Geotechnical Works: Class G

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
146 views35 pages

Geotechnical Works: Class G

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 35

MyCESMM2

Class G – Geotechnical Work

CLASS G
GEOTECHNICAL WORKS

[email protected] G1
MyCESMM2
Class G – Geotechnical Work

Measurement covered under other classes


❑ Excavation, filling and turfing for retaining structures (included in Class F:
Earthworks).
❑ Reinforced concrete foundation for retaining structures (included in Class I:
Concrete work)
❑ Sand replacement for ground treatment (included in Class F: Earthworks)
❑ Sub-soil drainage (included in Class Q: Drainage work)
❑ Pile embankment measured under respective classes (included in Class F:
Earthworks, Class I: Concrete work, Class H: Piling work)

[email protected]
G2
MyCESMM2
D1 Class G – Geotechnical Work
Earth shall be deemed to be materials A1
other than topsoil, natural hard Item description shall state the location
material, rock, artificial hard material or of the item if the work is more than 6 m
unsuitable material, unless otherwise above or below the road level.
stated in the item description.

D2 Excavate & Replace


Natural hard material shall be materials
other than rock and artificial hard
material, and requires other specialised
equipment.

D3
Rock and artificial hard material shall
be materials that require the use of
either hydraulic rock breaker or
pneumatic tools or explosives.

C1
Items for pull out test shall be deemed
to include all necessary equipment,
and submission of test procedure,
records and reports.

Pull out test


[email protected] G3
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
1. Plant and 1. Provision sum
equipment 2. Moving and sum
handling
3. Temporary staging sum

C2
Items for provision shall be deemed to
include provision of all necessary plant
and equipment, transportation to the
site, handling, assembling, and removal
off the site after completion of
operation.

C3
Items for moving and handling shall be
deemed to include the moving and
handling of all necessary plant and
equipment within the site and from
location to location as often as it is,
Ground anchorage drilling machine
whenever necessary for the execution
of the whole operation.

[email protected] G4
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description

G110 Provision of all necessary plant and equipment, transportation to the Sum
site, handling, assembling, and removal off the site after completion
of operation.

G120 Moving and handling all necessary plant and equipment within the sum
site and from location to location as often as is and whenever
necessary for the execution of whole operation.

G130 Temporary staging [on slope]. sum

Temporary staging

[email protected] G5
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
2. Retaining 1. Gabion 1. Rock-filled gabion m3
structures 2. Rock-filled gabion m2
mattress
3. Filter layer/separator m2

2. Cribwall 1. Single cell m2


2. Double cell m2
3. Triple cell m2
4. Quadruple cell m2
5. Filter layer/separator m2

Cribwall (single cell)


[email protected]
Rock filled gabion G6
MyCESMM2
Class G – Geotechnical Work
D4
Gabions filled with rocks exceeding 300 M2
mm high shall be classed as rock-filled The area of multiple cells cribwall shall
gabion, and those not exceeding 300 be the sloping area of the highest cells
mm high as rock-filled gabion mattress. from the commencing surface.
Filling shall be deemed to be imported,
unless otherwise stated. C4
Item for cribwall shall be deemed to
A2 include precast reinforced concrete
Item description for gabion shall state components and granular infill
the type and size of filling, and the type, materials.
gauge, and protective coatings of the
wire mesh. If laying underwater is A4
required, it shall be so stated.
Item description for cribwall shall state
the concrete grade, length of precast
A3 concrete header, combination and
Item description for rock-filled gabion type of granular infill.
mattress shall state the thickness.

M1
The area of single cell cribwall shall be
the sloping area from the commencing
surface

Gabion mattress
[email protected] G7
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description

G211.1 [1.0 m x 1.0 m x 1.0 m] rock-filled gabion with PVC-coated wire m3


gauge size of [2.7 mm] as per Specification clause (….) and as
shown in the drawings.

