Client Presentation
Client Presentation
Client Presentation
CLIENT PRESENTATION
13/01/2022
Disclaimer:
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
LOCATION
D
OA D
AR
R
R OA
G AR
NA G
NA
RAMWADI AP IT
METRO 5KM
STATION
(SITE)
PROPOSED
IT PARK
N
PLANS
1. SITE PLAN
3. BASEMENT PLAN
PROPOSED DESIGN 6.
7.
PARKING 1,2,3 FLOOR PLAN
SECTIONS
VIEWS
SITE PLAN
- - -18 M WIDE ROAD - - -
WING D WING C WING B WING A
- -60 M
LOBBY LOBBY LOBBY LOBBY
WIDE
PUNE-
FOOD COURT FOOD COURT FOOD COURT FOOD COURT
NAGA
R ROA
- D–-
*
BUILDING SERVICES
TOILETS LOBBY
DRIVEWAY FRONT OFFICE
BACK OFFICE OPEN SPACE
Disclaimer:
N
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
LOBBY
WING B
LOBBY BACK OFFICE
2 WHEELER PARKING RECEPTION
4 WHEELER PARKING FRONT OFFICE
AMENITIES
FOOD COURT
OFFICE
TOILETS
N
Disclaimer:
The current design is subject to change as per Developer
requirements and approvals. This presentation is only a
proposed planning presentation for external clients.
PLANS
CORE
BASEMENT FLOOR PLAN
N
NATURAL GROUND
2 WHEELER PARKING
4 WHEELER PARKING
DRIVEWAY
Disclaimer:
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
PLANS
N
2 WHEELER PARKING OFFICE RECEPTION SERVICES
4 WHEELER PARKING TOILETS FRONT OFFICE
Disclaimer:
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
PLANS
N
CORE 2 WHEELER PARKING 4 WHEELER PARKING DRIVEWAY RAMP
PLANS
N
OFFICE
TOILETS
CORE
SERVICES
Disclaimer:
The current design is subject to change as per Developer requirements and
approvals. This presentation is only a proposed planning presentation for external
clients.
PLANS
N
REFUGE AREA
Disclaimer:
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
PLANS
N
OHWT
OFFICE
TOILETS
CORE
TERRACE
VRF ODU SPACE
Disclaimer:
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.v
SECTIONS
C B
A A
C B
NN
SECTION BB
Disclaimer:
The current design is subject to change as per
Developer requirements and approvals. This
presentation is only a proposed planning
presentation for external clients.
SECTIONS
C B
A A
C B
NN
SECTION CC
Disclaimer:
The current design is subject to change as per
Developer requirements and approvals. This
presentation is only a proposed planning
presentation for external clients.
SECTIONS
SECTION AA
C B
A A
C B
Disclaimer:
NN
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
VIEWS
Disclaimer:
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
VIEWS
Disclaimer:
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
❏ TRAFFIC ANALYSIS
❏ IGBC CERTIFICATION
❏ PLUMBING
❏ ELECTRICAL
❏ FIRE FIGHTING
TRAFFIC ANALYSIS
18 M WIDE ROAD
60 M
WIDE
ROAD
N
● The traffic coming on the internal road is around 2275 PCU per hour in peak hour.
● The internal roads are 12 m (3 lanes wide one way), with a capacity of 3600 PCU per hour.
● Having 4 gates shall divide the traffic into 4 parts with average of 569 PCU coming in per
gate.
● The number of vehicles coming into the site is calculated to be 3675 per hour in peak hours
(including car,bikes & scooters)
● The gates are to have 3 incoming lanes during the morning peak and vice versa during
evening peak, allows to fulfill the peak hour traffic demand without increasing number of
gates
● Pedestrian entering into the site in peak hour i calculated to be around 4200, i.e,70 per minute
● The entire north side of the building is to be pedestrianised to improve walkability in the
premises
● Segregating the vehicular and pedestrian traffic improves pedestrian safety
● A 12M wide pedestrian area is provided on the north side which will be used by pedestrians to
reach their wings
● As per Indo-HCM, the LoS of such footpath comes out to be A which is very good and will pose
no inconvenience to the pedestrians.
PEDESTRAIN AREA
TRAFFIC ANALYSIS
FLOW OF PEDETAIN IN THE ELEVATORS - VERTICAL TRANSPORTATION
● No of elevators :16
● Passenger capacity : 20
● Speed of Elevators : 2.5M/s
● Passengers can access elevators only from
main lobby
● All Elevators can access all Entrance Floors
● All Elevators can Access all Destination Floors
● Destination Control system is Employed to
allot Elevators
● Peak duration - 2 hours, say 8 am - 10 am
● Peak hour - 1 hour, say, 9am - 10 am
● Peak of peak (simulation period) 15 minutes,
say 9.45m - 10 am
TRAFFIC ANALYSIS
FLOW OF PEDETAIN IN THE ELEVATORS - VERTICAL TRANSPORTATION
REQUIREMENTS
REQUIREMENTS
DESIGN BRIEF
WATER CALCULATION
PLUMBING
Hydrogeological
Report
Number of Recharge
Pits and Location
RWH
PLAN & SECTION OF RECHARGE PITS
SEWAGE TREATMENT PLANT-SBT
DESIGN BRIEF
SEWAGE TREATMENT PLANT-SBT
SPACE REQUIREMENT
TECHNOLOGY
SEWAGE TREATMENT PLANT-SBT
● Separate shafts for Electrical, Earthing strips, LA strips and LV are planned in each
building.
● PV System is planned on terrace area and the generated power will be utilized for
common load.
N
4. BATTERY UPS ROOM
ELECTRICAL CORE
5. MSEB METERING AREA
Electrical services are planned from switching station as source to each building.
ELECTRICAL
SPACE PLANNING
WING C
ELECTRICAL
LIGHTNING ARRESTER LAYOUT
HVAC
OFFICE
OFFICE
2M
OFFICE
11.5M OFFICE
OFFICE+REFUGE
11.5M OFFICE
285MM SLAB THK
OFFICE
OFFICE
OFFICE+REFUGE
11.5M OFFICE
OFFICE
11..5M OFFICE
2M PARKING
285MM SLAB THK
PARKING
4.5M
- CORE
PARKING
PARKING
- STAIRCASE
Disclaimer:
2M
2M
11.5M
11.5M
11.5M
11.5M
The current design is subject to change as per Developer requirements and approvals.
11.5M
This presentation is only a proposed planning presentation for external clients.
RCC STRUCTURE
2. HVAC LAYOUT
4. TOILET LAYOUT
DESIGN DETAILING
APIT - PRESENTATION
TYPICAL OFFICE DETAILING
N
FURNITURE LAYOUT
OFFICE
TOILETS
CORE
SERVICES
Disclaimer:
The current design is subject to change as per Developer requirements and approvals.
This presentation is only a proposed planning presentation for external clients.
TYPICAL OFFICE DETAILING
ELECTRICAL &
LV ROUTING
Disclaimer:
The current desing is subject to change as
per Devloper requirements and approvals.
This presentation is only a proposed
planning presentation for external clients.
TYPICAL OFFICE DETAILING
ELECTRICAL &
LV ROUTING
TYPICAL OFFICE DETAILING
HVAC DUCTING
TYPICAL OFFICE DETAILING
HVAC DUCTING
INTEGRATION IN SKETCHUP
TYPICAL OFFICE DETAILING
FIRE FIGHTING
LAYOUT
TYPICAL OFFICE DETAILING