Project ManagementLecture Six
Project ManagementLecture Six
Project Management
MNG 201
Lecture Six
Second Term (2021- 2022)
71 Dr. Mahmoud Malek
Dr. Asmaa Soliman
Ex (1):
A project of installing new Cabinets, Based on the
data given below:
1. Draw an arrow diagram
2. Determine The Total Time of The Project
3. Determine The Critical Paths(s)
4. Determine the ES, EF and Free Float for all
activities
5. Draw Bar Chart for Critical Path Only.
6. If Day 18 Nonworking day, what is the total time
with drawing
Ex (2):
A project of installing new Cabinets, Based on the
data given below:
1. Draw an arrow diagram
2. Determine The Total Time of The Project
3. Determine The Critical Paths(s)
4. Determine the ES, EF and Free Float for all
activities
5. Draw Bar Chart for Critical Path Only.
6. If Day 18 Nonworking day, what is the total time
with drawing
Quiz
A project of installing new Cabinets, Based on the
data given below:
1. Draw an arrow diagram
2. Determine The Total Time of The Project
3. Determine The Critical Paths(s)
4. Determine the ES, EF and Free Float for all
activities
5. Draw Bar Chart for Critical Path Only.
6. If Day 18 Nonworking day, what is the total time
with drawing