Making Best Use of Long Life Pavements in Europe Phase 3 - A Guide To The Use of Long-Life Rigid Pavements
Making Best Use of Long Life Pavements in Europe Phase 3 - A Guide To The Use of Long-Life Rigid Pavements
Making Best Use of Long Life Pavements in Europe Phase 3 - A Guide To The Use of Long-Life Rigid Pavements
net/publication/331224543
CITATIONS READS
0 498
8 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by László Gáspár on 18 March 2019.
Phase 3:
A Guide to the use of Long-Life Rigid Pavements
BRRC
TABLE OF CONTENTS
Executive Summary........................................................................................................iii
1. Introduction ............................................................................................................1
2. Traffic Assessment ................................................................................................4
3. Design and construction .......................................................................................7
3.1 Types of rigid pavements ......................................................................................7
3.2 Design concepts ...................................................................................................8
3.3 Design parameters................................................................................................9
3.4 Construction practice ..........................................................................................13
4. Assessment and Upgrading ................................................................................16
4.1 Assessment ........................................................................................................16
4.2 Upgrading ..............................................................Error! Bookmark not defined.
5. Maintenance ............................................................... Error! Bookmark not defined.
5.1 Pavement categories .............................................Error! Bookmark not defined.
5.2 Failures ..................................................................Error! Bookmark not defined.
5.3 Maintenance strategies ..........................................Error! Bookmark not defined.
5.4 Condition criteria for assessing the requirement for maintenance .................Error!
Bookmark not defined.
6. Economics............................................................................................................40
7. Research needs....................................................................................................41
8. Recommendations ...............................................................................................42
9. Summary...............................................................................................................46
10. References............................................................................................................47
Appendix A: National ReportS ............................................ Error! Bookmark not defined.
A1. Austria............................................................................ Error! Bookmark not defined.
A2. Belgium .......................................................................... Error! Bookmark not defined.
A3. Czech Republic.............................................................. Error! Bookmark not defined.
A4. France ............................................................................ Error! Bookmark not defined.
A5. Germany......................................................................... Error! Bookmark not defined.
A6. Greece............................................................................ Error! Bookmark not defined.
A7. Hungary.......................................................................... Error! Bookmark not defined.
A8. The Netherlands ............................................................ Error! Bookmark not defined.
A9. Poland ............................................................................ Error! Bookmark not defined.
A10. Switzerland .................................................................. Error! Bookmark not defined.
A11. United Kingdom........................................................... Error! Bookmark not defined.
FEHRL
FEHRL Report 2006/x ii
ELLPAG Phase 3 Report
FEHRL
FEHRL Report 2006/x iii
ELLPAG Phase 3 Report
Executive Summary
During 1998/99, the Western European Road Directors (WERD), now called the
Conference of European Directors of Roads (CEDR), asked its members for topics of
interest affecting the European road network, with the aims of identifying any knowledge
gaps and initiating research. Long-life pavements (LLPs) was one of the topics suggested
by the UK Highways Agency and was later endorsed by WERD as an appropriate area for
a co-operative approach.
The European Long-Life Pavement Group (ELLPAG) was subsequently established in
1999 as a FEHRL and CEDR Working Group to act as the focal point for determining the
way forward. Members of the Group comprise representatives of research institutes
(FEHRL members) and the UK Highways Agency, representing CEDR.
The original objectives of ELLPAG can be stated chronologically as short-term, medium
term and long-term objectives.
• The short-term objective of the Group was to produce, within 12 months of starting
the formal project, a State-of-the-art Review of current European knowledge on the design
and maintenance of long-life fully-flexible pavements.
• The medium-term objectives are to produce similar state-of-the-art reviews for the
other common pavement types.
• The long-term objective is to produce a user-friendly comprehensive Best Practice
Guidance note on long-life pavement design and maintenance for all the common types of
pavement construction used in Europe.
In 2002, a proposal for a first phase of work undertaken by ELLPAG was approved by
FEHRL and CEDR. Funding was secured from each of the core member’s national road
administrations to participate in this work. Phase 1 was completed in 2004 with the
publication of ‘A guide to the use of long-life flexible pavements in Europe’. The second
phase was completed and published in 2008. This document covers the third phase of
the work and provides guidance on the use of long-life rigid pavements in Europe.
As for the first and second phases, the work in this report has been sub-divided into six
main areas which correspond to the main chapters of this Report: Traffic Assessment,
Design and Construction, Assessment and Upgrading, Maintenance, Economics and
Research Recommendations. The methodology for creating this report mainly involved
each core ELLPAG member providing a National Report covering each of the above
subject areas. These National Reports have then been combined and summarised to
provide the essence of each of the six chapters.
FEHRL
FEHRL Report 2006/x 1
ELLPAG Phase 3 Report
1. Introduction
During 1998/99, the Western European Road Directors (WERD), now called the
Conference of European Directors of Roads (CEDR), asked its members for topics of
interest affecting the European road network, with the aims of identifying any knowledge
gaps and initiating research. Long-life pavements (LLPs) was one of the topics suggested
by the UK Highways Agency and was later endorsed by WERD as an appropriate area for
a co-operative approach.
The European Long-Life Pavement Group (ELLPAG) was subsequently established as a
FEHRL Working Group to act as the focal point for determining the way forward. Members
of the Group comprise representatives of research institutes (FEHRL members) and the
UK Highways Agency, representing CEDR.
Two levels of membership of the Group have been created. Core members are directly
involved in the work of the Group and their representatives attend regular meetings as
required. All core members are from either the FEHRL or CEDR organisations. Associate
or affiliate members are kept informed of the work of the Group and contribute through
supplying information as requested and commenting on draft outputs; these members do
not need to be part of either FEHRL or CEDR.
The original objectives of ELLPAG can be stated chronologically as short-term, medium
term and long-term objectives.
• The short-term objective of the Group is to produce State-of-the-art Review
of current European knowledge on the design and maintenance of long-life
fully-flexible pavements (Phase 1) and semi-rigid pavements (Phase 2).
These reports have been completed.
• The medium-term objectives are to produce similar state-of-the-art reviews
for the other common pavement types.
• The long-term objective is to produce a user-friendly comprehensive Best
Practice Guidance note on long-life pavement design and maintenance for
all the common types of pavement construction used in Europe.
Since then, the Group has progressed to the third phase of the work as shown in Figure
1.1 and is considering rigid pavements. This report is a state-of-the-art review of rigid
long-life pavements.
The Phase 1 Report used the following definition of a long-life pavement. “A long-life
pavement is a type of pavement where no significant deterioration will develop in the
foundations or the road base layers provided that correct surface maintenance is carried
out.” However, during Phase 2 it was recognised that an improved definition was required
that was also appropriate to both semi-rigid and rigid pavements. The revised definition,
that encompasses all pavement types, is as follows.
A well designed and well constructed pavement where the structural elements last
indefinitely provided that the designed maximum individual load and environmental
conditions are not exceeded and that appropriate and timely surface maintenance
is carried out.
