sub division of Project Real 30 days Tue 19/03/19 Thu 02/05/19
Estate
15 3.1.2.2 Preliminary Sale-Purchase 0 days Tue 30/04/19 Tue 30/04/19 Preliminary Sale-Purchase Agreement signed
Agreement signed
18 3.1.3.2 Quota Sale-Purchase 0 days Tue 30/04/19 Tue 30/04/19 Quota Sale-Purchase agreement is signed
agreement is signed
22 3.2.3 Technical details of the 0 days Fri 26/04/19 Fri 26/04/19 Technical details of the project finalised
project finalised
23 3.3 Lender's Energy audit and 43 days Thu 28/03/19 Thu 30/05/19
technical due diligence report
24 3.3.1 Site visit 1 day Thu 28/03/19 Thu 28/03/19 MVM Erbe
25 3.3.2 Data request for TDD 2 days Thu 28/03/19 Fri 29/03/19 Electraplan
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 1
ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
26 3.3.3 Zero report preparation 5 days Mon 29/04/19Mon 06/05/19 MVM Erbe
27 3.3.4 Zero report hand over 0 days Mon 06/05/19Mon 06/05/19 Zero report hand over
28 3.3.5 Technical Due Diligence process15 days Mon 29/04/19Mon 20/05/19 MVM Erbe
29 3.3.6 Discussion of TDD results 5 days Tue 21/05/19 Mon 27/05/19 MVM Erbe
30 3.3.7 Update of TDD based on 3 days Tue 28/05/19 Thu 30/05/19 MVM Erbe
discussion
31 3.3.8 Lender's TDD completed 0 days Thu 30/05/19 Thu 30/05/19 Lender's TDD completed
39 3.4.7 Lender's LDD completed 0 days Fri 31/05/19 Fri 31/05/19 Lender's LDD completed
43 3.5.3 Data collection 1 day Tue 26/03/19 Tue 26/03/19 Deloitte - Financial
45 3.5.5 Construction of the financial 15 days Thu 28/03/19 Wed Deloitte - Financial
model 17/04/19
48 3.5.8 Finalising financial model with 2 days Thu 09/05/19 Fri 10/05/19 Deloitte - Financial
the Altaaqa
49 3.5.9 Delivery of the financial 0 days Fri 10/05/19 Fri 10/05/19 Delivery of the financial model
model
54 4.4 Facility agreement is signed 0 days Mon 24/06/19Mon 24/06/19 Facility agreement is signed
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 2
ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
56 5.1 Preparation of draft EPC 25 days Mon Wed
contract 15/04/19 22/05/19
57 5.1.1 Examining draft EPC and 5 days Mon Tue 23/04/19 Altaaqa,Deloitte - Legal,Greencells
discussion of findings with 15/04/19
Altaaqa
59 5.1.3 Draft EPC contract prepard 0 days Thu 23/05/19 Thu 23/05/19 Draft EPC contract prepard
60 5.1.4 Signing PV plant EPC contract 0 days Tue 25/06/19 Tue 25/06/19 25/06
62 5.2.1 Examining draft O&M and 5 days Mon Tue 23/04/19 Altaaqa,Deloitte - Legal,Greencells
discussion of findings with 15/04/19
Altaaqa
64 5.2.3 Draft O&M contract prepared 0 days Wed Wed Draft O&M contract prepared
22/05/19 22/05/19
65 5.2.4 Signing PV plant O&M contract0 days Tue 25/06/19 Tue 25/06/19 25/06
66 5.3 Substation EPC signed 0 days Mon 24/06/19Mon 24/06/19 Substation EPC signed
68 5.5 Sub-station construction 0 days Mon Mon Sub-station construction contract secured and grid access is secured
contract secured and grid access 24/06/19 24/06/19
is secured
69 5.6 Positive insurance advisory 5 days Tue 25/06/19 Mon Marsh
report - NO INFO 01/07/19
72 5.8.1 Preparation and submission of 7 days Tue 25/06/19 Wed Deloitte - Legal
request for MEKH approval 03/07/19
74 5.8.3 MEKH approval received 0 days Wed Wed MEKH approval received
24/07/19 24/07/19
75 5.9 All Project Documents are 0 days Wed Wed All Project Documents are available in form and content acceptable to the Banks
available in form and content 24/07/19 24/07/19
acceptable to the Banks
76 5.10 1st disbursement - financial close0 days Wed 24/07/19Wed 24/07/19 1st disbursement - financial close
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 3
ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
84 6.2.5 Combiner Box 2 days Mon 04/11/19Tue 05/11/19
85 6.2.6 HV Subst-Long Lead Delivery 51 days Tue 10/12/19 Tue 25/02/20
Equip (arrival on site)
88 6.2.6.3 Circle breakers (SF6 110 - 1 day Fri 31/01/20 Fri 31/01/20
400kV)
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 4
ID WBS Task Task Name Duration Start Finish March 2019 April 2019 May 2019 June 2019 July 2019 August 2019 September 2019 October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020
Mode 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 03 08 13 18 23 28 02 07 12 17 22 27 02
121 6.5.1.4 Module Installation 35 days Mon 09/12/19Fri 31/01/20
122 6.5.1.5 Trenching works 35 days Mon 02/12/19Fri 24/01/20
123 6.5.1.6 Laying of string cables on tables
30 days Mon 02/12/19Fri 17/01/20
124 6.5.1.7 Laying of DC& MV cables 20 days Sun 15/12/19 Thu 16/01/20
125 6.5.1.8 Installation of Inverters 10 days Mon 16/12/19Fri 03/01/20
126 6.5.1.9 Connection of inverters 15 days Tue 14/01/20 Mon 03/02/20
127 6.5.1.10 Testing of DC cables 10 days Tue 14/01/20 Mon 27/01/20
128 6.5.1.11 Instalation of String 10 days Tue 14/01/20 Mon
Combiner Boxes 27/01/20
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 5
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 6
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 7
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 8
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 9
May 2020 June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021 June 2021 July 2021 August 2021 September 2021 October 2021 November 2021 December 2021
02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 01 06 11 16 21 26 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26 01 06 11 16 21 26 31 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13 18 23 28
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Altaaqa Hungary Maste
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Tue 16/04/19
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 10