G212 Rock-filled gabion mattress, [300 mm] thick with PVC-coated wire m2
gauge size of [2.7 mm] as per Specification clause (….) and as
shown in Drawing No. (....).

G213 Filter layer / separator as per Specification clause (….). m2

G221 Single cell with [1200 mm] header as shown in Drawing No. (….). m2

G223 Triple cell with [1650 mm + 1650 mm + 1200 mm] header as shown in m2
Drawing No. (…….).

G225 Filter layer / separator as per Specification clause (….). m2

[email protected] G8
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
2. Retaining 3. Reinforced soil 1. Reinforced earth filling m3
structures slope 2. Reinforced granular m3
filling
3. Erosion protection mats m2

4. Reinforced soil wall 1. Wall facing m2


2. Reinforced earth filling m3
3. Reinforced granular m3
filling
4. Pull out test nr

M3
Reinforced earth filling and
reinforced granular filling shall be
measured nett volume within the
reinforced zone.

D5
Reinforced earth filling and
reinforced granular filling is defined
as filling within the reinforced zone.
Reinforced soil slope

[email protected] G9
MyCESMM2
D6 Class G – Geotechnical Work
Reinforced earth filling and reinforced
granular filling shall be in accordance
with BS 8006-1:2010+ A1:2016.

A5
Item description for reinforced soil slope
shall state the location, type and
strength of material used.
Reinforced soil slope
M4
The area of erosion protection mat shall
be the nett area to the slope with no
allowance for laps and anchorage.

A6
Item description for erosion protection Erosion protection mat
mats shall state the type of material
and strength, where applicable.

M5
The area of reinforced soil wall is
measured from the commencing
surface.

[email protected] Reinforced soil wall G10


MyCESMM2
Class G – Geotechnical Work
M6
Sub-soil drainage shall be measured
under Class Q.

D7
Precast concrete panel shall be classed
as wall facing in retaining structure.

C5
Item for wall facing shall be deemed to
include soil reinforcement and
galvanising where applicable,
connections and/or jointing, geotextile
and accessories for wall joints.

A7
Item description for wall facing shall
state the type, size, and shape, where
applicable; and the concrete grade,
type of soil reinforcement and wall
height.

Wall facing
[email protected] G11
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description

G231 Reinforced earth filling as per Specification clause (….) and as shown m3
in Drawing No. (….).

G232 Reinforced granular filling as per Specification clause (….) and as m3


shown in Drawing No. (….).

G233 [HDPE] erosion protection mats with minimum tensile strength of [1.4 m2
kN/m] as per Specification clause (….).

G241.1 Not exceeding 6 m. m2

G242 Reinforced earth filling as per Specification clause (….). m3

G243 Reinforced granular filling as per Specification clause (….). m3

G244 Pull out test, including all necessary equipment and submission of nr
procedure, records, and report.

[email protected] G12
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
3. Slope stabilisation 1. Soil nailing 1. Stated length nr
2. Pull-out test nr

2. Rock bolt 1. Stated length nr


2. Pull-out test nr

3. Ground anchor 1. Earth m


2. Natural hard material m
3. Rock m
4. Pull-out test nr

4. Concrete buttress m2

5. Horizontal drain 1. Earth m


2. Natural hard material m
3. Rock m
4. Artificial hard material m
5. Unsuitable materials m

[email protected] G13
MyCESMM2
C6 Class G – Geotechnical Work
Items for soil nailing shall be deemed to
include drilling of borehole, corrugated
HDPE pipe if applicable, sleeve
grouting, sealant compound, Soil nailing
galvanised steel bearing plate and all
associated works.

A8
Item description for soil nailing shall
state the diameter of the borehole and
reinforcement bar, concrete grade
and the size of concrete pad.
Guniting
C7 /Shotcreting
Items for rock bolt shall be deemed to
include drilling of borehole,
reinforcement bar, reinforced concrete
pad, sleeve grouting, sealant
compound and all associated works.