FEHRL
FEHRL Report 2006/x 2
ELLPAG Phase 3 Report
Phase 1:
Review of Fully
Flexible LLPs
Research
Rigid LLPs
TIME
Phase 3:
Review of Rigid
LLPs
Phase 4:
Production of Best
Practice Guide
Rigid pavements comprise a concrete layer, the main structural element, laid onto a
bound or unbound sub-base layer. In some countries, a thin asphalt layer is used as a
surfacing layer or as an intermediate layer between the concrete and the sub-base.
Concrete, as a construction material, is relatively strong, durable and stable. The high
stiffness of concrete provides a good distribution of traffic loading leading to low stresses
in the underlying materials. It can be made with a wide range of materials, including
recycled and secondary aggregates and binders, which makes best use of available
materials and contributes to sustainable construction. Concrete is not damaged by vehicle
fire, does not emit harmful fumes, and has a high fire safety factor.
Concrete, however, is subjected to volume changes, i.e. expansion and contraction, due
to shrinkage and temperature variations. The movements in concrete pavements are
either accommodated by providing sufficient space, in the form of joints, or relieved by
cracks, which are usually held tightly closed by the steel reinforcement.
Rigid pavements have been generally used on roads which are likely to be heavily
trafficked, where delays to the travelling public from maintenance are needed to be kept to
a minimum. The amount of rigid pavement on the national road network varies for the
individual European countries. A relatively large amount of rigid pavements, considering
the length of the total national network, is found in Austria and Belgium with 36 and 35%,
respectively, followed by Germany at 25%. France, the Netherlands, Poland, Spain,
Switzerland and the UK have values less than 10%. The limited use of rigid pavements in
FEHRL
FEHRL Report 2006/x 3
ELLPAG Phase 3 Report
Europe is mainly associated with the relatively high initial costs. However, a long-life rigid
pavement with an improved long-term performance can significantly lower the whole life
cost.
The work undertaken during Phase 3 has been sub-divided into five main areas which
correspond to the main chapters of this report: Traffic Assessment, Design and
Construction, Assessment and Upgrading, Maintenance, Economics and Research
Recommendations. The methodology combined reviews of existing documentation and
contributions for each area from the core member participants. Table 1.1 lists the core
ELLPAG members who contributed to the tasks carried out in this Phase. A more detailed
list of the organisations involved in the core group of ELLPAG is given in Appendix B.
DWW (now DVS)– The Netherlands Arthur van Dommelen / Arjan Venmans
TRL – United Kingdom Brian Ferne (Chairman) / Vijay Ramdas / David Gershkoff, Khaled
Hassan & Guy Watts (Secretariat)
FEHRL
FEHRL Report 2006/x 4
ELLPAG Phase 3 Report
2. Traffic loading
The estimation of traffic loading for the design and maintenance of pavements is usually
carried out using a load equivalence relationship of the form given in Equation 2.1; where
L = load equivalence, P = axle load, Pr = reference axle load and n is an exponent relating
the factors which contribute to wear. The value of the exponent n (wear factor) varies
widely between different national design guidelines; in some instances the value of the
wear factor cannot readily be identified as is embodied in a design chart or equation.
n
P
L (2.1)
Pr
For the computation of design loading, traffic wear (or aggressivity) factors are often used.
The load equivalence concept is used to compute average traffic wear. Equation 2.2
illustrates this type of approach where T = design traffic, N = number of loads and
C = wear factor; other factors can be used in this calculation such as lateral wander of
traffic.
T N C (2.2)
A discussion was made in the Phase 1 Report (FEHRL, 2004) of the maximum level of
design traffic for each national design method declared in the ELLPAG questionnaire
responses. There was a wide variation in the maximum traffic design in each country
whereas the designs that were given from each country for these loadings were often
similar. However, much of the variation originated from differences in the reference
standard axle, the exponent of the load equivalence relationship and the legal maximum
axle load in each country.
The range of values for the exponent n of Equation 2.1 for fully-flexible and semi-rigid
pavements for the various member countries is given in the Phase 2 Report (FEHRL,
2009). However, there was only little information in the responses from member countries
for values of the exponent used for long life rigid pavements in Europe.
In the Phase 2 Report (FEHRL, 2009) it is considered that a difference in the exponents of
the load equivalence relationships and average ‘aggressivity’ of vehicles can be related to
the different anticipated deterioration modes in asphalt and hydraulically bound materials.
The onset of deterioration in asphalt, such as deformation or fatigue, is assumed to be
progressive and related to the axle loads on the structure. However, the main mode of
deterioration in rigid pavements is failure caused when high axle loading generates stress
levels that exceed the strength of the concrete. Provided that the stress levels are low, this
type of failure is rare. However if these stress levels are high the fracture within the
material can occur and a sudden onset of deterioration can be seen. Consequently, the
onset of deterioration in hydraulically bound layers is likely to be more sensitive to axle
loads than asphalt layers, hence the use of greater values for the exponent. Some
national design methods consider the different effects of traffic on asphalt and
hydraulically bound layers and others make no difference between the types of pavement
construction.
In France, an exponent of 5 is used for traffic assessment on fully-flexible pavements
whereas a larger exponent value of 12 is used for other pavement types including rigid
pavements.
FEHRL
FEHRL Report 2006/x 5
ELLPAG Phase 3 Report
Table 2.1 Equivalence factors for heavy traffic used in Austria (after RVS 03.08.63, 2008)
motorways 1,00
other roads 0,90
In the UK, sets of wear factors have been produced for use with either maintenance (W M)
or a new design (W N) situation; these are dependent on the class and category of
commercial vehicle but independent of the type of pavement construction. New design
situations include new road and pavement construction projects and road widening
schemes. The wear factors for a new design case are higher than for a maintenance case
in order to allow for the additional risk that arises from the additional uncertainty with traffic
predications for new roads. The standard axle in the UK is less than used in Austria and is
taken as 80kN. The background to the research in deriving the wear factors for use in the
UK is given in described by Atkinson et al. (2006).
The (UK) wear factors given in the HD24 (DMRB 7.2.1) are related to the class and
category of commercial vehicle and are reproduced in Table 2.2.
FEHRL
FEHRL Report 2006/x 6
ELLPAG Phase 3 Report
Table 2.2 Wear factors for commercial vehicles classes and categories in the UK
(reproduced from HD 24 (DMRB 7.2.1))
Commercial vehicle Wear factor
Class Category Maintenance (W M) New design (W N)
Buses and coaches PSV 2.6 3.9
2-axle rigid 0.4 0.6
OGV1
3-axle rigid 2.3 3.4
4-axle rigid 3.0 4.6
3 and 4-axle articulated 1.7 2.5
OGV2
5-axle articulated 2.9 4.4
6-axle articulated 3.7 5.6
OGV1 + PSV 0.6 1.0
OGV2 3.0 4.4
FEHRL
FEHRL Report 2006/x 7
ELLPAG Phase 3 Report
Figure 3.1. Schematic diagrams for URC (left) and CRCP (right)
FEHRL
FEHRL Report 2006/x 8
ELLPAG Phase 3 Report
an un-cracked condition and any induced transverse cracks are kept tightly closed by the
reinforcement.
