Online Examination:
Section - I Instructions:
- While attempting subjective examination Text formatting facility will be disabled such as use of bullets,
making the text bold, underlining the text etc. Only normal character on the key board will be available.
- Special characters available on the keyboard will be allowed.
- Students can not attempt more than 2 questions out of given 3.
- A blank (space typed) or any entry in the space provided will be considered as question is answered.
- Hand written answers are not allowed. Subjective test can be answered by using key board.
- No brail support shall be provided, but writer assistance shall be allowed. The student has to intimate it to
SCDL well in advance by completing applicable formalities.
- Answers for both the questions should not exceed more than 110 words. The maximum word limit per
answer is 55 words (for Subjective part).
Page 1 of 7
SCDL
1. Manufacturing cycle is small, hence, less WIP. 2. Material handling is minimum and automatic. 3.
Space required is small. 4. Work is mechanised, hence, labour costs are low. 5. Quality control is easy and
effective. 6. Delivery commitments are easy to accomplish. 7. Material requirements can be scheduled
easily and accurately.
2) What is dispatching in production activity control? What are the duties and responsibilities of a
dispatcher?
(5)
Dispatching is concerned with the preparation and distribution of work orders and instructions to shop to
perform the work as per schedule. Responsibilities are: 1. Order release. 2. Issue jigs/fixtures. 3. Return
surplus material to store. 4. Internal transport. 5. Set priorities for inspection. 6. Coordination with
scheduler. 7. Job allocation on machines. 8. Shift finished jobs. 9. Collect records after production runs.
Section 1 is complete.
Section - II Instructions:
Page 2 of 7
SCDL
Total Questions : 27
Total Marks : 60
1) As a general rule minimum size of the proposed site should be higher than actual plant size by
(2)
1] Two times
2] Three times
3] Five times
4] Seven times
4) A managerial statement of period-by-period [ time phased ] production rates , work force levels , and
inventory investment , given customer requirements and capacity limitations , is referred to as
(2)
1] Capacity Plan
2] Production plan
3] Staffing Plan
4] Strategic plan
5) What do you understand by the spare time present in an activity if it is started as late as possible and
finished as early as possible?
(2)
1] Dependent float
2] Free float
3] Independent float
4] Total float
6) Development of a good lubrication programme begins with the identification of lubrication points.
(1)
1] True
2] False
7) The situation where the variability of the process though is well within the variability allowed by the
Page 3 of 7
SCDL
8) The process is described in much detail as possible by graphically displaying the steps in proper sequence ,
is known as
(2)
1] DMAIC [ Define , Measure , Analyze, Improve and Control ]
2] Flowcharts
3] DFSS [ Design For Six Sigma ]
4] Checksheets
10) According to Japanese manufacturers , one of the ways to improve the quality of a product is to improve
quality of process used to make that product.
(1)
1] True
2] False
11) How many symbols are used to record facts relating to job under method study?
(2)
1] Eight
2] Five
3] Three
4] Four
12) :BLANK of production management is viewed as the efficiency with which inputs are converted into
output
(1)
1] Effeictiveness
2] Efficiency
3] Performance
4] Appraisal
13) Which are the factors on which the structure of the transportation cost depends?
(4)
1] Average distance of shipment
2] Characteristics of the commodity
Page 4 of 7
SCDL
3] Power
4] Medium of shipment
14) Which of the following factors related to the labour and wages are considered while deciding the plant
location?
(4)
1] Prevailing wage pattern
2] Octroi
3] Productivity of labour
4] Industrial relations
15) Following are some of the factors considered for evaluation of alternative layouts
(4)
1] Flow of Material
2] Equipment utilization
3] Ease of supervision
4] Delivery performance
16) REL chart exhibits relationship between :BLANK of departments in terms of degree of closeness desired
(1)
1] Pairs
2] types
3] sizes
4] areas
18) A time phased order system that under ideal circumstances schedules the order releases for needed
demand inventory items so that the items arrive just as they are required , is known as
(2)
1] Master Production Schedule [ MPS ]
2] Planning Horizon
3] Enterprise Resource Planning [ ERP ]
4] Material Requirements Planning [ MRP ]
19) :BLANK refers to the duration for which loading and scheduling is to be done.
(1)
1] Unit of measurement
2] Performance Standard
3] Unit of loading and scheduling
4] Effective capacity per work center
20) The :BLANK system is an information system to control production quantities in and between processes.
(1)
1] Kanban
Page 5 of 7
SCDL
2] Kaizan
3] JIT
4] Push
21) If activities are not deterministic, there is no need of finding probability of project completion by target
date.
(1)
1] True
2] False
22) The earliest start time of an activity equals earliest time for the event from which activity arrow
originates.
(1)
1] True
2] False
23) All activities lying on the non-critical paths must have total float and free float.
(1)
1] True
2] False
27) American Society of Mechanical Engineers and British Standard Institute have advocated :BLANK
symbols for graphical method of recording in method study
(1)
Page 6 of 7
SCDL
1] Six
2] Five
3] Four
4] Seven
Section 2 is complete.