A9
Item description for rock bolt shall state
the diameter of the borehole and
reinforcement bar, concrete grade
and the size of concrete pad
[email protected] G14
MyCESMM2
C8 Class G – Geotechnical Work
Items for ground anchor shall be
deemed to include prestressed
tendons, drilling, and grouting,
concreting and all associated works. Tensioning
ground
A10 anchor
Item description for ground anchor shall
state the size and type of anchor
tendons and grouting.

[email protected] G15
MyCESMM2
C9 Class G – Geotechnical Work
Items for concrete buttress shall be
deemed to include steel wire mesh,
PVC drain pipe, dowel bars, filter
materials and all associated works.

A11
Item description for concrete
buttress shall state the grade and
average thickness of the concrete.

M7
Concrete channel for horizontal
drain shall be measured under Class
R740.

C10
Item for horizontal drain shall be
deemed to include drilling,
perforated pipe and all associated
works.

A12
Item description for horizontal drain
shall state the type and diameter.

[email protected]
Horizontal drain G16
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description

G311.1 [100 mm dia.] soil nail with [T25] reinforcement bar as shown in nr
Drawing No. (....); [6 m] long.

G312.1 Pull out test on soil nail; to [1.5] times the working load of 50 kN. nr

G321.1 Type A with T32 bolt as shown in Drawing No. (….); [2 m] long. nr

G331 [Type 1] ground anchor as shown in Drawing No (….); Earth m

G340.1 [G25] concrete buttress with average thickness [not exceeding 300 m2
mm].

G351 [100 mm] diameter uPVC horizontal drain as shown in Drawing No. m
(….).

[email protected] G17
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
4. Surface protection 1. Guniting m2
2. Articulated slab m2
3. Rock netting m2
4. Stone pitching m2
5. Stone revetment m2

M8
The area of guniting and articulating slab shall
be their nett area to the slope.
Guniting

C11
Items for guniting shall be deemed to include
steel wire mesh, PVC drain pipe, dowel bar,
filter materials, and all necessary formwork.

A13
Item description for guniting shall state the
average thickness of the concrete and the
concrete grade.

[email protected] Articulated slab G18


MyCESMM2
C12 Class G – Geotechnical Work
Items for articulating slab shall be deemed to
include preparation of surface, blinding,
aggregate, geotextile and all necessary concrete
and formwork.

A14
Item description for articulating slab shall state the
thickness, type and jointing of the slab.
Rock netting
M9
The area of rock netting shall be measured nett
with no allowance made for laps.
Stone
C13 pitching
Items for rock netting shall be deemed to include
all necessary accessories.

A15
Item description for rock netting shall state the
type and gauge of chain mesh and anchoring
system.

A16
Item description for stone pitching and stone
revetment shall state the stone size and thickness.
[email protected] G19
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description

G410 [100 mm] thick [G25] guniting. m2

G420 [150 mm thick] concrete articulating slab as per Specification clause m2


(….) as per Drawing No. (....).

G430 Rock netting with PVC-coated wire gauge size of [2.7 mm] as per m2
Specification clause (….).

G440 [250 mm] thick stone pitching as per Specification clause (….). m2

G450 [250 mm] thick stone revetment as per Specification clause (….). m2

Mountainous road stretch


to Genting Highland
[email protected] G20
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
5. Ground treatment 1. Prefabricated m
vertical drains
2. Dynamic nr
compaction
3. Vibro compaction nr
4. Sand column m
5. Stone/Aggregate m
column
6. Soil-cement m
column

7. Geotextile m2
8. Geogrid m2

M10
Any filling required under this class to
be used as a working platform shall Reclamation filling
be measured under Class F3**.

[email protected] G21
MyCESMM2
M11 Class G – Geotechnical Work
Surcharge material (for pre-loading)
used with prefabricated vertical
drains shall be measured under
Class F3**. Vertical drain

A17
Item description for prefabricated
vertical drains shall state type and
cross-sectional dimensions of
drainage tube, wrapping material
and vacuum consolidation where
required. Type of soil shall be stated.

