SAP Activate Estimate Days Project

The document outlines a 642 day project with 74 tasks to implement an S/4HANA sample project. It includes planning activities like strategic planning, innovation strategy development and scoping. It also includes preparation tasks like enablement of the project team, provisioning a trial system and key user training. The project then outlines transition planning, preparation and execution activities to move to the S/4HANA platform.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
104 views19 pages

SAP Activate Estimate Days Project

The document outlines a 642 day project with 74 tasks to implement an S/4HANA sample project. It includes planning activities like strategic planning, innovation strategy development and scoping. It also includes preparation tasks like enablement of the project team, provisioning a trial system and key user training. The project then outlines transition planning, preparation and execution activities to move to the S/4HANA platform.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

ID Name Duration Start Finish

1 S/4HANA Sample Project 642 days April 2, 2020 8:00 AM September 16, 2022 5:00 PM
2 Discover 70 days April 2, 2020 8:00 AM July 8, 2020 5:00 PM

3 Strategic Planning 60 days April 2, 2020 8:00 AM June 24, 2020 5:00 PM

4 Create an Innovation Strategy and a High-Level Road Map 20 days April 2, 2020 8:00 AM April 29, 2020 5:00 PM

5 Accelerate Your Innovations with the Help of the SAP Leonardo 40 days April 30, 2020 8:00 AM June 24, 2020 5:00 PM
Innovation Services (Optional Task)

6 Create a 360-Degree View on Security 5 days April 30, 2020 8:00 AM May 6, 2020 5:00 PM

7 Define the Analytics Architecture 10 days April 30, 2020 8:00 AM May 13, 2020 5:00 PM

8 Application Value and Scoping 50 days April 30, 2020 8:00 AM July 8, 2020 5:00 PM

9 Discover the Value of SAP S/4HANA for Your Company 15 days April 30, 2020 8:00 AM May 20, 2020 5:00 PM

10 Identify the impact of SAP S/4HANA on existing business processes 15 days April 30, 2020 8:00 AM May 20, 2020 5:00 PM

11 Check the Conversion Readiness of SAP ERP 5 days April 30, 2020 8:00 AM May 6, 2020 5:00 PM

12 Perform a Business Scenario and Solution Mapping 15 days May 21, 2020 8:00 AM June 10, 2020 5:00 PM

13 Define the Implementation Strategy 10 days June 11, 2020 8:00 AM June 24, 2020 5:00 PM
14 Create a Strategic Road Map and Value Case 10 days June 25, 2020 8:00 AM July 8, 2020 5:00 PM

15 Trial System Provisioning 2 days May 21, 2020 8:00 AM May 22, 2020 5:00 PM

16 Provide a Trial System 2 days May 21, 2020 8:00 AM May 22, 2020 5:00 PM

17 Prepare 56 days July 8, 2020 5:00 PM September 24, 2020 5:00 PM

18 Project Team Enablement 4 days August 7, 2020 8:00 AM August 12, 2020 5:00 PM

19 Conduct Agile Training for the Project Team 1 day August 7, 2020 8:00 AM August 7, 2020 5:00 PM

20 Conduct SAP Solution Manager Training 1 day August 11, 2020 8:00 AM August 11, 2020 5:00 PM

21 Perform Mobilization Training for the Project Team 1 day August 10, 2020 8:00 AM August 10, 2020 5:00 PM

22 Conduct Project Team Enablement prior to Fit-Gap Analysis 1 day August 11, 2020 8:00 AM August 11, 2020 5:00 PM

23 Conduct Key User Training 1 day August 12, 2020 8:00 AM August 12, 2020 5:00 PM

24 Prototype 0 days July 8, 2020 5:00 PM July 8, 2020 5:00 PM

25 Run Prototyping 0 days July 8, 2020 5:00 PM July 8, 2020 5:00 PM

26 Transition Planning 23 days August 7, 2020 8:00 AM September 8, 2020 5:00 PM

27 Check the Conversion Readiness of SAP ERP 5 days August 7, 2020 8:00 AM August 13, 2020 5:00 PM

28 SAP S/4HANA Transition Project: Scope Definition and Objectives 5 days August 14, 2020 8:00 AM August 20, 2020 5:00 PM

29 Define Cutover Approach 5 days August 21, 2020 8:00 AM August 27, 2020 5:00 PM

30 Clarify Custom Code Adaption 5 days August 21, 2020 8:00 AM August 27, 2020 5:00 PM

31 Clarify Operational Readiness 5 days August 21, 2020 8:00 AM August 27, 2020 5:00 PM

32 Define Technical Architecture 10 days August 21, 2020 8:00 AM September 3, 2020 5:00 PM

33 Define the Data Migration Architecture 10 days August 21, 2020 8:00 AM September 3, 2020 5:00 PM

34 Perform Data Volume Planning 3 days September 4, 2020 8:00 AM September 8, 2020 5:00 PM

35 Define the UX / UI strategy 3 days August 21, 2020 8:00 AM August 25, 2020 5:00 PM

36 Prepare Interface Register 5 days August 21, 2020 8:00 AM August 27, 2020 5:00 PM
37 Run a Legacy Impact Analysis on Interface Inventory and Data 5 days August 21, 2020 8:00 AM August 27, 2020 5:00 PM
Integration