Jointed rigid pavements suffer from progressive defects occurring at the joints resulting in
increased maintenance costs to joints and slabs. The stresses, from thermal changes and
traffic, are mainly induced at slab corners and edges. Therefore, the use of dowel bars is
essential to distribute loads between slabs. The use of transverse joints can lead to
construction and maintenance difficulties from dowels not functioning properly, causing
joint associated distresses that influence the performance of the pavement.
To overcome the problems associated with transverse joints a CRCP was developed.
CRCP contains continuous longitudinal reinforcement with no internal expansion or
contraction joints. The thermal stresses within the pavement are relieved by transverse
cracks, which are held tightly closed by the reinforcement to give good aggregate interlock
and maintain the structural integrity of the pavement. A CRCP is considered to be
especially suited to areas with poor ground conditions or on heavily trafficked roads where
disruption to traffic for maintenance purposes should be a minimum. The initial
construction cost of a CRCP is higher than that of a jointed concrete pavement, however,
a reduced slab thickness and improved long-term performance can contribute significantly
to a low whole life cost. CRCP is the currently preferred type of rigid pavement in Belgium,
France, the Netherlands, Spain and the UK.
The concept of a continuously reinforced concrete has been used as a continuously
reinforced concrete base (CRCB) with a thick asphalt surfacing of 10cm. Due to the
relatively thick asphalt layer, which contributes to the structural capacity of the pavements,
CRCB is classified by the ELLPAG members as a semi-rigid pavement.
FEHRL
FEHRL Report 2006/x 9
ELLPAG Phase 3 Report
There are a variety of approaches to rigid pavement design currently used by the ELLPAG
members. For example, the UK has developed a suite of thickness curves for different
foundation types, concrete strengths and for different cumulative traffic loadings. The
Netherlands and France have developed analytical design tools for the calculation of the
pavement thickness in relation to the fatigue at the base of the pavement, concrete
strength and stiffness, crack width and spacing, and the amount of steel reinforcement.
Other member countries specify a range of concrete thicknesses in relation to the traffic
loading.
3.3.1 Traffic
The traffic parameters in the national road guidelines relating to the design of rigid
pavements are maximum axle load, standard design axle load, the design period and the
maximum cumulative traffic loading. The maximum axle load for the different countries
ranges between 105 and 130 kN, with the highest value being specified in Belgium,
France and Spain. The range of standard axles used to calculate cumulative traffic loading
is from 80 to 130 kN, with the highest value for France and the lowest for the UK. The
Netherlands adopts a different approach by designing to a spectrum of axle loads, where
50% are greater than 60 kN, 10% are greater than 100 kN and 0.1% are greater than 200
kN. The majority of the countries design concrete roads for a thirty to forty year life.
A comparison of the design criteria, Table 3.1, shows that most countries design on a
cumulative number of standard axles, although the equivalent standard axle load (ESAL)
varies between countries. Belgium uses other design criteria of an annual daily traffic
(ADT) flow. Design criteria in million standard axles (msa) with maximum national values
of 80 and 400msa are used in Austria and the UK, respectively. The increased maximum
cumulative traffic for design in the UK takes into account the potential damaging effect
from increased heavy good vehicles (HGV) axle loads.
Despite the similarity of traffic loading specification in many countries, it is not easy to
make a direct comparison between them because the variations of ESAL and the
maximum traffic loading within the design period of the pavements.
FEHRL
FEHRL Report 2006/x 10
ELLPAG Phase 3 Report
Country Standard axle (kN) Design period Design criteria for maximum traffic
(year)
Belgium classifies concretes based on their strength at 90 days, whereas the remaining
countries use the 28 day strengths. The majority of the countries use flexural and/or
compressive strength values, whilst France specifies concrete based on the splitting
tensile strength. The design compressive strength varies from 25 to 62.5 MPa for the
different countries and the flexural strength from 3.5 to 6 MPa.
FEHRL
FEHRL Report 2006/x 11
ELLPAG Phase 3 Report
3.3.3 Foundation
In rigid pavements traffic induced stresses are spread over a large area of the subgrade.
Therefore, variation in the subgrade strength is likely to have little influence upon the
structural capacity of the pavement.
When the subgrade comprises very low strength material it is often necessary to improve
the bearing capacity to allow construction of the upper layers. This could be achieved by
the addition of an unbound granular layer, in the form of a capping layer, or by in-situ
stabilisation of the soil. In Austria, the minimum bearing modulus of the subgrade from the
static plate test is 35 MPa and in Switzerland a modulus of 22.5 to 45 MPa is required. In
Spain, for the heaviest traffic the subgrade must be stabilised with cement. Two of the
ELLPAG member countries use capping layers, in the Netherlands the natural soil is
improved with a 50 cm layer of sand, and in the UK a granular capping layer is required
where the California Bearing Ratio (CBR) of the natural subgrade is less than 5%. In
France, the subgrade strength must be more than 120 MPa when heavy traffic is to be
carried.
The sub-base is a platform layer upon which the concrete layer is constructed. The UK
specifies a hydraulically bound material only for use under rigid pavements. This is to
ensure a durable and strong sub-base to resist erosion from the ingress of surface water
through joints and cracks. In France, the sub-base is also a lean concrete, except when
heavy traffic is to be carried. However, owing to frequent erosion problems the recent
trend is to use 9 cm of bituminous material as the sub-base layer for a CRCP. Other
countries, such as Austria, Belgium, and the Netherlands, use an intermediate bituminous
layer of 5 to 6 cm between the concrete and the sub-base.
Countries that allow a variety of sub-base materials are Austria, Belgium, Germany,
Poland and Switzerland. Belgium specifies a 20 cm lean concrete under the most heavily
trafficked roads, with 20 cm unbound sub-bases as an option for less heavily trafficked
pavements. In Spain the situation is similar but with 15 cm of lean concrete under the
most heavily trafficked roads and 20 to 40 cm of unbound granular sub-bases for less
heavily trafficked pavements. Austria, Germany, Poland and Switzerland specify either
bound or unbound sub-bases, with appropriate adjustments to the overlying concrete
thickness. In the Netherlands, an unbound sub-base comprising 25 cm thick of crushed
masonry or crushed concrete aggregate is specified.
FEHRL
FEHRL Report 2006/x 12
ELLPAG Phase 3 Report
35
30
Slab thickness (cm)
25
20
15 29 29 31
27 28
25 26 26 26
22 23
10
0
nd
ic
UK
m
nd
ria
n
ce
nd
an
ar
bl
ai
iu
la
la
st
an
pu
ng
Sp
la
lg
m
er
Po
Au
Fr
er
Be
Re
er
Hu
i tz
th
G
Sw
Ne
ec
Cz
Figure 3.2 shows that the thickness of URC designs ranged between 22cm and 31cm,
with Switzerland having the thinnest slab and the UK having the thickest slab, however,
the UK no longer constructs URC. In France, the Netherlands and Spain the use of rigid
pavement for high traffic loading is limited to CRCP. With the exception of the
Netherlands, Spain and the UK, the design thickness varies between 22 and 28 cm for the
other countries. The thickness values for Switzerland and Belgium were either 22cm or
23cm, whereas the thickness values for Czech Republic, France, Germany, Hungary,
Poland and Austria were between 25 and 28 cm.
