50% found this document useful (2 votes)
1K views11 pages

Method Statement For Installationtesting Commissioning of External Fire Hydrant

Method Statement for Installationtesting Commissioning of External Fire Hydrant (1) testing commissioning procedures

Uploaded by

riswan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
1K views11 pages

Method Statement For Installationtesting Commissioning of External Fire Hydrant

Method Statement for Installationtesting Commissioning of External Fire Hydrant (1) testing commissioning procedures

Uploaded by

riswan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

TITLE Ref. No.

:
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 1 of 13

METHOD STATEMENT FOR

INSTALLATION,TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT


TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 2 of 13

REVISION RECORD

This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.

Rev. No. Date By Chkd. Approvals Description and Page Numbers of Revisions
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 3 of 13

CONTENTS

1.0 PURPOSE

2.0 SCOPE

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITIES

6.0 EQUIPMENTS

7.0 PROCEDURE

8.0 ATTACHMENTS
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 4 of 13

1.0 PURPOSE

 This method statement is applicable for the Installation, Testing & Commissioning of External
Fire Hydrant for the project as mentioned in the Specifications & Approved Shop Drawings.

2.0 SCOPE

 This method Statement shall cover the Supply, Installation, Testing & Commissioning of
External Fire Hydrant in line with project requirements as indicated in the Approved Shop
Drawings, specifications & manufacturer’s instructions.

3.0 REFERENCE

3.1 Latest Approved shop drawings intended for Fire Fighting System
3.2 Specifications
3.3 Project Quality Plan
3.4 Project HSE Plan
3.5 Material Approval
3.6 Approved Method Statement for Installation & Testing for Fire Fighting System & Accessories

4.0 DEFINITIONS

PQP : Project Quality Plan


PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control Engineer.
WIR : Inspection and Test Request
MIR : Material Inspection Request
UPVC Class E : Ultra polyvinyl chloride
UPVC : Ultra polyvinyl chloride
HDPE : High density polyethylene
PEX PIPE : Cross-linked Polyethylene
G.I. Pipe : Galvanized Iron Pipe
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 5 of 13

 Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
 Project Manager
 Construction manager
 QA/QC Engineer
 Site Engineer
 HSE officer
 SK

5.1 Project Manager

 The work progress shall be carried out as per planned program and all the equipment’s required
to execute the works shall be available and in good condition as per project planned.
 Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.

5.2 Construction Manager

 Construction Manager is responsible to supervise and control the work on site.


 Coordinating with QA/QC Engineers, Site Team & Foremen for all activities on site.
 Control and sign all WIRs before issuing to Consultant approval.

5.3 Site Engineer

 The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
 Provision of all necessary information and distribution of responsibilities to his Construction
team.
 The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
 The constant coordination with the Safety Engineer to ensure that the works are carried out in
safe working atmosphere.
 The constant coordination with the QA/QC Engineer for any works to be carried out and initiate
for the Inspection for the finished works.
 He will ensure the implementation of any request that might be raised by the Consultant.
 Efficient daily progress shall be obtained for all the equipment and manpower.
 He will engage in the work and check the same against the daily report received from the
Foremen.
 The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.

5.4 QA/QC Engineer (MEP):

 The monitoring of executions of works at site and should be as per the approved shop drawings
and project specifications.
 Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
 He will follow and carries out all the relevant tests as per project specifications.
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 6 of 13

 Obtain the required clearance prior to Consultant’s inspections.


 Should acquire any necessary civil works clearances and coordination.
 QA/QC Engineer will assist the Consultant Engineer/ Inspector during Inspection.
 Check & ensure work is completed prior to offer Consultant for inspection.
 Coordination with site construction team.
 He will assist the Consultant Engineer/ Inspector during the inspection.
5.5 Site Foreman

 The carrying-out of work and the proper distribution of all the available resources in
coordination with the Site Engineer on a daily basis.
 Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
 Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
 Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.