38 Run a first Assessment on Output Management 5 days August 21, 2020 8:00 AM August 27, 2020 5:00 PM

39 Run a first Assessment on Training Requirements 3 days August 21, 2020 8:00 AM August 25, 2020 5:00 PM

40 Optional: Run a Technical Security Self Check 2 days August 21, 2020 8:00 AM August 24, 2020 5:00 PM

41 Transition Preparation 12 days September 8, 2020 5:00 PM September 24, 2020 5:00 PM

42 Execute on Follow-Ups from Transition Planning 0 days September 8, 2020 5:00 PM September 8, 2020 5:00 PM

43 Clean up of Archive Data 0 days September 8, 2020 5:00 PM September 8, 2020 5:00 PM

44 Cleanup Unused Code (Optional Task) 0 days September 8, 2020 5:00 PM September 8, 2020 5:00 PM

45 Improve Custom Code Quality Measures (Optional Task) 0 days September 8, 2020 5:00 PM September 8, 2020 5:00 PM

46 Prepare SAP Solution Manager for Project Support 10 days September 9, 2020 8:00 AM September 22, 2020 5:00 PM

47 Import the Best Practices content to SAP Solution Manager 2 days September 23, 2020 8:00 AM September 24, 2020 5:00 PM

48 Project Initiation 5 days July 9, 2020 8:00 AM July 15, 2020 5:00 PM

49 Conduct Handover Meeting(s) from Opportunity Phase 1 day July 9, 2020 8:00 AM July 9, 2020 5:00 PM

50 Review Order Form with Customer 1 day July 10, 2020 8:00 AM July 10, 2020 5:00 PM

51 Identify Stakeholders, Stakeholders' Requirements and Expectations 1 day July 13, 2020 8:00 AM July 13, 2020 5:00 PM
and Project/Deliverable Acceptance Criteria

52 Set Stakeholder Expectations for Agile Project 1 day July 14, 2020 8:00 AM July 14, 2020 5:00 PM

53 Create Project Charter 1 day July 13, 2020 8:00 AM July 13, 2020 5:00 PM

54 Create Project Management Plan 2 days July 14, 2020 8:00 AM July 15, 2020 5:00 PM

55 Establish Project Governance 4 days July 16, 2020 8:00 AM July 21, 2020 5:00 PM

56 Define Roles and Responsibilities 2 days July 16, 2020 8:00 AM July 17, 2020 5:00 PM
57 Define Project Organization 1 day July 20, 2020 8:00 AM July 20, 2020 5:00 PM

58 Review Project Management Plan 1 day July 21, 2020 8:00 AM July 21, 2020 5:00 PM

59 Plan Project 3 days July 22, 2020 8:00 AM July 24, 2020 5:00 PM

60 Create Scope Statement 3 days July 22, 2020 8:00 AM July 24, 2020 5:00 PM

61 Create WBS 2 days July 22, 2020 8:00 AM July 23, 2020 5:00 PM

62 Create Project Schedule 2 days July 22, 2020 8:00 AM July 23, 2020 5:00 PM

63 Create Budget 2 days July 22, 2020 8:00 AM July 23, 2020 5:00 PM

64 Plan Quality 2 days July 22, 2020 8:00 AM July 23, 2020 5:00 PM

65 Plan Communications 2 days July 22, 2020 8:00 AM July 23, 2020 5:00 PM

66 Plan Risks 1 day July 22, 2020 8:00 AM July 22, 2020 5:00 PM

67 Plan Procurement 1 day July 22, 2020 8:00 AM July 22, 2020 5:00 PM

68 Plan Stakeholders Management 2 days July 22, 2020 8:00 AM July 23, 2020 5:00 PM

69 Project Kick-Off and On-Boarding 9 days July 27, 2020 8:00 AM August 6, 2020 5:00 PM

70 Prepare for Kick-off Meeting 2 days July 27, 2020 8:00 AM July 28, 2020 5:00 PM

71 Conduct Kick-off Meeting 1 day July 29, 2020 8:00 AM July 29, 2020 5:00 PM

72 Prepare Team On-boarding Document 1 day July 30, 2020 8:00 AM July 30, 2020 5:00 PM

73 On-board Project Team 5 days July 31, 2020 8:00 AM August 6, 2020 5:00 PM

74 Project Standards, Infrastructure, and Solution 3 days August 7, 2020 8:00 AM August 11, 2020 5:00 PM

75 Define Project Standards 2 days August 7, 2020 8:00 AM August 10, 2020 5:00 PM

76 Determine Operational Standards 2 days August 7, 2020 8:00 AM August 10, 2020 5:00 PM

77 Define and Set Up Agile Project Standards and ALM Tools 2 days August 7, 2020 8:00 AM August 10, 2020 5:00 PM

78 Check Availability of SAP Solution Manager 2 days August 7, 2020 8:00 AM August 10, 2020 5:00 PM

79 Set up Project Team Logistics and Infrastructure 3 days August 7, 2020 8:00 AM August 11, 2020 5:00 PM
80 Setup and Test Remote Support 3 days August 7, 2020 8:00 AM August 11, 2020 5:00 PM

81 Execution, Monitoring, and Controlling of Results 2 days July 30, 2020 8:00 AM July 31, 2020 5:00 PM

82 Direct and Manage Project Execution 2 days July 30, 2020 8:00 AM July 31, 2020 5:00 PM

83 Monitor and Control Project Activities 1 day July 30, 2020 8:00 AM July 30, 2020 5:00 PM

84 Manage Issues, Risks and Changes 1 day July 30, 2020 8:00 AM July 30, 2020 5:00 PM

85 Communicate Status and Progress to Project Stakeholders 1 day July 30, 2020 8:00 AM July 30, 2020 5:00 PM

86 Organizational Change Management Roadmap 0 days August 6, 2020 5:00 PM August 6, 2020 5:00 PM

87 Prepare Organizational Change Management Roadmap 0 days August 6, 2020 5:00 PM August 6, 2020 5:00 PM

88 Conduct OCM Workshop with Project Manager and all Project 0 days August 6, 2020 5:00 PM August 6, 2020 5:00 PM
Workstream Owners