The same design parameters, as above, were used to derive a CRCP thickness. The
results from the five ELLPAG member countries which use such designs show that the
CRCP thickness ranged between 20 cm in Belgium and France, and 25 cm in the
Netherlands, Spain and the UK. New designs for CRCP in France show that a CRCP
thickness has been reduced to 17cm when laid on a bituminous sub-base layer of 9cm.
3.3.5 Reinforcement
The main function of the reinforcement in CRCP is to control the formation of cracks and
to hold them tightly closed to ensure high load transfer across cracks and improve the
structural integrity of the pavement. The reinforcement adds to the initial construction cost
but the improved long-term performance and the reduction in pavement thickness make
CRCP cost-effective.
The amount and location of the longitudinal reinforcement greatly influence the width and
spacing of transverse cracks, and hence the performance of CRCP. A low percentage of
reinforcement is mainly associated with large crack spacing and wide crack openings. The
amount of longitudinal reinforcement usually ranges from 0.6 to 0.7% of the concrete
cross section; a reinforcement content of up to 0.85% has been used in Belgium. The
longitudinal reinforcement is generally located in the mid-depth of the concrete slab to
reduce the risk of reinforcement corrosion.
Transverse reinforcement is used, in the range of 0.05-0.1%, to enable locating and fixing
the longitudinal reinforcement as well as eliminating the longitudinal cracks. Transverse
reinforcements are more susceptible to corrosion as they, in many cases, coincide with
FEHRL
FEHRL Report 2006/x 13
ELLPAG Phase 3 Report
transverse cracks. In Belgium, the longitudinal reinforcement bars are located at third-
depth on transverse bars, skewed at 60 degrees. These arrangements result in fine crack
widths and almost no reinforcement corrosion after many years in service.
3.3.6 Joints
For URC, the ELLPAG countries use either transverse contraction joints, or a combination
of contraction and expansion joints. The maximum spacing specified between contraction
joints is 5 m, with the exception of the Czech Republic which specifies a maximum
spacing of 6 m. Expansion joints are specified for use in Austria, Hungary, Poland, Spain
and Switzerland, with Austria and Hungary only specifying their use at the ends of
concrete slabs adjacent to a bridge structure.
Dowel bars are usually used at transverse joints and tie bars at longitudinal joints. The
dimensions of the dowel bars for the different countries range between 2 and 2.5 cm
diameter, and the length either 50 or 60 cm. In developing a new design for long-life rigid
pavements the dowel bars for use in European countries will be required to comply to the
European Standard EN 13877-3 (2004) in terms of bar dimensions and the quality of the
steel.
3.3.7 Terminations
In CRCP most of the longitudinal movement takes place at the ends of the slab. To ensure
that stresses are not transmitted, by the expansion of the slab, to adjacent structures and
pavements, the ends of the CRCP are either restrained by ground beam anchorage
terminations, or accommodated within joints, such as wide flange beams. Both systems
are relatively expensive to construct. Ground anchor beams are regarded as being
maintenance free but are not recommended where the ground conditions are weak. A
wide-flange beam is not so dependent on the ground conditions but requires routine
maintenance to maintain the joint sealant in a satisfactory condition.
FEHRL
FEHRL Report 2006/x 14
ELLPAG Phase 3 Report
concrete layer and foundation, and reducing the risk of freeze-thaw damage and
reinforcement corrosion.
The use of an intermediate asphalt layer between the bottom of the concrete layer and the
top of the sub-base has many advantages including that of providing a cushion to the
movements of the concrete layer and protecting the foundation from erosion. This
technique is specified in Austria, Belgium and the Netherlands. In Germany, a non-woven
fabric material is placed between the sub-base and concrete slab to prevent bonding
between layers and provide a route for under slab drainage. Other countries, such as the
UK, specify only bound sub-bases that provide a durable and non-erodable platform.
Table 3.3. Functional tests and categories of quality control (EN 13877-2)
Concrete strength, thickness and density are the commonly used tests to establish the
quality controls, but they could be carried out in different methods by ELLPAG members. For
example, most of the countries use cores from the finished hardened concrete for the
determination of compressive strength, whereas France determines the tensile strength
from moulded cylinders of material made at the time of construction.
Belgium, the Czech Republic and the UK use cores to determine the thickness of the
concrete. Austria and France use a levelling technique rather than cut cores. The Czech
Republic requires the number of cores given in Category1 whereas Belgium, France and the
UK require the higher number given in Category 2.
FEHRL
FEHRL Report 2006/x 15
ELLPAG Phase 3 Report
The density of concrete is generally obtained from cores. The Czech Republic requires the
number of cores tested to be Category 1, whereas France and the UK require the number of
samples to Category 2. Belgium uses the water absorption test method, which gives an
indication of the concrete density as well as its durability.
Of the remaining functional tests, the determination of Freeze/thaw resistance was cited,
by Belgium. The number of cores sampled is to that given in Category 2. There is also a
functional requirement for the position of the reinforcement in Belgium, which is not a
functional requirement given in EN 13877-2 (2004).
A questionnaire was prepared to gain information on the quality controls used by the
individual member countries of ELLPAG and the results are given in Table 3.4. It should
be noted that most countries operate certain rules/guidance relating to acceptance and
application of the different tests, but for simplicity and brevity of the Table these
rules/guidance are not recorded herein.
FEHRL
FEHRL Report 2006/x 16
ELLPAG Phase 3 Report
4.1 Assessment
The purpose of pavement condition assessment is to determine the structural properties
of a pavement, the extent of present defects and to identify the cause of damage. This
allows decisions to be made in order to:
check if the pavement is of a long-life type,
decide if the existing structure can be upgraded to a long-life pavement, or
find the most effective maintenance solution.
FEHRL
FEHRL Report 2006/x 17
ELLPAG Phase 3 Report
FEHRL
FEHRL Report 2006/x 18
ELLPAG Phase 3 Report
Figure 4.1: Investigation and assessment process (reproduced from HD30 (DMRB 7.3.3))
FEHRL
FEHRL Report 2006/x 19
ELLPAG Phase 3 Report
Small diameter cores should be taken to determine the thickness of the pavement layers.
These can be used for calibrating the GPR and for analysis of the FWD data. Larger
diameter cores should be taken for determining the strength and density of the concrete
slab, or cement bound sub-base, and for assessing the condition of the reinforcement.
Before reinstating the core holes, dynamic cone penetrometer (DCP) testing should be
undertaken to determine the thickness and CBR of the unbound layers.
FEHRL
FEHRL Report 2006/x 20
ELLPAG Phase 3 Report
failed and the process for determining the residual life are presented in TRRL Research
Report RR87 (Mayhew and Harding, 1987).
In Austria an analytical design procedure is available that has served as a base for the
standard design tables. This method may also be used for project level assessment using
data from FWD and possibly laboratory testing on samples cored or sawn from the
pavement, see the Austrian National Report and LItzka et al (1996).
Little or no use is made of the comparison between actual and design traffic loads for
prediction of residual life.
4.2 Upgrading
In the context of this report, the purpose of upgrading is to convert an existing rigid
pavement to a long-life rigid structure, able to withstand future traffic load without any
further damage developing in the structural layers. To reach this objective, strengthening
of concrete pavements is only a realistic option when the existing structure, although of
lighter design than required for a long-life behaviour, is in good structural condition.
