Sip5 Apn 084

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

SIPROTEC 5 – Point on Wave

Adjustment during
Commissioning (APN-084)
www.siemens.com/siprotec
SIPROTEC 5 Application
SIPROTEC 5 – Point on Wave: Adjustment during Commissioning

SIPROTEC Application
SIPROTEC 5 – Point on Wave: Adjustment
during Commissioning
APN-084, Edition 1

Content

1 SIPROTEC 5 – Point on Wave: Adjustment during Commissioning ........................................................................ 3


1.1 Introduction ...................................................................................................................................................... 3
1.2 Application Data ................................................................................................................................................ 3
1.3 Analyzing the first PoW close cycle ..................................................................................................................... 4
1.4 Conclusion ........................................................................................................................................................ 7

APN-084 2 Edition 1
SIPROTEC 5Application
SIPROTEC 5 – Point on Wave: Adjustment during Commissioning

1 SIPROTEC 5 – Point on Wave: Adjustment during


Commissioning
1.1 Introduction
Based on the Point on Wave (PoW) function in SIPROTEC 5, applied for closing of a capacitor bank, the checks
and adjustments required during commission are described here. Only the fundamental aspects of the PoW
are considered here, the influence on closing time from e.g. supply voltage or temperature are not
considered. These must be checked separately.
The principle source of data for the adjustments described here will be the fault log that is triggered during
the closing process. The recorded waveforms and binary traces can be used to support and check the data
and adjusted settings.

1.2 Application Data


In this description an ungrounded capacitor bank must be closed with PoW functionality. The corresponding
setting under “General” is shown below. The closing angles are pre-configured according o the application,
here 30° for the leading 2 phases and 120° for the last phase:

The first two poles (CA) close when the VCA voltage is zero (30° of reference voltage, ph A). The last pole, B,
closes at 120° which is the zero crossing of the VB voltage. The diagram below shows the voltage on the
capacitor with near perfect closing. The transient has only a small magnitude.

The circuit breaker data for closing is applied as follows:

Edition 1 3 APN-084
SIPROTEC Application
SIPROTEC 5 – Point on Wave: Adjustment during Commissioning

The closing and pre-arcing times have been set using the data provided for the circuit breaker as shown
above.

1.3 Analyzing the first PoW close cycle


After the close cycle is completed the fault log should be retrieved from the device. The PoW information in
the log can be checked in two steps.
1. Closing time (time until reference contact or auxiliary contact indicated CB has mechanically closed)
2. Make time (time until primary signals, current or voltage, indicate that electrical contact of the CB has
been made)

1.3.1 Closing Time


In the fault log find the following entries (note: if the values are not shown in the log, check the configuration
settings):

As there are no compensating factors via transducers in this application (e.g. closing voltage magnitude,
temperature etc.) the calculated closing time equals the set closing time (e.g. 62.4 ms for phase A). The
measured values (e.g. 63.364 ms for phase A) may not deviate severely so that the  closing time (0.963 ms
for phase A) remains small (not more than approx. 3 ms, for larger values check the CB data and settings).

APN-084 4 Edition 1
SIPROTEC 5Application
SIPROTEC 5 – Point on Wave: Adjustment during Commissioning

The measured closing time is derived from the reference contact or if this is not available from the auxiliary
contact. In this example there is no reference contact, so that the following binary signals are responsible for
the measured closing time:

The diagram below from the manual shows the closing time: start, stop and adjustment. For the adjustment
of the closing time the following parameters are used:

The “ closing time” measured will be subtracted from the set “Time delay ref.contact”. This is the reason why
settings may be negative when the “ closing time” was positive. See example calculation under heading
“Adapting the Reference contact delay”.

1.3.2 Make Time


The Make time is most important as it determines the point in time at which current starts flowing via the
circuit breaker. The extract from the fault log below shows the determined valued:

Edition 1 5 APN-084
SIPROTEC Application
SIPROTEC 5 – Point on Wave: Adjustment during Commissioning

The calculated make time is the set closing time minus the pre-arc time. The pre-arc time depends on the
voltage across the CB contacts as the breaker is closing. As the PoW always closes at the same point on wave
this is approximately the same every time. The pre-arc time is therefore not used to compensate the
measured make time. The parameters used to adjust the make time are the following:

The “CB correction time” is used to adapt the PoW response (make time). The applied correction time is added
to the closing time. A positive setting will therefore result in an earlier close command (longer closing time).
The positive  make time in the fault log above indicates that the measured make time was longer than
expected. The values from the fault log (green box) are therefore added to the old setting (in this case the old
settings are zero, so the  make time can be set directly as follows (only 2 decimal places):

The next closing operation will include these settings in the calculated close time (longer) and the make time
should now have a very small delta (exactly zero is generally not possible).

1.3.3 Adapting the Reference contact delay


Note: the reference contact adjustment should be done after the correction time adjustment as shown above.
From the new fault log after adjusting the correction time, the delta closing times are used to adapt the time
delay reference contact setting as follows:

APN-084 6 Edition 1
SIPROTEC 5Application
SIPROTEC 5 – Point on Wave: Adjustment during Commissioning

By subtracting the delta closing in the fault log from the “old setting” of “Time delay ref. cont.” in each phase
the make time is adjusted. The next close should show significantly smaller  closing time values:

In this test case the modified settings produce a perfect result with 0 ms deviation in all phases.

1.4 Conclusion
The PoW function can be adapted with the relevant settings using the information recorded in the fault log.
After adjustment the correct response can be checked with a new closure of the plant. In the above example
a shunt capacitor with ungrounded neutral was used, but the basic principles of the adjustment apply to all
types of plant.

Edition 1 7 APN-084
Published by For all products using security features of OpenSSL
Siemens AG 2021 the following shall apply:

Smart Infrastructure This product includes software developed by the


Digital Grid OpenSSL Project for use in the OpenSSL Toolkit.
Automation Products (http://www.openssl.org)
Humboldtstr. 59
This product includes cryptographic software
90459 Nuremberg, Germany
written by Eric Young ([email protected])
www.siemens.com/siprotec
This product includes software written
Our Customer Support Center by Tim Hudson ([email protected])
provides a 24-hour service.
This product includes software developed
Siemens AG
by Bodo Moeller.
Smart Infrastructure – Digital Grid
Customer Support Center
E-Mail:
[email protected]

APN-084 8 Edition 1

You might also like