89 Phase Closure and Sign-Off Phase Deliverables 23 days August 13, 2020 8:00 AM September 14, 2020 5:00 PM

90 Conduct Knowledge Management Gate 1 day August 13, 2020 8:00 AM August 13, 2020 5:00 PM

91 Conduct Project Quality Gate 2 days September 9, 2020 8:00 AM September 10, 2020 5:00 PM

92 Conduct Project Management Review Service 1 day September 11, 2020 8:00 AM September 11, 2020 5:00 PM

93 Obtain Customer Sign-Off for Phase Completion 1 day September 14, 2020 8:00 AM September 14, 2020 5:00 PM

94 Explore 242 days September 15, 2020 8:00 AM August 18, 2021 5:00 PM

95 Phase Initiation 4 days September 15, 2020 8:00 AM September 18, 2020 5:00 PM

96 Review Deliverables of Explore Phase 2 days September 15, 2020 8:00 AM September 16, 2020 5:00 PM

97 Review Acceptance Criteria 1 day September 17, 2020 8:00 AM September 17, 2020 5:00 PM

98 Review RACI Chart for Explore Phase 1 day September 18, 2020 8:00 AM September 18, 2020 5:00 PM
99 Learning Design 20 days September 15, 2020 8:00 AM October 12, 2020 5:00 PM

100 Develop a Training Concept 20 days September 15, 2020 8:00 AM October 12, 2020 5:00 PM

101 Activate Solution 50 days September 22, 2020 8:00 AM November 30, 2020 5:00 PM

102 Finalize Mandatory System Preparation Activities (System Conversion 20 days October 27, 2020 8:00 AM November 23, 2020 5:00 PM
only)

103 Reconfirmation of Scope for Activation (New Implementation only) 1 day September 22, 2020 8:00 AM September 22, 2020 5:00 PM

104 Activation of Best Practices and Test-Activated Processes (New 5 days September 23, 2020 8:00 AM September 29, 2020 5:00 PM
Implementation only)

105 Set up Integration with other Test Systems 5 days November 24, 2020 8:00 AM November 30, 2020 5:00 PM

106 Fit-Gap / Delta Design: Introduction 2 days December 1, 2020 8:00 AM December 2, 2020 5:00 PM

107 Make yourself familiar with Fit-Gap / Delta Design 2 days December 1, 2020 8:00 AM December 2, 2020 5:00 PM

108 Fit-Gap / Delta Design: Finalize System Setup 30 days December 3, 2020 8:00 AM January 13, 2021 5:00 PM

109 Prepare sample data 10 days December 3, 2020 8:00 AM December 16, 2020 5:00 PM

110 Enhance system setup with additional configuration 20 days December 17, 2020 8:00 AM January 13, 2021 5:00 PM

111 Fit-Gap / Delta Design: Fit/Gap Analysis - Solution Validation 30 days January 14, 2021 8:00 AM February 24, 2021 5:00 PM

112 Run Fit Gap Workshops 30 days January 14, 2021 8:00 AM February 24, 2021 5:00 PM

113 Fit-Gap / Delta Design: Gap Identification 5 days February 25, 2021 8:00 AM March 3, 2021 5:00 PM

114 GAP Documentation / Specification 5 days February 25, 2021 8:00 AM March 3, 2021 5:00 PM

115 Fit-Gap / Delta Design: Delta Scope Prioritization 5 days March 4, 2021 8:00 AM March 10, 2021 5:00 PM

116 Prioritize Delta Scope 5 days March 4, 2021 8:00 AM March 10, 2021 5:00 PM

117 GAP Validation 5 days March 11, 2021 8:00 AM March 17, 2021 5:00 PM

118 Validate Gaps 5 days March 11, 2021 8:00 AM March 17, 2021 5:00 PM
119 Fit-Gap / Delta Design: Delta Design 30 days March 18, 2021 8:00 AM April 28, 2021 5:00 PM

120 Finalize Delta Design 30 days March 18, 2021 8:00 AM April 28, 2021 5:00 PM

121 Design Review 5 days April 29, 2021 8:00 AM May 5, 2021 5:00 PM

122 Perform Design Review 5 days April 29, 2021 8:00 AM May 5, 2021 5:00 PM

123 Fit-Gap / Delta Design: Verify and Accept 10 days May 6, 2021 8:00 AM May 19, 2021 5:00 PM

124 Perform Validation and Approval Sessions 10 days May 6, 2021 8:00 AM May 19, 2021 5:00 PM

125 UX Activation and Design 87 days November 24, 2020 8:00 AM March 24, 2021 5:00 PM

126 UX Activation 10 days November 24, 2020 8:00 AM December 7, 2020 5:00 PM

127 UX Design 20 days February 25, 2021 8:00 AM March 24, 2021 5:00 PM

128 Security Design 30 days February 25, 2021 8:00 AM April 7, 2021 5:00 PM

129 Define Security Infrastructure 30 days February 25, 2021 8:00 AM April 7, 2021 5:00 PM

130 Fit-Gap / Delta Design- Central Finance Design 0 days February 24, 2021 5:00 PM February 24, 2021 5:00 PM

131 Run Central Finance Design 0 days February 24, 2021 5:00 PM February 24, 2021 5:00 PM

132 Data Volume Design 182 days September 15, 2020 8:00 AM May 26, 2021 5:00 PM

133 Get Transparency on the HANA DVM Quick Wins 5 days September 15, 2020 8:00 AM September 21, 2020 5:00 PM

134 Optional: Set Up a DVM Strategy for Business Documents 20 days April 29, 2021 8:00 AM May 26, 2021 5:00 PM

135 Get Transparency on Open Business Documents 10 days September 22, 2020 8:00 AM October 5, 2020 5:00 PM

136 Adapt your DVM Strategy 20 days April 29, 2021 8:00 AM May 26, 2021 5:00 PM

137 Data Migration Design 90 days February 25, 2021 8:00 AM June 30, 2021 5:00 PM

138 Prepare and Conduct Data Migration Assessment 20 days February 25, 2021 8:00 AM March 24, 2021 5:00 PM

139 Data Audit 10 days March 25, 2021 8:00 AM April 7, 2021 5:00 PM
140 Prepare and Present Data Migration Scope and Requirements 10 days April 8, 2021 8:00 AM April 21, 2021 5:00 PM
Document

