Real-Time Construction Project Progress
Real-Time Construction Project Progress
2007
Follow this and additional works at the FSU Digital Library. For more information, please contact [email protected]
THE FLORIDA STATE UNIVERSITY
COLLEGE OF ENGINEERING
By
AMINE GHANEM
Degree Awarded:
Summer Semester, 2007
The members of the Committee approve the Dissertation of Amine Ghanem
defended on June 8, 2007.
________________________
Yassir A. AbdelRazig
Professor Directing Dissertation
________________________
Jeffrey R. Brown
Outside Committee Member
________________________
John O. Sobanjo
Committee Member
________________________
Wei-Chou V. Ping
Committee Member
Approved:
___________________________________________________________
C. J. Chen, Dean, College of Engineering, Florida State University
The Office of Graduate Studies has verified and approved the above
named committee members.
ii
To
My parents,
Abdallah and Aicha
And my sisters
Lina, Dima, and Nadine
Who made all of this possible
For their endless encouragement and support
And also to
My fiancé
Nermine Majzoub
For her love and patience
iii
ACKNOWLEDGEMENTS
First and foremost, I thank Allah for His continuous bounties and guidance
in my life.
This dissertation concludes a learning journey at Florida State University. I
am grateful to many individuals who contributed to my learning experience at
Florida State University.
I would like to express my sincerest thanks to many key people: At the top
of the list, my advisor, Dr. Yassir AbdelRazig for his valuable guidance,
inspiration, and advice. Sincere appreciation is also extended to my committee
members: Dr. Jeffrey R. Brown, Dr. John O. Sobanjo, and Dr. Wei-Chou V. Ping,
who gave their time and input to my research. I would like also to thank Dr.
Garold Oberlender for his unconditional support and valuable advice and
feedback.
The assistance offered by Sperry & Associates and Haskell Company to
collect valuable data should be gratefully acknowledged here.
This research would not have been possible without the people who took
part of the survey I performed, and to whom I have promised anonymity. I am
also very thankful to my colleagues Dr. Mohamad El-Gafy, Mr. Rassem Awwad,
and Mr. Hassan Ghanem whose help in some of the conceptual thinking was
invaluable.
iv
TABLE OF CONTENTS
v
3.1.1.3 Pen Tablet/Touch PC...................................................Page 33
3.1.1.4 Rugged Notebooks ......................................................Page 34
3.1.1.5 Wearable Computers/Digital Hardhats.........................Page 34
3.1.1.6 Digital Pen....................................................................Page 34
3.1.2 Networks ............................................................................Page 35
3.1.2.1 Wireless Wide Area Networks......................................Page 36
3.1.2.2 Wireless Local Area Networks .....................................Page 36
3.1.2.3 Satellites Networks.......................................................Page 38
3.1.3 Mobile Applications ............................................................Page 39
3.1.3.1 CAD Applications .........................................................Page 39
3.1.3.2 Data Capture Applications ...........................................Page 39
3.1.3.3 Project Management Application..................................Page 40
3.2 Technology Assessment Methods.....................................Page 40
3.2.1 Assumptions and Fundamentals of Utility Theory .............Page 41
3.2.2 Types of Utility Functions .................................................Page 43
3.2.3 Hierarchical Structure of MAUT.........................................Page 45
3.2.3.1 Defining Evaluation Objectives ....................................Page 45
3.2.3.2 Defining Alternative Attributes......................................Page 45
3.2.3.3 Attribute Characteristics ...............................................Page 46
3.2.3.4 Assigning Attribute Weights .........................................Page 46
3.2.4 Analytical Hierarchy Process.............................................Page 48
3.2.4.1 Setting Priorities ..........................................................Page 49
3.2.4.2 Pairwise Comparison Scale.........................................Page 49
3.2.4.3 Eigenvector Prioritization Method ................................Page 50
3.3 Computer Construction Simulation ....................................Page 53
3.3.1 General Modeling and Simulation Systems.......................Page 53
3.3.1.1 GPSS...........................................................................Page 54
3.3.1.2 HOCUS ........................................................................Page 54
3.3.1.3 ITHINK.........................................................................Page 55
3.3.1.4 SLAMII.........................................................................Page 55
3.3.2 Construction Simulation Using Networks...........................Page 55
3.3.2.1 Cyclone........................................................................Page 55
3.3.2.2 RESQUE.....................................................................Page 56
3.3.2.3 COOPS........................................................................Page 57
3.3.2.4 CIPROS ......................................................................Page 57
3.3.2.5 STROBOSCOPE ........................................................Page 57
vi
4.3 Implementation Steps........................................................Page 66
4.3.1 Work Progress Measurement ......................................Page 69
4.4 Construction of Data Management System ......................Page 69
4.4.1 Data Dictionary..................................................................Page 70
4.4.2 Project Database ...............................................................Page 73
4.4.2.1 Database Queries ........................................................Page 74
vii
6.7.3.1 Cost Benefit Analysis ...................................................Page 136
6.7.4 Function D: E-Document Management .............................Page 137
viii
LIST OF TABLES
ix
Table 6.7: Benefits Calculation of Function A Case Study 1...................Page 129
Table 6.11: Cost Benefit Analysis of Function B Case Study 1...............Page 132
Table 6.12: Cost Benefit Analysis of Function B Case Study 2...............Page 132
Table 6.14: Rework & Process Elimination Savings Case Study 1 .........Page 135
Table 6.15: Rework & Process Elimination Savings Case Study 2 .........Page 135
Table 6.18: Cost Benefit Analysis of Function C Case Study 1 ..............Page 136
Table 6.19: Cost Benefit Analysis of Function C Case Study 2 ..............Page 136
x
LIST OF FIGURES
xi
Figure 4.8: Erection Drawings.................................................................Page 76
xii
ABSTRACT
xiii
CHAPTER 1
INTRODUCTION
1.1 Background
Construction is one of the largest industries in the United States, and its
second largest employer after government agencies. According to an
employment report from the U.S. Bureau Labor Statistics, construction
employment in the U.S. in the second quarter of 2005 account for roughly 7.2
million, or 5.4 percent of non-farm payroll employment (U.S. Census Bureau
2004). Moreover, the value of construction invested, a measure of the amount
spent on design, engineering, and construction, totaled $ 1 trillion in May 2004,
according to the Census Bureau. This amount is equivalent to roughly eight
percent of the U.S. gross domestic product (GDP). However the construction
industry has suffered from low performance due to low productivity, high accident
rates, late completion, and poor quality (Kashiwagi et al., 2004). In 2003, the U.S.
Bureau of Labor Statistics showed that labor productivity in construction has
been lagging behind other U.S. industries (see Figure 1) for the past 40 years.
A study performed by Nuntasunti (2003) summarized five factors
preventing the construction industry from improving performance: 1)
Fragmentation of the construction industry; 2) project specific nature of
construction; 3) temporary nature of relationships; 4) competitive bidding system;
and 5) stand alone islands of communication.
A construction project essentially involves a large amount of information of
various types. This is due to the fact that different parties perform independent
tasks on a project to produce a single final product. Since the design of a project
must somehow be communicated to many parties on the construction site, it is
important that clear information, coherent and efficient communication exist to
ensure successful work by all participants in the project. The specifications must
1
be translated into information that all parties can use in fulfilling their tasks.
Hence, the need for drawings, contracts, specifications, building codes, and other
forms of information emerges. At the same time, the performance of the project
must also be communicated back to management so that it can be controlled
effectively.
Figure 1.1: Construction Labor Productivity Index versus All Non-farm U.S.
Industries
2
1993). Information technology (IT) was developed as a means of meeting
complex information demands and of automating the tasks associated with them.
Advances in IT promised great leaps in productivity in the late 20th century,
however few industries have truly profited from IT’s promises. In the same
manner, automation technologies such as robotics offered similar benefits to the
construction industry with few tangible benefits yet realized (Skibniewsky and
Hendrickson 1990, Farid 1993).
The construction industry lags behind other industries in adopting
innovative new technologies. The need to accelerate the rate of technological
adoption in the construction industry has been well documented in the literature
(Mitropoulos and Tatum, 2000). This adoption comes from continuously seeking,
recognizing, and implementing new technologies that improve construction
processes (Laborde and Sanvido 1994). Each technology has its own technical,
economic, and risk considerations that make the selection process a difficult one.
The selection decision involves many tradeoffs among technology attributes.
Unlike the structured environment and highly repetitive processes in
manufacturing, construction poses many barriers to the implementation of
advanced technologies. Characteristic fragmentation, diversity, and fierce
competition of the construction industry combine to make research and
development (R&D) difficult (Tucker 1988). In a fiercely competitive environment
with thin profit margins, individual firms, especially the smaller ones, simply can’t
afford to conduct R&D or pay added regulatory costs of introducing new
technologies. In 1997, the industry spent only 0.6 percent of total revenues on
R&D, whereas most other industries committed 4 to 6 percent. An unfocused and
uncoordinated effort among the various R&D sectors makes this chronic under-
funding worse. The National Institute for Standards and Technology (NIST), the
Department of Transportation, and the Department of Energy sponsor conduct,
or cost-share with industry and academia research activities. The National
Science Foundation (NSF) funds more than 70 percent of academia’s
construction R&D efforts. The Army Corps of Engineer’s Engineering Research
and Development Center and the Naval Facilities Engineer Command’s
3
Engineering Service Center conduct lion’s share of government R&D. The
construction industry has barely just begun to examine ways of integrating its
management processes with information technology into a unified system. Non-
profit organizations such as the Construction Industry Institute (CII) and the
National Institute of Standards and Technology (NIST) are spearheading these
efforts through their FIATECH (Fully Integrated and Automated Technology) and
CONSIAT (Construction Integrated and Automation Technology) programs,
respectively, and are starting to address the barriers that stand in the way along
with research in Enterprise Resource Planning (ERP) in construction at other
institutions (O’Connor and Dodd 2000).
4
is needed between the site office and field personnel (Thorpe and Mead 2001).
These extra efforts are time consuming and waste of money. These inefficiencies
are embedded and distributed among many different activities and project
participants, and hence, the project team is generally not aware of the
implications and aggregate time and money waste associated with them.
Wireless technologies can be used to improve the accuracy and timeliness of the
data collected from sites and to improve communication flow. Previous research
on such technologies mainly discussed the technological feasibility of using a
particular technology to support various construction project tasks (Akinci et al.
2005, Jaselskis et al. 1995). But still there is a need for a comprehensive
framework to assess the effectiveness of using such technologies that
encompasses all different merits together: performance, reliability, risk, and cost.
The following section summarizes several problem areas in the
construction that this thesis will address:
(1) Independent islands of communication on the construction site:
Lacks of effective communication among various parties involved in
construction projects make information exchange inefficient. Moreover,
paper-based handling of change orders and Request for Information
(RFIs) increases difficulties in information exchange in a timely manner.
Even though project participants have been using various project
management tools to improve communication, there are still deficiencies
in updating the schedule and the progress of the construction project in a
real time fashion
(2) Obsolete paper-based and as-built drawings:
Paper prints are currently used to exchange design, shop, erection, and
as built drawings between project participants. Duplication of effort,
inconsistencies, errors, missing information, and extensive time needed to
find relevant information are common in paper-based documents.
(3) Decrease in productivity created by ineffective flow of information:
This problem is created by lack of information about availability of
materials on the construction site. Materials handling and storing is also a
5
problem. Time is commonly wasted trying to figure out where materials
are on the construction site, and whether or not there is enough quantity.
(4) Lack of assessing method for decision makers to select a
technology:
Each technology has its own technical, economic and risk consideration
that make the selection process difficult. Considering one aspect in
choosing and ignoring the others may not lead to the optimal decision.
Currently there are no tool that rationalizes and facilitates this complicated
decision making process.
6
(4) Developing a hybrid model for wireless technologies selection,
assessment and implementation.
(5) Applying the model on a pre-engineered steel construction and performing
a life cycle cost and cost benefit analysis, to illustrate the model
framework.
7
1.4.2 Models Formulation
The first step in this phase is to acquire and set up the hardware and
software required for the different phases of the research. Another step is to
establish the procedure of how resources on the construction site will be tracked,
by identifying the appropriate type of measurement method. This step is
achieved by investigating each activity in the main schedule, and assigning the
appropriate resources whether it is equipment, materials or labors resources.
The following step is to develop a central database where all information
captured on the construction site is sent to this database. This step is achieved
by creating different kind of relationships between the proposed tables using
Microsoft access. In this case SQL is used to establish appropriate queries.
The next step is to choose the right hardware and software for the real-
time tracking model by formulating a multi attribute utility model. The main part of
this stage is to construct a hierarchy of influence that includes the main objective,
criteria of evaluation and alternatives to be assessed. Then it uses eigenvector
prioritization method to develop a hybrid model for wireless selection and
assessment. The objective of this phase is to formulate the basic structure of the
hybrid assessment model for wireless technologies selection.
8
Figure 1.2: Research Methodology
9
1.5 Dissertation Organization
10
information about smart chips. Appendix B contains information of the survey
conducted in this research. Appendix C contains information about the data
gathered from both case studies. Appendix D contains information about the
simulation input and output files.
11
CHAPTER 2
This chapter lays necessary foundation for the research and includes
review of prior research efforts. The literature review of prior research efforts
includes reviewing the application of information technologies and the use of
barcode and Radio Frequency Identification (RFID) in the construction industry
and discusses the different application of each technology. In addition to the use
of smart chips, this chapter describes wireless technologies and its application on
the construction site. Then an ASCE survey presented by the CI wireless
committee is presented to identify barriers to wireless application. Finally the
needs for information and for users on the construction site are identified.
A simple project can be planned as a list of tasks with their start and finish
dates written on a piece of paper. A complex plan on the other hand, might deal
with thousands of tasks, resources, and a project budget of billions of dollars. As
the project becomes more and more complex, so does the requirement for a
project management system. It is a good practice to monitor a project’s
performance continuously throughout its various phases in order to maintain
certain cost, time, quality, and safety criteria. This will also help ensure that a
project can be completed within budget, on schedule, at the desired quality, and
with an acceptable safety record.
One of the main way of controlling a project’s quality, cost, and schedule
performance is to continuously monitor activities during the construction phase in
order to keep track of work done: materials and equipments used versus installed
12
quantities. These quantities can then be compared against quantities estimated
during the planning phase to gauge the project’s performance.
Construction Industry Institute (CII) uses six different methods to measure
the work progress at the construction jobsite, depending on the type of work to
be done. Table 2.1 summarizes these methods.
13
processor, or a spreadsheet documents before reaching the scheduler on a
weekly or monthly basis.
Repass et al. (1995) developed a new tool called updater to improve
efficiency and effectiveness of construction schedule updating. It employs
emerging palm-held computer technology to automate processes currently bound
to manual paper-based methods due to incompatibilities between computers and
the harsh construction environment.
Chin et al. (2005) presented a real time 4D CAD + RFID for project
progress managements. The model mainly presented building elements in 3D
CAD models according to as-built progress, where the as-built information is
collected in real-time by sensing the progress throughout the supply chain using
RFID. 4D+RFID aimed at supporting processes with a focus on structural and
curtain wall elements, such as steel columns and beams, concrete slabs, and
curtain walls, which are typically on the critical path of project schedules in high-
rise building construction projects. The process is that RFID is applied to sense
the progress status of ordering, delivery, receiving, and erection of building
elements, and then the as-built progress information is presented in 3D CAD
models.
Poku et al. (2006) developed a system called PMS-GIS (Progress
Monitoring System with Geographical Information Systems) to represent
construction progress not only in terms of a CPM schedule but also in terms of a
graphical representation of the construction that is synchronized with the work
schedule. In PMS-GIS, the architectural design is executed using a computer-
aided drafting (CAD) program (AutoCAD), the work schedule is generated using
a project management software primavera (P3), the design and schedule
information (including percent complete information) are plugged into a GIS
package (ArcViewGIS), and for every update, the system produces a CPM-
generated bar chart alongside a 3D rendering of the project marked for progress.
