Managing Transition Between Construction Completion, Pre-Commissioning, Commissioning, and Startup
Managing Transition Between Construction Completion, Pre-Commissioning, Commissioning, and Startup
November 2017
© 2017 Construction Industry Institute™
CII members may reproduce and distribute this work internally in any medium at no cost to internal recipients. CII members
are permitted to revise and adapt this work for their internal use, provided an informational copy is furnished to CII.
Available to non-members by purchase; however, no copies may be made or distributed, and no modifications may be made,
without prior written permission from CII. Contact CII at http://construction-institute.org/catalog.htm to purchase copies.
Volume discounts may be available.
All CII members, current students, and faculty at a college or university are eligible to purchase CII products at member
prices. Faculty and students at a college or university may reproduce and distribute this work without modification for
educational use.
Chapter
Executive Summary v
1. Introduction 1
Project Performance and Commissioning Impacts: 1
The Business Case
Commissioning Transitions and Complexities 2
Scope of this Research and Report 6
2. Methodology 9
3. Findings 13
CCSU Implementation Process 13
CCSU Solution Tools 15
CCSU Hot Spots 37
Heidelberg Spar Illustrative Case Study 48
References 139
iii
Executive Summary
Several prior studies indicate that commissioning failures are too common in frequency
and extremely costly in impact. The business case for action is clear, yet the transitions
between construction/pre-commissioning/commissioning/startup/close-out (abbreviated
CCSU in this publication, emphasizing the construction component) remain challenging
for many reasons. This is primarily due to contractual separations and the multitude of
organizational interfaces and handoffs during CCSU.
2. CCSU RACI Matrix – The RACI matrix builds on the CCSU activity
flowchart, defining whether each activity’s manager is Responsible, is
Accountable, should be Consulted, or should be Informed. While the
Commissioning/Startup manager is generally responsible for 49 of the
activities, 39 other activities are generally the responsibility of three other
key managers: Project manager, Construction manager, and Operations
manager.
v
3. CCSU Hot Spots – RT-333 provided further insight into the challenges of
CCSU transitions by identifying “hot spots”: CCSU activities that generally
either have unclear responsibility assignments, recurring problems, or
deficiencies, or that often fail to deliver on expectations. Twenty CCSU hot
spots surfaced from research-based screening efforts. Surprisingly, three-
quarters of the selected hot spots occur during the Construction phase,
emphasizing the challenges of transitions and indicating a need for greater
involvement and alignment by the project management team during this
phase.
Collectively, the findings from this study provide focused and substantive guidance on
how project teams can enhance the effectiveness of CCSU transitions.
http://go.cii.today/sp333-1
vi
1
Introduction
The business case for more careful and effective project commissioning is no
mystery. Numerous individual project case studies, industry studies, and publications
have documented the extensive added cost, delayed payback, and loss of investment
value that result from ineffective plant commissioning and startup. Some representative
findings include the following alarming statistics:
• The transition from [construction] execution into operations is where high
leakage of value occurs. In certain case studies, this leakage has destroyed
30% of the initial investment value. (Deloitte 2012)
• Of all CII 10-10 projects surveyed, 30% experienced commissioning cost
overruns and 40% had commissioning schedule overruns. (CII 2016)
• On average, companies reporting low use of CII’s Planning for Startup Best
Practice had a project cost 7.4% higher than those with high use of Planning
for Startup. (CII 2010)
• Of 130 oil and gas megaprojects (costing more than $1 billion), 78% were
classified as failures. (Merrow 2011)
• Overall, 47% of oil and gas production facilities had significant operability
problems. These failed projects averaged only 60% of planned production in
the first year, and 65% suffered long-term operations issues. (Merrow 2011)
• On average, offshore projects that leave the yard incomplete and need to
complete fabrication offshore have an actual hook-up/commissioning cost of
almost 250% of planned cost. (Lamport and Rosenberg 2005)
• Among 11 large steel manufacturing facilities started up in the late 1990s,
none reached design capacity within one year, and only one did so after two
years. (Bagsarian 2012)
Quantitatively, the RT-333 research found several examples of the costly effects
from delayed production:
• Greenfield biotech project: up to $3 million per day of lost production
• Deep-water spar projects: up to $2 million per day of lost production
• Large greenfield chemical plant projects: up to $1.5 million per day of lost
production
1
1. Introduction
To u n d e r st a n d t h e c o m p l ex i t y of
commissioning and star tup, one must
appreciate the complexity of the various CCSU
transitions. One way to do this is to overview
the five phases involved and recognize that
“a baton is being passed” at each of four
transitions:
1. Construction to Pre-Commissioning
2. Pre-Commissioning to Commissioning
3. Commissioning to Startup
4. Startup to Close-out
While the baton analogy may be overused, it seems very appropriate in this context. In
the case of CCSU, the baton represents incremental, documented progress: the project
evolves from an incomplete collection of physical objects during construction, to a physically
complete but not fully tested collection of systems, to ultimately an operating plant with
a fully-formed supportive infrastructure in both human and business system forms.
Figure 1 illustrates some of the complexities of phase transitions, and is helpful for
establishing some basic terminology. Fabrication (or pre-fabrication) adds another level of
transitional complexity, while sequential milestones represent progress markers. The dotted
horizontal swim-lanes indicate a systems-centric approach, rather than the conventional
emphasis on disciplines and geographical areas characteristic of field construction and
its management. (The scopes of Pre-Commissioning, Commissioning, and Startup are
described in detail in Appendix B. A full glossary of terms is provided in Appendix A.)
2
Site Systems/Subsystems Site Construction Pre-Commissioning Commissioning Startup Close-out
S1
S2
S3
SAT
Module-Integrated Systems MC EN TC PSSR TS IF FCP
Milestones
Transport
Fabrication Pre-Comm’ng
Skids/Modules
AT – Acceptance Testing
EN – Energization
FAT – Factory Acceptance Testing
MC AT FCP – First Commercial Product
IF – Introduce Feedstock (process materials)
MC – Mechanical Completion
PSSR – Pre-Startup Safety Review
SAT – Site Acceptance Testing
OEM/Engineering
Transport
TS – Turnover to Startup
Transition
FAT Interim Milestone
1. Introduction
3
1. Introduction
The figure provides motives, advantages, disadvantages, and sub-options for each
strategy. Abutting colored boxes depict contract and work scope, and indicate interface
management requirements or efforts. These interfaces are particularly relevant where
they coincide with the phase boundaries – and shed more light on CCSU transitional
challenges. Different organizations contractually engaged to execute different parts (or
phases) of the project establish fundamental boundary conditions for work scope and
associated responsibility assignments.
To better understand industry practice in this aspect, RT-333 asked 16 of its own
team members (owner and contractor) to identify which of these strategies they applied
to their various projects. The findings (i.e., collective averages) are shown in Figure 3.
Strategy B:
External
Commissioning
Team
Strategy A:
Owner– 25%
Construction
Contractor–
Equipment Strategy C:
Supplier Mix Turnkey by
56% Construction
Contractor
19%
4
Strategy A: Owner-Construction Contractor – Equipment Supplier Mix
Pre- Considerations/Motives Sub-Options
Construction Commissioning Startup • Owner, construction contractor, and • A1 – Owner-dominated
Commissioning
equipment supplier staff make up Commissioning execution
Oversight & the Commissioning team. • A2 – Construction contractor-
Owner/PM
Assurance • Variable: Level of Operations dominated Commissioning
involvement in Commissioning execution
• Contractor Commissioning • A3 – Equipment supplier-dominated
Management Owner/PM
execution trade labor supply only Commissioning execution
Operations Advantages Disadvantages
Owner +
Execution Construction Contractor Constr. Contr. + • Mix of skills/talents • Continuity of personnel
Eqpt. Supplier
1. Introduction
Figure 2. Three Dominant Models of Contracting and Service Delivery Identified by RT-333
5
1. Introduction
The CII Research Committee set up RT-333 with the following essential question:
How can the industry establish or clarify the accountabilities and responsibilities
among construction completion, pre-commissioning, commissioning, and
operations functions?
Early on, the team framed its intentions by first understanding prior commissioning-
related efforts and learnings by CII and others. These included the Planning for Startup
best-practice guidance established by RT-121 in the late 1990s, along with the more
recent work of RT-312, Best Practices for Commissioning and Startup.
Acknowledging these contributions and their continuing significance, RT-333 set out
to fill some knowledge-voids by defining CCSU transition activities, CCSU organization
functions, CCSU responsibility and accountability assignments, commonly problematic
“hot spots,” and an implementation process that ties together the key work products of
all three research teams.
Figure 4 depicts the relationship between the three bodies of work. Planning for
Startup guidance (RT-121) comes first and then transitions to CCSU execution efforts
(RT-333) early to mid-way through construction. The critical success factors (RT-312)
establish influential management efforts that provide an effective base or foundation
for both planning and execution (a listing of these is provided in Appendix D).
After this introductory segment, the structure of this report addresses methodology,
followed by findings. Findings are organized as solution tools, hot spots, and the Heidelberg
Spar illustrative case study. Conclusions and Recommendations recap key learnings,
followed by Appendices, which include a glossary of terms along with other elements.
6
Project Phases
Front-End Pre-
Detailed Design Construction
Feasibility Engineering Commissioning Commissioning Startup Close-out Operations
1. Introduction
7
2
Methodology
3. CCSU 4. Review of
2. Review of Literature and
System Phases RT-312
Corporate Practices
and Milestones Potential CSFs
7. CCSU
6. CCSU 8. CCSU
Contract
5. Organizational Activity List
Strategies/
Illustrative Functions and Flowchart
Delivery Models
Case Study
14. Validation
9
2. Methodology
Five major research products have resulted from the data collection and analysis
efforts, including the CCSU activity flowchart, the CCSU RACI matrix, hot spot
identification, hot spot characterizations, and the Heidelberg Spar illustrative case study.
Data gathering was conducted mostly through surveys and phone interviews.
CCSU Activity Flowchart – In its earliest form, this flowchart listed the CCSU
activities in the order they are executed, from the Construction phase through Project
Close-out. Activities were collected from literature review sources, team members’
company documents, and the research team itself. The list originally grew to include
more than 300 CCSU activities. Over time, with multiple reviews and revisions, RT-333
reduced the number of activities to 124 by eliminating repeats, combining like activities,
and excluding sector-specific activities. The remaining 124 activities were organized
into a matrix organized by phase timing and activity topic type. The team’s sub-teams
conducted “cold-eye” reviews of each phase-portion of the flowchart.
CCSU RACI Matrix – RACI matrices are a widely accepted industry-standard, efficient
way of modeling responsibility, accountability, consultation, and information-sharing
assignments for work activities. The CCSU RACI matrix was created by establishing
a listing of common capital project organizational functions (rather than roles or job
titles) and then assigning specific organizational functions as Responsible, Accountable,
Consulted, or Informed for each of the activities in the CCSU activity flowchart. This was
a highly iterative process in which the team’s sub-teams reviewed each other’s RACI
draft assignments and made modifications as needed. As with the flowchart itself, the
team’s sub-teams conducted “cold-eye” reviews of each phase-portion of the RACI matrix.
Hot Spot Identification – RT-333 used a survey to determine which CCSU activities
commonly have unclear responsibility assignments, result in recurring problems or
deficiencies, or often fail to deliver on expectations. The survey was completed by
both team members and their corporate colleagues that possess CCSU experience. A
total of 49 individuals representing 15 different companies participated in the screening
process. Each company’s representatives identified several CCSU activities that were
most problematic for their company, and documented their reasoning. The survey results
were compiled, and activities identified as problematic by three or more companies
were labeled as “hot spots.”
10
2. Methodology
hot spots cited should not restrict the breadth of issues considered or promote any
managerial complacency.
The Heidelberg Spar Case Study – RT-333 studied the Heidelberg Spar offshore
project to illustrate the positive impacts of effectively preventing or mitigating anticipated
CCSU hot spots (issues that had become evident on a prior, similar offshore spar project
that had experienced disappointing commissioning performance). The researchers
documented hot spot-related learnings and responsive actions taken from the Heidelberg
Spar project, along with a comparison of commissioning performance metrics between
the two projects. The illustrative case study was developed based upon shared project
documentation and in-depth interviews with key project personnel.
RT-333 sought to integrate all key commissioning-related guidance from CII into an
integrated CCSU implementation process. The team’s intent was to show how planning
for startup, commissioning critical success factors, and this new work by RT-333 can
be seamlessly integrated and implemented in a real-world capital project context. Like
many other steps in the team’s methodology, this effort was highly iterative, involving
many reviews and revisions.
Finally, 11 reviewers from outside RT-333 conducted validation reviews of the CCSU
activity flowchart, portions of the RACI matrix, and the hot spot characterizations. These
outside reviewers possessed a total 152 years of CSU experience on 169 different
commissioned projects. RT-333 received over 200 comments from the reviewers, and
made modifications in response to comments judged to be relevant, appropriate, and
beneficial.
11
3
Findings
5. Understand
Front-End 2. Plan for Startup (RTs 121 and 312)
CSU Contract
Engineering Strategy
3. Implement 4. Monitor
CSU Critical Associated CSF
Success Factors Leading Indicators
(RT-312) (RT-312) 7. Review the
RT-333 CCSU
Flowchart and
RACI Matrix
6. Confirm 8. Assign
Detailed Adequate Budget 9. Identify Names to
and Schedule for and Fill CCSU RACI
Design
Successful CSU Unassigned Organizational
Functions Functions
Pre-
Commissioning,
Commissioning,
and Startup
Close-out
13
3. Findings
The last five CCSU elements in the list above will be discussed in detail in this chapter.
For in-depth information on Planning for Startup and commissioning critical success
factors (and their indicators of achievement), see CII Implementation Resources 121-2
and 312-2, respectively.
14
3. Findings
For context and ease of comprehension, the 124 CCSU activities are also grouped
according to their topical or thematic category, for which there are four horizontal “swim
lanes”:
• Planning/Schedule/Management/Staffing (31 activities)
• Materials/Equipment/Components (27 activities)
• Subsystems/Systems/Interconnecting Systems (31 activities)
• Data/Documentation/Audits and Certifications (35 activities)
Interestingly, the activities are nearly evenly distributed across these four themes.