141 Data Migration Approach and Strategy Document 10 days April 22, 2021 8:00 AM May 5, 2021 5:00 PM

142 Test Data Management 20 days May 6, 2021 8:00 AM June 2, 2021 5:00 PM

143 Define Specifications for Data Migration 20 days June 3, 2021 8:00 AM June 30, 2021 5:00 PM

144 Run a Landscape Transformation Assessment (Selective Data 60 days February 25, 2021 8:00 AM May 19, 2021 5:00 PM
Transition only)

145 Set up Landscape Transformation Software (Selective Data Transition 5 days May 20, 2021 8:00 AM May 26, 2021 5:00 PM
only)

146 Set up Data Migration Services (New Installation scenario only) 3 days May 20, 2021 8:00 AM May 24, 2021 5:00 PM

147 Custom Code Impact 20 days February 25, 2021 8:00 AM March 24, 2021 5:00 PM

148 Create a List of Impacted Custom Code Objects 20 days February 25, 2021 8:00 AM March 24, 2021 5:00 PM

149 Integration Design 40 days February 25, 2021 8:00 AM April 21, 2021 5:00 PM

150 Define Interface Architecture 20 days February 25, 2021 8:00 AM March 24, 2021 5:00 PM

151 Prepare Integration Design 20 days March 25, 2021 8:00 AM April 21, 2021 5:00 PM

152 Analytics Design 30 days February 25, 2021 8:00 AM April 7, 2021 5:00 PM

153 Design the Analytics Architecture 30 days February 25, 2021 8:00 AM April 7, 2021 5:00 PM

154 Test Planning 172 days September 15, 2020 8:00 AM May 12, 2021 5:00 PM

155 Self-Enable on Test Management Tools and Solution Manager Test 10 days September 15, 2020 8:00 AM September 28, 2020 5:00 PM
Management

156 Test Scope Determination 5 days April 29, 2021 8:00 AM May 5, 2021 5:00 PM

157 Detailed Test Planning 5 days May 6, 2021 8:00 AM May 12, 2021 5:00 PM

158 Sandbox Setup / Conversion 35 days September 15, 2020 8:00 AM November 2, 2020 5:00 PM

159 Set Up SANDBOX (System Conversion scenario only) 30 days September 15, 2020 8:00 AM October 26, 2020 5:00 PM

160 Downtime Optimization Preparation (System Conversion scenario 5 days October 27, 2020 8:00 AM November 2, 2020 5:00 PM
only)
161 Set Up SANDBOX (New Installation scenario only) 5 days September 15, 2020 8:00 AM September 21, 2020 5:00 PM

162 DEV Setup /Conversion 15 days May 20, 2021 8:00 AM June 9, 2021 5:00 PM

163 DEV Setup (New Implementation) 10 days May 20, 2021 8:00 AM June 2, 2021 5:00 PM

164 DEV Setup (System Conversion) 15 days May 20, 2021 8:00 AM June 9, 2021 5:00 PM

165 Sizing 10 days May 20, 2021 8:00 AM June 2, 2021 5:00 PM

166 Perform / Check Sizing 10 days May 20, 2021 8:00 AM June 2, 2021 5:00 PM

167 Technical Architecture and Infrastructure Definition 55 days April 29, 2021 8:00 AM July 14, 2021 5:00 PM

168 Discover Technical Boundary Conditions 20 days May 20, 2021 8:00 AM June 16, 2021 5:00 PM

169 Create Technical Solution Map 10 days June 17, 2021 8:00 AM June 30, 2021 5:00 PM

170 Decide on Integration with Cloud Applications 10 days April 29, 2021 8:00 AM May 12, 2021 5:00 PM

171 Hardware Selection and Utilization 2 days July 1, 2021 8:00 AM July 2, 2021 5:00 PM

172 Develop Virtualization Strategy 3 days July 5, 2021 8:00 AM July 7, 2021 5:00 PM

173 Design Network 5 days July 1, 2021 8:00 AM July 7, 2021 5:00 PM

174 Test Preparation 5 days July 8, 2021 8:00 AM July 14, 2021 5:00 PM

175 Technical Design 20 days July 8, 2021 8:00 AM August 4, 2021 5:00 PM

176 Create a Technical Solution Design Document 20 days July 8, 2021 8:00 AM August 4, 2021 5:00 PM

177 Operations Impact Evaluation 10 days August 5, 2021 8:00 AM August 18, 2021 5:00 PM

178 Operations Impact Evaluation 10 days August 5, 2021 8:00 AM August 18, 2021 5:00 PM

179 Execution / Monitoring / Controlling Results 3 days September 21, 2020 8:00 AM September 23, 2020 5:00 PM

180 Update Project Management Plan 1 day September 21, 2020 8:00 AM September 21, 2020 5:00 PM

181 Direct and Manage Project Execution 2 days September 22, 2020 8:00 AM September 23, 2020 5:00 PM
182 Conduct SCRUM Meetings 1 day September 22, 2020 8:00 AM September 22, 2020 5:00 PM

