J K Engineering Manual 2020
J K Engineering Manual 2020
PUBLISHED BY
PUBLIC WORKS (R&B) DEPARTMENT, J&K
GOVERNMENT OF JAMMU & KASHMIR
PUBLISHED BY
The J&KPWD manual was adopted decades back from British system of engineering
practice. Since then it has not been updated in the form of document. Time and again, the
department has felt the need for a consolidated document which shall be reckoned as
engineering reference for practice of all activities ranging from inception of project to its
completion.
In order to complete the said process Government of Jammu and Kashmir has
constituted a technical advisory team vide Govt. Order No. 193 PW(R&B) of 2020 dated
07- 07- 2020 for drafting the engineering manual as part of institutional strengthening of
Public Works Department which shall be named as J&KPWD Engineering Manual 2020.
The draft “J&KPWD Engineering Manual 2020” has been derived from various manuals
of other states, besides CPWD Manual 2019 as a basic frame work and best practices in
vogue in the country.
With the passage of time, various documents have been adopted from various states of
the country to compile rules for the award and execution of contracts. This engineering
manual has been consolidated, updated and placed all these documents under one cover
with necessary modifications. Ambiguities, if any, in previous practices, have been clarified
in this manual.
In general, all engineering practices have been standardized and set of procedures
worked out to bring transparency and accountability in deliberation of powers at all
levels. This engineering manual is expected to bring financial discipline and accountable
code of practice in engineering department. The modern technical interventions like, GIS,
RMMS have been incorporated in the manual besides quality assurance mechanism. All
these have been linked to the JKPWDOMS web portal which is under development.
The standardization of engineering practices will finally lead to uniform code of practice,
which shall bring more transparency and accountability. The general public shall also be
aware of the working system of the department, which will guarantee safety of public
interests.
Legend of Abbreviations
AA Administrative Approval
AE Assistant Engineer
AO Accounts Officer
BG Bank Guarantee
BM Bituminous Macadam
CE Chief Engineer
DD Deputy Director
EE Executive Engineer
HD Head Draftsman
JE Junior Engineer
QA Quality Assurance
SE Superintending Engineer
TO Technical Officer
TS Technical Sanction
Part I General
1 Organizational Setup 01
2 Duties, Responsibilities & Powers 11
3 Human Resources and Training 44
4 Information Technology & MIS 50
5 Financial Management System (FMS) 57
6 Planning Policy 59
7 Planning, Budgeting & Funding 60
8 Geographical Information System (GIS) 66
9 Road Maintenance System (RMMS) 74
10 Safety Management 79
11 Environmental Management 87
12 Social Impact Management 97
1
Chapter 1
Organizational Setup
CHAPTER - 1
Technical Administrative Planning Finance Legal
Development
Special Additional
Commissioner Director Director
Secretary Secretary
Works
1
1.0.0 General
The Public Works Department is the functional arm of the UT of Jammu
and Kashmir for overall development by way of construction and
maintenance of roads, buildings, bridges and other infrastructural works.
The department has in house resources for planning, design, execution,
monitoring and maintenance of these assets. The department generally gets
projects funded by the State Government and Government of India under
various developmental schemes viz., CRF, PMGSY, NABARD, besides
schemes funded by multi-lateral agencies viz World Bank, Asian
Development Bank, etc. Works are executed under various contractual set
ups like EPC, PPP, etc. which make project execution and its funding easier
PWD ENGINEERING MANUAL-2020 CHAPTER - 1
2
1.1.0 Functional Set Up
The functional setup of various officers in the hierarchy has been briefly described
below.
3
1.1.2.2 Designers, Architects, Legal and Financial Experts/
Outsourcing of Works.
4
1.1.3 Chief Engineer Office R&B,
The Chief Engineer is the administrative and technical head of the respective wings
of the department and at divisional level of the UT administration and is
responsible for efficient work execution, monitoring and making funds available to
SEs/EEs. The CE is assisted by a Technical officer of the rank of EE who remains
controlling officer for administrative, technical and planning sections of the
headquarter. The financial wing under the control of a Chief accounts officer with
sufficient complement of subordinate staff is responsible for all financial matters
under the overall control of Chief engineer. The Chief Engineer has powers of
sanctioning estimates and entering into contracts within the limits of delegated
powers. In addition to the above, the Chief Engineer has an electrical wing under
CHAPTER - 1
the control of an Executive Engineer (Electrical) wing.
The chief engineer office has the following sections working under the guidance of
technical officer to CE and overall control of the Chief Engineer.
5. Drawing section: The drawing section is headed by head draftsman and shall
be responsible for checking of estimates, drawings, DPRs, and all other related
issues.
5
7. Receipt and Dispatch Section: This section is headed by senior Assistant
/Junior assistant for making receipt and dispatches of direction office, maintaining of
files, record keeping, correspondences, etc. The section shall have one person
dedicated for digitizing of all the correspondence.
There is a Law officer deputed by Law department in all direction offices who deals
with legal matters of the department.
DIQC is headed by the Chief Engineer and deals with design of buildings, bridges and
other structures referred to it. The Chief Engineer is assisted by Superintending
Engineer besides an establishment wing in his office. The SE is assisted by
executive engineers to vet designs referred to the department. The divisional offices
are supported by a team of AEEs, AEs and JEs. All the staff deputed to DIQC are
having a minimum qualification of B.E/B. Tech. Engineers with Masters/ PhD. degree
are to be preferred for posting in this department. The Department shall create a core
staff of engineers who shall be having aptitude and passion for design of structures so
as to develop a think tank for the UT/state who can guide and advise the
department. The department shall also update and revise Schedule of Rates and the
Data Book regularly. Moreover there is a requirement of separate electrical and
mechanical sections in the DIQC.
A Superintending Engineer is to head the Road Safety Cell of the department and
be supported by two executive engineers, one at Jammu and one at Kashmir. It is
the responsibility of the Road Safety Cell to coordinate road safety activities
implemented by the concerned executing divisions. However, the implementation
of road safety works is done through regular divisional offices. All the Engineers
of the cell must be imparted sufficient and regular trainings on the subject. At least
two engineers of the cell shall be trained as Certified Road Safety Auditors. The
responsibilities of Road safety cell is as under:
● SE, Road Safety Cell to liaise and correspond with Road Safety Authority at UT/state
level.
● The team to audit all the roads as per road hierarchy within a specified period of
time as desired by the CE DIQC.
● SE Road Safety to submit road safety audit reports to CE, DIQC and to DCW for
6
implementation by respective chief engineers.
● The Superintending engineer shall personally visit minimum 30% of the total roads
audited by the cell supported with geo tagged photographs.
● The executive engineer shall personally visit minimum 40% of the total roads
audited by the cell supported with geo tagged photographs.
The cell shall also be responsible for conducting studies at accident-prone locations
CHAPTER - 1
and suggesting remedial measures to eliminate possibility of accidents.
The DIQC Laboratory shall provide guidance in setting up local laboratories, both
in respect of equipping them and training of personnel. These laboratories shall
1.1.4.3 Library
All codes for reference, technical books and publications etc. for department is to
be made available in a properly catalogued library established in DIQC.
7
1.1.5 Circle Office
The Provinces under the control of the Chief Engineer are subdivided into circles
which are further controlled by respective Superintending Engineers at their level.
Superintending Engineer is responsible for the overall working of the circle under
their jurisdiction. The Superintending Engineer has the authority of sanctioning
estimates and entering into contracts within the delegated powers. They are
assisted by a Technical officer of the rank of Assistant Executive Engineer who
shall be administering both administrative and technical sections of the circle.
Assistant Accounts Officer deputed in the circle is to assist the SE in all financial
matters.
The main executive unit of the department next to circle office is the divisional
office coming under the control of an Executive Engineer. He has to manage
overall execution of all the projects assigned to him. All divisions have
subdivisions under them who are controlled by Assistant Executive Engineers. The
Executive Engineer is responsible for proper execution of all works in his Division
and also in guiding and controlling the subordinate officers with regard to
execution of works, site investigation, designs, estimates, billing and payments,
etc. He has authority of sanctioning estimates and entering into contracts within the
powers delegated to him. As drawing and disbursing officer of the division all
payments for works, supplies and services is made by the Executive Engineer. The
Executive Engineer renders prescribed financial accounts to the Accountant
General every month or as prescribed by the AG. The Divisional Office has three
branches in the office besides a quality control cell, viz. drawing branch, accounts
branch and establishment branch. The Executive Engineer is assisted by a
Technical Officer of the rank of an Assistant Executive Engineer and controls all
branches of the division including quality control cell. Accounts section is headed
by an Assistant Accounts Officer whereas the establishment section is managed by
a Head Assistant/ Junior Assistant in offices where such an officer is posted with
necessary supporting staff. The Technical Officer to Executive Engineer peruses
and submit all files to the Executive Engineer for final orders.
8
1.1.6.1 Stores
All divisions shall have stores under A.E Stores supported by a store keeper with
overall control of the concerned Executive Engineer.
CHAPTER - 1
detailed project reports, conducting site investigation and take all steps
necessary to ensure that all works under the charge of subdivision are properly
executed. He needs to maintain and render accounts as prescribed in the rules and
orders in force.
The lowest executive unit of the organizational setup is the sectional level office
under the control of an Assistant Engineer/ Junior Engineer whose jurisdiction may
Externally aided projects and specialized projects are under the Chief Engineer
(projects). Necessary technical and other staff, as per the requirement, supports
the Chief Engineer. Functions of the Chief Engineer is to be decided as per the
requirement of the project.
9
1.3.1 Repairs of Vehicles and Machineries
The repairs and maintenances of all the vehicles and machineries is attended to in
consultation and with the approval, wherever necessary, of the Department. The
concerned Mechanical Divisions to conduct fuel consumption testing, estimates for
repair and maintenance, work supervision for departmental vehicles, inspection
and issue of fitness certificate for road construction equipments of contractors,
work supervision for repair and maintenance of road construction equipments, road
roller, refrigerators, chiller plants HVAC, Air conditioners etc. They conduct
valuation of vehicles (also for scrapped vehicles), recommendation for
condemnation etc.
PWD ENGINEERING MANUAL-2020 CHAPTER - 1
The PMGSY wing of the Department shall deal with planning, project preparation,
construction, maintenance of roads and bridges of rural and urban area works as
per the guidelines of MORD, GOI. It has its headquarters in the both regions of
Jammu and Kashmir. Each is under the control of a Chief Engineer and shall have
same setup as mentioned under clause 1.1.3
10
Chapter 2
General
The duties and responsibilities of the officers of the department are given below.
CHAPTER - 2
As regards other officers, they shall continue carrying out such duties and hold
such responsibilities, as at present, based on existing rules, orders of superior
officers and or conventions until they are modified.
In addition, the following are considered as part of the duties of every officer of
the department.
1. Every officer to, if called upon by his superior officers, carry out as a temporary
measure, in addition to his duties and responsibilities, those of another officer
11
12. PWD Officers to oversee sufficient environment protection arrangements are
strictly observed in the office premises as well as at work sites.
13. Every officer in charge of project preparation and execution to oversee that
minimum disturbance is caused to individuals or community in terms of loss of
physical assets, access and livelihood.
14. If there is obstruction in the discharge of duties of any officer by an outsider,
He/she to seek legal redressal/ help of the police to discharge his duties without
interference.
15. All officers to guide and control the work of their subordinates. In case of any
disobedience, malingering, insolence, etc on the part of the subordinates, action as
warranted under service rules to be followed.
CHAPTER - 2
1. Provide Technical Guidance for ensuring both quality and progress of work.
2. Ensure co-ordination of activities of different wings of the department.
PWD ENGINEERING MANUAL-2020
12
2.3 Chief Engineer
It is the responsibility of Chief Engineer to ensure that the functions relating to his
wing are carried out efficiently. For this purpose, he requires to arrange to:
CHAPTER - 2
to his wing.
6. Inspect major work sites and works which require his guidance or instruction,
record the comments in the work spot order book and circulate the inspection note
to all concerned for follow up action.
7. Have a proper assessment of the requirements of essential items of stores and to
have them procured, stocked and distributed according to necessity.
8. Timely allot the funds under various heads as per budget allocation to the various
divisions.
13
24. Report to Government on old curiosities, relics, coins, minerals and any other item
of archaeological importance found on excavation any ancient masonry or other
old work of interest be opened up, or any religious edifice or relic be involved in
removal or destruction in the execution of a work
25. To conduct annual administrative inspections of circle and divisional offices.
Besides other things the administrative inspection team shall specifically ensure
that the records of the offices are maintained and are in safe custody. The team
shall also ensure that the digitization of records is in place and in absence of the
same shall recommend strong punitive action against the erring officers/officials.
26. To ensure mutation of revenue documents in favour of the department in case of
land/ other properties purchased by the department for road widening, establishment
of offices, etc.
27. Participate in meetings of Government tender committee, Chief Engineers‘
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
14
etc to record comments in the work spot order book and circulate the inspection note
to all concerned for follow up action.
7. Checking expenditure against budget grant as a subordinate controlling officer and
taking timely steps to move for re-appropriations, surrender of funds or
supplemental grant as may be necessary.
8. Ensuring that sanctioned staff is made available in the various offices etc. under his
jurisdiction as per rules.
9. Annual Inspection of the Divisional offices under his jurisdiction with a view to
ensure that the system of work in the Division is in place. He shall also specifically
ensure safety and instant availability of official record and digitization of the same.
He shall also recommend punitive measures in case of deficiency in maintenance
CHAPTER - 2
or safety of office record. The inspection shall also cover various aspects of the
questionnaire given as Appendix 200A and the same forwarded to the concerned
Chief Engineer. He shall also conduct technical audit in files in respect of all
Divisions under the circle every year and randomly check the bills finalized during
previous financial year.
10. Controlling matters connected with the establishment within his delegation such as
leave, transfers and postings, promotions, disciplinary action etc.
11. Collecting, scrutinizing and coordinating all necessary information for the
preparation of budget estimates of the circle under his jurisdiction.
12. Giving technical advice or opinion on matters within his jurisdiction referred to him by
The Executive Engineer is responsible for proper execution of all works under his
charge. For this purpose, he shall take timely action for the following:
1) Ensure that project reports (PPR/DPR) are prepared as per the relevant guidelines
with proper surveys, data, design, estimation, project execution schedule, etc. and
get the same administratively approved from the competent authority.
2) To ensure that concerned AEE has checked the correctness of proposals at the sites
during scrutiny of estimates and adequacy of provisions and give instructions
wherever required.
3) To move and obtain possession of land required for execution.
15
4) Invite tenders as per rules and to make contract arrangements.
5) To forecast and take steps to procure required materials and tools and plant for
meeting departmental obligation in contract work.
6) To provide adequate staff as per the operational needs of the Division. To
supervise and manage these staff to ensure that they carry out the duties adequately
and in a professional manner
7) To inspect works during execution and ensure that the good construction
practices are followed as per standard codes of practice. Quality control checks
are done as per the codal requirement of the work. He is to ensure that the
project is being strictly executed as per the time line of the project
implementation schedule.
8) To arrange periodical payments and watch expenditure done on the project.
9) To deal with such other matters as may be found necessary for proper execution.
10) To submit annual proposals for development or new construction, maintenance or
repair works under his jurisdiction with all necessary information based on the
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
Budget Manual.
11) To assess progress of works in monthly reviews. His observations shall be
recorded in the minutes which shall be forwarded to all subordinate officers and
senior officers as well.
12) To consolidate progress report of works in his division and forward to the Chief
Engineer and Superintending Engineer before 05th of every month.
13) To priorities works in his jurisdiction at the start of the financial year
14) To prepare the annual works programme ahead of the time and get the same
approved much in advance so that execution of works is started on the onset of
new financial year.
15) To ensure that the concerned AEE has finalized and approved materials, mix
design, job mix formulae, etc.
16) To visit sites and check execution of works frequently.
17) To record comments in the work spot order book and circulate inspection note to
all concerned for follow up action
18) To keep on record & update from time to time basic documents of property
rights of the govt./department i.e., land plans & land records including land
given on lease to private parties or corporations and govt. level approved lease
proposals & lease agreements.
19) To check the logbook of the equipments, machineries, plants and vehicles.
20) To report to the CE on old curiosities, relics, coins, minerals and any
21) other item of archeological importance found on excavation of any ancient
masonry or other old work of interest be opened up, or any religious edifice or
relic be involved in removal or destruction in the execution of a work.
22) To submit initial social assessment, check list along with all proposals for
works to be reviewed by the social cell (preliminary project report).
23) To obtain clearance from social cell for all categories of A and B wherever land
acquisition and displacement of people is involved, prior to execution of works.
24) To facilitate preparation of Land Acquisition Plan in co-ordination with Revenue
Department.
25) Executive Engineer must ensure that no tendering of works is done before getting
encumbrance free land for a project.
26) To prepare annual requirements of instruments based on the shortage arising either
from inadequate supply originally or from some of the available instruments
being in disorder in divisions, subdivisions and sections.
16
.
27) To propose disposal of the plants at the place or where it is transferred and to
conduct auction as per sanction received from competent authority
28) To inspect major buildings /structures periodically under his charge.
29) He shall be responsible for the proper maintenance and upkeep of all structures
under the maintenance charge of the division. In particular, he shall see that.
a. The structures are systematically and carefully inspected by himself or through his
subordinates particularly vulnerable portions thereof.
b. Timely action is taken to carry out essential works to prevent deterioration.
c. Regular maintenance works are carried out at the appropriate time.
30) As the disbursing officer of the department in regard to works, supplies and
services under his charge, he has to exercise proper control over the expenditure on
CHAPTER - 2
these items in accordance with the rules and orders in force and render proper
accounts for the same to the Accountant General in the prescribed manner. His
responsibility in this regard is detailed in the J&K Public Works Account Code.
31) The Executive Engineer to exercise administrative control over the entire
establishment of his division and regulate the establishment expenditure in
accordance with rules and orders in force and to conduct periodical inspections of
Sub division offices under his control at least once in a year with a view to see that
the administration of the subdivision is carried on properly in accordance with the
rules and/or special instructions. In case of deficiency found in the sub divisional
17
41) Ensure
that the APRs of all officers/officials in his jurisdiction are updated and
forwarded to HRD Cell annually or as and when required.
The T.O to S.E shall be of the AEE rank and shall look after all the correspondence
of the Superintending Engineer and submit relevant documents to the SE for final
orders. He shall be assisting the SE in all technical matters
18
xv) Officer shall get key materials tested so that the source of material is
approved.
xvi) The officer shall ensure issuance of relevant stationery to the subordinate staff
like, Quality control register, Daily visit register, Non compliance register, site
visit register, Material on site register (in case of departmental works) and
works register.
xvii) The officer shall ensure that the JE Incharge of works has established a
mechanism of good construction practices at site.
xviii) A laboratory as required at the site has been established by the contractor as
per agreement/ guidelines and is functional.
xix) All the tests are regularly done at the site and reports are being entered in QC
register which shall further be uploaded on the official online portal
JKPWDOMS.
xx) To check measure all concealed items of work and in addition 100% value
of item of each work which are not concealed, and measured by Assistant
Technical Officer to the Executive Engineer (TO to Exen) shall assist Executive
Engineer in technical matters& also associate in the tendering process in the
division. He shall also assist the Executive Engineer in issuance of safety
certificates of bridges, culverts and buildings on regular basis which will be
submitted to chief office through circle office.
2.10 Assistant Engineer
1 AE shall do setting out of works as per standard good practices of engineering and
ensure that works are carried out according to approved plans.
2 Forecasting and reporting the requirements of materials, tools and plant
etc. required for works sufficiently early so that they are arranged and supplied in
time.
3 Scrutinizing contractor's bills and recording accounts of materials, if any, issued for
works.
4 Supervising the progress of works and taking steps to remove bottle necks, if any.
5 Ensuring, in the case of contract works, that all the conditions of contract are
properly observed and taking appropriate action if any of these are violated.
6 Taking necessary steps for ensuring the effective execution of all works.
7 To keep and maintain of structures under his charge.
8 Survey, Investigation and collection of all field data necessary for construction of
new works or alterations and additions to existing works or maintenance of existing
structures which fall within his jurisdiction.
9 Controlling and overseeing the work of subordinate staff.
10 Ensure safe custody and rendering proper account (as per rules) of cash,
materials, scientific instruments, tools and plant etc. entrusted to him or which
pass through the section accounts.
11 Arrange urgent necessary action in case of an emergency to protect life and
government property.
20
12 Prepare and submit valuation report of buildings and structures, as required.
13 Adopt relevant quality control measures to ensure that quality of work is as per
approved specifications.
14 Responsible for carrying out field-tests correctly and timely communication of test
results to the higher authorities.
15 To implement/ communicate to the contractor in writing about instructions and
orders issued through the work spot order book by the higher officers.
16 To forward progress report in the prescribed form for all works on or before the
third day of every month
17 To ensure taking possession of land for works after the disbursement
of compensation and assistances as per the R&R policy.
18 To handover the site to the contractor or the authorized agent within specified time
CHAPTER - 2
frame after Allotment of work/agreement by the department.
19 To recommend application for extension of time of completion requested by the
contractor.
20 To submit the completion certificate along with drawings to the higher officers for
approval.
21 To take over completed structure/work from the contractor after ensuring that all
debris, balance materials, temporary construction etc., are removed and site cleaned up.
22 To hand over the completed works along with asset of completion drawings to the
concerned officer of the other department/agency.
Assistant Engineer posted in the Quality Control Cell of the divisional offices shall
assist the Executive Engineer in checking the quality of works at various sites.
They shall also issue quality control certificates which shall be entered in the
Quality Control Register (QCR) at the site for uploading the same in JKPWDOMS
for making the work eligible for payment.
The officer is under the direct control of Chief Engineer and shall be responsible
for all administrative matters in general and is responsible for the following:
1. Maintaining the administrative discipline of the direction office.
2. Assist the Chief Engineer in all administrative and personnel matters of the
direction office.
3. Processing and disposing of all the correspondence marked to him/her by the Chief
Engineer/ Technical Officer to the Chief Engineer.
4. Ensure safe custody of documents and other valuables entrusted to his/her care.
21
5. To dispose off papers of routine nature.
6. To organize and distribute work in the headquarters unit in respect of subordinate
staff.
7. To conduct fortnightly review of the "Register of Establishment Audit objections"
and to conduct monthly inspection of the "Register of Draft Para".
8. Organise administrative inspection of all offices in the P.W.D. as per directions of
Chief Engineer and forward reports with review thereof to the respective Chief
Engineer.
CHAPTER - 2
22
event of violation, the engineer in charge shall report the matter in writing to the
higher authority immediately.
xiii) Take charge of unserviceable dismantled materials obtained during the execution
of the work and arrange for their disposal in accordance with the standard
procedures.
xiv) The Engineer shall maintain and keep following registers/ docs always available
at the site
a). Spot Order Book, b). Site Visit Register,
c) Works Register,
d) Copy of Detailed Project Report (DPR) .
e) Copy of allotment with BOQ
xv) Verify bills submitted by the contractor and ensure all the supporting documents
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
viz, QC certificates issued by the Quality control team of the division, geo
tagged Photographs (Soft copy) and other requisite documents.
xvi) Carry out all instruction received from higher offices from time to time.
xvii) Plot the cross section and longitudinal section sheets and compute quantity of
earth work.
xviii) The Junior engineer being the custodian of the road shall at all times ensure
safety of the roads under his jurisdiction. In case of any unlawful activities, like,
unauthorized road cut, encroachments on road, government land, bridges, etc he
shall immediately put all his efforts to stop the violation and report the matter in
writing to the Assistant Executive Engineer / Executive Engineer.
xix) To have regular vigil over the avenue plantation and other road furniture, the
engineer shall ensure proper upkeep and safety of the same.
xx) Junior Engineer upon transfer shall ensure that he has closed all his/her works,
duly recorded on respective registers / M books signed by him and checked by
AEE, and shall handover all records to his immediate officer.
xxi) Besides routine duties JE shall also frame rent assessment and valuation of
structures as per the direction of the senior officers.
xxii) To affix signature on all documents and record prepared by Junior engineer.
24
b. Head Computer
A head computer shall be in the Chief Engineer‘s office who will be well-
versed
/ certified with AutoCAD and shall carryout the following duties.
1. Prepare drawings based on instructions given to him by higher officers.
2. Prepare prints/tracing of drawings.
3. Plot survey work based on field data furnished to him and mark contours in survey
drawings.
4. Check plotted sections and surveys received from subordinate officers/
Subdivisions with field book entries including checking reduction of levels.
5. Calculate quantities of various items of work involved from the designs and
drawings of structures and prepare detailed estimates.
6. Prepare data for items of work based on schedule of rates, and information
received from field regarding leads and lifts involved etc.
7. Check contractor's bills with regard to the estimates received from subordinate
offices.
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
Head Draftsman/ Draftsman in PWD office shall carryout the following duties.
1. Prepare drawings based on instructions given to him by higher officers.
3 Prepare tracing of drawings.
4 Plot survey work based on field data furnished to him and mark contours in survey
drawings
5 Check plotted sections and surveys received from subordinate officers with field
book entries including checking reduction of levels.
6 Calculate quantities of various items of work involved from the designs and
drawings of structures and prepare detailed estimate.
7 Prepare data for items of work based on schedule of rates, and
information received from field regarding leads and lifts involved etc.
8 Check contractor's bills with regard to the estimates received from subordinate
offices.
9 Verify issue of materials against requirement as per data in contractor‘s bill.
10 Prepare indents for departmental materials, tools and plant etc.
11 Prepare tender schedules and agreements.
12 Tabulate tenders.
13 Prepare draft letters and reports.
14 Carryout any other work that may be specifically assigned to him by Executive Engineer
and other superior officers.
Each PWD office has technical, financial and establishment wings. who have the
following duties:
25
2.15.1 Technical
The Technical branch in a PWD office shall be responsible for taking action on the
following,
1. Approval of structural designs.
2. Scrutiny of estimates: Any modification in the provisions in an estimate received
from the subordinate office shall be made only after the specific orders of the head
of the office. Scrutiny of estimate and issuing a copy of approved abstract of
estimate, data and detailed estimate to lower level office for execution.
3. Issuing Administrative and Technical Sanction for estimates as per prescribed
delegations. Scrutiny / sanctioning of estimates.
4. Preparation of tender schedule, tabulation of tenders, Scrutiny of tenders.
5. Submission of tenders to higher authorities.
6. Preparation of agreement documents.
2.15.2 Finance.
26
2.15.3 Establishment
The head of concerned branches shall forward files of works entrusted to them to the
head of the office through technical officer.
Agreement for works executed in Division and Circle offices shall be handed over
to the A.A.O of the division and the circle office respectively for safe custody who
shall maintain a separate register of agreements.
d. Electrical Wing
1. Scrutinizing all electrical design and drawings and submitting to Chief Engineer for
approval
2. Conducting site inspections and discussions with officials of user department,
assessing the requirements, incorporating any omissions, etc. for finalizing the design
and drawings and submitting to Superintending Engineer Electrical
3. Overall administrative and technical control of the electrical lab
4. Conducting necessary test with support of sub-ordinate technical staff to determine
the quality of various electrical materials
5. Conducting / supervising necessary tests within /outside the lab if such facility is not
available in the lab for giving approval to electrical materials
6. Issuing certificates for the materials tested
7. Recommending quality control measures in electrical works and
conducting inspection of work sites if necessary
8. Preparing inspection notes and submitting to Chief Engineer civil
9. Conduct training to the officials of PWD electrical wing.
10. Keeping in safe custody the samples of electrical materials approved by the
appropriate authority.
11. Executive Engineer Electrical for confirmation of material supplies or till the next
set of materials is approved by the authority He shall compare the samples in case
of dispute and conduct random checking whether the supplied materials are in
conformity with the standards and samples produced.
27
12. Shall be responsible for any other matters concerning electrical design, drawing,
quality control and testing assigned to him
13. Verifying the quality of different makes of materials.
14. Inspecting all major works in every district.
15. Sanctioning of all estimates within delegated powers.
16. Issuing instructions for preparation of annual Indents for materials, Tools and Plants
etc
17. Making payment to Electrical works
18. Ensuring disposal of all technical issues from subordinate staff by devising a
mechanism to clear all the correspondence in a timely manner at all levels.
19. Taking initiative in suggesting technical improvements and energy conservation
measures to CE.
20. Any other duties assigned to him by the superior officers
CHAPTER - 2
2.16.2 Assistant Executive Engineer, Electrical
The general responsibilities defined for the Assistant Engineer (Civil) whichever is
applicable will apply to the Assistant Engineer (Electrical) also. In addition, he shall be
responsible for:
1. Guiding and controlling of the work of the electrical staff attached to the section.
2. Arranging rectification of defects reported to him by the field staff and restoring supply.
3. Guiding in proper maintenance of installations and safety measures.
4. Periodical testing of installations, noting the test readings and making timely action
for rectification of defect, when the test readings are not within the safe limits.
5. Preparing and giving instruction for the preparation of estimates for electrification
works and verifying the adequacy in conformity with standards &norms.
6. Inspecting works in progress and giving necessary instructions
7. Taking measurements of all works and preparation of bills.
8. Carrying out any and other duties that may be assigned to him by his superior
officers.
28
2.16.4 Junior Engineer, Electrical
His duties shall include:
1. To supervise and record measurement in M.Book all under ground works like cable
laying, earthing, concealed pipe etc and work within the TS powers of Assistant
Engineer.
2. Inspection and verification of inventory register and ensuring that it is maintained
properly and entries are made up to date.
3. Overall supervision of the work in the section
4. Arranging shift duty of the staff and allocation of work to subordinates.
5. Maintaining Material at Site Accounts.
6. Security of the inventory Register.
7. Marking of points of works, supervision of works and taking required follow-up
action.
8. Periodical inspection of installation.
9. Preparation of estimate of works.
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
10. Keeping watch over the progress of work and reporting to the Assistant Engineer,
Electrical, about the same.
11. Checking the quality of materials on arrival at site and at the time of usage on work
to see that they comply with specifications.
12. Checking the quality of work under execution and checking whether the work is
executed as per agreement condition.
13. In the event of violation of any of the items referred as (11) and(12)
above, reporting the matter to Assistant Engineer/ AEE, Electrical, in writing, then
and there.
14. Maintaining work spot order book as per rules and keeping an account of the
daily usage of departmental materials on the work.
15. Taking charge dismantled materials obtained during the execution of work and
arranging for their disposal as ordered by higher officers.
16. Keeping account of Tools & Plant, if any, issued to Contractor.
17. Attending shift duty including holidays when posted in generating station/
substation.
18. Any other duties that may be assigned to him by his superior officers.
29
e. Design, Inspection& Quality Control (DIQC)
CHAPTER - 2
those referred to by the government.
4. Give timely instructions and guidance to subordinate officers on various matters.
5. Timely allot funds under various heads as per budget allocation to the various
divisions.
6. Exercise administrative, financial and technical powers delegated to him.
7. See that the rules regarding accounting and financial control at various levels are
properly enforced.
8. Prepare details for answering legislative assembly questions, submissions and
The S.E shall be assisting the chief Engineer in all administrative and technical
matters. He shall focus on developing an effective management system of clearing
and vetting of designs in a stipulated time frame. The projects shall a standard time
limit of 45 days from the date of receipt of the project. However, the intending
departments shall clear all the observations within overall time period of 15 days.
He shall also develop a flow chart for effective management system so that the
designs are cleared in a stipulated time frame. In case of designs having deficient
information the same shall be shifted from this flow chart and placed on a separate
plate form.
He shall approve the designs submitted to him by the divisional offices.
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
He shall also develop various design standard publications which can be used as
already recknor in the field and save considerable time in preparing the designs and
getting them vetted by concerned authorities.
The officer shall also coordinate the concern organizations like IRC, BIS etc. about
the field and design observations for incorporation in the relevant codes.
The officer shall also setup teams for development of standard software‘s for
framing of various standard PPRs the same are being used by different
departments for preparation of project reports, this will ensure uniformity in project
preparations.
Any other duty assigned to him by superior officer.
2.17.3 Executive Engineer
The Executive Engineer after receiving the designs from the S.E shall peruse the
same and assign it to AEE for checking the concept, methodology, and design
calculations of the same.
The Executive Engineer shall specify the date of completion by which AEE shall
have to submit the design depending on the quantum of work involved. The EE
shall constantly monitor the process of designing/ vetting by the AEE. He shall
ensure that the designs are not held up due to delays by the officer or by clearing of
the observations by the intending department.
In Case of delays due to clearance of observations or non cooperation of the
intending department the matter shall be immediately conveyed to the higher
authorities for a resolution by the DCW. However, the process should in no case
go beyond the standard time of 45 days. In case of projects going beyond the
deadline of 45 days the same shall have to be supported with explanation for the
delays.
He should update all the software available with the department and make them
available to the subordinate staff. He shall also keep an eye on latest developments
on new software‘s and new trends and techniques in the design. And make efforts
to keep the same available in the divisions.He shall also ensure that the latest and
updated codes having legal validity are followed in the vetting of designs.
Any other duty assigned to him by superior officer.
2.17.4 Assistant Executive Engineer
AEE shall on receipt of projects have a holistic perusal of the same so that the
proposals submitted by the intending departments are qualified on the basis of the
parameters of the project. He shall cross check all the design as per the latest
relevant codal procedures.
31
He shall also ensure the validity of the additions of the relevant codes of practice
so that the codes deleted from a specific date are not followed its legal validity
period.
He shall ensure that the projects are completed within their stipulated time frame.
The officer shall inculcate sense of scientific temperament in his subordinate team
in dealing with the designs so that the engineers working under him develop into
designers of future.
Any other duty assigned to him by superior officer.
A.E shall work as an Assistant with AEE and shall carry out works assigned to
him. The A.E shall do any other official duty assigned to him by superior officer.
32
2.18.2 Deputy Research Officer
8. Submitting quarterly progress report of the tests and research studies conducted by
the RRMTL to the R.O.
9. Inspecting various sites, where investigations are in progress and
issuing necessary instructions.
10. Ensure the collection of all necessary data required for the design form the
intending department .
11. Initiate actions for applied research.
12. Assist the R.O in other matters entrusted to him.
13. Any other duties assigned by the superior officers
Superintending Engineer shall head the Road Safety Cell of the department.
He Shall be supported by two executive engineers, 01 at Jammu and 01 at
Kashmir.
33
It shall be the responsibility of the Road Safety Cell to coordinate the road safety
activities implemented by the concerned executing divisions. However, the
implementation of road safety works shall be done through the regular divisional
offices. All the Engineers of cell should be imparted sufficient and regular
trainings on the subject, at least two engineers of the cell shall be trained as
Certified Road Safety Auditors.
The responsibilities of S.E Road safety cell shall be as under
1. He shall be controlling officer for the Central Road Safety Cell under the overall
control of Chief Engineer DIQC
2. Maintain and implement road safety policy and procedures of road safety and
audits.
CHAPTER - 2
3. Conduct road safety audit by ensuring whether the roads are confirming to
standard road safety audit requirements
4. Direct the Executive Engineers / field officers regarding road safety measures.
5. Coordinate with other agencies like traffic police, trauma care centers and motor
vehicles department
6. SE, Road Safety Cell shall liaise and correspond with Road Safety Authority at
UT/state level.
7. The team shall audit all the roads as per road hierarchy within a specified period of
time as desired by CE, DIQC/ DCW.
34
8. He shall monitor the work to ensure proper implementation of road safety audit
recommendations by respective executing agencies.
9. He shall ensure training of all the engineers working in the division for road safety
and road safety audit.
10. The Executive Engineer Road Safety shall issue road safety clearance certificate to
the concerned divisions on the recommendations of road safety auditors after
which only the final payments shall be released to the firm/contractor by the
divisions/executing agencies.
11. The E.E shall formulate teams for conducting studies at accident-prone
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
35
2.20 Ministerial Staff
2.20.1 Section Officer
Duties as per Manual of Office Procedure.
2.20.3Senior Stenographer
CHAPTER - 2
2.20.5 Junior Stenographer
Junior Assistant shall carryout any or all the ministerial duties as per Manual of
Office Procedure.
2.20.9Senior Superintendents
36
2.21. Chauffer/ Driver-I/ Driver-II
Their duties will include:
1. Drive the vehicles carefully with in the prescribed speed limits observing all the traffic
regulations.
2. Keep the vehicles in road worthy condition. This will include washing and cleaning
of vehicles.
3. Check water levels in radiator and battery, oil level in crankcase, fuel level in fuel tank
and tyre pressures every day before the vehicle is taken out.
4. Once a fortnight check oil level in gearbox and brake fluid.
5. Report any mechanical fault or damage immediately to controlling officer or the
officer in-charge.
6. Attend to routine maintenance as prescribed such as topping up of oil, filling
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
radiator, cleaning of oil and fuel filters, inflating tyres, applying grease where
required, etc.
7. When the vehicle is taken out for servicing point out any items needing special
attention and be available at the servicing station or work-shop to see that servicing
is done properly.
8. When the vehicle is taken for maintenance or for special repairs, assist in the
completion of the repairs or carry out such other jobs as are ordered to be done by
the officer In- charge of the vehicle.
9. In case of accidents the driver shall report the matter to the nearest police station
and the officer in charge of the vehicle and abide by instructions of the police in
regard to further movement of the vehicle.
10. Be in charge of the tools and spares of the vehicle entrusted to him.
11. Keep account of materials like fuel, lubricating oil etc. entrusted to his care.
12. Maintain log books as prescribed.
13. Take order from the officer in charge of the vehicle in regard to trips to be made,
passengers or materials to be carried etc.
14. Intimate in-advance the date of renewal of tax, insurance, pollution test, fuel tests
etc.
15. They will also carry out any other duties that may be specifically assigned to him by
their superior officers.
2.22. Peon:
Duties as per Manual of Office Procedure
37
ii. To ensure that the schedule for preparation of budget is adhered to by the
Department and the budget is drawn up according to the instructions issued by the
Finance Department from time to time;
iii. To scrutinize budget proposals thoroughly before sending them to the Finance
Department
iv. Release of funds timely under Capex/Revenue expenditure budget,
v. To see that complete departmental accounts and to ensure in particular that the
department not only maintain accounts of expenditure against Grants or
Appropriation directly controlled by it, but also obtain figures of expenditure
incurred by the subordinate offices so that the department has complete month-to-
month picture of entire expenditure falling within the jurisdiction;
CHAPTER - 2
vi. To watch and review the progress of expenditure against sanctioned grants
through maintenance of necessary Control Registers and to issue timely warnings
to controlling authorities where the progress of expenditure is not oven;
vii. To ensure the proper maintenance of the Registers of liabilities and commitments
as required under the state financial/Services Rules to facilitate realistic
preparation of budget estimates timely surrender of anticipated savings;
viii. To screen the proposals for supplementary demands for grants;
38
d. The financial implications as are involved spelt out in detail giving out the
basis of calculations as well;
e. If the cases pertain to the department rules and regulations, they are examined
in the light of relevant provisions of the rules and regulations and copy of such
rules and regulations is placed invariably in the departmental file;
f. The specific issue on which opinion/concurrence of the Finance Department is
needed is framed in an unequivocal language and mentioned in the
departmental noting;
g. The department continuously updates its rules and regulations and also keeps
updated copies of the J&K Civil Service Regulations, Financial Codes, and
Budget Manual etc. and refers to them before making out a performance to the
Finance Department.
delegated powers;
b. To ensure that the schedule for preparation of budget is adhered to by the
Department and the budget is drawn up according to the instructions issued by
the Finance Department from time to time;
c. To scrutinize budget proposals thoroughly before sending them to the
Administrative Department
d. Release of funds to the Subordinate offices after approval from Chief Engineer.
e. To see that complete departmental accounts and to ensure in particular that the
department not only maintain accounts of expenditure against Grants or
Appropriation directly controlled by it, but also obtain figures of expenditure
incurred by the subordinate offices so that the department has complete month-
to-month picture of entire expenditure falling within the jurisdiction;
f. To watch and review the progress of expenditure against sanctioned grants
through maintenance of necessary Control Registers and to issue timely
warnings to controlling authorities where the progress of expenditure is not
oven;
g. To ensure the proper maintenance of the Registers of liabilities and
commitments as required under the state financial/Services Rules to facilitate
realistic preparation of budget estimates timely surrender of anticipated savings;
h. To screen financial part of the proposals for supplementary demands for grants;
i. To identify in particular specific savings in cases of creation of posts and to
maintain a register for this purpose;
j. To scrutinizing proposals for delegation of powers to subordinate authorities;
k. To keep himself closely associated with the formulation of schemes and
important expenditure proposals from their initial stage;
l. To associate himself with the evaluation of progress/performance in the case of
projects and other continuing schemes and to see that the result of such
evaluation schemes and to see that the result of such evaluation studies are taken
into account in the budget formation;
m. To watch the settlement of audit objections inspection, reports, draft audit
para‘s etc.
39
n. The specific issue on which opinion/concurrence of the Finance Department is
needed is framed in an unequivocal language and mentioned in the departmental
noting;
o. The department continuously updates its rules and regulations and also keeps
updated copies of the J&K Civil Service Regulations, GFR/Financial Codes, and
Budget Manual etc. and refers to them before making out a performance to the
Administrative Department.
The Divisional Assistant Accounts Officer‘s main function shall be to assist the
Executive Engineer in exercising financial control over the transactions of the
Division and in maintaining accounts of the transactions correctly in accordance
with rules in force.
CHAPTER - 2
The Divisional Assistant Accounts Officer‘s t responsibilities shall include:
2.23.3 Accountant
40
2.24 Miscellaneous
etc.
5. In the case of rest houses not provided with running water, see that water
required is made available in the bath rooms for occupants.
6. See that bed linen, crockery, cutlery etc. are kept in clean and usable condition.
7. Provide sufficient linen for the use of occupants of each room according to
prescribed standards.
8. Where gardens exist see that the garden is watered, trimmed and kept clear of
rubbish.
9. Maintain the occupation register and see that every occupant fills up the
required columns on arrival and before leaving.
10. Collect rent due from the occupants and send the collections together with
copy of the occupation register to the concerned officer every 15 days or at such
intervals as prescribed.
11. Where reservations are ordered by the Executive Engineer ensure that
rooms are kept so reserved without being allowed to be occupied.
12. Keep account of furniture, linen, crockery and cutlery and any other item
entrusted to his charge and make periodical checks to see that they are all
available.
13. Arrange washing of linen, bed clothes etc, and keep account of item so
arranged to be washed.
14. Where the rest house is provided with catering arrangements, arrange supply of
good food as prescribed to the occupants at approved schedule of rates. This
schedule of rates shall also be exhibited in public.
15. Control the work of such subordinates in the rest house as are placed under his
charge and report to superior officers, cases requiring sanction of appointment of
substitutes, institution of disciplinary proceedings etc.
16. See that unnecessary fans, lights & Air Conditioners are switched off at the
appropriate time and the use of water and electricity economically controlled
without any inconvenience to occupants.
17. Bring to the notice of the Assistant Engineer in charge, all repairs and
maintenance required for buildings and installations, without delay.
18. They shall also carry out any other duties that may be specifically assigned to
them by their superior officers.
41
2.24.2 Drivers of Road Rollers
CHAPTER - 2
are necessary and are directed to be done.
5. Attend to routine maintenance as prescribed such as topping up of oil applying
grease, where required etc.
6. Whenever the rollers are left at roadside after the day's work it is his duty to see
that the danger light is put in front of the roller. This is to avert the chances of
other vehicles colliding against the roller.
7. When the roller is taken for maintenance or for special repairs, assist in the
completion of the repairs or carry out such other jobs as are ordered to bed one
by the officer under the control of the roller.