As has previously been indicated, in the CCSU Implementation Process (Figure 6),
the flowchart should be reviewed and discussed by the project team as a part of
Step 7: “Review the RT-333 CCSU Flowchart and RACI Matrix.” In regard to timing, it
is recommended that this step occur sometime between late Front-End Engineering
(also known as FEED, Detailed Scoping, or Basic Design) and early Detailed Design.
In the CCSU activity flowchart, CCSU activities that are associated with commonly
problematic CCSU “hot spots” (which will be discussed later) are indicated as shaded/
colored. (See Figure 7.) Refer to the glossary of terms provided in Appendix A to clarify
any unfamiliar terms.
15
3. Findings
1. Construction Phase
Early Mid Late
1 HS #11 E 7 EML 27 HS #6 ML
Conduct Construction- Conduct area-specific Plan for and manage
CSU alignment meeting health, safety, security, CSU schedule
on the execution plan and environ. training recovery
A. Planning/Schedule/Management/Staffing
2 HS #20 E 8 EML
Legend
Conduct Construction- Identify and manage Activity Hot Spot Phase
CSU team building CSU-related risks number number Timing
6 EML
Assess and
communicate CSU
effects from changes
B. Materials/Eqpt./
Mobilize CSU
document factory document site acceptance personnel with eqpt.
resources and facilities and integration tests
acceptance tests during FAT or on-site
13 HS #9 E 15 (60, 85) HS #2 E 29 ML
Perform preservation Complete and document
Procure CSU materials, individual equipment tests
including spare parts through fabrication and
(e.g., cold alignment,
construction megger testing)
16 E 18 EML 31 HS #3 M 34 ML 42 L 45 HS #8 L
C. Subsystems/Systems/
Interconnecting Systems
Identify Operations’ Transition to CSU Align on product and For brownfield projects, Complete collab. inspection
Hook up modules system-based execution execute the plan for walkthru of tags/systems by
responsible contact system performance
(from area- or physical tie-ins to Commissioning mgr, constr.
for each system discipline-based)
requirements existing plant systems contractor, and Operations
33 HS #4 ML 44 L
Perform cleaning,
Conduct point-to-point
passivation, and drying
of piping and ducts (incl. cable continuity checks
steam blowing, pigging)
19 HS #12 EM 23 EML 36 ML 39 ML 47 HS #5 L
Define system Update Construction Manage Identify and communicate
Monitor systems constr. punch list items
construction turnover documents based on construction quality
D. Data/Documentation/Audits
21 EML 25 EML 38 ML 41 ML
Execute related req’ts, Confirm regulator/ Conduct systems Transfer of custody
procedures, and assoc’d third-party verification of completion readiness and predefined
documentation for system safety-critical systems review turnover package
certific’ns and verifications
22 EML 26 EML
Execute the Review project-specific
asset data safety plans with focus
management plan on CSU transitions
16
3. Findings
2. Pre-Commissioning Phase
Early Mid Late
48 E 51 EML Legend
Conduct Identify and track
Pre-Commissioning open change Activity Hot Spot Phase
A. Planning/Schedule/
Management/Staffing
Activity Name
49 E 52 EML
Conduct
Comm’g-specific HSSE Close out identified
training for LOTO, JSA, punch list items
simult. ops., work requests A colored background signifies that
this is a Hot Spot.
50 E Activity numbers do not indicate
Coordinate system chronological execution order.
automation readiness re: Phase Timing:
req’ts, scope, sequence,
E = Early, M = Mid, L = Late
schedule, and software
53 (14) HS #1 E 58 E 67 M
Mobilize resources for Complete lubrication Conduct
Pre-Commissioning, and lubrication vessel and tank
including necessary inspections
check sheets
SMEs and third parties
B. Materials/Equipment/Components
54 E 59 EM 68 M
Verify the operation of Verify functionality of all Execute component funct’l
all protection devices gas and fire detection, tests for switchgear,
protection, and breakers, transformers,
and safety interlocks extinguishment systems motor control centers
56 E 61 EML 70 M
Manage Verify manual opening,
Commissioning and Perform energized
closing, sealing, and
Startup spares equipment tests
operation of valves
57 E
Check all rotating
equipment (including
correct rotation)
D. Data/Documentation/ C. Subsystems/Systems/
Audits and Certifications Interconnecting Systems
62 E 71 ML 73 L
Apply and verify Conduct system Verify automation
Pre-Commissioning
check sheets for software functions,
walk-downs with client
Pre-Commissioning prior to Commissioning human-machine interface
63 HS #16 EM 72 ML 74 (35) L
Conduct loop checks “First fill” (e.g., utility Complete pressure
and input/output (I/O) fluids); loading of catalyst, containment/flange integrity
point-to-point checks desiccants, polishers (leak) test (post-hydro test)
64 E 66 EML 75 L
Complete pre-functional Verify completion of req’d
Update as-built data, documentation,
checklists and issue drawing issue turnover for
power-on requests Comm’g certificates
65 EML
Identify and track
Pre-Commissioning
punch list items
17
3. Findings
3. Commissioning Phase
Early Mid Late
76 E 79 EML 91 M 97 L 98 L
Conduct Move team to Review, revise,
Commissioning
Perform site Perform pre-Startup
work-shift and approve Startup
safety audits safety review
A. Planning/Schedule/
Management/Staffing
77 E 80 EML 92 ML
Develop Conduct
Approve initial
Maintenance operator/maintenance
Startup procedures
information and plan training
78 E
Develop O&M Legend
procedure and
training materials Activity Hot Spot Phase
number number Timing
Activity Name
81 E 84 EML 93 M
Mobilize Mobilize Run-in of rotating
Commissioning Startup equipment including
B. Materials/Equipment/
coupled testing of
resources resources A colored background signifies that
rotation equipment
this is a Hot Spot.
Components
83 EM
Run diagnostic checks
on required valves
and instruments
C. Subsystems/Systems/
Interconnecting Systems
87 EML 100 L
Introduce
Place non-process
Commissioning
utilities into operation
materials and fluids
96 ML 103 L 106 L
Gather and complete Issue statement of
Conduct internal fitness for service, with
system turnover pre-Startup audit all assurance sign-offs;
documentation hand over to Operations
104 L
Conduct integrity
verification
(per insurance and/or
regulatory requirements)
18
3. Findings
4. Startup Phase
5. Close-out Phase
Early Mid Late
A. Planning/Schedule/
Activity Name
112 EML
Conduct performance
testing, including
tuning, ramp-up and
reliability testing
121 HS #7 124
Assure correctness and Issue final
completeness of as-built,
commissioned drawings, close-out report
documentation
122
Finalize
documentation,
including revisions
19
3. Findings
With this information in-hand, RT-333 proceeded to determine typical or common RACI
assignments for each of the 124 CCSU activities.
The RACI assignments pertain to four key different roles for each activity in the CCSU
flowchart: Responsible, Accountable, Consulted, and Informed (RACI, collectively).
Responsible individuals are charged with executing and completing the assigned
activity. Accountable individuals (for which there is only one per activity) are charged
with ensuring that the activity is completed to a satisfactory level. Consulted assignments
provide input for execution of the activity, while Informed assignments are essentially
“customers” or recipients of the activity’s end-results.
In order to determine the RACI assignments, the RT-333 members conducted multiple,
in-depth discussions for each of the 124 CCSU activities. In addition, external reviewers
provided additional review and input into the Responsible and Accountable assignments
for four key CCSU roles: Project manager, Construction manager, Commissioning
manager, and Operations manager.
20
Leadership Functions CSU Core Technical Functions
Name
Name
23 3D Model/BIM/Smart P&ID
5 Construction Management
11 Project Director/Executive
3 Engineering Management
13 Mechanical/Machinery
2 Project Management
18 Module Fabricators
19 Automation/DCS
A = Accountable
C = Consulted
16 Electrical
12 Process
14 Piping
I = nformed
15 HVAC
#
#
Project Close-out
117 Conduct Close-out Alignment meeting I RA I I C I C I R I I I I I I I I I I I I I I I I I I I
118 HS #18 Verify closure of HAZOP action items C A R I I C
Verify spares, training, O&M procedures, and planned
Project Close-out
119 A C C R
maintenance routines
Complete facility acceptance and align on any punch list
120 A I I I I C
items remaining
HS #7 Assure correctness & completeness of as-built,
121 A R I R
commissioned drawings and documentation
122 Finalize Documentation, including revisions RA R I I
123 Document and communicate CSU Lessons Learned C RA C C C C R I C C C C C C C C C C C C C C C C C C C C
124 Issue final close-out report C RA C C C C C C C C C I I I I I I I I I I I I I I I I I
Responsible - 4 3 - - - 1 - 1 - - 9 - - - - - - - - - - - - - - - 2 - 2
Subtotals
Accountable - 8 - - - - - - - - - 8 - - - - - - - - - - - - - - - - - 0
Consulted 3 - 2 2 3 2 3 1 4 2 2 24 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 18
Informed 1 - 2 1 1 1 2 5 2 1 1 17 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 34
3. Findings
21
3. Findings
22
The RACI analysis indicated that there are four key roles pertaining to CCSU
transition management: Project manager, Construction manager, Commissioning/
Startup manager, and Operations manager. The distribution of Accountable (A) and
Responsible (R) assignments by phase for these four key roles is presented in Table 2.
While the Commissioning/Startup manager is generally responsible for 40% of the
CCSU activities, the three other key managers (Project, Construction, and Operations)
are collectively responsible for 31% of the activities.
23
3. Findings
24
A R A R A R A R A R A R
Project Manager 15 1 8 1 8 1 1 1 8 4 40 8
Construction Manager 16 13 – 3 – – – – – – 16 16
Commissioning and
10 26 20 4 8 17 1 1 – 1 39 49
Startup Manager
Plant Operations
3 4 – – 12 8 7 2 – 1 22 15
Manager
Totals 44 44 28 8 28 26 9 4 8 6 117 88
3. Findings
The specific Accountable and Responsible activities assigned to these four managers
are presented in Tables 3 through 10.
25
3. Findings
26
3. Findings
27
3. Findings
28
3. Findings
28. Witness, track, and document site acceptance and integration tests
29. Complete and document individual equipment tests (e.g., cold
alignment, megger testing)
33. Perform cleaning, passivation, and drying of piping and ducts
#4
(including steam blowing and pigging)
35. Complete pneumatic or hydro testing of piping (weld integrity)
Construction
(n=16) 36. Monitor systems completion progress
Commissioning N/A
Startup N/A
Close-out N/A
29
3. Findings
Commissioning N/A
Startup N/A
Close-out N/A
30
3. Findings
54. Verify the operation of all protection devices and safety interlocks
#16 63. Conduct loop checks and input/output (I/O) point-to-point checks
Pre-
Commissioning 64. Complete pre-functional checklists and issue power-on requests
(n=20)
65. Identify and track Pre-Commissioning punch list items
67. Conduct vessel/tank inspections
68. Execute component functional tests for switchgear, breakers,
transformers, and motor control centers
69. Verify instrumentation functionality, including diagnostics and
equipment alerts
70. Verify manual opening, closing, sealing, and operation of valves
71. Conduct system Pre-Commissioning walk-downs with client, prior to
Commissioning
72. “First fill” (e.g., utility fluids); loading of catalyst, desiccants, polishers,
and so on
73. Verify automation software functions and human-machine interface
75. Verify completion of required data, documentation, and issue
turnover for Commissioning certificates
31
3. Findings
Startup
108. Monitor CSU key performance indicators
(n=1)
Close-out N/A
32
3. Findings
28. Witness, track, and document site acceptance and integration tests
30. Familiarize Operations personnel with equipment during FAT or on-
#15
site
31. Transition to CSU system-based execution (from area- or discipline-
#3
based)
34. Align on product and system performance requirements
33
3. Findings
Commissioning
95. Complete Commissioning punch list
(n=17)
106. Issue statement of fitness for service, with all assurance sign-offs;
hand over to Operations
Startup
107. Conduct Startup alignment meeting
(n=1)
Close-out
123. Document and communicate CSU lessons learned
(n=1)
34
3. Findings
Close-out N/A
35
3. Findings
106. Issue statement of fitness for service, with all assurance sign-offs;
hand over to Operations
Two separate companion electronic files are available with this publication:
• PDF file: CCSU Activity Flowchart and Hot Spots
• Microsoft Excel file: CCSU RACI Matrix
36
3. Findings
As discussed in the Methodology section, CCSU “hot spots” were sought out to
better understand common challenges, weaknesses, and/or threats pertaining to CCSU
transition efforts. Both RT member opinion and wider industry survey-based opinion were
used to screen the listing down to the 20 seemingly most-problematic CCSU activities.
A summary listing of these and the relative timing of occurrence are shown below in
Table 11. Interestingly, or perhaps even surprisingly, 15 of the 20 (75%) occur during the
Construction phase. This suggests that greater attention and effort are needed during
Construction if Commissioning and Startup are to be successful.
Since the CCSU hot spots represent opportunities for enhanced performance
from more focused planning and execution efforts, a greater understanding of them is
warranted. Accordingly, each of the 20 CCSU hot spots has been described in detail
with the following fields of information:
• Hot spot number, name, description, version number, and number of source
contributors
• Flowchart activity number
• Timing
• Project context and/or example scenario(s)
• Alleged common deficiencies
• Causal factors
• Qualitative impacts and/or threats to success
• Prevention and/or mitigation strategies
• RACI assignments
• CSU critical success factors and indicators of achievement
37
3. Findings
38
3. Findings
Timing
Construction: Early (Activity #14)
Pre-Commissioning: Early (Activity #53)
Causal Factors
• Vendors and SMEs are not sufficiently involved in Commissioning because of cost-
cutting.
• Commissioning is not well understood by most in industry. This lack of understanding
often causes unreasonable time constraints and cost pressures to be imposed on
Commissioning.
• Since Commissioning always occurs at the end of a project, it inherits the leftover
budget, schedule, and execution problems from all previous work.
39
3. Findings
Prevention/Mitigation Strategies
• Allocate appropriate budget for successful commissioning, especially for the timely
inclusion of SMEs and vendors.
