METHOD STATEMENT For Mobilization of Temporary Facilities and Utilities
METHOD STATEMENT For Mobilization of Temporary Facilities and Utilities
METHOD STATEMENT For Mobilization of Temporary Facilities and Utilities
METHOD STATEMENT
for the Mobilization of Temporary
Facilities and Utilities
1
JAVTolentino
Project: Owner: Revision No:
TABLE OF CONTENTS
Pages
1. INTRODUCTION …………………………………………………………………………… 3
2. SCOPE ……………………………………………………………………………………….. 3
3. PURPOSE ………………………………………………………………………………………. 3
4. DEFINITION ………………………………………………………………………………………. 3
5. RESPONSIBILITIES …………………………………………………………………………… 4
6. TF AND GENERAL DESCRIPTION ………………………………………………….... 5
7. SEWERAGE AND DRAINAGE SYSTEM ………………………………………… 7
8. POWER SUPPLY AND DISTRIBUTION SYSTEM ……………………………… 8
9. SAFETY FENCE …………………………………………………………………………… 9
10. MEDICAL CLINIC …………………………………………………………………………… 9
11. FUEL SUPPLY …………………………………………………………………………… 9
12. INTERNAL ROADS ………………………………………………………………………….. 10
13. REINSTATEMENT TO ORIGINAL CONDITION ………………………………………… 10
14. WORK PROCEDURE …………………………………………………………………………… 10
15. EQUIPMENT AND TOOLS ………………………………………………………………… 13
2
JAVTolentino
Project: Owner: Revision No:
1. INTRODUCTION:
This procedure defines the work method for Installation of Temporary Facilities and
Utilities for the Construction of Tilal Al-Narjis Project.
2. SCOPE:
The scope of this document is to establish the Construction of Temporary Office Facility
and Utilities of the Company Project Management Team including Contractor work forces
to performed the Construction of Tilal Al-Narjis Project. Contractor shall maintain and
provide adequate office facility, utilities and services to accommodate the Project
Management Team and Contractor work forces. Shall maintain continuous operation and
maintenance and catering work and removal of facilities after completion of Construction
Project. Temporary facilities shall support the field management of the project from initial
mobilization through to demobilization upon completion of the project. This facility shall
be in accordance with the Project specifications and Safety regulations.
3. PURPOSE:
This Method Statement covers the Construction and Installation of Temporary Facilities,
Clinic, Sanitary facilities, Mosque, Parking areas, Fence, Electrical supply connection and
wirings, Firefighting system, Air condition installation, Water distribution, Sewage disposal
and associated excavation, concrete work, erection and backfilling and final connection to
the system and associated plumbing works.
4. DEFINITIONS:
3
JAVTolentino
Project: Owner: Revision No:
5. RESPONSIBILITIES:
► Project Director
• Regularly meeting with clients, third parties and project managers to report
progress.
• Monitoring progress, providing financial control and ensuring project quality.
• Devising cost-effective plans and methods to enable effective completion of the
project.
• Ensuring necessary permits and legal papers are secured prior to project
commencement.
• Making strategic decisions and providing the necessary leadership and direction for
teams of project managers to implement those decisions.
► Construction Manager
• Responsible for the implementation of this method statement and to ensure the
progress works are in accordance with the schedule and specifications and they have
all necessary resources available to complete the work.
► QA/QC Manager
• Responsible for the quality audits to ensure the progress works are in accordance
with the schedule, specifications and standards in completing the work.
► HSE Manager
4
JAVTolentino
Project: Owner: Revision No:
► Logistic Manager
• Shall be responsible for all materials and equipment resources for the Construction
of Temporary Facilities and Utilities.
• Shall be responsible to maintain resources are ready to use during construction
activities.
► Site Engineer
► Safety Officer
• Shall be responsible to monitor and to ensure that the safety plan is being
implemented at site. Responsible for the safety measures at site, safety regulations
strictly followed as per Company Standards.
• Shall have responsibility to monitor during lifting operations activity at site.
• Monitor and check all tools and equipment gears prior for lifting operations.
• Visually check the set-up location of crane prior for lifting for unsafe condition or
unsafe act.
• Shall be available at site during lifting and rigging activities.