183 Monitor and Control Project Activities 1 day September 22, 2020 8:00 AM September 22, 2020 5:00 PM

184 Manage Issues, Risks and Changes 1 day September 22, 2020 8:00 AM September 22, 2020 5:00 PM

185 Communicate Status and Progress to Project Stakeholders 1 day September 22, 2020 8:00 AM September 22, 2020 5:00 PM

186 Release and Sprint Plan 9 days May 20, 2021 8:00 AM June 1, 2021 5:00 PM

187 Update and Prioritize Backlog 3 days May 20, 2021 8:00 AM May 24, 2021 5:00 PM

188 Estimate Backlog Items Effort 2 days May 25, 2021 8:00 AM May 26, 2021 5:00 PM

189 Conduct Release and Sprint Planning Meeting 2 days May 27, 2021 8:00 AM May 28, 2021 5:00 PM

190 Validate Release and Sprint Plan Against SoW 2 days May 31, 2021 8:00 AM June 1, 2021 5:00 PM

191 Change Impact Analysis 0 days May 19, 2021 5:00 PM May 19, 2021 5:00 PM

192 Validate Organizational Alignment Approach 0 days May 19, 2021 5:00 PM May 19, 2021 5:00 PM

193 Establish Baseline of Current State 0 days May 19, 2021 5:00 PM May 19, 2021 5:00 PM

194 Phase Closure and Sign-Off phase Deliverables 7 days August 5, 2021 8:00 AM August 13, 2021 5:00 PM

195 Conduct Knowledge Management Gate 1 day August 10, 2021 8:00 AM August 10, 2021 5:00 PM

196 Conduct Project Quality Gate 3 days August 5, 2021 8:00 AM August 9, 2021 5:00 PM

197 Execute Baseline Retrospective 1 day August 10, 2021 8:00 AM August 10, 2021 5:00 PM

198 Conduct Project Management Review Service 1 day August 11, 2021 8:00 AM August 11, 2021 5:00 PM

199 Manage Fulfilled Contracts 1 day August 12, 2021 8:00 AM August 12, 2021 5:00 PM

200 Obtain Customer Sign-Off for Phase Completion 1 day August 13, 2021 8:00 AM August 13, 2021 5:00 PM

201 Realize 252 days May 20, 2021 8:00 AM May 6, 2022 5:00 PM

202 Phase Initiation 4 days August 16, 2021 8:00 AM August 19, 2021 5:00 PM
203 Review Deliverables of Realize Phase 2 days August 16, 2021 8:00 AM August 17, 2021 5:00 PM

204 Review Acceptance Criteria 1 day August 18, 2021 8:00 AM August 18, 2021 5:00 PM

205 Review RACI Chart for Realize Phase 1 day August 19, 2021 8:00 AM August 19, 2021 5:00 PM

206 Plan Realize Phase 6 days August 20, 2021 8:00 AM August 27, 2021 5:00 PM

207 Plan Sprints and Solution Reviews 3 days August 20, 2021 8:00 AM August 24, 2021 5:00 PM

208 Plan Testing 3 days August 25, 2021 8:00 AM August 27, 2021 5:00 PM

209 Learning Realization 30 days August 20, 2021 8:00 AM September 30, 2021 5:00 PM

210 Train your Key User 20 days August 20, 2021 8:00 AM September 16, 2021 5:00 PM

211 Create Training Material for End User 30 days August 20, 2021 8:00 AM September 30, 2021 5:00 PM

212 Sprint Initiation (Iterative) 5 days August 25, 2021 8:00 AM August 31, 2021 5:00 PM

213 Conduct Sprint Planning Meeting (Iterative) 5 days August 25, 2021 8:00 AM August 31, 2021 5:00 PM

214 Execution Plan for Realize Phase 5 days September 1, 2021 8:00 AM September 7, 2021 5:00 PM

215 Manage Sprints 1 day September 1, 2021 8:00 AM September 1, 2021 5:00 PM

216 Manage Unit/String Tests 1 day September 2, 2021 8:00 AM September 2, 2021 5:00 PM

217 Manage Integration Test 1 day September 3, 2021 8:00 AM September 3, 2021 5:00 PM

218 Manage Security Test 1 day September 6, 2021 8:00 AM September 6, 2021 5:00 PM

219 Manage User Acceptance Test 1 day September 7, 2021 8:00 AM September 7, 2021 5:00 PM

220 Configuration: Introduction 0 days September 1, 2021 5:00 PM September 1, 2021 5:00 PM

221 Make yourself familiar with Configuration 0 days September 1, 2021 5:00 PM September 1, 2021 5:00 PM
222 Configuration: Handover 5 days September 2, 2021 8:00 AM September 8, 2021 5:00 PM

223 Run Handover Session 5 days September 2, 2021 8:00 AM September 8, 2021 5:00 PM

224 Configuration: Main Configuration 50 days September 9, 2021 8:00 AM November 17, 2021 5:00 PM

225 Perform Main Configuration 50 days September 9, 2021 8:00 AM November 17, 2021 5:00 PM

226 Configuration: Unit Test 15 days November 18, 2021 8:00 AM December 8, 2021 5:00 PM

227 Run Unit Test 15 days November 18, 2021 8:00 AM December 8, 2021 5:00 PM

228 Configuration: String Test 15 days December 9, 2021 8:00 AM December 29, 2021 5:00 PM

229 Run String Test 15 days December 9, 2021 8:00 AM December 29, 2021 5:00 PM

230 Configuration: Solution Walk-Through 5 days December 30, 2021 8:00 AM January 5, 2022 5:00 PM

231 Run Solution Walk-Through 5 days December 30, 2021 8:00 AM January 5, 2022 5:00 PM

232 Configuration: Bug Fixing 15 days January 6, 2022 8:00 AM January 26, 2022 5:00 PM

233 Resolve Identified Issues 15 days January 6, 2022 8:00 AM January 26, 2022 5:00 PM

234 Configuration: Documentation 15 days January 27, 2022 8:00 AM February 16, 2022 5:00 PM

235 Document Configured Settings 15 days January 27, 2022 8:00 AM February 16, 2022 5:00 PM

236 Configuration- Central Finance Implementation 0 days November 17, 2021 5:00 PM November 17, 2021 5:00 PM

237 Product Enhancements 20 days September 8, 2021 5:00 PM October 6, 2021 5:00 PM

238 Adjust Affected Existing Custom Code 20 days September 9, 2021 8:00 AM October 6, 2021 5:00 PM
239 Development of WRICEF objects 20 days September 9, 2021 8:00 AM October 6, 2021 5:00 PM