• Educate company executives and estimators on the importance of commissioning, as
well as the schedule and budget requirements for successful commissioning.
• Create a fully integrated construction-commissioning schedule with system-based
milestones.
• Development of a vendor/SME plan including a schedule and regular updates.
• If the construction schedule slides, do not reduce the scheduled time for
Commissioning. This will only result in further delay because of rushed Commissioning.
• Identify and involve the Commissioning team in the Design phase, giving them
adequate time to review the scope of commissioning, and plan for staffing accordingly.
• Involve Startup personnel in the pre-Startup safety review.
• Commissioning and Startup personnel should not report to the construction contractor,
but rather to the project manager.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technology [CII 2015]: Asset Data Management/Wireless Instrumentation.
40
3. Findings
RACI Designations
CSU Critical
Indicators of CSF Achievement
Success Factor
1. CSU Value 1.1 CSU manager is on the project organizational chart at the start of
Recognition front end engineering.
3.1 By the end of front end engineering, the CSU budget has been
3. Adequate
derived from knowledge of CSU strategy and scope of work, and if
Funding for CSU
needed CSU resources, not simply a percentage of TIC.
5.1 A CSU manager was assigned at the start of front end engineering
and remained with the project through to initial operations.
5. CSU Leadership
Continuity
5.2 The qualifications and the planned tenure of the CSU manager were
well-defined by early front end engineering.
41
3. Findings
Table 12 maps the links between the 16 commissioning CSFs (shown here with
abbreviated labels, but listed more fully in Appendix D) and the 20 CCSU hot spots.
Three CSFs stand out as key responsive strategies for a large number of hot spots:
• CSF 4: Alignment among Owner PM, Operations, CSU, Engineering,
and Construction
(17 hot spots)
• CSF 9: Detailed CSU Execution Plan
(10 hot spots)
• CSF 11: Definition of CSU Check-sheets, Procedures, and Tools
(10 hot spots).
The row totals in Table 12 indicate that each hot spot can be prevented by or
mitigated with between one and eight CSFs. Thus, hot spots and CSFs do not exist
in isolation of each other.
Tables 13, 14, and 15 identify which specific hot spots would benefit most from these
CSFs. These findings underscore the importance of alignment efforts, effective
execution planning, and accurate, timely CSU check-sheets and procedures in
preventing CCSU hot spots.
42
3. Findings
Table 12. Links between CCSU Hot Spots and CSU Critical Success Factors
7. Systems Engineering
9. Execution Planning
1. Value Recognition
8. Sequence Drivers
#5 Punch List x x x 3
#6 Schedule Recovery x x x x 4
#7 As-built Drawings x 1
#8 Inspection
x x x x 4
Walkthrough
#9 Procure Materials x x x x 4
#10 Utilities x x x x x x x x 8
Total 2 3 6 17 2 4 2 5 10 2 10 7 5 3 4 4 86
43
3. Findings
Table 13. Hot Spots that Benefit from Alignment (CSF #4)
CSF #4: Alignment among Owner PM, Operations, CSU, Engineering, and Construction
(from IR312-2, Achieving Success in the Commissioning and Startup of Capital Projects,
Volume I: Best Practices for Commissioning and Startup)
44
3. Findings
Table 14. Hot Spots that Benefit from an Execution Plan (CSF #9)
45
3. Findings
Table 15. Hot Spots that Benefit from Check-sheets and Procedures (CSF #11)
46
3. Findings
RT-333 analyzed the hot spot impacts, causal factors, and prevention/mitigation
strategies for all 20 hot spots to isolate any for any trends or alignments of opinion.
With respect to the impacts from failed hot spots, the following trends were observed:
• Nineteen hot spot failures (95%) commonly result in CSU schedule delays.
• Sixteen hot spot failures (80%) commonly result in increased CSU cost.
• Seven hot spot failures commonly result in increased health/safety/
environment risk.
• Seven hot spot failures commonly result in increased downtime and/or
decreased production post-startup.
• Seven hot spot failures commonly result in deteriorating relationships
between project delivery organizations.
With respect to hot spot causal factors, the following trends were observed:
• Eleven hot spots (55%) may result from roles and responsibilities that are
either unclear or unbalanced.
• Ten hot spots (50%) may result from a staffing problem, including lack of
sufficient relevant experience.
• Nine hot spots may result from unreasonable time and/or budget constraints
or pressure.
• Eight hot spots may result from lack of alignment between two or more
different parties.
Regarding recommended hot spot prevention and mitigation strategies, the following
trends were observed:
• Thirteen hot spots (65%) require greater alignment efforts (on a variety of
CCSU issues).
• Twelve hot spots (60%) can be prevented or mitigated with one or more of the
innovative commissioning technologies identified and characterized by RT-312.
• Eleven hot spots (55%) require a greater understanding of detailed CCSU
requirements.
• Ten hot spots (50%) require more timely involvement of Operations and/or
Maintenance personnel.
• Nine hot spots require more thorough CCSU documentation.
• Seven hot spots require more effective and/or timely involvement of subject
matter experts (SMEs) and/or original equipment manufacturers (OEMs).
47
3. Findings
Objective
The Heidelberg project was the second offshore project in a design one, build two
project program. The first project, also constructed in the Gulf of Mexico, was the deep-
water Lucius Spar. The benefits from the lessons learned from the Lucius Spar HUC
were leveraged on the subsequent Heidelberg HUC. Many of these lessons learned
were closely associated with the CCSU hot spots identified by RT-333.
Context
48
3. Findings
The challenges on Lucius led to the identification of many lessons learned that
were subsequently applied on Heidelberg. These lessons are outlined here, along with
indications of how they related to six different CCSU hot spots:
49
3. Findings
50
3. Findings
Productivity Program for Fabricators and HUC Personnel (Hot Spots #11, #14,
and #20)
• The Heidelberg project established both onshore and offshore programs.
• Its incentives program involved both cash and prizes – for the entire team,
rather than by trade, thus incentivizing all workers to meet an aggressive
startup goal as a team.
• The program incentivized onshore fabricators to hurry up work, rather than
drawing it out.
• The team understood the goals set for each HUC system and milestone.
• Percent-complete status measures (vs. incentive targets) were displayed
electronically offshore, to incentivize effort and encourage the HUC team.
Table 16 shows how Heidelberg responded to six related CCSU hot spots, including
associated RACI assignments. Note how, especially in the Relevance to Project and
Responsive Actions descriptions, the illustrative case study learnings affirmed many
of RT-333’s hot spot findings.
51
3. Findings
52
Table 16. CCSU Hot Spot Relevance, Responsive Actions, and RACI Assignments on Heidelberg
RACI Assignments
Hot Spot Relevance to Project and Responsive Actions
Responsible, Accountable, Consulted, Informed
Preservation has far-reaching impacts including, but not limited to, CSU success. R Operations Superintendent; OIMs
#2
The effects of not preserving equipment in a dusty fabrication yard on the U.S.
Perform Gulf Coast came at great cost to the CSU phase of a prior similar project, and
preservation A Hook-Up and Commissioning Lead
during the leak testing of piping/valve systems in particular. When the team
through all phases began trying to solve the problem on the Heidelberg Spar project, it learned just Construction Manager; Execution Manager;
and execute how hard it was to write an actionable yet not overly prescriptive preservation Operations Technical Services; HUC
the equipment plan. Operations managed the development with project funds, as they have C
Engineering Support Lead; Materials
preservation plan the long-term incentive in its going well, but it took the whole team’s attention, Coordinators (3x Contractors)
from engineering to fabrication to commissioning, to get it right. The team also
Project Manager; Operations Technical
experienced the pains of over-zealous preservation, including over-greasing and
Services; Hook-up and Commissioning
early replacements. An overly aggressive preservation program can cause just I
Lead; Integrated Planner/Scheduler;
as many problems a hands-off approach can.
Project General Manager;
Walkthroughs were often the source of conflict on a previous similar project,
#8
because fabrication/QA, Commissioning, and Operations generally did not Construction Manager and Execution
Complete participate in mechanical completion walkthroughs together. When the group Manager; Hook-up and Commissioning
collaborative “selling” and the group “buying” do not have to look each other in the eye and R
Lead; Commissioning Manager; Operations
inspection agree on what needs to be complete, the tendency is to over-exaggerate Superintendent; OIMs
walkthrough of tags completion on the selling side, and over-exaggerate incompletion or non-
and systems by the conformance on the buying side. On Heidelberg, the team enforced five-
Commissioning party mandatory walkthroughs, consisting of Engineering, Fabrication, QA,
manager, the Commissioning, and Operations representatives. By making the groups come A Hook-Up and Commissioning Lead
construction together, the Fabrication and QA teams were encouraged to get the work done
contractor, and correctly prior to the walkthrough, rather than doing the minimum amount of work
Operations required to get a system out of their sphere of responsibility. The team also set the Topsides Engineering Lead; QA Team
expectation that systems should be turned over for Pre-Commissioning as soon C
Leads; Commissioning Superintendent
as safely possible, and provided with a Fabrication team dedicated to working
punch-list items in parallel with Pre-Commissioning and at the direction of the
Commissioning manager. Engineering was present to provide judgment on safety
and code-compliance, arbitrating when questions arose on the ability to turn Project Manager; Operations Technical
systems over to Commissioning. Operations was present for general engagement/ I Services; Completions Leads; Contractor
awareness and to weigh in on preference items early, in the interest of addressing Construction Quality Control
them before they could cause any rework for the Commissioning team.
Table 16. CCSU Hot Spot Relevance, Responsive Actions, and RACI Assignments on Heidelberg (continued)
RACI Assignments
Hot Spot Relevance to Project and Responsive Actions
Responsible, Accountable, Consulted, Informed
On the prior similar project, Construction-CSU were not aligned on the execution Construction Manager; Execution
#11
plan, with Construction needing CSU to “take a back seat” while engineering Manager; QA Team Leads; HUC
Conduct R
and fabrication yard problems were corrected, yet with the Commissioning/ Lead; Commissioning Manager; OIMs;
Construction-CSU Operations teams still trying to commission whatever they could, which was not in Operations Team Leads;
alignment meeting the project’s best interest.
on the execution A Hook-up and Commissioning Lead
In contrast, on Heidelberg the team deployed an integrated schedule, formally
plan
starting when construction was ~60% complete in the yard. This established
project-level priorities that all groups were asked to work toward, which led to Topsides Engineering Lead; Operations
quick and clear alignment on the near-, mid-, and long-term goals that everyone C Superintendent; Operations Technical
was working toward. It also allowed the project management team to empower Services
the right people at the right time, to shift resources to meet needs as changes
occurred, and to manage each individual contractor’s desire to complete its
I All functions
scope as efficiently as possible.
Bringing in key Operations & Maintenance personnel early in the project has
#14
both positive and negative impacts, but must be done. Having them on board R Operations Superintendent
Identify and and contributing during the Design phase of a project results in a CSU program
integrate key with fewer last-minute requests and better buy-in. In the case of Heidelberg,
Operations & having Operations on board and responsible for scope during the CSU phase A Hook-Up and Commissioning Lead
Maintenance was critical to the project’s success. The team started with discussions on CSU
personnel and methodology during early yard fabrication, including what it wanted as far as
supporting systems completion management, turnover of systems, and the integration of Commissioning Manager; Completions
organizations commissioning and operations. These discussions resulted in the Commissioning C Leads; Operations Superintendent; OIMs;
team’s ability to build good plans that Operations could buy into the first time Operations Technical Services
around. The team had Operations present for all mechanical completion
walkthroughs, and also had them walk through system Commissioning
procedures with Engineering and Commissioning personnel, to ensure they Construction Manager; Execution Manager;
would be able to consent to the adequacy of the Commissioning procedures and I
Commissioning Superintendent
that, once complete, a system would be ready for startup.
3. Findings
53
3. Findings
54
Table 16. CCSU Hot Spot Relevance, Responsive Actions, and RACI Assignments on Heidelberg (continued)
RACI Assignments
Hot Spot Relevance to Project and Responsive Actions
Responsible, Accountable, Consulted, Informed
Similar to Hot Spot #8, system handover (Commissioning to Operations turnover) Topsides Engineering Lead; Hook-up and
#17
walk-downs were often the source of conflict on the previous similar project R Commissioning Lead; Commissioning
Conduct system because Operations did not want to accept ownership of systems until they were Manager; Operations Superintendent; OIMs;
walk-downs for 100% complete and even augmented to the satisfaction of their preferences.
turnovers On Heidelberg, mandatory three-party walk-downs were enacted, consisting A Project Manager
of Engineering, Commissioning, and Operations. (Engineering was included
as a third party to weigh in on whether supposed non-conformances were true Completions Leads; HUC Engineering
barriers to a safe, operable, and code-compliant startup, or just things that could C
Support Lead
be corrected by a follow-on Construction/Commissioning team post-startup.)
Engineering approval for non-conformances combined with the knowledge Commissioning Superintendent; GOM
that a follow-on team would correct most preference items after startup gave Compliance; Regulatory Affairs; Integrated
I
Operations the confidence that they could take ownership of a system as early as Planner/Scheduler; Completions System
possible, rather than drawing out the process. Administrator
On Heidelberg, many team-building events were held for the Construction, Project Manager; Construction Manager;
#20
Commissioning, and Operations teams. Most often these were informal events, R Execution Manager; Project General
Conduct held jointly to encourage friendship and good relationships between the groups. Manager
Construction-CSU Informal dinners, fight nights (boxing, mixed martial arts), BBQs, cook-offs, and
team building other events were held while the teams were onshore. Once offshore, the teams A Hook-up and Commissioning Lead
were allowed to retire early for holidays, major milestone completions, and
whenever a big sporting event was on. This all went a long way to building the Topsides Engineering Lead; Operations
type of culture where CSU teams were able to work efficiently and boosted the C
Superintendent; OIMs
morale in a situation where the industry was in a down cycle and members of the
team were working themselves out of a job. I
3. Findings
As shown by the performance metrics in Table 17, the HUC performance on Heidelberg
dramatically improved over its predecessor project, Lucius. The differential swings on
both schedule and cost performance are sizeable. While it is difficult to attribute such
success to any specific factor or set of factors, the Heidelberg leadership team feels
strongly that the Heidelberg project team’s proactive treatment of the six hot spots
described in Table 16 contributed significantly to this success.