The GIS-based system developed in this study helps to effectively communicate
the schedule/progress information to the parties involved in the project, because
14
they will be able to see in detail the spatial aspects of the project alongside the
schedule.
Memon et al. (2005) presented a system that integrated Auto CAD and
digital photos to track the progress of construction project. The system proposed
is called Digitalizing Construction Monitoring (DCM) Model. It has made a
practical attempt to automate the process of producing as-built construction
schedule by applying modern photogrammetry techniques to photographs and
integrating with CAD drawings. The applications of DCM model in monitoring the
progress enables project management team to better track and control the
productivity and quality of construction projects.
15
about installed quantities at the jobsite, which can then be matched with resource
expenditures such as labor hours, equipment use, etc. (Halpin 1985).
Potential application for materials tracking in commercial construction
include concrete placement operations and steel frame components tracking.
These applications provide viable uses because they offer incremental
improvements over existing methods, reduced labor costs, real-time identification
and tracking and they provide the potential for automatic billing upon receipt of
materials at a jobsite.
Jaselskis et al. (1995) proposed a system using RFID technology to
control concreting operations that would ensure proper delivery, billing, and
quality control for concrete. The process starts when the contractor places an
order with the concrete supplier. The requirements for the concrete mix and the
ID numbers for the assigned trucks would be transmitted to a computer in the
batch plant. Next the RFID tag would be programmed to provide concrete mix
admixtures, time of loading, and delivery location. When the truck arrives at the
jobsites, a scanner would read the RFID tag and communicate by RF link to the
jobsite computer. The RFID tag information would be matched with the electronic
data information from the plant. After the concrete placement is completed, the
concrete truck would again pass the scanner and the delivery completion time
would be transmitted to the concrete supplier to make plans for the next truck. In
the same paper, Jaselskis presented a system to manage critical materials on
the construction site. The system consists of assigning an RFID tag for each
material delivery vehicle. Each package of critical material would also have an
RFID tag. Both the vehicle and package tags would be read at the gate and
recorded on the jobsite computer. The jobsite computer would maintain
databases of materials on hand and their storage location, as well as materials
installed. The saved information was used to trigger payments from the
contractor to suppliers and generate requests for progress payments from the
contractor to the owner (Jaselskis et al. 1995)
Yagi et al. (2005) proposed the concept of parts and packets unified
architecture that allows parts or units to signal change in their attributes as they
16
go through the complex production system. The combination of RFID and glue
logic or active database was proposed as a possible control mechanism, which
achieves the required dynamic equilibrium for construction activity without
hindrance or halt of production at worst. When a chip implanted part passes
through a gate, the gate reads the product URL of the part. It determines what it
is, where it is, when it is, as well as in what state it is. The corresponding data
point in the glue logic is then altered, which generates an event and a chain of
succeeding actions.
Tserng et al. (2005) presented a web-based portal system that
incorporates wireless technology and mobile devices to improve the efficiency
and effectiveness of data acquisition on site and information sharing between
participants to assist the managers to control and monitor the delivery progress
in a construction supply chain delivery. The MConSCM system not only improves
the data acquisition on site efficiency by using automated bar code enabled PDA,
but also provides a monitor to control the construction progress.
17
applications. The technology has applications in both automated as well as
traditional construction sites (Oloufa et al. 2003).
Goodrum et al. developed a prototype tool tracking system to track tools in
a mobile environment and to inventory hand tools that may be located in either
mobile gang boxes or truck boxes. Active RFID technology has significant
potential to improve tool inventory and allocation on a construction jobsite. The
RFID tags have the capability to provide adequate read range and durability
needed for a tool tracking and inventory system research used active RFID tags
in the prototype tool tracking system (Goodrum et al. 2005).
18
mobile field workers but exploit existing handheld computing and sensor
technology (Pascoe 1998).
Liu et al. (1997) proposed the Digital Hard Hat (DHH) technology, which
enables dispersed users to capture and communicate multimedia field data to
collaboratively solve problems, and collect and share information. The DHH is a
pen based personal computer running Windows XP. It is used to collect
multimedia information. Special software called Multimedia Facility Reporting
System allows the field representative to save multimedia information into a
project specific database, which is then accessible to others through the World
Wide Web. The pen-based computer can also be used to communicate between
the construction site and other locations using a direct network connection, a
wireless network connection or any means of cellular communications.
Brilakis (2006) presented a case study on long-range, wireless
communications suitable for data exchange between construction sites and
engineering headquarters. He defined the requirements for a reliable wireless
communications model where common types of electronic construction data will
be exchanged in a fast and efficient manner, and construction site personnel will
be able to interact and share knowledge, information and electronic resources
with the office staff.
Singhvi et al. (2003) developed a context-aware information system
designed to deliver up to-date project information from the main office to the
construction site. The objective was to help the user manage the complexity of
the construction data by proactively tracking current resource requirements and
proactively obtaining access to context-relevant information and services. To
achieve this, the system used off-the-shelf handheld computing devices and an
on-site wireless network for local communication. This allowed continuous
access to data and resources as users moved around the job site. This work
highlighted the benefits of context-aware computing for on-site information
delivery at a construction site and the need for better communication methods.
Tsai et al. (2006) developed a synchronous system integrated with
wireless and speech technologies for on-site data collection. The system was
19
applied in a material management case study, in which construction workers
communicated directly with application devices to achieve synchronous
operations and simplify manual data entry. After the system tests, analytical
results relating to efficiency improvement indicate that the proposed synchronous
system increased productivity, time efficiency and comparative work efficiency
due to the decreased lead processes and operation time.
2.3 Barcode
The most popular ones are the Universal Product Code (UPC), the
European Article Numbering (EAN), Code 39, Interleaved 2 of 5 Code, and Code
128….etc. Code 39 is being used in construction and most construction related
applications (Blakey1990). In general, barcodes can be classified into three main
categories: linear, stacked, and matrix barcodes. Compared to linear barcode,
20
stacked and matrix barcodes have more data capacity and resist damage. More
information is presented in appendix A.
21
sight and become unreadable if they are scratched or dirty. Radio Frequency
Identification technology seems to solve all these problems encountered by the
use of barcode.
2.4 RFID
22
Figure 2.2 Antenna sealed with RFID tag
There are two classifications of RFID tags: passive and active. The means
in which they receive power for transmission determines their classification.
Passive tags depend on a power source provided by the RFID reader’s energy
field and may have read-write or read-only capabilities, whereas, the active tags
have an internal power source and are rewritable. Passive tags generally have
shorter read ranges but have a life that usually outlasts the object that it is
identifying. Active tags have longer reading ranges, high memory, and better
noise protection. However, these tags are larger and heavier, more expensive,
and have a shorter life (3 – 10 years) than passive tags. Read-only tags are used
for simple identification purposes because they can only store a limited amount
of information that cannot be altered. Such tags may be used to identify a
package of nails or screws because they have many applications and are not
designated to a particular item or activity.
2.4.2 Antenna
The function of the antenna attached to a reader is to transmit an
electromagnetic field that activates a passive tag when it is within reading range.
Once a passive tag is activated it can transmit information from its antenna to
that of the reader where it is processed. During rewriting applications the antenna
of the reader acts as a relay device in the reverse direction, the reader
communicates a message through its antenna, which transfers and stores the
23
new data to the activated transducer via its antenna. The RFID tag’s antenna is
practically maintenance free and can be configured in a variety of shapes and
sizes ranging in size from a grain of rice to the size of a brick (Zebra
Technologies, 2002).
2.4.3 Reader
Reader monitors incoming signals from the transponders to ensure valid
tag data and error free operation. Depending on the applications, readers may be
integrated into handheld computers or they may be stationary and positioned at
strategic points, such as a facility entrance or on an assembly line (Zebra RFID
Passive Tag Reader) (see Figure 2.3). The handheld readers offer portability,
however, the stationary devices offer a larger reading range. As stated above,
readers have an antenna for sending and receiving signals and a processor for
decoding them. The reader receives instructions and information from the
antenna through the scanner, which is a part of the reader that examines analog
output from the antenna. The scanner’s information is then converted into a
digital format by the reader, which the computer or processor can then use for
data analysis, recording, and reporting (CII, 2001). There are readers today that
can simultaneously read 100 to 2000 tags per second.
24
2.4.4 RFID Applications in Construction
Radio Frequency Identification technologies provide a wireless means of
communication between objects and readers. RFID has a place in construction
because it provides the industry a potential to improve construction productivity,
quality, safety, and economy, cutting labor and material costs and enhancing
project schedules. There have been quite few publications on RFID research and
applications in construction.
Radio Frequency Identification (RFID) has emerged as a technology that
can be effectively applied for real time measurement of project information in the
construction industry, such as for labor management, safety management,
equipment management, and progress management of various works including
concrete, pipe spools, earthwork, structural steel works, and curtain walls.
Furthermore, it is expected that RFID will improve the limits on progress
management (Jaselski 2003, Yagi 2005, and Song 2005).
The most prominent application of RFID in construction has been its ability
to improve the efficiency of the materials and equipment management process.
In a case study conducted by Bechtel in their $338 million Red Hills Project, time
spent locating and tracking pipe support and hangers was reduced by 30% (CII,
2002).
Rohm & Hass conducted an RFID pilot study that received, identified, and
tracked Honeywell smart instrument installation. Benefits outlined from this case
study can be summarized in inventory shrinkage, decrease of rework costs,
improvement in data integrity (CII, 2001).
Ngai et al. (2005) presented a case study on the development of an RFID
prototype system that is integrated with mobile commerce in a container depot.
They concluded that the system keeps track of the locations of stackers and
containers, provides greater visibility of the operations data, and improves the
control processes.
El-Misalami (2003) proposed a system using RFID to track the activities of
workers and equipment at the construction site. The resulting records were used
to update the cost control system. Each worker would have a read write RFID tag
25
to record his activities. The tag would be approximately the size of a credit card
and could be used as a worker identification badge. The use of equipment would
be tracked by associating the equipment with the operator and the operator’s
activity. The system was adapted for both tool-room checkout and large
equipment management.
RFID can also provide security to construction jobsites. Workers,
operators, and equipment tagged with RFID can record and make certain proper
usage and handling of equipment, materials, and documents. These systems
would also ensure that only qualified equipment operators have the ability to
operate restricted equipment, reducing the likelihood of misuse and accidents
(Durfee 2002).
Song et al. (2006) presented a case study of fabricated pipe spools in
industrial projects. Field tests of current RFID technology were conducted to
determine technical feasibility for automatically identifying and tracking individual
pipe spools in lay down are yards and under shipping portals Potential benefits
found from the use of RFID technology in automated pipe spool tracking may
include (1) reduced time in identifying and locating pipe spools upon receipt and
prior to shipping, (2) more accurate and timely information on shipping, receiving,
and inventory, (3) reduced misplaced pipes and search time, and increased
reliability of pipe fitting schedule.
26
coherent and efficient communication exist to ensure successful work by all
participants in the project. The specifications must be translated into information
that all parties can use in fulfilling their tasks. Hence, the need for drawings,
contracts, specifications, building codes, and other forms of information emerges.
At the same time, the performance of the project must also be communicated
back to management so that it can be controlled effectively. In order to explore
and develop new effective methods of information management on the
construction site, the starting point should be identification of on site construction
information.
27
Another study performed by Chen and Kamara showed that on site
construction information is grouped into twelve categories including drawings,
material information, equipment information, contract, progress, safety
information, sub-contractor information, design clarification, construction
methods, specification, labor information, and quality information (Chen and
Kamara 2006).
Scott and Assadi summarized sites records into three main categories
which consist of information related to finance, quality, and progress. Especially
the progress records typically kept by contractors and supervisors aim to identify
the project life cycle information consisting of weekly progress reports, day work
sheets, photographs, as-built schedule, and minutes of progress meetings (Scott
and Assadi 1999).
Bowden et al. indicated that the main type of information that the people
onsite deal with is paper based, which constitutes a disadvantage for site
information communication and exchange (Bowden et al. 2004). Lack or
inefficiency of information exchange can result in people on construction site
overlooking important issues that require immediate response and often causes
on site delays and loses in schedule and cost (Singhvi and Terk 2003).
28
and can’t be applied with traditional information management methods, relying
mostly on paper-based documents. The next section presents a framework of a
real time model to track the progress of the construction project.
29
Using another set of questions regarding the use of cutting edge computer
tools and means, CAD percentage was the most used with a percentage of more
than 60%. Video conference, web portal, and e-Learning come in second place
with 42%. RFID and GIS are still underused and have low percentage of less
than 20%. What is surprising is the percentage of barcode which is relatively low
especially that it has been introduced to the construction industry for a while.
$
"#
!
!
'
&
%
Figure 2.5 Cutting Edge Tools Used in the Construction
30
software, the fee of wireless services providers, the salaries of in-house technical
support personnel, the training of the users (De la Garza & Howitt, 1998).
The typical construction project brings together several disciplines and a
large number of subcontractors that have little incentive for sharing risks. Each
subcontractor is held responsible for their individual work which promotes a low
tolerance for risk within the industry. This prevents technology adoption.
Training and tech support need is another major concern of the
respondents. This lack of expertise may be a sign that use of wireless technology
in construction is still at its early stage. Data security and risk of data loss also
are barriers to its application. Till now, all communication systems are
susceptible to being violated and there is possibility that the information
transmitted being received by undesired users. So the information sent has to be
classified according to importance and how sensible it is so that precautions
would be taken.
Another factor that we can’t overlook is the lack of metrics to assess value
and quantify benefits of applying these technologies.
31
CHAPTER 3
BACKGROUND
This chapter lays necessary background for the research and includes
necessary information to conduct the research. First a detailed description of
wireless technologies is given, accompanied with identification of different parts
pertaining to this technology. Then a review of the concept of decision-making
and utility theory is presented. That includes an outline about the basics and
assumptions of the utility theory, followed by a description of different techniques
used in multi criteria decision-making. Furthermore, a definition of computer
simulation and its uses in construction is discussed to lay the necessary
background for the coming chapters.
32
digital assistants, 2) handheld computers, 3) pen tablet/touch PC, 4) rugged
notebook PC, 5) wearable computers/digital hardhats, and 6) digital pens
(COMIT 2005).
33
a stylus. They are usually made to meet the rugged standards since they are
intended for use in the field. They run on a full desktop operating system that has
been modified for touch screen interface and handwriting recognition. Most tablet
PCs offer all the features available to sophisticated PDAs and handheld
computers, plus some additional features and more power. An average size
tablet PC is about the size of a standard sheet of paper.
34
capability to perform this function very efficiently. Digital pens are able to store a
certain amount of standard size sheets of paper depending on the amount of
memory they have. Some of the digital pens researched can store up to 100
standard sheets.
3.1.2 Networks
Networks, which can support the connection and communication of mobile
computers with sufficient bandwidth, include all types of wireless networks such
as Wireless Wide Area Networks (WWAN), Wireless Local Area Networks
(WLAN), and satellite networks (COMIT 2005).
35
3.1.2.1 Wireless Wide Area Networks
WWAN covers a much more broad area than wireless LAN. According to
Fisher and Wang, today’s most wireless data links in the U.S takes place across
conventional second generation (2G) personal communication networks. The
transmission speed provided by 2G is up to 20 kbps. With the advent of 3G
networks, communication speed can reach 2 Mbps in fixed applications, although
most commercial deployments offer actual transmission rates closer to 100 kbps
in mobile environments. Although the third generation wireless technology has
not yet been fully implement throughout the world, the world’s leading companies
in this market. Samsung are already laying the groundwork for forth generation
(4G) technology.