42
2.25.4 AssistantExecutive Engineer, Mechanical
In addition to the duties as per section 2.8 whichever is applicable he shall be
responsible for:
1. Testing and issuing fuel consumption certificates of vehicles.
2. Preparation of estimates for repair and maintenance works and issuing
essentiality certificates for vehicles of all Government departments
3. Supervision of works and submitting of bills for repairs and maintenance.
4. Maintenance and repairs of all construction equipments of PWD
5. Supervision of works for repair and maintenance of refrigerators, HVAC chiller
plants, air conditioner set etc.
6. Valuation of vehicles including confiscated vehicles
7. Recommendation for condemnation of vehicles/machineries.
8. Attending the Condemnation Board meetings of Fire Force vehicles.
2.25.5Assistant Engineer
He shall have duties similar to clause 2.10 whichever is applicable
PWD ENGINEERING MANUAL-2020 CHAPTER - 2
2.26 Powers
The powers delegated to the various officers of the department in regard to
administration, technical and financial matters shall be used wisely and carefully. It
cannot and shall not be a weapon for implementing of work in piece meal evading
sanctions from higher authorities. No work may be started before a proper estimate
for it has been prepared and sanctioned by the competent authority, unless it is so
started strictly in accordance with a special order of Government or some specific
codal provisions or departmental rules. The nature and date of sanction shall be
clearly recorded in the bills relating to the work. It is the responsibility of the
implementing officer and officer who is passing the bills for the work, to see that
the respective work is executed underwritten orders of competent authority. They
shall also check and ensure that an Administrative Sanction and Technical
Sanction shall precede a tender from competent authority and sufficient funds
are provided in the budget for the respective work. All the controlling officers shall
ensure that no tenders are initiated unless administrative approval and technical sanction
has been accorded by the competent authority and funds are available in the budget. Any
violation of these principles of financial propriety shall be constraint as irregularity and
action as warranted under rules shall be initiated against the delinquent officers
including concerned DDO .
43
CHAPTER 3.
The Public Works Department of J&K employs over 16341 persons directly and
gives employment to over 80,000 persons indirectly. Being a service department,
the officers and staff of PWD shall be morally committed to the society and shall
uphold the values of the department. This shall be reflected always in the quality of
works, integrity and demeanor.
CHAPTER - 3
This cell shall be under the overall control of Development commissioner works
which shall coordinate with HRM wing as per Administrative Department.
44
3.5 HRIS and ID cards
The personal information of all members of staff shall be entered in to the
Human Resource Information System (HRIS) of the department JKPWDOMS
(under development in the department). The DDO shall ensure the information
regarding his office has been uploaded correctly. Once details uploaded the
members can download ID Cards
All members of staff shall possess the ID card at all times while on duty and shall be
displayed/ produced on demand. This card should be surrendered in the event of
discharge/retirement from service.
3.7 Rules
The quantum of work handled by the officers in Department may vary from time to
time and it is necessary that suitable norms shall be fixed, so that the staff strength
of the Department be augmented, reduced or arranged according to
requirements. In case of specialised works, new posts/ units shall be created. The
HR cell shall assess all such requirements and submit proposals for creation/
deployment/ abolishment of post to the Development Commissioner works.
The government will fix, from time to time, such norms for the various units under
the Public Works Department.
45
3.9 Disciplinary Actions/Misconduct
CHAPTER - 3
question.
3.11 Miscellaneous
3.11.1 Dress Code
All officers must present themselves in neat and clean attire. Those officers who
are required to wear a uniform at work must ensure that this is kept neat and clean.
3.11.3 Confidentiality
All information made available to employees in the course of their employment with
the department is to remain highly confidential. An officer shall not issue or
make any public statement concerning the public works department‘s operations or
release information on any operational matter.
3.12 Training
46
infrastructure Development Plan is relating to capacity building in the PW (R&B)
department for efficient implementation of the development programme. With ever
increasing interaction and mutual dependence of various stakeholders viz. Road
Agencies, Contractors, Consultants, etc. for the service and product delivery, there
is all-round need to enhance, develop and up-date the skills not only in technical
designs but also in project management, financial aspects, legal issues, social and
environmental aspects. There is need of skilled staff at all levels including skilled
labour, equipment operators, and supervisors, engineers with the government,
contractors and consultants. Jump in the project size has added to the complexities.
The concerned agencies dealing with the PWD are facing the challenge of rational
planning, project identification and development, efficient and transparent contract
procurement, administration, operation, and management of roads to provide good
quality of service to road users.
The main aim of training is:
PWD ENGINEERING MANUAL-2020 CHAPTER - 3
●To impart training to professionals of JKPWD at entry level and during service.
●To help engineers build up character and develop an all-round personality as
a part of Human Resource Development.
●To assist various organizations/Departments to have better infrastructure.
●To promote co-operation and foster exchange of knowledge, ideas and
experience in all the sphere of engineering among engineers in J&K
The department is committed to provide officers with the required training and
development so as to enable to perform their work more effectively and develop
their skills in line with departmental requirements. Other Human Resource
Systems shall support and synergize the training efforts.
Being a technical organization, the focus on skills training shall be based on the day-to-
day developments in the field of construction engineering. Training shall be under the
control of Human Resources Cell within the Administration wing.
Training shall focus on induction, refreshers training for present employees and
specialization for employees whose responsibilities or duties change through
advancement or Departmental transfer.
The concerned chief engineer shall decide the needs of the training under which
the personnel have to be trained. The person thus deputed will help and benefit
the Public Works Department as a whole.
All HODs shall arrange and recommend their engineering staff for regular
trainings at institutions like IAHE, CRRI, IRC etc
47
o Formulation of training courses as per the above need.
o Coordinating and finalizing training schedules for the staff.
o Publishing annual training calendar
o Engagement of permanent and temporary faculty for the training courses, as
required.
o Implementing training.
o Training feedback- this feedback, along with changes in individual performance
needs to be tracked, recorded and reviewed for modification in future
programmes.
o Periodic review of training course
1. Drawings
2. Road engineering
3. Structural components
4. Drainage
5. Bridge engineering
6. Record keeping
8. Testing of materials
9. Maintenance
11. Ethics
48
3.12.3 Refresher Courses
Refresher courses for the field staff brushes their knowledge on the subject
periodically and keep them abreast of recent developments in the field. Such
courses should be conducted on regular basis and the duration may be about a
week or less. Refresher courses may cover the subject in general and latest
techniques, machinery, new materials and state of art technology. Every
engineering officer at the level of JE and above should attend a refresher course
at every five years interval
PWD ENGINEERING MANUAL-2020 CHAPTER - 3
49
CHAPTER 4
CHAPTER - 4
ii. PWD Human Recourse Information System
iii. Contractors Information System
iv. Proposals
v. Tendering
vi. Store Procurement
Details of all the infrastructure available with the department shall be organised in
this module:
Existing road network (road gazette). The road gazette shall be incorporated in the
module and updated regularly
●Inventory of all buildings owned by the department
●Inventory of all buildings maintained by the department
●Inventory of all bridges under the jurisdiction of the Department management.
● These details shall help in proper maintenance of the assets and their management
50
4.1.2 PWD Human Resource Information System
Details of contractors/ firms based on their authorized contract cards/ pan cards:
●Personal information
●Legal Documents
●Details of contracting Card
●Bank Details
●Details of works Executed.
●Performance Certificates of the works.
●Details of works completed successfully with details like:
▪ Works Completed in time
▪ Works Completed before time.
▪ Works Completed after Time.
●Performance grading of the works executed
●Detail of works left halfway or incomplete
●Updation of the contractor with respect to latest tools, techniques and plants.
●Details of technical personnel on the rolls of the contractor.
●Details of Financial Transactions with the Department.
51
4.1.5 PROPOSALS
Details of all the works to be undertaken during the specific financial year shall be framed
online and will be hosted on the web portal which will be viewed / reviewed by higher
authorities thus making whole mechanism of technical sanction and administrative
approval online in a time saving and more transparent manner.
i) SSR shall be hosted online by DIQC Department which shall be accessible to all
the engineers of PWD.
ii) The Portal shall provide a window on which the items of work shall be automatically
imported from the SSR. The import of items shall also get the item code along with its
description, rate, etc.
iii) The quantities for the respective items shall be added in the said page which in turn
will generate the amount of each item of work.
iv) The appreciation if any, over various items of work shall be incorporated in the portal
4.1.8 PROCUREMENT
Provides the complete project planner of the works giving following details: o Stages
of the work.
o Scheduled dates of start and completion.
o Progress of work, comparing with envisaged schedule of activities pointing out lags
and leads as per CPM charts. Corrective measures to be taken accordingly.
o Quality Control Checks as per Quality Assurance and Monitoring Module.
o Project management and monitoring tracker based on CPM, PERT, etc. to be
developed
o Separate guidelines shall be formulated for creating a mechanism for timely or
early completion of works.
o Policy for recognition of engineers and contractors to be formulated and
implemented aimed at encouraging and inspiring the team, building a healthy and
positive working environment.
o Engineers and contractors achieving the targets ahead of their targeted schedules
shall be recognized and awarded suitably. This will automatically develop a trend
of timely completion of works and ultimately result in speedy constructions
thereby saving a lot of additional cost to the exchequer on account of inflation and
delay in completion time.
o Delay in completion of works shall also attract strong punitive measures
53
The department is having strong in-house quality control system which is
defined in chapter 24 of this manual.
The billing of the works shall be framed online on the basis of:
1. Allotment issued to the contractor
2. Final work done estimates
3. Progress of the work executed at site.
To be linked to the Procurement module of the works so that the departmental stores
issued to the contractor/firm are automatically adjusted in the bills.
Deductions for security deposits, taxes, etc. also to be linked for inbuilt adjustment in
CHAPTER - 4
the bills of the contractor.
Billings shall be processed only when the required Quality Assurance Grading (QAG) is
achieved in the quality monitoring module.
This will ensure transparency in the entire billing system as all the entries will be
Linked online.
4.1.12 MAINTENANCE
1. Assists in tracking and managing the maintenance part of the contract
1. Safety norms shall be followed as per the standard codal procedures issued by
BIS, IRC and other relevant organizations from time to time.
2. The safety standards thus prescribed shall be bound to be strictly followed at all
sites of execution of works in order to ensure absolute safety of men and
machinery.
3. All contractors / firms shall be bound to have safety engineers deputed at sites as
required under the safety standards/contract documents.
54
4.1.14 FEED BACK
1. An in-built system of getting the feedback from general masses which shall
automatically get generated in the Grievance Cell of the department.
2. The Grievance Cell shall filter the feedback & forward them to the stakeholders and
ensure the resolution of all the grievances within the stipulated period of time.
3. In case of grievances not being resolved at a specific level of authority within the
stipulated time frame, the grievance shall automatically get reported to the next
higher authority
4.2 Responsibilities
The responsibilities of all the PWD officers regarding the IT systems and MIS are
given in chapter 2.0.
4.3 Maintenance
Maintenance and upkeep of all the IT initiatives ranging from telecommunications/
network management to application development and data center management and
processing of PWD shall be either through AMC or utilizing the services of the
Consultants in the relevant field. Considering the security, measures for network
security including Firewalls Intrusion Detection System; antivirus/anti vandal software
to protect the servers and desktops is important and hence regularly monitored.
4.4 Functions
Key activities of JK PWD OMS:
Leveraging the tools of IT to promote productivity, communication, transparency,
knowledge management and informed decision making in all wings; thus
contributing to an image of a pro- active, efficient and customer-caring
department of Government.
Steering the formulation of a dynamic IT strategy and program for the department;
and the direction, monitoring and controlling of itsimplementation
Directing the acquisition of appropriate technology platforms, software
applications, GIS systems, video and teleconferencing systems, LANs, WANs,
and other resources related to the program, including their upkeep, maintenance,
expansion, up gradation and renewal.
Sourcing the IT related human resources of the department, through in-house
sources, to the extent available and through human resource outsourcing as
required.
Directing IT training and skill upgrading in coordination with the respective wings
with a view to creating and maintaining adequate human resources in Information
Technology in the Department.
Be responsible for data /information integrity and security, back up, disaster
recovery, redundancies, prevention of unauthorized access and implementation of
appropriate access protocols and policies.
55
Instituting a web portal management board for overseeing the functioning of the PWD
web portal.
Evangelizing the process of organizational transformation, promoting and imbibing
best of class systems and procedures in the department
website.
JKPWDRB, the PWD web portal is segregated for use of public, contractors and
the PWD officials with functions restricted to each category and transparency in
terms of information as relevant to the activities of PWD.
● All the Divisions of R&B department shall be uploading their works program for
the subsequent financial year much ahead of its commencement.
The information will be generated and consolidated at appropriate levels to enable
the department to plan in advance for preparation of DPRs, processing of
administrative approvals and arrangement of funds so that the complete
development plan is kept ready on all fronts for its execution resulting in the timely
implementation process of the plan. This will definitely eliminate all lags and
delays in execution of works in the department.
PWD shall prepare an IT strategy and shall get the approval of administrative
department. The department may develop new applications based on the so framed
IT strategy. The DCW shall consult Chief Engineers in developing PWD specific IT
strategy. Every three years, the strategy document may be revised according to the
progress achieved. General approach would be to develop centralized data bases and
distributed access through web technology. PWD shall also make use of
developments in Open Source to create system, which is free of perpetual licensing
wherever possible.
56
CHAPTER 5
CHAPTER - 5
Chief Engineers Office Circle Office Division Office Sub
Divi
sion Office
Chief Accounts Officer AAO Divisional Head Clerk
Assistant Director Accountant / Drafts man
Planning
Junior Clerk (Budget Clerk Clerk
Superintende Section (Budg
nt LD/UD Clerk ) et Section)
57
All Administrative sanctions with list of works for both plan and non-plan shall be
entered into FMS /JKPWDOMS system as per Appendix 500B & 500C. All works
shall get a project ID, as and when it is entered in the Project Management module of
JKPWDOMS. When the work is added through JKPWDOMS the project ID will be
generated. All offices shall note down the Project ID of each work and the project ID
shall be an integral part of all work related registers, reports and communications.
This will be used for payment of bills and financial monitoring through FMS.
JKPWDOMS shall use FMS data for project monitoring and tendering.
The central FMS unit shall make sure that all new plan and non-plan works are
available in the FMS for further processing.
All contractors entered into contract with PWD shall have a contractor ID. Division
Bill register from every Division shall be updated to FMS system Central FMS
unit shall prepare all necessary financial reports using this system.
PWD ENGINEERING MANUAL-2020 CHAPTER - 5
5.8 Longterm
The maintenance and data updating is an ongoing process and may require revision of
FMS and IT related database in future.
58
CHAPTER 6
6.1.1 Introduction
The main thrust of planning is to frame detailed road map for efficient use of available
resources by determining what is to be done and achieved within the given time period. It
formulates the policy to broke down the broad objectives of developmental programmes
into detailed works plan for each project by linking of costs with the resultant outcome of
investment made or to be made and helping in equilibrium between socio- economic and
governance parameters across the UT. The FMS, GIS and RMMS are tools that shall assist
the PWD in all the above policies and activities.
PWD ENGINEERING MANUAL-2020 CHAPTER - 6
6.3 Planning
59
CHAPTER 7
7.1 Budgeting
A budget is a system to control finances, provide minute details in respect of the expenditures
proposed for various programmes, enables to make confident financial decisions and meet
objectives and ensure sufficient money for future projects. It also improves decision-making
by foreseeing financial problems before they occur. Creating, monitoring and managing a
budget is key to successful implementation of projects by rendering allocation of resources
where they are needed. The annual budget proposal is based on programmes of the
department and while earmarking the funds priorities are to be fixed by the department after
analysis and assessments of the continuing works. The new works are planned only after
PWD ENGINEERING MANUAL-2020 CHAPTER - 7
ascertaining the availability of necessary fund flow to the scheme. To make budgets effective,
periodical review and revisions shall be done. This shall aid as an indicator of the revenues
and expenditure linked to each activity, moreover it shall provide for the economic, efficient
and effective use of resources required to deliver services and ensure that planning processes
are integrated with governments overall strategic and financial planning, budget preparation
and reporting processes and in accordance with applicable legislation, regulations and
policies.
The budget shall be realistic by use of historical information, i.e. the current annual
plan and previous Variable costs – electricity, water supply, petrol, fuel payments to
works including maintenance Fixed costs - items such as rent, establishment
charges, salaries etc. year‘s administration reports. It shall be based on a on a month-
by-month programme and shall include of equipments, vehicles and purchase of
stationary and other consumables, training costs, books Capital costs - purchases of
equipment, computers, vehicles and cost of works. and periodicals etc. The
government‘s overall strategic plan is presented to the Legislative Assembly before
budget and the describe the ministry's core business goals, objectives, strategies,
performance measures and are consistent with the government's strategic plan;
department must prepare proposals that: address the upcoming fiscal years targets;
The details to be furnished when submitting budget are given in the Budget Manual. All
necessary information shall be furnished in the budget estimates submitted by the
respective Executive Engineers and other Divisional Officers and the Superintending
Engineer and the Chief Engineer concerned shall scrutinize these. They shall then be
consolidated including establishment and all other expenditure in the various offices.
The Chief Engineers under the control of Buildings, Roads and Bridges branches of
the P.W.D. are the estimating officers of the department and they have to collect the
budget estimates of all the different branches viz. Roads, Bridges, Projects,
Administration, Buildings, electrical, electronic etc.
7.3. Selection of new works (Buildings)
List of new works of buildings under the administrative control of the P. W. D. shall
be prepared each year by concerned Executive Engineer and submitted to Chief
60
Engineer (concerned ) in accordance with the norms laid down in detailed project report
section of this manual so that cost arrived are at is realistic and it shall specify the
indicators for the cost arrived at based on technical inputs .This list shall be sent to
Chief Engineer with recommendations of the Superintending Engineer well ahead of
the date when budget proposals are to be sent to the Chief Engineer. In the case of
buildings for other departments of the UT the list of new building works to be carried
out by the P. W. D. during the budget year shall be prepared and finalized by the
departments concerned. This shall then be incorporated in their Part II proposals after
consulting the concerned Executive Engineer of the P. W. D. regarding cost and other
details. In the case of works where only investigation and preparation of preliminary
estimate are completed, the amount as per preliminary estimate can be noted in the
column 'estimate amount'. In other cases, where preliminary estimates are yet to be
prepared, the District Officer or head of the Department concerned shall furnish
sufficiently in advance- the requirements, site proposed etc. to the Executive
Engineer concerned in the district, who shall assess the rough cost of the work and
intimate the same to the concerned department for incorporation in the list of new
For all original works the department shall prepare and submit proposals through the
identified CE to the Ministry of Transport, Government of India. In case of CRIF works,
PW(R&B) department has to prepare a list of projects to be proposed under admissible CRIF
funding which shall include road map indicating district boundaries, National Highways, UT
Highways, major district roads and other rural roads in different colours for each project and
has to forward it to Ministry of Road transport and highways for sanction. The list of works
as and when sanctioned by the MoRTH is communicated to Chief engineers for further
course of action as per guidelines /codal procedures of the scheme.
7.6 Repairs and maintenance
61
7.7 Head of account
7.8 The major heads of accounts operated by PWD are given in the
appendices of the manual
Careful study of the progress which can be achieved during the year shall be made after
taking into account availability of land, materials, tools and plant, delays if any, due
to seasonal conditions or other reasons etc. and the budget provision to be made shall
be based on such study by the Executive Engineer. (b) In respect of new works these
shall be listed in the order of priority and the provision of funds for each shall be
determined taking into account the progress which can be expected during the year
after allowing for delays if any which may occur for getting possession of land,
arranging contracts, making available required materials, tools and plant etc. If the total
funds required for new works after making provision for each on the lines set out
above is found to be more than the total amount available for distribution, then a few
works with lesser priority shall be eliminated. Provision of funds for repairs of the
various categories of public works shall be made based on the principles detailed
in the respective chapters on maintenance as indicated below:
(a) Buildings
(b) Roads and Bridges-
In other case according to needs based on past experience the method of working out
funds required under establishment is detailed in Budget Manual. The provision in the
budget under tools and plant covers-
(a) Purchase of new tools and plant, and
(b) Repairs and carriage of existing tools and plant.
Provision for (a) is generally made on a Lump sum basis for the items to be procured
during the year as detailed in chapter 5 of Section V, Asset Management –Movable
Assets. Provision for (b) s hall be also made as a lump sum. There shall be a minor
head provided under major head to cover suspense transactions relating to miscellaneous
public works advances. All transactions recorded under this head shall ultimately be
removed either by payment or by recovery in cash or by adjustment to be the works
concerned. The transactions therefore consist of both debits and credits and the later
are adjusted as reduction of expenditure. Although the net financial effect of the
transactions may be either zero or a small amount representing the difference between
total expenditure and total credits, it is necessary for budget purposes to forecast the
likely total expenditure to be incurred during the year without taking into account the
credits and provide for the same under this head. This forecasting shall be done
based on previous year's experience allowing for necessary variations anticipated.
62
7.10 Preparation and Submission of Performance Budget
In addition to the Financial Budget referred to above it is also necessary to prepare
and submit a performance budget in respect of the activities of the various branches of
the department. This method of budgeting shall enable a department to set out in
the budget document the objectives of the department during a year, the programs
and activities by which these objectives are proposed to be realized, the expenditure
to be incurred on each of these programs and activities during the year, indicating the
broad physical achievements that are possible. This is a useful management tool both for
the Legislature and the departments in programming and evaluating the performance
of the departments. Performance Budget for this year and for next year shall be filled
up in the prescribed form. Guidelines for filling up the proforma sub activity-wise and
object-wise are given therein. The Executive Engineers of the Divisions shall fill up the
proforma and submit to the Chief Engineer through Superintending Engineer of Circle
and then to the Secretary to Government, every year. The Chief Engineers shall submit
The Chief Engineer is the chief controlling officer of the major budget heads
solely operated by the PWD. Each Chief Engineer shall function as the chief controlling
officer for the major budget heads or portions of major budget heads with which
hiswing has to deal. The Superintending Engineers under the control of Circles are
subordinate controlling officers to control the expenditure under the budget items dealt
by them. Executive Engineers under the control of Divisions and other Divisional
Officers of the P.W.D. are disbursing officers. It is the duty of the concerned Chief
Engineer to ensure that resources are collected, allocated and expenditures are
disbursed in an efficient, effective and economic manner. He shall hold subordinate
officers accountable for spending public money both in terms of outcomes achieved
and value for money. The chief controlling officers, the subordinate controlling
officers and disbursing officers shall exercise proper control over expenditure in the
manner detailed in the Budget Manual. Expenditure shall be watched in terms of each
unit of appropriation and steps taken to regularize unavoidable variations as soon as
such variation is anticipated.
.
7.11.1 Funding Departmental Revenues
PWD ENGINEERING MANUAL-2020 CHAPTER - 7
The P.W.D. shall be responsible for the collection and accounting of certain items of
revenue. The main items of revenue are given below:-
a. Rents. -rents for residential and non-residential buildings and quarters under the
control of the P. W.D including rents of furniture, amounts arising from lease of
stalls, fees realised for the use of rooms in rest houses, etc. shall be credited to
the concerned head.
b. Sale proceeds of trees belonging to Government along the sides of roads and on PWD
land or lease amounts thereof shall be credited under the concerned head.
c. Recoveries of expenditure: Recoveries on account of damage caused by occupants
to buildings and furniture, tools and plant charges from contractors, refund of unspent
balance of grant, contribution from local bodies or private parties in respect of
works, sale proceeds of old tools and plant, etc. shall be creditable to the concerned
head.
d. Fee collected by mechanical wing for testing of vehicle for fuel efficiency,
preparation of repair estimates, supervision of work etc.
e. Hire charges for machineries and equipments
f. Fines and confiscations, etc.
g. Miscellaneous: The receipts credited to concerned head shall be lease rent and sale
proceeds of avenue trees, wood, glass, fruits, vegetables, dead stock, waste paper an
other items, rents from land etc. It shall be the duty of the Executive Engineers and
officers subordinate to them to arrange realization of revenue to be collected by them
in time and also take all necessary steps to prevent leakage of revenue.
If the funds allotted through the budget by the State Government are insufficient for the
requirement of the department for their proper functioning, financial assistance from the
external funding agencies like NABARD, ADB, WB etc. shall be sought by the
Government to cater to the requirement.
P.W.D. may also obtained such loans for carrying out necessary roads and bridge
works. In the case of works where expenditure is reimbursed, the prescribed
proforma duly filled up shall be forwarded to the Finance Department for onward
transmission to the funding agency. The expenditure incurred for the purchase of
quality control equipments, for setting up of labs, purchase of tools and plants and
other expenses for the work shall also be reimbursed if the same is included in the
Administrative sanction of the work.
64
7.13 Administration Report
Every year the PWD shall award persons/ offices for meritorious service to the
department and society. Similarly, contractors shall also be suitably rewarded for
exceptional performances. For this purpose a committee headed by the DCW with all
Chief Engineers and one or two experts shall be constituted every year with the approval
of government. The committee shall fix the norms, procedure and criteria for
awarding the deserved persons.
65
CHAPTER 8
8.1.1 General
GIS is a computer system capable of capturing, storing, analyzing, and displaying
geographically referenced information.
PWD GIS shall mapped all roads in J&K State including bridges, junctions, culverts and
other objects of interest. It shall provide a complete and accurate map of the road network
in J&K.
PWD GIS shall be a tool for planning preliminary alignment; and development of the
road network to improve connectivity and to assist with better decision-making.
CHAPTER - 8
An important use of GIS is to enable PWD to develop efficient maintenance strategies
for roads and bridges. PWD GIS is the spatial database for the road maintenance
management system (RMMS). GIS plots can show roughness, potholes and other
criteria, which indicate the road, condition and thus help PWD to arrive at logical
decisions. Further, PWD can prepare and monitor annual work plans and maintenance
programs.
66
● Maintenance of the Geographical Database –Field collection of data for database
maintenance
● Coordinate GPS field data collection of new roads and bridges for regular
maintenance
● Inform Central GIS Unit about changes in road network for re-classification
● Maintain contact to Sub-Divisions and Sections
● Participate in regular meetings
● Provide map printouts to Sub-Divisions and Sections
The function of Sub-Divisions and Sections is mainly to provide the basis of the attribute
database through data collection. They shall also verify the various outputs and keep
these maps as reference.
PWD ENGINEERING MANUAL-2020 CHAPTER - 8
The source of all data in PWD is the Section, where it is collected and compiled. The
Sub- divisions hold a key function for data compilation since data will be aggregated
here. Data validation, computing and data references shall be checked at each level.
The key function for GIS and road maintenance management is at the Division level.
The data will be assembled and the first analysis is done in order to prepare yearly
maintenance programs.
8.2.4Data Processing
The table 8.1 gives an overview about the general functions in data processing of the
different levels.
Table 8.1 General functions of geographical data processing in PWD
administrative levels.
CHAPTER - 8
registers
8.6 Update of new road alignments:
The major change in the GIS data base will be caused by the construction of new roads
or eventually the conversion of roads into PWD roads or which have not been
captured accidentally. In case of conversion in to PWD road, the alignment of those
roads has to be captured like a new road.
In addition of upgrading existing roads, new roads are constructed yearly in every
Division. These new alignments have to be included in the database as update of the
68
Table 8.2 Proposed Sequence and responsibilities of maintenance activities
Ste Activity Responsible
ps Road alignment Road classification Location of bridges
and CD structures
1. Prepare print-out of Prepare print-out of Prepare print-out of Local GIS
Section Section / Sub-Division and Section Unit
/ Sub-Division with new mark manually alignment of / Sub-Division and
road and mark manually converted road mark location of bridge
approximate alignment / CD
Structure
2. Carry-out GPS field In case that road is not Carry-out GPS field To be
survey to capture captured in database, carry survey to capture coordinated
geographical coordinates out GPS field survey geographical by local GIS
of road coordinates of bridge / Unit
PWD ENGINEERING MANUAL-2020 CHAPTER - 8
CD
Structure
3. Forward GPS coordinates Forward map with marked Forward GPS Local GIS
to Central GIS Unit converted road or GPS coordinates to Central Unit
coordinates to Central GIS Unit
GIS Unit
4. Integrate coordinates of Re-classify road or integrate Integrate coordinates Central GIS
new road coordinates of converted of new bridge / CD Unit
into road structure into
geographical into geographical geographical database
Database database
5. Segmentation of new road Segmentation of Assignment of unique Central GIS
and assignment of unique converted ID to new bridge / C Unit
ID to segments road and assignment of structure
unique ID to segments
6. Forward of print-out for Forward of print-out for Forward of print-out for Central &
final approval by final final approval by Section local GIS
Section, Sub-Division, approval by Section, Sub- Sub-Division Division Unit
Division Division, Division
The GIS local units shall maintain registers for roads, bridges and junction in formats
given in table 8.3 and regularly update it with regards to spatial data.
The Central GIS Unit and the Local GIS Units shall perform analysis.
The Divisions shall prepare annual maintenance plans, based on various analyses and
forward it to the Chief Engineer through circle offices. Maps shall be integrated in
reports as attachments. The analytical operations on Circle level will have the purpose
to scrutinize the plan documents from the Divisions. Analytical operations by the Central
GIS Unit are supporting overall management decisions, mainly in terms of budget
allocations (for road maintenance). The operations will be carried out on behalf and for
the Chief Engineer. The Divisions shall prepare a set of thematic maps, to be
forwarded for the Sub- Divisions. The Sections through the Sub-Divisions shall verify
information derived from the database.
69
Table 8.3 gives an overview about the operational standard tasks of the
different levels.
CHAPTER - 8
Sub-Divisions / Sections Sub-Divisions and Sections
Perform analysis for maintenance on A3 sheets
planning and forward to Chief Engineer in
reports and as A3 sized maps
Sub- Data gathering
Division Verification of analysis
Section Data gathering
Verification of analysis
*(Topographic Maps with emphasizes on roads and bridges)
8.11.2Analysis results:
Analytical operations by the Central GIS Unit will be carried out on behalf and for
the Chief Engineer. Out puts shall be as A3 as well as A4. For presentation
purposes, maps could be printed on large sized paper. The results of analytical
operations on Circle level shall be in form of A3 sized maps. The Divisions based on
various analyses will generate maps on A4 paper. These maps shall be integrated in
various reports as attachments.
70
8.12 Monitoring of GIS Operations
The various attributed data that form the GIS system shall be documented regularly
and when changes occur. This shall be the responsibility of central GIS Cell.
There are several activities which shall be executed at regular intervals in order to keep
a certain level of know-how and to maintain the communication between the different
GIS Units:
• All GIS Units shall meet at least once in a year with the purpose of exchanging ideas,
reporting about experiences and problems, maintaining standards and
71
procedures and getting feedback from the Chief Engineers. The meeting shall be set,
organized and facilitated by the Central GIS Unit.
• Annually, the Central GIS Unit shall give a presentation on the complete database for
all Divisions and Circles provide a one day refresher-course about GIS technology and
introduce about latest development in general as well as within PWD in so far it is
relevant to GIS operations.
• All GIS Officers shall attend an external professional training on GIS issues for
about one week, once in two years. This training shall be tailored for the needs and
shall include need-related aspects such as refreshing the general know-how on
geographical information technology, latest trends and specific aspects, for
instance advanced spatial analysis procedures, marketing strategies, data security
aspects etc. Universities, other government organizations, private institutes or
consultants could provide the external training.
CHAPTER - 8
Besides these regular activities, there are occasional activities which may come up
or which supports the overall performance of GIS operations:
• In case of personnel transfer and open positions in GIS Units, the Central GIS Unit shall
provide and introduction course for there placement to assure smooth performances in
the different offices
• From time to time, one or two representatives of the Central GIS Unit shall visit selected
Local GIS Units for individual support. Such visits could be scheduled so that all offices
have been visited once within two years.
72
8.14.3 Shortest Route Identifier:
This tool is a typical travel tool to identify the optimal route from one specific point to
another one, based on criteria such as travel distance, riding quality of road, traffic
volume etc.
For PWD, the tool could be helpful to identify most frequented roads for planning
purposes. Table 900.2 relates to the identified needs for PWD to the above- described
tools and their technical functions.
Reference documents
73
CHAPTER 9
9.1.1 General
CHAPTER - 9
of defining maintenance activities, compiling a road inventory and condition survey
details, establishing priorities, establishing quality, quantity, performance standards
and compiling cost data.
74
9.2.2 Central RMMS Cell
The RMMS cell in the direction office shall be under the control of the chief engineer.
This cell shall be responsible for running and maintaining the RMMS program in all
aspects. Only this cell shall enter data onto the RIS database. All the other RMMS
Cells/Units shall only be able to enter data onto a secondary file which, once the data
has been verified at all intervening levels, shall be the responsibility of the RMMS in
PWD Head Quarters to update
the original database. This shall ensure the integrity of the database and prevent any
manipulation of the stored data that might adversely affect or influence the decision
making process.
The following shall be the functions of Central RMMS cell
CHAPTER - 9
75
9.2.3 Local unit
At Circle level the RMMS Cells shall have full use of the software, which shall be used
in the development of the maintenance strategy. These units shall also be able to
compare the effects of allocating some of the budget to various items such as
construction/rehabilitation of new roads.
At the Division level the RMMS Units will be able to view RIS database of the part of road
network for which they shall be responsible.
There shall be an Assistant Executive Engineer supported by Draftsman in the general
divisions under the control of the Executive Engineer with the following functions
1. The administration and upkeep of RMMS throughout the State to ensure that PWD
receives a suitable and adequate road maintenance budget to meet the required level
CHAPTER - 9
of service set by the road user.
2. Ensure the conduct of road condition survey on time to meet the
required budget submission
3. Together with the AEE(GIS) check data received from the district offices for
accuracy and consistency and note in particular any changes or queries;
4. Report to the RMMS Central Unit any problems with
the annual maintenance programme.
76
9.3.2 Road Condition Details
The RMMS Central Cell shall be responsible for investigating all road condition
surveys. They will contact the RMMS Cells in the three Circles who will be
responsible for collection and validation.
There is a need for those engaged in road condition surveys to meet together on an
annual basis to ensure that a uniform standard system is adopted for recording the
condition of the roads throughout the State. The timing of the surveys will be
subject to the approval of the DCW but will normally take place on an annual basis
after the winter season.
These Shall need to be updated on an annual basis to ensure that they reflect the
actual situation.
This task shall be the responsibility of the RMMS Central Cell.
These costs shall be generated and updated based on either recent or current
maintenance intervention contracts. The Divisions shall be responsible for submitting
this data to the RMMS/HQ Circle via the RMMS Cells in the Circles. The RMMS
Central Cell will be responsible to analyzing the contracts to determine the required
maintenance intervention costs. Different maintenance interventions may be used and
these must be added to this group of data along with the relevant costs.
77
9.8 Reporting
At the start of each financial year a new State version of the RMMS Database will be
released for all users. This will contain all the recently collected condition data and
Ordnance and Inventory revisions. Central unit users will be able to obtain new
versions via the network. Details of the completed maintenance work to be sent to the
RMMS Cell in the Circle for verification and onward transmission to the RMMS
Central Cell for updating the records. Maintenance intervention costs on a sq. metre
basis shall be returned to the RMMS Cell in the Circle for verification and onward
transmission to the RMMS Central Cell where they will be used to determine future
maintenance costs.
CHAPTER - 9
9.9 Specific use
78
CHAPTER 10
10.1 SAFETY
10.2 General.
This chapter details the safety measures to be followed in various construction and
maintenance operations. The aim is to provide and maintain a working environment
that is safe and effectively minimizes risks to the health of its employees, contractor,
equipments and members of the general public.
CHAPTER - 9
such harm eventuates or not, and also in the case ofevery accident.
Insisting on arrangements for the safe use, handling, storage and transport of
equipment and substances.
Insisting on adequate facilities and protective clothing & equipment to protect the
health and safety of all employees
The practice of safety involves shared responsibilities and a team approach by all
employees. Everyone associated with PWD shall be responsible for their own health
and safety, and the safety of others affected by the actions of their work. Necessary
provisions for safety shall be foreseen and incorporated in the estimates during project
preparation stage itself.
10.4 Accidents
Working in the construction industry can sometimes be dangerous. Work-
related accidents can cause serious injuries, while most of these accidents are
preventable. Accidents are mainly classified into 4 types, viz. fatal accident, grievous
injury accidents, minor injury accidents and non-injury accidents as per IRC 53 Road
Accident Forms A-1 and
4. The following procedure shall be adopted in case of accidents.
79
serious injury to any person (grievous injury), non-injury accidents involving loss of
property or would cause serious disruption of normal life in the area affected, such as
by interruption to main lines of communication etc. In case a major accident
involving structures under construction or under maintenance by P.W.D. occurs, the
following procedure shall be followed.
The Junior Engineer or Subordinate under the control shall inform the Assistant
Engineer, Assistant Executive Engineer and Executive Engineer of the accidents by
the quickest possible means. The Police Inspector having jurisdiction over the area
shall also be informed in cases of death or serious injury to person and where
criminal activity is suspected.
i. The Assistant Engineer and Assistant Executive Engineer concerned shall, on receipt
of such information proceed to the spot within the shortest time possible and organise
or assist in rescue operations. The Assistant Executive Engineer or in his absence the
iii. Superintending Engineer shall, on receipt of information, inspect the site within 3
days or as short a time as possible and ascertain by personal enquiry the causes of
the accident, the adequacy of relief measures, and also find out best means of
restoring normal activities in the affected area. His report shall be sent to Chief
Engineer independently of the Executive Engineer's report within 3 days after his
inspection.
iv. The Chief Engineer shall inspect the site within a week of the occurrence of fatal
accidents or as early as possible and make such personal enquiries as he feels
necessary in order to furnish a full report of the accident to the DCW and he in turn
submit report to Government, detailing the causes, the action taken thereafter and
action to be taken to restore normalcy in the area. In addition, this report shall contain
information as to whether there is prima facie negligence or dereliction of duty on the
part of any Government servant and if so, make recommendations regarding
disciplinary proceedings to be taken against the delinquents.
80
10.5 Job Hazard Analyses
A job hazard analysis is a technique that focuses on job tasks as a way to identify
hazards before they occur. It focuses on the relationship between the worker, the
task, the tools, and the work environment. After an uncontrolled hazard is
identified, steps shall be taken to eliminate or reduce them to an acceptable risk
level.
Many workers are injured and killed at the workplace which can be prevented by
looking at workplace operations, establishing proper job procedures, and ensuring
that all employees are trained properly. The best way to determine and establish
proper work procedures is to conduct a job hazard analysis.
Job Hazard Analyses (JHAs) shall be a part of major projects that entail:
CHAPTER - 10
jobs with a high frequency of accidents which pose a significant threat to health and
safety;
jobs that have already produced fatalities, disabling injuries, illnesses or
environmental harm;
jobs that have the potential to cause serious injury, harm, or damage, even if they
have never produced an injury or illness;
jobs involving two or more workers who must perform specific tasks
simultaneously; newly established jobs whose hazards may not be evident
because of lack of experience;
81
Training requirements
Responsibilities of each person involved in the job and publishing the names of the
persons and organizations to be contacted in the event of an emergency
A specific sequence of steps to follow to complete the work safely Permits required
Awareness of emergency procedures,
Publishing the location of the emergency responsive equipment and ensuring the
equipment is well located, visible and properly maintained.
A well-documented safe job procedure shall form the basis for initial job training
and as a briefing guide for infrequently performed jobs. It may be used as a
standard for safety inspections or observations and it will assist in completing
comprehensive accident investigations. Whenever an incident occurs, the Safe Job
Procedure shall be thoroughly reviewed by the worker and supervisor to ensure that
PWD ENGINEERING MANUAL-2020 CHAPTER - 10
no important step is missing and that the Job Procedures meet current regulations.
The Cell is primarily to coordinate the road safety activities of the PWD including
undertaking of road safety audits at various stages; identification of black spots,
improvement of accident sites in a phased manner, establishing Road Safety Cells at
a district level and interdepartmental co-operation, coordination and collaboration
with all stake holders of road safety and with the J&K State Road Safety Authority.
The following road safety activities shall be the prime responsibility of the road
safety cell of PWD,
Identification of Black spots as per Hon‘ble supreme court guidelines Prioritized
Blackspot Improvement Program
Road Safety Audit of existing roads
Mass Action schemes
Engineering measures for vulnerable road users Audit of upcoming project roads
Training and Establishing Road Safety Cells at district level Interdepartmental
coordination, cooperation and collaboration.
Accident report compilation with JKPWDOMS output, analysis, and
preparation of annual accident report
Implementation and Review of Road Safety Action Plan Development of Road
Safety Strategy and Program
82
10.6.2. Road Safety in Divisions
The road safety activity of PWD divisions shall be carried out by the Executive
Engineer assisted by his subordinates under the guidance of Road Safety Cell. They
shall also support the District Road safety wings.
The Divisional offices of road safety shall report all road accidents in their
jurisdiction to Road Safety Cell to propose safety engineering measures for such
locations; identify accident black spots; data from police departments, design and
priorities the schemes; and implement/improve such schemes under overall
supervision of Road Safety Cell. Also to coordinate the road safety activities of the
PWD at district level, prevention and eviction of encroachments on roads, action to
make the roads safe by timely maintenance and interdepartmental coordination with
CHAPTER - 10
all stakeholders of road safety. The Executive Engineer shall review and monitor the
progress of road safety works of concerned divisions and report will be submitted to
the RSC on a monthly basis.
6) Detailed design
7) BOQ
8) Economic Evaluation
9) Prioritization and program
10) Implementation
11) Monitoring and Evaluation
Black spot improvement programme shall be implemented in a phased manner and
the details of all above mentioned process shall be carried out as per the accident site
records on: JKPWDOMS
10.7.1. Signs
Signs shall be installed based on IRC-67-2001 and shall be carried out as per the
supplementary technical advice for IRC-67 shall be available at the website:
JKPWDOMS
In installation of signs priority shall be given to gateway sign, junction signings, bend
signs, school signs, regulatory and prohibit signs and hazard markers and hump
warning and informatory signs.
10.7.2. Markings
Markings shall be applied based on IRC-35-1997 or latest. In markings on a road,
priority shall be given to centre line, edge line (where adequate width is available),
junction marking with appropriate traffic control for junction, pedestrian crossing
markings, hump and rumble strip marking and hazard markings.
CHAPTER - 10
included and for minor works, 5% contract value shall be set apart for road safety
items.
85
Safety and inspection programs through the development of policies and
guidelines. Bridge inspection reports shall be prepared as per procedures detailed in
the Chapter on Bridge Maintenance.
Human life may get affected due to disasters like landslide, flood, earthquake,
cyclone, tornado, building collapse, external aggression, terrorist insurgencies etc.
The Deputy commissioner shall be under the control of emergency measures as per
norms of DDMA. PWD Executive Engineers, in liaison with the Deputy
commissioner, shall be in the fore front of salvage measures and shall get into action
on a war footing basis.
Executive Engineer with proper documentation from DDMA, shall arrange for
necessary refugee camps, with water supply and sanitary facilities. The Executive
PWD ENGINEERING MANUAL-2020 CHAPTER - 10
86
CHAPTER 11
11.1.1. Introduction
The objective of environmental management is to enhance the positive
environmental impacts and abate/mitigate negative environmental impacts of
construction activities and related works. Good environmental management also
ensures compliance with all applicable National, State and Local Environmental
CHAPTER - 11
legislations. This chapter provides the following information: Description of
environmental issues relevant to PWD activities List of applicable legislations at
the national, state and local level Institutional settings pertaining to legislation
Environmental clearance requirements For regular works, the process to integrate
environmental management measures with implementation. For certain other
works requiring further environmental studies prior to implementation, the
process for conducting the Environmental Impact Assessment (EIA) and
developing the Environmental Management Plan (EMP). Environmental training
& capacity-building Environmental communication and consultation.