Project
(HUC timing)
Lucius Heidelberg
Metric (Jan. 2015) (Jan. 2016)
Spar Production
Natural Gas (millions of cubic feet/day) 450 80
Nameplate Capacity
Basis
# of Commissioned Systems
174* 164
(Topsides and Hull)
RT-312 Indicators of
% Attainment 40% 80%
CSF Achievement
Planned (Months) 37 35
Project Schedule
(from Sanction to Actual (Months) 42 32
First Oil)
% Increase or (Decrease) 13.5% (8.6%)
Performance Comparison
Planned (Months) 5 5
HUC Work-hours
(against Lucius % (Decrease) – (58%)
Baseline)
*The 10 additional systems were used to handle the higher natural gas pass-through for Lucius.
55
4
Conclusions and Recommendations
Conclusions
This research has provided answers to the essential question that originally
prompted CII to create RT-333:
• A CCSU RACI matrix for the 124 activities was mapped across 60 common
project organizational functions. While the Commissioning/Startup manager
is generally responsible for 49 of the 124 activities (40%), three other
key managers are generally responsible for 39 activities (31%): Project
manager, Construction manager, and Operations manager. The RACI matrix
developed should be treated as a starting point for in-depth, project-specific
management team discussions.
57
4. Conclusions and Recommendations
• Hot spots provide further insight into the challenges with CCSU transitions.
Hot spots are CCSU activities that generally have unclear responsibility
assignments, recurring problems or deficiencies, or that often fail to deliver
on expectations.
• Twenty CCSU hot spots surfaced from screening efforts by 49 CCSU
managers. Interestingly, three-quarters of the hot spots occur in the
Construction phase, indicating a need for greater oversight or involvement by
the project team at this time.
• Each of the 20 hot spots has been fully characterized in 10 fields of
information, including common impacts, causal factors, and prevention/
mitigation strategies, for which trend analysis has been conducted.
• Hot spots were cross-linked with the 16 commissioning/startup Critical
Success Factors identified previously by RT-312. Analysis of this data
underscores the relevance between the two, and in particular, the importance
of the Alignment, Execution planning, and Check-sheet critical success
factors.
• The Heidelberg Spar illustrative case study was documented to demonstrate
the substantial value that can result from timely and effective treatment of
targeted CCSU hot spots.
Recommendations
• The transitions across Construction, Pre-Commissioning, Commissioning,
Startup, and Close-out require greater management attention than they are
generally given.
• Project teams should rigorously apply the implementation process
recommended in this report, which ties together the various key findings from
CII Research Teams 121, 312, and 333.
• The CII community would benefit from additional documented case studies
focused on applying the tools provided by this research.
• A field-friendly tablet application tool would aid implementation efforts
associated with this study’s findings.
58
Appendix A:
Glossary of Terms and Acronyms
The number in the rightmost column refers to each definition’s source: RT-333 or a
publication listed in the References.
Acceptance Testing done to prove that equipment has the ability to function within
RT-
Testing (AT) specified parameters. Usually performed by manufacturer personnel and
333
witnessed by project personnel.
Testing conducted to determine whether or not a system satisfies its
acceptance criteria and to enable the customer to determine whether or 20
not to accept the system.
As-builts Documents that accurately represent actual installed conditions,
equipment, and systems, such as drawings, computer graphics, equipment
1
data sheets, operation manuals, and maintenance manuals. They also
include the training program and training videotapes.
Asset Data Management of the documentation and data created and collected for the RT-
Management physical asset. Usually by means of an electronic database. 333
The commissioning database is a tool which contains all the data on
each commissioning system. Programmed using a relational database
program (such as MS Access) and residing on a server, the database
provides an itemized listing of the assets that are undergoing checkout and 26
commissioning, tracking of work for equipment assigned to commissioning
systems, and construction completion checklists. Numerous reports are
possible using different queries from the database table.
All the software in the technology stack between the operating system and
the application software, e.g., database management systems, middleware, 17
and application-enabling software.
Brownfield A project being conducted on, or in addition to, an existing physical asset. RT-
Project 333
Cable A check to be sure that low impedance electrical continuity exists between
Continuity two points in an electrical cable. This is a critical step to prevent incorrect RT-
Checks termination, and/or to check for physical damage or poor connections. May 333
also be referred to as “point-to-point” or “ring-out” check/test.
Check-sheets Instructional lists of tasks for the execution of various construction (or RT-
other) activities. 333
A record for documenting manufacturing, installation, and testing of
2
equipment
Close-out Referring to project close-out. The completion of all contractual obligations
by project participants. Complete and final documentation for Engineering, RT-
Construction, Commissioning/Completions, Operations/owner must be 333
included as part of project close-out.
Close-out A report completed upon project close-out by project personnel.
Report RT-
333
59
Appendix A: Glossary of Terms and Acronyms
Commissioning A phase of project execution when tasks, tests, and procedures are
performed to facilitate systems working in tandem for production. Usually
RT-
carried out by a team formed specifically for the purpose. For the
333
differences between the Pre-Commissioning, Commissioning, and Startup
phases, see Appendix B.
Putting into operation (or otherwise making “live” for normal duty) a
plant, equipment, systems, or sections thereof. Adjusting and optimizing
12
operating conditions for attainment of design performance and, where
applicable, stipulated guarantees.
Commissioning is a task directed by the area commissioning team
leader, with assistance from Operations, the contractor, and generally
the equipment manufactures representative. During Commissioning, the
equipment is test operated to assure that it will operate to the design plan.
Commissioning occurs prior to Startup and begins when the contractor(s)
deem the equipment is construction-complete or has agreement with
the Commissioning team leader to pre-commission, and ends when the
equipment is turned over to Operations. The phases of Commissioning
26
include safety, equipment checkout, dry runs, trial runs, and product runs
to the point of being released for initial operations.
Commissioning is complete when the product runs have taken place
and satisfy the product success criteria. Commissioning is a shared
responsibility between the Commissioning team and plant operations.
During Commissioning, a gradual transition occurs, whereby the
Commissioning team begins to function in a support role and the operators
“start to drive.”
The integrated testing of plant systems prior to the introduction of
4
feedstocks.
A well planned, documented, and managed engineering approach to the
startup and turnover of facilities, systems, and equipment to the end-user,
18
that results in a safe and functional environment that meets established
design requirements and stakeholder expectations.
A quality oriented process for verifying and documenting that the
performance of facilities, systems, and assemblies meets defined 21
objectives and criteria.
Group of energized and dynamic tests that constitute verification that
each systems or subsystem is fabricated, installed, cleaned, and tested in 2
accordance with the design and that the systems are ready for startup.
Commissioning A phrase describing the portion of a capital project when disparate RT-
and Startup systems are made to work together as a process to produce some product. 333
(CSU)
Commissioning and startup is the process that occurs at the end of
checkout where the equipment is functioned as a system according to the
project design intent. The control system programs are enabled for full
execution at this time. The final verification of interlocks, permissives, and
sequential operation is performed at this time. Process fluid circulation
26
(flushing) and machine movements are checked during this phase. The
Operations staff also transition into the project at this time and perform
the control actions with the support of the Commissioning team. Transition
to the plant lockout system occurs at this time to coincide with the normal
means of operating the plant and project.
60
Appendix A: Glossary of Terms and Acronyms
Construction Certificates issued upon system completion for a portion of the physical RT-
Completions asset. 333
Certificate
Document indicating that the system is physically complete. 2
Energization Adding a form of energy to a system or systems which will be part of its RT-
normal operation (e.g., electricity and flow of process materials) 333
Facility A final acceptance by the owner of the new physical asset (greenfield)
RT-
Acceptance or changes to an existing physical asset (brownfield) and an
333
acknowledgement that all contractual obligations have been fulfilled.
Factory Equipment acceptance testing done at the factory to demonstrate the
RT-
Acceptance correct operational capability of the equipment. Usually conducted with
333
Tests (FAT) project personnel present.
The partial commissioning and qualification of equipment and/or systems
16
prior to their shipment from the fabricator’s site.
An acceptance test in the supplier’s factory, usually involving the customer. 13
Inspection and static and/or dynamic testing of systems or major system
components to support the qualification of an equipment system 15
conducted and documented at the supplier site.
Feedstock The raw broth, containing particles to be removed, that is placed into
a laboratory or manufacturing appliance, such as a centrifuge or 10
chromatography column.
Raw material to supply or fuel a machine or industrial process. Also known RT-
as “process material.” 333
First The first product produced by the physical asset which can be sold. This
RT-
Commercial event usually marks the end of the Startup phase.
333
Product (FCP)
First Test The first product produced by the physical asset for testing. Usually RT-
Product produced during the Startup phase. 333
Greenfield A project being conducted to develop a new physical asset. RT-
Project 333
Handover Internal transfer of area/module or system assets between functional
2
groups within the project organization.
HAZOP Hazard and operability study – A study completed to identify risks to the
RT-
safety of personnel and equipment conducted by a team of experts familiar
333
with the project prior to project execution.
Technique for identification of potential hazards and operability problems. 12
Hazards and operability study – A method used to evaluate potential
hazards associated with the operation and maintenance of equipment and 4
systems.
Human- The electronic human interface for a controls system. RT-
Machine 333
Interface (HMI)
The HMI may comprise a number of switches, push buttons, and indication
lamps, or increasingly text displays and cathode ray tubes (CRTs) or liquid 10
crystal displays (LCDs).
61
Appendix A: Glossary of Terms and Acronyms
Loop Check A check of an individual portion of the controls system. Usually one of the RT-
last activities completed before the Commissioning phase. 333
Testing in which control system inputs and outputs are exercised and their
23
functionality verified.
Mechanical Attainment of readiness for commissioning of plant, equipment, systems
Completion or sections thereof, in which case all pre-commissioning activities are
(MC) included. In some instances, however, these terms may exclude pre-
12
commissioning, thus denoting completion to the extent of stipulated
mechanical tests having been satisfactorily fulfilled; pre-commissioning
then follows.
[Mechanical] construction completion is the point where the construction of
the commissioning system is complete or nearly complete and the control
of the equipment passes from the construction group to the commissioning
team. The completion of the equipment installation may include a Quality 26
Assurance/Quality Control (QA/QC) check by the construction contractors
but does not include a thorough checkout of the equipment and support
systems.
The point in a project at which all equipment and materials have been
10
installed but not commissioned (started-up).
Milestone point in time when tagged items and equipment within a
system is installed in accordance with all drawings specifications, and
2
documented in accordance with the inspection test plans and is ready for
pre-commissioning.
Modeling/ Optimization: The process of taking a facility from the point of where it
optimizers is able to run and perfecting, or “fine tuning,” each area to enhance the 26
operational ability of the mill.
Optimization: Modifying a program to improve performance; e.g., to make
28
it run faster or to make it use fewer resources.
Modeling: Construction of programs used to model the effects of a
postulated environment for investigating the dimensions of a problem for 28
the effects of algorithmic processes on responsive targets.
Modules Portions of the final physical asset not constructed in-place, but
RT-
constructed elsewhere and transported to the physical asset location and
333
tied-in.
A major section of a plant resulting from a series of remote assembly
operations and may include portions of many systems; usually the largest 10
transportable unit or component of a facility.
A container which can be transported by truck or railway and which is
equipped with the equipment necessary to perform the operation for which 10
it is designed.
A packaged functional hardware unit suitable for use with other
28
components.
Non- A report created to describe a quality issue with a specific part of the
RT-
Conformance physical asset, usually by project quality assurance personnel.
333
Report (NCR)
Non-process Fluids introduced to system(s) which are not included in the end-product, RT-
Fluids rather serve an ancillary purpose (e.g., lubricants). 333
62
Appendix A: Glossary of Terms and Acronyms
Non-process Utility systems that are not directly supporting processing, rather serve an RT-
Utilities ancillary purpose. 333
Operations A disciplined, systematic, documented, performance-based examination
Readiness of facilities, equipment, personnel, procedures, and management control
27
Review systems to ensure that a facility will be operated safely within its approved
safety envelope as defined by the facility safety basis.
Original The manufacturer/maker of a piece of equipment or subsystem. Not a
Equipment distributor. RT-
Manufacturer 333
(OEM)
Physical Asset The physical installation (e.g., plant, pipeline, spar, and factory) being RT-
constructed and commissioned for the purpose of production. 333
Pre- A phase of project execution when tasks preparatory to commissioning
Commissioning are completed on systems to ensure their readiness for commissioning.
RT-
Usually carried out by the construction contractor. For the differences
333
between the Pre-Commissioning, Commissioning, and Startup phases,
see the Appendix B.
Preparation, functional testing and making ready for commissioning
plant, equipment, systems or sections thereof suitably completed and 12
mechanically tested – for example, nitrogen purging; line-vessel cleaning.
Component-level testing of systems. Sometimes referred to as “pre-
commissioning,” “cold commissioning,” “construction completion,” or 4
“pre-op.”
Preparing the plant for commissioning (startup). This includes briefly
starting (bumping) all pieces of equipment, verifying their shaft rotation
is correct, verifying that valves, gauges, and other inline devices are 10
installed in the correct orientation, and performing functionality runs on all
equipment and material. This also includes leak tests.
Group of energized and static tests that constitute verification that the
equipment or component is fabricated, installed, cleaned and tested in 2
accordance with the design and ready for commissioning.
Preservation Deliberate protection of equipment and materials prior to initial operations
RT-
(when regular maintenance is occurring) from any degrading conditions
333
(e.g., moisture, high/low temperature, and rough handling).
Pre-Startup A review of systems prior to Startup focused on safety, and particularly
Safety Review focused on identifying any safety hazards in order to eliminate them RT-
(PSSR) prior to startup of systems. It is an element of OSHA’s Process Safety 333
Management regulations.
Process A manufacturing, cleaning, packaging, or distribution operation which may
10
be made up of a series of steps or stages.
A set of interrelated or interacting activities which transform inputs into
13
outputs.