Concrete pavements that show structural defects can only be treated to extend the service
life for a determinate period, or be totally reconstructed.
For a good structural condition of a concrete pavement, it is necessary that it is well
designed and built, without inherent flaws, but also that only a part of its bearing capacity
in terms of fatigue loading has been consumed. This implies that upgrading to a long-life
structure, in the sense as described above, should take place well within the structural life
span of the pavement. However, road authorities are used to planning structural
maintenance only after the first signs of structural damage become evident, which is
usually too late to allow upgrading to a long-life pavement.
Only if the possible benefits from a timely upgrading, utilising the existing asset and
reducing the need for future maintenance and the related traffic hindrance, can be shown
in a whole life economic analysis, this situation might change. Although such analyses are
still far from routine procedures in pavement engineering, they seem feasible provided that
good estimates of deterioration rates and life span of maintenance solutions can be given.
Because in the present situation road authorities in most cases choose to let the existing
pavement deteriorate structurally to a state where only a determinate service life
extension or reconstruction are the options, the state of the art descriptions given in the
national reports (Annex A) include much information about maintenance treatments to
extend the service life of jointed concrete pavements and about reconstruction treatments,
many of which result in a semi-rigid or flexible structure. The number of upgrading
treatments that result in a fully rigid long-life pavement is limited.
In this section a general summary will be given of the possible reconstruction and
upgrading treatments mentioned in the National Reports, but the consecutive more
detailed analysis will focus on the treatments that result in long-life rigid pavements.
FEHRL
FEHRL Report 2006/x 21
ELLPAG Phase 3 Report
UK BE HU NL PL AT CH ES CZ DE FR GR
Cracking Y Y Y Y Y Y Y Y Y Y Y NA
Joint damage Y Y Y Y Y Y Y Y Y Y Y NA
Joint filling Y Y Y Y - Y Y Y Y Y Y NA
Surface deterioration Y Y Y Y Y Y Y Y Y Y Y NA
Deflection at mid-slab FWD - FWD - FWD FWD FWD FWD FWD FWD - NA
Vertical deflection differences FWD - FWD FWD FWD FWD FWD FWD FWD FWD - NA
at joints/cracks
Thickness GPR GPR - - - - - GPR - - - NA
Joint movement DG FM - FM - - - - - CD - NA
Thickness Y - - Y - Y Y Y Y - - NA
Compressive strength, Y - - - - Y - - Y - - NA
fatigue strength
Stiffness - - - - - Y - - - - - NA
NA Not applicable
FEHRL
FEHRL Report 2006/x 22
ELLPAG Phase 3 Report
Asphalt overlays of 50 to 180mm may be Saw Cut and Sealed (SC&S) to prevent
reflective cracking. Similarly thin concrete overlays (<50mm) may be Slot Sealed (SS),
similar to SC&S, except for slot being sawn straight through to underlying joint, and not
shaped.
Summarizing, the upgrading or reconstruction of a rigid pavement can consist of
overlaying the untreated or ‘cracked and seated’ pavement with a concrete or asphalt
layer, with or without a de-bonding layer between the existing pavement and the overlay,
or constructing a new pavement, recycling the old pavement or rubbIising it to serve as a
foundation layer.
Of the overlays, asphalt overlays are used the most frequent, because of less initial
construction costs than that of a rigid overlay. Furthermore, it requires less construction
time, and therefore may reduce user costs during construction. However, the service life is
usually limited due to the tendency for reflective cracking which will ultimately lead to
spalling and pumping (less dominant deterioration modes are permanent deformation,
low-temperature cracking and fatigue cracking). Therefore it may not be the most
economical solution for long-term rehabilitation.
FEHRL
FEHRL Report 2006/x 23
ELLPAG Phase 3 Report
Rubblisation is rarely used, i.e. only when the pavement has deteriorated to such an
extent that other treatment options are no longer viable.
Obviously some of these treatments/activities would only be used at a certain time in the
life of a pavement; e.g. reconstruction and rubbilsation would not be appropriate in the
early life of the pavement but only as it nears the end of its useful life. The different
activities described above, and the period throughout a pavement’s life when they might
be appropriate, are diagrammatically summarised in Figure 4.2.
Routine maintenance
Medium & long term repairs
Asphalt
O l /SC&S/SS
Crack and seat
Concrete overlay
Reconstruction
Rubblisation
Age or Traffic
FEHRL
FEHRL Report 2006/x 24
ELLPAG Phase 3 Report
Table 4.2: Summary of techniques for upgrading and reconstruction of rigid pavements
UK BE HU NL PL AT CH ES CZ DE FR GR
2
Full depth reconstruction (rigid) Y - - Y Y - Y - - - NA
1
Partial reconstruction (rigid) Y Y - - Y Y Y Y - - Y NA
Empirical - - - - - - - - - Y? NA
Mechanistic / semi-empirical Y Y? Y? - Y? Y? Y? Y? Y? - Y? NA
FEHRL
FEHRL Report 2006/x 25
ELLPAG Phase 3 Report
Full depth reconstruction (rigid) CRCP may require a thin surfacing (low noise).
Recycling of concrete or overlaid con- For very heavily deteriorated pavements, where
crete pavement, re-use as sub-base concrete overlay is no longer feasible.
or aggregate for new rigid pavement. Requires new pavement to be constructed.
FEHRL
FEHRL Report 2006/x 26
ELLPAG Phase 3 Report
5. Maintenance
The ultimate purpose of road maintenance is to preserve or restore a road pavement to a
condition where users can travel in a safe and comfortable manner. The maintenance
requirements for determinate life rigid pavements are well understood, but there are no
general explicit maintenance strategies for long-life pavements at this time due to their
limited number. However, in some ELLPAG Member countries detailed maintenance
techniques have been developed, and as the number of LLPs increase firm guidelines
could be established for construction, and perhaps for identifying existing pavements that
exhibit the requirements and characteristics of long-life pavements.
Maintenance operations can be loosely separated into two categories, i.e. non-structural
maintenance normally associated with the upper layers and structural maintenance such
as rehabilitation or strengthening of the pavement. It must be recognised that the optimal
condition responsive maintenance applied to an ailing pavement is strongly dependant on
the ability to correctly diagnose the cause of the degradation observed. In doing so it is
particularly important to remember that although surface and structural deterioration may
occur independently, both can be initiated by degradation in the other; i.e. failure can be
induced in the surface as a result of structural deterioration and vice versa.
Guidance is presented in Appendices A2, A4 and A11 of this report regarding the use of
various damage indicators that can be used to assist in the formulation of maintenance
schedule and condition responsive operations.
Guidance and recommendations for appropriate maintenance operations to combat
degradation are presented in Appendices A1, A2, A3, A4, A8, A9 and A11 (Fine tuning of
technical repairs can be made by taking into consideration the category of road
particularly the traffic and the lane).