36
wireless technology currently undeveloped. It provides much larger range and
data bandwidth than WiFi does, which enable it transfers data intensive streams
such as videos. With a range up to 30 miles, a WiMax network can cover most
construction sites special cases such as road construction. Some municipals
have been considering using this technology to provide WiMax based wireless
cloud to cover the entire city. WiMax may become available some time in 2007.
There are three physical layers for WLANs: two radio frequency
specifications, and one infrared. WLAN configurations vary from simple,
independent, peer-to-peer connections between a set of PCs, to more complex,
intra building infrastructure networks. There are also point to point and point to
multipoint wireless solutions. In a typical WLAN infrastructure configuration, there
are two basic components:
i) Access Points: An access point/base station connects to a LAN by
means of Ethernet cable. Usually installed in the ceiling, access points receive,
buffer, and transmit data between the WLAN and the wired network
infrastructure. A single access point supports on average twenty users and has a
coverage varying from 20 meters in areas with obstacles (walls, stairways,
elevators) and up to 100 meters in areas with clear line of sight. A building may
require several access points to provide complete coverage and allow users to
roam seamlessly between access points.
ii) Wireless Client Adapter: A wireless adapter connects users via an
access point to the rest of the LAN. A wireless adapter can be a PC card in a
laptop, an ISA or PCI adapter in a desktop computer, or can be fully integrated
within a handheld device.
Bluetooth is a technology specification for small form factor, low cost,
short-range wireless links between mobile PCs, mobile phones, and other
portable handheld devices, and connectivity to the Internet. Bluetooth covers a
range of up to ten meters in the unlicensed 2.4 GHz band. Because 802.11
WLANs also operate in the same band, there are interference issues to consider.
Bluetooth technology and products started being available in 2001, but
37
interoperability seems to be a big problem. By mid 2002, WLANs migrate to the
5GHz band to avoid this problem.
Broadband wireless (BW) is an emerging wireless technology that allows
simultaneous wireless delivery of voice, data, and video. BW is considered a
competing technology with digital subscriber line (DSL). It is generally
implemented in metropolitan areas and requires clear line of sight between the
transmitter and receiving users.
38
video surveillance. The three main cost elements involved with setting up satellite
service are equipment purchases; service fees; and set up, training and license
fees (Web 2, 2004).
39
or 2) form building software, which can be manipulated to create what ever form
is desired. SHERPA (Ward et al., 2003) is one of the mobile data capture
systems, which enables users to utilize workforce driven mobile computers to
collect real time piling work data in the field through a WLAN.
40
judgments may become exceedingly difficult. Utility Function model was
developed to help individual decision maker facing a choice involving uncertainty
about outcomes (Dyer et al. 1992).
The main consideration is how to structure and assess an aggregate utility
function such that:
U (x1, x2, …….. xn) = ƒ [u1(x1), u2(x2), …….. un(xn)], Equation 3.1
Where Ui designates a utility function over single attribute xi
41
organization will display a clear intuition of preference between two events, even
if these events are uncertain. The axioms are the most obvious semantic
constraints on preferences with lotteries. The set of axioms involve some very
complex mathematical proofs that this author feels it is beyond the scope of this
thesis.
The first axiom is that of Orderability: Given any two states, the rational
agent prefers one of them, else the two as equally preferable. The decision
maker possesses a complete ordering of all alternatives available to him.
42
3.2.2 Types of Utility Functions
Traditional multiple attribute utility theory provides a methodology for
selecting from among a set of alternatives in the presence of uncertainty. In this
process, the degree of liking of the various possible decision outcomes is
evaluated and further described by probability density functions (utility functions).
Based on the identified utility functions, the degree of liking for each alternative,
commonly referred to as the expected utility, is calculated and used in the
selection process.
The degree of liking of the various possible decision outcomes is
evaluated and further described by probability density functions. Based on the
identified utility functions, the degree of liking for each alternative, commonly
referred to as the expected utility, is calculated and used in the selection process.
The assessment of a multiple attribute utility function is usually
accomplished by decomposing this function into m single attribute functions.
Each of these single attribute utility functions, Ui(yi), i =1, 2,…..,m, identifies the
degree of liking on the part of the evaluator of the various possible values that
can be associated with attribute i. Among all, two values, UL and UH are of a
particular significance. Typically, UL represents the value where the degree of
liking reaches zero, while UH represents the value where the degree of liking
reaches its ultimate level of 1.0. This can be translated into
Ui (UL) = 0.0 and Ui (UH) = 1.0
Between the two values UL and UH, the degree of liking varies from 0.0 to
1.0. The shape of the utility function Ui(yi), that depicts such change depends on
the evaluator’s risk attitude.
For utility independent attributes, the additive multiple attribute utility
function takes the form
ui(y1, y2, ….., ym) = w1u1(y1) + w2u2(y2) + ...... wmum(ym) Equation 3.2
Where ui(yi) = single attribute utility function for attribute i and ranges from
0.0 to 1.0; yi range of values taken by attribute i ; and wi corresponds to the
relative importance of attribute i.
43
Relative importances are positive numbers that sum up to unity. In
traditional MCDM problems where an alternative needs to be selected, the
expected utility value is calculated for each alternative based on equation 3.2.
Accordingly, the alternatives can be ranked and the alternative with the highest
EU value is then selected
The shape of the utility function ui (yi) identifies the degree of liking on the
part of the evaluator of the various possible values that can be associated with
attribute i. The utility curve may be simply straight line used for risk neutral
attitude, risk aversion, or risk seeking (Georgy 2005). Before finalizing the overall
decision-making process, a utility function (equation) must be fitted for the
decision criterion. The list of applicable standard forms of utility functions (Lifson
and Shaifer 1983) includes three types as shown in figure 3.2:
U(x) = A(1 + eBx )
U(x) = Ax + B
U(x) = A + Bcx
Where,
U(x) = utility value for decision attribute’s level x
X = decision attribute’s level
A, B, c = constants
44
The straight-line function, used for risk neutral attitude, is commonly
employed in practical applications.
45
3.2.3.3 Attribute Characteristics
It is important that the set of attribute be complete, so that it covers all the
important aspects of the problem; operational, so that it can be meaningfully
used in the analysis; decomposable, so that aspects of the evaluation process
can be simplified by breaking it down into parts; non-redundant, so that double
counting of impacts can be avoided; and minimal, so that the problem dimension
is kept as small as possible (Keeney 1976). Once a satisfactory level of
determining the attributes is reached, the quantification process begins by
defining suitable attribute measures. For example, the cost attribute is measured
in dollars. Unfortunately, not all attribute measures are quantifiable. However,
those non-quantifiable attributes can be defined in a subjective way. An example
of non-quantifiable attributes would be the friendly use of a new technology. The
subjective ratings for this attribute would depend on the personal judgment of the
decision maker (El-Misalami 2001).
46
assigns weights, wi (i = 1,…, m), to each of the m attributes. In order to assess
these weights, the relative importance of each attribute is determined by the
decision maker on a scale of 1 to 10 or 1 to 100. The next step requires the
decision maker to evaluate how well each of the n alternatives performs with
respect to each of the m attributes. In order to accomplish this, a numerical value
is assigned to indicate the degree to which each alternative achieves each
attribute. The worth of each alternative is then computed using a linear weighted
sum relationship and the alternative with the highest value is selected as the best
option.
In the utility-based methods, the decision maker answers some trade-off
questions to specify the single attribute utility functions, to select the form of the
multi attribute function, and to determine the scaling constants. The primary
advantage of this approach is that the problem becomes a single objective once
the utility function has been assessed correctly, thus ensuring achievement of the
best compromise solution.
Outranking methods are classes of multi criteria decision-making
techniques that provide an ordinal ranking of the alternatives. It allows the
decision maker to choose the alternative that are preferred for most of the criteria
and do not result in an unacceptable level of any one criterion. This approach
examines the non-dominated alternatives and searches for a subset of the non
dominated solutions for which a certain degree of dissension is acceptable to the
decision maker.
Goal programming (GP) can be used only when there exists an explicit
mathematical relationship between decision variables and the objectives and
constraints. GP is a good technique for identifying an acceptable solution when a
minimum acceptable achievement level has been defined for each objective.
The Analytic hierarchy process (AHP) is a multi criteria decision-making
technique that allows the consideration of both objective and subjective factors in
selecting the best alternatives. This approach is used to arrive at a cardinal
ranking of alternatives for multi attribute decision problems.
47
Among all of the possibilities, this study uses the eigenvector prioritization
method, which is commonly employed in the AHP developed by Saaty (1980).
This method is a popular alternative for deriving the preference structure in
various practical applications of MCDM (Zeleny 1982; Mollaghasemi and Pet-
Edwards 1997). The major strengths this method brings are its systematic
procedure and its ability to examine the consistency of the evaluator’s judgments.
48
collected into comparison matrices where each entry in the matrix belongs to the
relative importance scale used in the comparisons. The entries in the matrix are
then used to generate a derived ratio scale that reflects the local priorities of the
elements in the hierarchy.
The synthesis of priorities principle takes each of the derived ratio scale
local priorities in the various levels of the hierarchy and constructs a composite
set of priorities for the elements at the lowest level of the hierarchy.
C A1 A2 A3
A1 a11 a12 a13
A = (a ij) = A 2 1 / a12 a22 a23
A3 1 / a13 1 / a23 a33
Figure 3.3 Sample Comparison Matrix
49
Table 3.1 Pairwise Comparison Scale presented by Saaty
Degree of Definition Explanation
Importance
1 Equal importance Two elements contribute equally to the
property
3 Moderate importance Experience and judgment slightly favor
one element over another
5 Strong importance Experience and judgment strongly favor
one element over another
7 Very strong importance An element is strongly favored and its
dominance is demonstrated in practice
9 Extreme importance The evidence favoring one element over
another is of the highest possible order
of affirmation
2,4,6,8 Intermediate values Compromise is need between two
between two adjacent judgments
degrees of importance
50
Afterwards, elements of the eigenvector are calculated as the average of
each individual row of the normalized matrix as shown in figure 3.5.
51
The RI for various matrix sizes n has been approximated by Saaty (1980)
based on simulation run as shown in table 3.2.
RI 0.00 0.00 0.58 0.90 1.12 1.24 1.32 1.41 1.45 1.49 …
52
3.3 Computer Construction Simulation
53
3.3.1.1 GPSS
GPSS (General Purpose Simulation System) is a simulation modeling
language that was developed in the early 1960’s by IBM. GPSS is oriented
toward queuing systems. A GPSS simulation consists of temporary transactions
and permanent facilities, which flow around a network of block diagrams. These
transactions are created and destroyed as the simulation proceeds and which
move through various GPSS blocks. There are about 40 standard building blocks
in GPSS. Facilities are used to represent the resources needed by the
transactions at the nodes of the network (Damrianant, 1998). The most recent
version of GPSS is GPSS/World (Schriber, 1994).
GPSS/World employs a set of new GPSS Blocks and commands, which
support input/output, rescheduling, continuous and mixed modeling and multiple
data types that include integer, real, and string objects. Also, GPSS World
includes an embedded programming language called PLUS. PLUS language
consists of only a few statement types that can be used just about anywhere
within the simulation, including GPSS Blocks. This feature improved the flow of
simulations. Several new GPSS Blocks have been added to GPSS World. The
new blocks such as, OPEN, CLOSE, READ, WRITE, and SEEK Blocks provided
a powerful interface to programs written in other languages.
3.3.1.2 HOCUS
HOCUS (Hand Or Computer Universal Simulator) (Hills, 1971), developed
in the early 1960’s, enhanced and popularized the concept of activity cycle
diagrams. A HOCUS activity cycle diagram consists of two kinds of nodes:
queues (circles) and activities (boxes) connected by arrows. HOCUS could be
used for both discrete and continuous process modeling. It has been used for
numerous large-scale simulations in several industries in Europe (Poole and
Szymankiewicz, 1977).
54
3.3.1.3 ITHINK
ITHINK is a commercial computational package that has been developed
for modeling system dynamics. ITHINK provides friendly user interface and
animation and it can be used to model discrete systems, such as in construction
(Paulson, 1985). However, its modeling methodology is difficult to use and
understand when it comes to modeling discrete systems (Damrianant, 1998).
3.3.1.4 SLAMII
SLAM (Simulation Language for Alternative Modeling) was developed in
1979 as a commercial simulation language (Schriber, 1994). SLAMII was
designed in 1981 as an enhancement to SLAM. SLAM and SLAMII allow
modeling in a network form. SLAMII is a high-level simulation language with
FORTRAN and C versions that can model complicated applications. SLAMII
network models can be built, animated, and run by using another computer
program named SLAMSYSTEM.
55
This frequent use is due to the ability to provide a quantitative way of viewing,
planning, analyzing, and controlling the processes and operations (Halpin and
Riggs, 1992). It has been successfully used in modeling construction processes
such as concrete batch plant (Lluch and Halpin, 1982), tunneling (Touran and
Asai, 1987), and modeling construction resources and resolving construction
disputes (AbouRizk et al., 1992, and AbouRizk and Mohamed, 2000).
The Cyclone modeling methodology is a well established, widely used,
and simple methodology that is easy to learn and is effective for modeling
construction operations (Zayed et al. 2000). Among the six building blocks in the
Cyclone modeling methodology, both the Normal and the Combo elements
denote a work task within a process, but the former is used in a non-constrained
situation and the latter in a constrained one. The Queue element denotes the idle
state of a resource entity. Consolidation is a function used to consolidate flow
units at certain points in the system. The purpose of a Counter is to count the
number of times a key unit passes a particular control point in the network model
so that production can be measured. Finally, an Arc is a directional flow between
elements, which is used to model the resource entity's flow direction from node to
node.
MicroCYCLONE is a microcomputer-based program designed to run
CYCLONE simulation models. Before running the simulation, the graphical model
network should be converted into a numerical model using a specialized POL
(Problem-Oriented Language).
Many researchers have used CYCLONE as a base to build their
simulation systems such as Insight (Paulson et al., 1987), UM-CYCLONE
(Ioannou, 1989), Micro-CYCLONE (Lluch and Halpin, 1982), and
STROBOSCOPE (Martinez, 1996).
3.3.2.2 RESQUE
RESQUE is an acronym for RESource based QUEuing network simulation
system (Chang, 1986). RESQUE was designed as a significant enhancement to
56
Cyclone, where the model is not limited to the information conveyed by the
network.
3.3.2.3 COOPS
COOPS is an acronym for Construction Object Oriented Process
Simulation system (Liu, 1991). It is an extension and enhancement to CYCLONE
that was designed and implemented using an object oriented programming
language.
3.3.2.4 CIPROS
CIPROS is an acronym for Construction Integrated PROject and process
planning Simulation system (Tommelein et al., 1994). CIPROS is both a process
level and a project-planning tool. It contains an expandable knowledge base of
construction techniques and methods and makes extensive use of hierarchical
object-oriented representation of resources and their properties.
3.3.2.5 STROBOSCOPE
Stroboscope (State and ResOurce Based Simulation of Construction
ProcEsses) is a general-purpose simulation programming language specifically
designed to model construction operations (Martinez, 1996). It is based on
activity cycle diagrams (ACDs) and the activity scanning (AS) simulation
paradigm.
Stroboscope modeling elements have attributes, defined through
programming statements, which define how they behave throughout a simulation.
Resources in Stroboscope can be bulk or discrete, depending on their type. Bulk
resources represent entities that are not individual and cannot be uniquely
identified, such as sand, water, etc.
Discrete resources represent unique individual entities, such as a specific
truck, particular concrete block, etc. What mainly differentiate Stroboscope from
other simulation tools resides in its simulation language and its open design. Its
simulation language represents resources as objects that have assignable,
57
persistent, and dynamic properties and can actively and dynamically take into
consideration the state of the simulation process (Martinez, 1996).