This chapter is supported with Appendices that provide guidance on various
11.3.1. Land
Projects involving land disturbance, removal of vegetation and reshaping of
topography make the soil vulnerable to erosion, dust generation and generation of
waste materials. The mitigation measures shall be included in the planning and
design stage to ensure its effective implementation during the project execution.
These include: Compensatory planting. Ensure surface is reinstated, smooth and free
of encumbrances. Minimize waste from construction and reuse of waste material
wherever possible. Solid waste shall be placed to minimize intrusion into the
carriageway in consultation with local help/government authorities. Collect similar
types of construction waste into common piles and dispose suitably. Put general litter
and waste into special purpose bins or remove to covered designated area and ensure
it is contained.
11.3.2 Air
Air pollution occurs when the air contains pollutants like gases, dust, fumes or odour
in harmful amounts that affect the health or comfort of humans and animals or which
could cause damage to plants and materials. The sources of the air pollution in the
87
infrastructure projects include, but not limited to; Site clearance, transportation of
men and materials, construction of temporary accommodations, stock yards,
installation of construction plants during the pre- construction stage, Operation of
construction plants such as hot mix plant, concrete batching plant, crusher and wet
mix macadam (WMM) plant, Excavation of foundation, roadway and borrow areas,
Operation of machinery and vehicles, Construction of roadway, buildings and
bridges, Stock piles of materials With proper assessment of the degree of pollution
from each source, required mitigation measures and preventive measures can be
delineated for the protection of air quality from further degradation and keep the
ambient air pollution levels of the project area within limits stipulated in National
Ambient Air Quality Standards. Some of the measures for the prevention and
mitigation of the air pollution due to the project are: Selection of project location or
preferred alignment and design Fitting required air pollution control equipment for
the machinery, plants and vehicles With proper periodical maintenance and servicing
PWD ENGINEERING MANUAL-2020 CHAPTER - 11
of the pollution control equipment and the machinery, plant and vehicles
Limited tree cutting, and planting of more trees Watering of the access
roads and approach roads or provide seal coat Watering of the materials before
loading into the plants for reduction of dust generation Limit the extent of disturbed
areas and restore the disturbed areas
11.3.3. Water
Water pollution is" the loss of any of the actual or potential beneficial uses of water
caused by any change in its composition due to human activity" .Source of the
water pollution and impacts on the water environment include but not limited to:
Loss of water resources such as relocation of wells, hand pumps, tube wells, loss/
filling part of water bodies and change in the flow pattern of water.
Pollution of streams due to increase of sediment laden runoff, Pollution of water
sources from the oil spills, disposal of bituminous materials, stockyard of diesel,
engine oil, chemicals, bitumen, emulsion etc., Disposal of wastewater generated
from the temporary living facilities, Waste water generated from the operation of
plants, cleaning of machinery and equipment, Wash water from the workshop and
washing bay. With the proper characterization and quantification of waste water
from each source, required treatment facilities can be designed and implemented for
the control of water pollution. Some of the mitigation measures for the prevention
and/ mitigation of the water pollution are: Controlling the generation of sediment,
oil and grease, excess nutrients, organic matter, litter, debris and any form of waste
(particularly petroleum and chemical wastes) from a construction and disallowing
these substances into the waterways, storm water systems or underground water
tables. Such materials shall be captured before they reach drains and waterways by
following methods:
(i) Cover stockpiles or spray water to suppress dust,
(ii) Store all chemicals, fuels and other hazardous liquids and solids according to
manufacturer‘s specifications within a bunded and covered area or land depression
away from water ways,
(iii) Dispose of empty drums and as soon as possible appropriately or through a licensed
contractor or to a licensed disposal centre and
(iv) Water quality management e.g. using sand bags to filter water and remove sediment
and control litter; Limiting the areas of disturbed land, progressively clearing the
site in accordance with construction needs and rehabilitate as soon as possible,
Protect drainage lines with sediment basins and silt fences, Construction of proper
sanitation
88
facilities for the disposal of the wastewater generated from the kitchen and toilets.
Construction of proper wastewater treatment facilities for the waste water generated
from the workshops, concrete batching plants, hot mix plants and wet mix macadam (WMM)
plants. Wash out ready-mix concrete agitators and concrete handling equipment at such
facilities. Such treatment plants shall be considered while planning major infrastructure projects
and the treated water shall be recycled and reused for gardening or irrigation.
Rain water harvesting shall be done as per Clause 5.5.12 of Part 9 Section I of National
Building Code and the collected water shall be used for gardening, flushing, fire fighting or
washing purposes.
CHAPTER - 11
machinery, equipment, construction plants, construction works and vehicles plying on the
road. The noise pollution from the project activities can be reduced with the proper
planning and design of the noise control measures and proper work planning. Some of
the noise control measures for the reduction of the noise from the project are as follows:
Use of quiet equipments, machinery, plant and vehicles available in the market Proper
maintenance of equipment, machinery, plant and vehicles
Installation of machinery with correct foundations to reduce to vibration
Enclosing the noisy equipment, Providing noise attenuation screens, wherever required
Proper planning of the working hours (noise generating activities scheduled for the
Construction of road, bridges, buildings and other structures may impact flora and fauna.
The degree of the impact varies based on the location, scope and size of the project. Some
of the impacts that occur are:
Cutting of trees
Damage to the aquatic life Damage to the fauna
Damage to national parks, wild life sanctuaries and reserve forests Impacts on National Parks
Damage to Biosphere Reserves and Damage to the forests
With assessment of the nature and scale of impacts on flora and fauna, required preventive
or mitigation measures can be addressed during the planning and design stage. The
damage to the biological environment can be prevented or reduced with the
implementation of preventive or mitigation measures designed during the planning and
design stage. Some of the common mitigation measures are:
Saving the trees as far as possible with proper design and alignment changes and
selection of location of the project
With proper work planning during execution for the reduction of disturbance to the aquatic
life Providing proper animal crossings, water crossings, fencing and traffic control
measures Planting tree saplings by
(i) providing temporary protective barrier around existing trees for
protection during construction works, and
(ii) not placing equipment or excavate within 2 metres of a tree.
89
11.3.6. Cultural Environment
There may be some impacts on the cultural environment due to the infrastructure
project during the pre-construction and construction stages. The impact varies from
loss of the part of the property to the total property.
The negative impact on the cultural environment can be prevented by changing the
location of the project and/mitigated by the relocating or modifying the affected
structure. An important aspect here is the timely and open communication with the
property owners and community by:
Speaking to the local representatives. Placing signages at prominent positions.
Providing a newsletter to affected people.
The various prevailing environmental acts and rules relevant to the PWD
activities are listed here. This includes Central Acts & Rules administered by the
Ministry of Environment & Forests, other National legislation that are relevant
and J&K Acts & Rules
In addition to the above detailed legislations, the rules and conditions of the following
Acts/ Legislations have to be followed:
Explosives Act,1884 and ExplosiveRules,1983
Petroleum Act,1934 and Petroleum Rules,2002.
The Mines and Minerals (Regulations and Development) Act, 1957 and rules
there under.
90
In Appendix 1100.1, a brief description of these Acts & Rules as well as their
implementing agency has been provided.
The additional legislations, which are to be followed in J&K, are as follows: J&K
Forest Act and its amendments
J&K Forest Rules
J&K Private Forests (Vesting and Assignment) Act
J&K Forest (Vesting & Management of Ecologically Fragile Lands) Act & Rules.
Government Order – J&K Forest (Vesting & Management of Ecologically Fragile
CHAPTER - 11
Lands) Rules – Constitution of Tribunal
J&K Preservation of Trees Act J&K Forest Produce Transit Rules
J&K Restriction on Cutting and Destruction of Valuable Trees Rules. Forest
Settlement Rules
J&K water resources regulations and management act 2010 along with J&K
Water Resources Regluations and Management Rules.
In the particular context of the various PWD activities, the provisions of these
legislations should be kept in mind for their relevance in the context of each works
/ projects that are being proposed for implementation.
MoEF is the nodal agency in the administrative structure of the Central Government,
for the planning, promotion, co-ordination and overseeing the implementation of
environmental and forestry programmes. The principal activities undertaken by
Ministry of Environment & Forests, consist of conservation and survey of flora,
fauna, forests and wildlife, prevention & control of pollution, afforestation and
regeneration of degraded areas and protection of environment, in the framework of
legislations.
MoEF has set up regional offices. The regional office for the J&K is is responsible
for collection and furnishing of information relating to EIA of projects, pollution
control measures, methodology and status, legal and enforcement measures and
environmental protection in special conservation areas such as national parks,
sanctuaries, wetlands, and forests.
PCB is a statutory authority attached to the MoEF and located in New Delhi. The
main functions include the following:
Advise the Central Government on any matter concerning prevention and control
of water and air pollution,
Plan and execute a nation-wide programme for the prevention, control or
91
abatement of water and air pollution;
Co-ordinate the activities of the State Board and resolve disputes among them;
Provide technical assistance and guidance to the State Boards;
Plan and organise training of persons engaged in programme on the prevention,
control or abatement of water and air pollution;
Organise through mass media, a comprehensive mass awareness programme on
the prevention, controlor abatement of water and air pollution;
Collect, compile and publish technical and statistical data relating to water and air
pollution; Lay down, modify or annul emissions and air/water quality standards,
Prepare Manuals, Codes and guidelines, and Disseminate information.
92
10. PUC Certificate for Vehicles and Road Transport Department
Machinery
11. Permission for setting up of Local Health Departments and Local Body
Labour
12. Permission for Jal Shakti (Irrigation and Flood Control)
construction/expansion of road Department.
near or on top of embankment of
river, nallah, water channel,
irrigation channel etc.
Based on the works /projects being done, PWD needs to ensure that the
necessary clearances are obtained prior to implementation and the clearance
CHAPTER - 11
conditions are complied with during implementation.
In the regular works / projects of the PWD, the environmental issues need to be
properly and effectively managed. In principle, PWD needs to ensure the following
in all its regular works / projects:
Avoid or minimize tree cutting as far as possible; if tree cutting is unavoidable, make
plans for compensatory plantation,
93
Documentary evidence shall be available to demonstrate compliance with the
standard EMP. This can include periodic progress reports, file notes, audit reports,
photographs, and minutes of meetings or video. The contractor shall retain them in
safekeeping for perusal by the PWD.
Failure to reasonably satisfy and comply with the standard EMP requirements may
result in the contractor receiving partial payment against the contract claims and
also a noting in the contractor‘s performance certificate.
94
Decision Decision- making process involve consultation between the project proponent
Making (assisted by a consultant) and the impact assessment authority (assisted by
an expert group if necessary)
Monitoring of Monitoring shall be done during both construction and
the Clearance operation phases of a project.
Conditions
Conducting EIAs and preparing EMPs are studies that are done by external
consultants on behalf of the PWD. Taking into account the particular context of
these works / projects, the PWD shall prepare terms of reference for conducting the
EIAs and preparing the EMPs. PWD shall refer to the EIA Notification 2006 for
information on various aspects of conducting EIAs, its knowledge of the state and
the dimensions of the proposed works / projects in preparing the terms of reference.
CHAPTER - 11
The external consultants will be selected using the Government procurement
procedures. Once mobilized, the external consultants conduct the studies and
prepare reports that are to be reviewed and accepted by the PWD. Based on the
report outcomes, the project planning and design shall be changed so that the
environmental impacts are minimized.
EMP is a project specific plan with the following contents:
Table of preventive, mitigation and compensation measures
(collectively referred as ―management measures‖) for all identified significant
impacts at the pre-construction, construction and operational stages of the project;
95
stipulated in the project-specific EMP. PWD has to ensure that the contractor obtains
the necessary environmental clearances and also adheres to the project-specific EMP
requirements through the pre-construction and construction stages. After the
construction stage is completed, the project- specific EMP will include activities
during the operational phase. PWD shall ensure that these activities and the project-
specific EMP is compiled throughout the project cycle.
PWD will ensure that the induction and refresher training programmes cover
environmental management as well. PWD‘s shall develop, establish and maintain
training modules on a variety of environmental subjects that will include the
following:
PWD ENGINEERING MANUAL-2020 CHAPTER - 11
96
CHAPTER 12
Social impacts of development projects will have both positive and negative effects
on individuals, households and the local community in particular and the society in
general. Social impacts of development projects vary depending on the size and
type of projects settings and the characteristics of the community affected. These
may include potential changes to population, lifestyle, cultural traditions,
CHAPTER - 12
community dynamics, and quality of life and well-being. Involuntary
displacement induced by development projects has extreme social impacts,
which in many cases warrant detailed and specific study leading to resettlement.
PWD recognizes the need to assess the potential social impacts of the projects and
is committed towards responsible management of the same. These guidelines have
been developed to assist Public Works Department officers in the management of
social issues in planning and execution of its project.
The purpose of these guidelines is to
● Demonstrate and explain the process used in PWD to manage and protect the social
values
97
Issues Measures When to
Address
Acquisition of land and assets resulting Conduct Social Impact Assessment of
in families being displaced or loss of affected community (ies) – access to
livelihood causing discomfort. Stirring houses, business, and farmlands
agitations and results in road blocks by affected and consider options for
locals. This gives negative impression of relocation, improvement, P D
the project to local community, mistrust compensation.
and lack of confidence arises which
delays the project due to numerous
reasons
98
S-1: Projects are those that will affect 200 PAPs or more or if Project Affected
persons (PAPs) are physically displaced and will require a detailed Social Impact
Assessment Report that would include a Resettlement Action Plan. These documents
are to be submitted for approval by concerned EE and clearance by the authority
concerned for administrative /technical sanction.
S-2: Projects are those in which no PAP is physically displaced or less than 200
PAPs are affected. In this case a Social Management Plan (SMP) is required
that would include an abbreviated resettlement plan
S-3: Projects, on the other hand will not have any households affected at all i.e, they
can be classified as ‗socially benign‘. However, submission of a Social Status
Report is required.
CHAPTER - 12
12.5. SIA Process and contents
99
12.6. Activities comprising Social Impact Assessment
(scoping);
❖ predicts (or analyses) likely impacts and how different stake holders are likely to
respond;
❖ assists evaluating and selecting alternatives (including and development
option);
❖ assists in sites election;
❖ recommends mitigation measures;
❖ assists in the valuation process and provides suggestions about compensation
(non-financial as well as financial);
❖ describes potential conflicts between stake holders and advises on resolution
processes;
❖ develop scoping strategies for dealing with residual or non-mitigatable impacts;
❖ contributes to skill development and capacity building in the community;
❖ advises on appropriate institutional and coordination arrangements for all parties;
❖ assists in devising and implementing monitoring and management programs.
12.7.1. Scoping
Scoping identifies the type of the social impacts that are likely to be expected and
clarifies the issues relevant to the project including the frames of reference; major
issues; key variables to be considered; the geographical area of most importance and
other areas of likely impact; the units of analysis and methods of measuring or
determining impact; interested parties or stakeholders (including those who have
vested interests in the project or the affected community, and other groups who will
suffer any impacts from the development; and identification of community leaders
and spokes persons from the stakeholder groups. Undertaking a literature review to
identify previous studies of a similar nature to the proposed intrusion is an
important step in the scoping process which should be commenced as early as
possible. Scoping is largely conceptual process undertaken by the SIA task force
with assistance from discussions with interested parties.
100
12.7.2. Profiling
Profiling, sometimes considered to be part of the scoping process, involves
gathering information about the community in the pre-impact state to be
provided initial estimates for input into prediction models, and to provide
baseline information with which to compare changes when they occur. Some
of this data may already exist in the form of secondary data such as census
and other government and community records, local histories, maps,
newspapers and telephone directories. Otherwise, a social survey may be
required to collect this essentially quantitative data. Interviewing long term
residents is also a valuable source of information. Attempt should be made
CHAPTER - 12
to consider the nature of changes that are inherent in the cultural setting and
likely to effect change on the community independent of the current
development project. The likely impact of other development projects in the
proximity of the current development and any cumulative impacts should be
considered.
The SIA task force by its involvement in the implementation planning of the
development can make concrete suggestions that mitigate impacts and maximize
the potential benefits accruing to the development. The actual mitigation and
enhancement strategies will depend on the nature of the development and the nature
of the impacts. The major task of the SIA task force is to identify the elements of
the development that can be modified in order to reduce impacts. The impact itself
is the result of a stimulus (the aspect of the development causing the impact) and a
response (the way in which the community responds). It is possible to change or
modify the nature of the community response, or its ability to adapt to new inputs,
so that potential negative impact scan become positive or beneficial features of the
development (Branch et al, 1984).
It is in mitigation that SIA is most useful, and where the science of SIA is most
developed. There are a range of possible mitigation strategies that are applicable
to almost all developments, or that are adaptable to suit the individual needs of
the specific development proposal.
12.7.5. Audit
Audit refers a review of the whole procedure of SIA as it was applied to the specific
project. It is important to review predictions and in many cases predictions could be
different to out come because SIA has been successful in its role of mitigation and
monitoring. Care needs to be placed on the interpretation of predictions at the
assessment stage, and during any audit.
101
12.7.6 Engagement of consultants
SIA is an inherently local activity. External consultants should be employed, but the
success of SIA rests on a thorough understanding of the local culture and the way the
culture responds to specific intrusions. It is vital that local expertise be used in the
conduct of the SIA, and that information about each project be developed so that the
lessons learnt from one SIA process can be applied to others as well. For projects
in S-1 category external consultants may be engaged for preparation of SIA.
PWD ENGINEERING MANUAL-2020 CHAPTER - 12
The work requiring the land to be acquired should have been administratively
sanctioned and funds must have been provided. Unless otherwise ordered by the
Government the Officer competent to issue T.S. for the work concerned shall be the
authority to make selection of site. When the P.W.D undertakes construction of
buildings or other structures for other Departments, Local bodies etc., the
responsibility for selection of site shall vest with the concerned Department or
Authority, who may consult the officer of the P.W.D competent to issue T.S. for the
work regarding the technical suitability of the site before finalizing the site. The
officer who selects the land is bound to see that the interest of government, the public
and of private/ individuals likely to be affected are duly considered.
With regard to ascertaining the suitability it may be necessary to conduct some
preliminary examinations, inspections or tests at site. These should be done with the
consent of the owner, if he is willing, before moving for acquisition. The help of the
officers of the Revenue Department may be sought in this regard. If, however, there is
objection to these preliminary works being done, and if prima facie, the site appears
suitable and necessary the Executive Engineer may move for land acquisition. In such
cases, as soon as the notification under section 3(1) is published the necessary surveys
and tests should be done.
Any additional impacts identified during project execution shall be dealt with in
accordance with the R&R policies. The check list of social impact shall be filled in and
reported for calculation of entitlement and disbursement.
102
12.10 RIBBON DEVELOPMENT
Table -1
CHAPTER - 12
LAND WIDTH FOR DIFFERENT CLASSES OF ROAD.
Land width in metres
Class of Plain & rolling country Mountain and steep terrain
roads Rural areas Urban areas Rural areas Urban areas
Normal Range Normal Range Normal Exceptional Normal Exceptional
National
45 30-60 30 30-60 24 18 20 18
It should be noted however, that acquisition of adequate right of way is itself not a panacca for
the problem of ribbon development and can only be a useful supplement. Even where adequate
right of way existed, ribbon development has taken place. On many highways because of lack of
suitable measures for con training the general building activity and number of accesses along
the highways. It is. therefore, to be stressed that acquisition of liberal right-of-way should be
supplemented by other methods.
103
along the highways are obvious since they would benefit much from the necessibility to the
communication arteries and nearness to the cities. The undesirable effect of such growth can be
avoided if proper control is exercised in the use to which the land abutting on the highway right-
of-way is put. Conversion of agricultural land into industrial use along the strip of high way land
can be prevented if the State reserves the right to determine the use to which land can be put. The
process by which land use is controlled effectively by the State is known as "Zoning", and in this
country, the matter is dealt with by the Town and Country Planning Authorities in the States. As
part of the overall planning process, the States or the local authorities draw up rules and
regulations governing the development of land in the area with a view to achieving safety, health
and general welfare. Master plans are prepared for the towns and the countryside, laying down
clearly the use to which land can be put, and it is incumbent on developers to conform to these
PWD ENGINEERING MANUAL-2020 CHAPTER - 12
plans. Such planning measures should be enforced more extensively keeping in view the traffic
needs. Greater cooperation between the Highway Authorities and the Town and Country Planning
Agencies in this regard will be beneficial.
In order to prevent overcrowding and preserve sufficient space for future road improvements, it is
often advisable to lay down restrictions regarding the building lines, set-back distances, control
lines, height of buildings, provision of open spaces, etc. along the highway. Such measures can
also help in securing. Adequate sight distance & preserving the aesthetic value of the highway.
Building lines express the limits beyond which totally any building construction may be
permitted. It may also be desirable to limit the nature of building activity even beyond the
building lines. In such cases, the concept of ― Control Lines‖ is established, and unrestrained
building activity permitted only beyond these lines. Preferably the following minimum standards
should be followed for Building & Control Lines:
104
Table : 2 STANDARDS FOR BUILDING LINES & CONTROL LINES
CHAPTER - 12
between between lines &
building control road Normal Exceptional Normal Exceptional
lines lines boundries
(m) (m) (set back
distance
(m)
*If the land width is equal to the with between building lines indicated in this column, the building
lines shall be set back 2.5 metres from the road land boundary lines.
105
PART – II
106
Chapter 13
13.1. Project Preparation
13.2. Introduction
All works in PWD are classified into original new works, upgradation works and repairs &
maintenance. A project report is required for all works except emergencies, repairs and
maintenance. For maintenance and repair works, the Executive Engineer shall submit proposals
for the same to the Chief Engineer through the Superintending Engineer for consideration and
CHAPTER - 13
approval.
107
Chapter 14
14.1. INVESTIGATION
14.2. General.
It is most important that every work shall be properly investigated and all relevant data collected
and correlated before finalizing the design and estimate for the work. Wrong choice of site or
designs based on incorrect or insufficient data can result in considerable avoidable expenditure
and delays. Hence maximum attention shall be given to investigation and furnishing of full and
correct field data required. Modern equipments shall be used as far as possible.
PWD ENGINEERING MANUAL-2020 CHAPTER - 14
Investigation may often have to be carried out in two phases; viz. preliminary investigation
and detailed investigation. In the preliminary investigation phase, various alternative sites or
alignments etc. shall be examined and a comparative study of the merits of the different
alternatives possible to serve the purpose intended shall be made. Based on such study, the final
choice of the site or alignment as well as broad features of the proposals shall be made. The
financial implication of each proposal shall be looked into and the most economical one shall be
finally recommended without sacrificing the technical feasibility. In the detailed investigation
phase, all the data required for designing the work at the site or along the alignment finally
chosen should be collected.
The Executive Engineer concerned shall decide whether the investigation shall be done by
the department or entrusted to any other agencies considering the special nature and urgency of
the work. The Junior Engineer/Assistant Engineer will be responsible to conduct the preliminary
investigations through the department investigation wing or through empaneled agencies with
the approval of Executive Engineer i.e., he will indicate the various alternatives to be
considered, and the preliminary data to be collected to enable a final choice, of site or alternate
alignment. On the basis of the preliminary investigation, the Assistant Engineer must send a
report to the Executive Engineer/ authority competent to issue technical sanction for the work,
through Assistant Executive Engineer concerned, giving the comparative merits of the different
alternatives studied and his own recommendations. The authority competent to approve the
proposal shall then make a final choice of the alternatives examined, or if additional data is
required, he shall call for the same. The economic aspect shall be looked into before the final
selection. After the final choice is made, detailed investigation shall be conducted. The Design
Engineer responsible for designing the work shall also inspect the site to acquaint himself with
all the site conditions if found necessary. Wherever shifting of utility services is required the
concerned department may be informed well in advance so as to enable them to take further
steps for shifting the same.
In the case of works for the use of other Departments of the J&K, the Executive Engineer
or the Assistant Engineer must keep the local officers of the respective Departments informed of
the investigation work being done. The opinions of the officers of the concerned Department
may also be taken into account in regard to choice of site and features required for the work. The
onus for technical details however shall be vested with the P.W.D. The bench marks and survey
reference points shall be carefully selected and properly established so that there is no likelihood
of these being missed when the work is taken up for execution. Wherever possible, the
benchmarks may be connected to the nearest permanent Mean Sea Level (M.S.L.) Bench
Mark.Funds for investigation shall be separately provided in the budget every year as lump sum
provision. This provision shall be utilised for expenses in connection with the investigation. The
competent authority shall approve the investigation estimate as per delegation of powers. If sub
soil exploration is found necessary, this shall be mentioned in the proposal submitted for
approval.
108
14.3. Preparation of investigation reports
Based on the site investigation conducted the Assistant Engineer shall prepare and submit the
investigation report in accordance with the provisions contained in the relevant codes and
practices (IRC/IBC etc) and the same shall be submitted to the next higher authority for further
necessary action and approval by the competent authority.
The different classes of roads under PWD are National Highways (NH), State Highways (SH),
and Major District Roads (MDR). Other District Roads and Village Roads in the J&K are
currently under the control of JKPWD.
14.4.1.1 Investigations
The following Investigations are to be carried out during the planning stage, before design and
preparation of estimates and tender documents for the construction of new road pavements,
both for new roads and for widening of existing carriageway. For more details refer (1)
IRC:SP:19-2001, manual for Survey, Investigation and Preparation of Road Projects, First
Revision (2) IRC: 37-2001 Guidelines for Design of Flexible Pavements, Second Revision (3)
IRC:58-2002, Guidelines for Plain jointed Rigid pavements for Highways, Second Revision
(Indian Roads Congress Publications) Topographic surveys and investigations for surface and
sub-surface drainage requirements for the new road pavements. Soil Survey, material surveys
and laboratory tests (wet sieve analysis, liquid limit, plastic limit, IS Heavy / Modified
Proctor compaction test, soaked CBR test on soil and specified tests on aggregates to be used
in GSB and GB layers) to assess their properties and decision on the choice of different
pavement materials/layers, their availability and location of borrow pits/quarries. Traffic
studies, particularly classified traffic volume of all heavy vehicles. Axle load studies on heavy
vehicles and evaluation wheel load distribution and design value of cumulative standard axle
loads by conducting relevant studies on 20 percent sample or by making use of available /
secondary data and assumed values of vehicle damage factors.
109
14.4.1.3 Preparation of Estimates and Tender details
The estimates, tender details and tender documents with all conditions of contract are to be
prepared in conformity with the design and drawings prepared as above.
Investigation for the Design, Estimation and Construction of Flexible Pavement Overlay
on Existing Flexible Road Pavements
14.4.1.4 Investigations
The following investigations are to be carried out during the planning stage, before the design,
preparation of estimates and tender documents for the strengthening of existing road
pavements/construction of overlay over existing road pavements. Refer IRC:81-1997. Tentative
Guidelines for strengthening of Flexible Road Pavements Using Benkelman Beam Deflection
Technique, First Revision (Indian Roads Congress Publication).
Basic data on existing road, such as
PWD ENGINEERING MANUAL-2020 CHAPTER - 14
110
14.4.2.2. Design and drawing
CHAPTER - 14
repeated formation of depressions or ruts-the existing pavement layer over the badly filled up
trenches to be cut and removed including 300 mm depth of sub grade soil and refilled using
cohesion-less and compacted using plate vibrator in two to three layers, and relaying of the other
pavement layers similar to the existing pavement layers and (d) profile correction of existing
pavement surface, as separate items. Preparation of tender details and special conditions in
conformity with the design and estimates.
14.4.3. Bituminous Road construction
The compaction of embankment/fill and sub grade adopted are as per Standard Proctor
Compaction. This has to be upgraded to IS heavy compaction as per MoRTH specification. In
fact, compaction in any granular / stabilized layer must refer to IS heavy compaction as specified
Shoulder gives adequate side support to the pavement and also drains off surface water from the
carriageway to the road side drain. Where side footpath is not constructed, normally a shoulder
exists which needs appropriate construction and maintenance for proper functioning of the road.
Shoulder is invariably neglected and remains without outward slope for efficient draining of surface
water. This is of utmost importance in J&K where the snow fall is heavy.
The construction of shoulder is required to be done in layers each matching the thickness of
adjoining pavement layer using selected earth/granular material. Only after a layer of pavement,
shoulder shall be laid and compacted for same matching thickness; next corresponding layers in
PWD ENGINEERING MANUAL-2020 CHAPTER - 14
pavement shall be taken up, and then the shoulder. This procedure shall be followed upto the surface
course. The material, density and compaction shall be as per the specification of sub grade, where it
is earthen shoulder; and the required cross-fall should be maintained. Paved shoulders should have
the specification consisting of sub base, base and surfacing courses and conforming to the relevant
specifications of corresponding items for pavement layers.
Any contractor registered in the appropriate class in PWD can bid for the works. Which is discussed
in chapter 20.
14.5.2 Pre-Qualification
All Bidders shall provide in Section-2, Forms of Bid and Qualification Information, preliminary
description of the proposed work method and schedule, including drawings and charts, as necessary.
The proposed methodology should include programme of construction backed with equipment
planning and deployment duly supported with broad calculation and quality assurance procedures
along with Quality Assurance Plan(QAP), proposed to be adopted justifying their capability of
execution and completion of work as per technical specifications, within stipulated period of
completion. In this method initially a notice is published to invite intending bidders to express their
interest in bidding for the particular work. They are asked to furnish information on several points on
the basis of which screening is to be done. Tender forms are issued only to those contractors who
pass the selection criteria. In this system, the number and identify of tenderers who can bid gets
frozen at the outset. Thereafter, the bids of all the bidders have to be opened and the work awarded
straightaway to the lowest responsive bidder since every bidder is already screened. Sometimes, this
system is not favored because it consumes a lot of time because of two notice periods once for pre-
qualification and then again for the bid proper and also each bidder knows who the other bidders are.
It is also seen sometimes that an unworthy entity finds a place in the prequalified list. Proponents of
the system, however, say that bidders chosen being entities of great stature there is no fear of a cartel
being formed.
In this system the qualification criteria are set and put in the bid documents. The bidders are asked to
supply detailed information on these criteria. The bids will be opened and bid of the lowest quoted
bidder will be evaluated on the basis of such information. The employer will evaluate and compare
only Bids determined to be substantially responsive. A substantially responsive bid is one which
confirms to all terms, conditions, and specification of the bidding documents. The employer will
award the contract to the Bidder whose bid has been substantially responsive to the bidding
documents and who has offered lowest evaluated bid price.
In this system no bidder knows in advance as to who the other bidders are since any one can
put in a bid at the last minute. However, the downside is that every bidder has to incur expenditure
and effort to prepare a detailed bid whether he is going to qualify or not.
112
14.5.4 Qualification Criteria
The location or layout of the centre line of the road on the ground is called alignment. The
alignment of road shall be decided only after conducting proper surveys and investigation. The
horizontal alignment includes straight paths, horizontal deviations and curves. Changes in gradient
and vertical curves are covered under vertical alignment of road.
In general, new roads will have to follow the existing cart tracks and other such existing
alignments. The provisions of IRC SP 19 and IRC SP 48 shall be followed.
The ideal alignment between two points shall satisfy the requirement as given under:
CHAPTER - 14
Short: It is desirable to have a short (or shortest) alignment between two terminal stations. A
straight alignment would be shortest, though there may be several practical considerations, which
would require deviations from the shortest path.
Easy: The alignment shall be such that it is easy to construct and maintain the road with minimum
subsequent problems. Also, the alignment shall be easy for the operation of vehicle with easy
gradients and curves.
Safe: The alignment shall be safe enough for construction and maintenance from the view point of
stability of natural hill slopes, embankment and cut slope and foundation of embankment. Also, it
Economical: The road alignment would be considered economical only if the total cost including
initial cost, maintenance cost and operational costs, is the lowest.
Sound: The alignment shall be on the firm ground and shall not be susceptible to large settlement,
deformation, landslide, etc.
Aesthetics: While selecting the alignment, the aesthetics of the area shall be borne in mind.
The various factors, which control the road alignment, may be listed as:
Obligatory points: These are control points governing the alignment of the roads. These control
points may be divided broadly into two categories:
Points through which the alignment is to pass. Points which the, alignment shall avoid. Obligatory
points through which the road alignment has to pass may cause the alignment to often deviate from
the shortest path. The various examples of this category may be a bridge site, intermediate town, a
mountainous pass or a quarry.
Traffic: In most of the cases, the people use certain routes traditionally. These may either be due
to convenience, social connection with other areas, etc. The proposed alignment shall keep in view
this traffic flow pattern. At the same time one shall also have fair judgement of future trends in mind.
113
Geometric designs: Geometric design factors, such as, gradient, radius of curve and sight distance
would also govern the final alignment of the road. As far as possible, steep gradient shall be avoided
and limited to the ruling or design gradient. Thus, it may be necessary to change the alignment in
view of the design, speed and maximum allowable super-elevation. It may be necessary to make
adjustments in the horizontal alignment of roads keeping in view the minimum radius of curve.
The absolute minimum sight distance, which shall invariably be available in every section of the
road, is the safe stopping distance for the fast moving vehicles. Also, there shall be enough distance
visible ahead for safe overtaking operations of vehicles. Hence, the alignment shall be finalised in
such a way that the obstructions to visibility do not cause restrictions to the sight distance
requirements. The relevant IRC specifications shall be adopted.
Economy: The alignment finalized based on the above factors shall also be economical. Avoiding
high banking, deep cutting, major crossing and balancing of the cuts and fills can decrease initial
cost of construction. At the same time, care shall be taken to see that it is not likely to involve costly
maintenance and operational expenses. The vehicle operating costs may be given due consideration
PWD ENGINEERING MANUAL-2020 CHAPTER - 14
Various other factors that may govern the alignment are drainage considerations, hydrological
factors, social obligations, etc. The vertical alignment (particularly the gradient and change of grade)
is often guided by drainage considerations. The sub-surface water level, seepage flow and high flood
level are also the factors to be kept inview.
For selection of road alignment in hilly area, reference may be made to Hill Roads Manual (IRC:
SP: 48). In hill roads, additional care has to be taken for ecological considerations, such as:
Stability against geological disturbances Land
degradation and soil erosion Destruction and
denudation of forest
Interruption and disturbance to drainage system
Aesthetic considerations
Siltation of water reservoirs
14.7. Surveys
Final location of the alignment is based on ground verification, and therefore, the engineering
surveys are to be carried out. The surveys may be completed in four stages as below:
Reconnaissance.
Preliminary Survey.
Determination of Final Centre Line.
Final Location and Detailed Survey
To facilitate the survey team in the tentative selection of alternative alignments for subsequent
detailed ground reconnaissance, it will be advisable to make use of modern techniques like, aerial
survey, photogrammetry and remote sensing.
Keeping in view the obligatory points the next step will be to undertake reconnaissance survey in
the following sequence:
Study of topographical survey sheets, revenue maps, geological and meteorological maps, and
aerial photographs or GIS maps where available Preliminary aerial survey/ satellite imagery
reconnaissance (as against Aerial Photographs), where practicable and feasible.
Ground reconnaissance, Final reconnaissance of inaccessible and difficult stretches
114
14.7.2. Preliminary survey:
The preliminary survey is a relatively large scale instrument survey conducted for the purpose of
collecting all the physical information which affects the proposed location of a new highway or
improvements to an existing highway preliminary surveys include census surveys, traffic surveys,
soil and material surveys, topographic surveys and drainage studies.
The main objectives of the preliminary survey are:
To survey the various alternative alignments proposed after the reconnaissance and to
collect all the necessary details of topography, drainage and soil.
To compare the different proposals in view of the requirements of a good alignment. To
estimate the quantity of earthwork, materials and other construction aspects and to work
CHAPTER - 14
out the tentative costs of alternate alignments.
To finalise the best alignment from all considerations.
The survey procedure and map preparation is explained in IRC SP 19.
Making use of the maps from preliminary survey showing the longitudinal profile, cross-sections
and contours, a few alternative alignments for the final centre line of the road are drawn and
studied and the best one satisfying the engineering, aesthetic, environmental, social and economic
requirements is selected. Horizontal curves are designed and the final centre line is marked on the
The alignment finalised after the preliminary surveys is to be translated on the ground by
establishing the centre line. The line to be established in the field shall follow as closely as
practicable the line finalised after the preliminary survey and conforming to the major and
minor control points established and the geometric design standards .However, modifications in
the final location may be made in the field if necessary.
The investigation for bridges shall be done as per the IRC SP 54 and IRC Codes named in Section
(Appendices).1512, Bridges on State Highways, Major District Roads and Other District Roads.
The presence of high non-erodable banks generally offers an ideal site, which reduces the cost of
approach embankments and their protection works.
Narrowness of the channel and large average depth compared to maximum depth:
This ensures large average depth of flow compared to maximum depth of flow and reduced
waterway, which greatly reduces the overall cost of the bridge structure.
Straight reach of the river u/s and d/s of the proposed site:
The course of river or stream over which the bridge is constructed shall have a straight reach for
at least 100 metres on either side of the proposed crossing. Straightness of the reach both u/s and
d/s ensures uniform distribution of discharge/velocity. Curvature in the stream especially on the
u/s leads to obliquity and concentration of the flow on the convex side leading to higher scour,
and consequent cost of foundation and protection works. If the bank on the convex side is
erodible, it may lead to heavy recurring expenditure in protecting the abutments and the
embankment on that side.
Right angled crossing offers minimum possible bridge length and reduces chances of obliquity of
flow with respect to the substructure.
Curves except gentle one are preferably to be avoided on approaches and bridge proper from
visibility and safety considerations. The approaches on both sides shall have a minimum straight
reach of 15m for major bridges and 10m for minor bridges. Also steep gradients shall be avoided
on approaches.
Where existing two-lane highway is proposed for widening to four-lane:
The additional two-lane bridge shall be sited as close to the existing bridge as possible. However,
in case of bridges having well foundations, distance sufficient for generation of passive resistance
of soil shall be provided.
Although it may not be feasible to satisfy all desirable attributes simultaneously, the selected site
shall represent the most desirable mix of the attributes consistent with overall economy, including
the cost of approaches. Sometimes more than one site may have to be examined at the preliminary
stage and comparisons made regarding cost and relative advantages and disadvantages. Based on
such study, the final choice of site shall be made.
116
Guidance may be taken from the following:
IS1892 – Code of Practice for Site Investigation for Foundations may be utilized for guidance
regarding investigation and collection of data.
Test on soils shall be conducted in accordance with relevant parts of IS: 2720 – Methods of Test for
Soils. The tests on undisturbed samples to be conducted as far as possible at simulated field
conditions to get realistic values. IS: 1498–Classification and Identification of soils for general
engineering purposes.
14.9.2. Preliminary Investigation:
Preliminary investigation shall include the study of existing geological information, previous site
reports, geological maps, etc. And surface geological examination. These will help to narrow
down the number of sites under consideration and also to locate the most desirable location for
CHAPTER - 14
detailed sub-surface investigation. If the bridge site is pre-determined due to other reasons, the
preliminary investigation is not necessary and shall straight away conduct the detailed
investigation.
14.9.3. Detailed Investigation:
Based on data obtained after preliminary investigations, the bridge site, the type of
structure with span arrangement and the location and type of foundations, the programme of
detailed investigations, etc. shall be tentatively decided in consultation with the Superintending
Engineer. If preliminary investigation is not conducted, the Assistant Engineer shall decide a
suitable interval, not greater than 20 metres along the alignment for taking trial pits/bore holes.
The competent authority as prescribed in the delegation of powers shall approve the
design of any kind of structure before the detailed estimate is prepared. The Assistant
Engineer/Assistant Executive Engineer and the Executive Engineer shall personally
inspect the site and see that the proposed design can be implemented on ground.
The Development commissioner works/Chief Engineer may, if required, entrust the
design to an empaneled consultant as he deems it fit to the context. If the Development
commissioner works feels that proof checking is required, he may do so either through
CHAPTER - 15
Designs Wing or through another approved agency. Detailed design in all such cases
shall be accepted by the Development commissioner works/ Chief Engineer and
communicated to the authority that has referred the design. The priority for the design
work shall be fixed by the concerned Chief Engineer and communicated to the DCW
For details regarding design methodology refer Appendix – 1500.
119
Chapter 16
16.0 ESTIMATES
All proposals for expenditure on works and on tools and plant in the PWD should be presented
in the form of one or other of the following estimate, for scrutiny by the authority competent to
sanction the same. The estimate shall be prepared using software developed by the department.
PWD ENGINEERING MANUAL-2020 CHAPTER - 16
The software shall contain provision for quantity survey, data preparation with schedule of rates
and local market rate, provisions for online submission and approval of estimates and other
features required. The software shall be updated as and when required.
Preliminary Estimate
Detailed Estimate
Recast Estimate
Working Estimate
Supplementary
Estimate
Revised Estimate
120
16.1.1. Preliminary Estimate.
All plan and non-plan works shall be initiated only through a preliminary estimate. This is
prepared to form a reasonably accurate idea of the probable expenditure and also the essential
features of the proposal, at a stage where the necessity or the general desirability of the works
proposed has not been decided upon by the competent authority.
Preliminary estimates for works shall be prepared by the junior Engineer based on site inspection
with the help of field staff and based on Schedule of rates in force. The Assistant Engineer shall
verify the provisions and ensure that they are adequate and as per appendix 1600 A before
CHAPTER - 16
forwarding it to his superior officer for issuing administrative sanction. In the case of buildings,
Electrical wing shall prepare rough cost estimate for electric works and forward the same to the
concerned Executive Engineer of buildings wing for incorporating the same in the preliminary
estimate. The preliminary estimate must contain a report, giving information on all aspects of the
work for satisfactory completion, with specifications, and justification for the work. It must also
include the details of site conditions, with site plan and layout drawings.
In the case of buildings, the concerned Administrative Department may also be consulted. Where
the help of the Architect is necessary he may be approached through the Development
commissioner works Above all preliminary estimate must be accompanied by a certificate from
the Assistant Engineer stating that ―I, the undersigned hereby certify that this preliminary estimate
has been prepared by me after site inspection and the provisions included are essentially required
and adequate for the proper completion of work‖. Examples of preliminary estimates in respect of
a road, a bridge and a building work are illustrated in Appendix 1600(B1, B2, B3) .
The preliminary project report (PPR) for Administrative sanction should contain the following:
1. Docket Sheet as per Appendix 1600C Site plan (also a District index map)
121
A detailed realistic programme chart for execution.
A certificate signed by an Assistant Engineer as stated above. Plans and designs of Works
Details of quantities of different items of work involved based on the design and drawings.
Normally every item included in the estimate shall conform to the relevant clauses of standard
specification for road and bridge works of MoRTH published by Indian Roads Congress in the
roads and bridges and to the National Building Code in the case of buildings. Where items, which
are not covered by standard specification, are involved, the description of the item shall be full
and clear. A data sheet showing the' estimated unit rate for the different items of work.
For road and bridge works :- the estimate shall be prepared as per the Standard Data Book for the
analysis of rates (MoRTH) published by IRC. (available software can be utilised).
For buildings: - The estimate shall be prepared as per relevant IS codes, National Building
Code 2005 and the J&K Municipal Building Rules.
PWD ENGINEERING MANUAL-2020 CHAPTER - 16
Work done through contract agency, the data shall make a provision for contractor's profit at 10%
of the net cost of the items less cost of departmental materials, if any, supplied. If items not
included in the schedule of rates are included in an estimate, the data for unit rate shall be worked
out based on the market rate for the item or its components. The market rate shall be ascertained
by making local enquiries in the most suitable manner found expedient
The district average conveyance shall be adopted for preparing estimates of all works.
An abstract giving the description of the different items involved and the total quantities, the unit
rate and the cost of each item. To the total of the several items as per this abstract 3.0% is added
to cover the cost of contingencies. This abstract shall also give the total quantities of materials to
be arranged for as departmental supply.