Dynamic
A18 compaction
Item description for dynamic
compaction shall state the weight
of the drop hammer, number of
drops and height of drop.

A19
Item description for vibro
compaction shall state the depth of
treatment required.

Vibro compaction
[email protected] G22
MyCESMM2
A20 Class G – Geotechnical Work
Item description for sand column,
stone/aggregate column and soil-
cement column shall state the
diameter of the columns and the
size of aggregate, where Geogrid
applicable.
Geotextile
A21
Item description for soil-cement
column shall state the grout mix
design.

M12 Stone column


The area of geogrid and geotextile
shall be measured nett with no
allowance for laps.

A22
Item description for geotextile and
geogrid shall state the type, grade
and the technical specification of
the materials or reference number
of the product

Cement column
/Jet grouting
[email protected] G23
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description

G510 [100 mm x 3 mm] prefabricated vertical drains as per Specification m


clause (…………).

G520 Dynamic compaction using [10 tonne] drop hammer with [five] nr
drops at height of 15 m.

G530 Vibro compaction up to depth of [10 m] as per Drawing No (….) nr

G540 1000 mm diameter sand column as per Specification clause (….). m

G550.1 1000 mm diameter stone column as per Specification (….). m

G560 1000 mm diameter soil / cement column as per Specification (….). m

G570.1 Woven geotextile with minimum ling term design strength of m2


[100kN/m] as soil reinforcement as per Specification clause (…).

G580 Geogrid with minimum long term design strength of [75kN/m] as soil m2
reinforcement as per Specification clause (…) for reinforced soil
slope.

[email protected] G24
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
6. Grouting work 1. Drilling for grout 1. Earth m
holes 2. Natural hard material m
3. Rock m
4. Artificial hard material m
5. Unsuitable materials m

2. Sleeve pipes m

3. Injection 1. Cement t
2. Sand t
3. Bentonite t
4. Aluminium powder kg
5. Chemical t
6. Pulverised fuel ash t
7. Pea gravel t

4. Connection for nr
grouting
5. Water pressure test nr

[email protected] G25
MyCESMM2
Class G – Geotechnical Work
M13 M14
Drilling through previously grouted holes The mass of grout injection measured shall
in the course of stage grouting shall not not include the mass of mixing water.
be measured. Where grout holes are
expressly required to be extended,
drilling through previously grouted holes C15
shall be measured as drilling through Connection for grouting shall be deemed
rock. to include provision of packer as expressly
required.
A23
Item description for drilling for grout A25
holes shall state the method, diameter Item description for connection for grouting
and maximum depth. shall identify those which are in stages,
distinguishing between those which are in
C14 ascending and descending stages
Items for sleeve pipe shall be deemed to
include grouting of annulus space
between the sleeve pipe and the drilled
holes.

A24
Item description for sleeve pipe shall
state the diameter and type of material

[email protected] G26
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description

G611 [50 mm] diameter for depth not exceeding [10 m] in: Earth m

G613 [50 mm] diameter for depth not exceeding [10 m] in: Rock m

G615 [50 mm] diameter for depth not exceeding [10 m] in: Unsuitable m
material

G620 uPVC sleeve pipes for [50 mm] diameter grout hole. m

G631 Cement [ strength] t

G633 Bentonite [mix...] t

G640.1 Connection for grouting [in ascending stage with single packer nr
setting].

G650 Water pressure test as per Specification clause (….). nr

[email protected] G27
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
7. Diaphragm walls 1. Excavation 1. Earth m3
2. Natural hard material m3
3. Rock m3
4. Artificial hard material m3
5. Unsuitable materials m3

2. Concrete m3

3. Reinforcement 1. Mild steel bar t


2. High tensile steel bar t
3. High tensile steel fabric m2
4. Fabric of other stated m2
material
4. Waterproofed joints sum
5. Guide wall m
6. Preparing top of m
walls to receive
capping
7. Preparing cast in m
pockets or chases

[email protected] G28
MyCESMM2
M15 Class G – Geotechnical Work
The depths of concrete in diaphragm
walls shall be measured from the cut-off Diaphragm Wall
level to the toe level.