► Surveyor
• Responsible for carrying-out surveying work activities. Ensure all required markings
are properly correct. Keeping data records of survey and shall submit reports.
► Discipline Foreman
5
JAVTolentino
Project: Owner: Revision No:
6.1.2. Area covered of Temporary Facility and the Contractor Install the Facilities
as detailed on approved drawings.
6.3. Utilities
6
JAVTolentino
Project: Owner: Revision No:
• Contractor shall provide portable fire extinguisher for safety requirement and
clearly marked for easy access when required during emergency.
• Smoke detectors will be placed as per safety requirements.
• One portable fire extinguisher place near entry exit doors.
• Safety officers will continuously monitor the hazards, associated with the
storage of combustible, flammable storage, to enhance the associated risk
level is maintain very low.
6.4. Mosque
Contractor shall provide paved parking area and Shed. Ensure constructed
parking/shed as per drawing layout plan.
6.6. Sidewalk
Install and fixed sidewalk to provide a safe path for people to walk. Ensure
installation as per drawing layout plan.
7
JAVTolentino
Project: Owner: Revision No:
Contractor shall provide transport of sewage generated from Temporary Facilities via
vacuum trucks then utilize through direct point of approved disposal area.
8
JAVTolentino
Project: Owner: Revision No:
• Contractor shall responsible for the calculation of electrical loads use in the
facilities to ensure power generators adequate for power supply.
On receipt of the Diesel Generator Set and accessories at site, necessary precautions
shall be taken for unloading, shifting, as follows:
• All materials received at site shall be ensured that are as per delivery note.
• Ensure that all Equipment used at site are free from any damage or deformity
of any kind. Any damages observed shall be repaired suitably.
• Any discrepancies, damage etc., found will be notified and reported for
further action.
• Ensure all civil works are completed for the area to carry out the installation.
• After the activities under the general installation procedures are completed,
the unit shall be loaded from the storage place, by the suitable loader Forklift
or crane, to shift the respective generator location.
• Proper care to secure units, while above shifting loading/unloading as well as
placing shall be carried out with at most care and precautions as required for
the safe operation.
• Diesel Generator Set will be off loaded to the place nearest to the installation
and protected properly from dust & environment, etc.
• Prior to installation, the foundation will be checked for cleanliness and level.
• Ensure that the installation of Diesel Generator Set is carried out in
accordance with manufacturer’s recommendations.
• Install the rubber isolator as per manufacturer recommendations.
• Main Distribution Board will be installed and connected to other sub panels,
Power Distribution work shall be done to facilitate the site.
• Required power and control termination shall be carried out.
• The contractor shall provide and install chain link fence and diagonal support shall be
installed at end point and corner points of posts.
• Install fence shall be provided with tension wire rod to fix tightening of fence, other
accessories provided as needed.
Gates elements shall be provided and install based on detailed location approved
plan.
• The contractor shall provide adequate lightings coverage of the Facilities.
9
JAVTolentino
Project: Owner: Revision No:
• Contractor shall provide Diesel tanker for Fuel distribution system shall be designed
so as to supply diesel to power generators and equipment. Diesel tankers shall be
refilling the fuel in certain interval when it is idle after changeover is done.
The contractor shall be responsible for removal of all installed facilities and underground
utilities after completion of the project and all areas covered on the site Facilities restored
on the original condition.
14.1. Materials
11
JAVTolentino
Project: Owner: Revision No:
• Lifting chains, wire rope slings, hooks and shackles must be checked of
competent personnel.
• Erect all bracings members as per drawing. Make alignment of structure with
suitable tools and tackles like chain puller, guy ropes jacking systems etc., as
appropriate and safe. Checking the verticality and centering of columns.
Complete structure erection in the similar manner.
14.5. Telecommunication
• Contractor shall supply, installation, testing for cables line network for data
and telephone for office facilities.
14.5. Specialties
12
JAVTolentino
Project: Owner: Revision No:
• Excavator/JCB
• Skid loader
• Bull Dozer/Loader
• Trucks/Mini trucks/Pick up
• Water Truck/Water pump
• Boom Truck/Trailers
• Crane
• Transit Mixers
• Concrete Vibrators and Power tools
• Roller compactor/Plate compactor/Jumping compactor
• Power Generators
• Welding machine
• Air compressors
13
JAVTolentino