In summary, guidance for the specific maintenance of long-life pavements has yet to be
fully established. Indicators can be used to help identify problems and define appropriate
procedures. However, it is important not to become too focussed on these issues at the
expense of basic routine tasks. In other words, engineers should not lose sight of the fact
that long-life pavements, in common with determinate life pavements, are reliant on
certain routine maintenance tasks, such as ensuring the correct function of a drainage
system (see Appendices A2 and A11) and maintenance of sealants at the joints between
adjacent pavement sections to help prevent the ingress of water into the pavement.
FEHRL
FEHRL Report 2006/x 27
ELLPAG Phase 3 Report
Rigid pavements are being used around many road networks, with or without a surface
course, on various types of foundations, for rural roads to motorways, serving urban and
non-urban locations and carrying different traffic compositions and load spectra. Examples
of these are:
Jointed concrete non-doweled slabs without surfacing on low volume rural roads.
A distressed road condition can be assessed by testing and visual inspections that may
provide individual indications of the road’s condition. A combination of one or more these
individual indicators can be conducted, in more or less sophisticated ways, to determine a
global performance indicator or index. Recommendations on the use of combined
indicators were reported be found in the final report of the COST Action 354 (Litzka et al,
2008).
For the different road categories, the condition indicators may be expressed in different
ways. However, importantly, for a given category of road and associated traffic flow, the
indicators will normally be assigned threshold values which when achieved will trigger the
appropriate level of maintenance activity. An interesting example of this is presented in
Appendix A4 (the French National Report) where cracking, pumping and faulting are the
distress indicators taken into account. This process has, as a matter of fact, a built-in
expertise based on past experience and diagnosis.
FEHRL
FEHRL Report 2006/x 28
ELLPAG Phase 3 Report
5.2 Failures
Properly designed and constructed rigid pavements require comparatively little
maintenance or repair. But defects can occur and these will not all have the same
influence on the rate of deterioration of the pavement. For example, some defects evident
at the time of construction may not deteriorate with time and the traffic loading is of little
consequence. However, other defects can lead to deterioration of the pavement and will
inevitable require maintenance to restore the pavement to a satisfactory condition.
Failures in concrete pavements are usually a result of problems associated with one or
more of the following:
Foundation
o Settlement
o Poor drainage
o Water penetration from the surface
o Frost heave
Joints
o Joint sealing failures
o Misaligned and locked dowel bars
o Stepping
o Spalling at arrises
o Compression failure
Slab-related (e.g. related to deterioration of the concrete)
o Cracking
Transverse
Longitudinal
Diagonal
Corner
o Punchouts and punchdowns (predominantly in CRCP)
o Surface spalling and scaling
o Vertical slab movement
Failures of remedial works to joints and the slab which have been carried out
incorrectly or with inappropriate materials.
Examples of joint and joint sealing problems are shown in Figures 5.1 to 5.3. Figure 5.1
illustrates the different types of joint sealant failure which can occur after a period of time
and Figures 5.2.to 5.3 illustrates problems which arise from joints failing to work in the
appropriate manner. Figure 5.4 illustrates a structural failure arising from joint corner
cracking.
Figure 5.5 illustrates dowel bars which have not been aligned correctly and may cause a
joint failure by not allowing the joint to function correctly.
The surface of concrete is generally robust, and deterioration of the concrete from pieces
of material or aggregate breaking away from the surface, either close to a joint or in the
main slab can be an indication of freeze/thaw damage, poor compaction of the material or
problems with the mixture. Once the surface starts to deteriorate, loose pieces of material
may come away and cause a hazard to passing traffic.
FEHRL
FEHRL Report 2006/x 29
ELLPAG Phase 3 Report
a) Adhesion b) Cohesion
Figure 5.1 Examples of joint sealant failure
Figure 5.2 Example of joint arris spalling Figure 5.3 Example of compression
failure (CPMM 2001) failure (CPMM 2001)
FEHRL
FEHRL Report 2006/x 30
ELLPAG Phase 3 Report
Typically, cracks in concrete between 0.5 mm and 1.5 mm wide have the potential to
generate a loss of aggregate interlock across the fracture. Wider cracks are associated
with a complete loss of aggregate interlock and a high potential for failure of the steel
reinforcement where installed.
Cracks in a jointed URC pavement cannot be sustained in most instances, and may
require the reinstatement of the bay.
Transverse cracks, up to 0.5mm wide, typically occur in reinforced rigid pavements but do
not detract from the performance of the pavement. In CRCPs widely separated transverse
cracks increase the probability of reduced aggregate interlock and resulting in increased
stresses within the pavement slab and the potential for rupture of the longitudinal
reinforcement.
Transverse cracks induced at a close spacing and connected by longitudinal cracking can
lead to a localised defect where a block of concrete may become loose. These are
commonly known as a “punchout” where pieces of material break away from the surface
or a “punchdown”, when pieces of material are pushed into the underlying layers. In both
cases pieces of material can be dislodged by passing traffic. Examples of major crack
defects arising from intersected crack patterns and loose blocks of material are shown in
Figure 5.6.
FEHRL
FEHRL Report 2006/x 31
ELLPAG Phase 3 Report
Cracks that are neither transverse nor longitudinal are termed diagonal cracks and are
often associated with slab settlement. These typically occur at locations where there are
large differences in subbase or subgrade support, such as under bridges or over culverts.
In jointed pavements, diagonal cracking may be observed across the corner of a slab,
which is indicative of localised poor support under the concrete; in such cases a void may
form allowing the passage for water that will lead to further deterioration, unless
appropriate maintenance is applied. In a CRCP, diagonal cracking has been observed
coincident with skewed transverse reinforcement; this could lead to a pattern of bifurcate
cracks, but though undesirable it may not develop into a problem.
The development of a longitudinal crack is of greater concern than either transverse or
diagonal cracking as it may be indicative of structural failure of the slab. A longitudinal
crack may also result from the poor positioning, or the omission, of a longitudinal crack
inducer, or the failure of transverse joints to function properly
In general, the failure of a pavement can be attribute to a combination of one or more of
different causes, and with one factor influencing the others, resulting in either surface
deterioration or structural distress. The consequence or evidence of most types of failures
is observable at the pavement surface level. However, failures such as lack of bonding
between layers, water contamination and thickness abnormalities are generally detected
by non destructive techniques such as GPR, Deflectograph, and FWD etc. A selection of
problems in each of the above categories and suggested methods of treatment are
indicated in the following Sections.
FEHRL
FEHRL Report 2006/x 32
ELLPAG Phase 3 Report
FEHRL
FEHRL Report 2006/x 33
ELLPAG Phase 3 Report
In the UK there is a requirement that all concrete running surfaces should be covered with
a thin wearing course system (TWCS), this has to be considered when deciding upon
maintenance treatments.
FEHRL
FEHRL Report 2006/x 34
ELLPAG Phase 3 Report
When structural repairs are deemed to be uneconomic (usually decided by a whole life
costing exercise) rehabilitation or strengthening of the pavement is the preferred
maintenance options, as shown in Figure 5.7.