Costing towards mitigation of environmental damages shall also be included either as apart of
civil work (5-7% of cost of work) or as a separate item of BOQ
The estimates for the specialized works pertaining to DG sets, HVAC, Sub Stations, fire fighting
and lifts should be made on category basis as provided in CPWD manual in absence of
specifications laid by concern departments. The name and make of agency / firms be avoided and
these agencies / firms should annually be graded under each category depending on their quality
and specifications.
As far as possible lump sum rules (LS) shall be avoided in a detailed estimate except for petty
items the total of which shall not exceed 5% of the estimate. L. S. provision is also permissible in
case of items whose details cannot before seen at the time of preparation of the detailed estimate
or where it is proposed to work out the details later on. In such cases working estimates shall be
prepared against these lump sum provisions as soon as the details can be known, before the L. S.
are operated on. Such working estimates will be treated as part of the detailed estimate.
There shall be no repetition of item in an estimate.
The estimates for various types of buildings such as School Building, College Buildings, Hospital
Buildings, Residential Buildings, Office Buildings etc to be framed as per standard specifications
and norms as given by CPWD and relevant competent authority.
16.1.3. Working Estimate
A working estimate is intended to give the details of the works and the cost thereof, which are to
be carried out against a L. S. provision made in an estimate. Normally therefore, the working
estimate shall not exceed the amount of L. S. provision in the estimate for the main work. If
however, it is not possible to limit the cost of the works included in the working estimate to the
L.S. provision, care shall be taken when sanctioning the working estimate that the overall excess
is within the powers of the authority sanctioning the working estimate. Working estimates shall
be prepared with the same care as in the case of detailed estimate. It shall be as realistic as
possible. If the works as per the working estimate are to be entrusted to the contractor for the
main work' then the rates to be included in the working estimate shall be his quoted rates for
agreed- items and rates worked out as per his agreement for allied and extra items. In cases where
a different agency can be entrusted with the works as per the working estimate, the rates to be
adopted shall be based on the schedule of rates prevalent at the time of preparation of the working
estimate and on the market rates where there is no schedule item.
In respect of projects, working estimates shall be sanctioned by subordinate officers only after
consultation with the authority under the control of the project, to whom a copy of the sanctioned
working estimate shall also be sent. The authority under the control of the project shall
122
maintain a register of all working estimates sanctioned against each particular sub head of the
project estimate, to see that the provisions in the sanctioned project estimate are not exceeded.
Each working estimate shall be treated as a detailed estimate for exercising the powers of
sanction.
It may sometimes happen that after the estimate for a work has been technically sanctioned but
before it is taken up for execution some changes are found necessary in the estimate for the
work. In such cases a fresh estimate may by prepared and got sanctioned in cancellation of the
originally sanctioned estimate. This fresh estimate is called a recast estimate and is dealt with as
if it is an original estimate. If however, before a recast estimate is prepared some expenditure
has been incurred in an originally sanctioned estimate, then this procedure cannot be followed
and instead a revised estimate shall be prepared and got sanctioned.
CHAPTER - 16
16.1.5. Supplementary Estimate
Any development or extension of a work thought necessary while the work is in progress which
is not fairly contingent on the work as first sanctioned must be converted by a supplementary
estimate. In effect this supplementary estimate is an original estimate for the additional works
consequent on the development or extension of a project or work under execution.
Administrative sanction shall therefore be obtained for the supplementary estimate from the
same authority, which sanctioned the original estimate even if the cost can be met from savings
in the original estimate. The competent authority in this case is the authority that is empowered
to accord administrative sanction to the work as a whole, i.e., including original and
National Highways are the responsibility of the Government of India and the JKP.W.D. acts as
the agent of the Government of India for investigation, construction and maintenance of
National Highways.
Agency charges fixed from time to time will be added in the estimate to cover the cost of
establishment. For original works chargeable to National Highways, the designs shall be sent for
technical scrutiny and comments, to the Government of India, Ministry of Road Transport and
Highways (MoRTH). After it is cleared technically, the executing agency shall prepare a
detailed estimate but forward only the general abstract of cost along with detailed information to
the central government for accord of administrative approval. The executing agency shall
accord technical approval and financial sanction to the detailed estimate already prepared within
3 months from the date of according administrative approval by the central government and
shall commence execution of works within contract time from the date of according
administrative approval failing which the Administrative approval accorded by the central
government shall stand cancelled automatically and executing agency shall approach central
PWD ENGINEERING MANUAL-2020 CHAPTER - 16
A separate estimate shall be prepared annually for all anticipated ordinary repairs of each
building or road/bridge work or group of such works during the working year. No
administrative sanction shall be required for maintenance and repair works. The original Typical
Maintenance Estimates (TME) and the changing TME due to modifications in the plan of
buildings shall be approved by the Chief Engineer Subsequent change in TME due to schedule
revision shall be approved by the Executive Engineer The Chief Engineer shall accord approval
subject to availability of funds and necessity. Estimates for maintenance work are dealt with in
Chapter 25, Asset Management and Chapter 26 to 28.
124
Chapter 17
PWD schedule of rates shall be followed by all the government departments while preparing the
estimate for works funded by the State Government. All estimates shall be prepared based on
actual conveyance. SoR shall be updated every year with effect from 1st April. For this purpose
Chief Engineer DIQC is the authority to finalize the SoR for approval of Government. The CE
DIQC shall publish in the Web Site before 15th March. The source for various construction
materials shall be fixed by the Chief Engineer R&B on 1st April once in every 5 years based on
CHAPTER - 17
the proposals submitted by the Executive Engineers of each district for periodical revision of
Schedule of Rate.
MORTH data as per IRC Guide lines for roads and CPW D data and National Building Code for
buildings shall be adopted.
The Executive Engineer of each district shall fix local market rates for materials and labour
twice every year. The rates shall be fixed as on 1st April and 1st October every year. These rates
shall be followed by Executive Engineers of all wings for preparing local market rate
justification estimate for tender approval. The justification estimate shall also include 10%
contractors profit and 5% overhead charges. The justification estimate shall be submitted to the
tendering authority directly by the Assistant Engineer before the date of opening oftenders.
125
Chapter 18
18.0. SANCTIONS
The estimate for an original work requires the following sanctions before it is taken up for
execution. Administrative Approval
Technical sanction
location. The Executive Engineer shall forward the preliminary estimates and related documents
to the Chief Engineer with a copy to Superintending Engineer for his comments. The
Superintending Engineer shall forward his comments if any within seven days of receipt failing
which; it is deemed to be correct and approved by him. After the preliminary estimate and
sketch plans are received, the concerned department or government will decide whether further
steps shall be taken to execute the work and if so, the appropriate authority vested with power of
Administrative Sanction will issue the Administrative sanction. In some cases provisions for
certain works required by other departments of the State are made in the P.W.D. budget even
before formal Administrative Sanction has been accorded. The Executive Engineer in whose
jurisdiction the work is located shall then take the initiative in contacting the District Officer of
the concerned department for the necessary information regarding requirements, location etc.
The Executive Engineer shall then prepare a preliminary estimate with sketch plan and forward
to the Administrative Department if it is within his powers of technical sanction or to the
Superintending Engineer if it is beyond his powers of sanction. The Superintending Engineer
shall forward it to the Administrative department if it is within his powers of sanction and if it is
beyond his powers he shall forward it to the Chief Engineer. The Chief Engineer shall forward
the preliminary estimate to the Administrative Department for sanction. Where the work
concerned is a project beyond the power of sanction of Chief Engineer, Administrative Sanction
is to be accorded by Administrative department.
In case of buildings the competent authority shall accord administrative approval for works on
the basis of prelimery estimate or detailed estimate as the case may be. The estimates shall be
based on sanctioned plinth area rates/sanctioned schedule of rates. The administrative approval
by competent authority to be accorded only after technical vetting/sanction from concern
competent authority.
126
18.1.2. Technical Sanction.
In all cases, the competent authority in the P.W.D. is on the basis of detailed project report for
accords technical sanction. It implies that the competent technical authority is satisfied about the
suitability of the work to meet the requirement, its structural soundness and about the quantities,
specifications and rates of the different items of work, which will be involved in completing the
work. Before according T.S for major projects exceeding Rs. 10 crores, the Environment Cell
shall review the projects to ensure compliance to environmental regulations before being
accorded Technical Sanction. The TS issuing authority shall take into consideration the views
and comments recorded in the docket sheets by the intermediate officers and effect changes if
required before issuing TS.
Before according Technical Sanction to a work relating to another Department, the plans shall
be got countersigned by the head of the concerned department or such Officer who may be
delegated with power for this purpose.
Technical Sanction shall be issued only based on the Administrative Sanction for the work and
CHAPTER - 18
the amount of Technical Sanction for any work shall not exceed the amount of Administrative
Sanction by more than 10% and it should be in confirmation with GFR 2017. Before
Administrative Sanction is issued availability of funds shall be ensured for execution of the
work either through budget provision or through re-appropriation from other works under the
prescribed rules for such re-appropriation or by deposit in the case of deposit works.
The following are the usual sources of funds for execution of works. By a specific provision for
the work in the Budget for the year.
By re-appropriation of savings in the budget allotments for other work- subject to the rules
regarding such re-appropriation.
By obtaining a supplementary grant for the work.
Other agencies
The detailed project report for all original works should necessarily contain the preparatory
documents such as the environmental impact assessment report and / or the environmental
management plan and/ or the special environmental conditions to the contract. The environment
cell should vet these and provide a note prior to according the Technical Sanction. This note
should confirm the project‘s adherence to the environmental requirement of the code and
manual. Technical Sanction for an estimate is issued in the approved form only. The delegation
of powers for technical sanction at various levels are given in the appendices.
127
18.1.2.1. Technical Sanction Register
In every office where technical sanctions are accorded, a register in the approved form shall be
maintained as under 1800A. Each estimate sanctioned in a financial year shall be numbered
consecutively and entered in the register. Technical sanctions given to working estimates need
only be noted against the sanction given for the main work originally and need not be given a
separate number and noted in the register. When technical sanction is issued for a revised
estimate and a fresh number is given for this estimate then the fact that the original estimates
stands cancelled shall be noted against the original sanction. Correspondingly, there shall be one
entry in revised sanction quoting the original estimate. When the supplementary estimate is
sanctioned, the original technical sanction shall be cancelled and fresh technical sanction issued
PWD ENGINEERING MANUAL-2020 CHAPTER - 18
including the supplementary estimate. The respective divisional offices and the central PWD
offices must also maintain the electronic form of the Register.
The power to Accord Administrative Approval, Technical Sanction and Award of Contracts shall
be as per S.O. 15, Dated. 09-01-2019, given in appendices.
18.1.3 The Power to Purchase of stores and other contingent / Miscelleneous expenditure shall be as per
delegation made vide S.O. 58 Dated 31-12-2.19, given in appendices
128
Chapter 19
CHAPTER - 19
the basis of their financial resources, professional experience and records, as follows.
Class A
Class B
Class C
Class D
129
SRO : 122 Dt: 26th May 1992 : -
In exercise of the powers conferred by Section 1C of the Jammu and Kashmir registration of
Contractors Act, 1956, (Act No. XIV of 1956)., the Government hereby makes the following
rules, namely:-
I. These rules may be called the Jammu and Kashmir Registration of Contractors Rules, 1991
II. They shall come into force from the date of their publication in the Government Gazette.
III. They shall apply to the following departments namely.
(a) Roads and Buildings Department;
(b) Irrigation and Flood Control Department;
PWD ENGINEERING MANUAL-2020 CHAPTER - 19
130
2. Civil Works Contractors: - There shall be following Classes of contractors in each
Department as per SRO 196 dated:- 28th June 2011:-
CHAPTER - 19
Class ―D‖ Upto Rupees fifteen lacs Any one of the three regions of J&K
State Viz Jammu, Kashmir & Ladakh
(1) The applicant seeking enlistment in class ‗C‘ and class ‗D‘ shall be required to choose the
131
Eligibility:- No Person shall be eligible for being registered as Contractor under these rules
unless:
Dozer of shovel 1
PWD ENGINEERING MANUAL-2020 CHAPTER - 19
Truck or Tipper 2
Concrete Mixer 2
Concrete Vibrator 2
Compressor 4
Diesel Generator with welding plant 1
Concrete Compression
Testing Machine 1
Theodolite 1
Surveying Level 1
At least one Degree holder (Civil) and one Diploma Holder (Civil or Mechanical).
132
(iii) Possess the following plants and equipment namely:
Truck or tipper -1
Concrete Mixer -2
Concrete Vibrator -2
Compressor -1
Diesel Generating set with Welding plant concrete compression -1
Testing Machine -1
Surveying level -1 ;and
iv) Should have successfully and satisfactorily completed as a class ‗B‘ contractor at least three
works of an aggregate value of not less than Rs. 20.00 lacs and should have worked as a Class B‘
CHAPTER - 19
contractor for three years; and
v) In case of technically qualified individual or firm the field requirement in respect of
construction of civil works by an individual/ any one of the partners of the firm required shall be 7
years for a Degree holder in civil Engineering and 15 years for a diploma holder in civil engineering
( c) In the case of class ‗B‘ Contractors or the firm or individual:-
(i) Has sound financial capacity to execute the works of department in that class and
(ii) Shall be required to employ at least one diploma holder (civil) at the award of work.
133
(e) In the case of Class ―D‖ contractors, the individual or firm:
(i) Has sound financial capacity to execute the works of the department in that class, and
(ii) Should have worked at least with any registered ‗D‘ class contractor for a period of one year and
acquainted himself or themselves sufficiently with the elementary knowledge required for execution
of civil works the certificate to this effect should among other things indicate the name of work where
the applicant has worked. Provided that no field experience shall be required for enlistment in this
class for degree and diploma holder in civil engineering
PWD ENGINEERING MANUAL-2020 CHAPTER - 19
Note: The service period of a degree of diploma holder in civil engineering in government or semi-
government organization shall be considered as a field experience required of the eligibility
Explanation:
For purpose of this rule individual or firm shall be constituted to have sound financial capacity if he or
it possess property and bank balance not below the extent shown against each written certificate of an
officer not below the rank of Assistant Commissioner (revenue) or a scheduled bank certifying
minimum cash balances during past three months
Class Movable ( liquid) Immovable (assets)
Class Special For Rupees Five Lac Rupees Fifteen Lac
Class A For Rupees Three Lac Rupees Seven Lac Fifty
Thousand
Class B One Lac and Fifty Thousand Rupees Two Lac Fifty
Thousand
Class C Rupees Fifty Thousand Rupees One Lac Fifty Thousand
Class D Rupees Twenty Thousand Rupees Fifty Thousand
Further the contractors otherwise eligible to various class under these rules and possessing degree
or diploma or diploma in civil, engineering shall be entitled to fifty percent concession in respect
of, financial requirement both under movable and immovable assets as defined above.
134
classes except class - D)
(iii) Legal bond to the effect that machinery and immovable property declared by
him/them is free from all encumbrances except the mortgage of the lending
bank/public sector financial institution and will not be transferred or disposed
by him/them without specific authorization of the registering authority (for all
classes.)
iv) Legal bond authorizing the department to recover any money due from him/them
on any account by sale, auction of his/their immovable property (for all classes)
v) Character certificate to be issued by an Officer being not below the rank of
Superintendent of Police of the District concerned after due verification from
CID.
(b) That the applicant is not already in service in any Government department,
Corporation or undertaking or member of either House of the parliament or legislature.
District Development Board or a student of any educational institute or in receipt of any
stipend from the government
(c) That the applicant (s) if a retired employee (s) of Government Corporation or
undertaking is not disallowed under service conduct Rules of the
Government/Corporation/undertaking from where he has retired.
(d) That the applicant has not been declared insolvent by a court of competent
Jurisdiction:
(e) That the applicant has not been convicted of an offence under chapter X VII and
VIII of Ranbir Panel Code same of 1989 of under the Hoarding and profiteering
Prevention Ordinance (VIX) Samvat 2000.
(f) That the applicant (s) has not/have not backed out from any contract in Public
Works Department;
135
2. On receipt of application accompanied by certificates and affidavits indicated in sub rule (1)
the applicant or authorised representative of the firm seeking application may be called upon personal
attendance before the Head of the Department
3. The Head of Department to whom application has been made shall there on scrutinize the
application and unless the applicant is found eligible, he shall enter the contents of the application in
a register Initiated by him for the purpose and inform the applicant accordingly for payment of
registration fee, prescribed here under:-
(I) Class Special Twenty thousand
PWD ENGINEERING MANUAL-2020 CHAPTER - 19
4. The applicant may be registered even for a Class lower then applied for
Note: -
A Central register of contractors so enlisted shall be maintained by the Public works Department as
per format specified in Form No. IV. Head of Department shall furnish information in the prescribed
format to the department for purpose of maintaining a consolidated record of contractors.
(d) If the head of the department is of the opinion that the work and conduct of the applicant has not
been satisfactory in relation to the work of the public works department executed by him in the
past.
9. Issue of certification.
(1) The head of the department to whom application, has been made shall upon scrutinizing the
application, deposition of prescribed fee and unless the applicant is in eligible under rule 4 or
the registration or renewal thereof is refused under rule 5 or 6 and ensuring that the contents
of the application have been recorded in a register maintained by the department for the
purpose, issue a certificate of registration of the class in form II.
(2) Once the certificate of registration has been issued the contractor shall be eligible to purchase
Besides the above affidavit, the following certificate shall be produced from the concerned
Superintending Engineers or Executive Engineers under whose supervision the works have been
executed during the period by the contractor, seeking renewal of registration;
(a) Character certificate to be issued by an officer not less than the rank of Superintendent of
Police of concerned district after verification from CID.
(b) A certificate to be issued by an officer not less the rank of Superintending Engineers that the
137
applicant has not/have not backed out from the contract in public works department.
(c) A certificate to be issued by an officer not below the rank of superintending engineer that the
applicant‘s work and conduct remained satisfactory in relation to work of public works department
and the quality of work executed by the contractor remained good.
(d) A certificate to be issued by an officer not below the rank of Executive Engineer that the
applicant has not been a defaulter in making payment to the labour engaged by him and there have
not been or is any labour claim/award pending against him in a labour court on account of works
allotted.
(2) An application for renewal of registration shall be made to the head of the department in
form III and shall be accompanied by the following fees;
PWD ENGINEERING MANUAL-2020 CHAPTER - 19
1) If at any time, after a person is registered as contractor, the head of department is satisfied
that such contractor has incurred any of the disqualification in these rules, he shall serve a
notice upon the contractor, indicating the ground on which it is proposed to suspend or
blacklist or remove his name from the register to show cause why such order should not
be issued.
(2) If the head of department is of the opinion that the explanation tendered by the contractor is
not satisfactory he shall pass an order of suspension of black-listing or removal of the name
of the contractor from the register and such order shall be communicated to the contractor.
138
iii) Third time backing out from the contract shall cause black-listing for five years provided
that no such order of suspension or black-listing or removal shall prevent the contractor
from executing and completing the works or effect his rights and obligations in respect of
any contract sanctioned to him that department or any other department while the
registration was in force.
12. All orders passed by head of department under rule 11 shall be communicated to the department
and also be got published in the Government Gazettes.
13. As per SRO-277 Dated:- 26th July 2010
a) Competent Authority means Chief Engineer in respect of ―Special class‖ and ―class A‖ and
Superintending Engineer in respect of class ―B‖, ―C‖ , and ―D‖ .
139
Chapter 20
Works in the public works department are executed by any one of the following methods.
Tenders are floated online (jktenders.gov.in) as per standard bidding document
By Item Rate Contract: In this contract the total approximate quantities of the respective items
of work and the time of completion are specified and the contractual obligations cover the rate
the approximate quantities involved and the time of completion. In the case of Item Rate
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Composite Tenders shall be followed for all kinds of Building and Road works:
(1) System of composite tendering shall be followed for all kind of building and road works
(irrespective of cost). Apart from civil work and horticulture work, the composite tender should
also include component of internal electric installations and other internal & external electrical
works including services.
(2) If requirements of the work so demand, the T/S Authority may dispense with the system of
composite tendering with recorded reasons.
Guidelines on composite tendering are given under:
1. Only one agency is fixed, i.e. the main contractor who is responsible for executing the entire
work. The Engineer in Charge of the major component of the work calls bids for the composite
work. The cost of bid document (if any) and Earnest Money is fixed with respect to the combined
estimated cost put to tender for the composite bid.
2. The officers of minor disciplines within their individual T/S powers, approve and submit the
schedules for minor components of the work along with terms and conditions to the T/S Authority
of the major component well in time. Technical sanction and approval of NIT for the combined
work is accorded by the competent authority of the major component under whose T/S powers the
total estimated cost of work falls, after combining the cost of major and minor components. If the
combined amount of the detailed estimate for the composite work does not fall within the T/S
powers of the official in-charge of the major component, then the same is sent to his/ her next
higher authority competent to accord T/S and approve the NIT for the composite work.
3. The officers of individual minor components prepare market rate justification of the minor
components before opening of the technical bid (in case of two/three bid) / financial bid (in case
of single bid) and hand it over to the NIT approving authority. The NIT approving authority
prepares the market rate justification of the total work before opening of technical bid. In case of
tenders to be accepted by RWB/CWB, the market rate justification is submitted by the NIT
approving authority to the RWB/CWB before opening of technical bid.
4. The eligible tenderers quote rates for various items of major as well as minor components of
work. The lowest tenderer is decided based on quoted rates in respect of all the schedules attached
in tender documents. It is obligatory on the part of the main contractor to sign the tender
documents for all the components.
5. The Department lays down eligibility criteria for agencies responsible for execution of
specialized components of works. Agencies engaged by the main contractor are required to fulfill
the laid down criteria. In case the main contractor himself meets the required eligibility criteria as
laid down by the Department for specialized work, he is allowed to execute the same after due
verification etc.
6. The main contractor gives detailed execution programme of the work which forms part of his
agreement with the department. He indicates in the programme, the time/stage of the work when
the agencies of specialized components of works will be deployed by him.
7. Acceptance of the tender is done by the NIT approving authority within his powers to accept
tenders as per the Financial powers delegated to the Officers vide S.O. 15, Dated 09-01-2019, and
is conveyed by the Engineer in charge of major component of the work on behalf of the Lt.
Governor of the Union Territory of J&K. After the work is awarded, the contractor signs copies
140
of agreement depending upon number of Executive Engineer‘s or any other authority designated
by Chief Engineer, PW(R&B) Department, in charge of minor components and hands over one
set of agreement to concerned officer of minor component. Executive Engineer or any other
officer as notified by Chief Engineer, PW (R&B) Department from time to time, of major
component will operate part A and part B of the agreement. Executive Engineer or any other
officer as notified by CPWD Directorate from time to time, in charge of minor components
operate Part C along with Part Á‘ of the agreement.
8. The main contractor enters into MOU with agencies associated by him for execution of
specialized component as per NIT conditions. .
9. Running payment for the major component is made by Engineer in Charge to the main
contractor. Running payment for minor components shall be made by the Executive Engineer in
charge or any other officer as notified by Chief Engineer, PW (R&B) Department from time to
time, of the discipline of minor component directly to the main contractor.
EPC (Engineering, Procurement and Construction) /Lump sum contract: Here the total cost
of the completed works as per drawings and specifications and the time of completion form the
essence of the contract. In adopting this contract the drawings and specifications must be full
and complete in order to prevent claims arising for variations due to any ambiguity in them.
Cases may, however, arise where some modifications to the designs or specifications are found
necessary due to site conditions or other reasons. The bidder shall assess and evaluate &
convince himself that the amount quoted by him is adequate. The department will not entertain
any extra claim for such modification within the scope of the work, during execution. This
method shall be adopted only in unavoidable circumstances where the situation warrants. The
cutoff value of projects, above which all contracts will be taken up under EPC methodology will
be decided by the Competent Authority.
141
For executing contract on EPC methodology, the following important provisions are to be
considered while framing estimate, preparing NIT etc:
(1) The consultant appointed by the NIT approving authority shall prepare the concept design,
preliminary drawings and specifications based on detailed requirements of the work, in
consultation with the client before preparation of Preliminary Estimate.
(2) Soil investigation report shall be appended in the NIT for indicative purpose only.
(3) The responsibility of investigations, designing, planning, procurement, construction, safety,
quality, and risk of engineering lies with the contractor and the same will be incorporated in the
NIT.
(4) Mode of measurements for payment purpose will be decided by the NIT approving authority.
(6) The award of work shall be decided based on competitive call of tenders. The Chief Engineer
ascertains the reasonability of prices using analytical methods such as tendered amount for similar
works whose tenders were accepted in the recent past, PAR rates duly enhanced by the current
cost index and any other method approved by the Chief Engineer for ascertaining the
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
142
(ii) Floor plans for building etc. and geometry for other works etc.
(iii) Elevations/Sections/Perspectives .
(iv) Layout plan(s)
(i) 3-D Block view (s)
(ii) Area and/or Length statements as applicable
(iii) Specifications in detail for each structure/building and its services to be included in the
DPR.
6. The DPR (in respect of works in which detailed engineering including architectural design is
done before sanction) or PPR (Where only conceptual engineering and architectural planning is
done before sanction) based on the PPP submitted to the client includes, in addition to the PPP,
the following:-
(i) Brief description of the Procurement Method (which also mentions the name of work).
(ii) The obligations on the part of the client department, PWD, and the contractor with specified
time limits for smooth execution of work.
Percentage rate contract: In this type of contract the departmental rates for the different
items of work in an estimate are published and the contractor quotes his rate at a percentage
above, or below or at par the estimate rates so published. Only a single percentage applicable to
all the items is quoted and this percentage rate is applicable to extra items, if any, are found
necessary during construction. Other conditions of contract are similar to those applicable to
schedule contracts.
A modification of this type of contract is when, instead of estimate rates for a work, the schedule
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
of rates is published and the contractor is asked to quote a percentage above, below or at par, the
schedule of rates so published.
The most appropriate form of contract shall be decided upon in individual cases before inviting
tenders. The authority competent to accord technical sanction to the estimate is the authority,
which will decide whether the work is done departmentally or through contract. In the latter
case, the authority will also decide upon the form of contract. This method shall be followed for
all works up to and including TS powers of Superintending Engineer.
A Performance Based Maintenance Contract (PBMC) is a lump sum contract of all ordinary
maintenance activities (Standard Jobs) in which the contractor is paid a set monthly/quarterly
premium irrespective of the amount of work required to keep the road or building safe and
defect-free. It becomes the contractor‘s responsibility, without separate direction from PWD, to
keep the road condition to a specified standard and period and he may incur some financial
penalty if he fails to achieve this standard. Part of the contract requirement is use of specialized
equipment specifically for road maintenance, and there are limited provisional works for larger
repairs/resurfacings. This system shall be adopted only for major works on roads/Buildings,
which satisfy minimum standards as per norms. The road or buildings to be included in this
contract shall be decided by the Chief Engineer. The contract shall be valid for minimum period
of three years beyond the defect liability period. If necessary, an initial rehabilitation work shall
be done before arranging PBMC. Annual stage contract shall be incorporated for roads identified
by Chief Engineer with a maximum financial ceiling defined by administrative department.
These works shall be tendered well in advance so that the participation is large.
144
(7) Estimates of fees of Private Architect/ Consultant are to be added in the estimate only.
(8) If specific provision is not available in the sanctioned estimate, then separate enabling estimate is
to be submitted to the client for fees of Architect/Consultant.
(9) Details for Execution, realization of deposits and settlement of accounts of Deposit works are
given as under:
Realization of Deposits :
(i) Whenever a deposit work is to be under taken, the deposit is realized before any liability is
incurred on the work.
(ii) In the case of deposit works of autonomous bodies which are financed entirely from Government
grants, and from whom receipt of deposits is assured, 33-1/3% of the estimated cost of the work
or 10% of the estimated cost of the work, is got deposited inadvance at the time of issue of A/A
&E/S and balance amount i.e.23-1/3% of the estimated cost of the work is got deposited before
award of work. Thereafter, the expenditure incurred is got reimbursed through monthly bills
145
20.4. Bidding of works
Before bids are invited for a work there should be Administrative Sanction for the work Technical
Sanction for the work 100% possession of hindrance free land. However, in the case of road
projects bids can be invited with prior permission of Govt. provided 60% of land required is
available and balance can be made available during the course of construction.
The arrangement of works shall normally be made through bids (tenders) for works having
administrative and technical sanctions with proportionate provisions of funds in the Budget for the
year. The bidding of works shall be resorted to only after getting possession of the required land
free of encumbrances.
If there is a time lag of one year between the date of preparation of the estimate and the date of
tender of a work, it is necessary to verify whether any changes have occurred necessitating
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
modification to the provisions in the estimate. If the modifications required are only minor the
officer competent to enter into contract may invite tenders on the basis of the sanctioned estimate.
Otherwise the estimate shall be recast and tenders invited on that basis.
The bid document shall not contain conflicting vague and ambiguous provisions resulting in
disputes, delays and financial losses. The stipulated period of completion of work shall be realistic
and based on magnitude of work.
Subordinate officer shall not split the bigger work into smaller work so that these small works fall
within their jurisdiction in respect of TS and award of work etc. The entire work shall be tendered
as one work.
Adequate time for publicity shall be given so that competition in tendering is not restricted.
The Biding of works shall be as per PWD Standard Biding Document through e-Tendering
process on the web site www.jktenders.gov.in.
The tenders which do not fulfill the pre-requisites as per tender notice and tender documents can
only be rejected.
If the lowest bidder backs out, there should be re-tendering in a transparent and fair manner. In
such a situation, the NIT approving authority may call tender at short notice if so justified in the
interest of work. The contractor who has backed out shall not be allowed to participate in the
retendering process. All notices regarding any change in dates and time of receipt/opening of
tenders are to be uploaded on the website.
146
20.5.1 Pre-requisites for Empanelment by PWD as Hot Mix Plant Owner
The plant holder seeking Empanelment for Hot Mix Plant shall provide the following information to
the PWD Department for consideration of Empanelment.
There after the same shall be verified by the concerned Executive Engineer and Empanelment
certificate issued by the Chief engineer PW(R&B) Department Kashmir/Jammu Engineer PWD after
the case is recommended for consideration by the concerned Superintending Engineer. The following
supporting documents shall be appended with the application for consideration of Empanelment: -
Make and Model of the plant.
Stability & durability of tools and equipment acquired. Capacity of the plant. Inventory of equipment.
Revenue papers of land on which the plant has been established. List of staff technical/Non-technical
to be working at plant.
NOC from Pollution Control Board. Material testing laboratory.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Character Certificate to be issued by respective Superintendent of Police. NOC‘s from all the line
PHE Department
PDD Department
Education Department
Health Department
Forest Department
Any other documents as required by the concerned chief engineer in the interest of Government
147
CHAPTER - 20
PWD ENGINEERING MANUAL-2020
STANDARD BIDDING DOCUMENT
(Standard Template)
148
20.6.1.1. Instructions to Bidders (ITB)
Table of Clauses
A General
1 Scope of Bid 20 Deadline for Submission of Bids
2 Source of Funds 21 Modification & Withdrawal of Bids.
3 Eligible Bidders
CHAPTER - 20
5 One Bid per Bidder
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
24 Clarification of bids
B Bidding Documents 25 Examination of Bids and Determination of
10 Amendment of Bidding
Documents 27 Award of Contract
D Submission of Bids
18 Bidding through e-
Tendering
19 Electronic submission of
Bids
149
A. GENERAL
1. Scope of Bid
1.1 The Employer (named in Appendix to ITB) invites bids for the construction of works (as defined
in these documents and referred to as ―the works‖) detailed in the table given in the ITB. The
bidders may submit bids for any or all of the works detailed in the table given in the ITB.
1.2 The successful bidder will be expected to complete the Works by intended completion date
specified in the Contract data.
1.3 Throughout these bidding documents, the terms ―bid‖ and ―tender‖ and their
derivatives(bidder/tender, bid/tender, bidding/tendering etc.) are synonymous.
2. Source of Funds
2.1 The expenditure on the budget will be met from the budget of Govt. of India. .
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
3. Eligible Bidders
3.1 This Invitation for Bids is open to all Bidders as mentioned in NIT (Individual/Joint
Venture).Joint venture bidding is allowed for the works costing Rs.15.00 Crores and above in
J&K State/UT.(to be read with clause 2.11 of section 2 –qualification information.)
3.2 All Bidders shall provide in Section-2, Forms of Bid and Qualification Information, a
statement that the Bidder is neither associated nor has been associated directly or indirectly,
with the consultant or any other entity that has prepared the design, specifications and other
documents for the project or being proposed as Project Manager for the Contract. A firm that
has been engaged by the Employer to provide consulting services for the preparation or
supervision of the work, and any of its affiliates shall not be eligible to bid.
3.3 Bidders from Joint Venture are allowed as per 3.1and as per clause 2.11 of Section- 2
(qualification Information).
4.1. All Bidders shall provide in Section-2, Forms of Bid and Qualification Information,
preliminary description of the proposed work method and schedule, including drawings and charts,
as necessary. The proposed methodology should include programme of construction backed
with equipment planning and deployment duly supported with broad calculation and quality
assurance procedures along with Quality Assurance Plan(QAP), proposed to be adopted justifying
their capability of execution and completion of work as per technical specifications, within
stipulated period of completion
4.2. In the event that prequalification of quotation bidders has been under taken, only bids for
prequalified bidders will be considered for award of contract, The qualification bidders should
submit with their bids any information updating their original prequalification application‘s
application or alternatively confirm in their bids that the originally submitted prequalification
remains essentially correct as of date of bid submission. The update of confirmation should be
provided in section 2 a copy of the original prequalification application and letter of
prequalification should also be furnished. With the updated information, the bidder must continue
to be qualified in accordance with the criteria laid down in the prequalification document. All
bidders shall also furnish the following the information in Section 2.
4.3. All the bidders shall include the following information and documents with their bids in
150
Section -3 Qualification Information unless otherwise stated in Appendix to ITB.
a) Copies of original documents defining the constitution or legal status, registration card with
latest renewal, place of registration, and principal place of business; written power of attorney of
the signatory of the Bid to commit the Bidder
b) Financial turn over, year-wise, achieved on execution of civil
engineering works for the last five years i.e. to duly certified by the Chartered Accountant
c) Completion Certificate of having executed and completed or substantially completed successfully
single wok of similar nature as defined under clause 4.6 (A-ii)of qualification criteria in any Govt.
or Semi- Govt Department during the last five years duly issued by an officer not below the rank of
Executive Engineer or equivalent.
CHAPTER - 20
(d) The bidder shall also furnish details of other civil works of similar nature executed and completed
in any Govt. or Semi Govt. department during the last 5 years .and details of works underway or
contractually committed; and clients who may be contacted for further information on those
contracts;
(e) Copy of PAN card issued by the Income TAX Authority.
f) Reports on financial standing of the bidder such as profit and loss statement, balance sheet and
auditors report for the last five years and supported with ITR and TDS for the last five years.
(g) Major items of construction equipment proposed to carry out the Contract;
(h) Qualifications and experience of key site management and technical personnel proposed for
contract;
Bids for joint venture are accepted for the works valuing Rs.15.00 Crore and above. (To be read
with clause 2.11& 2.12 of section-2 –Qualification Information.)
The applicant should have achieved minimum annual value of general construction work (as
certified by Chartered Accountant, and at least 50(fifty) percent of which is from Engineering
(Civil/Electrical/Mechanical as relevant to the work being procured) construction works carried
out in any of the year over a stated period (normally five to seven years, ending 31 st March of
previous year), calculated by applying an appropriate multiplier to the projected annual
151
construction expenditure on the subject contract. The multiplier of 2 may be used, but for very
large contracts should not be less than 1.5.
However, in case of Road/Bridge works under MoRTH, NABARD and State Sector, the
guidelines as circulated by MoRTH shall apply while as in case of Road/Bridge works under
PMGSY, the guidelines as circulated by PMGSY shall apply.
b) Particular Construction Experience and Key Production Rates
The applicant should have:
1. Successfully completed or substantially completed similar works during last seven years
ending last day of month previous to the one in which applications are invited should be either
of the following:-
1.1 Three similar completed works costing not less than the amount equal to 40 (forty) percent
of the estimated cost; or
1.2 Two similar completed works costing not less than the amount equal to 50 (fifty) percent
of the estimated cost; or
1.3 One similar completed work costing not less than the amount equal to 80 (eighty) percent
of the estimated cost; and
2 The applicant should also have achieved the minimum annual production value of the key
construction activities (e.g dredging, piling, or earthworks etc) stipulated.
The similarity of work shall be pre-defined based on the physical size, complexity
methods/technology and /or other characteristics, and scope of works. Substantial completions
shall be based on 80 (eighty) percent (value wise) or more works completed under the
contract. For contracts under which the applicant participated as a joint venture member or
sub-contractor, only the applicant‘s share, by value, shall be considered to meet this
requirement. For arriving at cost of similar work, the value of work executed shall be brought
to current costing level by enhancing the actual value of work at simple rate of seven percent
per annum, calculated from the date of completion to the date of Bid opening.
However, in case of Road/Bridge works under MoRTH, NABARD and State Sector, the
guidelines as circulated by MoRTH shall apply while as in case of Road/Bridge works under
PMGSY, the guidelines as circulated by PMGSY shall apply.
(a) Availability (either owned or leased or by procurement) of the key and critical equipment for this
work as per Annexure –I below.
Based on the studies, carried out by the Engineer, the minimum suggested major
CHAPTER - 20
equipment to attain the completion of works in accordance with the prescribed construction
schedule are shown in the Annexure-I below:-
153
PWD ENGINEERING MANUAL-2020 CHAPTE
The Engineer in charge shall be at liberty to direct the contractor to get additional plant and
equipment if necessary for timely complementation of project. The applicant should own or
should have assured ownership/lease/hire the following key items of equipment, in full working
order, and must demonstrate that, based on known commitments; they will be available for use
in the proposed contract.
The Bidders should, however, undertake their own studies and furnish with their bid, a detailed
construction planning and methodology supported with layout and necessary drawings and
calculations (detailed) as stated in clause 12 of ITB to allow the employer to review their
proposal. The numbers, types and capacities of each plant/equipment shall be shown in the
proposals along with the cycle time for each operation for the given production capacity to
match the requirements.
(b) Availability for this work of personnel with adequate experience as required as per Annexure-II.
The contractor should have details vetted from department of pension & pensioners' welfare /
Department of labour and employment/ department of financial services, in the form of CPF/NPS
muster roll of technical and non-technical personel as a proof of Key personnel working in
UAL-2020 CHAPTER - 20
firm/company.
(c) Liquid assets and/ or availability of credit facilities of no less than amount indicated in Appendix to
ITB (credit lines / letter of credit certificates from banks for meeting the funds requirement etc. usually
the equivalent of the estimated cash flow for three months in peak construction period)
4.6(C) To qualify for a package of contracts made up of this and other contracts for which bids
are invited in the ITB, the bidders must demonstrate having experience and resources
sufficient to meet the aggregate of the qualifying criteria for the individual contracts.
4.6 Bidders who meet the minimum qualification criteria will qualify only if their available bid capacity is
more than the total estimated cost of the works. The available bid capacity will be calculated as under:-
154
Available Bid capacity = (AxNxM-B)
Note: The statements showing the value of existing commitments and on-going works as well as
the stipulated period of completion remaining for each of the works listed should be
countersigned by the Engineer in charge, not below the rank of an Executive Engineer or
equivalent. The certificate should be furnished as per format shown in qualification
information (Section-2).
4.7 Even though the Applicants meet the above qualifying criteria, they are subject to be
disqualified if they have:
i. Made misleading or false representations in the forms, statements and attachments submitted;
and / or
ii. Record of poor performance such as abandoning the works not properly completed the contract
inordinate delays in completion, litigation history or financial failure etc and /or
iii. Participated in the previously bidding for the same works and had quoted unreasonably high bid
prices and could not furnish rational justification to employer
7. Site Visit
7.1 The Bidder, at the Bidder‘s own responsibility and risk is encouraged to visit and examine the
Site of Works and its surroundings and obtain all information that may be necessary for
preparing the Bid and entering into a contract for construction of the Works. The costs of
visiting the Site shall be at the Bidder‘s own expense.
155
B. BIDDING DOCUMENTS
8.1 The set of bidding documents comprises the documents listed below and Addenda issued in
accordance with Clause 10 of ITB.
9.1 The electronic bidding system provides for online clarification. A prospective bidder requiring any
clarification of the bidding document may notify online the authority inviting the bid .The
authority inviting the bid will respond to any request(s) for clarification received earlier than 10
days prior to the dead line for submission of bids. Description of clarification sought and the
response of the authority inviting the bid will be uploaded for information of the public or other
bidders without identifying the source of request for clarification.
CHAPTER - 20
9.2.1 The bidder or his official representative is invited to attend a pre-bid meeting, which will take
place at the address, venue, time and date as indicated in NIT.
9.2.2 The purpose of the meeting will be to clarify issues and to answer questions on any matter that
may be raised at that stage.
9.2.3 The bidder is requested to submit any questions in writing or by cable to reach the employer not
later than two days before themeeting.
G MANUAL-2020
9.2.4 Minutes of the meeting, including the text of the questions raised(without Identifying the source of
enquiry) and the responses given will be transmitted without delay to all bidders. Any modification
of the bidding documents listed in Sub-Clause 8.1which may become necessary as a result of thepre-
bid meeting shall be uploaded and bidder shall be automatically informed through messaging/mail
through jktenders.gov.in.
156
9.2.5 Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
10.1 Before the deadline for submission of bids, the Employer may modify thebidding
documents by issuing online corrigendum. The corrigendum will appear on the web page of the
website www. Jktenders.gov.in under the ―Latest Corrigendum‖ and e-mail notification is also
automatically sent to those bidders who have moved this tender to their ―My tenders‖ area.
10.2 Any addendum thus issued shall be part of the bidding documents and shall be
deemed to have been communicated to all the bidders who have moved this tender to their ―My
Tenders‖ area. Incase any addendum/ Corrigendum, the system will automatically send e-mail to all
bidders who have downloaded the bidding document.
10.3 To give prospective bidders reasonable time in which to take an addendum into
account in preparing their bids, the Employer shall extend, as necessary, the deadline for submission
of bids, in accordance with Clause 20.2 of ITB.
157
C. PREPARATION OF BIDS
11. Language of the Bid
12.1 The bid to be uploaded by the bidder as Volume V of Bid document (Refer Clause 8.1) shall
be in two separate parts.
i) Bid Security and Bid document fee in the form as specified in Section8
ii) Qualification Information and supporting documents as specified in Section2.
iii) Certificates, undertaking, affidavits in section 2.
iv) Any other information pursuant to clause 4.0 of these instructions.
v) Undertaking that, the bid shall remain valid for the period of 120 days after the deadline of
date of opening of technical bids mentioned in the NIT.
vi) Acceptance/non- acceptance of dispute reviewexpert
Part-II of the bid shall be named as ―Financial Bid and shall comprise.
Bidders must ensure to upload scanned copy of all necessary documents mentioned in NIT and SBD
with technical bid.
12.3 Following documents, which are not submitted with the Bid, will be deemed to be part of the
Bid separately sealed and marked
Section Particulars
1 Notice Inviting Tender
2 Instruction to Bidders(ITB)
3-4 Conditions of Contract
5 Contract Data
6 Specifications
9 Drawings
CHAPTER - 20
13. Bid Prices:
13.1 The Contract shall be for the whole Works, as described in Clause 1.1 of ITB, based on the
priced Bill of Quantities submitted by the Bidder online.