63
Appendix A: Glossary of Terms and Acronyms
Punch List A list of outstanding work tasks, which are sometimes required to be RT-
completed before turnover can occur. 333
A list of action items developed near the end of a project that must be
completed prior to the constructor turning over a project to the owner.
4
Critical punch-list items must be completed before the unit may be started.
Non-critical punch-list items can be completed post-Startup.
The punch list is a mechanism to identify design and/or construction
changes. The punch list differs from the problem log in that the items
on it may be safety enhancements not included in the original design,
embellishments that are discretionary in nature or project scope changes.
Any item is “fair game” to be added to the punch list but additional cost 26
is usually incurred for punch list items. Therefore, an item-by item review
is necessary to avoid “scope creep.” Punch list review meetings can be
lively and contentious, therefore, the punch list is usually managed by the
construction manager or the person who “holds the purse strings.”
List detailing incomplete construction related items. 22
RACI Matrix A tool for assigning roles and responsibilities for activities on a project.
The acronym RACI stands for Responsible, Accountable, Consulted, and 11
Informed.
Run-in A test conducted on coupled rotating equipment with no load. RT-
333
Safety-critical Systems critical to the safety of personnel from construction through RT-
Systems operations (e.g., fire detection and fire suppression). 333
Site Equipment testing performed at owner site (with the vendor and owner
Acceptance present), which demonstrates and documents that the factory acceptance
RT-
Testing (SAT) testing punch list items have been resolved, and that equipment, systems,
333
or modules comply with owner specifications, prior to further testing. Also
known as an integration test.
An acceptance test at the customer’s site, usually involving the customer. 13
Inspection and/or dynamic testing of the systems or major system
components to support the qualification of an equipment system 15
conducted and documented at the manufacturing [job] site.
Skid Modules made to contain systems or parts of systems, which are
RT-
constrained to particular physical dimensions for ease-of-transport (e.g.,
333
the size of a semi-truck trailer or standard shipping container).
An assembly of individual pieces or stages of equipment, complete with
inter-connecting piping and connections for external piping. The assembly 10
may be mounted on a skid or other structure prior to delivery.
Skid-mounted equipment is generally an independent piece of
equipment designed for a specific processing step in the production of
10
a pharmaceutical product. Examples include equipment units such as a
compressor station or a refrigeration unit.
64
Appendix A: Glossary of Terms and Acronyms
65
Appendix A: Glossary of Terms and Acronyms
System The documentation showing that a given system has been tested and
RT-
Certification shown to function properly within its parameters. Depending on the system,
333
these may or may not be issued by governing agencies.
The process through which a system, subsystem, or piece of equipment
2
has been installed, tested, and certified as ready to be put in service.
Systems Completion of the construction of individual systems with discrete
RT-
Completion beginning and ending points within the physical asset. Systems completion
333
is often tracked to determine progress towards Mechanical Completion.
The process through which the technical integrity and design of a newly
built facility is verified and the new facility is turned over from the project to 2
asset owner or from contractor to owner.
Tie-in A connection between an existing system and a new system. RT-
333
Transfer of A formal process to transfer the care (maintenance), custody (ownership)
RT-
Custody and control (operational responsibility) of an asset or system from one
333
party to another.
Turnover The act of turning over the physical asset (in part or whole) to another
party. Usually made official by signatures of both the transferring party and RT-
the receiving party, and only with their consent. Turnover packages are 333
generally transferred upon turnover.
Turnover is the distinct point in time when the primary responsibility
or “ownership” of a commissioning system changes. The main turnover
transitions are:
26
1. From the contractor to the commissioning team
2. From the commissioning team to the operations team
The jurisdictional transfer of control over specified components/systems
from one organization to another for the purposes of care, custody, and 4
control.
Also known as “hand over” in the U.K. A formal transfer of custody for a
18
system or unit to another group, department, or operating company.
Turnover A compilation of documents accompanying the turnover of a part of
RT-
Package the facility from one party to another. Usually comprises drawings,
333
certifications, manuals, and so on.
A collection of pertinent design, construction, vendor, and operational
documentation. This collection of documentation is used for the
qualification and process validation activity, as well as reference and single 19
source information for the life of any particular system, process, or piece of
equipment.
The required documentation to define that a system has been built,
2
installed, tested and is ready to be placed into operation.
Turnover to The sequential turnover of the physical asset from the construction team to RT-
Commissioning the commissioning team for commissioning. 333
(TC)
Minor milestone in project when pre-commissioning activities for a
discipline (or collection of systems) are essentially complete and ready to 2
commence commissioning.
66
Appendix A: Glossary of Terms and Acronyms
Turnover to The sequential turnover of the physical asset from the commissioning team RT-
Startup (TS) to the operations team for Startup. 333
Signifies that a system’s construction, pre-commissioning and
commissioning work are complete and the required safety verification is 2
ready to commence startup.
Walk-down A collaborative, multi-party inspection and review of a system to determine
RT-
readiness prior to turnover. Participants should include the commissioning
333
manager, construction contractor, and an operations representative.
Walkthrough See “walk-down” RT-
333
Work Shift Project leadership labor planning efforts to accommodate more than one RT-
Management work shift. 333
67
Appendix B:
Scopes of Pre-Commissioning vs. Commissioning vs. Startup
Pre-Commissioning
Commissioning Startup
(a.k.a. “Static Commissioning”)
Component Level Multi-component Integration and System Level System Level
• Activities are typically post-mechanical • All construction is complete and verified • First introduction of feedstocks,
completion (at component level) but prior to prior to initiation of commissioning (but post- produced fluids, and media
energization and introduction of any feed stocks construction) • All tests that indicate that the entire
• Activities may or may not be the responsibility of • Energization of equipment starts the production system is working as
the construction contractor commissioning process intended with respect to regulatory
Scope Description
• Concludes with a ready-for-commissioning • Actions immediately prior to Startup requirements, safety, operability,
certificate for each system product production rate, quality of
• Concludes with a “ready-for-startup” or product, environmental performance,
• Rotating equipment: bump for, rotation “pre-startup safety review” certificate for the integration with prior/existing systems,
guards, installed, rotation check, motor bumps, entire unit and/or for each system systems performance (i.e., response
alignment checks, and uncoupled checks time, energy consumption), testing the
• Typically concludes with “ready for shutdown of systems, and so on.
commissioning” certificate or completed • First test product is produced and
check sheets available for property/characteristics
testing
• Operator readiness may be tested on a
test run
69
Appendix B: Scopes of Pre-Commissioning vs. Commissioning vs. Startup
70
Pre-Commissioning
Commissioning Startup
(a.k.a. “Static Commissioning”)
Component Level Multi-component Integration and System Level System Level
1. Line-vessel cleaning; Initial leak checks; Non- 1. All energized and/or dynamic tests that 1. Initial manual operation of whole
operating checks, inspections, testing, cleaning, constitute verification that each system or facility/system, by loop prior to going to
flushing, blowing, drying, adjusting; Cold subsystem is fabricated, installed, cleaned, and automatic
aligning of equipment, piping, instrumentation, tested in accordance with design intentions, and
2. Transfer from manual loop control to
electrical systems, cold alignment checks, that systems are ready for startup
auto control by loop or by sub-system
spring hanger settings, and some equipment
2. Chemical cleaning and steam blowing
tests (all items documented on construction and 3. Purging of temporary fluids
pre-commissioning check sheets). 3. Final leak checking and air freeing; Leak and
4. Start and verify analyzer/process
tightness testing
2. Mechanical equipment, wiring checks for analytics functionality and operability
installation accuracy; point-to-point continuity 4. “First fill” (e.g., lubricants, utility fluids); loading
5. Start and integrate any additional items/
checks of catalyst, desiccants, polishers, and so on.
systems beyond the base system
3. Mechanical function tests 5. Checkout of control systems and emergency
6. Turn on modeling/optimizers, such as
shutdown systems; testing of all safety function
4. Construction rework, as required loop tuning or batching recipe controls
Key Inclusions
systems
5. All verification tests to ensure equipment is 7. Test and validate controls at design
6. Rotating equipment run-in; coupled testing of
fabricated, installed, cleaned, and tested in capacity or any other lesser desired
rotation equipment
accordance with the design capacity level
7. Circulation with temporary fluids
6. All tests and inspections required prior to any 8. Any ramp-up step and tests
dynamic testing 8. Testing of utilities
9. Conduct validation of product quality
7. Function checks accomplished with discipline- 9. Interlocks functional tests (such as microbe tests, and metallurgy
specific check sheets tests)
10. Testing of control functions and replacement of
8. Power-off checks of equipment, piping, and temporary components
electrical cable 11. Overall system commissioning (whole)
9. Non-operating adjustments performed before 12. Running proper diagnostic checks on all
system turnover valves, transmitters, pumps, and so on, using
10. Initial required calibrations functionality test templates.
11. All loop checks 13. Purging of fluids
12. Preservation 14. Additional required calibrations or re-calibration
(e.g., safety valves and instruments).
13. All static/non-energized checks completed
Appendix C
Hot Spot Characterizations
Timing
Construction: Early (Activity #14)
Pre-Commissioning: Early (Activity #53)
71
Appendix C: Hot Spot Characterizations
Causal Factors
• Vendors and SMEs are not sufficiently involved in commissioning because of cost-
cutting.
• Commissioning is not well understood by most in industry. This lack of understanding
often causes unreasonable time constraints and cost pressures to be imposed on
commissioning.
• Since commissioning always occurs at the end of a project, it inherits the leftover
budget, schedule, and execution problems from all previous work.
• Commissioning is not treated as a stand-alone discipline, and thus gets subordinated
to construction.
• Startup personnel are often brought in from other facilities because of staffing
constraints.
• Extreme winter working conditions and remote job sites can make it difficult to mobilize
resources (human and other).
Prevention/Mitigation Strategies
• Allocate appropriate budget for successful commissioning, especially for the timely
inclusion of SMEs and vendors.
• Educate company executives and estimators on the importance of commissioning, as
well as the schedule and budget requirements for successful commissioning.
• Create a fully integrated construction-commissioning schedule with system-based
milestones.
• Development of a vendor/SME plan including a schedule and regular updates.
• If the construction schedule slides, do not reduce the scheduled time for
Commissioning. This will only result in further delay because of rushed Commissioning.
• Identify and involve the Commissioning team in the Design phase, giving them
adequate time to review the scope of Commissioning, and plan for staffing accordingly.
• Involve Startup personnel in the pre-Startup safety review.
• Commissioning and Startup personnel should not report to the construction contractor,
but rather to the project manager.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technology [CII 2015]: Asset Data Management/Wireless Instrumentation.
72
Appendix C: Hot Spot Characterizations
RACI Designations
CSU Critical
Indicators of CSF Achievement
Success Factor
1. CSU Value 1.1 CSU manager is on the project organizational chart at the start of
Recognition front end engineering.
3.1 By the end of front end engineering, the CSU budget has been
3. Adequate
derived from knowledge of CSU strategy and scope of work, and if
Funding for CSU
needed CSU resources, not simply a percentage of TIC.
5.1 A CSU manager was assigned at the start of front end engineering
and remained with the project through to initial operations.
5. CSU Leadership
Continuity
5.2 The qualifications and the planned tenure of the CSU manager were
well-defined by early front end engineering.
73
Appendix C: Hot Spot Characterizations
Execute Preservation
Perform preservation through all phases and execute the equipment preservation plan
Timing
Construction: Early (Activity #15)
Pre-Commissioning: Early (Activity #60)
Commissioning: Early (Activity #85)
Causal Factors
• No preservation/preventive maintenance leader has been assigned.
• It is unclear who is responsible for executing the preservation plan.
• Preservation is difficult to do right because of inadequate resources to properly track
and maintain equipment/materials.
• Preservation occurs too late or is overlooked completely because it is not an immediate
priority.
• There is a lack of alignment on the importance of preservation at the management level.
• Preservation does not receive enough attention during contracting and project planning.
• Construction contractors are relied upon to perform preservation with little oversight.
74
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Ensure that contract documents specify preservation requirements, so that
preservation can be contractually set up for success.
• Develop a project-specific preservation plan as part of project planning.
• Assign a preservation leader/coordinator with a dedicated mixed-trade crew before
construction begins.
• Consider having Operations personnel perform preservation; this will allow them to
familiarize themselves with the equipment before installation.
• Store equipment properly both on- and off-site. Maintain preservation standards
meticulously through startup.
• Plan for staffing-up early to have enough plant operations personnel on site to help
perform preservation tasks.
• Set up an electronic/data framework for tracking equipment/material location, for
recording preservation requirements and actions, and for tracking preservation
schedule milestones.
• Educate managers on the importance of preservation, as well as the schedule and
budget requirements for successful preservation.
• Work with vendors to identify any equipment for which proper preservation has not
been performed.
RACI Designations
75
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
1. CSU Value 1.1 CSU manager is on the project organizational chart at the start of
Recognition front end engineering.
3.1 By the end of front end engineering, the CSU budget has been
3. Adequate
derived from knowledge of CSU strategy and scope of work, and if
Funding for CSU
needed CSU resources, not simply a percentage of TIC.
76
Appendix C: Hot Spot Characterizations
System-based Execution
Transition to CSU system-based execution (from area- or discipline-based)
Flowchart Activity # 31
Timing
Construction: Mid
77
Appendix C: Hot Spot Characterizations
Causal Factors
• There is a major lack of alignment between Construction management and
Commissioning management. The importance of this transition to project success is
often not understood by Construction managers.
• Prior to the point of transition, the Commissioning manager must be the one to decide
which systems have work priority. This sudden transition of decision-making power
can cause problems. The Construction manager still has ultimate authority (turnover
has not yet occurred),. and he or she may be unwilling to listen to the Commissioning
manager.
• Projects are not resource-loaded for commissioning early on, and the required order
for commissioning is not known until long after the start of construction.
• No C-CSU transition plan was ever created.
• The C-CSU transition plan was poorly done, with ill-defined points of transition.
• Too many exceptions to the transition plan are granted in order to progress the work;
which leads to issues and mistakes later.
• Instead of focusing on driving the transition, leadership is focused either on bulk
construction or systems commissioning: not on bridging the transition gap.