5.6 Safety Officer

 The implementation of all safety measures in accordance with the HSE plan and that the whole
work force is aware of its proper implementation.
 The implementation of safety measures is adequate to maintain a safe working environment on
the work activity.
 Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
 The site is maintained in a clean and tidy manner.
 Ensure only trained persons shall operate the power tools.
 Ensure all concerned personals shall use PPE and all other items as required.
 Ensure adequate lighting is provided in the working area at night time.
 Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
 Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
 Ensure safe access to site work at all times.

5.7 Store Keeper (SK)

 Responsible for overall Store operations in making sure to store the material delivery to the site and
keep it in suitable area that will keep the material in safe from rusty and damage.
 One who will acknowledge the receiving of materials at site in coordination with QA/QC &
concerned Engineer.

6.0 EQUIPMENTS

Following tools shall be arranged before starting the job.


a. Tool Box.
b. Measuring Tape.
c. Hack Saw Blade
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 7 of 13

d. Spirit Level
e. Electric Drill Machine
f. Step Ladders
g. Threading Machine
h. Solvent Cement
i. Electric welding machine. (if required)
j. Torque Wrench
k. Pipe Cutting Machine
l. Grinding Machine
m. Pressure Gauge
n. Hammer
o. Water Level Marker
p. Mobile Scaffolds
q. Staging Platforms

7.0 PROCEDURE

 Work Sequence/Procedure

7.1 General Requirements


 All the materials received at site shall be as per the approved technical material submittal
for External Fire Hydrant to be inspected upon receipt & approved by the engineer prior in
proceeding with the installation through MIR. Any discrepancies, damages etc., should be
reported to the supplier for rectification or replacement & to be removed from site
immediately.
 All construction/inspection/testing works shall be carried out in accordance with the
specifications & to be done by qualified Mechanical Engineers and shall be checked and
approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
 Contractor has to clarify the procedure for material delivery to the site through Consultant
Engineer at site.

7.2 Delivery & Storage

7.2.1 Material Transport/ Delivery

 During transportation ensure that the equipment & its components (if any) are delivered in
a shipping package and or shall be at least in a box covered with plastic. Extra care in
unloading the equipment is required to avoid scratching or denting.
 Where ever possible the loading and offloading of the External Fire Hydrant shall be
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 8 of 13

carried out by hand. If weight cannot bear by hand, fork lift shall be used.
 Equipment shall not be dropped onto hard surfaces & should not be dragged along the
ground.
 All the received units shall be checked & inspected to ensure that it is complying with the
approved material submittals prior to site storage.

7.3 Storage

7.3.1 Storage on Site Store

 To ensure that deterioration of the External Fire Hydrant does not occur during storage, it is
recommended to store the equipment in sheltered conditions that are protected from weather
elements and accidental damage.
 External Fire Hydrant shall be protected with plastic/ tarpaulin or shall not be removed from
the shipping package unless otherwise instructed to do so.
 All packages for the equipment reaching the site shall be identified as per package list.

7.4 Sequence of Installation for the External Fire Hydrant


7.4.1 Safety
 All site safety rules & regulations shall be complied with.
 Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in
the installation, testing & commissioning and shall be recorded.
 All operatives will be equipped with minimum personnel protective equipment; hard hat,
coveralls, safety boots, safety glasses.
 The persons using cleaning fluid and solvent cement have to wear hand gloves.
 Ensure only qualified personnel shall install, test & commissioned the equipment.
 During Testing & Commissioning, display warning sign boards necessarily provided and
barricade the area whenever necessary.
 Ensure that all operatives fully understand the method of these activities.
7.4.2 Pre- Installation Procedure
 Before commencement of installation activity, the supervisor must ensure that:
 Delivered Fire Hydrants shall have been inspected & approved via MIR by the Consultant
prior to installation at site.
 All Installations & Pressure Testing of Fire Fighting Pipe works have been completed &
approved by the Consultant.
 Relevant documents or certificates shall be presented at the time of inspection if required
by the Consultant.
 Permission to start or Civil Clearances prior to installation has been given by the main
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 9 of 13

contractor.
 All relevant Shop drawings for the installation of the equipment shall be available &
approved by the Consultant. No installation shall be done without Approved Shop
Drawings.
 Installation activities shall only commence when all associated works by the Civil have
been verified & completed.
 Safe access shall be provided by the Main Contractor thru Work Permit in coordination
with the Safety in charge at site.
 Inspect the relevant area for any possible clashes with other services.
 Check for other services, making sure that there is no interference between each service &
adequate access to work and for future maintenance can be maintained.