D8
Diaphragm walls are walls constructed
with the use of bentonite slurry or other
temporary support fluids.

C16
Items for excavation for diaphragm walls
shall be deemed to include preparation menardbachy.com.au

and upholding sides of excavation.

A26
Item description for excavation shall
state the maximum depth and thickness
of wall.

A27
The mix specification or strengths shall
be stated in item description for
concrete in diaphragm walls

[email protected] G29
MyCESMM2
M16 Class G – Geotechnical Work
The mass of steel reinforcement shall be
M18
taken as 0.785 kg/m per 100 mm² of cross
section (7.85 t/m³). The mass of other The mass measured for reinforcement,
reinforcing materials shall be taken as in tonne, shall be up to two decimal
stated in the contract. place.

D9 M19
The nominal diameter stated in the item Guide walls shall be measured on
description for bar reinforcement shall be both sides of the diaphragm walls
the cross-sectional diameter defined in MS
146.

C17
Items for reinforcement shall be deemed to
include labour for cutting, bending and
placing.
Guide wall
A28
Item description for steel bars shall state
the size of the bars.

M17
The mass measured for reinforcement shall
include the mass of reinforcement expressly
required in laps and special chairs.
[email protected] G30
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description .


G711 Excavation for [1.2 m] thick diaphragm wall not exceeding for the m3
following. Earth , commencing from [... m] to [... m], max depth […].

G720 [Grade C40] tremie mix concrete. m3

G732.1 High tensile steel bar reinforcement; Nominal diameter: [20 mm]. t

G740 Waterproof joints [size … thk] . sum

G750 Guide walls [concrete grade…]. m

G760 Preparing top of walls to receive capping as per Specification clause m


(….).

G770 Preparing cast in pockets or chases as shown in Drawing No. (....). m

[email protected] G31
MyCESMM2
Class G – Geotechnical Work
First division Second division Third division Unit
8. Instrumentation 1. Piezometer nr
2. Inclinometer nr
3. Surface marker nr
4. Settlement plate nr
5. Displacement nr
marker
6. Magnetic nr
extensometer
7. Deep levelling nr
datum

8. Monitoring nr

C18
Items for piezometer and inclinometer
shall be deemed to include pre-boring
and installation.

A29
Item description for piezometer and Displacement
inclinometer shall state the type, depth marker
and material used
[email protected] Surface marker G32
MyCESMM2
Class G – Geotechnical Work
A30
Piezometer
Item description for settlement
plate shall state the dimensions
of plate, depth and material
used.

M20
Measurement of monitoring in
number shall be based on the
trips to the location of the
instrumentation.

C19 Inclinometer
Items for monitoring shall be
deemed to include
preparation of monitoring
report.

A31
Item description for monitoring
shall state the personnel and
number of trips required.

Magnetic extensometer
[email protected] G33
MyCESMM2
Class G – Geotechnical Work

MyCESMM2 Library Description

G810 Piezometer as per Specification clause (…..) and as shown in the nr


drawings.

G820 Inclinometer as per Specification clause (…..) and as shown in the nr


drawings.

G830 Surface marker. nr

G840 Settlement plate as per Specification clause (…..) and as shown in nr


the drawings.

G850 Displacement marker. nr

G860 Magnetic extensometer as per Specification clause (……….). nr

G870 Deep levelling datum. nr

G880 Monitoring of instrument for the above instrument at the project site nr
by [Geologist] as per Specification clause (…..……).

[email protected] G34
MyCESMM2
Class G – Geotechnical Work

THE END

[email protected] G35