Figure 5.8 Reconstruction of the ring road Antwerp, using concrete, to provide a long
lasting low maintenance pavement
FEHRL
FEHRL Report 2006/x 35
ELLPAG Phase 3 Report
Consolidation Under-slab grouting (MT) or slab replacement and treat foundation (LT)
Problem Treatment
FEHRL
FEHRL Report 2006/x 36
ELLPAG Phase 3 Report
Problem Treatment
(1)
Transverse cracking See general rule below
Full depth repair with a joint installed (LT)
Full depth repair at crack (LT) , or leave joint locked and convert the crack to a
joint with full depth repair (LT)
Full depth repair (LT)
Rehabilitation/strengthening
(1)
Longitudinal cracking See general rule below
Treat expansion problem
Treat support problem
Rehabilitation/strengthening
(1)
Diagonal cracking See general rule below
Treat foundation problem
Corner cracking Transverse full depth repair (LT) or corner repair (MT)
Slab rocking Full depth bay end replacement (LT) or under slab grouting (MT)
Failure adjacent to Reinstate all unsound material, replace slab if less than half of remaining slab
temporary repair is sound (LT)
Punchouts/punchdowns* Full depth repair (LT)
FEHRL
FEHRL Report 2006/x 37
ELLPAG Phase 3 Report
The “need for intervention” level is nominally between the satisfactory and bad. However,
in practice, the unacceptable threshold of some of the indicators is set relatively higher or
lower depending on the category of road (e.g. motorways, secondary roads). Different
index values may be used to initiate different maintenance operations.
The indices describe the condition of the pavement for a given length of 100m. Indices, for
rigid pavements, exist for the following parameters.
Skid resistance
Unevenness
Slab stepping
Surface defects
Bearing capacity
FEHRL
FEHRL Report 2006/x 38
ELLPAG Phase 3 Report
Table 5.5 presents the relation between the degree of deterioration for
cement concrete pavements and the value of the index.
Bearing capacity. The bearing capacity is determined from deflection
measurements and an expression in the form of an index is related to the
total service life available and the residual service life left. It is to be noted
that the end of the service life (total bearing capacity exhausted) is reached
for a degree of deterioration of 50% regarding fatigue cracking. This level
triggers reinforcement.
A combined global index is also produced and is considered as an indicator connected to
safety. It is a weighted linear combination of the indicators for surface distresses and both
longitudinal and transverse profiles.
Table 5.5. Degree of deterioration of surface distress determined from visual inspection
FEHRL
FEHRL Report 2006/x 39
ELLPAG Phase 3 Report
roughness of the road surface for each of the proposed top layers, the noise generated by
traffic for each of the road surfaces. Qualitative criteria must be quantified by an expert
and are hence subject to a more subjective perception of one or more individuals.
Examples of such criteria are: surface types of adjacent sections, hindrance to traffic
during road works, expected maintenance costs in future. These criteria must be
evaluated by an expert for each of the alternatives.
The classification is achieved by a “multi-decider” process. The calculation of the ranking
uses a multi-criteria method based on the “multi-attribute utility theory” (MAUT). The best
ranking obtained, when taking into account all criteria, will be the optimal solution.
The contribution of each criterion to the overall score of the optimal solution can be
compared to the contribution that criterion to the overall score of all alternative solutions,
as illustrated in Figure 5.3 (alternatives on the horizontal axis, score on the vertical axis,
optimal solution with highest score, each colour represents another criterion and its
contribution to the score of each alternative).
Validation of the software system is obtained by running comparative tests on a certain
number of real or virtual (nevertheless plausible) cases and by comparison of the
computed results with the opinions of a team of experts.
Figure 5.3. Example of determining the optimal score using multi attribute utility theory
(as used in Belgium)
FEHRL
FEHRL Report 2006/x 40
ELLPAG Phase 3 Report
6. Economics
To be provided by LAVOC/EPFL with TRL
Cost benefit analysis is largely complete, e.g. base case scenarios are complete
determined from both English and French construction/maintenance information. Some
sensitivity analyses have been completed. Data requires to be consolidated in a readily
appreciable mode. Some further sensitivity analysis will be undertaken.
It was noted that the potential cost saving from the use of concrete pavements stemmed
from the quality of construction; e.g. properly constructed concrete pavements enjoyed a
long service life and that surface repairs at intervals was all that was required to maintain
them in good condition. However if the pavement was poorly constructed then the
maintenance requirements were substantially greater with associated higher costs; i.e. the
saving is accrued as a result of good practice, which may be achieved at a small cost,
resulting in a longer service life.
It was also noted that a large potential saving would be accrued from reduced user-
delays, as surface maintenance can be carried out at night.
FEHRL
FEHRL Report 2006/x 41
ELLPAG Phase 3 Report
7. Research needs
The primary objective of ELLPAG is to collate and generate knowledge on long-life
pavements. In many cases, these actions assist to satisfy many of the gaps in knowledge
that may be identified within a particular country; however, there are cases where
additional knowledge is required.
The contributors to the ELLPAG project individually identified a number of research needs
in the area of long-life rigid pavements. Some of these have been addressed by one or
more member countries, but several subject areas that merit further work have been
identified from the findings of this study. Many of these research needs are of common
interest to all European countries concerned with extending the durability of their national
road network and reducing operating costs.
Areas for further study can be placed in identifiable groups that can be summarised as
follows.
Pavement Structure
Design
Construction
Quality control
Performance
Maintenance
Economics
Recommendations for future research that address these needs are presented in the next
Section.
FEHRL
FEHRL Report 2006/x 42
ELLPAG Phase 3 Report
8. Recommendations
Pavement structure
Develop standard techniques for assisting in the identification of a rigid pavement with the
potential to be upgraded into a long-life pavement. This can be the basis for the decision
whether upgrading (strengthening) or reconstruction of the existing concrete pavement is
the appropriate measure at a given situation.
Develop an analytical model that considers the different deterioration mechanisms of rigid
pavement. In particular the model should be able to assess the likely degradation resulting
from increased traffic flow, e.g. the damaging effects of multi-axle heavy goods vehicles.
The model should be able to predict the long term performance of a long-life rigid
pavement and also help to design the upgrading (see also “Design”).
Design
In many countries current rigid pavement design is based on an empirical method
using historic performance data (e.g. as in the UK). Work is required to develop a
suitable analytical method of design for long-life rigid pavements.
The design should take into account material properties, utilise a versatile
approach to optimisation of slab thickness for the given design traffic for
unreinforced and continuously reinforced concrete pavements as well. In the latter
case also the amount and location of reinforcement should be determined. In
addition the design should be sufficiently versatile to relate these factors to
structural performance and cost efficiency to show the difference between
determinate life pavements and long life pavements. This would permit different
countries with differing resources to produce economic designs (that would
compare favourably with determinate life pavement designs).
The design tool VENCON 2.0, Van Leest et al (2005), (as currently used in The
Netherlands) relates concrete thickness and the amount/position of steel
reinforcement for continuously reinforced concrete pavements. This tool covers an
important area of design that could be included in a new analytical design.
Research is required to provide the following.
a. Validation of the design model implemented in VENCON 2.0: the tension
bar model for prediction of crack width and distance needs further
validation.
b. Optimisation of design of reinforcement: the tension bar model
implemented in VENCON 2.0 predicts that the amount of reinforcement
required decreases with decreasing concrete cover. Predictions of crack
width need to be corroborated by observations in test sections.