Prevention/Mitigation Strategies
• Develop a transition plan as part of project planning. Consider the critical path for
systems needed for Pre-Commissioning, Commissioning, and Startup. Also consider
physical space requirements and be sure that information from the design team is
readily available at the time of transition.
• Have a resource-loaded commissioning-driven schedule. Define system boundaries
and the order of system completion/turnover early during project planning and include
it in the request for proposals (RFPs) and the contract with the construction contractor.
• Align Construction management and Commissioning management early (shortly after
the contract has been signed) on the importance of the transition to system-based
execution. Align on what triggers the transition to system-based execution. Get buy-
in from field construction supervision (superintendents/foremen) on systems-based
completion.
78
Appendix C: Hot Spot Characterizations
RACI Designations
79
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality, and
HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
80
Appendix C: Hot Spot Characterizations
Flowchart Activity # 33
Timing
Construction: Mid
Causal Factors
• There is a lack of Systems thinking during FEED, which makes it impossible to clean
flow lines as scheduled. The required utilities may not yet be online, or systems may
not yet be ready for pressurization.
• Specifications for cleaning, drying, passivation, and so on are not clearly defined in a
timely manner.
• EPC contractors often do not have the expertise to perform cleaning and other such
tasks, and are sometimes unwilling to hire specialty contractors.
• The construction environment is not well-suited to the meticulous nature of proper flow
line cleaning, drying, and so on.
• Construction contractor personnel often do not have a good understanding of the
effects when system cleaning is not done properly.
• Time constraints (especially on plant turnarounds) are tight and result in heavy
pressure from upper management to get the plant operational.
• Construction schedule is often delayed, pushing cleaning activities until the very end,
prior to system turnover; the resultant schedule pressure diverts focus from cleaning.
• There can be a fundamental incompatibility between CSU schedule pressure and the
experience level of available CSU staff; especially at remote project locations.
81
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Define cleaning, drying, and other specifications clearly for EPC contractors. Make
the specifications/instruction easy to find, read, and use. One example being a piping-
class flushing matrix.
• Hire a specialty contractor to perform flow line cleaning, passivation, preservation
and drying. Allow the specialty contractor to suggest the correct method to meet the
specification for approval by the client.
• If there are problems during cleaning/drying, admit that problems have occurred, and
consider repeating those activities properly.
• Stress systems-thinking during FEED, all the way through startup. Ensure that the
necessary utilities will be online and available for use in cleaning, drying, and so on.
• Create detailed engineered plans supportive of cleaning and drying to eliminate
ambiguity and short cuts; for example, calculate the flushing flow rate needed instead
of using just a velocity requirement.
• Use side-stream filtration for normal equipment. Note this will need the control and
safety systems to be functional.
• Define the collection and disposal of chemical effluents in accordance with
environmental authorities and regulations.
• Isolate instrumentation during cleaning, passivation, and drying. This will prevent
damage to the instrumentation.
• Use QA/QC personnel to witness cleaning and drying activities performed by the
construction contractor.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technology [CII 2015]: Completion Management Systems.
82
Appendix C: Hot Spot Characterizations
RACI Designations
Responsible: Piping
CSU Critical
Indicators of CSF Achievement
Success Factor
7. CSU System
7.1 Formal CSU design review has occurred by the end of front end
Engineering
engineering.
during FEED
83
Appendix C: Hot Spot Characterizations
Punch List
Identify and communicate Construction punch list items critical for
Pre-Commissioning, Commissioning, and Startup
Flowchart Activity # 47
Timing
Construction: Late
Causal Factors
• Projects are often behind schedule by the time the punch list is created and there is a
rush to begin Commissioning/Startup.
• The construction contractor may not have the expertise or proper support to install
some complex systems (e.g., instrumentation, electrical, and/or controls).
• Commissioning and Operations teams have different priorities and perspectives, which
can cause them to have different ideas about which items are critical.
• Some critical punch list items may be missed at first, and then found later. Items may
also get kicked back to the contractor, because the work was not up to specification.
This back-and-forth can draw out the process and take a long time.
84
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Clearly define the scope of the project up-front, in order to avoid loading punch lists
with work items that are outside the project scope.
• Implement a punch-list procedure that is signed-off by all parties.
• Consider that Operations personnel may work with the as-built plant for many years,
with little or no opportunity for making changes. Involve Operations personnel in the
design to help identify these items long before punch lists are created.
• Assign QA/QC personnel, who do not report to the construction contractor, to identify
issues to be resolved before the punch list is created.
• Perform a thorough joint walk-through where all punch list items are identified. Then, in
a separate meeting with Commissioning and Operations, identify by common consent
which ones are actually critical.
• Align Commissioning and Operations teams on the punch list framework and on which
systems are critical for Pre-Commissioning, Commissioning, and Startup before
construction begins. Hold joint problem-solving meetings to resolve disagreements
on critical items among Construction, Commissioning, and Operations teams. When
deciding on critical versus non-critical punch-list items, conduct compromise sessions
with involved stakeholders, to come to an agreement on which items must be
completed before Startup.
• Utilize a change management system.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technology [CII 2015]: Completion Management System.
85
Appendix C: Hot Spot Characterizations
RACI Designations
16. Collaborative
Approach to 16.1 Joint meetings, involving both CM and CSU managers, were
Construction-CSU conducted starting around 50-percent construction complete.
Turnover
86
Appendix C: Hot Spot Characterizations
Schedule Recovery
Plan for and manage CSU schedule recovery
Flowchart Activity # 27
Timing
Construction: Mid
Causal Factors
• Possible causes of a need for schedule recovery include weather impacts, low labor
productivity, inexperienced craftsmen, badly managed work fronts, disagreements on
quality standards, and not including enough float in construction schedules.
• In a hot market or in a remote location, it can be difficult to get enough experienced
craftsmen. Staff turnover can be an issue as local jobs compete for the best
craftspeople.
• Systems are delivered to the Commissioning team out of order, not following the
priority schedule. Construction teams will sometimes front-end load work in order to
provide better cash flow, or for other reasons.
• Construction contractors may not have planned for schedule recovery; for example,
by including float in their schedule estimates. Usually they give completion dates
according to their staffing plans. It is difficult to have confidence in those dates.
• When construction runs behind schedule, turnover packages are delivered to the
Commissioning team late and in an incorrect order.
• The reasons why packages are late do not always get tracked or understood, so CSU
recovery tactics cannot be planned accordingly.
• Equipment failure during Commissioning can impact commissioning sequence and
may require schedule adjustment
87
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Conduct a schedule risk assessment that identifies where the schedule risk is greatest.
• Assist the construction team in delivering systems in the prescribed order to the
commissioning team, even if some are late.
• Use a critical path approach to construction work, according to the CSU test matrix
schedule.
• Actively track construction issues and plan for appropriate CSU recovery tactics.
• Use and review schedule performance metrics for work and contracts.
• Adjust manpower/shift timing to increase the rate of completion.
• Contractually ensure that adequate float is included in the schedule and that it covers
project risks.
• Align on quality standards, code interpretation, and specifications up front.
• Make sure Construction understands system scoping and priority.
• Conduct early and thorough QA/QC of installed systems, with consideration of the
functional specification.
• Provide for named individuals in key positions in project contracts.
• Utilize a change management system.
RACI Designations
88
Appendix C: Hot Spot Characterizations
13. Integrated
13.1 Project schedule included system logic interdependencies and
Construction/CSU
turnover milestones prior to 30-percent construction complete.
Schedule
89
Appendix C: Hot Spot Characterizations
As-built Drawings
Assure correctness and completeness of as-built, commissioned drawings and
documentation
Timing
Project Close-out
Causal Factors
• There are gaps in the formal process for managing as-built drawings during Execution
phases. This results in version control issues and, ultimately, in incomplete as-built
drawings.
• There is often a lack of designated drawing ownership and responsibility for updating
as-built drawings and data.
• Projects personnel are more focused on the physical asset; there is a lack of
appreciation for accurate data.
• As the end of the project nears, personnel from each team start to leave as they begin
demobilization.
• The impetus for completing as-built drawings is low, since their impact will come after
most Construction and Commissioning personnel have left the project.
• There often is an incorrect assumption that drawings are accurate.
90
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Require accurate as-built drawings as part of the final turn-over package.
• Train Operations personnel on maintaining the as-built drawings that are provided to
them by the Commissioning team.
• Contractually require a final check of the physical asset against as-built drawings.
Expend the resources to ensure compliance.
• Contractually require progress as-built drawings and documentation through the
Construction phase and link this to approval of monthly requests for payment. The
owner must have quality control personnel available to verify the accuracy of the as-
built drawings and documentation.
• Perform a meticulous walk-down to check the physical asset against as-built drawings
before the final turnover of care, custody, and control.
• Keep paperwork processes as simple as possible.
• Ensure the participation of qualified QA/QC personnel.
• Have documentation control.
• Do training on record-keeping. Some documentation personnel come from
Construction and do not have a culture of good record-keeping.
• Make one or two people accountable for the whole system. When everyone is in
charge, no one is.
• Ensure prioritization and resources for accurate drawing updates at close-out. Assign
responsibility and accountability for this to individuals and follow up on their delivery.
91
Appendix C: Hot Spot Characterizations
RACI Designations
CSU Critical
Indicators of CSF Achievement
Success Factor
14.1 A master set of asset drawings was readily available and document
control procedures were effective, from construction through final facility
turnover.
14. Accurate
14.2 An asset information plan has been defined, reviewed, and approved by
As-built
the end of detailed design.
Information
14.3 A detailed as-built plan has been defined, reviewed, and approved
by the end of detailed design, and was referenced within the project
execution plan.
92
Appendix C: Hot Spot Characterizations
Inspection Walkthrough
Complete collaborative inspection walkthrough of tags and systems by the
commissioning manager, the construction contractor, and Operations
Flowchart Activity # 45
Timing
Construction: Late
Causal Factors
• Inspection walkthroughs of tags and systems at mechanical completion are often
not well defined contractually. The scope of these inspections is often unclear to
construction contractors.
• Mechanical completion is often not well defined contractually. The specifics of what
constitutes a complete system are often understood differently by different parties.
• Some construction contractors tend to push mechanical completion inspection
walkthroughs too early. The walkthroughs occur prior to all mechanical completion,
which generates punch-listing of a significant amount of incomplete work. Too many
obvious punch list items then distract from lesser items, which get missed.
• If QA/QC personnel report to Construction management, they will have a conflict of
interest in qualifying systems that are still deficient.
93
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Clearly define mechanical completion and the level of inspection for each system in
contract documents.
• Conduct alignment meetings between the parties who will be present at inspection
walkthroughs on the definition of what is agreed to in project contracts.
• Clearly define system limits during detailed design so there is no ambiguity about in
which system a particular component is included.
• Identify a responsible party to assist in the pre-mechanical completion walkthrough
that understands the commissioning prerequisites (e.g., commissioning manager,
construction quality assurance)
• Ensure that QA/QC of construction work is done by personnel who do not have a
conflict of interest.
• Set up a methodology to walk down systems, but only with the disciplines that are
needed for each system.
• Ensure labeling and tagging requirements are correct and included in the project
specifications package.
• Make sure to have proper documentation and signatures on the walk-down forms
(everything should be recorded so that decisions are not lost).
• Try to keep walkthroughs simple, with key people from the necessary disciplines. Too
many people will complicate the process.
• Utilize a change management system.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technology [CII 2015]: Completion Management System.
94
Appendix C: Hot Spot Characterizations
RACI Designations
CSU Critical
Indicators of CSF Achievement
Success Factor
6. System Milestone
6.1 System acceptance criteria were incorporated into the contract with
Acceptance Criteria
the execution contractor.
and Deliverables
16. Collaborative
Approach to 16.1 Joint meetings, involving both CM and CSU managers, were
Construction-CSU conducted starting around 50-percent construction complete.
Turnover
95
Appendix C: Hot Spot Characterizations
Procure Materials
Procure CSU materials, including spare parts
Flowchart Activity # 13
Timing
Construction: Early
Causal Factors
• Materials are ordered too late and do not arrive on site until after they are needed.
• Some materials, including spare parts, are not recognized as having long lead-time.
• Spare parts and temporary spools are overlooked or under-estimated during
procurement planning.
96
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Ensure proper and timely procurement of commissioning materials and spares,
especially those needed for pre-commissioning.
• Appoint one or more Commissioning personnel to work with procurement management
early in construction.
• Ensure that there is a procedure for having timely fabrication of temporary spools for
CSU.
• Purchase spare parts separately from the equipment in an itemized order, so that it is
clear what spare parts will be available. Bill spare parts to commissioning and original
equipment to construction.
• Conduct a detailed analysis of how long parts will last, and how likely it is that they will
need to be replaced during Commissioning. Use this as a risk analysis of spares and
make purchases accordingly.
RACI Designations
Consulted: CSU Planning, Progress Tracking, and Schedule Control; CSU Cost
Estimation and Controls; Procurement Expediting; Materials Receipt and
Verification; Warehouse and Storage Management
Informed: Preservation
97
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
3.1 By the end of front end engineering, the CSU budget has been
3. Adequate
derived from knowledge of CSU strategy and scope of work, and if
Funding for CSU
needed CSU resources, not simply a percentage of TIC.
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
13. Integrated
13.1 Project schedule included system logic interdependencies and
Construction/CSU
turnover milestones prior to 30-percent construction complete.
Schedule
98
Appendix C: Hot Spot Characterizations
Utilities
Confirm availability of utilities needed for Pre-Commissioning and
Commissioning
Flowchart Activity # 32
Timing
Construction: Mid
Causal Factors
• Vendor documentation/O&M manuals do not readily provide information on equipment/
system utility needs.
• Construction schedules are made to make construction more efficient, but not
necessarily to deliver systems in the necessary order.
• The CSU execution plan and integrated Construction-CSU schedule may not consider
utility needs for Pre-Commissioning/Commissioning.
• The contractor may not construct in the correct order to be able to deliver the utilities
systems first.
• There is a lack of handoff of utilities to Operations after CSU, lack of handoff to plant
HSE, and lack of recognition of simultaneous Operations and Construction activities.
