Method Statement For Installationtesting Commissioning of External Fire Hydrant
Method Statement For Installationtesting Commissioning of External Fire Hydrant
:
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 1 of 13
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.
Rev. No. Date By Chkd. Approvals Description and Page Numbers of Revisions
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 3 of 13
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENTS
7.0 PROCEDURE
8.0 ATTACHMENTS
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 4 of 13
1.0 PURPOSE
This method statement is applicable for the Installation, Testing & Commissioning of External
Fire Hydrant for the project as mentioned in the Specifications & Approved Shop Drawings.
2.0 SCOPE
This method Statement shall cover the Supply, Installation, Testing & Commissioning of
External Fire Hydrant in line with project requirements as indicated in the Approved Shop
Drawings, specifications & manufacturer’s instructions.
3.0 REFERENCE
3.1 Latest Approved shop drawings intended for Fire Fighting System
3.2 Specifications
3.3 Project Quality Plan
3.4 Project HSE Plan
3.5 Material Approval
3.6 Approved Method Statement for Installation & Testing for Fire Fighting System & Accessories
4.0 DEFINITIONS
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
Project Manager
Construction manager
QA/QC Engineer
Site Engineer
HSE officer
SK
The work progress shall be carried out as per planned program and all the equipment’s required
to execute the works shall be available and in good condition as per project planned.
Specific attention is paid to all safety measures and quality control in coordination with Safety
Engineer and QA/QC Engineer and in line with PSP and PQP.
The method of statement to the system shall be implemented according to the Consultant project
specifications and approved shop drawings.
Provision of all necessary information and distribution of responsibilities to his Construction
team.
The work progress shall be monitored in accordance with the planned work program and he will
provide reports to his superiors.
The constant coordination with the Safety Engineer to ensure that the works are carried out in
safe working atmosphere.
The constant coordination with the QA/QC Engineer for any works to be carried out and initiate
for the Inspection for the finished works.
He will ensure the implementation of any request that might be raised by the Consultant.
Efficient daily progress shall be obtained for all the equipment and manpower.
He will engage in the work and check the same against the daily report received from the
Foremen.
The passage of all the revised information to the Foremen and ensure that it’s being carried out
properly.
The monitoring of executions of works at site and should be as per the approved shop drawings
and project specifications.
Ensure WIRs and MIRs are being raised for activities in timely manner and inspected by the
Consultant.
He will follow and carries out all the relevant tests as per project specifications.
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 6 of 13
The carrying-out of work and the proper distribution of all the available resources in
coordination with the Site Engineer on a daily basis.
Daily reports of the works are achieved and coordinated for the future planning with the Site
Engineer.
Incorporate all the QA/QC and Safety requirements as requested by the concerned Engineer.
Meeting with any type of unforeseen incident or requirement and reporting the same to the Site
Engineer immediately.
The implementation of all safety measures in accordance with the HSE plan and that the whole
work force is aware of its proper implementation.
The implementation of safety measures is adequate to maintain a safe working environment on
the work activity.
Inspection of all the site activities and training personnel in accident prevention and its proper
reporting to the Construction Manager and the Project Manager.
The site is maintained in a clean and tidy manner.
Ensure only trained persons shall operate the power tools.
Ensure all concerned personals shall use PPE and all other items as required.
Ensure adequate lighting is provided in the working area at night time.
Ensure high risk elevated areas are provided are barricade, tape, safety nets and provided with
ladders.
Ensure service area/inspection area openings are provided with barricade, tape, and safety nets.
Ensure safe access to site work at all times.
Responsible for overall Store operations in making sure to store the material delivery to the site and
keep it in suitable area that will keep the material in safe from rusty and damage.
One who will acknowledge the receiving of materials at site in coordination with QA/QC &
concerned Engineer.
6.0 EQUIPMENTS
d. Spirit Level
e. Electric Drill Machine
f. Step Ladders
g. Threading Machine
h. Solvent Cement
i. Electric welding machine. (if required)
j. Torque Wrench
k. Pipe Cutting Machine
l. Grinding Machine
m. Pressure Gauge
n. Hammer
o. Water Level Marker
p. Mobile Scaffolds
q. Staging Platforms
7.0 PROCEDURE
Work Sequence/Procedure
During transportation ensure that the equipment & its components (if any) are delivered in
a shipping package and or shall be at least in a box covered with plastic. Extra care in
unloading the equipment is required to avoid scratching or denting.
