PROJECT NAME.

- Master Projet Manangent 03-Dec-22 09:04


document No.- 001

Activity ID Activity Name Planned Start Planned Finish Planned Planned Total Jan 22 Jan 29 Feb 05
Cost 1 2 3
Duration Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri
BL MASTER BUILDING 22-Jan-22 28-Mar-22 53d $24,195.00

22-Jan-22 03-Feb-22 11d $8,350.00 03-Feb-22,...


BL.1 INFRASTRUCTURE
BL.1.1 Excavation 22-Jan-22 25-Jan-22 4d $4,440.00 Excavation
BL.1.2 Soil Excavation 24-Jan-22 26-Jan-22 3d $1,080.00 3d Soil Excav...
BL.1.3 Framing 27-Jan-22 02-Feb-22 5d $2,200.00 5d Framing
BL.1.4 Insulation 31-Jan-22 03-Feb-22 3d $630.00 3d Insulation
BL.2 HARDENING 03-Feb-22 12-Mar-22 29d $13,105.00

BL.2.1 Concreting 03-Feb-22 05-Feb-22 1d $790.00 1d Concreting


BL.2.2 Wall Working 07-Feb-22 17-Feb-22 8d $5,010.00 8d
BL.2.3 Plastering 12-Feb-22 26-Feb-22 12d $2,705.00 12d
BL.2.4 Painting 21-Feb-22 12-Mar-22 15d $4,600.00
BL.3 FACILITIES 22-Jan-22 28-Mar-22 53d $2,740.00

BL.3.1 SANITARY INSTALLATIONS 12-Mar-22 19-Mar-22 6d $1,440.00


BL.3.1.1 Excavation 12-Mar-22 15-Mar-22 3d $480.00
BL.3.1.2 Piping 15-Mar-22 17-Mar-22 2d $800.00
BL.3.1.3 Pipe Covering 19-Mar-22 19-Mar-22 1d $160.00
BL.3.2 ELECTRICAL INSTALATION 22-Jan-22 28-Mar-22 53d $1,300.00
BL.3.2.1 Excavation 20-Mar-22 23-Mar-22 4d $640.00
BL.3.2.2 Wiring 24-Mar-22 27-Mar-22 2d $500.00
BL.3.2.3 Wire Covering 27-Mar-22 28-Mar-22 1d $160.00
BL.3.2.4 A 22-Jan-22 22-Jan-22 1d $0.00 A
BL.3.2.5 B 22-Jan-22 22-Jan-22 1d $0.00 B
BL.3.2.6 C 22-Jan-22 22-Jan-22 1d $0.00 C

Remaining Level of Effort Project Baselin... MASTER BUILDING of 2 TASK filter: All Activities
Actual Level of Effort Secondary Bas... © Oracle Corporation
PROJECT NAME.- Master Projet Manangent 03-Dec-22 09:04
document No.- 001

Feb 12 Feb 19 Feb 26 Mar 05 Mar 12 Mar 19 Mar 26


4 5 6 7 8 9 10
Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat

12-Mar-22,...

Wall Worki...
Plastering
15d Painting

19-Mar-22,...

3d Excavation
2d Piping
1d Pipe Cover...

4d Excavation
2d
1d

Remaining Level of Effort Project Baselin... MASTER BUILDING of 2 TASK filter: All Activities
Actual Level of Effort Secondary Bas... © Oracle Corporation