13.2 The Bidder shall make online entries to fill the Item Rates in Bill of Quantities.
Item Rate Method requires the bidder to quote rates and prices for all items of the Works
described in the Bill of Quantities. The items for which no rate or price is entered by the
Bidder will not be paid for by the Employer when executed and shall be deemed
covered by the other rates and prices in the Bill of Quantities. Upon numerical entry, the
Percentage Rate method requires the bidder to quote a percentage above/below /at par of the
schedule of rates applicable/as mentioned in the advertised BOQ.
13.3 All duties, taxes and other levies payable by the Contractor under the contractor, or for
any other cause including GST, shall be included in the rates, price and the total bid price
submitted by the Bidder.
13.4 The rates & prices quoted by the bidder shall be fixed for the duration of the contract and
shall not be subject to adjustment or any account.
14.1 The unit rates and the prices shall be quoted by the bidder entirely in Indian Rupees. All
payments shall be made in Indian Rupees.
15 Bid Validity
15.1 Bids shall remain valid for a period not less than 120 days (One hundred twenty days)
after The deadline date for opening of Technical bids as specified in NIT. A bid valid for a
shorter period shall be rejected by the Employer as non-responsive. In case of discrepancy in bid
validity period between that given in the undertaking pursuant to Clause 12.1 (v) and the Form
of Bid submitted by the Bidder, the latter shall be deemed to stand corrected in accordance with
theformer and the Bidder has to provide for any additional security that is required.
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer
may request that the bidders may extend the period of validity for a specified additional period.
The request and the bidders‘ responses shall be made in writing or by cable. A bidder may
159
refuse the request without forfeiting his Bid security. A bidder agreeing to the request will not
be required or permitted to modify his bid except as provided in 15.3 hereinafter, but will be
required to extend the validity of his Bid security for a period of the extension, and in
compliance with Clause 16 of this chapter in all respects
15.3 Bid evaluation will be based on the bid prices without taking into consideration the above
correction.
CHAPTER - 20
PWD ENGINEERING MANUAL-2020
160
16 Bid Security
16.1 The bidder shall furnish as part of his Bid, a Bid Security in the amount as shown in
Column 5 of the table of (NIT) for this particular work. This bid security shall be in favour of
employer as named in Appendix and may be in one of the following forms:
a. Deposit-at-call Receipt from any scheduled Indian Bank or a foreign Bank located in India and
approved by the Reserve Bank of India
b. Bank Guarantee from any scheduled Indian bank, in the format given in Volume
c. Fixed Deposit Receipt, issued by any Scheduled Indian Bank or a foreign Bank approved by the
Reserve Bank of India
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
16.2 Bank Guarantee (and other instruments having fixed validity) issued, as surety for the bid
shall be valid for 45 days beyond the validity of the bid. The BG should be verified before
allotting the contract
16.3 Any bid not accompanied by an acceptable Bid Security and not secured as indicated in Sub-
Clauses16.1 and 16.2 above shall be rejected by the Employer as non-responsive.
16.4 The Bid Security of the unsuccessful bidder will be returned within 28 days of the end of the
bid validity period specified in sub-clause 15.1.
16.5 The Bid Security of the Successful bidder will be discharged when the bidder has signed the
Agreement and furnished the required Performance Security.
16.6 The Bid Security may be forfeited
a) If the Bidder withdraws the bid after bid opening during the period of bid validity;
b) In the case of a successful Bidder, if the Bidder fails within the specified time limit to
18.1 The bidding under this contract is electronic bid submission through website
www.jktenders.gov.in Detailed guidelines for viewing bids and submission of online bids are
given on the website. The Invitation for Bids under PW(R&B) department is published on this
website. Any citizen or prospective bidder can logon to this website and view the Invitation for
Bids and can view the details of works for which bids are invited. The prospective bidder can
submit bids online; however, the bidder is required to have enrolment/registration in the website
161
and should have valid Digital Signature Certificate (DSC) in the form of smart card/e- token. The
DSC can be obtained from any authorised certifying agencies. The bidder should register in the
web site www.jkternders.gov.in using the relevant option available
Then the Digital Signature registration has to be done with the e-token, after logging into the site.
After this, the bidder can login the site through the secured login by entering the password of the
e- token and the user id/ password chosen during registration. After getting the bid schedules, the
Bidder should go through them carefully and then submit the documents as asked, otherwise, the
bid will be rejected.
18.2 The completed bid comprising of documents indicated in ITB clause 12, should be
Uploaded on the website given above through e-tendering along with scanned copies of requisite
certificates as are mentioned in different sections in the bidding document and scanned copies of
the Bid Document, E-challan/ receipt and Bid Security in approved form.
18.3 The bidder shall furnish information as described in the Form of Bid on Commissions or
CHAPTER - 20
gratuities, if any, paid or to be paid to agents relating to the Bid, and to contract execution
if the bidder is awarded the contract.
19.1 The bidder shall submit online two separate files. Part I, marked as Part I:
Technical Qualification Part and Part II; marked as Part II: Technical- Financial Part. The
above files will have markings as given in the Bid Data Sheet. The contents of the Technical
Qualification and Technical Financial bid shall be as specified in clause 12 of the ITB. All
the documents are required to be signed digitally by the bidder. After electronic on line bid
20.1 Complete Bids in two parts as per clause 19 above must be submitted by the Bidder
online not later than the date and time indicated in the Appendix to ITB.
20.2 The Employer may extend the deadline for submission of bids by issuing an
Amendment in accordance with Clause 10.3 of ITB. In such case all rights and obligations of the
Employer and the bidders previously subject to the original deadline will then be subject to the
new deadline.
21.1 The electronic bidding system would not allow any late submission of bids after
due date and time as per server time.
21.2 Bidders may modify their bids by uploading their request for modification before
the deadline for submission of bids. For this, the bidder need not make any additional
payment towards the cost of tender document. For bid modification and consequential re-
submission, the bidder is not required to withdraw his bid submitted earlier. The last modified
bid submitted by the bidder within the bid submission time shall be considered as the bid. For
this purpose, modification/withdrawal by other means will not be accepted. In online system
of bid submission, the modification and consequential- submission of bids is allowed any
number of times. The bidders may withdraw his bid by uploading their request before the
deadline for submission of bids; however, if the bid is withdrawn, the re-submission of the
bid is not allowed.
21.3 No bid shall be modified or withdrawn after the deadline of submission of bids.
162
21.4 Withdrawal or modification of a bid between the deadline for submission of bids and the
expiration of the original period of bid validity specified in clause 15.1 above or as extended
pursuant to Clause 15.2 may result in the forfeiture of the Bid Security pursuant to Clause 16.
22.2 The file containing the Part-I of the bid will be opened first.
22.3 In all cases, the amount of Bid Security, cost of bid documents, and the validity of the bid
shall be scrutinized. Thereafter, the bidders‘ names and such other details as the
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Employer may Consider appropriate, will be notified as Part-I bid opening summary by the
Authority inviting bids at The online opening. A separate electronic summary of the opening is
generated and kept on-line.
22.4 The Employer will also prepare minutes of the Bid opening, including the information
disclosed in accordance with Clause 22.3 of ITB and upload the same for viewing online.
22.5 Evaluation of Part-I of bids with respect to Bid Security, qualification information
and other information furnished in Part I of the bid in pursuant to Clause 12.1 of ITB, shall be
taken up and completed within five working days of the date of bid opening, and a list will be
drawn up of the qualified bidders whose Part- II of bids are eligible for opening.
22.6 The result of Technical evaluation shall be made public on jktenders.gov.in site following
which there will be a period of two working days during which any bidder may submit
objections if any in writing to the tender receiving authority which shall be considered for
resolution before financial bid opening.
22.7 The Employer shall inform the bidders, who have qualified technical evaluation, of the
date, time of online opening of financial bids. If the specified date of opening of financial bid
is changed, in the event of the specified date being declared a holiday for the Employer, the
bids will be opened at the appointed time and location on the next working day.
22.8 Financial bids of only those bidders will be opened online, who have qualified in
Technical Evaluation. The bidders‘ names, the Bid prices, the total amount of each bid, and
such other details as the Employer may consider appropriate will be notified online by the
Employer at the time of bid opening.
22.9 The Employer shall prepare the minutes of the online opening of Financial Bids and
upload the same for viewing online.
23 Process to be confidential
23.1 Information relating to the examination, clarification, evaluation and comparison of Bids and
recommendations for the award of a contract shall not be disclosed to Bidders or any other persons
not officially concerned with such process until the award to the successful Bidder has been
announced. Any effort by a bidder to influence the Employer‘s processing of bids or award decision
may result in the rejection of his bid.
163
24 Clarification of Bids and contacting the Employer: -
No Bidder shall contact the Employer on any matter relating to its bid from the time of the bid
opening to the time the contract is awarded. If the bidder wishes to bring additional information
to the notice of the Employer, it should do so in writing.
24.1 Any attempt by the bidder to influence the Employer‘s bid evaluation, bid Comparison or
contract award decision may result in the rejection of his bid.
25.1 During the detailed evaluation of ―Technical Bids‖ the Employer will determine whether
each Bid (a) meets the eligibility criteria defined in Clause 3 and 4,(b) has been properly signed;
CHAPTER - 20
(c) is accompanied by the required securities and; (d) is substantially responsive to the
requirements of the Bidding documents. During the detailed evaluation of the ‗Financial Bid‘
the responsiveness of the Bids will be further determined with respect to the remaining bid
conditions i.e. priced Bill of Quantities, technical specifications and drawings.
A substantially responsive ―Financial Bid‖ is one, which conforms to all the terms, conditions
and specifications of the Bidding documents, without material deviation or reservation.
A material deviation or reservation is one
(i) which affects in any substantial way the scope, quality or performance of the works:
(ii) which limits in any substantial way inconsistent with the bidding documents the
25.2 If a ―Financial Bid‖ is not substantially responsive it will be rejected by the Employer
and may not subsequently be made responsive by correction or withdrawal of the non-
conforming deviation or reservation.
26.1 The Employer will evaluate and compare only the bids determined to be substantially
responsive in accordance with Sub-Clause 25.2.
26.2 In evaluating the bids, the Employer will determine for each bid the Evaluated Bid price
adjusting the Bid price through making an appropriate adjustment for any other acceptable
variation, deviations, and price modifications offered in accordance with sub-clause 21 of ITB.
26.3 The Employer reserves the right to accept or reject any variation or deviation. Variations
and deviations, and other factors which are in excess of the requirements of the bidding
documents or otherwise result in unsolicited benefits for the Employer shall not be taken into
account in Bid evaluation.
164
Additional performance security
S.No Percentage of unbalanced bid viz -a- viz Adv.cost to be deposited on quoted bid by
L1
1 Upto and including 15% below Nil
2. >15% upto and including 20% below 5%
3 >20% upto and including 25% below 10%
4 >25% upto and including 30% below 15%
5 >30% below 20%
Payment for the items for which quoted rates are higher than estimated/DPR rates shall be
restricted to estimated/DPR rates only till completion of items for which quoted rates are
lower than the estimated/DPR rates.
It should al so be ensured than advertised Quantities as per the BOQ should not exceed
the advertised quantities in any case in order to ensure that intense position of the bidders
does not get changed.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
After evaluation of the price analyses, the Employer may require that the amount of the
performance security set forth in clause 30of ITB be increased at the expense of the
successful bidder to a level sufficient to protect the Employer against financial loss in the
event of default of the successful bidder under the Contract.
26.5 A Bid which contains several items in the Bill of Quantities which are
unrealistically which cannot priced low and be substantiated satisfactorily by the bidder
may be rejected as non-responsive.
26.6 There should be no post tender negotiation with L1 as per CVC guidelines. In case L1
backs out, there should re-tender.
Integrity Pact, in respect of a particular contract, shall be operative from the date IP is
signed by both the parties till the final completion of the contract. Any violation of the same
would entail disqualification of the bidders and exclusion from future business dealings.
165
Sample of integrity pact agreement is given here under:-
To,
………………………..,
………………………..,
………………………..
Sub: NIT No. …………………………………. for the work ……………..... ..............
Dear Sir,
It is here by declared that PWD is committed to follow the principle of transparency, equity and
competitiveness in public procurement.
The subject Notice Inviting Tender (NIT) is an invitation to offer made on the condition that the
Bidder will sign the integrity Agreement, which is an integral part of tender/bid documents, failing
which the tenderer/bidder will stand disqualified from the tendering process and the bid of the
bidder would be summarily rejected.
This declaration shall form part and parcel of the Integrity Agreement and signing of the same shall
be deemed as acceptance and signing of the Integrity Agreement on behalf of the PWD.
Yours faithfully
Executive Engineer
166
To,
Executive Engineer,
………………………..,
………………………..
Sub: Submission of Tender for the work of …………………… …....……………....
Dear Sir,
I/We acknowledge that PWD is committed to follow the principles thereof as enumerated in the
Integrity Agreement enclosed with the tender/bid document.
I/We agree that the Notice Inviting Tender (NIT) is an invitation to offer made on the condition that
I/We will sign the enclosed integrity Agreement, which is an integral part of tender documents,
failing which I/We will stand disqualified from the tendering process. I/We acknowledge that THE
MAKING OF THE BID SHALL BE REGARDED AS AN UNCONDITIONAL AND
ABSOLUTE ACCEPTANCE of this condition of the NIT.
I/We confirm acceptance and compliance with the Integrity Agreement in letter and spirit and
further agree that execution of the said Integrity Agreement shall be separate and distinct from the
main contract, which will come into existence when tender/bid is finally accepted by PWD. I/We
acknowledge and accept the duration of the Integrity Agreement, which shall be in the line with
Article 1 of the enclosed Integrity Agreement.
I/We acknowledge that in the event of my/our failure to sign and accept the Integrity Agreement,
while submitting the tender/bid, PWD shall have unqualified, absolute and unfettered right to
disqualify the tenderer/bidder and reject the tender/bid is accordance with terms and conditions of
the tender/bid.
Yours faithfully
167
To be signed by the bidder and same signatory competent / authorised to sign the relevant
contract on behalf of PWD.
INTEGRITY AGREEMENT
This Integrity Agreement is made at ............... on this ........... day of ........... 20......
BETWEEN
Lt Governor of Jammu and Kashmir represented through Executive Engineer, .................................,
(Name of Division)
PWD, ......................................................................., (Hereinafter referred as the (Address of Division)
„Principal/Owner‟, which expression shall unless repugnant to the meaning or context hereof include
its successors and permitted assigns)
AND
.............................................................................................................
(Name and Address of the Individual/firm/Company)
through .................................................................... (Hereinafter referred to as the (Details of duly
authorized signatory)
“ Bidder/Contractor” and which expression shall unless repugnant to the meaning or context hereof
include its successors and permitted assigns)
Preamble
WHEREAS the Principal / Owner has floated the Tender (NIT No. ................................) (hereinafter
referred to as “ Tender/Bid”) and intends to award, under laid down organizational procedure, contract
for ................................................................................................................................ (Name of work)
hereinafter referred to as the “Contract”.
AND WHEREAS the Principal/Owner values full compliance with all relevant laws of the land, rules,
regulations, economic use of resources and of fairness/transparency in its relation with its Bidder(s) and
Contractor(s).
AND WHEREAS to meet the purpose aforesaid both the parties have agreed to enter into this Integrity
Agreement (hereinafter referred to as “ Integrity Pact” or “ Pact”), the terms and conditions of which
shall also be read as integral part and parcel of the Tender/Bid documents and Contract between the
parties.
NOW, THEREFORE, in consideration of mutual covenants contained in this
Pact, the parties hereby agree as follows and this Pact witnesses as under:
(a) No employee of the Principal/Owner, personally or through any of his/her family members, will in
connection with the Tender, or the execution of the Contract, demand, take a promise for or accept, for
self or third person, any material or immaterial benefit which the person is not legally entitled to.
(b) The Principal/Owner will, during the Tender process, treat all Bidder(s) with equity and reason. The
Principal/Owner will, in particular, before and during the Tender process, provide to all Bidder(s) the
same information and will not provide to any Bidder(s) confidential / additional information through
which the Bidder(s) could obtain an advantage in relation to the Tender process or the Contract
execution.
(c) The Principal/Owner shall endeavor to exclude from the Tender process any person, whose conduct
in the past has been of biased nature.
2) If the Principal/Owner obtains information on the conduct of any of its employees which is a criminal
offence under the Indian Penal code (IPC)/Prevention of Corruption Act, 1988 (PC Act) or is in
violation of the principles herein mentioned or if there be a substantive suspicion in this regard, the
Principal/Owner will inform the Chief Vigilance Officer and in addition can also initiate disciplinary
actions as per its internal laid down policies and procedures.
168
Article 2: Commitment of the Bidder(s)/Contractor(s)
1) It is required that each Bidder/Contractor (including their respective officers, employees and
agents) adhere to the highest ethical standards, and report to the Government / Department all
suspected acts of fraud or corruption or Coercion or Collusion of which it has knowledge or
becomes aware, during the tendering process and throughout the negotiation or award of a
contract.
a) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm, offer,
promise or give to any of the Principal/Owner‟s employees involved in the Tender process or
execution of the Contract or to any third person any material or other benefit which he/she is not
legally entitled to, in order to obtain in exchange any advantage of any kind whatsoever during the
Tender process or during the execution of the Contract.
b) The Bidder(s)/Contractor(s) will not enter with other Bidder(s) into any undisclosed agreement
or understanding, whether formal or informal. This applies in particular to prices, specifications,
certifications, subsidiary contracts, submission or non-submission of bids or any other actions to
restrict competitiveness or to cartelize in the bidding process.
c) The Bidder(s)/Contractor(s) will not commit any offence under the relevant IPC/PC Act.
Further the Bidder(s)/Contract(s) will not use improperly, (for the purpose of competition or
personal gain), or pass on to others, any information or documents provided by the
Principal/Owner as part of the business relationship, regarding plans, technical proposals and
business details, including information contained or transmitted electronically.
d) The Bidder(s)/Contractor(s) of foreign origin shall disclose the names and addresses of
agents/representatives in India, if any. Similarly Bidder(s)/Contractor(s) of Indian Nationality
shall disclose names and addresses of foreign agents/representatives, if any. Either the Indian
agent on behalf of the foreign principal or the foreign principal directly could bid in a tender but
not both. Further, in cases where an agent participate in a tender on behalf of one manufacturer,
he shall not be allowed to quote on behalf of another manufacturer along with the first
manufacturer in a subsequent/parallel tender for the same item.
e) The Bidder(s)/Contractor(s) will, when presenting his bid, disclose any and all payments he has
made, is committed to or tends to make to agents, brokers or any other intermediaries in
connection with the award of the Contract.
3) The Bidder(s)/Contractor(s) will not instigate third persons to commit offences outlined above
or be an accessory to such offences.
4) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm indulge in
fraudulent practice means a willful misrepresentation or omission of facts or submission
offake/forged documents in order to induce public official to act in reliance thereof, with the
purpose of obtaining unjust advantage by or causing damage to justified interest of others
and/or to influence the procurement process to the detriment of the Government interests.
5) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm use Coercive
Practices (means the act of obtaining something, compelling an action or influencing a decision
through intimidation, threat or the use of force directly or indirectly, where potential or actual
injury may befall upon a person, his/ her reputation or property to influence their participation in
the tendering process).
169
Article 3: Consequences of Breach
Without prejudice to any rights that may be available to the Principal/Owner under law or the
Contract or its established policies and laid down procedures, the Principal/Owner shall have the
following rights in case of breach of this Integrity Pact by the Bidder(s)/Contractor(s) and the
Bidder/ Contractor accepts and undertakes to respect and uphold the Principal/Owner‟s absolute
right:
1) If the Bidder(s)/Contractor(s), either before award or during execution of Contract has
committed a transgression through a violation of Article 2 above or in any other form, such as
to put his reliability or credibility in question, the Principal/Owner after giving 14 days notice
to the contractor shall have powers to disqualify the Bidder(s)/Contractor(s) from the Tender
process or terminate/determine the Contract, if already executed or exclude the
Bidder/Contractor from future contract award processes. The imposition and duration of the
exclusion will be determined by the severity of transgression and determined by the
Principal/Owner. Such exclusion may be forever or for a limited period as decided by the
Principal/Owner.
2) Forfeiture of EMD/Performance Guarantee/Security Deposit: If the Principal/Owner has
disqualified the Bidder(s) from the Tender process prior to the award of the Contract or
terminated/determined the Contract or has accrued the right to terminate/determine the
Contract according to Article 3(1), the Principal/Owner apart from exercising any legal rights
that may have accrued to the Principal/Owner, may in its considered opinion forfeit the entire
amount of Earnest Money Deposit, Performance Guarantee and Security Deposit of the
Bidder/Contractor.
3) Criminal Liability: If the Principal/Owner obtains knowledge of conduct of a Bidder or
Contractor, or of an employee or a representative or an associate of a Bidder or Contractor
which constitutes corruption within the meaning of IPC Act, or if the Principal/Owner has
substantive suspicion in this regard, the Principal/Owner will inform the same to law
enforcing agencies for further investigation.
Article 4: Previous Transgression
1) The Bidder declares that no previous transgressions occurred in the last 5 years with any
other Company in any country confirming to the anticorruption approach or with Central
Government or State Government or any other Central/State Public Sector Enterprises in
India that could justify his exclusion from the Tender process.
2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the
Tender process or action can be taken for banning of business dealings/ holiday listing of the
Bidder/Contractor as deemed fit by the Principal/ Owner.
3) If the Bidder/Contractor can prove that he has resorted / recouped the damage caused by
him and has installed a suitable corruption prevention system, the Principal/Owner may, at its
own discretion, revoke the exclusion prematurely.
Article 5: Equal Treatment of all Bidders/Contractors/Subcontractors
1) The Bidder(s)/Contractor(s) undertake(s) to demand from all subcontractors a commitment
in conformity with this Integrity Pact. The Bidder/Contractor shall be responsible for any
violation(s) of the principles laid down in this agreement/Pact by any of its
Subcontractors/sub-vendors.
2) The Principal/Owner will enter into Pacts on identical terms as this one with all Bidders
and Contractors.
3) The Principal/Owner will disqualify Bidders, who do not submit, the duly signed Pact
between the Principal/Owner and the bidder, along with the Tender or violate its provisions at
any stage of the Tender process, from the Tender process.
...............................................................
(For and on behalf of Principal/Owner)
.................................................................
(For and on behalf of Bidder/Contractor)
WITNESSES:
1. ..............................................
(signature, name and address)
2. ...............................................
(signature, name and address)
Place:
Dated :
171
D. AWARD OF CONTRACT
27.1 Subject to Clause 28, the Employer will award the Contract to the Bidder whose Bid has
been determined. To be substantially responsive to the Bidding documents and who has
offered the lowest Evaluated Bid Price, provided that such bidder has been determined to be (a)
eligible in Accordance with the provisions of clause 3 of ITB and (b) qualified in accordance
CHAPTER - 20
with the Provisions of clause 4 of ITB; and
(i) To be within the available Bid Capacity adjusted to account for his bid price which is
evaluated the lowest in any of the packages opened earlier than the one under
consideration.
(ii) The work shall not be awarded without proper verification of documents provided by
the tenderers such as EMD, BG, Completion Certificate, IT returns etc.
28.0 Employer‘s right to accept any Bid and Reject any or all Bids
28.1 Notwithstanding Clause 27 the Employer reserves the right to accept or reject any
bid and to cancel the bidding process and reject all bids, at any time prior to award of
Contract, without thereby incurring any liability to the affected bidder or bidders or any
obligations to inform the affected bidder or bidders of the grounds for the Employer‘s
28.2 The acceptance of tenders shall not be delayed without any justification.
29.0 Notification of Award and signing of Agreement
29.1 The Bidder whose Bid has been accepted will be notified of the award by the
54Employer prior to expiration of bid validity period by cable, telex or facsimile confirmed by
registered letter. This letter (hereinafter and in the Conditions of Contract called ―the Letter of
Acceptance‖) will state the sum that the Employer will pay the contractor in consideration of
the execution, completion and maintenance of the Works by the Contractor as prescribed by the
Contract. (Hereinafter and in the Contract called ―the Contract Price‖).
29.2 The notification of award will constitute the formation of the Contract subject only to
the furnishing of a performance security in accordance with provision of clause 30 of ITB.
29.3 The Agreement will incorporate all agreements between the Employer and
the successful Bidder. It will be signed by the Employer and the successful
Bidder after the Performance Security is furnished.
29.4 Upon the furnishing by the successful bidder the performance security, the Employer
will promptly notify the other bidders that their bids have been unsuccessful.
30 Performance Security
30.1 Within 21 (twenty one) days after the date of receipt of the Letter of Acceptance, the
successful bidder/contractor shall deliver to the Employer/concerned authority, a
Performance Security in the shape of CDR/FDR/BG for an amount equivalent to 5% of
contract price plus additional performance security in the shape of CDR /FDR/ BG for the
unbalanced bid in terms of clause 26.4 of ITB.
30.2 If the Performance Security is provided by the successful bidder in the form of a bank
172
guarantee, it shall be issued by either (a) at the Bidder‘s option, by a Nationalized / Scheduled Indian
Bank or (b) by a foreign reservation. A material deviation or reservation is one bank located in India
and acceptable to the Employer.
30.3 Failure of the successful bidder to comply with the requirements of Sub-Clause 30.1 of ITB shall
constitute sufficient grounds for cancellation of the award and forfeiture of the Bid Security.
30.4 Standard guarantees for water proof treatment, anti termite treatment and other specialized item
of work shall be obtained from the contractor/firm.
The Employer proposes that (Name of the proposed Dispute Review Expert as indicated in the
Appendix to ITB)to be appointed as Dispute Review Expert under the contract at a daily fee as
indicated in Appendix plus reimbursable expenses .If the bidder disagrees with this proposal, the
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
bidder should so state in the bid. If, in the letter of Acceptance, the Employer has not agreed on the
appointment of the Dispute Review Expert, the Dispute Review Expert shall be appointed by the
Council of Indian Road Congress at the request of either party.
33.1 The Employer will reject a proposal for award if it determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in competing for the contract in question and will
declare the firm ineligible, either indefinitely or for a stated period of time, to be awarded a contract
with National Highways Authority of India / State PWD and any other agencies, if it at any time
determines that the firm has engaged in corrupt or fraudulent practices in competing for the contractor,
or in execution.
33.2 Furthermore, Bidders shall be aware of the provisions stated in Clause 53.2of the Conditions of
Contract.
34.1 The scope and specifications of the work shall not be changed without prior approval of
competent authority.
173
APPENDIX TO ITB
Clause Reference with respect to Section –I.
CHAPTER - 20
6. Price level of the financial year YYYY-YY (particular year to be mentioned) [C1.4.6&4.8]
7. The pre-bid meeting will take place at office of Chief Engineer, R&B Department Kashmir/Jammu
on DD/MM/YY [C1.9.2.1]
8. The technical bid will be opened in the office of Chief Engineer, PW(R&B) Department Kashmir
/Jammu On /20YY at 11.00 A.M.
9. Address of the Employer:
10. Identification of Scheme:
Bid for: Construction of Bid reference No:- dated /20YY.
Do not open before _ at 11.00 A.M
14. CDR/FDR/BG in favour of Chief Accounts Officer PWD (R&B) Jammu/Kashmir Payable at
Srinagar [C1.30 OF ITB]
15. Dispute Review Expert; T.O to Chief Engineer, PW(R&B) Department Jammu/Kashmir
Clause 32 OF IT Band 23 of GCC
174
15(a): Performance Security shall be valid until a date 28 days after the expiry of
Defect
Liability Period of 3 years after intended date of completion.
The successful bidder shall have to deposit an additional performance security in the shape of CDR/
FDR/ BG before award of contract in case the bide of the successful bidder is found to be unbalanced
and the following scale shall apply thereto: -
S.No Percentage of unbalanced bid viz -a- viz Adv. Cost Additional performance
security to be deposited on
1 Upto and including 15% below Nil
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
16. Base year :e.g. 2014-15 (particular year to be mentioned) No escalation factor is allowed for
similar nature of work.
175
For Individual Bidders
1.1 Constitution or legal status of Bidder (attach copy)
Place of registration
CHAPTER - 20
TDS, ITR, Profit and Loss statement and Year 20YY-YY
Balance sheet.** Year 20YY-YY
Year 20YY-YY
1.3. Work performed as prime contractor (in the same name & style) on construction
works of similar nature over the last five years. Attach certificate issued by an officer
not below the rank of Executive Engineer or equivalent.
Project Name of Description Contract No Value of Date of Stipulated Actual date Remarks
1.4 Work performed as sub-contractor (in the same name & style duly supported with an
authority letter regarding approval of sub-contract by the competent authority) on
construction works of similar nature over the last five years. Attach certificate issued by an
officer not below the rank of Executive Engineer or equivalent.
Project Name of the Description of Contract No Value of Date of Stipulated Actual date of Remarks
Name employer work contract (Rs issue of Period of completion explaining
* in crore) work completion * reasons for
Order delay & work
completed
**** A certificate of performance evaluation of all such works/commitments in hand on the part of
the bidder issued by the concerned Chief Engineer/Superintending Engineer/Executive Engineer to
the affirmation that the contractual obligations are being performed satisfactorily without
compromise on quality parameters and time lines.
176
1.5(a) Achieved a minimum average financial turnover on execution of civil engineering works (
defined as billing for works in progress or completed in all classes of civil engineering
construction works only) during any three out of the last five financial years(yyyy-yy to yyyy-yy)
not less than 33% of the proposed contract /contracts applied. the information supplied in this
connection should be duly certified by a chartered accountant and be duly supported by tds and
income tax returns for the last five years.
(b) Having satisfactorily completed or substantially completed, at least one contract of similar
nature of work of any Govt./Semi Govt. department during the last five years as the case may be
(Building/Road/Bridge Work) of at least 33 % of the value of proposed contract during the last
five years.(Certificate to this effect to be issued by an officer not below the rank of Executive
Engineer or equivalent.). No escalation factor is allowed for similar nature of work and only work
upto allotted amount shall be considered.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
The work may have been executed by the Applicant as prime contractor or as a member of joint
venture. In case a project has been executed by a joint venture, weightage towards experience of
the project would be given to each joint venture partner in proportion to their participation in the
joint venture. Substantially completed works means those works which are at least 90%
completed as on the date of submission of bid (i.e. gross value of work done up to the last date of
submission is 90% or more of the original contract price) and continuing satisfactorily.
For this a certificate from employer shall be submitted along with the application
incorporating clearly the name of the work, contract value, billing amount, date of
commencement of works, actual date of completion of work, satisfactory performance of the
contractor and any other relevant information.
The certificate should be furnished as per format shown in qualification information section-
2 clause no:- 1.3 supported with allotment which shall also be uploaded.
Description of Place & Contract No. Name & Value of Stipulated Value of Anticipated
Work State & date address of contract (Rs Period of works date of
Employer in lakhs) completion remaining to completion
be completed
(Rs. in lakhs)
1 2 3 4 5 6 7 8
177
Enclose certificate(s) issued by an officer not below the rank of Executive Engineer or equivalent
1.6 Availability of Major items of Contractor‘s equipment proposed for carrying out the Works. List
all information requested below. Refer also to Clause 4.3(f) and 4.6(B) of the Instructions to
Bidders.
Item of Equipment Description, make, Condition (new, good, Owned, leased (from
and age (years), and poor) and number whom?) or to be
capacity available purchased.
Financial reports for the last five years: balance sheets, profit and loss statements, auditors reports,
etc. List below and attach copies.
1.11 Proposed work method and schedule. The Bidder should attach descriptions,
Drawings and charts as necessary to comply with the requirements of the Bidding documents. [
Refer ITB Clause 12]
1.12 Applicants who meet the minimum qualification criteria will be qualified only if
there available bid capacity at the expected time of bidding is more than the total estimate cost of
the works. The available bid capacity will be calculated as under:-
Information on Bid Capacity (works for which bids have been submitted and works which
are yet to be completed) as on the date of this bid.
The item of work for which data is requested should tally with that specified in ITB clause
4.6 Qualification and experience of technical/key personnel required for administration and
execution of the Contract [Ref. Clause 4.6 (B) (b)].Attach biographical data. Refer also to sub
Clause 4.3 (h) of instructions to Bidders and Sub Clause 8.1 of the Conditions of Contract.
178
Position Name Qualification Year of Experience Years of experience in
(General) similar nature of work
Attach copies of certificates on possession of valid license for executing water supply/ sanitary
work/ building electrification works [Reference Clause 4.3 of Chapter SBD ]
1.15 Quality Assurance Programme (to be framed in accordance with the requirements
/guide lines/manual uploaded on departmental website.
2.1 Bidders should provide any additional information required to fulfil therequirements of
Clause 4 of the Instructions to the Bidders, if applicable.
(i) Affidavit on correctness of information.
(ii) Undertakings
The applicant should have achieved minimum annual value of general construction work (as
certified by Chartered Accountant, and at least 50(fifty) percent of which is from Engineering
(Civil/Electrical/Mechanical as relevant to the work being procured) construction works carried
out in any of the year over a stated period (normally five to seven years, ending 31 st March of
previous year), calculated by applying an appropriate multiplier to the projected annual
construction expenditure on the subject contract. The multiplier of 2 may be used, but for very
large contracts should not be less than 1.5.
However, in case of Road/Bridge works under MoRTH, NABARD and State Sector, the
guidelines as circulated by MoRTH shall apply while as in case of Road/Bridge works under
PMGSY, the guidelines as circulated by PMGSY shall apply.
2.3 Particular Construction Experience and Key Production Rates
The applicant should have:
Successfully completed or substantially completed similar works during last seven years
ending last day of month previous to the one in which applications are invited should be
either of the following:-
1. Three similar completed works costing not less than the amount equal to 40 (forty) percent
of the estimated cost; or
2. Two similar completed works costing not less than the amount equal to 50 (fifty) percent
of the estimated cost; or
3. One similar completed work costing not less than the amount equal to 80 (eighty) percent
of the estimated cost; and
2.4 The applicant should also have achieved the minimum annual production value of the key
construction activities (e.g dredging, piling, or earthworks etc) stipulated.
The similarity of work shall be pre-defined based on the physical size, complexity
methods/technology and /or other characteristics, and scope of works. Substantial
completions shall be based on 80 (eighty) percent (value wise) or more works completed
179
under the contract. For contracts under which the applicant participated as a joint venture
member or sub-contractor, only the applicant‘s share, by value, shall be considered to meet
this requirement. For arriving at cost of similar work, the value of work executed shall be
brought to current costing level by enhancing the actual value of work at simple rate of seven
percent per annum, calculated from the date of completion to the date of Bid opening.
The applicant should demonstrate that he has excess to, or has available, liquid assets (aggregate
Of working capital, cash in hand and uncommitted Bank Guarantee‘s) and / or credit facilities of
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
not less than 10% of the value of the contract/ contracts applied for (construction cash-flow may
be taken as 10% of the estimated value of contract / contracts).
The audited balance sheets for the last five years should be submitted, which must demonstrate
the soundness of the applicant‘s financial position, showing long term profitability including
and estimated financial projection for the next two years. If necessary, the employer will make
inquires with the applicant‘s bankers.
2.7 Joint Venture:- (Applicable for the works costing Rs.15.00 Crores and above in J&K
State/UT). If the bidder is a Joint Venture ,the partners would be limited to three
(including lead partner).Joint Venture firm shall be jointly and severally responsible for
completion of the project.
2.8 Joint Venture must fulfil the following minimum qualification requirement:-
i. Qualifying factors to be met collectively:
(i) annual turnover from construction; (ii) particular construction experience and key production
rates; (iii) construction cash flow for the subject contract; (iv) personnel capabilities; and
(v)equipment capabilities;
2. Qualifying factors for lead partner:
(i) Annual Turnover from Construction; (ii) particular construction experience; (iii) financial
capability to meet cash flow requirement of subject contract –t less than of 50 (fifty) per cent
of the respective limits prescribed in case of individual contractors may be accepted;
(iii) adequate sources to meet financial commitments on other contracts;
(iv) financial soundness;
3. Qualifying factors for other partner: Same as for lead partner except that for the factors
specified in (2) (iii) above, a lower limit of 25 (twenty-five) per cent may be accepted instead
of 50 (fifty) per cent.
Provisions required to be Included in the Joint Venture Agreement
If the application is made by a Joint Venture of two or more firms ,the evidence of clear
mandate ( i,e in the form of respective Board Resolution duly authenticated by competent
authority)by such two or more firms willing to form Joint Venture among themselves for
the specified projects should accompany duly recognizing their respective authorised
signatories signing for and on behalf of respective firms for the purpose of forming the
Joint Venture .A certified copy of the power of attorney to the authorised representatives,
signed by legally
180
authorised signatories of all the firms of the Joint Venture shall accompany the
application. The JV Agreement shall need to be submitted consisting but not limited to
the following provisions.
a) Name, Style and Project(s) specified JV with Head Office address b)Extent (or Equity)
for participation of each party in the JV
c) Commitment of each party to furnish the Bond money (i.e. Bid, security, performance
security) to the extent of his participation in the JV.
CHAPTER - 20
e) Working Capital arrangement.
g) Provision for cure in case non-performance of responsibility by any party of the J.V
h) Provision that NEITHER party of the JV shall be allowed to sign, pledge, sell or
otherwise dispose of all or part of its respective interests in JV to any party including
existing partner(s) of the JV .The Employer derives right for any consequent action
l) The Joint Venture (JV) Agreement shall be duly registered by First class Munsiff.
181
20.6.1.2. GENERAL CONDITIONS OF CONTRACT
A. GENERAL
1. Definitions
1.1 Terms which are defined in the Contract Data are not also defined in the
Conditions of Contract but keep their defined meanings. Capital initials are used to
identify defined terms. The Adjudicator (synonymous with Dispute Review Expert) is the
person appointed jointly by the employer and the Contractor to resolve disputes in the
first instance, as provided for in Clauses 24 and 25. The name of the adjudicator is
defined in the contract Data.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the Bid.
The Completion Date is the date of completion of the Works as Certified by the Engineer in
accordance with the clause 49.
The Contract is the contract between the Employer and the Contractor to execute, complete
and maintain the Works. It consists of the documents listed in Clause 2.3 below.
The Contract Data defines the documents and other information which comprise the Contract.
The Contractor is a person or corporation body whose Bid to carry out the works has been
accepted by the Employer.
The Contractor‘s Bid is the completed Bidding document submitted by the contractor to the
Employer and includes Technical & Financial -Bids.
The Contract Price is the price stated in the Letter of Acceptance and thereafter as adjusted
in accordance with the provision of the Contract.
Days are calendar days; months are calendar months. A Defect is any part of the works not
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
183
2. Interpretation
(a) Agreement
CHAPTER - 20
(b) Letter of Acceptance, notice to proceed with the works
(f) Specifications
(i) Any other document listed in the Contract Data as forming part of the Contract.
3.1 The language of the Contract and the law governing the Contract are stated in the contract
Data.
4. Engineer‘s Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters
between the Employer and the Contractor in the role representing the Employer.
5. Delegation
5.1 The engineer may delegate any of his duties and responsibilities to other people except to
the Dispute Review Expert after notifying the Contractor and may cancel any delegation
after notifying the Contractor.
6. Communications
6.1 Communications between parties, which are referred to in the conditions, are effective only
when in writing. A notice shall be effective only when it is delivered (in terms of Indian
Contract Act
184
7. Other Contractors
The Contractor shall cooperate and share the Site with other contractors, public authorities,
utilities, and the Employer between the dates given in the Schedule of other Contractors. The
Contractor shall as referred to in the Contract Date, also provide facilities, and services for them
as described in the Schedule. The employer may modify the schedule of other contractors and
shall notify the contractor of any such modification.
8 Personnel
8.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel
as referred to in the Contract Data to carry out the function stated in the Schedule or other
personnel approved by the Engineer. The Engineer will approve any proposed replacement of
key personnel only if their qualifications, abilities, and relevant experiences are substantially
equal to or better than those of the personnel listed in the Schedule.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
8.2 If the Engineer asks the Contractor to remove a person who is a member of the
Contractor‘s staff or his work force stating the reasons the contractor shall ensure that the
person leaves the Site within seven days and has no further connection with the working the
Contract.
9.1 The Employer carries the risks which this Contract states are Employer‘s risks, and the
Contractor carries the risks which this contract states are Contractor‘s risks.
10.1 The Employer is responsible for the excepted risks which are (a) in so far as they directly
affect the execution of the works in the Employer‘s country, the risks of war, hostilities,
invasion, act of foreign enemies, rebellion, revolution, insurrection or military or usurped
power, civil war, riot commotion or disorder (unless restricted to the Contractor‘s employee‘s),
and contamination from any nuclear fuel or nuclear waste or radioactive toxic explosive, or(b)
a cause due solely to the design of the works, other than the Contractor‘s design.
11.1 All risks of loss of or damage to physical property and of personal injury and death which
arise during and in consequence of the performance of the contract other than the excepted risks
are the responsibility of the Contractor.
12. Insurance:
12.1. The Contractor shall provide, in the joint names of the Employer and the Contractor,
insurance cover from the start date to the end of the Defects Liability Period, in the amounts and
deductibles stated in the contract Data for the following events which are due to the
Contractor‘s risks:
a) loss of or damage to the works, Plant and Materials;
b) loss of or damage to Equipment; loss of or damage of property (except the works, Plant,
Materials and Equipment) in connection with the Contract; and personal injury or death.
185
12.2Policy and certificates for insurance shall be delivered by the Contractor to the engineer for
the Engineer‘s approval before the Start Date. All such insurance shall provide for
compensation to be payable in the types and proportions of currencies required to rectify the
loss or damage incurred.
12.3. If the Contractor does not provide any of the policies and certificates required, the
Employer may affect the insurance which the contractor should have provided and recover the
premiums the Employer has paid from payments otherwise due to the Contractor or, if no
payment is due, the payment of the premiums shall be a debt due.
12.4. Alterations to the terms of insurance shall not be made without the approval of the Engineer.
12.5. Both parties shall comply with any conditions of the insurance policies.
13.1 The Contractor, in preparing the Bid, shall rely on any site Investigation Reports referred
CHAPTER - 20
to in the Contract Data, supplemented by any information available to the Bidder.
16.1 The Contractor may commence execution of the Works on the Start Date and shall
carryout the Works in accordance with the programme submitted by the Contractor, as updated
with the approval of the Engineer, and complete them by the Intended Completion Date.
17.1 The Contractor shall submit specifications and Drawings showing the proposed
Temporary Works to the Engineer, who is to approve them if they comply with the
Specifications and Drawings.
17.4 The contractor shall obtain approval of third parties to the design of the Temporary Works
where required.
17.5 All Drawings prepared by the Contractor for the execution of the temporary works, are
subject to prior approval by the Engineer before their use
18. Safety
18.1 The Contractor shall be responsible for the safety of all activities on the Site.
18.2 Safety helmets to be used by engineers on site as well as work men/construction
personnel‘s. It has to be made mandatory for the contractor in contract to provide the
necessary safety helmets to both skilled/unskilled work force.
The contractor should also provide safe drinking water and toilet facilities to the
labours etc besides covered enclosures for having lunch/refreshments.
186
19. Discoveries
20.1 The Employer shall provide adequate Site to the Contractor to start and carry out his
construction activity.
21.1 The Contractor shall allow the Engineer and any person authorized by the Engineer
access to the Site, to any place where work in connection with the Contract is being carried out
or is intended to be carried out and to any place where materials or plant are being manufactured
/ fabricated / assembled for the works.
22. Instructions
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
22.1 The Contractor shall carry out all instructions of the Engineer, which comply with the
applicable where the site is located.
22.2 The Contractor shall permit the Employer to inspect the Contractor‘s accounts and
records relating to the performance of the Contractor and to have them audited by auditors
appointed by the Employer, if so required by the Employer.
23. DISPUTES:
23.1 : If the contractor believes that the decision taken by the Engineer was either outside the
authority give to the Engineer by the contract or that the decision was wrongly taken, the
decision shall be referred to the Dispute Review Expert within 14 days of the notification of
Engineer‘s decision.