240 Enhancement and development of user interface (e.g. FIORI) 20 days September 9, 2021 8:00 AM October 6, 2021 5:00 PM

241 Custom Development 0 days September 8, 2021 5:00 PM September 8, 2021 5:00 PM

242 Sprint Closing 3 days February 17, 2022 8:00 AM February 21, 2022 5:00 PM

243 Conduct Sprint Review Meeting 1 day February 17, 2022 8:00 AM February 17, 2022 5:00 PM

244 Signoff Sprint Results 1 day February 18, 2022 8:00 AM February 18, 2022 5:00 PM

245 Conduct Sprint Retrospective 1 day February 21, 2022 8:00 AM February 21, 2022 5:00 PM

246 Security Implementation 30 days August 20, 2021 8:00 AM September 30, 2021 5:00 PM

247 Implement Security 30 days August 20, 2021 8:00 AM September 30, 2021 5:00 PM

248 Data Volume Management Configuration 20 days August 20, 2021 8:00 AM September 16, 2021 5:00 PM

249 Cleanup or Archive Data 20 days August 20, 2021 8:00 AM September 16, 2021 5:00 PM

250 Configure Data Archiving and Data Aging (Design Time) 10 days August 20, 2021 8:00 AM September 2, 2021 5:00 PM

251 Test execution of Data Archiving and Data Aging (Runtime) 10 days September 3, 2021 8:00 AM September 16, 2021 5:00 PM

252 Integration Validation 45 days January 27, 2022 8:00 AM March 30, 2022 5:00 PM

253 Identify the IV Scope 10 days January 27, 2022 8:00 AM February 9, 2022 5:00 PM

254 Initiate the Corresponding IV Support Activities 30 days February 10, 2022 8:00 AM March 23, 2022 5:00 PM

255 Initiate SAP Going-Live Check 5 days March 24, 2022 8:00 AM March 30, 2022 5:00 PM

256 Data Migration and Verification 45 days August 27, 2021 8:00 AM October 28, 2021 5:00 PM

257 Legacy Data Migration (New Implementation) 40 days August 27, 2021 8:00 AM October 21, 2021 5:00 PM

258 Perform Load and Verification Runs (System Conversion) 40 days September 3, 2021 8:00 AM October 28, 2021 5:00 PM
259 Perform Client Transfer (LT Scenario- Client Transfer) 40 days September 3, 2021 8:00 AM October 28, 2021 5:00 PM

260 Perform System Merge (LT scenario- System Merge) 40 days September 3, 2021 8:00 AM October 28, 2021 5:00 PM

261 Perform Company Code Transfer (LT Scenario- Company Code 40 days September 3, 2021 8:00 AM October 28, 2021 5:00 PM
Transfer)

262 Custom Code Quality 10 days August 20, 2021 8:00 AM September 2, 2021 5:00 PM

263 Establish / Adjust Custom Code Quality 10 days August 20, 2021 8:00 AM September 2, 2021 5:00 PM

264 Integration Implementation 50 days May 20, 2021 8:00 AM July 28, 2021 5:00 PM

265 Implement Integration Design 30 days May 20, 2021 8:00 AM June 30, 2021 5:00 PM

266 Validate Integration Implementation 20 days July 1, 2021 8:00 AM July 28, 2021 5:00 PM

267 Analytics Configuration 35 days August 20, 2021 8:00 AM October 7, 2021 5:00 PM

268 Configure Analytics and Digital Boardroom 30 days August 20, 2021 8:00 AM September 30, 2021 5:00 PM

269 Knowledge Transfer 5 days October 1, 2021 8:00 AM October 7, 2021 5:00 PM

270 Test Preparation 20 days December 30, 2021 8:00 AM January 26, 2022 5:00 PM

271 Prepare Tests 20 days December 30, 2021 8:00 AM January 26, 2022 5:00 PM

272 Test Execution 65 days January 27, 2022 8:00 AM April 27, 2022 5:00 PM

273 Perform Integration / Regression / User Acceptance Test 40 days January 27, 2022 8:00 AM March 23, 2022 5:00 PM

274 Perform Test Steps 20 days March 24, 2022 8:00 AM April 20, 2022 5:00 PM

275 Test Suite Analytics and Reporting 5 days April 21, 2022 8:00 AM April 27, 2022 5:00 PM

276 QAS Setup/ Conversion 10 days August 20, 2021 8:00 AM September 2, 2021 5:00 PM

277 QAS Setup (New Implementation) 5 days August 20, 2021 8:00 AM August 26, 2021 5:00 PM

278 QAS Setup (System Conversion) 10 days August 20, 2021 8:00 AM September 2, 2021 5:00 PM

279 Sizing and Scalability Verification 5 days February 17, 2022 8:00 AM February 23, 2022 5:00 PM
280 Optional: Perform Sizing Verification 5 days February 17, 2022 8:00 AM February 23, 2022 5:00 PM

