This document summarizes the bonding history of an oil and gas pipeline. It lists 11 joints that were bonded together including pipes, flanges, elbows and tees. For each joint it provides the bonding date, bonder ID, pre-padding and post-padding report numbers. It was signed off by representatives from the contractor Arabian Industries Projects and Petroleum Development Oman to verify the quality of the bonded joints.

Uploaded by

chandana kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
352 views1 page

Joint Summary Sheet

This document summarizes the bonding history of an oil and gas pipeline. It lists 11 joints that were bonded together including pipes, flanges, elbows and tees. For each joint it provides the bonding date, bonder ID, pre-padding and post-padding report numbers. It was signed off by representatives from the contractor Arabian Industries Projects and Petroleum Development Oman to verify the quality of the bonded joints.

Uploaded by

chandana kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

GRE BONDING HISTORY SHEET

CONTRACT NO :C3100000175 REPORT NO: RMS-001-01

PROJECT TITLE : Khulud Phase -2 Development Project DATE:


24-12-2022
COMPANY : Petroleum Development Oman SHEET NO:
1 of 6
CONTRACTOR : Arabian Industries Projects TEST PACK NO: TP-31-DC-01-04

LINE NO :4''-D-65012-17011M6-01 PIPE MANUFACTURER : FPI- Muscat

Sl.No. COMPOUND 1 COMPOUND 2 COMPOUND NO 1 LENGTH 1 COMPOUND NO 2 LENGTH 2 Fitting Details Joint No. Bonder ID Bonding Bonding Report Pre-Padding Post Padding Remarks
MM MM Date No Rep No Report No

1 Flange Pipe 35 #FMT 1233 #150 FJ-1 BR-01/BR-02 11/30/2022 B-003 YIB-AIP-2022- YIB-AIP-2022- Tg Tested
062145120060146
CVL-1326 CVL-1428

2 Pipe Elbow #FMT 1233 90 45° FJ-2 BR-01/BR-02 12/11/2022 B-018 YIB-AIP-2022- YIB-AIP-2022-
062144125060124
CVL-1326 CVL-1428

3 Elbow Pipe 90 #FMT 6000 45° FJ-3 BR-01/BR-02 12/5/2022 B-011 YIB-AIP-2022- YIB-AIP-2022- Tg Tested
062144125060124
CVL-1326 CVL-1428

4 Pipe Pipe 6000 2222 - FJ-4 BR-01/BR-02 12/7/2022 B-015 YIB-AIP-2022- YIB-AIP-2022-
102148100100016 102148100100042
CVL-1326 CVL-1428
YIB-AIP-2022- YIB-AIP-2022-
5 Pipe Tee 102148100100042 2222 062146125010177 95 Equal Tee FJ-5 BR-01/BR-02 12/11/2022 B-018
CVL-1326 CVL-1428

6 Tee Pipe 95 1443 Equal Tee FJ-6 BR-01/BR-02 12/12/2022 B-019 YIB-AIP-2022- YIB-AIP-2022-
062146125010177 102148100100042
CVL-1326 CVL-1428

7 Pipe Elbow 1443 180 90° FJ-7 BR-01/BR-02 12/7/2022 B-015 YIB-AIP-2022- YIB-AIP-2022-
102148100100042 062145125060009
CVL-1326 CVL-1428

8 Elbow Pipe 180 874 90° FJ-8 BR-01/BR-02 12/12/2022 B-019 YIB-AIP-2022- YIB-AIP-2022-
062145125060009 102148100100041
CVL-1326 CVL-1428

9 Pipe Elbow 874 180 90° FJ-9 BR-01/BR-02 12/6/2022 B-012 YIB-AIP-2022- YIB-AIP-2022-
102148100100041 06214512560011
CVL-1326 CVL-1428

10 Elbow Pipe 180 853 90° FJ-10 BR-01/BR-02 12/12/2022 B-019 YIB-AIP-2022- YIB-AIP-2022-
06214512560011 102148100100060
CVL-1326 CVL-1428

11 Pipe Flange 853 35 #600 FJ-11 BR-01/BR-02 11/30/2022 B-003 YIB-AIP-2022- YIB-AIP-2022-
102148100100060 062145120060328
CVL-1326 CVL-1428
Notes:

For Arabian Industries Projects For PDO