0% found this document useful (0 votes)
115 views13 pages

Scheduling A Material Requirement Planning (MRP)

This document provides steps for scheduling a material requirement planning (MRP) run. It instructs the user to (1) select the Schedule MRP Runs tile to open the app, (2) choose New and enter "MRP for SG224" as the job name, and (3) select parameters including plant 1010, material SG224, and single run recurrence pattern before (4) scheduling the MRP run.

Uploaded by

Mahlaqa Noor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
115 views13 pages

Scheduling A Material Requirement Planning (MRP)

This document provides steps for scheduling a material requirement planning (MRP) run. It instructs the user to (1) select the Schedule MRP Runs tile to open the app, (2) choose New and enter "MRP for SG224" as the job name, and (3) select parameters including plant 1010, material SG224, and single run recurrence pattern before (4) scheduling the MRP run.

Uploaded by

Mahlaqa Noor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

Scheduling a Material Requirement Planning (MRP)

1
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

Would you like to know how a production planner schedules a material


requirement planning (MRP)?

If so, follow this interactive tutorial.

(1) To open the app, select the Schedule MRP Runs tile.

2
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(2) Choose New.

The job template Material Requirements Planning (MRP) has been


selected for you.

3
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(3) In the Job Name field, enter MRP for SG224 and press Enter.

Ensure that Start Immediately has been selected.

This has been selected for you.

4
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(4) To display parameters, select the scroll bar to scroll down.

(5) In the Plant field, enter 1010 and select the Material field.

5
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(6) In the Material field, enter SG224 and press Enter.

(7) Select Changed BOM Components.

6
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

Select planning mode 1.

This has been selected for you.

(8) To enter scheduling parameters, select the scroll bar to scroll up.

7
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(9) Choose Define Recurrence Pattern.

Ensure that Start Immediately is selected.

This has been selected for you.

8
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(10) To select a recurrence pattern, open the list.

(11) Choose Single Run.

9
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(12) Choose OK.

(13) Choose Schedule.

10
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(14) Choose Go to refresh the application jobs table.

The new job you have scheduled has been added to the application jobs
table.

11
SCHEDULING A MATERIAL REQUIREMENT PLANNING (MRP)

(15) To return to the launchpad, choose Home.

You have successfully scheduled a material requirement planning (MRP).

This concludes the interactive tutorial.