Also in other European countries analytical design tools for concrete pavement
design have been developed and are in use as various software packages. It is
recommended to start a common project on European level to evaluate and
compare these various tools in order to propose the development of common
European software (a similar attempt has been conducted within the European
AMADEUS-project for flexible pavements some years ago).
FEHRL
FEHRL Report 2006/x 43
ELLPAG Phase 3 Report
Construction
Effective solutions have already been presented for applying and removing the
wearing course.
Develop end performance specifications to be used for the construction of long-life
pavements. More understanding of the materials behaviour are required to allow
the development of such specifications. Because performance specifications,
rather than individual material properties, are central to defining the performance of
the final product, their use allows the wider and more efficient use of primary and
alternative materials. It could also be used for the prediction of the structural
residual life
Improve the construction quality of the complete pavement starting from the sub-
base and base layers. Most causes for the deterioration of concrete pavements
are coming from poor quality of the underlying construction and not from the
concrete layer quality itself. Investigation of the actual deterioration more in detail
is necessary in order to get hints for improvements, especially for long life
pavements.
Generate a guidance document for continuously reinforced concrete pavement
individual details in respect of the execution of construction work for a basic
renewal on maintaining the flow of traffic needs to be looked into.
Investigate in detail the use of asphalt interlayers in concrete roads (unreinforced
and continuously reinforced concrete pavements), as different applications are
used throughout Europe based on local experience.
Investigate especially the bonding (amount and durability) between and concrete
and asphalt layer and between concrete and other base layers (like cement
stabilised or unbound coarse layers) to decide to what extent it can be taken into
account for design purposes.
Optimisation of exposed aggregate concrete surfaces with respect to noise
reduction and skid resistance as well. Also share the experience with these
techniques between European countries.
Investigation on effective use of thin surface courses (long term bonding, bridging
joints or cutting at joints etc.) for new pavements and restoration.
Investigate the problem of skid resistance of concrete surfaces in tunnels
compared to adjacent sections outside.
Quality Control
Assess the importance of supervision, the use of good quality materials and
construction tolerances etc for the successful construction and performance of
LLPs.
Develop a quality control standard for the construction of long-life rigid pavements
Performance
Investigate the compatibility of rigid pavements with other pavement types.
Concrete pavement can be constructed as inlays or used in widening schemes
FEHRL
FEHRL Report 2006/x 44
ELLPAG Phase 3 Report
Maintenance
Development of a generic maintenance strategy for long-life rigid pavements, with
particular regard for European countries. (Implementation documents taking into
account specific national requirements, resources and practices should be
developed by the individual countries.)
Economics
Develop a method for undertaking in depth assessments of the benefits of long-life
(rigid) pavements to existing highway networks. Establish a whole life cycle
method for cost comparisons of different pavement designs including long-life
pavements, to be used in Design & Construct contract specifications (these
methods will include all long-term damage in the assessment of pavement
suitability). This should take account of current economic models and up to date
information. The model should consider and compare the different types of long-
life pavements. The model should be sufficiently flexible to suit the requirements,
resources and practices of individual countries.
FEHRL
FEHRL Report 2006/x 45
ELLPAG Phase 3 Report
knowledge gap between laboratory testing and the observed performance of in-
service pavements.
Nevertheless, accelerated testing of a long life pavement (LLP) presents several
advantages and disadvantages when compared to a study of a determinate-life
pavement.
The classical distress mechanisms considered by APT are mainly related
to the structural performance, but the type of deterioration to be expected is
quite different for an LLP
The number of axle loads applied during an APT test does not usually
exceed 1 million. Testing of determinate-life pavements overcomes this
drawback by increasing the load level, but it is not so clear that can be
done for LLP
The ability to exercise a degree of control on the variability of factors that
influence performance, help simplify the understanding the concept and
principals governing pavement deterioration
Ageing of a road pavement is difficult to simulate, and this is especially
important for LLP. More information is required.
Overcoming the drawbacks would enable a new and efficient way to understand
LLPs, evaluate new, improved, materials and thereby generate improved designs.
FEHRL
FEHRL Report 2006/x 46
ELLPAG Phase 3 Report
9. Summary
To be completed after the remainder of the report is complete.
FEHRL
FEHRL Report 2006/x 47
ELLPAG Phase 3 Report
10. References
Atkinson V M, Merrill D, and Thom N, (2006). Pavement Wear Factors. TRL Project
Report number PPR066. Transport Research Laboratory, Wokingham, UK.
British Cement Association (BCA), (1994). Concrete pavements for highways.
Publication document number 46.030. BCA, UK.
Centre de Recherches Routières (CRR). (Belgian Road Research Centre, BRRC)
Bruxelles. Wavre, Belgium.
CRR (1985). Code de bonne pratique pour le dimensionnement des chaussées à
revêtement en béton de ciment. Recommandations C.R.R. – R 57/85
CRR (2005). Code de bonne pratique pour l’exécution des revêtements en béton.
Recommandations C.R.R. – R 75/05.
CRR (2006). Aide multicritère au choix des revêtements routiers. Publication de
synthèse C.R.R. – F 42/06.
Vl (2001). Catalogus – Schade aan wegverhardingen, Ministerie van de Vlaamse
Gemeenschap, administratie Wegen en Verkeer, i.s.m. OCW.
(http://wegen.vlaanderen.be/documenten/publicaties/schade.php)
Design Manual for Roads and Bridges (DMRB). The Stationary Office, Norwich.
HD24: Traffic Assessment (DMRB 7.2.1)
HD29: Structural assessment methods (DMRB 7.3.2)
HD30: Maintenance assessment procedure (DMRB 7.3.3)
Forum of National Highway Research Laboratories (FEHRL). Brussels, Belgium.
FEHRL (2004). A guide to the use of long-life fully-flexible pavements. ELLPAG
Phase 1 Report. FEHRL Report 2004/1.
FEHRL (2008). A guide to the use of long-life semi-rigid pavements. ELLPAG Phase
2 Report. FEHRL Report 2008/1.
Mayhew H C and Harding H M (1987). Thickness design of concrete roads. TRRL
Research Report RR87. Transport Research Laboratory, Wokingham, UK.
Litzka J, Leben B, La Torre F, Weninger-Vycudil A, et al (2008). The Way Forward for
Pavement Performance Indicators across Europe. COST Action 354. FSV,
Germany.
Litzka J, Molzer Ch, and Blab R (1996) Modifikation der Österreichischen Methode zur
Dimensionierung des Straßenoberbaus (Modification of the Austrian Method for
Pavement Design). Bundesministerium für wirtschaftliche Angelegenheiten,
Straßenforschung, Heft 465, 1996
Wistuba M, Steigenberger J and Pichler R (2004). Joint-Design On Concrete
Motorways In Austria. Proceedings 9th International Symposium on Concrete
Roads, ISBN 975-8136-20-8, Istanbul, 2004.
Comité Européen de Normalisation (CEN). Brussels, Belgium.
EN 13877-2 (2004). Concrete pavements. Functional requirements for concrete
pavements.
FEHRL
FEHRL Report 2006/x 48
ELLPAG Phase 3 Report
FEHRL