Stroboscope’s open design allows the user to determine the input and
output at two levels. The first level uses Stroboscope’s built-in programmability
language. The second level extends Stroboscope through dynamic link libraries
created with high level languages: C and C++ (Martinez, 1996).
Stroboscope includes an optional Graphical User Interface (GUI) hosted
under Visio 3.0 or later version. Stroboscope also has some of the characteristics
that general-purpose programming languages have such as, built-in logarithmic
and trigonometric functions, conventional variables and arrays, and structured
flow control with if-elseif-else-endif blocks.
58
CHAPTER 4
59
As shown in figure 4.1, the framework of the real-time project tracking
model is divided into three modules. Two input modules and one output module.
The first part of the framework is related to the construction site.
Resources, composed of materials, labors and equipments, are tagged with
RFID tags. Site engineer and foremen are provided with RFID readers and
PDAs. These are the constituents of the system on the construction site. RFID
tags are scanned using the readers and information are sent to the central
database located at the office. In case needed on the construction site,
information is extracted from the database using mobile device.
60
database is accessed from a work station. Construction and site office are linked
together using wireless network. Wireless network ensures dual ways of
communication. Information is sent to the database to be accessed by people off-
site, and people on construction site can access information stored in the
database.
The third part of the framework is the output. Updating the schedule
instantly allows the user to track the progress of the project and to conduct
analysis such as earned value analysis to get an objective measurement of how
much work has been accomplished on the project.
61
allow repeated droppings while carrying it across the site. A drop test rating of
four feet is preferable, since this would allow repeated droppings from the chest
of an average height person. The computer display should be rated as sunlight-
readable, since it will often be used in direct sunlight. The mobile device must
support wireless networking options, which is not a problem for just about any
mobile device on the market today. The battery system must allow for at least
eight hours of normal operation to accommodate the average workday. Most
devices include a “hotswap-capable” option to allow switching out batteries while
the device is in use. This option combined with purchase of an extra battery
suffices for most battery types and mobile devices. Tablet computers were
deemed more appropriate than notebook computers for use on a construction
site where the user is most often standing up and walking the site.
Notebook computers are almost always heavier and have keyboards that
require two free hands to manipulate efficiently. The rugged notebooks are also
more expensive. Cost quotes and computer specifications were obtained through
websites and by consulting with various rugged computer manufacturers and
authorized resellers over the phone.
Table 5.10 gives a comparison of some of the rugged mobile devices
researched based on price and the requirements mentioned. The tablet computer
chosen to base the analysis on is the iX104C2V model manufactured by Xplore.
This model is moderately priced for rugged tablets and more rugged than most
with an IP 67 rating and drop test of four feet.
Field Manager could be equally accommodated on a handheld computer
or a PDA. The handheld computers are generally more highly priced. They do
have a slightly larger screen, but the difference was determined to be
insignificant. The rugged Recon PDA distributed by Rugged Notebooks was
selected for the analysis. It is priced comparably to some other rugged PDAs,
and like the tablet chosen is very rugged with an IP 67 rating and drop test of four
feet. For both the tablet and the PDA, cameras were selected as an add-on to
allow each user to communicate issues arising in the field more effectively.
62
Base Price +
Make & Wireless IP Rating &
Type Noted Memory Screen Type Battery Weight
Model Networking Drop Test
Upgrades
4 Hr Lithium Ion
Hi Brite Sunlight- 802.11b WLAN +
512MB RAM IP52, 3' drop to Standard + Optional
Readable Internal GPRS/GSM
Scribe Upgrade concrete Second Ion +
Upgrade Module
Rugged Tablet Centrino $4,535 Hotswap Capable 4.85lb
8.4" SVGA LCD
802.11b/g WLAN + IP54, 26 3' drop Main Battery Pack
512MB RAM Transmissive
GPRS/EDGE to plywood over 3.6AH + Expansion
Itronix Duo- Upgrade display Duo-
Cingular concrete Battery 3.6 AH
Rugged Tablet Touch $3,629 Touch 3.9lb
Standard 5.7AH
10.4" Integrated 802.11b IP67; 4' drop to
Lithium Ion +
Table 4.1 Rugged Mobile Device Comparison
63
12.1" LCD XGA
6.6AH Lithium Ion +
Outdoor Intel 802.11b and g + IP54, 26 3' drop
512MB DDR Optional 3.6AH Li Ion
Transmissive EDGE-GPRS T- to plywood over
Rugged Itronix Go- RAM Media bay battery
ColorVue w/ MOBILE concrete
Notebook $4,750 pack 8.2lb
Book III Touchscreen
Rugged
Convertible 12.1" Sunlight 57Watt Li Ion w/ 4 Hr
512MB DDR Integrated 802.11 b/g IPx4, 26 3' drops
Notebook / Kontron Readable XGA Life + backup 57Watt
SDRAM WLAN w/out transit case
Tablet Revolution $5,049 Display Li Ion Battery 8.0lb
Cisco 350 WLAN w/ 3AH Lithium Ion +
128MB 3.8" VGA Color IP67, 2 meter
Rugged Itronix Go- Internal Antenna + Optional Backup 3AH
SDRAM LCD drop
Handheld Book Q200 $2,931 CDMA Sprint Li Ion 1.76lb
Symbol PPT Transflective IP54, 4' drop to
64MB RAM 802.11b WLAN 1.7AH Li Ion
Rugged PDA 8800 $1,862 Color LCD concrete 0.68lb
802.11b CF Card Kit
Sunlight- IP67, 26 4' drop 3.8 AH NiMH Battery
64 MB + Audiovox
Readable Color to plywood over for Over 15 Hrs.
SDRAM GSM/GPRS CF Card
LCD concrete Operation
Rugged PDA Recon $2,238 and CF Cap 1.06lb
4.2.1.2 Wireless Infrastructure Alternatives
Cost quotes and specifications were gathered from wireless infrastructure
manufacturers and resellers through websites and phone conversations. The
802.11b WLAN equipment needed for the implementation consists of access
points (APs) with protective enclosures and omni-directional antennas.
The Orinoco AP-4000 was the access point chosen, along with 5dBi omni-
directional antennas. It was estimated that 2 APs and four antennas would
sufficiently provide wireless access to the project site. These APs cover the 2.4
to 2.5 GHz frequency band. Range boundaries characterize the circumference of
the radio cell that the access point produces (Web 1, 2006). The maximum
outdoor signal range (in the ideal wide-open situation) for this frequency band is
said to be between 1000 and 1500 feet outdoors. The indoor maximum range is
between 200 and 300 feet. One of the wireless provider representatives that
were consulted with claimed that the addition of an omni-directional antenna
could increase an AP’s range by 60%. Connectivity indicates the point at which a
device can associate with an AP at a specific data rate. The 802.11b standard
has a maximum data rate of 11Mbps. As the device moves away from the access
point, the data rate will drop from 11 to 5.5 to 2 to 1Mbps to no connectivity. A
data rate of 1Mbps is still relatively high and should be capable of supporting the
data transfer needed for this application.
The overall performance of the WLAN will be affected by interference and
number of users. A WLAN used on a construction site will have ever-changing
interference due to changing site conditions and equipment usage as the project
progresses. This application is considering only seven users of the WLAN, which
is extremely low and would not present a problem. The only way to truly know the
optimum number and location of APs on site is to perform a site survey. A
wireless specialist could be hired to do this, or the users themselves could test
the network by walking the site with their mobile device. The connectivity and
performance (based on ratio of packets sent to packets received) can be
checked this way. The LCC analysis includes the cost of bringing a wireless
consultant out to the site every three months to perform this service.
64
The price range of APs is approximately between $500 and $900. The AP
chosen has a price of $527. The Symbol AP-4131was quoted at $670 by a
Symbol reseller; therefore, the AP chosen is reasonably priced.
Cellular service providers were contacted to gather information for the two
alternatives using wireless subscriptions. T-Mobile and Cingular were contacted
for price quotes on unlimited data-usage plans for both PDAs and tablet
computers.
65
down to 15 cents per label. Appendix C has a description and specifications of
the equipment used as per the manufacturer publication.
66
data exchange is highlighted in figure 4.2 where the users have access to both
planned data files and actual activities that will help to conduct earned value
analysis and monitor the performance of the entire project.
Individual objects scheduled for arrival on the construction site are tagged
at the vendor factory using radio frequency identification tags. The encoded
information is scanned directly into a portable computer and wirelessly relayed to
a remote project database. This database has dual functions. A database query
returns graphical representations (e.g. computer aided design CAD) like where to
install the materials and the method used for installation. The second function of
the database is to relate the materials to the corresponding activities in the
project schedule. Based on the amount of installed materials on the construction
site and the related activity, BCWP and ACWP are updated. In turn the schedule
will implement the changes automatically every time information is recorded in
the PDA and sent through the wireless connection to the database.
The same logic is applied to the equipment on the construction site. The
activities that involve only equipment work, like excavation and hauling, are
tracked through the number of hours these equipments are used. Based on the
productivity of the crew and machines, the quantity of work to be done, and the
67
total number of hours, BCWP and ACWP can be updated. Figure 4.3 represents
the general system configuration.
Although the system logic was presented, there are some obstacles to
overcome. The main ones are how to define the percent complete for each work
item, and how to relate different tag categories (equipment, worker, materials) to
each other.
This research is just limited to materials usage, especially the steel parts
because of the limited data available, and both case studies presented to the
author were a pre engineered construction site. But the same logic and database
constructed for steel construction can be applied to other materials and other
resources in general.
68
4.3.1 Work Progress Measurement
As mentioned in table 2.1 in chapter 2, based on the activity under
investigation, there exist 6 different types of measurement method. In our study,
we are concerned with steel construction, pre-engineered and fabricated part. So
the suitable two methods for our case studies are either units completed or
weighted or equivalent unit.
In the next section, we attempt to present a database where all the
information will be stored. This database will have a dual function to store
information, update schedule, keep users informed of all activities, and at the
same time retrieve information.
69
The system is shown in figure 4.4. The user interface provides
viewing/input window that allows user to interact with the system through the
worldwide web using an Internet browser. The queries component performs the
necessary steps to satisfy the user need. The project database stores the original
information and it’s updated on a continuous basis. Upon completion of the
project, all information collected in the project database can be transferred to a
historical database. Java script functions, Visual Basic-Script functions, and
HTML can be used to design the set of web-forms to facilitate data entry and
retrieve. This research just focuses on the construction of the database part.
Web development, Java Server Pages and Java Script technologies to transform
the Internet into a user friendly interface are not within the scope of this research.
70
erection process: 1) tracking status for each pre-engineered building element, 2)
locating and identifying the mark of each steel element at the lay down area to
determine erection sequence, 3) positioning each engineered steel element at
the final position area, and 4) updating the schedule once the activity is done.
Table 4.2 presents the dictionary definition for the categories and
subcategories used in the database.
71
Table 4.2 Continued
Class Name Data Definition Type of Units Data Format
Element Data
Section Order in which Text N/A XX
number section of
structural steel
frame will be
erected
Field date Date which erector Date/time dd-mm-yy N/A
Delivery ask materials to be
Request delivered
Factory Date which factory Date/time dd-mm-yy N/A
delivery date expects materials
to be delivered
Identification Product identity Text N/A XXXX
number number to help
identify members
on jobsite
Erection start Date which erector Date/time dd-mm-yy N/A
Erection start erection of
status steel parts
Erection Date which erector Date/time dd-mm-yy N/A
completed finish erection of
steel parts
Section Order in which Text N/A XX
number section of the steel
frame will be
fabricated
Fabrication Fabrication Date which Date/time dd-mm-yy N/A
Status start fabricator start to
fabricate parts
Fabrication Date which Date/time dd-mm-yy N/A
completed fabricator finish to
fabricate parts
Delivery Delivery Date which steel Date/time dd-mm-yy N/A
Status start fabricator start to
deliver steel parts
Delivery Date which steel Date/time dd-mm-yy N/A
Completed fabricator finish to
deliver steel parts
RFID Identification Product identity Text N/A XXXX
number number to help
identify members
on jobsite
72
4.4.2 Project Database
A binary relationship is used in designing the database. Relationship types
involve one-to-one (1:1), one-to-many (1: M), and many-to-many (M: N)
relationships. Different types of attributes are used in the development of this
database, including composite, single-valued, multi-valued, null-valued, and key
attributes. Composite attributes form a hierarchy that decomposes a unit into
smaller components, each with its own independent meaning, as in a project that
is decomposed into activities, and activities are decomposed into their resources.
The database implementation is accomplished using the Microsoft Access 2000
environment (see the tables and relationships shown in figure 4.4). In essence,
these tables map the entities and their respective relationships. The data type of
the primary key in the entity tables is auto-number, which avoids the redefinition
of the key.
As shown in figure 4.5, we have 13 tables that cover the database thought
for this research. Some of these tables are dummy table, just to assure a many
to many relationship, or many to one relationship. Mainly the database is
modeled conceptually using 9 physical entities. The physical entities represent
the company, user, project, project details, materials details, erection drawings,
connection drawings, section details, and department details. These entities
record the internal information of the project being modeled such as names of
companies, projects, materials, sections…At the same time these entities are
related to each other with a logic combination to make them interacting with each
other. The input information at the beginning that will be stored in the database is
a mix of Microsoft Project columns input information, like activity name duration
of activity, and at the same time information provided by the manufacturer of
materials. In our case study it will be steel parts. It will include materials
specifications, quantities, and of course RFID tag numbers to identify the
materials. In addition to that, it includes information related to fabrication,
shipping and erection schedule.
73
Figure 4.5: Project Database Tables and their Relationships
74
Figure 4.6 User Interface
75
Figure 4.8 Erection drawings
Now that the framework of the real-time project tracking model was
presented, the next step is to develop an assessment system that will evaluator
to choose the right tools for the proposed model
76
CHAPTER 5
The assessment model is divided in two parts. The first part consists of
developing the utility function model that will help evaluator to choose between
available technologies for real time project progress tracking. This phase include
presenting the main objective and identifying the attribute that will help the
evaluators in their decisions, and the alternatives to be assessed. The second
part consists of analysis and identifying the best alternative that serves our need.
Figure 5.1 presents the Analytic Hierarchy process flow chat.
77
Figure 5.1 Analytic Hierarchy Process
78
However, on site engineers usually use written documents, drawings,
contracts, specifications, and shop drawings for job sites. As a result a gap in
time and space between the job site and office causes the duplex, lack and
confusion of data and information. In other words, existing means of processing
information and collecting data are not only consuming and costly, but also
reduce the performance of project management in information acquisition.
Furthermore, construction contractors normally depend on interactions over the
telephone or fax machine to communicate with suppliers, subcontractors, and
designers. Consequently, transactions are often lost or misunderstood. Such
means of communicating information between sites and offices, and among all
participants, are ineffective and inconvenient.
As mentioned in chapter 3 a good way to improve communication on the
construction and between construction site and office is by using information
technologies that will provide a framework for a real time project progress
tracking.
Because the Utility function requires developing selection criteria for
evaluation technology, three main objectives were identified: (1) technical merit,
(2) economic merit, and (3) low risk merit. Systems utilities were calculated
based on the degree to which these objectives were achieved (Ghanem et al.
2007).
79
rechargeable nickel cadmium cells. Others use disposable alkaline batteries.
Very few are powered by both types that include a backup source of power.
Wireless connection speed in order to update the host computer system
instantaneously as data reading occurs is a concern for people on the
construction site. Not all systems have this capability.
Rugged characteristic of the equipments used on the construction site
determine to what extent they can survive in harsh environment. These
equipment have passed durability tests up to military standards; they can
withstand falls, vibration, dust, and rain.