281 Optional: Perform Scalability Verification 5 days February 17, 2022 8:00 AM February 23, 2022 5:00 PM

282 IT Infrastructure Setup 30 days August 20, 2021 8:00 AM September 30, 2021 5:00 PM

283 Set Up IT Infrastructure 20 days August 20, 2021 8:00 AM September 16, 2021 5:00 PM

284 Test IT Infrastructure 10 days September 17, 2021 8:00 AM September 30, 2021 5:00 PM

285 Operations Implementation 30 days August 19, 2021 8:00 AM September 29, 2021 5:00 PM

286 Collect detailed Operations Requirements 10 days August 19, 2021 8:00 AM September 1, 2021 5:00 PM

287 Roles and Responsibilities 10 days September 2, 2021 8:00 AM September 15, 2021 5:00 PM

288 Support Processes and Procedures 10 days September 2, 2021 8:00 AM September 15, 2021 5:00 PM

289 Operations Support Tools 10 days September 2, 2021 8:00 AM September 15, 2021 5:00 PM

290 Operations Documentation 10 days September 2, 2021 8:00 AM September 15, 2021 5:00 PM

291 Knowledge Transfer 10 days September 16, 2021 8:00 AM September 29, 2021 5:00 PM

292 Cutover Preparation 94 days October 22, 2021 8:00 AM March 2, 2022 5:00 PM

293 Production System Setup 10 days October 22, 2021 8:00 AM November 4, 2021 5:00 PM

294 Create Cutover Plan (New Implementation) 10 days February 17, 2022 8:00 AM March 2, 2022 5:00 PM

295 Create Cutover Plan (System Conversion) 10 days February 17, 2022 8:00 AM March 2, 2022 5:00 PM

296 Create Cutover Plan (Landscape Transformation) 10 days February 17, 2022 8:00 AM March 2, 2022 5:00 PM

297 Execution, Monitoring and Controlling Results 7 days August 20, 2021 8:00 AM August 30, 2021 5:00 PM

298 Direct and Manage Project Execution 2 days August 20, 2021 8:00 AM August 23, 2021 5:00 PM

299 Update Project Management Documents 1 day August 24, 2021 8:00 AM August 24, 2021 5:00 PM
300 Manage Project Issues, Risks, and Changes 5 days August 24, 2021 8:00 AM August 30, 2021 5:00 PM

301 Communicate Project Status and Progress 1 day August 24, 2021 8:00 AM August 24, 2021 5:00 PM

302 Plan and Execute Agile Sprints 1 day August 24, 2021 8:00 AM August 24, 2021 5:00 PM

303 Perform Scrum-Of-Scrums Meeting (Iterative) 1 day August 24, 2021 8:00 AM August 24, 2021 5:00 PM

304 Organizational Alignment 30 days August 19, 2021 5:00 PM September 30, 2021 5:00 PM

305 Execute Role Mapping and Transition Planning 0 days September 30, 2021 5:00 PM September 30, 2021 5:00 PM

306 Conduct Sounding Board and Pulse Checks 0 days September 30, 2021 5:00 PM September 30, 2021 5:00 PM

307 Communicate Sprint Scope and Plan (Iterative) 0 days September 30, 2021 5:00 PM September 30, 2021 5:00 PM

308 Communicate Sprint Result (Iterative) 0 days September 30, 2021 5:00 PM September 30, 2021 5:00 PM

309 Refine and Execute Communication Plan 0 days September 30, 2021 5:00 PM September 30, 2021 5:00 PM

310 OCM and Testing alignment 0 days August 19, 2021 5:00 PM August 19, 2021 5:00 PM

311 OCM and Data Migration alignment 0 days August 19, 2021 5:00 PM August 19, 2021 5:00 PM

312 Phase Closure and Sign-Off Phase Deliverables 7 days April 28, 2022 8:00 AM May 6, 2022 5:00 PM

313 Conduct Knowledge Management Gate 1 day May 3, 2022 8:00 AM May 3, 2022 5:00 PM

314 Conduct Project Quality Gate 3 days April 28, 2022 8:00 AM May 2, 2022 5:00 PM

315 Execute Baseline Retrospective 1 day May 3, 2022 8:00 AM May 3, 2022 5:00 PM

316 Conduct Project Management Review Service 1 day May 4, 2022 8:00 AM May 4, 2022 5:00 PM

317 Manage Fulfilled Contracts 1 day May 5, 2022 8:00 AM May 5, 2022 5:00 PM

318 Obtain Customer Sign-Off for Phase Completion 1 day May 6, 2022 8:00 AM May 6, 2022 5:00 PM

319 Deploy 251 days October 1, 2021 8:00 AM September 16, 2022 5:00 PM

320 Phase Initiation 2 days May 9, 2022 8:00 AM May 10, 2022 5:00 PM
321 Allocate Resources and Update Project Schedule 2 days May 9, 2022 8:00 AM May 10, 2022 5:00 PM