24. Arbitration:
24.1 : The Arbitration shall be conducted in accordance with the Arbitration procedure stated in
the Special Conditions of the Contract.
25.1 : Should the Dispute Review Expert resign or die, or should the Employer and the
Contractor agree that the Dispute Review Expert is not fulfilling his functions in accordance
with the provisions of the contract; a new Dispute Review Expert will be jointly appointed by
the Employer and the Contractor. In case of disagreement between the Employer and the
Contractor, within 30 days, the Dispute Review Expert shall be designated by the appointing
authority designated in the Contract Data at the request of either party, within 14 days of receipt
of such request.
187
B- TIME CONTROL
26. Programme
26.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer
for approval a Program showing the general methods, arrangements, order, and timing for all
the activities in the works along with monthly cash flow forecast.
26.2 An update of the Programme shall be a program showing the actual progress achieved on
each activity and the effect of the progress achieved on each activity and the effect of the
progress achieved on the timing of the remaining work including any changes to the sequence of
the activities.
26.3 The Contractor shall submit to the Engineer, for approval, an updated Program at
intervals no longer than the period stated in the Contract Data. If the Contractor does not submit
CHAPTER - 20
an updated Programme within this period, the Engineer may withhold the amount stated in the
Contract Data from the next payment certificate and continue to withhold this amount until the
next payment after the date on which the overdue Programme has been submitted.
26.4 The Engineer‘s approval of the Programme shall not alter the Contractor‘s obligations.
The Contractor may revise the Programme and submit it to the Engineer again at anytime. A
revised Programme is to show the effect of Variations and Compensation Events.
27.2 The Engineer shall decide whether and by how much to extend the Intended Completion
Date within 35 days of the Contractor asking the Engineer for a decision upon the effect of a
Compensation Event or Variation and submitting full supporting information. If the Contractor
has failed to give early warning of a delay or has failed to cooperate in dealing with a delay,
the delay by this failure shall not be considered in assessing the new Intended Completion Date.
27.3 The Engineer shall within 14 days of receiving full justification from the contractor for
extension of Intended completion date refer to the employer his decision. The employer shall in
not more than 21 days communicate to the Engineer the acceptance or otherwise of the
engineer‘s decision.
28.1 The Engineer may instruct the Contractor to delay the start or progress of any activity
within the Works.
29 Management Meetings
29.1 Either the Engineer or the Contractor may require the other to attend a management
meeting. The business of a management meeting shall be to review the plans for remaining
work and to deal with matters raised in accordance with the early warning procedure.
29.2 The Engineer shall record the business of management meetings and is to provide copies
of this record to those attending the meeting and to the Employer. The responsibility of the
parties for actions to be taken is to be decided by the Engineer either at the management
meeting or after the management meeting and stated in writing to all who attended the meeting.
188
30. Early Warning
30.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely future
events or circumstances that may adversely affect the quality of the work, increases the Contract
Price or delay the execution of works. The Engineer may require the Contractor to provide an
estimate of the expected effect of the future event or circumstance on the Contract Price and
Completion Date. The estimate is to be Provide by the Contractor as soon as reasonably
possible.
30.2 The Contractor shall cooperate with the Engineer in making and considering proposal for
how the effect of such an event or circumstance can be avoided or reduced by anyone involved
in the work and in carrying out any resulting instruction of the Engineer.
C. QUALITY CONTROL
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
31. Quality Assurance Programme (For Works Valuing Rs.10.00 crores and Above)
The Contractor shall prepare and submit a quality control plan/mechanism (Quality Assurance
Plan‖ or ―QAP‖) and make all necessary arrangements to ensure its compliance. Having regard
to the requirement of the project, Quality assurance plan shall be devised by taking into
consideration the quality assurance manual/ guide which is available on the web site of
PW(R&B) Department of Chief Engineer(s) Jammu/ Kashmir; this manual or guide can also be
availed from the office of Chief Engineer Jammu/ Kashmir; District Superintending Engineers
and Executive Engineers.
While submitting the bid, the bidder along with other documents shall submit Quality
Assurance Plan (QAP)as per the clause 4.1 and 4.3(p)of ITB. However a final QAP shall be
framed by the successful bidder after the allotment of work. The Engineer –in charge shall
convey its comments to the contractor within a period of 21 days of receipt of the QAP after the
allotment of work, stating the modifications, and the contractor shall incorporate those in the
QAP to the extent required for conforming with the provisions of Quality Assurance
manual/guide, which shall be approved by the competent authority and treated as inseparable
part of agreement to be signed between the contractor and the department.
32. Tests
32.1 If the Engineer-in-Charge instructs the contractor to carry out a test not specified in the
specification to check whether any work has a defect and the test Confirms the defect, then the
contractor shall have to pay for the tests and the defective work shall have to be dismantled and
reconstructed in accordance to the IRC/MOST/BIS/PWD/NBO Specifications as applicable.
The Engineer in-charge of site shall ensure / will certify that the lab has been established & tests
performed.
The contractor will furnish documentary proof of procurement of materials like cement, steel and
other equipment and goods to the engineer in-charge. This will include original vouchers for all
quantities in lieu of purchase of materials/ equipments etc from the original manufacturer or
authorized dealer/distributor to the satisfaction of engineer in-charge for ascertaining genuineness of
materials. Attested copy of such material shall be submitted along with the bills.
No extra payment on account of quality control measures shall be paid to the contractor
33.1 The Engineer shall check the Contractor‘s work and notify the Contractor of any Defects that
are found. Such checking shall not affect the Contractor‘s responsibilities. The Engineer may
instruct the Contractor to search for a Defect and to uncover and test any work at site.
189
34. Correction of Defects
34.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects
Liability Period, which begins at Completion and is defined in the Contract Data. The Defects
Liability Period shall be extended for as long as Defects remain to be corrected.
34.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within
the length of time specified by the Engineer‘s notice.
35.1 If the Contractor has not corrected a Defect within the time specified in the Engineer‘s
CHAPTER - 20
notice, the Engineer will assess the cost of having the Defect corrected, and the Contractor will
pay this amount.
D. COST CONTROL
36. Bill of Quantities
36.1 The Bill of Quantities shall contain items for the Construction, Installation, testing, and
commissioning work to be done by the Contractor.
36.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for
36.4 When the Programme is updated, the contractor is to provide the Engineer with an updated
cash flow forecast.
37.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of
the work completed less the cumulative amount certifiedpreviously.
37.2 The Engineer shall check the Contractor‘s monthly statement within 14 days and certify
the amount to be paid to the Contractor after taking into account any credit or debit the month in
question in respect of materials for the works in the relevantamounts.
37.4 The value of work executed shall comprise the value of the quantities of the items in the
Bill of quantities completed.
37.5 The value of work executed shall include the valuation of variations and Compensation
Events.
37.6 The Engineer may exclude any item certified in a previous certificate or reduce the
proportion of any item previously certified in any certificate in the light of later information.
38. Payments
38.1 Payments shall be adjusted for deductions for advance payments, retention, other
recoveries in terms of the contract and taxes, at source, as applicable under the law.
190
38.2 Items of the works for which no rate or price has been entered in will not be paid for
bythe Employer and shall be deemed covered by other rates and prices in theContract.
39. Tax
The rates quoted by the Contractor shall be deemed to be inclusive of all taxes including
GST (SGST AND CGST) that the Contractor will have to pay for the performance of this
Contract up to the completion. The Employer will perform such duties in regard to the
deduction of such taxes at source as per applicable law from time totime.
40. Currencies
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
42. Retention
The Employer shall retain from each payment due to the Contractor the proportion stated in the
Contract Data until Completion of the whole of the Works.
42.1 On Completion of the whole of the Works half the total amount retained is repaid to the
Contractor and half when the Defects Liability Period has passed and the Engineer has certified
that all Defects notified by the Engineer to the Contractor before the end of this period have been
corrected.
42.2 On completion of the whole works the contractor may substitute retention money with an
―on demand‖ Bank guarantee.
43.1. In the event of failure on part of the Contractor to achieve timely completion of the project
including any extension of time granted under clause 27,he shall ,without prejudice to any other
right or remedy available under the law to the Employer on account of such breach, pay as
agreed Liquidated Damages to the Employer and not by way of penalty in a sum calculated at
the rate per week or part thereof as stated in the Contract Data .For the period that the
completion date is later then the intended completion date ,Liquidated Damages at the same rate
shall be withheld if the Contractor fails to achieve the Mile Stones prescribed in the Contract
Data .However, in case the Contractor achieves the next mile stone ,the amount of the
Liquidated Damages already withheld shall be restored to the Contractor by adjustment in the
payment certificate. Both the parties expressly agree that the total amount of Liquidated
Damages shall not exceed 10% of initial contract price and that the Liquidated Damages
payable by the Contractor are mutually agreed genuine pre-estimated loss and without any proof
of actual damage likely to be suffered and incurred by the Employer, and the Employer is
entitled to receive the same and are not by way of penalty.
The Employer may, without prejudice to any other method of recovery, deduct the amount of
such damages from any sum due, or to become due to the Contractor or from performance
security or any other dues from Government or Semi-Government body within the State.
191
The payment or deduction of such damages shall not relieve the Contractor from his obligations to
complete the works, or from any other of his duties, obligations or responsibilities under the contract.
The Contractor shall use and continue to use his best endeavors to avoid or reduce further delay to the
works, or any other relevant stages.
43.2. If the intended completion date is extended after Liquidated Damages have been paid, the
Engineer shall correct any such payment of Liquidated Damages by the Contractor by adjusting
the next payment certificate.
43.3: It is agreed by the contractor that the decision of the Employer as to the Liquidated Damages
payable by the Contractor under this clause shall be final and binding,
CHAPTER - 20
44. BONUS – The bidder who has successfully completed three CRF works within the
Prescribed time over the last five years shall be rewarded with the multiplying factor of 2.75 instead
of 2.5 for ascertaining the available bid capacity of the bidder during the technical evaluation of his
bid. The bidder to this effect shall furnish the completion certificates of works issued by an officer
not below the rank of Executive Engineer or equivalent.
Security advance shall be paid for the quantity as per allotment of work or requirment at site which
46. Securities
46.1 The Performance Security (including additional Performance security for unbalanced bids)
shall be provided to the Employer no later than the date specified in the Letter of Acceptance and shall
be issued in an amount and form and by a bank or surety acceptable to the Employer, and denominated
in Indian Rupees. The performance Security shall be valid until a date 28 days from the date of expiry
of Defects Liability Period and the additional security for unbalanced bids shall be valid until a date 28
days from the date of issue of the certificate of completion.
47.1 Loss or damage to the Works or Materials to be incorporated in the works between the start date
and the end of the Defects Correction period shall be remedied by the contractor at the contractor‘s
cost, if the loss or damage arises from the contractor‘s acts or omissions.
The Contractor shall request the Engineer to issue a CERTIFICATE OF COMPLETION of the
works and the Engineer will do so upon deciding that the Work is completed.
192
49.0 Taking Over
49.1 The Employer shall take over the Site and the works within seven days of the Engineer
issuing a certificate of Completion.
50.1 The Contractor shall supply to the Engineer a detailed account of the total amount that the
Contractor considers payable under the Contract before the end of the Defects Liability Period.
The Engineer shall issue a Defect Liability Certificate and certify any final payment that is due
to the Contractor within 56 days of receiving the Contractor‘s accounts if it is correct and
complete. If it is not, the Engineer shall issue within 56 a schedule that states the scope of the
corrections or additions that are necessary. If the Final Account is still unsatisfactory after it has
been resubmitted, the Engineer shall decide on the amount payable to the Contactor and issue a
payment certificate, within 56 days of receiving the Contractor‘s revised account.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
51.1 If ―as built‖ Drawings and/or operating and maintenance manuals are required, the
Contractor shall supply them by the dates stated in the Contract Data.
51.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the
Contract Data, or they do not receive the Engineer‘s approval, the Engineer‘s approval, the
Engineer shall withhold the amount stated in the Contract Data from payment due to the
Contractor.
52. Termination
52.1 The Employer may terminate the contract if the contractor causes a fundamental breach of
the Contract.
52.2 Fundamental breaches of Contract include, but shall not be limited to the following:
(a) The Contractor stops work for 28 days when no stoppage of work is shown on the current
programme and the stoppage has not been authorized by the Engineer;
(b) The contractor is declared bankrupt or goes into liquidation other than for approved
reconstruction or amalgamation;
c) If the contractor fails to deploy machinery and equipment or personnel as specified in the
Contract Data or Appendix to ITB at the appropriate time.
(d) The Engineer gives Notice that failure to correct a particular Defect is fundamental breach
of Contract and the Contractor fails to correct it within a reasonable period of time determined
by the Engineer;
(f) The Contractor has delayed the completion of works by the number of days for which the
maximum amount of liquidated damages becomes payable as defined in the Contract data; and
193
(g) If the Contractor, in the judgment of the Employer has engaged in corrupt or fraudulent
practices in competing for or in the executing the Contract.
For the purpose of this paragraph: ―corrupt practice‖ means the offering, giving, receiving or
soliciting of anything of value to influence the action of a public official in the procurement
process or in contract execution. ―Fraudulent practice‖ means a misrepresentation of facts in
order to influence a procurement process or the execution of a contract to the detriment of the
Borrower, and includes collusive practice amount Bidders (prior to or after bid submission)
designed to establish bid prices at artificial non-competitive levels and to deprive the Borrower of
the benefits of free and open competition‖.
52.3 When the Employer gives notice of a breach of contract to the contractor fora cause other
CHAPTER - 20
than those listed under Sub Clause 53 above, the Engineer shall decide whether the breach is
fundamental or not.
52.4 Notwithstanding the above, the Employer may terminate the Contract for convenience.
52.5 If the Contract is terminated the Contractor shall stop work immediately, make the Site safe
and secure and leave the site without shifting any equipment as soon as reasonably possible.
54.0 Property
54.1 All materials on the Site, Plant, Equipment, Temporary Works and Works are deemed to be
the property of the Employer, if the Contract is terminated because of a Contractor‘s defaulted.
55.1 If the Contract is frustrated by the outbreak of war or by any other event entirely outside
the control of either the Employer or the Contractor the Engineer shall certify that the Contract
has been frustrated. The Contractor shall make the Site safe and stop work as quickly as possible
after receiving this certificate and shall be paid for all work carried out before receiving it and for
any work carried
194
out afterwards to which commitment was made.
55.2 Death or permanent invalidity of the contractor: the contractor shall indicate nominee for
the contract at the time of signing of the agreement. If the contractor dies during currency of the
contractor or becomes permanently incapacitated, and his/her nominee are not willing to
complete the contract, the contract shall be closed without levying anydamages/compensation.
However, if the nominee expresses his/her intention to complete, the balance work and
the competent authority is satisfied about the competence of nominee, then the competent
authority shall enter into a fresh agreement for the remaining work strictly on the same terms &
conditions under which the contract was initially awarded.
1. LABOUR
The contractor shall, unless otherwise provided in the contract, make his own arrangements for
the engagement of all staff and labour, local or other, and for their payment, housing, feeding
and transport.
The Contractor shall, if required by the Engineer, deliver to the Engineer a return in detail, in
such form and at such intervals as the Engineer may prescribe, showing the staff and the
numbers of the several classes of labour from time to time employed by the Contractor on the
site and such there information as the Engineer may require.
During continuance of the contract, the contractor and his sub-contractors shall abide at all
times by all existing labour enactments and rules made there under, regulation, notifications and
bye laws of the State or Central Government of local authority and any other labour
law(including rules), regulations, bye laws that may be passed or notification that may be issued
under any labour law in future either by the State or Central Government or the local authority.
Salient features of some of the major labour laws that are applicable to construction industry are
given below. The Contractor shall keep the employer indemnified in case any action is taken
against the Employer by the competent authority on account of contravention of any of the
provisions of any Act or rules made there under, regulations or notifications including
amendments. If the Employer is caused to pay or reimburse, such amounts as may be necessary
to cause or observe, or for non-observance of the provisions stipulated in the
notifications/byelaws/Acts/Rules/regulations including amendments, if any, on the part of the
contractor, the engineer/employer shall have the right to deduct any money due to the contractor
including his amount of performance security. The employer/engineer shall also have right to
recover from the contractor any sum required or estimated to be required for making good the
loss or damage suffered by the employer. The employer of the contractor and the Sub-
Contractor in no case shall be treated as the employees of the employer at any point of time.
a) Workmen Compensation Act 1923: The Act provides for compensation in case of
injury
195
by accident arising out of and during the course of employment.
b) Payment of Gratuity Act 1972: Gratuity is payable to an employee under the Act on
satisfaction of certain conditions on separation if an employee has completed 5 years‘ service or more
or on death the rate of 15 days wages for every completed year of service. The Act is applicable to all
establishments employing 10 or more employees.
c) Employees P.F. and Miscellaneous Provision Act 1952: The Act Provides for monthly
contributions by the employer plus workers @ 10% or 8.33%. The benefits payable under the Act are:
(i) Pension or family pension on retirement or death, as the case may be(ii) Deposit linked insurance
on the death in harness of the worker. (iii) Payment of P.F. accumulation on retirement/death etc.
d) Maternity Benefit Act 1951: The Act provides for leave and some other benefits to women
CHAPTER - 20
employees in case of confinement or miscarriage etc.
e) Contract Labour (Regulation & Abolition) Act 1970: The Act provides for certain welfare
measures to be provided by the Contractor to contract labour and in case the contractor fails to
provide, the same are required to be provided, by the principal employer by law. The principal
employer is required to take certificate of registration and the contractor is required to take license
from the designated officer. The Act is applicable to the establishments or contractor of principal
employer if they employ 20 or more contractlabour.
f) Minimum Wages Act 1948: The employer is supposed to pay not less than the minimum
g) Payment of Wages Act 1936: It lays down as to by what date the wages are to be paid, when
it will be paid and what deductions can be made from the wages of the workers.
h) Equal Remuneration Act 1979: The Act provides for payment of equal wages for work of
equal nature to Male and Female workers and for not making discrimination against Female employees
in the matters of transfers, training and promotionsetc.
i) Payment of Bonus Act 1965: The Act is applicable to all establishments employing 20 or
more employees. The Act provides for payments of annual bonus subject to minimum of 8.33% of
wages and maximum of 20% of wages to employees drawing Rs.3500/- per month or less. The bonus
to be paid to employees getting Rs. 2500/- per month or above upto 3500/- per month shall be worked
out by taking wages as Rs.2500/- per month only. The Act does not apply to certain establishments.
The newly setup establishments are exempted for five years in certain circumstances. Some of the
State Governments have reduced the employment size from 20 to 10 for the purpose of applicability of
this Act.
j) Industrial Disputes Act 1947: The Act lays down the machinery and procedure for
resolution of Industrial disputes, in what situations a strike or lock-out become illegal and what are the
requirements for laying off or retrenching the employees or closing down the establishment
196
Central Government to 50). The Act provides for laying down rules governing conditions of
employment by the employer on matters provided in the Act and get the same certified by the
designated Authority.
l) Trade Unions Act 1926: The Act lays down the procedure for registration of trade unions of
workmen and employers. The Trade Unions registered under the Act have been given certain
immunities from civil and criminalliabilities.
m) Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits employment of
children below 14 years of age in certain occupations and processes and provides for regulation of
employment of children in all other occupations and processes. Employment of Child Labour is
prohibited in Building and ConstructionIndustry.
p) Factories Act 1948: The Act lays down the procedure for approval at plans before setting up a
factory, health and safety provisions, welfare provisions, working hours, annual earned leave and
rendering information regarding accidents or dangerous occurrences to designated authorities. It is
applicable to premises employing 10 persons or more with aid of power or 20 or more persons
without the aid of power engaged in manufacturingprocess.
Any Dispute or difference arising between the department and contractor shall be dealt in
accordance with J&K Arbitration Act in vogue.
(a) In case of Dispute or difference arising between the Employer and a domestic contractor relating
to any matter arising out of or connected with the agreement ,such disputes or difference shall be
settled in accordance with the Arbitration and Conciliation Act 1996.The parties shall make efforts
to agree on a sole Arbitrator and only if such an attempt does not succeed then the Arbitral
Tribunal
197
consisting of 3 Arbitrators one each to be appointed by the Employer and the contractor and the
third Arbitrator to be chosen by the two Arbitrators so appointed by the parties to act as presiding
Arbitrator, shall be considered. ,In case of failure of the two Arbitrators appointed by the parties
to reach upon a consensus within a period of 30 days from the appointment of the Arbitrator
appointed subsequently, the Presiding Arbitrator shall be appointed by the Council ,Indian Road
Congress.
b) The Arbitral Tribunal shall consist of three Arbitrators one each to be appointed by the Employer
and the Contractor. The third Arbitrator shall be chosen by the two Arbitrators so appointed by
the parties, and shall act as Presiding Arbitrator. In case of failure of the two Arbitrators
appointed by the parties to reach upon a consensus within a period of 30 days from the
appointment of the Arbitrator appointed subsequently, the Presiding Arbitrator shall be appointed
by the Council, Indian Road Congress.
CHAPTER - 20
c) If one of the parties fails to appoint the Arbitrator in pursuance of sub-clause (a) and (b) above
within 30 days after receipt of notice of appointment of its Arbitrator by the other party, then the
Council of Indian Road Congress shall appoint the Arbitrator. A certified copy of the order of the
Council of Indian Road Congress making such appointment shall be furnished to each of the
parties.
d) Arbitration proceedings shall be held at Srinagar/Jammu , India and the language of the
arbitration proceeding and that of all documents and communications between the parties shall be
English.
e) The decision of the majority of Arbitrators shall be final and binding upon both the parties .The
cost and expenses of Arbitration proceedings will be paid as determined by the Arbitral Tribunal.
f) Performance under the contract shall continue during the arbitration proceedings and payments
due to the contractor by the owners shall not be withheld, unless they are the subject matter of the
arbitration proceedings.
4. The defects liability period is 03Years from the actual date of completion [Cl.1.1 & 35]
198
5. The start date shall be seven days from the date of issue of the notice to proceed
[Cl.1.1of this chapter] with the work.
B. Amount of liquidated damages for delay in completion of work ------ For whole of work 1% of the
initial contract price, rounded off to the nearest thousand, per week.
C. Maximum limit of liquidated damages for delay in completion - 10% of the initial contract price of
work rounded off to thenearest
9. The works consist of -------------------------------------- The work shall, inter-alia, include the
following as specified or as directed. [Cl.1.1]
199
built‖ drawings and other related documents; and other items of work as may be required to be
carried out for completing the works in accordance with the drawings and the provisions of the
contract and to Insure safety.
(C)Building Works
To be incorporated
D) Other Items
Any other items as required fulfilling all contractual obligations as per the [Cl.1.1] of ITB Bid
documents.
The following documents also from part of the contract: [Cl.2.3(i) of GCC]
CHAPTER - 20
Specification of Roads and Bridges (4th edition)
1. The law which applies to the contract is law of Union of India [Cl.3.1 of GCC]
2. The language of the contract documents is English. [Cl.3.1 of GCC]
3. The Schedule of other contractors [Cl7 of GCC]
4. The schedule of key personnel [Cl.4.6(B) of Section-I]
5. The minimum insurance cover for physical property, injury and death is Rs. 5 lakhs per
occurrence with the number of occurrences limited to four. After each occurrence, contractor
will pay additional premium necessary to make insurance valid for four Occurrences always.
[Cl..12 of GCC]
6. Site investigation report [Cl..13 of GCC]
10. The period for submission of the programme for approval of Engineer shall be [Cl.26 of GCC]
21 days from the issue of Letter of Acceptance.
11. The period between Programme updates shall be 30 days. [Cl.26 of GCC]
200
17. The Securities shall be for the following minimum amounts equivalent as a percentage of the
Contract Price: Performance Security for 5% of contract price plus additional security on account of
un-balanced bid in terms of ITB Clause 26.4
18 The standard form of Performance Security acceptable to the Employer shall be CDR/FDR or an
unconditional Bank Guarantee of the type as presented in Section 8 of the Bidding Documents.
21 The amount to be withheld for failing to supply ―as built‖ drawings by the datarequired
Rs.2% of contract value.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
22. The following event shall constitute fundamental breach of contract. ―The Contractor has
Contravened Clause 9 of GCC.‖ [Cl.53 of GCC]
24. The percentage to apply to the value of the work not completed representing the Employer‘s
additional cost for completing the Works shall be 20 percent [.Cl.54 of GCC]
201
Annexure-I
In Original
CHAPTER - 20
[Name of Country]having our registered
office at (hereinafter called ―the Bank‖)are bound unto the
Name of Employer](hereinafter called ―the
Employer‖)in the sum of * for which
payment well and truly to be made to the said Employer the Bank binds himself, his successors and
assigns by these presents.
SEALED with the Common Seal of the said bank this day of 20 . THE
CONDITIONS of this obligation are:
1) If after Bid opening the bidder withdraws his Bid during the period of bid validity specified in
the Form of Bid.
202
.
Annexure-II
(BID Validity)
UNDERTAKING
1. The undersigned do hereby undertake that our firm M/s
agree to abide by this bid
for a period days for the date fixed for receiving the
same and it shall be binding on us and may be accepted at any time before the expiration of
that period.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Title of Officer
Time of firm
Date
Annexure-III
Credit facility
is awarded to the above firm, we shall be able to provide overdraft/ credit facilities to the
extent of Rs.
to meet their working capital requirements for executing the above contract
during the contract period.
(Signature) Name of
Bank Address of the
Bank
203
Annexure-IV
AFFIDAVIT on correctness of Information furnished with the Bid.
1. I, the undersigned, do hereby certify that all the statements made in the required attachments
are true and correct.
2.The undersigned also hereby certifies that neither our firm
M/s have abandoned any work on National
Highways in India /any other work of state Government or central Govt. Nor any contract awarded to
us for such works have been rescinded, during last five years prior to the date of this bid.
That our firm has not been black listed or debarred in any state or central Govt. department .Neither
our firm has any history of litigations.
In case the contract for the work is awarded in our favour we shall invest a minimum cash up to 25%
of value of the contract during the implementation of work.
CHAPTER - 20
We authorise the department to seek references from our bankers
Name of bank is Branch Account No.
3. The undersigned hereby authorize (s) and request (s) any bank, person, firm or
Corporation to furnish pertinent information deemed necessary and requested by the Department to
verify this statement or regarding my (our) competence and general reputation.
4. The undersigned understand and agrees that further qualifying information may be requested,
and agrees to furnish any such information at the request of the Department/Project implementing
agency.
WE solemnly affirm that the information give in the bid is correct to the best of my knowledge and
belief and nothing of any sort has been concealed.
Title of Officer
Name of Firm
DATE
Annexure-V
PERFORMANCE BANK GUARANTEE
To,
.............................................. [Name of Employer]
………………………… …[ address of Employer]
……………………………………………………………..….
WHEREAS [name and address of
Contractor] (hereinafter called ―the Contractor‖) has undertaken, in pursuance of Contract
No. dated to execute _ [name of
Contract and brief description of Works] (hereinafter called ―the Contract‖);AND WHEREAS it
has been stipulated by you in the said Contract that the Contractor shall furnish you with a Bank
Guarantee by a Nationalized/Scheduled bank of India for the sum specified therein as security for
compliance with his obligations in accordance with the Contract.
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee.
NOW THEREFORE we hereby affirm that we are the guarantor and responsible to you on behalf
of the Contractor, up to a total of Rs. [amount of guarantee] (Rupees________________)
204
such sum being payable in the types and proportions of currencies in which the Contract Price is
payable, and we undertake to pay you, upon your first written demand and without cavil or
argument, any sum or sums within the limits of [amount of guarantee] as aforesaid
without your needing to prove or to show grounds or reasons for your demand for the sum
specified therein. We hereby waive the necessity of your demanding the said debt from the
Contractor before presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of the Contract
or of the Works to be performed there under or of any of the Contract documents which may be
made between you and the Contractor shall in any way release us from any liability under this
guarantee, and we hereby waive notice of any such change, addition or modification.
This guarantee shall be valid until 28 days from the date of expiry of the Defects Liability Period.
Signature and seal of the guarantor
Name and Designation
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
* An amount shall be inserted by the Guarantor, representing the percentage the contract price
specified in the contract including additional security for unbalanced Bids. If any and
denominated in Indian Rupees.
Annexure-VI
UNDERTAKING
Title of Officer
Name of Firm
DATE
205
Annexure-VII
Letter of Acceptance
(Letterhead paper of the Employer)
…………………………… (Date )
To:
( Name and address of the contractor)
Dear Sirs,
This is to notify that your Bid dated for execution: completion and
maintenance of the (name of the contract and identification number,
as given in the Instruction to Bidders) for the Contract Price of Rs. (Rupees
Authorized signatory
(Name & title of signatory
(Name of Agency)
1. Delete ―corrected and‖ or ―and modified‖ if only one of these actions, Delete as corrected and
modified in accordance with the Instructions to Bidders, if corrections or modifications have not been
affected.
2. To be used only if the contractor disagrees in his Bid with the Adjudicator proposed by the
Employer in the ―Instructions to Bidders‖.
Annexure-VIII
Issue of Notice to proceed with the work
(Letterhead of the Employer)
(Date)
To,
(Name and address of the Contractor)
Yours faithfully,
206
.
Agreement Form
Agreement
Annexure-IX
name and identification number of Contract) (hereinafter called ―the Works‖) and the Employer
s accepted the Bid by the Contractor for the execution and completion of such Works and the
remedying of any defects therein, at a contract price of Rs._ NOW THIS AGREEMENT
WITNESSETH as follows:
1. In this Agreement, words and expression shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to, and they shall be deemed
to form and be read and constructed as part of this Agreement.
2. In consideration of the payments to be made by the Employer to the Contractor as hereinafter
mentioned, the Contractor hereby covenants with the Employer to execute and complete the
works and remedy any defects therein conformity in all aspects with the provisions of the
Contract.
3. The Employer hereby covenants to pay the Contractor in consideration of the execution and
completion of the Works and the remedying the defects wherein the Contract price or such other
sum as may become payable under the provisions of the Contract at the times and in the manner
prescribed by the Contract.
4. The following documents shall be deemed to form and be read and constructed as part of this
Agreement viz:
i) Letter of Acceptance
ii) Notice to proceed with the works:
iii) Contractor‘s Bid;
iv) Contract Data:
v) Conditions of Contract : Special Conditions of Contract;
vi) Additional condition:
vii) Drawings:
viii) Bill of quantities and
ix) Any other document listed in the Contract Data as forming part of the contract.
In witnessed whereof the parties there to have caused this Agreement to be executed the day and
year first before written.
The Common Seal of ..................was hereunto affixed in the presence of: Signed, Sealed and
Delivered by the said……………………………………………………………………………
207
......................................................................................................................................................
CHAPTER - 20
20.6.1.9 Drawings & BOQ
NOTE: The SBD is broadly based on the generic guidelines necessarily broad in nature
on the Manual for procurement of works 2019 issued by department of Expenditure, Ministry
of Finance, GoI. It has been supplemented to suit the local/specialized needs ofPWD.
208
20.6.2 Standard Bidding documents for Heritage work.
Tender Document
Conservation of _ (Heritage Site) Contents
S. No. Particulars
Tender notice
Articles of agreement
Proforma 1 to 9
Specifications
Schedule of quantities
Drawings
209
1. Memo of issue of tender
CHAPTER - 20
Date of submission :
2. Tender notice
Infrastructure
The contractor should have supporting infrastructures such as scaffoldings, grouting machines,
and lime mortar machine, water spray machines, tools used for conservation works etc.
In-House Team
The contractor shall have in-house skilled labors, masons craftsmen, supervisors and technician.
He/ she shall also appoint a conservation architect or a well-qualified civil engineer or
experienced architect on site to supervise the work full time.
210
Important points for applying
1. The conditions should be read carefully and, understood clearly before applying and pricing the
schedule for various items. Only those shall apply who have working experience in building
conservation.
2. The documents supplied comprise of various sections as detailed on the "Contents" sheet. Tender
shall be completed filling all the blanks appropriately.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
3. Full signatures should be affixed as required at places particularly marked "Signature ofTenderer"
and the form of Tender shall also be witnessed.
4. All other pages of the tender documents shall be initialed before submission of the tender.
Rates must invariably be quoted in words also.
5. List of works in hand at the time of submission of tender should be given together withrelevant
contract amount, contract period and date of commencement of such works.
7. Complete set of documents and the schedule of quantities should be returned in a sealedcover
together with the drawings, if supplied.
8. Complete set of documents and the schedule of quantities should be returned in a sealed cover together
with the drawings, if supplied.
Envelop No.1: This is to contain forwarding letter and instrument of earnest money and
the cost of tender document if not submitted. There will be only specified document as
stated below.
Envelop No.2: This is to contain the priced schedule of quantities, the specifications,
conditions, etc. No alterations shall be done to the documents, is any changes /
clarifications, counter conditions, etc. will be in the forwarding letter in envelop No.1 only.
211
List of documents to be submitted along with tender:
CHAPTER - 20
Documents) submitted at any stage, we shall be entirely responsible and liable for any action
as deemed fit under the Law".
i. Original documents shall be produced as required for cross verifications. on opening of
technical bid of tender- ENVELOPE–I.
All the above certificates / documents shall be submitted duly signed with seal and attested
from a Gazetted Officer or an officer in PSE or their C.A.
10. Every tender shall be accompanied by Earnest Money of Rs. 50,000/- (Rupees Fifty Thousand
Only) in the form Demand Draft drawn in favour of-------------------------- J & K‖ and any--------
---
------ payable at of ― tender not accompanied by such Earnest
Money is liable to be rejected straightway. (E.M.D. in any other form shall not be accepted)
11. Conservation architect of the project will first scrutinize and settle all conditions stated by all
the tenderers in their covering letters (if any) before opening the priced part of the tender. If
necessary, the priced schedule of quantities will be kept in the safe custody of the Employer
until such time as all clarifications/negotiations necessitated due to the conditions stated
by the tenderers are obtained/conducted to the satisfaction of Employer/Architect / to enable
him to consider the priced schedule of quantities on a reasonably comparable basis. The rates
shall be all inclusive.
12. Notwithstanding the option of the Employer / Architect / to seek clarifications / negotiations on
conditional tenders, he never- the less reserves the right to summarily reject conditional tenders.
No escalation except as provided in the standard conditions will be considered for any other
item and such stipulation, if made, will render the tender liable to be rejected.
13. Time is the essence of the contract. The time allowed for the completion of the work is 4 (four)
months from 2 weeks after the date of written order to commence work. The successful
contractor will have to consult the conservation architect of the project and finalized the
conservation strategy, process of specialized conservation items of works, specification and
resources of the materials required for the project, mortar proportions etc. A bar chart of,
various activities of work should be prepared so that the work gets completed within the
stipulated time and required quality could be obtained. The exercise shall be done within 15
days from the date of acceptance of tender.
212
14. The Earnest Money will be retained in the case of the successful tenderer as part of the security
for due fulfillment of the contract. In case the successful tenderer does not accept work order or
does not start the work physically within two weeks from the date of issue of work order,
earnest money will be forfeited in favors of the Employer. There upon the work order shall
stand withdrawn.
15. The tenderer will submit his tender after carefully examining the whole of the tender documents
and the conditions of tender and of contract, Appendix to the conditions of contract, the
drawings and specifications, the bills of quantities, etc. and after a detailed examination of site
conditions likely to be met.
16. The Contractor whose tender is accepted shall furnish by way of initial security deposit, for the
fulfillment of the contract such sum as will amount to 2% of the total value of the contract
including the Earnest Money (E.M.) deposited along with the tender and the Earnest Money will
form part of the security Deposit. The initial security deposit is to be paid by the contractor, to
the Employer / within 14 (fourteen) days of intimation to him of the acceptance of this
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
tender. This initial security Deposit (excluding the EMD) shall be acceptable in the form
of a Bank Guarantee. Such Bank Guarantee shall be from a nationalized bank in the form to be
approved by the Employer/Architects.
17. Together with the money paid under clause 17 above further retention of 8% of the value of the
work done from every running bill will be deducted till total retention including EMD and
initial security Deposit paid earlier is 5% of the contract value, and shall be held by the
employer as Total Security Deposit. This Deposit will also be acceptable in the form of a Bank
Guarantee from any nationalized Bank. On the Architects/Employer certifying to the
completion of the work, 50% of the total Retention amount shall be released to the contractor
with the final certificate of payment and the balance 50% will be retained for a further period of
12 months after the completion certificate is issued by the Employer/Architects, or shall be
released against Bank Guarantee from any nationalized bank , valid for 12 months.
18. In case, where the same item of work is mentioned at one or more places in the schedule of
quantities the lowest of the rates quoted by the contractor for the item shall be taken for the
payment of this item, and shall be binding on him.
19. The rates quoted by the contractor shall include all eventualities such as heavy rain, sudden
floods etc., which may cause damage to the executed work or which may totally wash out the
work. Until the completion certificate is issued to the contractors, the employer will not be
responsible for such damage or wash out of the construction work.
20. If the contractor fails to complete the work by the scheduled date of completion or within any
sanctioned extended time, he will have to pay liquidated damages at 0.5 % (half) of balance
contract amount for each week beyond the date that the work remains incomplete subject to
maximum of 5% of the contract value ( without extra items) as per clause 29 of the General
conditions of contract.
21. If the contractor completes the work before the scheduled date of completion he will be able to
get incentives at 0.5% for each week.
22. Mobilization advance, if required by the contractor, can be granted up to maximum of 5% of the
contract value against Bank
213
23. Guarantee of equivalent amount from any nationalized Bank valid for the full currency of the
contract. The total advance will be recovered with interest in installments to be decided by the
Employer/Architects in such a manner that the total recovery is made before 80% of the total
contract amount work is complete.
24. The notice inviting tenders (filled up pre-qualification document), the conditions of tender andthe
duly completed form of tender will form a part of the agreement to be executed by the successful
tenderer with the Employer.
Your faithfully
CHAPTER - 20
For J & K SIGNATURE OF THE TENDERER
214
3. The General Condition Of The Tender
1. In the event of the tender being submitted by a firm, it must be signed by a person duly
authorized through a power of attorney issued by all the partners and a certified copy of the
power of attorney should be enclosed with the forwarding letter or separately by each member
thereof, or in the event of the absence of any partner, it must be signed on his behalf by a person
holding a power of attorney authorizing him to do so and such power of attorney shall be
produced with the tender and it must disclose that the firm is registered under the Indian
partnership Act.-'Each and every signature given shall be separately witnessed. A Contractor or
Contractors who himself / themselves has/have tendered or who may tender for the work shall
not witness the tender of another person for the same work. Failure to observe this condition
would render tenders of the contractors tendering as well as witnessing the tenders liable for
summary rejection.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
2. The tenderer must quote his rates only on the proper form of the tender, both in figures and
words and both in decimal coinage in the respective spaces provided there for . If the rates' are
not quoted in words also the tender is liable for rejection. The amount for each item should be
worked out in figures only for the probable quantities specified in the bills of quantities and the
requisite total given both in figures and words. Special care is to be taken to write the rates in
figures and words in such way that no interpolation is possible. Erasures and alterations must be
avoided, but if made unavoidably while pricing the bills of quantities, the wrong figures and
words must be neatly scored under the initials of the tenderer and the correct figures and words
neatly rewritten (but not overwritten or by using white fluid).Overwriting is not permitted. In the
case of figures, the word ‗Rs.‘ should be written before the figure of rupees and the word 'P'
written after the decimal figures, e.g. Rs. 2.15 P & in the case of words, the word 'Rupees' should
similarly precede and the words ' Paise only' should be written at the end, closely following each
rate & each amount. The words 'only' should not be written in the next line. Unless the rate
quoted is in whole rupees closely followed by the word 'only' the amount should invariably be up
to two decimal places.
3. Errors in the pricing of bills of quantities shall be dealt with in the following manner :-
(I) In the event of a discrepancy between the rates quoted in words and the rates in
figures the former shall prevail.
(ii) In the event of an error occurring in the amount column of the bills of quantities as a
result of the wrong extension of the unit rate and the quantity, the unit rate shall be
regarded as firm and extension shall be amended on the basis of the correct rates.
(iii) All errors in totaling in the amount column and in carrying forward the totals shall be
corrected.
(iv) The tender total shall be accordingly amended except that there shall be no
rectification of any errors, omissions or wrong estimate, in the prices inserted by the
tenderer in the bills of quantities.
4. Where alternative items are given, only the rates in figures and words are to be entered and not
the amounts there of. A tender which does not show the rates in figures and words for the
alternative items may be rejected. The Employer reserves to himself the right to take into account
any or all of the alternative items for the purpose of accepting a tender or to operate upon any or
all of the said alternative items during the execution of the work, partly or fully, as required. The
resultant variation in quantities of the relevant items shall not vitiate the contract.
215
5. The quantities furnished in the bills of quantities are only probable quantities liable to alternation
by omission, deduction or addition, and it would be clearly understood that the contract is not a
lump sum contract and the Architects do not, in any way, assure the tenderer or guarantee that
the said probable quantities are correct or that the work would correspond thereto. Payments will
be regulated on the actual quantities of work authorized done and measured at the site at the
accepted rates. No claims for change in quantities (+ or -) will be entertained. The drawings,
forming parts complementary installations specifications and the bills of quantities, of the
contract, are explanatory of and are to one another, representing together the works / to be carried
out.
If neither the drawings nor the specifications nor the accepted bills of quantities include any
part/parts the intention to include which is nevertheless clearly inferred and which are obviously
necessary for the proper completion of the works/ installations, all such parts shall be supplied
and executed by the contractor at no extra charge.
CHAPTER - 20
Anything contained in one or another of (a) the drawings, (b) the specifications and (c) the
accepted bills of quantities and not found in the others will be equally binding as if it were
contained in each of them.
6. No alterations, which are made by the tenderer in the drawings, specifications, or probable
quantities accompanying this notice will be recognized and if any such alterations are made the
tender will be invalid. Remarks or explanations should be set out in duplicate in a separate
covering letter and will become binding only if specifically accepted in writing by the Employer
at the time of acceptance of the tender. Conditional tenders will however be liable for summary
rejection.
8. The tenderer shall also bear all expenses in connection with the preparation and submission of
his tender and attendance for subsequent negotiations/clarifications. Omission, neglect or failure
on the part of the tenderer to obtain requisite and reliable information on any matter affecting his
tender, the contract and the construction, completion and maintenance (during defects liability
period) of the work shall not relieve the tenderer whose tender is accepted from any liability in
respect of the contract.
The tenderer whose tender is accepted shall not be entitled to make any claim for increase in
the rates quoted and accepted excepting in pursuance of any specific provision in the contract as
such and then only in terms of that specific provision or to make any representation on the
ground that he was supplied with any information or given any promise or guarantee of any sort,
by the Employer, his agents and servants of by the Architects or their representatives or by any
'other persons, unless such information, promise or guarantee was furnished to the tenderer in
advance of the date of receipt of tenders and in writing under proper authority.
9. The Contractor, upon award of work, shall furnish the following details for the approval of the
Conservation architect of the project:
Material specification should be finalized in consultation with the project conservation architect.
Contractor should collect the samples of the required materials such as lime, sand, surkhi, wood,
bel, san, colors, mud etc.
216
These should tested in the lab and then approve. The names of manufacturers of specialized items
such as patented water proofing systems / materials, flush doors, flooring tiles, false ceilings,
insulating materials, , steel, glazing, etc. which he proposes to use in the work.
The makes and types of fittings, materials, subject to the makes and type stipulated in the
specifications, which he proposes to use in the work.
The details of licenses granted to him and/or to professional qualified and/or licensed technical
personnel on his staff who will be engaged on the work (and submit, if called for, the licenses for
inspection by the Architects).