The screen size of both computers and PDA measured by inches is an
important attribute, because users have to check erection drawings and small
screen size tries to be an obstacle when tiny details need to be checked.
Some systems have the writing ability and others have the touching
screen ability. On the construction site while the user most of the time will be
standing and holding in one hand the equipment, probably it will affects its choice
regarding the writing system.
In addition to that the weight of the equipment is another concern when
the user will be holding it most of the time in his hand.
Another concern is the ability of the system to accommodate all required
software on the construction site. Mainly CAD and project management software
are a main concern for user on the construction site, in order to check the project
schedule and check the erection drawings when it is needed.
Accuracy of the system used especially when tags are being scanned on
the construction site is a concern too. Users tend to scan the tags from a
distance and interference with object or other tags has to be taken into
consideration.
Because technology cost is very important consideration, the initial
investment includes the equipment purchase cost, as well supporting cost for
software and accessories.
80
Figure 5.2: Hierarchy of Influence as Applied in the Study
Operating cost should also be considered. It includes the cost of the tags
whether they are active or passive tags, the cost of system maintenance and the
updates that occur in the system.
81
Incorporating new technologies into a company system is believed to
improve the quality of processes. But at the same time lead to cut in labor or
some people see it as saving in labor.
Concerning the risk factor resulting from using new technology, all risk
factor are included under the low risk criteria. Each evaluator evaluates
technologies based on how certain or uncertain he is about the technology.
Sources of uncertainty are numerous. Some sources could be related to the
system itself, such as the security of the system and how it can prevent hacking
the system. Another issue is a reliability issue that is associated with new
technologies. Equipment and performance reliability fall into this category. Users
want to make sure that the equipments and system they are using are reliable
with minimum down time.
82
Table 5.1 Continued
Attributes Measures
Operating Cost % of Project Total Cost
Unsatisfactory/Moderate/Satisfactory /Very
Saving in Labor
Satisfactory
Unsatisfactory/Moderate/Satisfactory /Very
Quality Improvement
Satisfactory
Equipment Reliability Low/Moderate/High
Performance Reliability Low/Moderate/High
Investment Risk Low/Moderate/High
Security Yes/No
As shown in table 5.1, some attributes are quantitative and others are
qualitative. Economic merit attributes, such as technology’s initial and operating
costs, are quantifiable. All system reliability attributes require subjective judgment
because the user has to specify his preference that systems meet or not meet
the attribute described.
To obtain information about the preferences and the weight of the defined
attributes, a survey was sent to 200 people from different construction sites.
The first step was to determine the minimum number of respondents to
validate the survey. In a study conducted by Barlett, Kotrkik, and Higgins in 2001,
a table for determining minimum returned sample size for a given population size
was presented. According to them, an alpha level of 0.05 is acceptable for most
research. And for continuous data, a margin error of value 3% is acceptable.
Based on the tables presented by them, the minimum required returned sample
to validate the survey result should be 75 responds based on a population of
200. 60 people respondent to the survey, so we were short by 15. Salkind (1997)
recommended over sampling to reach the desired number. This method was
used and we ended up by receiving 77 filled surveys from people involved with
the construction industry in the form of both paper ballet and secured online
forms. The survey mainly contained two parts: the purpose of the first part was to
determine the set of priorities of the attributes in order to calculate the weight of
83
each attribute. The second part of the survey was to determine the utilities by
getting the evaluator preferences on the degree of liking for each attribute.
Appendix B contains the full form of the survey and the table developed by Barlet
et al. to determine the minimum size of survey filled.
Figure 5.3 illustrates the various job titles of the survey respondents. Most
of the responses are from engineers of companies with business areas in
building & civil construction. Other responses are scattered among all sectors
and job titles commonly found in the industry.
84
Based on the hierarchy of influence established earlier, four pairwise
matrices needed to be developed. Figure 5.4 presents the four pairwise matrices
resulting from the hierarchy of influence. Each matrix represents the relative
importance of one attribute over another with respect to a specific criterion. The
numbers shown in these matrices are the final preferences established by the
evaluators from the survey.
For example in the matrix representing relative importance to fulfill real
time project progress tracking numbers (figure 5.4a), a value of 5 (first column
second row) means that economic criteria is 5 times more preferred to
technology criteria with respect to the model. At every level in the hierarchy, a
similar pairwise analysis is conducted for each criteria / subcriteria of that level.
86
using equation 3.5 and 3.6, and in case CR was greater than 10% additional
steps were taken or in some cases the matrix was rejected. Out of the 77 people
who replied to the survey, 21 matrices were rejected cause of failure to the
consistency check.
The first matrix of each row represents the normalized pairwise. The
normalized matrix is calculated by adding the values in each column of the
pairwise comparison matrix, and then dividing each element in the pairwise
comparison matrix by its column total. The second matrix provides an estimate of
the relative priorities of the elements being compared. It is calculated by
computing the average of the elements in each row of the normalized matrix.
These values from each set of matrix were used to develop the weight of each
attribute.
Then consistency is calculated as follows:
Step 1: Normalize the comparison matrix by dividing the values of each column
over the sum of this column.
Step 2: Calculate the elements of the eigenvector matrix by averaging the
elements of each individual row of the normalized matrix.
Step 3: Calculate the transition matrix by multiplying the comparison matrix with
the calculated eigenvector.
Step 4: Calculate the matrix dominant eigenvalue noted (max using equation 3.4.
Step 5: Compute the Consistency Ration (CR) based on equation 3.6
Step 1 Step 2
Real time Tech.
Tech 0.08 0.05 0.11 0.08
Econ. 0.42 0.24 0.22 0.29
Risk 0.50 0.71 0.67 0.63
Normal Matrix Eigenvector Matrix
87
Step3 Step 4 Step 5
0.24
0.90 3.09 0.08
1.99
Transition Matrix Dominant Eigenvalue Consistency Ratio
Step 1 Step 2
Econ. Init.Cost Oper.Cost Sav.Lab. Qual. Imp.
Init.Cost 0.46 0.54 0.55 0.27 0.46
Oper.Cost 0.23 0.27 0.28 0.27 0.26
Sav. Lab. 0.15 0.14 0.14 0.36 0.20
Qual. Imp. 0.15 0.05 0.03 0.09 0.08
Normal Matrix Eigenvector Matrix
2.02
1.13
0.81 4.22 0.08
0.34
Transition Matrix Dominant Eigenvalue Consistency Ratio
0.26
0.53
1.15 4.14 0.05
2.26
The evaluator from the survey provided their assessment of the UL and UH
value for each attribute. Table 5.2 and 5.3 show the average values of the
evaluator assessment for UL and UH respectively along with their standard
deviations
89
Table 5.2 Assessment of UL
Attributes Assessment of UL Standard
deviation
Technical Requirement Skills Low N/A
Accuracy Low N/A
Rugged Characteristic IP33 N/A
Screen dimension 2 1.32
Battery life 4 1.26
Weight including Battery 6 2.94
Writing Ability Typing N/A
Software Accommodation CAD N/A
Wireless Connection Speed 56 Kb N/A
Initial Investment 2% 0.78
Operating Cost 1% 0.36
Saving in Labor Moderate N/A
Quality Improvement Moderate N/A
Equipment Reliability Moderate N/A
Performance Reliability Low N/A
Investment Risk Low N/A
Security No N/A
Though the risk attitude could differ among the different evaluators, it is
assumed that they have a neutral risk attitude. Thus a linear function could be
90
used to depict the utility between UL and UH (refer to figure 3.2). The utility
function would have the form:
UT = 0.0032U1(y1)+0.0136U2(y2)+0.008U3(y3)+0.0152U4(y4)+0.0096U5(y5)
+0.168U6(y6)+0.0024U7(y7)+0.0064U8(y8)+0.004U9(y9)+0.128U10(y10)
+0.075U11(y11)+0.058U12(y12)+0.024U13(y13)+0.04U14(y14)
+0.11U15(y15) +0.18U16 (y16) +0.33U17 (y17) Equation 5.2
91
Table 5.4 Single Attribute Utility Functions
Attributes Designation Single attribute utility function ui(yi)
Technical Requirement Skills y1
u1(y1) = { 0, y1 + 2
y1 - 2, 2 <y1< 3
1, y1 , 3
where 1=very low, 2=low, 3= moderate,
4= high
Accuracy y2
u2(y2) = { 0, y2 + 2
y2 - 2, 2 <y2< 3
1, y2 , 3
where 1=very low, 2=low, 3= moderate,
4= high
Rugged Characteristic y3
u3(y3) = { 0, y3 + 3
0.5y3 - 1.5,
1, y3 , 5
3 <y3< 5
Screen dimension y4
u4(y4) = { 0, y4 + 2
0.25y4 - 0.5,
1, y4 , 6
2 <y4< 6
Battery life y5
u5(y5) = { 0, y5 + 4
0.25y5 - 1,
1, y5 , 8
4 <y5< 8
u6(y6) = { 0, y6 , 6
- 0.25y6 + 1.5,
1, y6 + 2
2 >y6 > 6
Writing Ability y7
u7(y7) = { 0, y7 + 1
0.5 y7 - 0.5, 1 <y7< 3
1, y7 , 3
where 1=typing, 2=writing, 3= touching
Software Accommodation y8
u8(y8) = {0, y8 + 2
0.5y8 - 1, 2 <y8<4
1, y8 , 4
where 1=None, 2=CAD, 3= PM,4= both
Wireless Connection Speed y9
u9(y9) = { 0, y9 + 2
0.5y9 - 1, 2 <y9< 4
1, y9, 4
where 1=14 Kb, 2=56 Kb, 3= 256 Kb,
4= 2Mb, 5= 11Mb
92
Table 5.4 Continued
Attributes Designation Single attribute utility function ui(yi)
Initial Investment y10
u10(y10) = { 0, y10 , 2
-0.66y10 + 1.32,0.5 >y10 > 2
1, y10 + 0.5
Operating Cost y11
u11(y11) = { 0, y11 , 1
-1.33 y11+ 1.33,.25 >y11 >1
1, y11 + 0.25
Saving in Labor y12
u12(y12) = { 0, y12 + 3
y12 - 3, 3 <y12< 4
1, y12 , 4
where 1=very unsatisfactory, 2=ununsatisfactory,
3= moderate, 4= satisfactory, 5=
very satisfactory
u13(y13) = { 0, y13 + 3
y13 - 3, 3 <y13<4
1, y13 , 4
where 1=very unsatisfactory, 2=ununsatisfactory,
3= moderate, 4= satisfactory, 5= very
satisfactory
u14(y14) = { 0, y14 + 3
y14 - 3, 3 <y14<4
1, y14 , 4
where 1=very low, 2=low, 3= moderate,
4= high
Performance Reliability y15
u15(y15) = { 0, y15 + 2
0.5y15 - 1, 2 <y15< 4
1, y15 , 4
where 1=very low, 2=low, 3= moderate,
4= high
Investment Risk y16
u16(y16) = { 0, y16 + 2
y16 - 2, 2 <y16< 3
1, y16 , 3
where 1=very low, 2=low, 3= moderate,
4= high
Security y17
93
The four alternatives that we are trying to investigate in this study are a
combination of mobile devices with wireless communication capabilities as
shown in table 5.5.
Table 5.6 illustrates the values of the attributes of the four alternatives
being considered in this study. Based on the single attribute utility functions given
in table 5.4, the corresponding utility values of the various alternatives are
calculated and listed in table 5.7.
94
Table 5.6 Continued
Attributes Alternative1 Alternative2 Alternative3 Alternative4
Equipment Reliability high moderate high moderate
Performance high moderate high moderate
Reliability
Investment Risk moderate moderate low low
Security no yes No yes
Values of UT can vary between 0 and 1. The larger the UT value for an
alternative the more favorable it is to be used in the real time model. As shown in
table 5.7 for case study 1, the utility function of the four alternatives varied
between 0.59 and 0.93, which suggest that none of the four alternatives are
perfect enough to obtain aggregate utility close to 1. Although alternative 2 had
the highest utility of value 0.93 corresponding to the most favorable choice.
As shown in table 5.8 for case study 2, the utility function of the four
alternatives varied between 0.62 and 0.98, which suggest alternative 2 had the
highest utility of value 0.98 corresponding to the most favorable choice and the
closest to 1.
Both Case studies ranked Alternative 2 as the best alternative that fulfills
the need for real-time project progress tracking. Although in both case studies
alternative 2 had the highest life cycle cost with a value of $48,503 and $81,062
respectively for each case study. Even though Alternative 1 had the highest initial
cost, but the recurring cost for alternative 2 was the highest for both case study.
From this observation, a conclusion can be made that cost is not a major
attribute to establish which tools should be used in the real-time project progress
95
tracking model. Cost was embedded inside the assessment model as two
attributes: initial investment and operating cost. These two attributes are
represented as percentages of total cost of the project. So a sensitivity analysis
has to be done to determine the range of projects for which the cost will be a
major factor in taking decisions.
Another observation from the assessing model is noted. Evaluator gave
big importance for risk criteria, so it is good to know how this criteria influence our
choice. So another sensitivity analysis is conducted to see results change by
applying different risk scenarios.
Last but not least, an observation is made that both technical and
economical criteria have a complementary relationship. That mean the more the
requirements is needed, the more cost is associated with it. In this case the
attribute cost will get less value, but the technical merit will get greater utility
value and vice versa.
96
Cost Analysis
1.2
0.8 2%
Utilities
1%
0.6
0.50%
0.4 measure
0.2
0
1 2 3 4
Alternatives
The corresponding utility value for each cost variation is shown in table
5.9.
In all cases, alternative 2 had the highest utility value corresponding to the
favorite alternative to be used on the construction site. Another observation is
related to the order of alternative preferences. The same order was obtained
each time: (1) Alternative 2, (2) Alternative 4, (3) Alternative 1, and (4) Alternative
2. Plus it is hard to prove from these alternatives that both technological and
economical criteria are complimentary. The reason is these alternatives are very
close in their measures.
97
5.4.2 Effect of Changing Risk Weight
Evaluator gave risk merit the highest weight with a value of 0.63. In our
assessment model, risk criteria included four attributes: equipment reliability,
performance reliability, investment risk, and security. To measure to which extent
risk affects the user preferences output, three different weights were used: 0.25,
0.50, and 0.75 maintaining the other weight the same. The values of the utilities
resulting are shown in table 5.10 and in figure 5.7.
Risk Analysis
1.2
1
0.25
0.8
Utilities
0.5
0.6
0.63
0.4
0.7
0.2
0
1 2 3 4
Alternatives
From the risk analysis table, it is safe to conclude that the values of
weights less than 0.63 led to a change in alternatives ranking. In this case,
Alternative 4 is the favored one. The order of preferences is: (1) Alternative 4, (2)
Alternative 2, (3) Alternative 1, and (4) Alternative 3.
98
Risk merit is an important criterion in our multi-attribute model, and it affects the
user preferences when changed.
99
CHAPTER 6
100
was completed in July 2006. Sperry & Associate Company, based in
Tallahassee, FL, was the design build firm responsible for the project. The total
project cost was approximately $3 million and was under the budgeted amount.
The project included the construction of one huge building divided into two
parts: the first part represented the A/C plant, and the second part represented
the offices. An aerial view of the construction site through differences phases of
the project is shown in Figure 6.1. For more details about the steel erection and
different phases of the project check Appendix B. The building is pre-engineered
steel building (PEB) with metal sheeting as wall and roof covers. The advantages
that PEB present are its fast completion, straight forward erection, and usually
the PEB fabricator is the one that perform the design. The PEB steel parts were
provided by American Eagle Company based in Columbus, Georgia. Compared
to conventional steel buildings, PEB offer numerous advantages especially when
it comes to low rise buildings. In addition to the lower initial cost and faster
delivery, owner will only have to deal with one party, Steel fabricator, for the
design and fabrication of buildings.
