Financial Evaluation
Financial Evaluation
Financial Evaluation
a) Payback Period:
This is one of the widely used methods for evaluating the investment proposals. Under this
method the focus is on the recovery of original investment at the earliest possible. It determines
the number of years to recoup the original cash out flow, disregarding the salvage value and
interest. This method does not take into account the cash inflows that are received after the
payback period. There are two methods in use to calculate the payback period
1) Where annual cash flows are not consistent vary from year to year.
2) Where the annual cash flow are uniform.
Project A Project B
Year Cash flow $ Year Cash flow $
0 -700 0 -700
1 100 1 400
2 200 2 300
3 300 3 200
4 400 4 100
5 500 5 0
Since the two projects are mutually exclusive, the one with the higher NPV has to be accepted.
Thus, project A is selected as its NPV is higher than that of project B. Had the two projects been
independent of one another, both of them would be accepted because both projects have positive
net present values (NPVs).
Unit 4 Activity 1
ABC PLC is considering an investment in a cement project. It has on hand $180, 000. It is
expected that the project may work for seven years and likely to generate the following annual
cash flows.
Year Cash Flows
1 30,000
2 50,000
3 60,000
4 65,000
5 40,000
6 30,000
7 16,000
The cost of capital is 8%
Required: - Calculate the Net Present Value.
a) Profitability Index Method / Benefit Cost Ratio
Profitability index method is the relationship between the present values of net cash inflows and
the present value of cash outflows. It can be worked out either in unitary or in percentage terms.
The formula is
Suppose you were looking at an investment with investment costs $100,000 and net cash flow as
given below. The Required Rate of Return is 20%.
What’s the IRR? If we require a 20 percent return, should we take this investment?
We can set the NPV equal to zero and solve for the discount rate:
Unfortunately, the only way to find the IRR in general is by trial and error, either by hand or by
calculator.
At 10%,
At 30 %,
With a little more effort, we can find the IRR using the following formula
Where
• L = Lower discount rate L = Low
• H = Highest discount rate H = High
• NPVL = The NPV results for the lower discount rate
• NPVH = The NPV results for the higher discount rate
IRR = 28.5%
So, if our required return were less than 28.5 percent, we would take this investment. If our
required return exceeded 28.5 percent, we would reject it.
In our example, the NPV rule and the IRR rule lead to identical accept-reject decisions.