Only approved agencies shall be use to obtain such specialized items and approved agencies
deployed to carry out requisite items of work. The Architect's decision in this regard shall be
binding to all the parties concerned.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
10 The rates quoted in the bills of quantities shall unless specified otherwise will be for all heights,
be deemed to be for finished work insitu, item by item as provided for, and shall include cost for
all necessary material and labors, all necessary incidental charges such as water, electricity, tools
and plants and machinery, sheds, marking out, clearing site, etc. and for all taxes, octroi, excise,
Sales Tax on works contract and any other tax or duty levied by Government, Central or Local,
or Local Authority, if any as applicable. The rates shall be firm and not be subject to any
variations in exchange rates, in taxes, duties etc. in railway freight and the like including labor
conditions, etc. The rates are not subject to escalation otherwise than as specifically provided for
in the contract.
11 It will be the sole responsibility of the contractor to procure all required materials such as Lime,
wood, sand and as well as equipments such as lime chakki , water spray machines etc required
for the work and for its safe storage and custody at site. The contractor shall purchase these
materials only of approved manufacturer and only from the authorized dealers. These materials
shall conform to the relevant ISI standards and the detailed specifications stipulated elsewhere in
this contract. The contractor shall maintain a proper account of quantity of lime , surkhi , sand
and other materials purchased and brought to the site of work and that utilized in the work and he
shall also maintain any other accounts in the manner as may be required by the
Employer/Architects. He shall also allow inspection of all these accounts, records and also of
stocks in hand, by the authorized representatives of the Employer/Architects.
12 The tenders submitted shall remain open for acceptance for a period of 90 days from the date
of their opening. Should any tenderer withdraw his tender before the expiry of the said period or
make any modifications to his tender which are not acceptable to the Employer the earnest
money will stand forfeited.
13 The Employer does not bind himself to accept the lowest tender and reserves to himself the
right to reject any or all of the tenders received without assigning any reason. Further, the
Employer reserves the right to award any component of the project or group of components to
tenderers or to award the entire work to one tenderer.
14 The Employer further reserves the right to delete or reduce at any time, any section of the
bills of quantities with out assigning any reasons whatsoever there for and no claim will be
entertain in this regard.
217
15 The tenderer whose tender is accepted is bound to execute formal agreement with the Employer
within one month of the date of intimation of award of work in accordance with the draft
agreement which will include but not be limited to the notice inviting tender, condition of
tender, form of tender, Articles of Agreement, Bills of quantities, Conditions of contract,
Special conditions if any, the drawings and specifications, but his liability under the contract
shall commence from the date of written order to commence work whether the formal
agreement is drawn or not. The Contractor shall bear all expenses in connection with the
execution of the said agreement including fees for stamping and registration of documents as
required.
16 The Contractor whose tender is accepted shall furnish by way of initial security deposit, for the
fulfillment of the contract such sum as will amount to 2% of the total value of the contract
including the earnest money (E.M.) deposited along with the tender and the Earnest Money will
form part of the security Deposit. The initial security deposit is to be paid by the contractor to
the Employer within 14 (fourteen) days of intimation to him of the acceptance of his tender.
This Initial security Deposit (excluding the EMD) shall be acceptable in the form of a bank
CHAPTER - 20
guarantee such guarantee shall be from a nationalized bank in the form to be approved by the
Architect and the Employer.
17 The Retention Money will be realized by deduction from the running bills at 8% of the value
of work done as certified by the Architects from time to time till such time when together with
the initial security deposit such deductions amount to a maximum 5% of the contract value.
18 The Total Retention amount will be acceptable in the form of a Bank Guarantee from any
nationalized bank. 50% of the Total Retention amount shall be released to the contractor
with the final certificate of payment and the balance 50% will be retained for the duration of
19 The Security Deposit or Retention Money will bear no interest what so ever until the date of
release.
20 Any tender which is conditional or purports to alter, vary, omit any of these conditions is likely
to be rejected.
21
a) The contractor, upon award of work, is required to consult the conservation architect of the
project and should prepare the conservation strategy, bar charts for various items, process
of specialized conservation items of work, materials specifications, tools specification,
drawing verifications to carry out conservation works on site etc He should get written
approval of the conservation architect for all conservation items of work .
b) Over and above the contractor has to supply monthly programme chalked out showing
important milestones to be achieved and the progress actually achieved compared with, the
target of the same in the programme and shortfall, if any planned for being made up in the
programme for next month. It should be submitted in Proforma given on page No.---------
c) The first running bill of the contractor shall not be certified by the Architect unless the
programme is satisfactorily submitted to the architect. Further the architect shall have the
power to withhold subsequent certificates if relevant detailed monthly programs are not
submitted.
22
a) The work in general shall conform to the "Specifications 91-92-96 & latest electrical
specification published PWD, and the "Specifications for works" stated in this tender.
b) In case items not covered by the general specifications referred to in 22 (a) above, reference
shall be made to the appropriate I.S. Code.
218
c) Should there be any difference in the particular specifications of individual item of work
and the description of item as given in the Schedule of quantity, the latter shall prevail.
d) In case of any work for which there is no specification in I.S. specifications or in the
specifications forming part of tender documents or in case there is any variation, such work
shall be carried out in all respects in accordance with the instructions to be issued by the
Architect..
23 Water supply, Drainage, Sanitary Installations and Electrical work shall be executed in
conformity with the rules, regulations and byelaws of local Municipal / Electrical
Authorities.
24 The Contractor, upon the award of contract, shall furnish all the particulars required and
make the necessary applications, if any, to the local Municipal Authorities or Electrical
Boards for obtaining water supply and under ground sewage or electricity connections,
transformer and obtain the same at his cost for temporary connection, but for permanent
connection Employer will reimburse the amount after submitting proper document.
25 The work shall be carried out under the directions and supervision of and subject to the
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
26 Canvassing in connection with tenders is strictly prohibited and the tender submitted by the
Contractor who resorts to canvassing is liable to be rejected.
27 Any item rate tender containing percentage below / above will be summarily rejected but
there is no objection to Contractors giving over all rebates on their rates in the tender.
28 On acceptance of the tender the Contractor shall in writing and at once inform the Employer
and the Architects the name of his accredited representative(s) who will be responsible to
take instructions from the Architects / Employer.
29 The work of any part of it shall not be transferred, assigned or sublet without the written
consent of the Employer.
30 The Contractor shall be required to co-operate and work in co-ordination with and afford
reasonable facilities for such other agencies / specialists as may be employed by the
Architects on other works /sub-works in connection with the project/scheme of which this
work forms a part.
31 The Contractor will be required to insure the work as per clauses 25 and 26 of the Conditions
of Contract.
32 The Contractor shall be required to conduct required tests of tube-well water (if a new tube
well is to be bore) from approved Laboratory.
33 The Contractor is required to comply with all Acts of Government relating to labour and the
Rules and Regulations made there under from time to time and to submit at the proper times
all particulars and statements required to be furnished to the appropriate Authorities.
219
4. Form of the Tender Works
To
,J & K
Dear Sir/s,
Having duly examined the tender documents including the drawings, specifications, designs, schedule
of quantities relating to the works specified in the under written memorandum and having visited the
site of the said works and having acquired all the requisite information relating there to as affecting
this tender, I we hereby offer to execute the works specified in the under written memorandum within
the time specified there in at the rates specified in the schedule of quantities and in accordance, in all
respects, with the specifications, designs, drawings and instructions in writing referred to in the
conditions of tender, the Articles of Agreement, special conditions, the schedule of quantities and
CHAPTER - 20
conditions of contract and with such materials as are specified by and in all other respects in
accordance with such specifications, the schedule of quantities and the conditions of contract as
applicable.
Memorandum
Percentage, if any, to be deducted: 8% from running bills (From Running Account Bills)
I / We do hereby undertake to execute and complete the whole or part of the work (as desired by
you) at the respective rates which I/We have quoted in this tender, I/We further hereby agree to
abide by and fulfils all the terms and provisions of the said conditions of contract annexed hereto
and the conditions of tender as applicable or in default there of to forfeit and pay the sums of
money mentioned in the said conditions.
A sum of Rs.50, 000/- (Rupees Fifty Thousand only) is hereby forwarded as Earnest Money
Deposit (E.M.D.) in the form of Demand Draft drawn in favor of― ___ ,payable at
On .
I/we agree that should I/we fail to commence the work as specified in the above mentioned
memorandum the Employer shall without prejudice to any other right or remedy be at liberty to
forfeit the earnest money, otherwise the said earnest money shall be retained by him towards
security deposit mentioned in the above memorandum (ii) to execute all the works referred to in
the tender documents upon the terms and conditions contained or referred to therein and to carry
out authorized variations at the rates quoted in the tender.
220
Our Bankers are:-
1.
2.
3.
2.
3.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
221
5. Articles of agreement
CHAPTER - 20
quantities and specification describing the work to be done to be prepared by the
, , (hereinafter called "the Architects / conservation architect").
AND WHEREAS the said drawings numbered as on page ----------- inclusive, the bills of quantities
marked page --------(inclusive) and the specifications as stated have been signed by or on behalf of
the parties hereto:
AND WHEREAS the Contractor has agreed to execute the work upon the conditions of tender and
the conditions of contract and further subject to the special conditions set forth in schedule- II
hereto attached (hereinafter collectively referred to as " the said conditions") as per the said
drawings and as described in the said specification and included in the said bills of quantities for the
sum of Rupees. ---
222
Schedule I
Schedule II
As per addendum, correspondence and the letter of acceptance marked pages--------to ----- --.
As Witness our hands the day and year first above written, in presence of
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Occupation: Designation:
Address: Address:
in presence of
1. Interpretation Clauses
In construing these conditions, the specifications, the schedule of quantities and contract
agreement, the following words shall have the meanings herein assigned to them except where the
subject or context otherwise requires.
Headings and marginal notes to the conditions of contract shall not be deemed to form part thereof
or be taken into consideration in the interpretation or construction thereof or of the contract.
Where the context so required, words importing persons include firms and corporations and words
importing the singular also include the plural and vice versa.
Employer shall mean, PWD, ― ― ADDRESS_
Architects/ conservation architect shall mean project team of
PWD , Address , J & K.
Contractor shall mean -
include his/their (Legal representatives,) permitted assigns or successors.
Site shall mean the land and/or other places on, into or through which work is to be executed
under the contract or any adjacent land, path or street through which work is to be executed under
the contract or any adjacent land, path or street which may be allotted for use for the purpose of
carrying out the contract.
The contract or this contract shall mean the tender documents comprising of the notice
inviting tender, instructions to tenderers, form of tender, the tender conditions, the drawings,
priced bills of quantities, the acceptance thereof and the articles of agreement, together with the
223
conditions of contract with the appendix and special conditions, if any, the specifications, designs,
drawings and instructions issued from time to time by the Architects. And all these documents
taken together are deemed to form one contract and they shall be complementary to one another.
Bills of quantities variously also termed 'priced bills of quantities', 'Schedule of quantities',
'Schedule of rates' shall mean the schedule of quantities originally furnished with the notice
inviting tender, duly priced in by the tenderer and accepted by the Employer for inclusion as a part
of the contract for contract agreement it may also be referred to as the contract schedule.
Notice in written or written notice shall mean a notice in written, typed or printed
CHAPTER - 20
characters sent (unless delivered personally or otherwise proved to have been delivered) by
registered post to the last known private or business address or to the registered office of the
addressee and shall be deemed to have been received when in the ordinary course of post it would
have been delivered. "Drawings" shall mean the drawings referred to in the Specifications and any
modifications of such drawings approved in writing by the Architect and such other drawings as
may from time to time be furnished or approved in writing by, the Architect.
Act of Insolvency shall mean any Act of Insolvency as defined by the Presidency Towns
insolvency Act or the Provincial Insolvency Act or any act amending such original.
Net Prices: If in arriving at the contract amount the Contractor shall have added to or deducted
from the total of the items in the tender any sum, either as a percentage or otherwise, then the net
price of any item in the tender shall be the sum arrived at by adding to or deducting from toe
actual figures appearing in the tender as the price of the item a similar percentage or proportion of
2. Architects Instructions:
The contractor shall execute the whole and every part of the work in the most substantial
(superior) and workmanlike (1st class) manner both as regards materials and work man ship and
otherwise in every respect in strict accordance with the specifications, conforming exactly, fully
and faithfully to the designs, drawings and instructions in respect of the work given by the
Architects and under the directions of and under the supervision of and subject to the approval in
all respects by the Architects who may in their discretion and from time to time issue further
drawings and/or written instructions, directions and/or details and explanations which are
hereafter collectively referred to as "Architects Instructions" in regard to:
b. Any discrepancy in the drawings or between the schedule of quantities and/or drawings
and/or specifications.
224
c. The removal from the site of any materials brought thereon by the Contractor and the
substitution of any other materials there for.
e. The dismissal from the works of any persons employed there upon.
g. The amending and making good of any defects under clause- 20. Conditions of Contract.
i. The Contractor shall forthwith comply with and duly execute any work strictly in accordance
with such Conservation architect/ architect instructions provided always that verbal instructions,
directions and explanations given to the Contractor or his representative upon the works by the
Architects shall, if involving a variation, be confirmed in writing by the Contractor within seven
days and if not dissented from in writing within a further seven days of receipt of such
confirmatory order by the Architects such shall be deemed to be ―Architect's instructions ―
within the scope of the contract.
j. Manner of execution of work: The Architect shall be entitled to direct at what point or points
and in what manner the works are to be commenced and from time to time carried on.
k. Variation to be approved by Employer: Not with standing anything herein contained, the
Architects or their representative shall not, without the prior concurrence in writing of the
Employer, issue any instructions verbal or in writing which will result in the employer having to
pay the Contractor an additional sum greater than Rs. 10,000. When such instructions are issued
to the Contractor shall submit through the Architects a statement of variations giving quantity
and rates duly supported by analysis of rates, vouchers, etc. The rates of scrutiny and final
acceptance of the Employer under the terms of clause 18 here of shall form a supplementary
schedule of rates.
225
described therein provided that the same may be reasonably inferred there from, and if the
contractor finds any discrepancy in the drawings, or between the drawings, schedule of
quantities and the specifications, he shall immediately and in writing refer the same to the
Architects who shall decide which is to be followed, subject to :
a. Any thing shown or contained in anyone or other of
(i) the drawings,
(ii) specifications and
(iii) the contract schedule and not shown in the others shall be equally binding as if it were
contained in each of them.
b. Figured dimensions are to be followed in preference to the scaled and large scale details in
preference to small scale drawings.,
CHAPTER - 20
i. The drawings,
ii. Specifications, covered by bills of quantities,
iii. Architect's specifications,
iv. The latest CPWD Specification
v. IS Codes and Standards.
5. Contractor to Conform to Local Regulations
The Contractor shall conform to the provision of any Act of the legislature relating to the
works and to the Regulations and Bye-laws of any Authority and of any water, lighting and other
companies and/or Authorities with whose systems the works are proposed to be connected., and
226
with the Architect's instructions, and the Contractor shall upon the request of the Architect furnish
proof to his satisfaction that they so conform and, if required, shall also furnish all invoices,
accounts, receipts and other vouchers for the purpose. The Contractor shall place orders for all
materialsrequired in time and in any case not later than the dates fixed in the approved programme.
Where in the matter of procurement of such materials as arecontrolled or the distribution of
which is regulated by Government, Central or Local, or by any other Central or Local Authority, the
Employer is obliged to issue any certificates or sign applications for license permit, by virtue of
orders of such Government or Authority or by custom or practice it shall be the sole responsibility
of the Contractor to arrange for matter with the concerned Authorities and to procure the materials
in time for incorporation in the works/installations according to the programme, and the Employer
or the Architects will not assume any responsibility for delays in this regard nor any responsibility
for the payment of fines, penalties, demurrage and the like due to the Contractor not taking timely
action in the process of procurement.
The Contractor shall not raise any plea, quoting delays in the completion of the formalities or
ofdelays by the Authorities concerned, for any compensation whatsoever. However, the Contractor
shall before he places orders for supply, furnish to the Architect, at his own expenses, samples of
materials proposed to be used in the works, well in time. The Architects shall within two weeks of
the day of supply of samples or within such further period as it may require depending upon each
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
case intimate to the Contractor whether the samples are approved or not. If samples are not
approved the contractors shall forth wise arrange to supply to the Architect for his approval fresh
samples complying with specifications and with the Architect‘s instructions.
The Contractor shall indemnify the" Employer or any agent, servant or employee of the Employer
against any action, claim or proceeding relating to infringement or use of any patent or design or
any alleged patent or design rights and shall pay any royalties or other charges which may be
payable in respect of any article or material or part thereof included in the contract. In the event of
any claims being made or action being brought against the Employer or any agent, servant or
employee of Employer in respect of any such matters as aforesaid, the Contractor shall
immediately be notified thereof provided that such indemnity shall not apply when such
infringement has taken place in complying with specific directions issued by the Employer or the
Architect in connection with the contract in spite of the Contractor having brought to their notice
such likely infringement or other wise. However, the Contractor shall pay any royalty or other
charges in respect there of. All charges on account of octroi, terminal or sales tax and other duties
including cartage on materials obtained for the work from any source shall be borne by the
Contractor. The Contractor should include in his rates all charges mentioned above.
8. Test of Material
The Architect shall be entitled to have tests carried out where and when deemed necessary (in
addition to the mandatory tests required by the C.P.W.D. Specifications) for materials to be
incorporated in the works/installations, supplied by the Contractor or otherwise, notwithstanding
that as provided in the previous sub-clauses, satisfactory proof has already been furnished, at the
cost of the Contractor who shall also provide at his expense all facilities which the Architect may
require for the purpose Samples, whether submitted to govern bulk supplies or required for testing
before use, and suitable packages to contain them shall be provided free of all charges by the
Contractor. Testing charges, if any, shall be borne by the Employer. All other expenses required to
be incurred for taking the samples, packing, conveying, transportation etc. shall be borne by the
Contractor himself. The Employer's liability to bear testing charges is in nature of reimbursement to
the Contractor i.e. the Contractor shall pay the charges initially direct to the testing agency. The
Contractor shall not be entitled to any other expenses, overheads, incidentals. He shall produce
proper account, and supporting details for verification by the Site In charge and the Architect. The
site In charge shall maintain a register of tests. The entries shall be signed by Contractor‘s
representative and, by the Site In charge. The register shall remain in custody of the Site In charge. /
Assistant Engineer. For the field tests made at site by the Contractor, there shall be no payment by
the Employer. The methods of sampling, the nature and extent of the tests to be carried out and their
interpretation shall be in accordance with the relevant Indian standards unless otherwise provided
for in this contract. The names of the laboratories or test houses in which the tests are to be carried
out shall be got approved by the Architects.
227
9. Supervision by Contractor
The Contractor shall give all necessary personal superintendence during the execution of the
works, and as long thereafter, as the Architects may consider necessary until the expiration of the
"Defects Liability Period", stated in the Appendix hereto, and this shall include due and proper
attention to all communications, oral or written and to all correspondence in a business like and
serious manner. All claims and other submissions etc. shall be supported by and based on
authentic and relevant facts only. The Contractor shall also during the whole time the works are in
progress, employ a competent and qualified supervisor preferable from conservation background
who shall be approved by the Architect and who shall be constantly in attendance at the works.
Any directions, explanations instructions, or notice given by the Architects to such
representative(s) shall be held to have been given to the Contractor.
CHAPTER - 20
If the Contractor fails to appoint and keep on the works a competent and qualified supervisor as
aforesaid the Architects shall have powers to suspend the works till such time a competent and
qualified representative as aforesaid is posted and the Contractor shall not be entitled to claim
extension of time and/or compensation on the plea of such suspension of the works.
The Architects may deduct at the rate of 15,000 / per month for the period a qualified
representative as aforesaid is not employed by the Contractor.
Aid for the expeditious execution of the works the Contractor shall be required to apply for a
temporary telephone connection .under C.Y.T. category and keep the same current for the
duration of the contract. All cost and charges in this connection will be borne by the Contractor. It
228
improvements or testing etc. pointed out by the Chief Technical Examiner should be carried out
by the Contractor at his cost and any deduction suggested by such C.T.E. will be effected from
any sums which may be due to which may become due to the Contractor. Contractor shall afford
all reasonable facilities to the above Vigilance staff and also provide them with ladders, tapes,
plumb, bob, level etc. as required and directed and also necessary labourers skilled, unskilled to
enable them to complete their inspection/study/technical scrutiny and no extra shall be admissible
to the contractor on this account.
the Architect, the Asstt. Engineer or the Architect's representatives, but such examination shall not
in any way exonerate the Contractor from the obligation to remedy any defects which may be
found to exist at any stage of the work or after the same is completed. Subject to the limitation of
this clause the contractor shall take instructions only from the Architects. The contractor must
provide to be available at site permanently such measuring tools, implements and instruments as
are necessary to execute and periodically examine the correctness of the works. A leveling
instrument and staff must be available at site through the currency of the contract, while other
instruments arranged promptly when needed at site. The Contractor is to provide and keep in good
repair one proper temporary office, with toilet complete with furniture, storage units, electric
lights, fans and cooler for the use of the Asstt. Engineer and clear the same away on completion of
the contract. The contractor shall also allow the said persons or the representatives of the
Architects/ Employer free use of the contractor‘s telephone at the site at all reasonable times in
connection with the work.
Provided that the Contractor shall be paid the charges for the cartage only of materials actually
and bonafide brought to the site of the work by the Contractor and rendered surplus as a result of
the abandonment or curtailment of the work or any portion thereof and then taken back by the
Contractor, provided however, that the Employer shall have in such cases the option of taking
over all or any such materials at their purchase price or at local current rates whichever may be
less.
b. Should the Contractor not attend or neglect or omit to send such agent then the
measurements, as taken by the Asstt. Engineer shall be taken to be correct measurements of
the works and the Contractor shall be legally bound by such measurements. Such
measurements shall be taken in accordance with the prescribed method of measurements.
The Contractor or his agent may at the time of measurement take such notes and
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
c. All extra works, omissions and variations made without the Architect's knowledge, if
subsequently sanctioned by him in writing (with the prior approval in writing of the
Employer), shall be included in such measurements but grouped separately at the end if so
required.
d. The measurements of all hidden and high rated items to be checked by senior officer such
as Superintending Engineer, Executive Engineers.
b. If the rates for the extra, altered or substituted (deviated) work are not provided for
(available) in the contract schedule, they shall to the extent possible be derived out of the
rates given in the schedule for similar or near similar items. For the purpose of such
derivation, where necessary and when so directed, the Contractor shall furnish detailed
analysis.
c. Where (a) and (b) are not applicable or where applicability of (ii) is rather too indirect or
inconsistent, the rates shall be arrived at using rates of items of work taken from J & K
schedule of rates (Latest/ LMR to be vetted By DIQC). Such rates from DSR shall be
increased or decreased by ratio representing:
Rate from Contract Schedule
Rate from J & K schedule of rates (Latest/ LMR to be vetted By DIQC)
of similar comparable items from the same trade as that of extra, altered, substituted work.
d. In respect of a contract which incorporates more than one schedule the rate applicable in case
(a) above if not provided for in the corresponding schedule pertaining to the work in which the
addition, alteration or substitution (deviation) occurs, shall be taken as the west applicable rate
in the other schedule; similarly, in case (b) above, if similar or near similar items cannot be
found in the corresponding schedule pertaining to the work in which the addition, alteration or
substitution (deviation) occurs, similar or near similar items of the lowest rate from the other
schedule shall be adopted.
e. In the case of additional, altered. or substituted (deviated) work for which rates cannot be
reasonably derived as at (a), (b) & (c) above, the rates shall be worked out adopting market
prices, substantiated by purchase bills / vouchers / dependable standard price lists, using
231
factors and constants for quantum of materials, labour, T& P and sundries from standard
P.W.D. data / Analysis adding 15% towards profits and overheads together. When called
upon to do so the Contractor shall submit to the Architects his purchase bills/vouchers or
such other satisfactory proof in support of the market rates.
f. The question as to what particular items, being similar or near similar to the additional,
altered or substituted (deviated) work in the contract schedule are to be adopted for
derivation of rates for the additional, altered or substituted (deviated) work and whether the
said rates cannot contract schedule will be decided by the Architect entirely at his
discretion which is not open to be questioned. Like wise the question of applicability of (b)
being indirect or inconsistent andof similar comparable items from the same trade or
otherwise will be decided by the Architect at his discretion which is not open to be
questioned.
CHAPTER - 20
g. In cases (b), (c), & (d) the Contractor is required to submit his analysis of rates adopting the
principles enunciated and the Architects after scrutinizing the analysis and other
information furnished, will allow such rates as he considers reasonable after obtaining
Employer's sanction.
h. Where extra work is of such nature that it cannot be properly measured or valued the
Contractor shall be allowed day work prices at the net rates stated in the tender or the
priced schedule of quantities or, if not so stated then, in accordance with the local day work
rates and wages for the district, provided that in either case if required by the Architects,
vouchers, muster rolls and other documents required for proper verification of the labour
employed and the materials deployed on the said work and the costs thereof be delivered to
Any defect, shrinkage, settlement or other faults which may appear within the 'Defects Liability
Period' stated in the Appendix hereto, or if none so stated, then within 12 to 36 months as per
232
Employer‘s direction after the completion of the works, arising in the opinion of the Architects
from materials or workmanship not being in accordance with the contract, shall on demand which
shall be made within the defects liability period, in writing by the Architects and within such
reasonable time as shall be stated therein specifying the work, materials or articles complained of
notwithstanding that the same may have been passed or/and certified, paid for, be amended and
made good by the Contractor, at his own proper charge and cost and in case of default the
Employer may employ other person or persons to amend and make good such defects, shrinkage,
settlements or other faults, and all damages, loss and expenses shall upon the Architect's
certificate in writing, be recoverable from him by the Employer or may be deducted by the
Employer from any money due or that may become due to the Contractor or the Employer may in
lieu of such amending and making good by the Contractor deduct from any money due or that
may become due to the Contractor a sum to be determined by the Architect equivalent to the cost
of amending and making good such work and in the event of the amount retained under clause 35
being insufficient recover the balance from the contractor together with any expenses the
Employer may have incurred in connection therewith. Should any defective work have been done
or material supplied by any sub-contractor employed on the works who has been nominated or
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
approved by the Architect as provided in clause 13 and 23 the contractor shall be liable to make
good in the same manner as if such work or material had been done .or supplied by the Contractor
himself and been subject to the provisions of clause 2 hereof. The contractor shall remain liable
under the provisions of this clause notwithstanding the signing by the Architect of any certificate
or the passing of any accounts.
22. Completion Certificate
The works shall not be considered as completed until the Architect has certified in writing that
they have been so completed and the defects Liability Period shall commence from such certified
date of completion of work. Within ten days of the completion of the work, the contractor shall
give notice of such completion to the Architect and within ten days of the receipt of such notice
the Architect shall inspect the work and if there is no defect in the work, shall furnish the
Contractor with a certificate of completion, otherwise a provisional certificate of completion
indicating defects (a) to be rectified by the Contractor and/or (b) for which payment will be made
at reduced rates, shall be issued. No certificate of completion, provisional or otherwise shall be
issued nor shall the work be considered to be completed until the Contractor shall have removed
from the premises on which the work was executed, all scaffolding, surplus materials, rubbish and
all huts and sanitary arrangements required, for his/their work people on the site in connection
with the execution of the works and as shall have been erected or constructed by the Contractor(s)
and cleaned off the dirt from all wood work, doors, windows, walls, floors or other parts of any
building, in upon or about which the work, was executed, or of which he may have had
possession for the purpose of the execution thereof, and not until, the work shall have been
measured by the Architects. If the Contractor shall fail to comply with the requirements of this
clause as to removal of scaffolding, surplus materials and rubbish and all huts and sanitary
arrangements as aforesaid and cleaning off dirt on or before the date fixed for the completion of
the work, original or extended in terms of clause 30 herein, the Employer after issuing due notice,
may at the expense of the Contractor remove such scaffolding, surplus materials and rubbish etc.
and dispose of the same as he think fit and clean off such dirt as aforesaid and the Contractor shall
have no claim in respect of any such scaffolding or surplus material as aforesaid except for any
sum actually realized by the sale thereof. And the expense, if any, so incurred may be recovered
from any money due or that may become due to the Contractor by the Employer. If several sub-
works covered by separate schedules are included in the contract, and if at any time before the
completion of the entire work, the Employer takes possession of any of the separate sub works
that may have been duly completed in accordance with the contract and so certified by the
Architects, notwithstanding any other provision in this contract in this regard, a completion
certificate may be issued in respect of that sub-work subject to the provisions in the previous sub-
clauses (regarding completion certificate), having been complied with in respect of the said duly
completed work, the defects liability period for such sub work may be reckoned from the separate
date of completion so certified and that part of the full security deposit as may be proportionate
(contract value of this sub work to the whole contract value) be attributed to this sub work may be
refunded in accordance with and subject to
233
the provisions of clause 21 . The same principles will apply where different dates are specified in
the contract for different sub works.
23. Specialists
All specialists, merchants, tradesmen and other executing any work or supplying and fixing any
goods for which prime cost prices or provisional sums are included in the schedule of quantities
and/or specification who may be nominated or selected by the Architects shall be deemed to be
sub- contractors employed by the Contractor and are herein referred to as nominated sub-
contractors. The co-ordination between various specialist agencies shall be ensured by the
Contractor who should keep them supplied with a copy of each of the memorandum of work
/ programme chart, or the part concerning and its amendment if and when made, and of the
probable dates their presence is required in such manner so that the progress of the project is
not affected adversely and is obtained consistently. No nominated sub-contractors shall be
employed on or in connection with the works against whom the Contractor shall make
reasonable objection or (save where the Architect and Contractor shall otherwise agree) who will
CHAPTER - 20
not enter into a contract providing :
a. That the nominated sub-contractor shall indemnify the Contractor against the same
obligations in respect of the sub-contract as the Contractor is under in respect of this contract.
That the nominated sub-contractor shall indemnify the Contractor against claims in respect of any
negligence by the sub- contractor, his servants or agents or any misuse by him or them of
scaffolding or other plant, the property of the Contractor or under any workman's compensation
act in force.
b. Payment shall be made to the nominated sub-contractor within fourteen days of his receipt of
the Architect's certificate provided that before any certificate is issued the Contractor shall upon
234
which may arise in respect of the works or in consequence thereof and shall at his own expense
arrange to effect and maintain, until the completion of the contract, with an approved insurer a
policy of insurance in the joint names of the Employer and Contractor against such risk and
deposit such policy or policies with the Architect from time to time during the currency of this
contract. The Contractor shall also similarly indemnify the Employer against all claims which
may be upon the Employer whether under the Workmen's compensation Act, or any other statute
in force during the currency of this contract or at common law in respect of any employee of the
Contractor or subcontractor and shall, at his own expense, effect and maintain until the virtual
completion of the contract, with an approved insurer a policy of insurance in the joint names of
the Employer and the Contractor against such risks and deposit such policy or policies with the
Architects from time to time during the currency of the contract. The Contractor shall be
responsible for anything which may be excluded from the insurance Policies above referred to
and also for all other damages to any property arising out of and incidental to the negligent or
defective carrying out of this contract. He shall also indemnify the Employer in respect of any
cost, charges or expenses arising out of claims or proceedings and also in respect of award of or
compensation for damage arising there from. The Employer with the 'concurrence of the Architect
shall be at liberty and is hereby empowered to deduct the amount of any damage, compensation,
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
costs, charges and expenses arising or occurring from or in respect of any such claims or damage
from any or all sums due or to become due to the Contractor.
235
delay) on or before the "Date of completion" stated in the Appendix subject nevertheless to the
provision for extension of time hereinafter.
CHAPTER - 20
failing to complete the works on or before the date specified in the Appendix as "date of completion"
or such extended date under clause 30 he shall be liable to pay as compensation an amount stated in
the Appendix as "liquidated damages" for every day that the work remains incomplete beyond the
"date of completion" or extended date. as the case may be, provided always that the entire amount of
compensation to be paid under the provisions of this clause shall not exceed five percent of the
contracted amount.
a. that the Contractor shall have no claim other than extension of time for the delay in completion
of the work due to such hindrance
b. that the Contractor shall suspend the works whenever called upon to do so in writing by the
Architects and shall be allowed reasonable extension of time for completion of work due to such
suspension of work and nothing else.
c. that the Contractor's application for extension of time is open to be rejected if it is not submitted
within 15 days of the date of hindrance
d. The Architect shall, in granting extension, specify separately the period which shall not qualify
for application of PVA.
236
winding up made against it or pass an effective resolution for winding up voluntarily or subject
to the supervision of the court and of official assignee or the Liquidator in such of insolvency or
winding up, as the case may be, shall be unable within seven days after notice to him requiring
him to do so, to show to the reasonable satisfaction of the Architects that he is able to carry out
and fulfill the contract and to give security there for if so required by the Architects.
Or if the Contractor (whether an individual, firm or incorporated Company) shall suffer
execution to be issued,
Or shall suffer any payment under this contract to be attached by or on behalf of any of the
creditors of the contractor; or shall assign or sublet this contract without the consent in writing of
the Employer first obtained;
Or shall charge or encumber this contract or any payments due which may become due to the
Contractor there under;
Or if the Architect shall certify in writing to the Employer that the Contractor:
a. has abandoned the contract or has failed to commence the works, or
b. has failed to commence the work, or has without any lawful excuse under these conditions
suspended the progress of the works for 14 days after receiving the Architects' notice to proceed,
or
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
c. has failed to proceed with the works with such due diligence and failed to make such due
progress as would enable the works to be completed within the time agreed upon, or
d. has failed to remove the materials from the site or to pull down and replace work for seven days
after receipt from the Architect of written notice that the said materials or work were condemned
and rejected by the Architect under these conditions or
e. has neglected or failed persistently to observe and perform all or any of the acts, matters or things
by this contract to be observed and performed by the Contractor for seven days after written
notice shall have been given to the contractor requiring the Contractor to observe or perform the
same, or has to the detriment of good workmanship, or without the consent in writing of the
Employer sublet any part of the contract, or
f. has violated any conditions of contract.
Then and in any of the said cases the Employer may notwithstanding any previous waiver, after
giving seven I days' notice in writing to the Contractor, determine the contract, but without
thereby affecting the powers of the Architects or the obligations and liabilities of the Contractor
the whole of which shall continue in force as fully as if the contract had not been so determined
and as if the works subsequently executed had been executed by or on behalf of the Contractor.
And further, the Employer by his Agents or servants may I enter upon and take possession of the
works and all plant, tools, scaffoldings, sheds, machinery, steam or other power utensils and
materials lying upon the premises or the adjoining lands or roads and use the same as his own
property or may employ the same by means of his own servants and workmen in carrying on and
completing the works or by employing any other Contractor shall not in any way interrupt or do
any act, matter or thing to prevent or hinder such other contractor or other person or persons
employed for completing and finishing or using the materials and plant for the works. When the
work shall be completed or as soon thereafter as convenient the Architect shall give notice in
writing to the Contractor to remove his surplus materials and plant, and should the Contractor fail
to do so within a period of 14 days after receipt thereof by him, the Employer shall be entitled to
sell the same by public auction and give credit to the Contractor for the amount realized.
The Contractor's account shall also be credited with the amount that would have been payable to
him, for the uncompleted work (completed by the Employer through other contractor or person or
persons as aforesaid) in terms of his agreement as if the contract had not been determined and he
(the Contractor) had continued to execute the work to its completion. The actual gross expense to
the Employer including incidental charges in completing the uncompleted work through other
contractor or person or persons shall be debited to the Contractor's account if it be not less than
the credit for the uncompleted work as above referred. If however, the said debit to be made be
less than the said credit, then the amount to be debited shall be equal to the value of the credit
given as above referred. The Architect shall thereafter ascertain and certify in writing what if
237
anything in the final accounting is due to or payable to the Contractor by the Employer or to the
Employer by the Contractor taking into account the credit (if any), to the Contractor for the sale
of the surplus materials and plant and the loss the Employer shall have been put to in procuring
the works to be completed. The amount, if any, owing to the Contractor and which shall be
certified shall there upon be paid by the Employer to the Contractor and vice versa, and the
certificate of the Architect in this regard shall be final and conclusive between the parties.
CHAPTER - 20
pass an effective Resolution for winding up either compulsorily or subject to the supervision of
the court or voluntarily,
Or if the official Assignee or the Employer shall repudiate the contract,
Or if the Official Assignee or the Liquidator in any such winding up shall be unable within
fifteen days after notice to him requiring him to do so to show to the reasonable satisfaction of
the Architect that he is able to carry out and fulfill the contract and to make all payments due,
and to become due there under , and if required by the Architect to give security for the same,
Or if the works be stopped for six months under the order of the Architect or the Employer or by
any injunction or other order, of any Court of law, then and in any of the said cases the
Contractor shall be at liberty to determine the contract by notice in writing to the Employer
b. All goods or work for which prime cost prices or provisional sums of money are provided
may be selected or ordered from any manufacturers or firms by the Architects in consultation
with the Employer who reserves to himself the right of paying direct for any such goods or work
and deducting the said prices' or" sums from the amount of contract. Should any goods or work,
for which prime cost prices or provisional sums are provided or portions of the same be not
required, such prices or sums, together with the profits allowed for the same and such additional
amounts as the Contractor may have allowed for carriage and fixing will be deducted in full
from the amount of the contract. Whether the goods be ordered by the Contractor or otherwise,
the Contractor shall receive and sign for such goods and be responsible for their safe custody as
and from the date of their delivery upon the works, and for such payment in the contract.
shall fix the same, if called upon to do so, at his own cost. Fixing shall cover unloading, getting
in, unpacking and return of empty and other incidental work.
c. In cases in which provisional quantities of material are contained in the contract the
Contractor
238
shall provide such material to such amounts or to greater or less amounts as the Architect shall
direct in writing at the net rates at which he shall have priced such items in the schedule of
quantities; should however any such items be entirely omitted, which omissions shall be at the
Architect's discretion, no profit on such items shall be allowed to the Contractor.
d. No prime cost sum or sums (or any portion thereof) shall be included in any certificate for
payment to the Contractor until the receipted accounts relating to them have been produced by
the Contractor to the Architect. Such account shall show all discounts and sum or sums in
respect of such discounts shall be treated as a trade discount provided always that should the
Contractor in lieu of producing such receipted accounts request the Architect in writing to issue a
certificate on the .Employer for such sum or sums due either on account in settlement to a sub-
contractor direct, the Architect shall upon satisfying himself that the sub-contractor is entitled to
the same, so issue the certificate, and such sum or sums shall be deducted from the amount of the
contract at the settlement of accounts and any profit or further sums which the Contractor is
properly entitled in respect of such sub-contract, and which is in conformity with the terms of the
contract, shall be allowed to the Contractor at the settlement of accounts as though the amount of
such certificate to the sub-contractor had been included in a certificate drawn in favor of the
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Contractor.
e. If the Contractor neither produces the receipt nor gives authority to the Architect to issue a
certificate in favor of such sub-contractor direct, the Architect may, upon giving the Contractor
seven days‘ notice in writing of his intention to do so, issue to the subcontractor such certificate
direct on the Employer and obtain the receipt from the sub-contractor, which receipt shall be
deemed as discharge for the amount of such certificate as though given by the Contractor. In the
event of such default on the part of the Contractor, he shall not be allowed any profit he may
have added in the schedule of rates upon such sub contract.
f. The exercise of the option before referred to by the Contractor and the issue of certificates
before described to sub-contractor upon the Contractor's request or the issue to the sub-
contractor direct of the certificates by the Architect shall not however, relieve the Contractor
from any of the liabilities in respect of insufficient, faulty or incomplete work of the sub-
contractor for which he may be liable under the terms of the contract.
g. If any provisional items are provided for work of a nature usually carried out by the Contractor
in the ordinary course of his business the Employer shall give the Contractor an opportunity for
tendering for the same without prejudice to the Employer's right to accept any or reject any or all
of the tenders received.
239
a. The Architect may in his discretion certify on general assessment about 80% of the claim
immediately on receipt of an interim bill verified by the Assistant Engineer prior to
checking/taking measurements and issue the relevant certificate for the balance after duly
'checking / taking measurements as aforesaid.
b. The Architect may at his discretion include in the interim certificate such amount as he may
consider proper on account of any materials which are in his opinion nonperishable and are in
accordance with the contract and which have been brought on the site in connection therewith and
are adequately stored and/or protected against damage by weather or other causes but which have
not at the time of advance been incorporated in the work 80% of their purchase value on
production of vouchers for the same. When materials on account of which such advance has been
made under this sub-clause are incorporated in the work the amount of the advance shall be
deducted from the next payment to be made under any of the clauses of this contract.
c. And when the works have been completed and the Architect shall have certified in writing that
they have been so completed the contractor shall submit the final bill in respect of the contract
works within one month thereafter. In accordance with the certificate to be issued by the Architect
CHAPTER - 20
a payment shall be made by the Employer as named in the Appendix ―Installment after virtual
completion". And the Contractor shall be entitled to the payment of the final balance in
accordance with the final certificate to be issued in writing by the Architect after the expiration of
the he period referred to as "the Defects Liability Period" in the Appendix hereto from the date of
completion or as soon after the expiration of such period as the works shall have been finally
completed and all defects made good according to the true intent and meaning thereof whichever
shall last happen. Provided always that the issue by the Architect of any certificate during the
progress of the works or at or after their completion shall not relieve the Contractor from his
liabilities under clause 2 and 21 nor relieve the Contractor of his liability in case of fraud,
dishonesty, or fraudulent concealment relating to the works or materials or to any matter dealt
240
of the letter by Employer /Architect or when delivered by hand immediately after receipt thereof
by the contractor(s), whichever is earlier. Further, a letter signed by the officials of
Employer/Architect that the letter was so posted to the contractor(s) shall be conclusive.
will send within thirty days of receipt by him of the written notice aforesaid to the contractor a
panel of three names of persons who shall be presently unconnected with the organization for
which the work is executed, and they should be either a fellow of the Institute of Engineer's
(India) or fellow of Indian Institute of Architects
c. The Contractor shall on receipt by him of the names as aforesaid select anyone of the persons
named to be appointed as a sole arbitrator and communicate his name to the Appointing
Authority shall thereupon without any delay appoint the said person as the sole arbitrator. If the
Contractor fails to communicate such selection as provided above within the period specified,
the Appointing Authority shall make the selection and appoint such selected person as the sole
arbitrator.
d. If the Appointing Authority fails to send to the Contractor the panel of three names as
aforesaid within the period specified, 'the Contractor shall send to the Appointing Authority a
panel of I three names of persons who shall be unconnected with either party. The Appointing
Authority shall on receipt by him of the names I as aforesaid select anyone of the persons named
and appoint him as the sole arbitrator within 30 days of receipt by him of the panel and inform
the Contractor accordingly. If the Appointing Authority fails to communicate such selection as
provided herein within the period specified the Contractor shall be entitled to appoint one of the
person from the panel as the sole arbitrator and communicate his name to the Appointing
Authority.
e. If the Arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates
his office due to any reason what so ever another sole arbitrator shall be appointed as aforesaid.
f. The work under the contract, shall however, continue during the arbitration proceedings and no
payment due or payable to the Contractor shall be withheld on account of such proceedings.
g. The Arbitrator shall be deemed to have entered on the reference on the date he issues notice to
both the parties fixing the date of the first hearing.
h. The Arbitrator may from time to time, with the consent of the parties, enlarge the time for
making and publishing the award.
i. The Arbitrator shall give a separate award in respect of each dispute or difference referred to
him. The Arbitrator shall decide such dispute in accordance .with the terms of the contract and
give a reasoned award.
j. The fees, if any, of the Arbitrator shall, if required to be paid before the award is made and
published, be paid half and half by each of the parties. The costs of the reference and of the
award including the fees, if any, of the Arbitrator who may direct to and by whom and in what
manner, such costs or any part thereof shall be paid and may fix or settle the amount of cost to be
so paid.
k. The award of the Arbitrator shall be final and binding on both the parties.
l. Subject to aforesaid the provisions of the Arbitration and Conciliation Act, 1996 or any
statutory modification or reenactment thereof and the rules made there under, and for the time
being in force, shall apply to the arbitration proceeding under this clause.
m. The venue for Arbitration shall be New Delhi unless otherwise directed by the Arbitrator under
241
compelling circumstances (e.g. a hearing at site for physical inspection / verification).
