Project ManagementLecture Six

This document contains lecture slides on project management from Dr. Mahmoud Malek and Dr. Asmaa Soliman of the Mechanical Engineering Department at Higher Technological Institute in 10th of Ramadan City. The slides provide examples and solutions for using activity-on-arrow diagrams to analyze project schedules, including determining total project time, critical paths, early and late start and finish times, and float.

Uploaded by

Omar Mobarez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views7 pages

Project ManagementLecture Six

This document contains lecture slides on project management from Dr. Mahmoud Malek and Dr. Asmaa Soliman of the Mechanical Engineering Department at Higher Technological Institute in 10th of Ramadan City. The slides provide examples and solutions for using activity-on-arrow diagrams to analyze project schedules, including determining total project time, critical paths, early and late start and finish times, and float.

Uploaded by

Omar Mobarez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

Higher Technological Institute (HTI), Mechanical Engineering

10th of Ramadan City Department

Project Management
MNG 201
Lecture Six
Second Term (2021- 2022)
71 Dr. Mahmoud Malek
Dr. Asmaa Soliman

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
Solved Examples on Activity On Arrow (A.O.A)
72

Ex (1):
 A project of installing new Cabinets, Based on the
data given below:
1. Draw an arrow diagram
2. Determine The Total Time of The Project
3. Determine The Critical Paths(s)
4. Determine the ES, EF and Free Float for all
activities
5. Draw Bar Chart for Critical Path Only.
6. If Day 18 Nonworking day, what is the total time
with drawing

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
73
Solution

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
Solved Examples on Activity On Arrow (A.O.A)
74

Ex (2):
 A project of installing new Cabinets, Based on the
data given below:
1. Draw an arrow diagram
2. Determine The Total Time of The Project
3. Determine The Critical Paths(s)
4. Determine the ES, EF and Free Float for all
activities
5. Draw Bar Chart for Critical Path Only.
6. If Day 18 Nonworking day, what is the total time
with drawing

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
75
Solution

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
Quiz on Activity On Arrow (A.O.A)
76

Quiz
 A project of installing new Cabinets, Based on the
data given below:
1. Draw an arrow diagram
2. Determine The Total Time of The Project
3. Determine The Critical Paths(s)
4. Determine the ES, EF and Free Float for all
activities
5. Draw Bar Chart for Critical Path Only.
6. If Day 18 Nonworking day, what is the total time
with drawing

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman
77
Solution

Higher Technological Institute (HTI), 10th of Ramadan City.


Project Management, Dr. Mahmoud Malek, Dr. Asmaa Ahmed Soliman