• The pre-commissioning scope of work is not well defined, or is not defined at all. The
needs for utilities during pre-commissioning may be unknown by the construction team.
• There is a lack of systems-thinking from FEED onward on projects.
99
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Align on the pre-commissioning scope of work early in the project and include it in
contract documents.
• Develop a commissioning and startup matrix that includes the utilities and temporary
systems needed for CSU.
• Transition to systems-based completion at the appropriate time, and focus first on
systems that are required for safety/utilities/control.
• Construction scheduling should consider the critical path for commissioning activities,
including having the right utility supports in-place.
• Require vendors/OEMs to provide detailed information on the utility needs of their
equipment/materials.
• Require direct and periodic contact/communication with respective utility providers to
confirm utilities service interface requirements, inspection schedule, and connection
schedule.
• Include milestones for completion of utility systems and coordination with utility
companies in the detailed CSU execution plan.
• Require HSE/LOTO to sign-off on systems before they are energized.
• Make contingency plans (and budgets) for when a utility might not be available on time.
For example, if utility air is not available, rent compressors.
• Plan and manage the Project HSE-to-Operations HSE handoff for utilities.
100
Appendix C: Hot Spot Characterizations
RACI Designations
CSU Critical
Indicators of CSF Achievement
Success Factor
7. CSU System
7.1 Formal CSU design review has occurred by the end of front end
Engineering during
engineering.
FEED
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
101
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
13. Integrated
13.1 Project schedule included system logic interdependencies and
Construction/CSU
turnover milestones prior to 30-percent construction complete.
Schedule
16. Collaborative
Approach to 16.1 Joint meetings, involving both CM and CSU managers, were
Construction-CSU conducted starting around 50-percent construction complete.
Turnover
102
Appendix C: Hot Spot Characterizations
Kickoff Alignment
Conduct Construction-CSU alignment meeting on the execution plan
Flowchart Activity # 1
Timing
Construction: Early
Causal Factors
• Changes in personnel after the original meeting.
• Common industry terms are understood differently by different parties.
• Individuals’ lack of experience with performing construction and construction quality
assurance.
• Individuals do not understand CSU requirements.
• Conflicts of interest arise, because the construction company is also the construction
quality assurance company.
• Pressure is placed on project schedule.
• CSU execution practices vary widely across the industry.
103
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Ensure that alignment is obligated contractually.
• Ensure that all relevant stakeholders attend the CSU alignment meeting.
• Bring construction managers onto the project early, even as early as the Design
phase. This gives them a chance to familiarize with, and contribute to, planning for
commissioning activities, especially for brownfield projects.
• Sign-off and archiving of the Construction-CSU alignment meeting by all stakeholders,
with any new/replacement stakeholders also required to sign-off.
• Periodic review of alignment goals, with modifications as necessary, and sign-offs by
all stakeholders.
• Ensure that project organization silos do not prevent communication between, and
alignment of, project personnel at all levels.
• Ensure and communicate the owner’s commitment to successful commissioning –
including committing the necessary resources and funding.
• Utilize a risk assessment system.
RACI Designations
104
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
2. Critical Interfaces 2.1 Project team has identified all tie-ins and individual shut-downs
on Brownfield by 30-percent detailed design complete; and these have been
Projects integrated into the construction-CSU integrated schedule.
3.1 By the end of front end engineering, the CSU budget has been
3. Adequate
derived from knowledge of CSU strategy and scope of work, and if
Funding for CSU
needed CSU resources, not simply a percentage of TIC.
6. System Milestone
6.1 System acceptance criteria were incorporated into the contract with
Acceptance Criteria
the execution contractor.
and Deliverables
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
13. Integrated
13.1 Project schedule included system logic interdependencies and
Construction/CSU
turnover milestones prior to 30-percent construction complete.
Schedule
105
Appendix C: Hot Spot Characterizations
Flowchart Activity # 19
Timing
Construction: Early
106
Appendix C: Hot Spot Characterizations
Causal Factors
• Requirements for construction turnover packages are often not well defined in contract
documents.
• Construction relies on engineering for the most current revision of documents
delivered to the field. Without good communication of design change documents,
submission of turnover packages will be negatively impacted.
• Incomplete system definition can cause problems when trying to create turnover
packages.
• There is often a lack of client review/approval of systems. Plant personnel are very
busy and do not have time to review and approve all of the system definitions.
• Turnover packages are often not viewed as urgent, so they are put off. Further, there
is a general dislike of paperwork. The meticulous attention required to construct a
turnover package is something that most would rather avoid.
• In a contract bidding situation, the construction contractor usually has no say as
to the terms of the contract, including those regarding turnover packages. Owner
organizations can impose onerous and complicated requirements without any input
from the construction contractor.
107
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Define requirements for turnover packages more specifically, including schedule
milestones and definition of terms.
• Define turnover requirements in the construction contract.
• Ensure the establishment of standard communication for process change
documentation from Engineering to the Construction Contractor.
• Coordinate system turnover package definition tasks with client and other project
stakeholders to ensure their involvement and approval.
• Assign one or more turnover package managers.
• Owners should make an effort to reduce the complexity of turnover package
requirements.
• Ensure that a good turnover package software/tool is in place.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technologies [CII 2015]:
–– Smart P&IDs
–– Asset Data Management/Wireless Instrumentation
–– Completion Management Systems.
RACI Designations
108
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
6. System Milestone
6.1 System acceptance criteria were incorporated into the contract with
Acceptance Criteria
the execution contractor.
and Deliverables
14. Accurate As- 14.2 An asset information plan has been defined, reviewed, and
built Information approved by the end of detailed design.
14.3 A detailed as-built plan has been defined, reviewed, and approved
by the end of detailed design, and was referenced within the
project execution plan.
16. Collaborative
Approach to 16.1 Joint meetings, involving both CM and CSU managers, were
Construction-CSU conducted starting around 50-percent construction complete.
Turnover
109
Appendix C: Hot Spot Characterizations
Start Maintenance
Initiate maintenance procedures
Timing
Startup: Early
Causal Factors
• Some systems, such as utilities systems, begin operation long before others, and
Maintenance staff are not yet on site to initiate maintenance procedures.
• The gradual handover of systems to the Operations team makes it more difficult to staff
initial maintenance of the facility.
• There is often a lack of alignment between Operations & Maintenance (O&M) and
Commissioning on brownfield projects.
• The Design and Operations groups are so siloed that designers have little interaction
with field personnel or first-hand experience with O&M.
110
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Align maintenance staff as a part of the Operations team early on.
• Do not allow turnover of a system from Commissioning to Operations until
maintenance personnel for that system are on site.
• Integrate O&M personnel as part of the joint-review of the plant design. This should
ensure at least some measure of design for operability/design for maintainability.
• Maintenance personnel (that support the project) should have helped create the asset
maintenance strategy back in late FEED/Basic Design or early in Detailed Design. This
early involvement will help ensure their buy-in to the process and effort.
• Use maintenance personnel who are dedicated to the project. This should help ensure
that they feel ownership over the project and plant.
• Use vendors with high-quality maintenance procedures and resources. Bring vendor
representatives to the site to train plant maintenance personnel on how to perform
maintenance on their equipment.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technologies [CII 2015]:
–– Simulation-based Virtual Commissioning
–– Operator Training.
RACI Designations
Responsible: Maintenance
Consulted:
111
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
2. Critical Interfaces 2.1 Project team has identified all tie-ins and individual shut-downs
on Brownfield by 30-percent detailed design complete; and these have been
Projects integrated into the construction-CSU integrated schedule.
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
112
Appendix C: Hot Spot Characterizations
O&M Involvement
Identify and integrate key Operations & Maintenance personnel and supporting
organizations
Flowchart Activity # 5
Timing
Construction: Early
Causal Factors
• Key O&M human resources are too busy with their day-to-day work to support CSU.
• Operations personnel may not be interested in participating in the project at this point;
changes to the plant only become important to them the day they begin to operate it.
• Key O&M human resources are retiring.
• In some sectors, and on most greenfield projects, experienced and capable operators
are relatively few, so it can be difficult to get them on a project as early as this stage.
• Difficulty in hiring additional staff – unionized organizations (e.g., government) have
rigid hiring and firing policies, which makes it difficult to scale up a project team for a
brief period of time.
113
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Create drivers for stakeholders outside the project team to align with the vision for the
project and help deliver.
• The CSU team should spend the necessary time aligning within the group as well as
with the project team.
• Coordinate early with SMEs and take advantage of their expertise to ensure CSU
success.
• Establish resource requirements and commitments early during the FEED phase.
• Execute a CSU charter that identifies resource expectations and involvement. Have it
signed by both the project manager and plant operations management.
• Ensure that O&M management deliverables and targets are compatible with the
project goals.
• Maintain a project succession plan for all key personnel, including plans for a shadow/
alternate for each key operations position.
• Conduct risk analysis meetings with O&M personnel participation. Make assignments
for risk mitigation of specific items so that there is not confusion about who is
responsible for what between disciplines/organizations.
114
Appendix C: Hot Spot Characterizations
RACI Designations
CSU Critical
Indicators of CSF Achievement
Success Factor
2. Critical Interfaces 2.1 Project team has identified all tie-ins and individual shut-downs
on Brownfield by 30-percent detailed design complete; and these have been
Projects integrated into the construction-CSU integrated schedule.
3.1 By the end of front end engineering, the CSU budget has been
3. Adequate
derived from knowledge of CSU strategy and scope of work, and if
Funding for CSU
needed CSU resources, not simply a percentage of TIC.
115
Appendix C: Hot Spot Characterizations
Familiarize Operations
Familiarize Operations personnel with equipment during factory acceptance tests
or on-site
Flowchart Activity # 30
Timing
Construction: Mid
116
Appendix C: Hot Spot Characterizations
Causal Factors
• Operations personnel are not available or have not yet been selected for the project.
–– Operators are in short supply.
–– Greenfield project has not yet been able to hire operators.
–– Operators are reluctant to participate so early in the project.
–– Operators are busy operating the existing facility (brownfield) or other facilities
(greenfield), and management may be reluctant to staff up before they feel it is
absolutely necessary.
–– The cost of having operators on the job “before there is anything to operate” is
perceived as wasted money from the business case perspective.
• New processes or equipment types require an investment in the “learning curve.”
Inexperienced operators hired for a greenfield project may not be able to learn during
FAT what they really need to know about the equipment.
• The project site and location of FAT may be far apart with poor transportation to or from
remote locations, making attendance at FATs difficult, inconvenient, and expensive.
• Operations personnel are inconsistently involved.
• Other work is perceived to be more urgent than familiarizing Operations personnel with
equipment before it is installed and online.
• Because the supply chain for equipment is not transparent, Commissioning and
Construction personnel may not know when equipment will arrive or where it is on-site
once it does arrive. This makes the familiarization and training of Operations personnel
on site more difficult.
• Budget constraints can minimize travel ,and thus reduce the number of FAT
observations.
117
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Ensure that contracts with OEMs/suppliers include provisions for FAT/SAT
participation.
• Bring key Operations personnel on the project early enough for them to participate in
equipment familiarization during FAT or on-site (or both).
• Implement equipment tracking solutions so that the location and status of equipment
is always known. This will make equipment familiarization much more efficient and
effective.
• If equipment familiarization did not occur during the Construction phase, do it
during Pre-Commissioning or even during Commissioning. While this timing is less
convenient, it will still educate operators and help prevent problems during initial
operations.
• Ensure that budgets, contracts, and staffing allow for Commissioning and Operations
personnel to be involved in the project early enough to have time to become familiar
with equipment.
• Preservation and many Pre-Commissioning/Commissioning tests and checks are
activities that Operations personnel should be committed to and participate in,
because they will be most effected by how well the equipment operates.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technologies [CII 2015]:
–– Asset Data Management/Wireless Instrumentation
–– Simulation-based Virtual Commissioning
–– Operator Training
RACI Designations
118
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
3.1 By the end of front end engineering, the CSU budget has been
3. Adequate
derived from knowledge of CSU strategy and scope of work, and if
Funding for CSU
needed CSU resources, not simply a percentage of TIC.
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
119
Appendix C: Hot Spot Characterizations
Flowchart Activity # 63
Timing
Pre-Commissioning: Early
Causal Factors
• Because loop and I/O checks are one of the first pre-commissioning activities, they are
often not performed carefully.
• Project management personnel often lack technical understanding of controls systems.
• There is often a lack of alignment between construction and CSU teams on the
requirements/procedure for loop and I/O checks.
• There is often a lack of training to identify loop check failures in complex systems.
• Loop folders are often not complete (missing or outdated documents) or are completed
late.
120
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Contractual terms need to support the time and resources necessary for these checks.
• Procedures for controls system tests and checks must be identified, completed, and
documented early in the Detailed Design phase.
• Align construction and CSU on the standards and procedure for loop and I/O checks of
systems. If possible, reference these standards and procedures in contract documents.
• Follow a CSU plan to define requirements for all Commissioning efforts and quality
assurance checks.
• Assign CSU personnel to perform or witness loop and I/O checks, rather than
Construction personnel.
• Provide knowledgeable technical human resources to perform quality assurance tasks,
specific to controls systems.
• Prepare the loop folders early.
• Test third-party interfaces as part of the DCS FAT testing.
• Perform QC on installations to ensure the work was performed according to the loop
and I/O check procedures.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technology [CII 2015]: Asset Data Management/Wireless Instrumentation.
RACI Designations
Responsible: Electrical; Automation/DCS; Instrumentation and Controls; System
Commissioning Teams
Accountable: Commissioning and Startup Management
Consulted:
Informed: CSU Planning, Progress Tracking, and Schedule Control; Systems
Completions Database and Support; OEM/Supplier
121
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
13. Integrated
13.1 Project schedule included system logic interdependencies and
Construction/CSU
turnover milestones prior to 30-percent construction complete.
Schedule
122
Appendix C: Hot Spot Characterizations
System Walk-downs
Conduct system walk-downs for turnovers
Flowchart Activity # 94
Timing
Commissioning: Mid
Causal Factors
• Construction and CSU do not align on what is included in system walk-downs.