102
into place through different methods. Figure 6.4 shows a Tilt-Up panel being
erected.
Figure 6.2: Aerial View of JCHS Site Just Before Owner Move-In
103
Figure 6.4: Tilt-Up Panel Wall Erection
104
fabricator load schedule, the steel factory created the fabrication and shipping
schedule. Figure 6.5 shows the fabricator shop where PEB parts were being
fabricated and the piece mark labeled on the steel members. All steel parts are
numbered to correspond to a set of erection drawings which indicates the
location of each piece.
105
6.2.3 Steel Erection
The major components comprise of rigid frame, columns and rafter, eave
struts, purlins, girts, flange braces, end-wall columns and bracing systems which
may be cables, rods angles or portals.
All materials for the first bay erection were prepared. The rafter sections
required were identified by part number, and then assembled as near as possible
to their lifting positions. Then the first four columns were erected at the braced
bay, meanwhile the part number and orientation, and position over anchor bolts
were verified. Next step was to position the crane for lifting the assembled rafter
sections. Figure 6.7 shows the erection process as the columns are lowered
carefully to be fixed on the anchor bolts. The last picture shows worker fixing
purlins on the rafters.
(a) Column Lowered (b) Fixing Column (c) Fixing Purlins on Rafters
Figure 6.7 Erection
106
the steel crew needs to perform a specific task, how data are shared, and where
to get those data from. This helps us to diagnose existing PEB steel construction
processes to find out alternative processes. Figure 6.8 presents the materials
and information flow of the PEB steel construction processes.
107
As seen in the diagram, information and materials are passed from one
party to another via conventional approach. Key data sources within the defined
system are: fabricator, worker, foreman, and site manager. The next two sections
will define the productivity of the current practices and need for improvement.
108
shakeout and erection. The next section presents the implementation of our
study into a simulation model to study the cycle productivity.
Correcting 0% 0% 0% 0% 0% 0%
error
Non work 20% 4% 5% 9% 3% 9%
related
Ineffective communication
work
Searching for 2% 8% 6% 6% 8% 5%
materials
Break time 2% 6% 1% 3% 3% 4%
109
there was a problem with erection or with the steel parts, there is a
communication back and forth between the construction site and the steel
fabricator. Based on a lot of trial and error and trying different simulation model,
the author decided to separate both the shipping process from the erection
simulation process. The reason behind it is shipping process takes more time
then erection and when placing both processes into one simulation model the
results looked inaccurate.
Figure 6.9 and 6.10 presents PEB steel simulation model for both shipping
and erection. The shipping model is formed of 10 entities covering one cycle of
the process. The cycle starts from loading the materials at the fabricator shop till
offloading material on construction site. The erection model is formed of 30
entities covering one cycle of the process. The cycle starts from steel parts
available on the constructions site till erection of one bay of the steel structure.
Once the graphical model was established the next step is to transform it
into an input language that Micro Cyclone understands. Appendix D includes the
input files for both simulation files. Durations and Resources were also
incorporated in the input file. The duration units used in the input file is hour.
Some entities that represent inefficiency in the processes were included in the
model. Once the user gets familiar with Cyclone program, transition from
graphical input to computer language the simulation software understand
become easy step. Web Cyclone is case sensitive and all typing should be done
in upper case letters.
As you notice in the model, some resources were idle when others were in
use. Next section discusses those entities, especially that they represent
opportunity for improvement our processes and increase efficiency and minimize
waste. The simulation output will be discussed, once the To Be information flow
diagram is established and its simulation model is performed.
110
Figure 6.9 Shipping Simulation Model
111
Figure 6.10 Erection Simulation Model
112
locating, sorting, and identifying steel components. Instead of setting the steel
directly off the delivery trucks, all the steel was off loaded and shakeout was
done as the steel was delivered. This practice resulted in double handling of
materials in the erection operations.
Once fabricated, the fabricator labeled each steel member with a unique
piece mark and sequence number to identify it directly on the erection drawings
and its proper place. However, to make it easy to find materials for erection, the
workers marked each piece one more time with white chalk based on the
erection hand map they made. This process leads of course to considerable
unproductive duplication.
Another concern is raised when workers try to locate the exact material to
be erected. Foreman determines the exact order in which each steel member
has to be erected. Workers identify components with paper-based information.
As a result, a significant portion of time is spent in the lay-down areas searching
by hand to identify components.
During our interview with the people on the construction site, it was found
that material and information flow can be lost, disconnected and distorted while
flowing from information sources to end user. Good examples were given to the
author when he was on the construction site. Workers didn’t know when next
shipping date is scheduled. Connectors had no full idea of where each steel
element was positioned. Foreman had no idea of the status of a shop drawing
approval after implementing some changes and which sequence of steel
elements was fabricated and stored at the factory and ready to be shipped.
It was also noticed that critical information from the field to the office had a
delay and lacked real time touch. According to the productivity ratings data
mentioned in table 6.1, foreman spent most of his time communicating with
workers, 33% of his time on work related communication and 20% for non-work
related communication. These percentages are higher than the average values,
17 % and 9% respectively.
Another two communication problems identified with the current process
are with the approval drawings and request for information. Actually usual delays
113
associated with the steel supply process are encountered during approval stage
of shop drawings. Many weeks are wasted due to movement of hard copy
drawings from one party to another.
The other major delay in case problem aroused on the jobsite and can’t be
resolved at the field office, so the site engineer had to submit a request for
information (RFI) to the technical engineering department. RFIs were sent via fax
with a sketch and a reference in the drawings and in case photos were attached
they had to be mailed by federal express. This would delay RFI turnaround times.
114
Figure 6.11 Proposed Materials and Information Flow
115
When the steel component’s identity can be read directly through a
portable RFID reader, the erection sequence and position information of each
piece in their final location are automatically extracted from the common
database through wireless networks in real time. This situation makes
information stored in the database accessed at any time by people on the
construction site, and updates make construction activities from the jobsite
available to all process units who need the information in real time.
116
the pieces stores them before the installation. There may be as many as 2,000
fabricated steel parts in an average size of buildings.
Radio Frequency Extenders (RFEs) can used as transceivers (readers)
that provide a communication link between the PC software and the tags as
shown in figure 6.12. RFEs are connected together and to the PC via Ethernet
cables. Data is written to any tag by connecting the laptop to the portal and a
single RFE.
The truck loaded with steel materials arrives at the project job site and is
sent to one of the designated laydown areas. Workers are provided with
handheld computer/ RFID reader. The reader used has a form like a standard PC
card and can be incorporated into the existing handheld computer using a PC
card expansion pack. Omni antenna and software are also installed in the
handheld computer. So worker at the laydown area identify the pieces using
RFID readers, and coordinate the unloading and storage of the steel parts. Any
discrepancy between the packing list and the steel parts unloaded from the truck
is sent back to the fabricator for resolution, or in case there are discrepancies
between the bill of materials and the unloaded materials, it will be directly
117
captured and fabricator will be contacted. Savings are captured when the
simulation model for the improved process is performed, especially with the
improvement in productivity.
118
Figure 6.13 Proposed Shipping Simulation Model
119
Figure 6.14 Proposed Erection Simulation Model
The main output of simulation is the productivity result, which shows the
number of cycles per unit duration. This productivity data is what can be used to
evaluate the performance of a process design at a glance. A site engineer can
also use the sensitivity analysis function to try to improve the productivity of a
process by changing the resources. Based on Web CYCLONE, the construction
120
simulation result of a repetitive cycle in both projects was presented as the
productivity. For computing productivity of both shipping and erection process,
‘Hours’ was used as the time unit as shown in table 6.2
The cycle number in Table 6.2 represents the number of time both
systems cycle. For instance, one cycle of shipping steel materials (Refer to
Figure 6.9) includes Queue node (1: Steel batch) to Queue (10). In case of
erection process (Refer to Figure 6.10), Queue node (4: Steel Available) to
accumulator (30) is included in the one cycle of the system. It is usually defined
by user. Therefore, the productivity of shipping can be calculated through dividing
‘Cycle number’ by ‘Total simulation time (i.e., 30/107.3 = 0.279) and 300 / 2155.9
= 0.139 for erection). The same is done for the To Be processes.
Based on the simulated productivity table, it takes 3.58 hours in order for
one truck to reach the construction site using the conventional process. On the
other hand it will take 2.24 hours in order for one truck to reach the construction
site. At the same time it takes 7.19 hours to erect one pre engineering steel bay.
But using the proposed process it will take 5.68 hours to erect one bay.
As summary, there will be saving in money at least one hour in the
shipping process and 1.5 hours in the erection process. Next section will quantify
those benefits and turn it into dollars.
121
6.7 Proposed Model Benefits
122
other initial costs. The total present worth of life cycle costs for each alternative is
shown.
123
Table 6.3 Continued
Computer
Software
Microsoft Office $550
Field Manager (FMngr) $300 $/EA
Pocket CAD $199 $/EA
20%
Maintenance & Upgrades value $/EA First Year Free
Training
Manuals $150 $/EA
Plus Traveling
Instructor Comes to Location $2,000 $/Day Expenses
124
Table 6.4 LCC Calculations
CALCULATIONS
125
Table 6.4 LCC Continued
Wireless Consultant
Network
Implementation &
Upkeep $152 / 3Mo (IT wage * 8Hrs.)
On-Going Training
On-Going Training $208 / 6Mo APM-wage * 8Hrs
Staff Time Spent
Training $240 / 6Mo FM-wage * 8Hrs
Downtime Due to
Device Failure
30Hrs/Yr *(SI-wage + Site
Engineer-wage+ PM-
Computer Failure $4,366 wage)
30Hrs/Yr *(SI-wage + Site
Engineer-wage+ PM-
Network Failure $4,366 wage)
Interest Rate
Calculations
fM = (1+fY)^(1/M)-1
Effective Monthly (M = # of Periods per Year
Inflation Rate = fM 0.19% = 12)
Monthly Discount Rate
= rM 1.00% rM = r/M
Constant Effective
Monthly Discount Rate
= iM 0.81% iM = (rM - fM)/(1+fM)
A summary of the LCC analysis is shown in table 6.5 and 6.6 to cover
both case studies. All costs have been discounted back to the beginning of the
first month using adjusted monthly discount rate. Planning and feasibility costs
are assumed to be incurred at the same time as equipment purchases. The total
present worth of life cycle cost for each alternative is shown. Even though only
one alternative will be discussed later on when cost benefit analysis will be done,
but the LCC for all other alternatives were done, because it was used as an
attribute to determine the best alternative that satisfy the projects technological,
economical and risk criteria.
The variation in the total LCC for the four alternatives was around $10,000
for case study 1. The cheapest alternative is rugged PDA/smart chips with
wireless subscription. The most expensive alternative is rugged tablet/smart
chips with WLAN connection. Each investment situation is unique and requires
diversified investment choices. Therefore, in today’s complex and dynamic
126
construction environments, it is risky to rely on one method. It is necessary to use
multiple methods and compare their output against each other. Next step is to
conduct a cost benefit analysis and break-even analysis.
The variation in the total LCC for the four alternatives was around $25,000
for case study 2. The cheapest alternative is rugged PDA/smart chips with
WLAN. The most expensive alternative is rugged tablet/smart chips with Wireless
subscription. Each investment situation is unique and requires diversified
investment choices. Therefore, in today’s complex and dynamic construction
127
environments, it is risky to rely on one method. It is necessary to use multiple
methods and compare their output against each other. Next step is to conduct a
cost benefit analysis and break-even analysis.
As we can notice, the cost of the model for case study 2 is more
expensive than case study 1, and that can be explained by the fact that case
study 2 jobsite is much bigger than case study 1, and its location is farther from
steel manufacturer.
128
6.7.1 Function A: Site Inspection Savings
This function addresses the need of three common types of inspection: 1)
structural, 2) material, and 3) safety. A structural inspector compares design
documents with the actual installation. In several locations during our site visit,
the structural inspector, Mr. Ramon Piera (case study 1), was faced with an
unclear design document, requiring him to get clarification from the designer
(situated in main office in Alabama). A material inspector verifies that a material
meets the requirements of the applicable specification. A safety inspector
identifies potentially hazardous situations and supervises compliance with safety
regulations. The suitable implementation of function A returns savings in travel
cost and time from jobsite to the site inspector’s remote office as well as
inspection time. Baseline assumptions for case study 1 are formulated to
calculate annual benefits.
• 30 % of the total inspections can be remotely supported by this function
• At least 30 minutes of inspection time per inspection
• The frequency of site inspection: two times per week
• Driving distance:150 miles
• Average driving cost per mile: $0.36
• Average cost per man-hour of the site inspector: $70 (U.S. Department of
Labor)
Based on the assumptions above, the annual benefits of this function are
projected in table 6.7.
Table 6.7 Benefits Calculation of Function A
Driving Cost 150miles*($0.36/mile)*(4weeks/month) $1,555
*(12months/year)*30%
*(2 inspection/week)
Travel Time 150min*(1hour/60min)*($70/hour) $5,040
Cost *(4weeks/month)*(12months/year)
*30%*(2 inspection/week)
Inspection 30min*(1hour/60min)*($70/hour) $1,008
Time Cost *(4weeks/month)*(12months/year)
*30%*(2 inspection/week)
Total Cost per Inspector $7,603
129
Baseline assumptions for case study 2 are formulated to calculate annual
benefits.
• 30 % of the total inspections can be remotely supported by this function
• At least 30 minutes of inspection time per inspection
• The frequency of site inspection: two times per week
• Driving distance:200 miles
• Average driving cost per mile: $0.36
• Average cost per man-hour of the site inspector: $70 (U.S. Department of
Labor)
Based on the assumptions above, the annual benefits of this function are
projected in table 6.8.
The benefits summarized above include the direct benefits to the system
related to inspection. In addition to the direct benefit, there are also several
possible indirect benefits (e.g., fast turnaround time to complete inspections)
involved in system implementation. However, it is extremely hard to quantify
indirect benefits in term of dollars.
130
have direct access to any information from off site experts who have more
experience, or able to solve design problems or other errors, using technology
integrated communication tools. An obvious benefit of function B is a reduction in
travel cost and RFI processing time. To determine number of RFIs cases for our
case project, the RFIs log was examined. The RFIs log maintained 256 RFIs
during 4 months between many different companies as shown in Appendix C.
Most of the RFIs were generated between Sperry associates and the PEB
manufacturer company American Buildings Company. Based on this information,
the following baseline assumptions are formulated.
• 1 hour of RFI processing time can be saved by the use of function B
• The frequency of an on site visit is one visit every 5 RFIs
• 100% of total site visits can be remotely supported by function B
• Average cost per man hour of an engineer: $96 (U.S. Department of
Labor)
Based on assumptions above, the benefits of function B (Case study 1)
are calculated in table 6.9.
150min*(1hour/60min)*($96/hour)
Travel $36,864
*(256RFIs/4months)*(12months/year)
Time Cost
*(1visit/5RFIs)
RFI
1hour*($96/hour)*(256RFIs/4months) $14,746
Processing
*(12months/year)*(1visit/5RFIs)
Time
Total Cost per Engineer $59,904
131
Table 6.10 Benefits Calculation of Function B
Driving 200miles*($0.36/mile)*(256RFI/4months) $11,058
Cost *(12months/year)*(1visit/5RFIs)
200min*(1hour/60min)*($96/hour)
Travel $49,152
*(256RFIs/4months)*(12months/year)
Time Cost
*(1visit/5RFIs)
RFI
1hour*($96/hour)*(256RFIs/4months) $14,746
Processing
*(12months/year)*(1visit/5RFIs)
Time
Total Cost per Engineer $74,956
From the data in table 6.11, the benefits to cost ratio is 1.23 and the total
benefits of function B is $11,401 more than it total cost.
