Road BOQs - Draft
Road BOQs - Draft
Road BOQs - Draft
A1 Allow a sum to cover preliminary costs - Mobilisation, demobilisation and setting up of site
ITEM - -
offices and site stores
B1 Construction of access roads to quarry sites including their maintenance throughout the working
km - -
period
Page 1
Bill No.2: Setting out and Site Clearing Works Unit Qty Rate (UGX) Total (UGX)
Clear site of all trees including stumps, grass, bushes and boulders and Grub all roots of trees,
Sm
B2 grass and bushes including excavation of top soil from road formation
C2 Extra over item B2 for boulders over 1.5m maximum girth. No.
D2 Cut and remove from site trees (up to 1m girth), including removal of stumps and roots No.
Page 2
Bill No.3: Earth Works Unit Qty Rate (UGX) Total (UGX)
B3 Excavation to level m3
E3 Preparation of borrow pit Site consisting of clearing vegetation and removing topsoil m2
Excavation, hauling, placing, watering and compaction of approved fill material in embank-ments
m3
F3 & lowspots to create a level road bench.
F5 Excavation of Rock m3
Page 3
Bill No.4: Drainage Works. Unit Qty Rate (UGX) Total (UGX)
E4 600mm diameter m
F4 900mm diameter m
G4 1200mm diameter m
H4 1500mm diameter m
Page 4
Supply and install steel pipe culvert rings:
I4 1200mm diameter m
J4 1500mm diameter m
N4 A142 BRC m2
O4 Provide, place and compact hardcore / Rockfill foundation layer for structures m3
P4 Class 10 (1:4:8) m3
Q4 Class 15 (1:3:6) m3
Page 5
R4 Class 20 (1:2:4) m3
S4 Class 25 (1:1.5:2) m3
Page 6
Bill No.5: Gravelling and Completion of Works.
Excavate gravel, remove boulders, stockpile, load, haul, offload, spread, water and compact in m3
B5 place.
Page 7
Collection
Sub-total I
ADD
VAT (18%)
Total I
Page 8
MAIN SUMMARY
3 Earth works
4 Drainage works
Sub-total I
VAT (18%)
GRAND TOTAL