Bungalow Schedule
Bungalow Schedule
Bungalow Schedule
Ace Developers'
Foundation Walling
Ace Developers'
Element 2; GROUND FLOOR FRAME
EPS PANELS (1panel dimension = 3x1.2 Mtrs)
Double wall panels 100 Board 8,500 850,000.00
Concrete fill in EPS (1:2:4)
Cement 172 Bags 650 111,800.00
Sand 20 Tonnes 2,000 40,000.00
Ballast 41 Tonnes 2,000 82,000.00
Wall Mortar ratio (1;3) Inner & outer side; and slurry sum included
Cement 244 Bags 650 158,600.00
Sand 41 Tonnes 2,000 82,000.00
Lime; for Slurry 13 Bags 200 2,600.00
Total carried to collection 1,326,200.00
Element 3; UPPER FLOOR
In situ slab concrete (1:2:4-18mm aggregate)
Cement 180 Bags 650 117,000.00
Sand 22 Tonnes 2,000 44,000.00
Aggregate 18mm 45 Tonnes 2,000 90,000.00
EPS Panel for Slab (1panel dimension = 1.2x2.5 Mtrs)
Floor/Slab panel 50 Boards 6,500 325,000.00
Concrete fill in EPS (1:2:4)
Cement 132 Bags 650 85,800.00
Sand 15 Tonnes 2,000 30,000.00
Ballast 32 Tonnes 2,000 64,000.00
Wall (inner and outer) & Slab Mortar
Cement 195 Bags 650 126,100.00
Sand 33 Tonnes 2,000 66,000.00
Slab and Beam Reinforcement, High yield steel (1 bar length= 12 meters)
10mm diameter 105 Bar 820 86,100.00
12mm diameter 115 Bar 1,220 140,300.00
Ace Developers'
Element 4; ROOFING (flat roof with eps)
SUMMARY
Element No. 1: Substructure 1,205,880.00
Labour 10% 241,120.00
TOTAL SUBSTRUCTURE 1,447,000.00
Element No. 2: Ground floor 1,326,200.00
TOTAL 3,305,100.00
Ace Developers'