Introduction To Pre-Stressed Structures
Introduction To Pre-Stressed Structures
Introduction to
Pre-stressed Structures
Goman Ho
Arup Fellow
29 Mar 2023
• In prestressed concrete, tendons are used to apply prestress compression to the member
• The axial compression counteracts the tensile stresses induced by the applied loadings
1
3/28/2023
Pre-stressing
Pre-tensioning Post-tensioning
Internal External
Pre-tensioning Method
2
3/28/2023
Post-tensioning Method
Source: Prof. Dr. Azlan Abdul Rahman, Universiti Teknologi Malaysia © UTM 2006
3
3/28/2023
Un-bonded Post-Tension
• In post-tensioning, the steel in the concrete is stretched after the curing process.
• Unlike bonded, un-bonded provides tendons freedom of movement by coating each tendon
with grease and covering it with a plastic sheathing
• Tension on the concrete is achieved by the cables acting against the steel anchors that are
buried in the perimeters of the concrete
• Advantages
- Post-stress grouting is eliminated
- Ability to de-stress the tendons
- Economical
- Replaceable
- Simple stressing equipment
4
3/28/2023
Un-bonded Post-Tension
10 Dead End
10
5
3/28/2023
Post-tensioning System
11
11
Tendons
Cross Section
12
12
6
3/28/2023
Tendons
Cross Section at Deviator
13
13
14
14
7
3/28/2023
15
15
Pretensioning System
• Strands are pretensioned between end anchorages
and the concrete members cast around strands.
Pretensioning of strands
Casting of concrete
16
16
8
3/28/2023
Pretensioning System
17
17
19
19
9
3/28/2023
20
20
PT Deck
21
21
10
3/28/2023
22
22
23
23
11
3/28/2023
24
24
25
25
12
3/28/2023
https://roselliott.files.wordpress.com/2012/04/dsc00769.jpg
Typical Section
of Shear Key
26
26
27 Source: https://www.youtube.com/watch?v=aClkJkRn3E0
27
13
3/28/2023
28
28
29
29
14
3/28/2023
Incremental Launching
• Deck is produced in casting yard located behind the abutment in segments by match-
casting. The deck is jacked forward a distance equal to the length of the segment in each
cycle.
• Applicable to deck with constant cross section with straight alignment or constant
horizontal and vertical curvature
• Launching stage is critical in prestress design
30
30
31 Source : https://www.youtube.com/watch?v=vKGYs71N72c
31
15
3/28/2023
32
32
Superior ULS performance with bonded tendons Inferior ULS performance with unbonded tendons
Thicker web due to reduction of effective web thickness Web can be sized thinner
the presence of cables
Depth of deck could be more effectively utilized – cable Cables extreme position restricted by deviator – typ
typically around 125mm from soffit at mid span around 350mm form soffit at mid span
Cable profile more complicated to avoid clashing and Cable profile generally simpler – need attention to avoid
achieve efficient design, particular with the use of clashing with blister for highly curved deck
blisters.
Higher PT loss due to friction and wobble Less PT loss due to friction and wobble
33
33
16
3/28/2023
• Precast pier
34
34
35
35
17
3/28/2023
Precast Pier
• Hollow pier section divided into segments
• Post-tensioning of internal prestress
• Pier base portion may need to be in-situ RC for ductility
under seismic
36
36
37
37
18
3/28/2023
Detailing Practice
38
Considerations of Detailing
• Attention to detailing of prestressing tendons is required to achieve a buildable and robust
design.
• The following aspects will be discussed:
- Cover to tendons
- Spacing of tendons
- Requirement of proprietary system
- minimum radius and straight length
- work clearance for stressing
- anchorages
- Coordination with reinforcement
- Checking of clashing between cables
- Tendon Profile
39
•
39
19
3/28/2023
40
40
41
41
20
3/28/2023
Tendon Profile
• Tendon profile shall be presented to reflect the design tendon profile but shall also be
allowed for some tolerance during construction.
42
42
43
43
21
3/28/2023
4
4
44
45
22
3/28/2023
46
46
Clashing Check
47
47
23
3/28/2023
Prestressing in Buildings
48
49
24
3/28/2023
51
51
The Site
• Residential Redevelopment at 2A Seymour Road, HK
Azura
• Usage: Residential
(CSR1)
• Services:
• Structural
• Geotechnical
52
52
25
3/28/2023
CSR2
Azura
(CSR1)
53
Tower Section
2 Levels of
Penthouse • Site at Mid-levels of Hong Kong
Island, Seymour Road
Transfer Plate
2 Levels of Clubhouse +
3 Levels of Car Park
54
26
3/28/2023
Typical Floor
CORE
55
Local Thickening
2900mm
56
56
27
3/28/2023
57
57
58
58
28
3/28/2023
59
59
Site Photos
60
60
29
3/28/2023
61
61
Site Photo
62
62
30
3/28/2023
63
63
64
64
31
3/28/2023
Project Details
65
65
66
66
32
3/28/2023
Elevation
67
67
K11
68
68
33
3/28/2023
69
69
70
70
34
3/28/2023
http://www.tallbridgeguy.com/tag/county-bridge-concept/
71
71
72
72
35
3/28/2023
73
73
74
74
36
3/28/2023
75
75
76
76
37
3/28/2023
77
77
Any Questions ?
78
38