Where ever possible the loading and offloading of the External Fire Hydrant shall be
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 8 of 13
carried out by hand. If weight cannot bear by hand, fork lift shall be used.
Equipment shall not be dropped onto hard surfaces & should not be dragged along the
ground.
All the received units shall be checked & inspected to ensure that it is complying with the
approved material submittals prior to site storage.
7.3 Storage
To ensure that deterioration of the External Fire Hydrant does not occur during storage, it is
recommended to store the equipment in sheltered conditions that are protected from weather
elements and accidental damage.
External Fire Hydrant shall be protected with plastic/ tarpaulin or shall not be removed from
the shipping package unless otherwise instructed to do so.
All packages for the equipment reaching the site shall be identified as per package list.
contractor.
All relevant Shop drawings for the installation of the equipment shall be available &
approved by the Consultant. No installation shall be done without Approved Shop
Drawings.
Installation activities shall only commence when all associated works by the Civil have
been verified & completed.
Safe access shall be provided by the Main Contractor thru Work Permit in coordination
with the Safety in charge at site.
Inspect the relevant area for any possible clashes with other services.
Check for other services, making sure that there is no interference between each service &
adequate access to work and for future maintenance can be maintained.
Prior to installation, ensure that all External Fire Hydrants are equipped with
associated appurtenances as per manufacturer standard & supply according to the
approved material submittal.
All External Fire Hydrants shall be covered & protected for moisture, corrosion,
dust & any deterioration before & after the installation.
Ensure all pipework to be connected to the External Fire Hydrant has the proper size
& have been hydraulically tested.
Pipes shall be free of debris or dirt prior to connection.
Mark the location & size of the Valve pit in preparation. Inform civil staffs for
construction.
Valve pits shall be of concrete construction to adequately house the valves.
Ensure that the location of the valves are readily accessible for inspection,
operation, testing & for future maintenance.
Provide plinths for the External Fire Hydrants. Size of plinths shall be as per the
size requirement & size shall be as per the approved details.
Place the External Fire Hydrant on the plinths as per the approved installation
details.
Each fire hydrant will be provided with isolation valve with the correct size.
Ensure that the isolation valve shall open & close from the surface of the ground
level.
Whenever required, provide valve pit covers on the pit for protection.
After installation, raise an inspection to the Consultant for approval & acceptance.
7.4.3.2.2 Installation Procedure of Butterfly Valves:
Install butterfly valves as per the approved drawings. Ensure that it is readily
accessible for operation & maintenance.
Ensure valve disc does not interface with the operation of other system components
adjacent to the butterfly valve.
If the valve is hard to close, it may be due to debris lodge in the sealing area. This
can be corrected by backing-off the hand wheel and closing it again several times if
necessary. Don’t force the valve to seat by applying a wrench to hand wheel. This
may distort the valve components or scratch the sealing surfaces.
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 00
INSTALLATION, TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Date :
Page 10 of 13
The inlet & outlet piping of the valve shall be properly supported to prevent
excessive stress to the valve body. Do not use the valve body to support pipeline
position as it may result in distortion of the valve body.
Prior to commissioning, ensure that all instruments (if any) to be used during the
commissioning shall be calibrated. Calibration certificates shall be available.
Ensure that all installed External Fire Hydrants & Valves have been installed as per
the approved shop drawings, manufacturers’ recommendation.
Piping system has been tested for leaks. Approval for all preliminary inspections
shall be available during the commissioning stage.
Ensure all External Fire Hydrants have been installed & fix properly with the
correct alignment & spacing.
Ensure firmness & tightness of supports prior to Commissioning of the Fire
Hydrant.
Verify that the external Fire Hydrant shall be easily accessible.
Verify that the hydrant has been fitted with maintenance record tag.
Verify that signage has been provided that clearly indicates the location of the fire
hydrant.
Simulate fire conditions by opening a valve.
Verify that all water flow alarm & valve monitoring system switches operate
correctly.
Verify water pressure & flow at the hydrant.
Connect a fire hose & open the fire hydrant valve. The water throw shall be at least
20 meters.
8.0. ATTACHMENTS