7.4.3 Installation Procedure for the External Fire Hydrant

 Prior to installation, ensure that all External Fire Hydrants are equipped with
associated appurtenances as per manufacturer standard & supply according to the
approved material submittal.
 All External Fire Hydrants shall be covered & protected for moisture, corrosion,
dust & any deterioration before & after the installation.
 Ensure all pipework to be connected to the External Fire Hydrant has the proper size
& have been hydraulically tested.
 Pipes shall be free of debris or dirt prior to connection.
 Mark the location & size of the Valve pit in preparation. Inform civil staffs for
construction.
 Valve pits shall be of concrete construction to adequately house the valves.
 Ensure that the location of the valves are readily accessible for inspection,
operation, testing & for future maintenance.
 Provide plinths for the External Fire Hydrants. Size of plinths shall be as per the
size requirement & size shall be as per the approved details.
 Place the External Fire Hydrant on the plinths as per the approved installation
details.
 Each fire hydrant will be provided with isolation valve with the correct size.
 Ensure that the isolation valve shall open & close from the surface of the ground
level.
 Whenever required, provide valve pit covers on the pit for protection.
 After installation, raise an inspection to the Consultant for approval & acceptance.
7.4.3.2.2 Installation Procedure of Butterfly Valves:
 Install butterfly valves as per the approved drawings. Ensure that it is readily
accessible for operation & maintenance.
 Ensure valve disc does not interface with the operation of other system components
adjacent to the butterfly valve.
 If the valve is hard to close, it may be due to debris lodge in the sealing area. This
can be corrected by backing-off the hand wheel and closing it again several times if
necessary. Don’t force the valve to seat by applying a wrench to hand wheel. This
may distort the valve components or scratch the sealing surfaces.
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 10 of 13

 The inlet & outlet piping of the valve shall be properly supported to prevent
excessive stress to the valve body. Do not use the valve body to support pipeline
position as it may result in distortion of the valve body.

7.4.4. Testing & Commissioning Procedures


7.4.4.1 Visual Inspection & Testing Procedure

 After documentations & visual checks, Testing shall proceed further.


 Ensure all pipe works has been hydrostatically tested & completed. Refer to
Approved Method Statement Ref. No.: MS-6012-0021 Rev.02.
 All supporting system has been completed, properly installed & fixed.
 Ensure all instruments (if required) to be used during the testing shall be calibrated
& records shall be available.
 Ensure that the all Equipment is in their proper location as mentioned on the
Approved Shop Drawings.

7.4.4.2 Commissioning Procedure for the External Fire Hydrant

 Prior to commissioning, ensure that all instruments (if any) to be used during the
commissioning shall be calibrated. Calibration certificates shall be available.
 Ensure that all installed External Fire Hydrants & Valves have been installed as per
the approved shop drawings, manufacturers’ recommendation.
 Piping system has been tested for leaks. Approval for all preliminary inspections
shall be available during the commissioning stage.
 Ensure all External Fire Hydrants have been installed & fix properly with the
correct alignment & spacing.
 Ensure firmness & tightness of supports prior to Commissioning of the Fire
Hydrant.
 Verify that the external Fire Hydrant shall be easily accessible.
 Verify that the hydrant has been fitted with maintenance record tag.
 Verify that signage has been provided that clearly indicates the location of the fire
hydrant.
 Simulate fire conditions by opening a valve.
 Verify that all water flow alarm & valve monitoring system switches operate
correctly.
 Verify water pressure & flow at the hydrant.
 Connect a fire hose & open the fire hydrant valve. The water throw shall be at least
20 meters.

8.0. ATTACHMENTS

8.1. Inspection & Test Plan

8.2. Installation Check Sheet


TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 11 of 13

8.3. Testing & Commissioning Check Sheet

8.4. Risk Assessment

You might also like