322 Perform Kick-off Meeting 1 day May 9, 2022 8:00 AM May 9, 2022 5:00 PM

323 Learning Realization 25 days October 1, 2021 8:00 AM November 4, 2021 5:00 PM

324 Create Training Execution Plan 5 days October 1, 2021 8:00 AM October 7, 2021 5:00 PM

325 Execute End User Training 20 days October 8, 2021 8:00 AM November 4, 2021 5:00 PM

326 Integration Validation 10 days May 10, 2022 8:00 AM May 23, 2022 5:00 PM

327 Finalize Integration Validation 10 days May 10, 2022 8:00 AM May 23, 2022 5:00 PM

328 Operations Readiness 10 days May 10, 2022 8:00 AM May 23, 2022 5:00 PM

329 Operational Readiness (System Conversion) 5 days May 10, 2022 8:00 AM May 16, 2022 5:00 PM

330 Operational Readiness (New Implementation) 10 days May 10, 2022 8:00 AM May 23, 2022 5:00 PM

331 Organizational Readiness 0 days May 9, 2022 5:00 PM May 9, 2022 5:00 PM

332 Perform Business Validation and Transition Planning 0 days May 9, 2022 5:00 PM May 9, 2022 5:00 PM

333 Dress Rehearsal 20 days May 10, 2022 8:00 AM June 6, 2022 5:00 PM

334 Finalize IT Infrastructure Services 10 days May 10, 2022 8:00 AM May 23, 2022 5:00 PM

335 Perform Cut-Over Rehearsal 10 days May 24, 2022 8:00 AM June 6, 2022 5:00 PM

336 Execution, Monitoring and Controlling Results 23 days May 11, 2022 8:00 AM June 10, 2022 5:00 PM

337 Update Project Management Plan 1 day May 11, 2022 8:00 AM May 11, 2022 5:00 PM

338 Direct and Manage Project Execution 2 days May 12, 2022 8:00 AM May 13, 2022 5:00 PM

339 Monitor and Control Project Activities 1 day May 12, 2022 8:00 AM May 12, 2022 5:00 PM

340 Manage Issues, Risks and Changes 3 days May 12, 2022 8:00 AM May 16, 2022 5:00 PM

341 Conduct Project Quality Gate 3 days June 7, 2022 8:00 AM June 9, 2022 5:00 PM

342 Communicate Status and Progress to Project Stakeholders 1 day June 10, 2022 8:00 AM June 10, 2022 5:00 PM

343 Release Closing 4 days May 10, 2022 8:00 AM May 13, 2022 5:00 PM
344 Prepare Product Backlog for Next Release/Sprint 2 days May 10, 2022 8:00 AM May 11, 2022 5:00 PM

345 Conduct Release Retrospective 1 day May 12, 2022 8:00 AM May 12, 2022 5:00 PM

346 Update the Release and Sprint Plan 1 day May 13, 2022 8:00 AM May 13, 2022 5:00 PM

347 Production Cutover 3 days June 10, 2022 8:00 AM June 14, 2022 5:00 PM

348 Convert Productive System (System Conversion) 3 days June 10, 2022 8:00 AM June 14, 2022 5:00 PM

349 Production Cutover (New Implementation) 3 days June 10, 2022 8:00 AM June 14, 2022 5:00 PM

350 Production Cutover (Selective Data Transition) 3 days June 10, 2022 8:00 AM June 14, 2022 5:00 PM

351 Hyper Care Support 22 days June 15, 2022 8:00 AM July 14, 2022 5:00 PM

352 Monitor Resource Consumption 20 days June 15, 2022 8:00 AM July 12, 2022 5:00 PM

353 Analyze Workload 20 days June 15, 2022 8:00 AM July 12, 2022 5:00 PM

354 Check System Scalability 5 days June 15, 2022 8:00 AM June 21, 2022 5:00 PM

355 Follow-up on GoingLive Check (Verification Session) 5 days June 15, 2022 8:00 AM June 21, 2022 5:00 PM

356 Delete Obsolete Data with the "Obsolete Data Handling Tool" 2 days July 13, 2022 8:00 AM July 14, 2022 5:00 PM

357 Post Go-Live End User Training 17 days November 5, 2021 8:00 AM November 29, 2021 5:00 PM

358 Prepare End-User Training for Scope Option 3 days November 5, 2021 8:00 AM November 9, 2021 5:00 PM

359 Deliver End-User Training for Scope Option 10 days November 10, 2021 8:00 AM November 23, 2021 5:00 PM

360 Collect Training Evaluations Feedback 2 days November 24, 2021 8:00 AM November 25, 2021 5:00 PM

361 Perform People Readiness Assessment 2 days November 26, 2021 8:00 AM November 29, 2021 5:00 PM

362 Handover to Support Organization 40 days July 13, 2022 8:00 AM September 6, 2022 5:00 PM

363 Resolve and Close Open Issues 30 days July 13, 2022 8:00 AM August 23, 2022 5:00 PM

364 Handover Operations Responsibility 10 days August 24, 2022 8:00 AM September 6, 2022 5:00 PM
365 Project Closure and Sign-Off Project Deliverables 8 days September 7, 2022 8:00 AM September 16, 2022 5:00 PM

366 Conduct Knowledge Management Gate 1 day September 9, 2022 8:00 AM September 9, 2022 5:00 PM

367 Conduct Project Quality Gate 2 days September 7, 2022 8:00 AM September 8, 2022 5:00 PM

368 Manage fulfilled Contracts 1 day September 9, 2022 8:00 AM September 9, 2022 5:00 PM

369 Resolve and close open Issues 2 days September 12, 2022 8:00 AM September 13, 2022 5:00 PM

370 Finalize Project Closeout Report 2 days September 14, 2022 8:00 AM September 15, 2022 5:00 PM

371 Obtain Sign-off for Project Closure and Results Acceptance 1 day September 16, 2022 8:00 AM September 16, 2022 5:00 PM

372 Run 0 days September 6, 2022 5:00 PM September 6, 2022 5:00 PM

373 Operate Solution 0 days September 6, 2022 5:00 PM September 6, 2022 5:00 PM

374 Safely and Efficiently Operate the new Solution 0 days September 6, 2022 5:00 PM September 6, 2022 5:00 PM

375 Continuously Optimize IT Operations 0 days September 6, 2022 5:00 PM September 6, 2022 5:00 PM

376 Improve and Innovate Solution 0 days September 6, 2022 5:00 PM September 6, 2022 5:00 PM

377 Periodically Update your SAP System 0 days September 6, 2022 5:00 PM September 6, 2022 5:00 PM

378 Initiate a new Innovation Cycle 0 days September 6, 2022 5:00 PM September 6, 2022 5:00 PM