Curbstone Method Statment
Curbstone Method Statment
Purpose.
To Enhance the knowledge and technical skills for the staff, workmen involved in the
activities associated with the Curbstone works incorporating the specific project
requirements.
Scope.
The method statement will provide information regarding the pre-work requisites,
sequence of works, the right workmanship and things need to consider prior during
Curbstone Works.
Storage of Materials.
Proper handling during delivery and transpiring to the site is required to avoid
damages such as chipped or broken edges, scratch, cracks etc.
Materials to be stored in dry area to protect from color variation due to
moisture content if being wet by water.
Accessories such as grout, cementitious material for mortar, mechanical bolts
and anchor bolts need to be keep in dry area.
Ensure the proper handling and safe keeping of the material in site.
Surface Preparation and Setting out.
Prior to start any installation, surface preparation & setting out is required. For
surface preparation are must be clean, sound and roughness accordingly if
installation required mortar bed.
Surveyor to provide the surveyor marking for the correct layout based on
approved shop drawing and to be checked by Site Engineer.
QA/QC Engineer to verify the surface preparation & layout before offering to
consultant inspection.
Holes for dowel bar & bolts must be done accordingly with proper cleaning and
hole depth are being checked based on the approved drawing.
Curbstone installation.
Responsibility.