X-MAS & NEW YEAR HOLIDAY WORKS PLAN /5-WEEKS LOOK AHEAD

1.0 SCOPE
This plan covers the civil works for excavations, blinding, rebar works, formworks, concreting,
and blockworks of perimeter fencing and equipment foundation bases. Also included in this
plan is casting of slabs for project bond and proposed site visit of project bond ROW/Work
Sites. On this holiday season.

2.0 SUMMARY OF THE PLANNED DATES FOR THE HOLIDAY WORKS.

S/N Activity Start Date Finish Date

1 Excavation of trenches for fencing 30/11/2020 8/01/2021

Casting of Project Bond Concrete Slabs at GNL base in


2 24/11/2020 17/01/2021
Warri

3 Project Bond Site Visit 07/01/2021 08/01/2021

4 Concrete Blinding on trenches 08/12/2020 12/01/2021

Rebar works and formworks for continuous strip


5 04/12/2020 16/01/2021
foundation and retaining wall for fencing

6 Concreting of strip foundation for fencing 10/12/2020 16/01/2021

7 Block works for fencing 11/12/2020 21/01/2021

Setting out of equipment bases in process area


(Instrument air skid foundation, Water bath heater skid
8 11/12/2020 13/12/2020
foundation, Condensate accumulator foundation, Gas
metering skid foundation)

Excavation for equipment foundation bases (Instrument


air skid foundation, Water bath heater skid foundation,
9 14/12/2020 17/12/2020
Condensate accumulator foundation, Gas metering skid
foundation)

Filling and compaction of bases (Instrument air skid


foundation, Water bath heater skid foundation,
10 15/12/2020 20/12/2020
Condensate accumulator foundation, Gas metering skid
foundation)

Blinding of equipment foundation bases (Instrument air


skid foundation, Water bath heater skid foundation,
11 14/12/2020 21/12/2020
Condensate accumulator foundation, Gas metering skid
foundation)

Fixing of Rebar works (Instrument air skid foundation,


12 Water bath heater skid foundation, Condensate 17/12/2020 27/12/2020
accumulator foundation, Gas metering skid foundation)
Formwork (Instrument air skid foundation, Water bath
13 heater skid foundation, Condensate accumulator 19/12/2020 26/12/2020
foundation, Gas metering skid foundation)

Placing of concrete (Instrument air skid foundation,


14 Water bath heater skid foundation, Condensate 21/12/2020 04/01/2021
accumulator foundation, Gas metering skid foundation)

15 Foundation works for Security post 22/12/2020 04/01/2021

16 Generator Base foundation 22/12/2020 06/01/2021

Movement of Procured Tie-in Materials (i.e. Piping,


17 22/12/2020 09/01/2021
Fittings, Valves, etc). to ABA CIGA site

NOTE:

1. The relocation of anode ground bed and underground cables will affect the
start and finish date of fencing, equipment foundation bases and other
structures.

2. CONTACT OF GNL SITE MANAGER EZEKIEL EDAFE


Phone – 08163952333; Email – [email protected]

GNL EMERGENCY CONTACT PERSON PROMISE A. AMADI


Phone – 08058406433; Email – [email protected]

2ND GNL EMERGENCY CONTACT PERSON FELIX O. OWUMI:


Phone – 08028441084; Email – [email protected]