From the data in table 6.12, the benefits to cost ratio is 0.92
132
Table 6.12 Cost Benefit Analysis of Function B
Costs Total cost using Alternative 2 $81,062
Driving Cost $11,058
Remote
Travel Time $49,152
Problem
Benefits RFI Processing $14,746
Solving
Time
Total Benefits $74,956
Benefit to Cost Ratio = $74,956/ $81,062= 0.92
Net Benefits = $74,956 - $81,062= $-6,106
$400,000
$350,000
$300,000
Cost
$250,000
$200,000
$150,000
$100,000
$50,000
$0
15 12 10 5 1
Visit per RFIs Numbers
The upper graph shows that with the increase of the distance from the
construction site, the more sensitive to the site visit frequency the results will be.
It also shows a logarithmic increase in total money saved as the number of visits
to site per number of RFIs decreases. From the graph above, we can calculate
133
the break even of implementing this model just based on the fact of mentioning
the total distance traveled and the number of visit for every RFIs.
To summarize the benefits of this function, we agree on:
• RFIs process will improve providing remote workers a real time tool using
the internet to get access to activities going on construction site.
• With this system, the ability to quickly resolve construction claims and
shorten the time for RFIs will bring other benefits, but these are difficult to
determine.
• Due to the difficulty in assessing indirect and intangible costs, the
economic analysis used in this chapter focus on measuring direct cost and
benefits. However, intangible costs and benefits are equally important and
need more in-depth exploration.
134
The other benefits that can be calculated based on this function are work
process elimination and reduce in reworks. That was shown in the work process
flow of the PEB steel structure. Applying the proposed model on the construction
site, eliminate time to stakeout the materials once they are on the jobsite, and
eliminate the need to mark the steel parts again, to identify the parts when
erection starts. Based on measuring the time it took the workers to stakeout the
steel parts, and again to make their own notes to identify the steel parts and
mark them, it was safe enough to make the assumptions that 5% of the total cost
of the project would be saved by implementing function C.
Table 6.14 Rework and Process Elimination Savings for Case study 1
Rework and
Process 5%*$3,000,000 $150,000
Elimination
Table 6.15 Rework and Process Elimination Savings for Case study 2
Rework and
Process 5%*$12,600,000 $630,000
Elimination
So the total saving gained from function C for case study 1 will be:
So the total saving gained from function C for case study 2 will be:
135
6.7.3.1 Cost Benefit Analysis
Based on table 6.16, the total cost and benefits are calculated in table
6.18 to calculate the economic impacts of function C for case study 1.
From the data in table 6.18, the benefits to cost ratio is 3.86 and the total
benefits of function C is $138,591 more than it total cost.
Based on table 6.17, the total cost and benefits are calculated in table
6.18 to calculate the economic impacts of function C for case study 1.
From the data in table 6.19, the benefits to cost ratio is 8.22 and the total
benefits of function C is $586,032 more than it total cost.
136
6.7.4 Function D: E-Document Management Savings
This function addresses bottleneck in the shop drawing approval process
of structural steel construction. The submittal log maintained five shop drawing
packages between Sperry and Associates and American Building Company
during the shop drawing approval stage. Using e-drawing will accelerate the
process of drawing moving from one party to another and the work flow will be
much faster. So if a modification is required, it can be completed on line and sent
to the next party involved in the approval process in real time.
The costs for a traditional paper based document delivery are calculated
based on the following assumptions:
• Five sets of drawings are reproduced by the steel supplier
• Plan-printing price for one set of drawings (30 sheets) is $65
• Typical UPS rate associated with sending a 20Lbs tube of drawing
package to each party involved in the approval process is $80
137
The total savings is $213,348, which represents roughly 7% of the total
cost of the project. Implementing the proposed model will result in at least
additional 7% in profit. This was based only on direct savings.
The total savings is $678,039, which represents roughly 5.5% of the total
cost of the project. Implementing the proposed model will result in at least
additional 5.5% in profit. This was based only on direct savings.
138
CHAPTER 7
139
alternatives were tested in the evaluation model to determine the best alternative
to be used in our case studies.
Then the research proposed a framework for a real-time model for project
progress tracking. The basic premise of the proposed model is to network
previously stand alone islands of communication on a construction site to allow
for the network between different parties involved in the construction project. So
a database was developed to show where the information will be stored, how
they can be retrieved, and how the progress of the activities is implemented in
the master schedule to keep all parties updated.
Then two case studies were used to highlight the values of implementing
such model on the construction site. That was achieved first by studying the
construction process, developing flow diagram, and then performing simulation
analysis to determine productivity before and after implementing the real-time
project progress-tracking model.
140
site and not able to access the site office. Simple queries using SQL are
presented to represents some of the information needs on the construction
site.
• This research identifies the need to improve construction site efficiency by
implementing information technology. Barriers to implementation of such
systems on construction site are identified. Some of the barriers are lack of
assessment method to incorporate different criteria in the user judgment and
lack of metrics to assess benefits. So the need to a decision support tool and
a clear benefit assessment metrics arises.
• A hybrid decision support model for real-time project tracking model selection
is developed. The model applies principles from multi-attribute decision theory
to help decision makers to select and evaluate the appropriate information
technology for the required construction application. This model is based on
analytic hierarchy process that applied eigenvector method to determine the
users’ preferences. The model evaluates each proposed criteria and give it a
utility function value. The alternative with the highest utility value corresponds
to the best alternative that fulfills the need. With small modifications, the
hybrid decision model can be used to assess other can of goals by just
modifying the required attributes for assessment.
• For models implementation, two steel construction projects were used as
examples for the proposed models. An information flow diagram, followed by
simulation model for Pre-Engineered process from shipping the steel
materials till erection on the construction site was developed. Then a
feasibility study of implementing the proposed project tracking model and its
impact on the construction project was conducted. Because the multifaceted
benefits of the various applications, different scientific methods were used to
measure the value that the technology integrated model will incorporate into
the construction process.
141
7.3 Limitations
The construction industry is very conservative, and will only adopt new
information technologies if they are simple to implement, and provide immediate
benefits. Hopefully, the value assessment study we included in this thesis will
open the window for real time tracking using information technology.
The model presented in this research should be fully developed by writing
a computer program to link Microsoft project and Microsoft Access, and then link
Microsoft Access to the RFID software. It is recommended that a pilot project be
conducted by construction companies looking to invest in the proposed model
before completely changing the current process. If the pilot project is a success
142
and the company wants to implement this change for all future projects, then
further effort should go into planning and research to ensure that a smoothly
running system is being developed.
The survey developed in this survey should be continued by getting a
bigger population size. At the end the bigger the population is, the better the level
of confidence and the less the margin of error allowed.
This research only attempted to evaluate two categories of hardware
computing and wireless connection. Future work should include more categories
like wearable computers.
143
APPENDIX A
SMART CHIPS
Linear barcode
parallel and varying width of bars and spaces (see figure 3.2). These bars work
as the license plate data holders, typically hold 10 to 20 characters, where they
Stacked
In this type, short individual linear barcodes are stacked on the top of each
other (see figure 3.3). This stack barcodes store relatively a large amount of data
(up to 1000 characters) along the height of the code. The most successful
symbology is the portable data file (PDF 417) in which a series of data items can
Stacked Barcode
Source: (http://www.taltech.com/resources/intro_to_bc/bcsymbol.htm)
144
Matrix barcodes (Two-dimensional)
The need to increase the data capacity and information density of barcode
Matrix Barcodes
Source: (http://www.taltech.com/resources/intro_to_bc/bcsymbol.htm)
145
Global RFID tag classification
Class 0 Passive Factory programmable (64 bit only)
bit min.)
memory
Class 4 Active – battery powered Long range (300’), user memory, sensors…
146
147
Passive RFID Tag
148
149
Handheld RFID Reader
150
Jobsite Information Needs (adapted from de la Garza and Howitt 1998)
1. Request for Information (RFI) Design intent and clarification
Subcontractor information
Contract specifications
Contract drawings
Work package information
Means and methods
Implementation problems
151
APPENDIX B
SURVEY
It will take you about 15-20 minutes to answer the questionnaire. Your
participation will be most appreciated and your responses will not be released to
any other parties without your consent.
Regards,
152
Informed Consent
This survey is being conducted by Amine Ghanem, a graduate student with Florida State
University's College of Engineering, as research for his thesis on assessing the feasibility
of implementing wireless technologies in construction. Dr. Yassir AbdelRazig is the
Graduate Advisor for this student, and will be the professor overseeing this research.
Your participation in this research is voluntary, and consists of filling a series of online
tables about user preferences that will take approximately 20 minutes. By law, you must
be 18 years old or older to participate in this research. By submitting your survey you are
indicating your consent to participate, and that you are at least 18 years old. You may
withdraw consent at any point by closing the Web page before completing and submitting
the survey. There will be no penalty for non-participation. All answers will be kept
completely anonymous, and information obtained during the course of the study will
remain confidential to the extent allowed by law.
If you are uncomfortable supplying your name, email address, and company name, you
may complete the survey without including this data.
If you are interested in receiving the final results please provide us with your name and
email address at the end of the survey.
If you have any questions about your rights as a subject for this research you may contact
the Chair of the Human Subjects Committee, Institutional Review Board, at 850-644-
8633. If you have any questions regarding this research please contact Amine Ghanem
by email at [email protected] or by phone 850-410-6211. Dr. AbdelRazig can be reached at
[email protected].
Name *
Email Address *
Company Name *
Education Level
Experience
Position
* Optional fields
153
Section 2: Setting Priorities
Please assign a weight from 1 to 9 based on the relative importance of one element over
another with respect to the criteria. Please refer to the table below for the degree of
importance
Degree of
Definition Explanation
Importance
1
Equal importance Two elements contribute equally to the property
• Remember that the element that appears in the left hand column is always
compared with the element appearing in the top row
• For example if technological criteria is 4 times more important than economic
criteria, put 4 in the appropriate box and if economic criteria is 3 time less
important than risk criteria put 1/3 in the appropriate box as shown in the table
below:
154
1) Please fill the table below with the degree of importance in order to fulfill a real
time project progress tracking
2) Please fill the table below with the degree of importance in order to fulfill the
technological importance
3) Please fill the table below with the degree of importance in order to fulfill the
economical importance
Initial Operating Saving in Quality
Investment Cost Labor Improvement
Initial
1
Investment
Operating
1
Cost
Saving in
1
Labor
Quality
1
Improvement
155
4) Please fill the table below with the degree of importance in order to fulfill the risk
importance?
Equipment Performance Investment
Security
Reliability Reliability Risk
Equipment
1
Reliability
Performance
1
Reliability
Investment
1
Risk
Security 1
Attributes Measures UL UH
Technical Moderate/Satisfactory Very Low Very Low
Requirement Skills
Accuracy Low/high Very Low Very Low
Rugged Characteristic IP00 IP00 IP00
Screen dimension inches 2 2
Battery life Hours 1 1
Weight including Lb 0.5 0.5
Battery
Writing Ability Typing/Touching Typing Typing
Software CAD/Project None None
Accommodation Management/Both
Wireless kbps- Mbps 14Kb 14Kb
Connection Speed
% of Project Total 0.25% 0.25%
Initial Investment
Cost
% of Project Total 0.25% 0.25%
Operating Cost
Cost
Saving in Labor Satisfactory/moderate Very Unsatisfactory Very Unsatisfactory
Quality Satisfactory/moderate Very Unsatisfactory Very Unsatisfactory
Improvement
Equipment Low/High Very Low Very Low
Reliability
Performance Low/High Very Low Very Low
Reliability
Investment Risk Low/High Very Low Very Low
Security Y/N Yes Yes
156
Thank you very much for your willingness to participate in this short survey. If you
are interested in receiving the final result please provide us with your information
below:
Name
Email Address
157
Ingress Protection Rating Explanation
158
Minimum Sample Size of a Population
159
APPENDIX C
CASE STUDY DOCUMENTS
160
Different Phases of the Project
161
Pre-Engineered Building Elevation
162
Pre-Engineered Building Elevation Continue
163
Plan of the Pre-Engineered Building
164
Bill of Materials
165
Bill of Materials Continue
166
Bill of Materials Continue
167
Case Study 2 Files
168
Different Phases of the Project
169
Master Schedule
170
Master Schedule Continue
171
Master Schedule Continue
172
Master Schedule Continue
173
Master Schedule Continue
174
Master Schedule Continue
175
APPENDIX D
STEEL SHIPPING
PRODUCTIVITY INFORMATION
Total Sim. Time Unit Cycle No. Productivity (per time unit)
107.3 30 0.27954059805008047
STEEL SHIPPING
STEEL SHIPPING
176
WAIT TO
QUEUE 4 0.1 3 12.3 11.43 107.3 0.4 0
OFF-LOAD
CREW
QUEUE 5 0.4 1 46.7 43.55 107.3 1.4 0
AVAILABLE
CRANE
QUEUE 6 0.4 1 46.7 43.55 107.3 1.4 0
AVAILABLE
TRUCK
QUEUE 10 3.1 6 107.3 100.00 107.3 8.1 4
QUEUE
177
Results: PROPOSED STEEL SHIPPING
STEEL SHIPPING TO BE
PRODUCTIVITY INFORMATION
Total Sim. Time Unit Cycle No. Productivity (per time unit)
67.1 30 0.4471830100933253
STEEL SHIPPING
STEEL SHIPPING
178
OFF-LOAD
CREW
QUEUE 6 0.3 1 23.2 34.58 67.1 0.7 0
AVAILABLE
CRANE
QUEUE 7 0.3 1 23.2 34.58 67.1 0.7 0
AVAILABLE
TRUCK
QUEUE 11 0.4 6 15.6 23.26 67.1 0.6 2
QUEUE
179
Results: STEEL ERECTION
STEEL ERECTION
PRODUCTIVITY INFORMATION
Total Sim. Time Unit Cycle No. Productivity (per time unit)
2155.9 300 0.13915594220655672
STEEL ERECTION
180
STEEL ERECTION
181
FORKLIFT
QUEUE 28 0.6 1 1260.4 58.46 2155.9 4.2 0
IDLE
182
PROPOSED STEEL ERECTION
PRODUCTIVITY INFORMATION
Total Sim. Time Unit Cycle No. Productivity (per time unit)
1699.3 300 0.17654286547624465
STEEL ERECTION
183
STEEL ERECTION
184
IDLE
185
Input Files
186
19 COM 'CONNECT GIRDERS' SET 18 PRE 17 18 FOL 18 20
20 QUE 'WAIT TO CONNECT GIRDER TO COLUMNS'
21 QUE 'CRANE IDLE'
22 COM 'ERECT GIRDERS' SET 22 PRE 18 20 21 FOL 18 21 23
23 FUN CON 2 FOL 24
24 QUE 'BRACING AVAIL'
25 QUE 'WORKERS IDLE'
26 COM 'INSTALL BRACING' SET 25 PRE 24 25 FOL 25 27
27 QUE 'PURLINS AND GIRTS AVAILABLE'
28 QUE 'FORKLIFT IDLE'
29 COM 'INSTALL PURLINS AND GIRTS ' SET 28 PRE 11 27 28 FOL 11 28 30
30 FUN COU FOL 4 QUA 1
DURATION INPUT
SET 6 NOR 3 1
SET 9 NOR 1 0.5
SET 12 NOR 0.5 0.2
SET 16 NOR 0.5 0.2
SET 18 NOR 1.5 1
SET 22 NOR 2 1
SET 25 NOR 3 1
SET 28 NOR 3 1
RESOURCE INPUT
4 'COLUMN' AT 4
1 'CRANE' AT 5
2 'WORKERS' AT 6
1 'COLUMN' AT 8
4 'ERECTORS' AT 11
2 'CONNECTORS' AT 14
2 'GIRDERS' AT 17
2 'CONNECTORS' AT 18
1 'CRANE' AT 21
2 'WORKERS' AT 25
1 'FORKLIFT' AT 28
ENDDATA
Erection Input Model
187
9 NOR 'TRAVEL BACK' SET 4 FOL 10
10 FUN COU FOL 11 QUA 1
11 QUE 'TRUCK QUEUE'
DURATION INPUT
SET 1 NOR 1 0.5
SET 2 NOR 7 2
SET 3 NOR 1 0.5
SET 4 NOR 7 2
RESOURCE INPUT
1 'RFID Tags' AT 1
1 'STEEL BATCH' AT 2
3 'TRUCK' AT 5
1 'CREW' AT 6
1 'CRANE' AT 7
6 'TRUCKS' AT 11
ENDDATA
Proposed Shipping Input Model
188
30 FUN COU FOL 4 QUA 1
DURATION INPUT
SET 6 NOR 3 1
SET 9 NOR 1 0.5
SET 12 NOR 0.5 0.2
SET 16 NOR 0.5 0.2
SET 18 NOR 1.5 1
SET 22 NOR 2 1
SET 25 NOR 3 1
SET 28 NOR 3 1
RESOURCE INPUT
4 'COLUMN' AT 4
1 'CRANE' AT 5
2 'WORKERS' AT 6
1 'COLUMN' AT 8
4 'ERECTORS' AT 11
2 'CONNECTORS' AT 14
2 'GIRDERS' AT 17
2 'CONNECTORS' AT 18
1 'CRANE' AT 21
2 'WORKERS' AT 25
1 'FORKLIFT' AT 28
ENDDATA
189
REFERENCES
1) Abduh, M., Skibnieski, M. (2002). “Utility Assessment of Electronic
Networking Technologies for Design-Build Projects”. Journal of Automation in
Construction (12) 167-183
3) Akinci, B., Boukamp, F., Gordon, C., Huber, D., Lyons, C., and Park, K.