• The correct personnel for the walk-downs may not be available, as they already have
moved on to other projects.
• The scope of walk-downs and associated contractual requirements are insufficiently
defined.
• Stakeholders have different expectations about what makes a system ready for startup.
• Operations personnel are not available during Pre-Commissioning/Commissioning to
identify problems.
• The duration of walk-downs and the manpower required are not accurately assessed
during CSU planning.
123
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Align on the scope of system walk-downs early, and include a specific definition in
contract documents.
• Ensure the timely participation and sign-off of Operations personnel during the Design
phase in order to avoid late changes.
• Ensure that each system has an individual identified as responsible for coordinating
that system’s walk-down for turnover.
• Accurately assess the time and manpower required for system walk-downs during
CSU planning.
• Remove and replace individual contributors that are not dedicated to coordinated,
unified walk-downs and team unity among all the contributors.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technology [CII 2015]: Completion Management Systems.
RACI Designations
124
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
6. System Milestone
6.1 System acceptance criteria were incorporated into the contract with
Acceptance Criteria
the execution contractor.
and Deliverables
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
125
Appendix C: Hot Spot Characterizations
HAZOP Closure
Verify closure of HAZOP action items
Timing
Project Close-out
Causal Factors
• Changes made to the facility design post-HAZOP may not get risk-assessed.
• Closing HAZOP items is time consuming, detailed, an undesirable task, and requires a
high level of technical expertise.
• An 80/20 mentality is applied in a zero-tolerance context
• Cost-cutting pressures, if the project is over-budget.
• There may not have been an assigned responsible party for identifying HAZOP items
or for determining the risk profile.
• HAZOP action items often result from late design changes, and thus impact
construction sequencing and productivity. For these reasons action items may not be
closed or completed.
• The only chance for Operations personnel to ask for changes may be during the
HAZOP review, so they erroneously add HAZOP action items under operability
justifications.
126
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• All changes and as-built redlines post-HAZOP must be documented and properly risk-
assessed.
• Assign the parties responsible for closing HAZOP action items during the HAZOP
review.
• An effective, rigorous management of change (MOC) program must be in effect at the
start of initial operation.
• Require the closure of HAZOP action items before startup/operations on safe mode.
• Closure of HAZOP action items should be tracked in the detailed project schedule.
• HAZOP completion and close-out documentation should be a requirement for the pre-
startup safety review (PSSR).
• Develop detailed commissioning sequence packages and perform a HAZOP review for
each sequence.
• Ensure effective implementation of MOC and alternate operating procedure programs.
• Give Operations personnel adequate opportunities to make design changes outside
the HAZOP review, so they do not feel the need to add operability issues as HAZOP
action items.
• Create a detailed definition/formulation for which items qualify as HAZOP items.
RACI Designations
127
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
14. Accurate As- 14.2 An asset information plan has been defined, reviewed, and
built Information approved by the end of detailed design.
14.3 A detailed as-built plan has been defined, reviewed, and approved
by the end of detailed design, and was referenced within the
project execution plan.
128
Appendix C: Hot Spot Characterizations
Flowchart Activity # 37
Timing
Commissioning: Mid
Causal Factors
• The operation test procedures are not defined early enough in the project.
• There is a lack of continuity (or availability) of documentation, making it difficult to
create good operation test procedures.
• Personnel that have experience with operational testing are not typically staffed on the
project early enough to include meaningful input.
• Insufficient CSU experience, which can lead to inadequate commissioning procedures.
• Over-reliance on subcontractor procedures. Insufficient prime contractor procedures
for pulling/coordinating all of the subcontractor procedures together.
• Delay in receiving subcontractor test procedures, especially for customized equipment
which requires customized operational test procedures.
• Turn-over of key Operations/Commissioning personnel.
129
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Ensure consistency and continuity of documentation: vendor information à function
specifications à test plan à commissioning plan à acceptance results.
• Align on and define operation test procedures early.
• Staff one or two key personnel, with experience in operational testing, early enough to
provide meaningful input to test development.
• Provide experienced Commissioning personnel during the Design phase to ensure
that means for commissioning are built into design (i.e., tie-in points for temporary
equipment, recycle piping for prime movers or station recycle means, tie-ins for
flushing equipment, and temporary power).
• Insert wording in the prime and subcontractor contracts for providing test procedures
in a timely fashion with some schedule float.
• Vet the commissioning team to ensure sufficient commissioning experience, and that
the construction contractor is using capable personnel on the project.
• Ensure that systems (especially safety systems) are functional before the operational
tests are conducted.
• This hot spot can be prevented or mitigated with the following Innovative CSU
Technologies [CII 2015]:
–– Simulation-based Virtual Commissioning
–– Operator Training.
RACI Designations
130
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
131
Appendix C: Hot Spot Characterizations
Team Building
Conduct Construction-CSU team building
Flowchart Activity # 2
Timing
Commissioning: Early
Causal Factors
• There is often a lack of shared responsibility for project success between Construction,
CSU, Engineering Design, Operations, and other parties, and so they do not naturally
act as a team.
• The owner may try to prevent communication of multiple parties with the Construction
Contractor, preferring instead to have only one point of contact. The owner may even
totally prevent engineering/design from communicating with Construction. While this
prevents the construction contractor from getting mixed messages, it also drastically
limits open communication of problems and prevents teamwork.
• Lack of true alignment between teams on project execution, even though nominal
alignment meetings have been held.
• Different goals between Construction, CSU, and Operations lead to different priorities.
• Operations-CSU team building is just as important as Construction-CSU team building.
• Individuals may get along well enough, but cannot succeed working together if the
organizational structure and/or contractual terms of the project do not set them up for
success.
• Non-productive and unhealthy competition between teams from separate departments
or companies.
132
Appendix C: Hot Spot Characterizations
Prevention/Mitigation Strategies
• Conduct Construction-CSU team building, multiple times as required to support project
complexity, duration, and personnel changes.
• Ensure that the construction manager and commissioning manager have a good
working relationship. They should mutually respect one another.
• Ensure that all parties on the project feel shared responsibility for the ultimate success
of the project.
• Develop an open culture where project team members of any level are able to identify
problems and bring them to the attention of the group without fear of being looked
down upon.
• Team building activities are more effective early in the project, however can still be
conducted later in the project and should be continued periodically through to the end
of the project.
• Personnel selection is very important. Cooperative, congenial, open attitudes are
important along with experience and technical competence. One person in a key role
who does not communicate well with others will hurt the team and the project.
• Project contracts and organizational structures should promote open communication
of the project teams, especially among Construction and CSU. The two parties should
have a balance of influence, with neither reporting to the other. Good contracts and
organizational structures will set up the parties for successful Commissioning and
Startup.
RACI Designations
133
Appendix C: Hot Spot Characterizations
CSU Critical
Indicators of CSF Achievement
Success Factor
5.1 A CSU manager was assigned at the start of front end engineering
and remained with the project through to initial operations.
5. CSU Leadership
Continuity
5.2 The qualifications and the planned tenure of the CSU manager
were well-defined by early front end engineering.
9. Detailed CSU 9.2 The CSU execution plan was integrated into the overall project
Execution Plan execution plan and had evident linkages to other project functions
(e.g., engineering, construction, operations, maintenance, quality,
and HSE)
9.3 Operations provided input into the preparation of the detailed CSU
execution plan.
134
Appendix D
CSU Critical Success Factors and
Associated Indicators of Achievement (from CII 2015)
Critical Top 30
CSF Indicators of Achievement
Success Factor Indicator
135
Appendix D: CSU Critical Success Factors and Associated Indicators of Achievement
Critical Top 30
CSF Indicators of Achievement
Success Factor Indicator
136
Appendix D: CSU Critical Success Factors and Associated Indicators of Achievement
Critical Top 30
CSF Indicators of Achievement
Success Factor Indicator
9. Detailed CSU 9.2 The CSU execution plan was integrated into the
Execution Plan overall project execution plan and had evident
linkages to other project functions (e.g., engineering,
construction, operations, maintenance, quality, and
HSE)
137
Appendix D: CSU Critical Success Factors and Associated Indicators of Achievement
Critical Top 30
CSF Indicators of Achievement
Success Factor Indicator
12. CSU Team 12.2 CSU team members understood the links between
Capability their actions and the technical metrics for project
success.
138
References
1. Akashi, Y., Castro, N., Novakovic, V., Viaud, B., Jandon, M. The IEA/ECBCS/Annex
40 Glossary on Commissioning.
2. American Petroleum Institute. (2013). Facilities Systems Completion Planning and
Execution. API Recommended Practice 1FSC, 1st Ed.
3. Bagsarian, T. (2001). “Avoiding startup stumbles.” Iron Age New Steel, 17(2), 16-19.
4. Construction Industry Institute (1998). Planning for Startup, Implementation Resource
121-2. Austin, TX.
5. Construction Industry Institute (2010). CII Value of Best Practices Report.
Benchmarking and Metrics 2010-4. Austin, TX.
6. Construction Industry Institute (2015). Achieving Success in the Commissioning
and Startup of Capital Projects, Volume I: Best Practices for Commissioning and
Startup. Implementation Resource 312-2, Austin, TX.
7. Construction Industry Institute (2015). Achieving Success in the Commissioning and
Startup of Capital Projects, Volume II: Mini-Case Studies. Implementation Resource
312-2, Austin, TX.
8. Construction Industry Institute (2016). Identification and Implementation of Critical
Success Factors in Commissioning and Startup of Capital Projects. Research Report
312-11, Austin, TX.
9. Deloitte & Touche (2012). Effective Operational Readiness of Large Capital Projects:
Avoiding value leakage in the transition from project execution into operations,
Johannesburg, RSA.
10. Gonzalez, M. (2017). “ISPE Glossary.” International Society for Pharmaceutical
Engineering. <http://www.ispe.org/glossary> (April 25, 2017).
11. Haughey, D. “RACI Matrix.” Projectsmart. <www.projectsmart.co.uk> (Apr. 27, 2017).
12. Horsley, D. (1998). Process Plant Commissioning. Institution of Chemical Engineers,
Bookcraft Ltd., Bath, UK.
13. International Society for Pharmaceutical Engineering (2001). GAMP® 4: Good
Automated Manufacturing Practice Guide for Validation of Automated Systems, as
referenced in ISPE 2017 (Reference 10).
14. International Society for Pharmaceutical Engineering (2001). ISPE Baseline® Guide,
Vol. 4: Water and Steam Systems, 2nd Ed, as referenced in ISPE 2017.
15. International Society for Pharmaceutical Engineering (2001). ISPE Baseline® Guide,
Vol. 5: Commissioning and Qualification, as referenced in ISPE 2017.
16. International Society for Pharmaceutical Engineering (2004). ISPE Baseline® Guide,
Vol. 6: Biopharmaceutical Manufacturing Facilities, as referenced in ISPE 2017.
139
References
17. International Society for Pharmaceutical Engineering (2005). GAMP® Good Practice
Guide: IT Infrastructure Control and Compliance, as referenced in ISPE 2017.
18. International Society for Pharmaceutical Engineering (2007). ISPE Baseline® Guide,
Vol. 1: Active Pharmaceutical Ingredients, 2nd Ed, as referenced in ISPE 2017.
19. International Society for Pharmaceutical Engineering (2007). ISPE Good Practice
Guide: Commissioning and Qualification of Pharmaceutical Water and Steam
Systems, as referenced in ISPE 2017.
20. International Society for Pharmaceutical Engineering (2008). GAMP® 5: A Risk-
Based Approach to Compliant GxP Computerized Systems, as referenced in
ISPE 2017.
21. International Society for Pharmaceutical Engineering (2009). ISPE Good Practice
Guide: Heating, Ventilation, and Air Conditioning (HVAC), as referenced in ISPE 2017.
22. International Society for Pharmaceutical Engineering (2011). ISPE Good Practice
Guide: Project Management for the Pharmaceutical Industry, as referenced in ISPE
2017.
23. International Society for Pharmaceutical Engineering (2012). GAMP® Good Practice
Guide: A Risk-Based Approach to Testing of GxP Systems, 2nd Ed, as referenced
in ISPE 2017.
24. Lamport, W., Rosenberg, D. (2005). “Hook-up and Commissioning: The Last Step
to a Successful Project.” Upstream Industry Benchmarking Conference.
25. Merrow, E. (2011). Industrial Megaprojects: Concepts, Strategies, and Practices for
Success, 1st Ed., Wiley, Hoboken, NJ.
26. Tribe, M., Johnson, R. (2008). “Effective Capital Project Commissioning.” Pulp and
Paper Industry Technical Conference, 2008. PPIC 2008. Conference Record of
2008 54th Annual. Seattle, WA.
27. U.S. Department of Energy (2006). “Glossary of Environment, Safety and Health
Terms.”
28. U.S. Food & Drug Administration (2014). “FDA Glossary of Computerized System
and Software Development Technology.” <https://www.fda.gov/iceci/inspections/
inspectionguides/ucm074875.htm> (April 25, 2017).
140
Notes
141
Research Team 333: Transition Management between Construction
Completion, Pre-Commissioning, Commissioning, and Startup
Mark Bergman, Zurich
Ed Brown, Zachry Group
* Beth Buerger, Bentley Systems Inc.
Alejandro Castaño, Construtora Norberto Odebrecht S.A.
Ginger Craig, Southern Company
Juan Cruz, SBM Offshore
Nathan Dykstra, ArcelorMittal
Mary Kay Garcia, Eli Lilly and Company, Chair
Glenn Griffith, Occidental Petroleum Corporation
* Matt Lamey, Anadarko Petroleum Corporation
* Brant Mock, The University of Texas at Austin
Pat Noonan, Haskell
Brian Nordmann, Emerson
* Jim O’Connor, The University of Texas at Austin, Principal Investigator
* Jenny Parish, EnLink Midstream
* Mauricio Rodriguez, Smithsonian Institution
Joel Tremblay, Chevron
Amin Vahdat, WorleyParsons, Vice Chair
Skip Vaughn, Architect of the Capitol
Peter Walker, Coreworx Inc.
Past member
Chris Tisdel, Autodesk, Inc.
* Principal authors