(2005). “A formalism for utilization of sensor systems and integrated project
models for active construction quality control.” Automation in Construction,
15(2), 124–138.
9) Barringer, H. P., and Weber, D. P. (1996). “Life cycle cost tutorial”. Fifth
international conference on process plant reliability. Houston, Texas.
12) Bernold, L.,E., Treseler, J.,F., (1991) “Vendor analysis for best buy in
construction ,” Journal of construction engineering and management, vol.117,
No. 4, pp. 645-658
190
13) Blakey, L. (1990) “Barcodes: Prescription for precision, performance, and
productivity”. Journal of Construction Engineering and Management, ASCE,
116(3), 468-477.
15) C. Harmon, R. Adams, Reading between the lines, Helmers Publishing, Inc.,
Pterborough, NH, 1984
16) Cheng, M. Y. & Chen, J. C. (2002), “Integrating bar code and GIS for
monitoring construction progress”. International Journal of Automation in
Construction, 11(3), 23–33.
17) Cheok, G. S., Lipman, R. R., Witzgall, C., Bernal, J., and Stone, W. C.
(2000). NIST Construction Automation Program Rep. No: 4 Non- Intrusive
Scanning Technology for Construction Status Determination, Building and
Fire Research Laboratory, National Institute of Standards and Technology,
Gaithersburg, Md
18) Chin, S., Yoon, S., Kim, Y.S., Ryu, J., Choi, C., Cho, and C.Y. (2005)
“Realtime 4D CAD + RFID Project Progress Management”. Construction
Research Congress, San Diego, USA.
21) Coe, L. (1993), Wireless Radio, A Brief History, McFarland & Company, Inc.,
North Carolina.
22) COMIT. (2003). "Current status of Mobile IT." Construction Opportunities for
Mobile IT.
24) Construction Industry Institute (CII) (1986a), Project Control for Engineering,
Publication 6-1, The Construction Industry Institute, The University of Texas
at Austin, Austin, Texas.
25) Construction Industry Institute (CII) (1987a), Model Planning and Controlling
System for EPC of Industrial Projects, Publication 6-3, The Construction
Industry Institute, The University of Texas at Austin, Austin, Texas.
191
26) Computer Economics, Inc. (2004) “Handheld Computer Market Projections,”
Computer Economics, Inc. website, http://www.computereconomics.com/
28) Dell’Isola A., J., Kirk J., S. (19950. “Life cycle costing design professionals”.
McGraw-hill, New York.
29) Dhillon, B., S. (1989). “Life cycle costing”. Gordon and Breach Science
Publisher, Amsterdam, Holland.
30) Durfee, Adam and Paul Goodrum. RFID, MEMS, and their Applications in the
Field of Construction. White Paper. 11 January, 2002
31) El-Dirabi, T., Rasic, I. (2004). “Framework for managing life cycle cost of
smart infrastructure systems”. Journal of computing in civil engineering,
vol.18, n. 2, pp. 115-119
33) El-Misalami, T., Wlaters, R., Jaselskis, E., (2006). “Construction IT Decision
Making Using Multiattribute Utility Theory for Use in a Laboratory Information
Management System”. Journal of construction engineering and management,
(12) 1275-1283
35) Garett, J. II., Sieworiek, D. P., and Smailagic, A. (1998). “Wearable computer
for Bridge inspection.” Proc. Int. Symposium on wearable computers,
Pittesburgh, 160-161
36) Ghanem, A., AbdelRazig, Y. (2007) “Real time Construction Project Progress
Tracking: A Utility Function Model for Technology Evaluation and Selection”,
Proceeding of the Construction Research Congress, Grand Bahamas Island
192
38) Goodrum, P., Mclaren, M., Durfee, A., (2005), “The application of active radio
frequency identification technology for tool tracking on construction job sites,”
Journal of Automation in Construction
39) Halpin, D.W. (1985), “Financial and Cost Concepts for Construction
Management”, John Wiley & Sons, Inc. New York, Ny
41) Inglesby, T. (2000) “Handheld Computing: In the field, Handhelds Can Make
a Difference,” ConstruTech, 3(4), http://www.construtech.com/
43) Jaselskis, E., Anderson, M., Jahren, C., Rodriguez, Y., Njos, S. (1995).
“Radio Frequency Identification applications in construction industry”. Journal
of construction engineering and management, vol. 121, n. 2, pp. 189-196
44) Johnson, K.D. and Tatum, C.B. (1993), “Technology in Marine Construction
Firms,” Journal of Construction Engineering and Management, v119, n1,
pp148-162
45) Karkkainen, M. (2003). “Increasing efficiency in the supply chain for short life
goods using RFID tagging”. International journal of retail & distribution
management, vol. 31, n. 10, pp. 529-536.
46) Kashiwagi D., Sullivan K., Greenwood D., Kovell J., and Egbu C. (2004).
“Source of construction industry instability and performance problems”.
Performance based studies research group, Arizona State University
47) Kidston, P., (2005) “Controlling construction project using earned value
analysis”
48) Laborde M., Sanvido V., (1994). “Introducing new process technologies into
construction companies”. Journal of construction engineering and
management, Vol. 120, No. 3, 488-508
50) Liu, L. Y. (1997). “Construction field data collection using the digital hardhat”.
Proceeding of Fifth Construction Congress, Minneapolis, MN
193
51) Lundberg, E. J. & Beliveau, Y. J. (1989), “Automated lay-down yard control
system—ALYC”. Journal of Construction Engineering and Management,
ASCE, 115(4), 535–44.
53) Memon, Z. A., Majid, M., Mustaffar, M. (2005) “An Automatic Project
Progress Monitoring Model by Integrating Auto CAD and Digital Photos”.
Proceedings of the ASCE International Conference on Computing in Civil
Engineering, Cancun, Mexico.
54) Mitropoulos P., Tatum C. B., (2000). „Forces driving adoption of new
information technologies“. Journal of construction engineering and
management, Sept./Oct. 340-348
56) Ngai, E., Cheng, T., Au, S., Lai, K. (2005). “Mobile commerce integrated with
RFID technology in a container depot”
59) O’Connor, J.T. and Dodd, S.C. (2000), “Achieving integration on capital
projects with enterprise resource planning systems,” Automation in
Construction, Elsevier Science B.V., Amsterdam, The Netherlands, v9, n5-6,
pp515-524, September
61) Oloufa, A., Ikeda, M., Oda, H. (2003). “Situational awareness of construction
equipment using GPS, wireless and web technologies”, Journal of automation
in construction, vol. 12, pp. 737-748
62) Pascoe, J., Ryan, N. S., and Morse, D. R. (1998). “Human computer giraffe
interaction: HCI in the field.” Workshop on human computer interaction with
mobile devices, GIST technical report G98-1, University of Glasgow
194
63) Pena-Mora, F., Dwivedi, G. 2002, “Multiple device collaborative and real time
analysis system for project management in civil engineering”, Journal of
computing in Civil Engineering
64) Prasad R., Ruggieri M. Editorial (2003). “Unified Global Infrastructure”,
Wireless Personal Communications, Vol. 26, Nos. 2–3, pp. 89–91.
65) Poku, S., Arditi, D. (2006) “Construction Scheduling and Progress Control
Using Geographical Information systems”. Journal of Computing in Civil
Engineering, volume 20, (5), p 351-360
66) Rasdorf, W. J. & Herbert, M. J. (1989), “Bar codes on the job site”. ID
System, 9(3), 32–36.
68) Repass, K., De la Garza J., Thabet, W., (1999) “Mobile schedule tracking
technology at the jobsite” In Proceedings of Construction Congress VI, Feb.
20-22
69) Salkind, N. J. (1997). Exploring research (3rd ed.). Upper Saddle River, NJ:
Prentice Hall.
73) Singhvi, V., Fish, W. and Terk, M. (2003) “Context-Aware Information System
for Construction Site Applications” Proceedings of Construction Research
Congress In Construction - Wind of Change: Integration and Innovation
74) Skibmiewski, M., and Hendrickson, C. (1990) “Automation and Robotics for
Road Construction and Maintenance,” Journal of Transportation Engineering,
ASCE, v116,n3
195
76) Song, J., Haas, C., Caldas, C., Ergen, E., Akinci, B. (2006) “Automating the
Task of Tracking the Delivery and Receipt of Fabricated Pipe Spools in
Industrial Project”. Journal of Automation in Construction, 15 p 166-177
78) Thorpe, T., and Mead, S. (2001). “Project-specific web sites: Friend or foe?”
Journal of Construction Engineering and Management, 127(5), 406–413.
79) Tsai, M. K., Yang, J. B., and Lin, C. Y. (2007) “Integrating Wireless and
Speech Technologies for Synchronous On-Site Data Collection”. Journal of
Automation in Construction, 16 p 378-391
80) Tserng, H., Dzeng, R., Lin, Y., Lin, S. (2005). “Mobile construction supply
chain management using PDA and bar codes”. Computer Aided Civil and
Infrastructure Engineering, vol. 20, pp. 242-264
81) Tucker, R.L. (1988) “High Payoff Areas for Automation Applications,”
Proceedings of the 6th International Symposium on Automation and Robotics
in Construction, Japan Industrial Robot Association, Tokyo, Japan, pp9-16
82) Tucker, R.L., Haas, C.T., Borcherding, J.D., Allmon E., and Goodrum, P.M.
(1999) “U.S. Construction Labor Productivity Trends, 1970-1998,” Center for
Construction Industry Studies, Report No. 7, The University of Texas at
Austin, Austin, Texas, March 1999
83) U.S. Census Bureau, 1997 Economic Census: Construction, Appendix A-8,
10 January 2000, www.census.gov
85) Ward, M. J., Thorpe, A., and Price, A. D. F. (2003). "SHERPA: Mobile
wireless data capture for piling works." Computer-Aided Civil and
Infrastructure Engineering, 18, pg. 299-312.
88) William, Trefor P. (2003). “Applying Hand held Computers in the Construction
Industry.” Practice Periodical on Structural Design and Construction. 8.4.
196
89) Wirt, D., Showalter, W. E. & Crouch, G. (1999), “Integrating permanent
equipment tracking with electronic operations and maintenance manuals,
Durability of Building Material and Component”. Information Technology in
Construction, vol. 4, NCR Research Press, pp. 2716–23.
90) Yagi et al., Arai, E., Arai, T. (2005). “Parts and packets unification radio
frequency identification application for construction”. Journal of automation in
construction, vol. 4, pp. 477-490
91) Zebra Technologies (2002). “Small labels provide big savings opportunities
for electronics manufacturers”. www.zebra.com/IS/manuf_electronics.htm
92) Zayed T. M., and Halpin, D. W. (2000) “Simulation as a Tool for Resource
Management”. Proceeding of the 2000 Winter Simulation Conference.
93) Web 1: Geier, Jim. “Defining Access Point Range Boundaries.” Wi-fi Plane
Tutorials. 27 May 2003.
http://www.wifiplanet.com/tutorials/article.php/2212591
197
BIOGRAPHICAL SKETCH
EDUCATIONAL BACKGROUND
SUMMARY OF EXPERTISE
Project Management
Construction Estimation
Information Technologies in Construction
Project Control and Scheduling
Simulation Model
Risk Analysis
Cost Benefit Analysis
Applications of GIS in transportation systems
198
PROFESSIONAL CERTIFICATIONS
TEACHING EXPERIENCE
199
WORK EXPERIENCE
o Advances PowerPoint
Electronic Campus
o Advanced PowerPoint
200
o Blackboard Communication
PUBLICATIONS
Ghanem, A., AbdelRazig, Y.: “Real time Construction Project Progress Tracking: A
Utility Function Model for Technology Evaluation and Selection”, to be presented in the
Construction Research Congress, Grand Bahamas Island, May 2007
Ghanem, A., AbdelRazig, Y., and Mehdi, S. M.: “Evaluation of a Real Time
Construction Project Progress Tracking”, to be presented in Joint International
Conference on Construction Culture, Innovation, and Management, Dubai, UAE,
November, 2006
Ghanem, A., Abichoux, T., and AbdelRazig, Y.: “Sprayfield Technology to Treat
Wastewater Treatment Plant Effluent”, accepted in the 3rd International Conference on
Water Resources in Mediterranean Basin, Tripoli, Lebanon, November, 2006
Ghanem, A., and AbdelRazig, Y.: “A Framework for Real Time Construction Project
Progress Tracking”, proceeding of the 10th International Conference on Engineering,
Construction and Operations in Challenging Environments, Houston, Texas, March, 2006
El-Gafy, M., AbdelRazig, Y., and Ghanem, A.: “Dynamic Construction Site Layout
Using Ant Colony Optimization”, proceeding of the 85th meeting of the Transportation
Research Board (TRB), Washington DC., February, 2006
201
Ghanem, A., Mehdi S., and AbdelRazig, Y.: “Risk Management in Engineering Design
Projects”, the Journal of Project Management, under review
Ghanem, A., Oberlender, G.: “Six Sigma in Construction Projects”, creative components
submitted as fulfillment of Master Degree
Ghanem, A., Chatila, W.: “Management and Rehabilitation of an Existing Building”, thesis
submitted as fulfillment of Bachelor Degree
LISTINGS
AFFILIATIONS
PHI KAPPA PHI (Oklahoma Chapter) Honor Society for excelling school
achievements: Member since 2002
Tau Beta Pi (Florida Etta Chapter) Engineering Honor Society: Member since 2005
(Treasurer)
Fiatech Student Member, Involved with Smart Chips project since 2006
202
AWARDS
The Conference Presentation Grant. Awarded by the Florida State University Office of
Graduate Studies to assist in Conference presentation, (March 2006 and October 2006).
The Dissertation Research Grant. Awarded by the Florida State University Office of
Graduate Studies to assist the research of my dissertation, October 2006.
Best Teaching Award. Nominated by the Florida State University for best Teaching
Assistant, March 2007
203