CHAPTER - 20
compensation so paid, and without prejudice, to the rights of the Employer under subsection (2) of
section 12 of the said Act, the Employer will be at liberty to recover such amount or any part
thereof by deducting it from the security deposit or from any sum due by the Employer to the
Contractor under this contract or otherwise. The Employer shall not be bound to contest any claim
made against him under sub section (1) of section 12 of the said Act, except on the written request
of the Contractor and upon his giving to the Employer full security for all costs for which the
Employer might become liable in consequence of contesting such claim.
242
42. Apprentices Act
The Contractor shall comply with provisions of the Apprentice Act,1961, and the Rules and
orders issued there under from time to time. Failure to do so will amount to a breach of contract
and the Employer may in his discretion terminate the contract. The Contractor shall also be
liable for any
44 . Use of materials
Contractor is required to use materials as described in the specifications and approved by the
conservation architect.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
45 Site Drainage
All water which may accumulate on the site during the progress of the works, or in trenches and
excavations, from other than the excepted risks (as defined in this contract) shall be removed
from the site to the satisfaction of the Architect by the Contractor at his own expense.
46. Nuisance
The Contractor shall not at any time, do, cause or permit any nuisance on the site or do anything
which shall cause unnecessary disturbance or inconvenience to owners, tenants or occupiers of
other properties near the site and to the public generally.
243
51. Suspension of Works
If the Contractor, except on account of any legal restraint upon the employer preventing the
contingency of the works, or on account of any of the causes mentioned in the clause 'Extension
of Time' or in the case of a certificate being withheld or not paid when due, shall suspend works
or if the opinion of the Architects, shall neglect or fail to proceed with due diligence in the
performance of his part of the Contract of if he shall more then once make default in the
respects mentioned in clause 20 (removal of improper work and materials), the Employer
through the Architect shall have the power to give notice in writing to the Contractor requiring
that the works be proceeded within a reasonable manner, and with reasonable dispatch such
notice shall not be unreasonably given and must signify that it purports to be a notice under the
provisions of this clause and must specify the acts or defaults on the part of the Contractor upon
244
.
shall be applied/adopted). Subject to other conditions being satisfied it shall be open to the
Architect to consider certification of a bill which is dominantly for materials at site only.
245
7. Referencing appendix
Appendix 1
Clause No.
CHAPTER - 20
Date of completion i.e months from the above date
Installment after virtual completion 50% of the Total Security Deposit will be
released along/ with the final certificate
of payment and the certified balance after
Defects Liability Period (after due
adjustments, if any).
Period for honoring Interim Certificates Ten working days from the date of receipt
of the certified bill from the Architect.
Period for Honoring Final Certificate 12 weeks from the date of receipt of the
Appointing Authority
Signature of the Bidder
246
Appendix 2
Drawings
The following drawings are available for inspection at the office of the Architects as stated
hereinbefore and the tenderers are deemed to have studied the same. This set of drawings will
form a part of the formal agreement.
=====================================================================
SL. Type Drawing No. Total No.
=====================================================================
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
247
Proforma 1
CONTRACTOR‘S LIABILITY AND INSURANCE: SUMMARY
CHAPTER - 20
a. Loss or damage to works or any part thereof and all materials at site from any cause whatsoever
b. b
b. Damage loss or injury to any property of the Employer or consultant to any person including the
Employer or Consultant his Agent and servants.
c. Claims under the workmen‘s Compensation Act 1933, the Minimum Wages Act 1948 and the
contract 1 above (Regulation and Abolition Act 1970)
………………………… ……………….
………………………… ……………….
Witness:
……………………
……………………
……………………
248
Proforma 2
Deviated Items
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Extra Items
Deleted Item (-)
Net Excess Savings
Tender amount
249
Proforma 3
Name of
Work
Interim Bill No
CHAPTER - 20
Deviated Items
(Pink Sheets)
Extra Items
(Yellow
Sheets)
Net Excess/Saving
250
Proforma 4
Contractor liability
==================================================================
a)
b)
c)
===================================================================
Damage loss or injury Claim under the workman Remarks
to any property of compensation Act 1923
Employer/Consultant The minimum Wages Act
or his Agents and 1948 & Contract Labour
Servants Regulation & Abolition
Act 1970
====================================================================
5 6 7
NB: Details o further policies if any taken and the loss or damage if any under that policy may please be indicated
separately at appropriated places.
Signature of Contractor
Address………………..
…………………..
Witness………………………….
251
Proforma 5
Draft for letter to be written by the Contractor to the Consultant in connection with the Virtual
Completion
Having executed the work in terms of the Contract, we hereby certify and affirm that we have virtually
completed the contracted works.
CHAPTER - 20
We hereby certify that the works has been executed wholly to our satisfaction and with the materials
and workmanship in accordance with the contract between us. We do certify further that we have
executed the work in accordance with the applicable laws and without any transgression of such laws.
Signature of Contractor
Address…………………………….
252
Proforma 6
Certificate of insurance policy
This is to certify that the work for which this bill is resented was executed only after obtaining
the necessary insurance policies in accordance with obligation under this contract and during the
execution of such work, the Insurance Policy was current and valid as detailed below:
Compensation
Act
1 2 3 4 5
Policy No. -
Value in Rs. -
Date of issue -
Date of Expiry -
253
Proforma 7
BANK GUARANTEE
- 20
In the consideration of PWD , (hereinafter referred
MANUAL-2020
as Employer ) having agreed to exempt M/S___a company registered under the , having its registered
office at (hereinafter called the said Contractor) from the
PWD ENGINEERINGCHAPTER
demand, under the terms and conditions of the Agreement dated made between
Employer and the Contractor (hereinafter as the said Agreement) from the security deposit for the due
fulfillment of the said Contractor of the terms & conditions contained in the said Agreement on production
of a Bank Guarantee for Rs.----------------(Rupees ), we constituted under the
Banking Companies (Acquisition & Transfer of Undertaking Act 1970) having its Head Office at------------
--and one of its branches at (hereinafter referred to as ―the Bank") at the request of M/S (contractor)
do hereby undertake to pay to Employer an amount not exceeding Rs.-------- (Rupees ) against any loss or
damage caused to or suffered or would be caused to or suffered by the Employer by reason of any breach
by the said Contractor of any terms & conditions contained in the said Agreement.
We ---------------------------------------------------------- further undertake and agree that the Employer shall have
the full liberty without our consent and without effecting in any manner our obligations hereunder to vary
in all the terms and conditions of the said Agreement of to extend time of performance by the said
contractor from time to time, or to postpone for any time or, from time to time, any of the powers
exercisable by the Employer against the Contractor and to forebear or enforce any of the terms and
254
conditions relating to the, said Agreement and we shall not be relieved from our liabilities by reason or any
such variation or extension being granted to the said Contractor or for any forbearance, act of omission on
the part of the Employer or any indulgence by Employer to the said Contractor by any such matter or thing
whatsoever under the law relating to sureties would, but for this provision have effect of so relieving us.
This guarantee shall remain valid and in full force till------------- and if no demand or claim under this
guarantee is made on us in writing on or before ------------- we shall be discharged from all liabilities under
the guarantee. Our liabilities under this guarantee are restricted to Rs.---------------------------------- Rupees--
----------------) we further undertake to renew this guarantee on the receipt of call from Employer without
any reference to the Contractor. Our liabilities to renew the guarantee shall be absolute.
This guarantee shall not be discharged due to the change in the constitution of Employer, or the
Contractor We----------------------------------------------------------------lastly, undertake not to revoke this
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
guarantee during its currency except with the previous consent of Employer in writing.
Place:
Signature
Dated : day of
255
Proforma 8
BANK GUARANTEE
(On non-Judicial stamp paper of appropriate value (For Mobilization Advance)
In consideration of the Employer which expression shall unless repugnant to the subject or
context include its successors and assigns) having agreed under the terms and conditions of
contract vide its agreement dated --- made between ---------------------------------------- and the
Employer in connection with the ― conservation of --------------------------------------------- (Heritage
Site)‖ (hereinafter called the 'contract' which expression shall, wherever the context so requires
include its successors and assignee).
Whereas one of the conditions of the contract places on the contractor is that the owner should
make a payment of Rs ------ (Rupees _____) being ( )
Place
Signature
Dated day of
256
8. Specifications
I. General Specifications
Without forgoing the requirements of the conditions of Tender and the Conditions of Contract the
works in general shall conform to the "CPWD Specifications-" published by PWD, J & K and the
"Specifications for works" stated in this tender. In case items not covered by the general specifications
referred above, reference shall be made to the appropriate I.S. Code. If there is any difference in the
particular specifications of individual item of work and the description of item as given in the Schedule
of quantity, the latter shall prevail. In case of any work for which there is no specification in I.S.
specifications or in the specifications forming part of tender documents or in case there is any variation,
such work shall be carried out in all respects in accordance with the instructions to be issued by the
Architects. The term engineer-in-charge appearing in the specifications shall mean the Arch. or his
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
authorized representative as the context may demand consistent with the conditions and other
stipulations of this contract. The term Department shall mean the Employer. Any reference to ISI shall
also mean reference to its successor Bureau of Indian Standards. All corrections to "Specifications-" or
latest revisions of I.S. shall be deemed to apply to this contract.
Materials bearing ISI certification mark shall be given highest preference for use in the works.
Where the Contractor is required to do, perform, execute (etc.) any work or service or the like it shall
be deemed to be at his own cost. Absence of terms providing, Supplying, installing, fixing, etc. shall
not even remotely entitle the Contractor to any additional payment therefor. The rates accepted in
the Schedule of Quantities apply to all floors, heights, depths, leads lifts, spans, sizes, shapes,
locations, etc. unless a distinction has been included in the very Schedule.
The Specifications and the Schedules may have been divided into various sub-heads for convenience
only. This does not limit applicability of one to the other nor does it absolve the Contractor of his
responsibility to complete any trade/item of work as reasonably inferred from one or more of such sub-
heads.
All work under this contract is deemed to be performed above subsoil water level. However,
removalof water collected from rains and the like shall be treated as part of contractual risk /
obligation. Screws, bolts, nuts, washers, hold fasts, lugs, anchors, clamps, plugs, suspenders, brackets,
straps and fasteners of the like are deemed to be included in the rates of various items unless the
Schedule of Quantities expressed a different intention. Resetting any displacements, making good
holes/chases and such other incidental jobs are included in rates of respective items for which these are
required
Material specifications‘
257
a) Testing the type of lime while buying
Slaking of quick lime is the best way to analyze the lump lime (quick lime) before buying.
Firstly, fill a litre (quart) measure with the burnt quicklime lumps available in the market or
local resources. Take small lumps of quicklime into an open container and filled it filled with
fresh clean water so that the quicklime is fully covered. Hold it in position below the water for
few minutes only and observes the reaction very carefully it gives all required information while
reacting with water.
Pure lime or fat lime -The lime hisses, swells rapidly, decrepitates, increases in temperature
sufficiently to produce water vapor, and turns to powder almost immediately or within a few
CHAPTER - 20
minutes. Volume is at least doubled by slaking.
Slightly hydraulic lime - The lime is inactive for a longer period than for fat lime, up to quarter
of an hour before there is any change. This will tend to be the slow opening up of cracks with
little or no falling to powder. A small amount of vapor may be seen, but considerably less and
cooler than for pure lime.
Moderately hydraulic lime -Similar to slightly hydraulic lime, but the change of state does not
commence for at least an hour or more after immersion.
Eminently hydraulic lime -An alteration in the state of the lime is barely noticeable, increase in
temperature is slight and cracks formed are very small and in some cases do not appear at all.
b) Testing of well burnt lime
258
.
a) Sand
Sand particles plays an important role in the bonding .It is always preferred to use sharp and
angular sand for preparing lime mortar which provides good bonding of these crystals. Round
sand particles have tendency to slip one another so it does not produce workable lime mortar.
Sand shall be clean and gritty and from approved sources of fine sand and course sand. It shall
be well graded, and shall be free from salt, loam dust or other impurities. It shall be washed with
fresh water on site if so directed by the architect. The fine aggregates used shall confirm of IS:
383 f or grading, strength and all other impurities. Where required by the Architect, the fine
aggregated shall be subjected to the following tests in accordance with the procedures specified
in IS: 383.
b) Course aggregates
The course aggregates used shall be clear, hard washed and screened gravel of crushed stone
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
having a specific gravity of not less than 2.56 and shall be free from dust, fine materials, clay of
loam and soft or elongated particles. The course aggregate used shall conform of the IS: 369 for
grading, strength and other properties. Where required by the Architect, the course aggregates
shall be subjected to the following tests in, accordance with the procedure specified in IS: 383.
259
.
Brick for lakhori masonry repair works- Same size and color of bricks should be preferred for
the masonry repair works. If old bricks are not decayed, they should be reused. If old bricks
easily available from other resources, they can be used for such kind of repair works.
H) Timber
Timber is to be of the best of its kind, properly seasoned, of mature growth, free from worm
holes, saps, wraps, cracks and other defects. In general wood means best available wood of J &
K su ch as for Deodar wood to be used or the kind of wood already used in the historical
building. All woodwork shall be planned neatly and truly finished to the exact dimensions. All
joints shall be neat and strong truly and accurately fitted and glued before being fitted together.
CHAPTER - 20
I) Reuse of old material
As this is a specialized work of restoration the work will also entail reuse of historic material
were ever possible. After removal or demolishing or areas all serviceable material needs to be
staked safely and all non serviceable material may be disposed, only after the approval of the
consultant. Contractor will make efforts in preserving the authenticity of the building. Material
taken out of the building will be first checked for their possibility of reuse after proper treatment
& repairs. The decision of the consultant in this regard will be final. When dismantling stone
masonry, pre-cast or wooden / steel members previous to re building, it may be necessary to
mark or number the old items so that it could be replaced to its original position more readily. In
260
III) Tools for conservation
Racking and repointing tools, plastering tools, measuring tools, ramming tools should be
made as per the site specific conditions and as directed by the conservation architect. For curing
of lime work only specified water spray pump should be used.
character of a heritage resource is based on the assumptions that the historic materials and
features and their unique craftsmanship are of primary importance and that in consequence, they
are to be retained, and restored to the greatest extent possible, not removed and replaced with
materials and features which appear to be historic, but which are in fact new.
Conservation should be carried out in accordance with a conservation plan, which brings
together all of the information and research necessary to guide the proposed action; ensure that
what is to be conserved is properly recorded before, during and after work; make provision for
recording where continued preservation is no longer possible or where loss is taking Place
through change or ongoing decay, and ensure that all records are retained in readily accessible
archives;
Conservation should include effective arrangements for monitoring the condition and
safety of the site and for routine maintenance and good housekeeping.
CHAPTER - 20
material is inappropriate covering original building material with a new material is inappropriate
and shall not be approved. Stucco should not be applied to existing heritage properties where
other original materials survive. When feasible remove later covering materials such as cement
plastering, inappropriate painting etc that obscures the original building material and have not
achieved historic significance. After removal of the outer layer, original layer should be repaired
as required. Painting brick masonry/ stone masonry/ historic decorative works is inappropriate.
It changes the character of a building and may deteriorate the original material as well as affect
the sense of visual continuity among other masonry structures in the area. Repair deteriorated
primary building material in a manner that maintains its heritage character. Modern consolidant
such as Epoxies and resins should not be used for any type of consolidation work. Use the
262
20.6.4 Consultancy Services
Consultancy services involve providing expert or strategic advice for project related
consultancy services which include feasibility studies, project management, engineering
services, training and development etc.
Engagement of consultants may be resorted in situations requiring high quality services for
which the procuring entity does not have requisite expertise. Approval of competent authority
should be obtained before engaging of consultant(s).
CHAPTER - 20
In consultancy services:-
For details regarding consultancy may refer to manual for procurement of consultancy and
other services 2017 issued by Government of India Ministry of Finance, Department of
Expenditure.
CONSULTANCY SERVICE
(THROUGH E- PROCUREMENT MODE)
FOR CONSTRUCTION OF
263
OFFICE OF THE EXECUTIVE ENGINEER R&B Division
FRESH TENDER NOTICE
NIT No.
Dated:
Expression of interest (EOI) for Consultancy service (Through e-procurement mode)
(TWO COVER SYSTEM)
For and on behalf of the President of India, Executive Engineer, PWD (R&B) Division
invites Expression of Interest (EOI) for selection of consultant for Architectural and allied
Engineering Consultancy Services from Registered firms /Consultants/Agencies under Indian
Partnership Act/Societies Registration Act or registered companies under companies act or the
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
following work
Bid documents can be seen at an d downloaded from the website http://jktenders.gov.in. Bid
documents contain qualifying criteria for bidder, specifications, bill of quantities, Conditions and
other details.
Bids must be accompanied with cost of Tender document in shape of e-challan through Treasury
indicating Treasury Voucher No. & date and also indicating the name of work duly crediting to
0059-PWD (Revenue) uploading a copy of treasury challan /receipt. Earnest money/Bid security in
shape of CDR/FDR/ BG Pledged to the original instruments in respect of cost of documents, EMD
and relevant documents of L1 must be submitted to the Chief Engineer PW (R&B) Department -
before the issuance of allotment in favour of lowest bidder.
264
Financial Bids will be opened online in the office of the Chief Engineer PW (R&B) Department of
the technically responsive bidders.
The bid for the work shall remain open for acceptance for a period of 120 days from the date of
opening of bids. H any bidder/tenderer withdraws his bid/tender before the said period or makes any
modifications in the terms and conditions of the bid, the said earnest money shall stand forfeited.
Other details can be seen in the bidding documents. Instructions to bidders regarding e-tendering
process The interested bidder can download the NIT/bidding document from the website
http://jktenders.gov.in
To participate in bidding process, bidders have to get (DSC) "Digital Signature Certificate" as per
Information Technology Act-2000, to participate in online bidding. This certificate will be required
for digitally signing the bid. Bidders can get above mentioned digital certificate from any approved
vendors. The Bidders, who already possess valid (DSC) Digital Signature Certificates, need not to
procure new Digital Signature Certificate.
The bidders have to submit their bids online in electronic format with Digital Signature. The bids
cannot be uploaded without Digital Signature. No Proposal will be accepted in physical form. Bids
will be opened online as per time schedule mentioned above. Before submission of online bids,
bidders must ensure that scanned copies of all the necessary documents have been produced when
CHAPTER - 20
required. The department will not be responsible for delay in online submission of bids whatsoever
reasons maybe. All the required information for bid must be filled and submitted online. Bidders
should get ready with the original copies of cost of documents & EMD as specified in the tender
documents. The original instruments in respect of cost of Documents. EMD and relevant documents
of L1must be submitted to the Tender Opening Authority before the issuance of letter of allotment is
issued in favour of the lowest bidder.
The details of cost of documents, (copy of each challan) Copy of EMD instrument specified in the
tender documents should be Uploaded online (scanned copies) otherwise bid will not be accepted.
Bidders can contact the undersigned for any guidance for getting DSC or any other relevant details
in respect of e-tendering process.
Executive Engineer
PWD(R&B)______
Copy to the
265
1. INSTRUCTIONS TO BIDDER
Scope of Bid
The Executive Engineer as a representative of the President of India invites bids for the
Expression of Interest (as described in these documents and referred to as "the EOI'). The
name and identification number of the EOI is provided in the Appended NIT. The bidders may
submit bids for any or all of the EOI detailed in the table given in the Notice Inviting Tender.
Bid for each EOI should be submitted separately.
Throughout these documents the terms "bid" and "tender" and their derivatives (bidder/
tenderer, bid/tender, bidding/tendering etc.) are synonymous.
Q Qualification of the Bidder I Eligibility Criteria).
In order to qualify, all bidders must upload copies of documents as deined below:-
documents /Annexures to be uploaded
Annexure 1 -Copy of GSTIN registration and latest clearance certificate FORM GST - 3B
I.e. latest clearance certificate FORM GST- 3B of the preceding month to the issue of NIT.
For the NIT issued in month. the bidder has to upload the latest clearance certificate FORM
GST- 3B of the preceding month i.e. of
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
266
a). Made misleading or false representations in the forms, statements, affidavits duly attested
by magistrate and attachments submitted in proof of the qualification requirements: and/or
b). Record of poor performance such as abandoning the works, not properly completing the
contract inordinate delays in completion, litigation history, or financial failures etc.
One Bid per Bidder.
Each Bidder shall submit only one Bid for one work. A Bidder who submits more than one Bid
will cause the proposals with the Bidder's participation to be disqualified.
Cost of Bidding
The Bidder shall bear all costs associated with the preparation and submission of his Bid, and
the Employer will, in no case be responsible or liable for those costs.
Site Visit
The Bidder, at his own cost, responsibility and risk is encouraged to visit, examine and
CHAPTER - 20
familiarize himself with the site of works and its surroundings and obtain all information that
may be necessary for preparing the Bid and entering into a contract for construction of the
works. The costs of visiting the site shall be at the Bidder's own expense. He may contact the
Executive Engineer in-charge of work for any guidance relating to site visit.
BIDDING DOCUMENTS.
(TWO COVERSYSTEM)
Part I. This shall be named Technical Bid and shall comprise of Scanned copies mentioned it
serial No.2 Qualification of the bidder.
Part II. This shall be named Financial Bid and shall be uploaded in separate part in the financial
cover as .xls format in Electronic form which the bidder shall qote % age rate for the
complete job.
267
NOTE:- Disclosure of Financial bid in Technical bid part I shall render the bidder no
responsive.
Copy of EMD in the form of CDR/FDR/Demand Draft in favour of ______________________
All duties taxes, royalties and other levies payable by the contractor under the contract, or for any
other cause, shall be included in the rates (excluding the Goods and Services Tax), prices and
total Bid price submitted by the Bidder .and nothing extra what so ever shall be payable in this
regard to the bidder.
The rates and prices quoted by the Bidder shall be fixed for the duration of the contract and shall
not be subject to adjustment on any account.
Currencies of Bid and payment.
The unit rates and the prices shall be quoted by the bidder entirely in Indian Rupees. All
payments shall be made in India Rupees.
Bid Validity
Bids shall remain valid for period of submission 120 Days after the deadline date for bid
In exceptional circumstances, prior to expiry of the original time limit, the employer may request the
bidder to extend the period of validity for a specified additional period. The request and the bidder's
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
responses shall be made in writing. A bidder may refuse the request without forfeiting his earnest
money. A bidder agreeing to the request will not be required or permitted to modify his bid, but will
be required to extend the validity of his earnest money for a period of the extension, and in
compliance with clause 16 of ITB in all respects. Earnest Money. The bidder shall furnish, as part of
the Bid, earnest Money as mentioned in above NIT. Any bid not accompanied by an Earnest Money
shall be rejected by the Employer as non responsive.
The earnest money of unsuccessful bidders will be returned within 30 days of the end of the Bid
validity period. The earnest Money of the successful Bidder will be released after successful
completion of the work to be certified by the Engineer- in-charge
SUBMISSION OF BIDS
Submission of Bids: The Bidder must submit separately "Technical Bid" and "Financial Bid"
Technical Bid: to be opened on (As per Date Schedule) in the presence of Evaluation Committee.
Financial Bid: Shall be opened in case of qualified bidders Only thereafter.
DEADLINE FOR SUBMISSION OF BIDS
Complete Bids (including Technical and Financial) must be submitted online not later than the (As per
Date Schedule). The employer may extend the deadline for submission of bids by issuing an
amendment, in which case all rights and obligations of the Employer and the bidders previously
subject to the original deadline will then be subject to the new deadline. Process to be Confidential
Information relating to the examination, clarification, evaluation, and comparison of bids and
recommendations for the award of a contract shall not be disclosed to bidders or any other persons not
officially concerned with such process until the award to the successful Bidder has been announced.
Any attempt by a Bidder to influence the Employer's processing of bids or award decisions may result
in the rejection of his Bid.
19.0 . Clarification of Bids and Contacting the Employer
No Bidder shall contact the Employer or any matter relating to its bid from the time of the bid opening
to the time the contract is awarded.
Any attempt by the bidder to influence the Employer's bid evaluation, bid comparison or contract
award decision may result in the rejection of his bid.
Examination of Bids and Determination of Responsiveness During the detailed evaluation of
"Technical Bids", the Employer will determine whether each Bid
(a) meets the eligibility criteria defined in Qualification criteria and fulfils all other terms and conditions
of bidding documents and 2
(b) has been properly signed;
(c) is accompanied by the required securities; and
(d) is substantially responsive to the requirements of the bidding documents.
A subsequently responsive "Financial Bid" is one which conforms to all the terms, conditions, and
specifications of the bidding documents, without material deviation or reservation. A material
deviation or reservation is one
268
(a) which affects in any substantial way, inconsistent with the bidding documents, the employer's rights
or the Bidder's obligations under the Contract; or
(b) whose rectification would affect unfairly the competitive position of other bidders presenting
substantially responsive bids.
IF a "Financial Bid" is not substantially responsive it will be rejected by the employer,
and may not subsequently be made responsive by corrections or withdrawal of the nonconforming
deviation or reservation. PRICE PREFERENCE
There will be no price preference to any bidder. SCOPE OF WORK
The Firms/Consultant shall be required to provide service for:- Construction of
1.1 Taking clients instructions and preparation of drawings.
Preparation of site plan.
Site evaluation, analysis and impact of existing and I or proposed development on its immediate
CHAPTER - 20
environs.
1.4 Inspection, supervision and evaluation of works. Any other individual / specific requirements of the
project.
Preparation of concept and technical project report and preparation of tender documents on
BOQ basis.
1.7 Rendering of comprehensive Architectural Services including issuing good for construction
drawings and all other construction documents.
SCHEDULE OF SERVICES:
The Firms/Consultant shall after taking instructions from the client render the following
1. CONSTRUCTIONSTAGE
I. Prepare and issue working drawings and details for proper execution of works during
construction. The working drawings shall have to be submitted in hard & soft copies as per
requirement as directed by Engineer in-charge.
II. Inspect, supervise and evaluate the construction works during execution and wherever
necessary clarify any decision, offer interpretation of the drawings/specifications
2. COMPLETION STAGE
Prepare and submit 06 sets of as built drawings for structure in hard and soft copies.
269
4. FEES FOR THE WORK.
Fees payable for the assigned works shall be inclusive of all services like sanitary, plumbing,
electrification, sewerage line, landscaping and development of site etc. Complete job to the
satisfaction of the Engineer -in-charge.
5. For preparation of conceptual drawings scheduled fee shall be paid to the Firms /
Consultant.
Mere preparation of conceptual drawing & its approval from project authority shall not confer
any right on the Architect for claiming the allotment for entire work.
S
chedule of Payments
Stage 1 On submitting concept drawing & rough 10% of total fees payable
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
The Firm/ Consultant shall be required to visit site as & when required, however nothing extra
shall be paid for site visits.
270
Sr. Criteria Marks Maximum
No Marks
A. Average Annual Turnover for last 03 Financial
Years ending
0 t o 2 crores 5 20
2 to 5 crores 10
5 to 10crores 15
Above 10 crores 20
B Maximum size of Institutional/Office building
complex project handled in terms of built up
area within last five years. 20
above 1.00 lacs sft 5
CHAPTER - 20
1.0 lac to 3.00 lac sft 10
above 3.00 Lacs sq.ft 20
C Architectural firm with experience of
5 yrs or more 5
10 yrs or more 10 20
15 yrs or more 15
20 yrs or more 20
D Team members on permanent pay roll of the
organization.
Architect (with more than 3 yrs exp) 2
TOTAL 100
Only the financial bids of top three scores of technically responsive bidders will be opened o
online.
Illustration
A,B,C,D,E,F are six bidders having the following technical marks:
BIDDER TECHNICAL MARKS
A 95
B 75
C 84
D 80
E 78
F 88
Here bidders A, F and C are top three scores, which shall be considered for financial opening.
inancial Opening of Bids (TWO COVER SYSTEM)
F
271
The bids of only the bidders shortlisted as defined above shall be opened financially and
selection shall be made on the basis of Least Cost Method i.e the bidder who has quoted
lowest% age rate shall be considered for assignment of the job. However the agency
securing the highest score in Technical evaluation shall have the option of matching the
price bid of the lowest bidder & shall be preferred for assignment of the job, in case the
agency matches the price bid of the lowest bidder among the shortlisted bidders.
Executive Engineer
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
272
The necessary documents and annexures to be attached by the consultant taking part in
Bidding process.
A. Technical Proposal
B. Brief description of the registered Firm/Consultancy
C. Declaration for competing
D. Contact details of the Firm
E. List of experts / architects
CHAPTER - 20
PWD ENGINEERING MANUAL-2020
273
TECHNICAL PROPOSAL
From: To
Dear Sir,
I, on behalf of as an
Firms/Consultant herewith enclose Technical Proposal for engagement of
my / our Organization for:-
1). Construction of
Yours faithfully,
Signature of the authorized signatory:
Name of the authorized
274
"Annexure A"
(Note: The Firms/Consultant should also give details of the ongoing similar
assignments in the below format).
CHAPTER - 20
Owner/ Cost of Date of Date of
Assignment of Assignment
S.No. Sponsor Assignment Commencement Completion
(Brief Project satisfactorily
Scope) completed
1 2 3 4 5 6 7 8
Note: The applicant must attach documentary evidence in support of their submission above
275
"Annexure B"
Declaration
276
"Annexure C"
1. Name of Firms/Consultant
CHAPTER - 20
registered under the Indian
Companies Act, 1956/ the
partnership Act, 1932
4. Whether the
Firms/Consultant
has been blacklisted by any
Central Govt. / State
Govt./PSU/ Govt. Bodies /
Enclose:-
1. Copy of Certificate of Incorporation.
2. Copy of Article of Association in respect of 3above.
3. Undertaking in respect of 4above.
Signature of the
applicant Full name of
the applicant
Stamp and Date
277
"Annexure D"
S. Relevant
Name Designation Qualification Experience
NO
1
2
3
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
4
5
6
7
8
9
Signature of the
applicant Full name of
applicant
Stamp & Date
278
IMPORTANT INSTRUCTIONS
Due to technical/Software constraints the %age rate for the work Expression of interest (EOI)
shall be uploaded in.xlsx format. The%age quoted by the bidder in the basic rate column shall be
treated as %age for the said work. The total Amount Columns in Figures and Words shall not be
considered.
For Example
CHAPTER - 20
Basic Rate in Figures to be entered
Shall be treated as
279
20.6. Check List for Release of CDR
S. No Particulars Remarks
01 Position of AAA whether accorded or not
02 Position of Technical Sanction
03 Date of actual start of work
04 Date of completion of work
05 Actual date of completion of work
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
280
(a) 20.7. Technical Evaluation checklist and format
Name of Work :- .
Advertised cost:- lacs
NIT No
Last date of receipt of Bids = / /2020
Date of Opening Technical Bids = / /2020
CHAPTER - 20
Bidder No: T ---/ ---
Bid participation
Single
Registration NO.
duly renewed
Place of Registration/Incorporation
281
Fixed deposit receipt, issued by any scheduled
Indian Bank or a foreign Bank approved by the Name of
Bank
Bank
Reserve Bank of India.
4 PAN No
1 Tipper Trucks
2 Excavator
3 Lift Mixer
4 Mixer
5 Vibrator
6 Generator (125 KV
7 Dewatering Pump
9 Welding Machine
10 Roller
283
Experience with respect to pre-qualification
criteria mentioned in SBD.
18
284
The statements showing the value of existing
commitments and on-going works as well as
the stipulated period of completion remaining
for each of the works listed should be
20
countersigned by the Engineer in charge, not
B = Rs. Lacs,
below the rank of an Executive Engineer or
equivalent.
21
CHAPTER - 20
Basic Amount ITR/TDS Index
Year (Lacs) Factor Indexed Amount (Lacs)
Financial Turn with respect to SBD
20YY-YY 0.00
23 20YY-YY 0.00
20YY-YY 0.00
20YY-YY 0.00
(A* N* M -B)
Available Bid Capacity
Qualifying Requirement more than Rs. Lacs
( ) = Rs.
Amount - Lacs
285
Remarks
Responsive/ Non Responsive
R&B
(b)
Name of Work :-
NIT No
Last date of receipt of Bids = / /2020
Date of Opening Technical Bids
286
Name of Bidder
Bid participation
1
Constitution / Legal Status
CHAPTER - 20
Registration NO.
Place of Registration/Incorporation
4 PAN No
287
Details of participation in joint
7
venture
references.
288
Tipper Trucks 4 No
Excavator = 2 No.
Mixer =4 No.
CHAPTER - 20
Vibrator = 6 No.
289
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
21
Inde Indexe
Financial Turn with respect to SBD x d Amoun
Year Basic Amount (Lacs) ITR/TDS Fact t (Lacs)
or
23
290
Qualifying requirement as per SBD
Rs____________________lacs
Max Avg Financial turn Over
CHAPTER -
1.5
N=Number of Years prescribed for
Completion of work.
(A* N* M -B)
Amount
Remarks Non-Responsive
The Bidder T1/02 namely ABC has not Uploaded the registration
Card nor Renewal of registration . Besides the bidder has uploaded
Certificates for similar nature of work which are either under
value or Ongoing work. Further the the latest GST Clearence
Certificate has not been uploaded .Hence the Bidder has been
assessed as NON-RESPONSIVE .
291
9
(C)Technical summery evaluation sheet
Name of Work :-
NIT No
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
1 RESPONSIVE
NON
2
RESPONSIVE
As such we may load the Technical Bid Evaluation Summary / Results on the web
site for information of all the concerned and opening of financial bids of the
responsive bidders.
292
9
20.8.Vendor Development
The program for providing training to the new generation contractors who are qualified
in civil engineering shall be conducted by the HRD wing of the department. The objective shall
be to attract interest from new generation contractors into the construction industry.
CONTRACT MANAGEMENT
General provisions common to both Construction and Maintenance works. Provision related to
Construction works Provisions related to Maintenance works.
CHAPTER - 20
The financial powers given separately as ―Compendium of Financial Powers Delegated to
PWD Officers‖.
Relaxation of any provision of the SOPs in the interest of requirements of work in keeping with
the provisions in the preamble to the PWD Works Manual 2020 would be allowed to any officer
by the next higher authority not below the rank of a Chief Engineer with recorded reasons.
In case of any conflicting provisions in the Manual and SOPs vis-a-vis ―The General Conditions
of Contract (GCC)‖, the provisions made in the GCC shall prevail in contract management.
Similarly, Acts, Laws as notified by the government, GFR provisions and CVC guidelines shall
293
20.9. Single cover
(A) NOTICE INVITING T,ENDE _RFOR CIVIL WORKS FOR SINGLE COVER
SYSTEM( upto Rs.2.50 Crores)
NIT No. of 20YY-YY DATED:••
For and on behalf of the Lt. Governor, UT J&K, e-tenders (In single
cover system) are invited on Percentage basis from approved and eligible Contractors
registered with J&K Govt., CPWD, Railways and other State/Central Governments for
the following works
Cost of Earne
M.H of Closs of
Nome of Work T/Doc. st
Account Contracto
Money r
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Position of AAA:
Accorded Position of funds Available
The Bidding documents Consisting of qualifying information, eligibility criteria, specifications,
Drawings, bill of quantities (B.O.Q),Set of terms and conditions of contract and other details
can be seen/downloaded from the departmental website www jktenders.gov.in as per schedule
of dates given below·-
1 Date of Issue of Tender Notice
2 Period of downloading of bidding documents I. /.2020 from 10.00 AM.
3 Bid submission Start Date I. 2020 from 10.00 AM.
4 Bid Submission End Date I. /.2020 upto 4.00 PM.
5 Date & time of opening of Bids (Online)
_1._/..2020 at 11.00 A.M in the office of
Executive Engineer Division Bids must be accompanied with cost of Tender document in shape
of Treasury Challan in favour of Executive Engineer R&B Division (tender inviting authority)
and Earnest money I Bid security in shape of CDR/FDR/BG(The Date of Treasury Challan
earnest money/Bid securitv should be between the date of start of bid and Bid Submission End
date)pledged to Executive Engineer R&B Division (tender receiving authority).
The date and time of opening of Bids shall be notified on Web Site www.jktenders.gov.inand
conveyed to the bidders automatically through an e-mail message on their e-mail address.
The bids of Responsive bidders shall be opened online on same Web Site in the Office of
Executive Engineer R&B Division
(tender receiving authority).
The earnest money in favour of unsuccessful bidder shall be released only after submission of
Treasury Challan
The bids for the work shall remain valid for a period of 120 davs from the date of opening of
Technical bids
The earnest money shall be forfeited, lf:-
Any bidder/ tenderer withdraws his bid/ tender during the period of bid validity or makes any
modifications in the terms and conditions of the bid.
294
Failure of Successful bidder to furnish the required performance security within the specified
time limit. Failure of Successful bidder to execute the agreement within 28 days after fixation of
contract. Instruction to bidders regarding e-tendering process.
Bidders are advised to download bid submission manual from the "Downloads" option as well as
from
"Bidders Manual Kit" on website www.jktenders.gov.into acquaint bid submission process. To
participate in bidding process, bidders have to get 'Digital Signature Certificate {DSC)' as per
Information
Technology Act-2000. Bidders can get digital certificate from any approved Vendor.
The bidders have to submit their bids online in electronic format with digital Signature. No bid
will be accepted in physical form.
Bids will be opened online as per time schedule mentioned in Para-1.
CHAPTER - 20
Bidders must ensure to upload scanned copy of all necessary documents with the bid. Besides,
original photocopies of documents related to the bid be submitted physically / by registered post
/through courier before the date specified in Para-1.
Bidders must ensure to upload scanned copy of all necessary documents with the technical bid.
Note:- Scan all the documents on 100 dpi with black and white option.
295
/have not been uploaded shall be entertained in the form of hard copv. However, in case of any
clarification the bidders shall have to produce original documents in support of sop copies if need
arises
General Conditions of Contract:-
The date of start of the work shall be reckoned within one week from the date of issuance of
LOI/Contract allotment as the case may be Penalty for delay in completion:- ln case of delay in
completion of work beyond stipulated period of completion, penalty upto maximum of 10% of
the contract shall be imposed.
Time extension:-Suitable time extension shall be granted in case of increase in scope of work and
in the event of delay beyond control of contractor to be determined by the department.
Advance Payments:- No mobilization advance/equipment advance shall be paid unless
otherwise specified in the SBD.
Secured Advance:- No secured advance is admissible unless otherwise specified.
Schedule of Payment:- The payment schedule shall be fixed after award of contract in favour of
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
successful bidder, on the basis of availability of funds and value of work executed, shall be
determined by the Engineer. Amendment of bidding document:- Before the deadline for
submission of bids the employer may modify the bidding documents by issuing Addendum.
The tender receiving authority reserves the right to accept or reject any tender or all tenders
without assigning any reason thereof.
Unbalanced Bid:- In case bid of the bidder Is unbalanced. The bidder has to upload additional
performance security in shape of CDRIFDRIBG as per the breakup given below .failing which
the tender shall be rejected The date of CDRIFDRIBG should be between the date of start of
bid and bid submission end date).
Percentage of unbalanced bid viz advertised
S.No coston account of low rates Additional Performance Security
For and on behalf of the Lt. Governor, UT J&K, e-tenders (In single cover system) are
invited on Percentage basis from approved and eligible Contractors registered with J&K
Govt., CPWD, Railways and other State/Central Governments for the following works:-
CHAPTER - 20
Cost of Earnest
Adv. Cost (Rs.ln Locs) Time of M.H of Closs
S.No Nome of Work T/Doc. Money (ln
completion Account of
(In Rupees} Rs.}
Contr
actor
2 3 4 5 6 7 8
Development of
1. -- 600/- 1- Days "
Position of AAA: Accorded Position of funds Available
The Bidding documents Consisting of qualifying information, eligibility criteria,
Bids must be accompanied with cost of Tender document in shape of Treasury Challan in favour of
Executive Engineer R&B Division (tender inviting authority) and Earnest money I Bid security in shape
of CDR/FDR/BG(The Date of Treasury Challan earnest money/Bid securitv should be between the date
of start of bid and Bid Submission End date)pledged to Executive Engineer R&B Division (tender
receiving authority).
The date and time of opening of Bids shall be notified on Web Site www.jktenders.gov.in and conveyed
to the bidders automatically through an e-mail message on their e-mail address. The bids of Responsive
bidders shall be opened online on same Web Site in the Office of Executive Engineer R&B Division
(tender receiving authority).
The earnest money in favour of unsuccessful bidder shall be released only after submission of Treasury
Challan
The bids for the work shall remain valid for a period of 120 davs from the date of opening of Technical
bids
The earnest money shall be forfeited, lf:- Any bidder/ tenderer withdraws his bid/ tender during the
period of bid validity or makes any modifications in the terms and conditions of the bid.
297
Failure of Successful bidder to furnish the required performance security within the specified time
limit. Failure of Successful bidder to execute the agreement within 28 days after fixation of contract.
Instruction to bidders regarding e-tendering process.
Bidders are advised to download bid submission manual from the "Downloads" option as well
as from "Bidders Manual Kit" on website www.jktenders.gov.into acquaint bid
submission process.
To participate in bidding process, bidders have to get 'Digital Signature Certificate {DSC)' as per
information Technology Act-2000. Bidders can get digital certificate from any approved Vendor.
The bidders have to submit their bids online in electronic format with digital Signature. No bid
will be accepted in physical form.
Bids will be opened online as per time schedule mentioned in Para-1.
Bidders must ensure to upload scanned copy of all necessary documents with the bid. Besides, original
photocopies of documents related to the bid be submitted physically I by registered post /through
courier before the date specified in Para-1.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Bidders must ensure to upload scanned copy of all necessary documents with the technical bid.
Note:- Scan all the documents on 100 dpi with black and white option.
The department will not be responsible for delay in online submission due to any reasons.
Scanned copy of cost of tender document in shape of Treasury Challan in favour of Executive
Engineer R&B Division
and Earnest Money Bid Security in shape of CDR/FDR/BG. (The date of earnest
money/Bid security should be between the date of start of bid and Bid Submission End date)
pledged to Executive Engineer R&B Division must be uploaded with the documents
of the bid.The original Treasury Challan (cost of tender document), CDR/FDR/BG (earnest
money/bid security) and relevant bid documents shall be obtained from the lowest bidder before
the fixation of contract. Bidders are advised not to make any change in BOQ (Bill of Quantities)
contents. In no case they should attempt to create similar BOQ manually.
Price escalation on and Taxes: - The %age rate method requires the bidder to quote a percentage
above / below / at par of the schedule of rates applicable/ as mentioned in the advertised
BOQ. The percentage quoted by the bidder shall be deemed to include price escalation and
all taxes upto completion of the work. Deduction on account of taxes shall be made from the
bills of the contractor on gross amount of the bill as per the rates prevailing at the time of
recovery.
Bidders are advised to use "My Documents" area in their user on R&B e-Tendering portal to
store such documents as are required.
In case of CRF and any other specified project. The relevant guidelines standard bidding
document shall be followed.
Instructions to Bidder(ITB)
All bidders shall upload the following information and documents along with qualification criteria
qualification information with their bids:-
Copies of original documents defining constitution/ legal status, place of registration and
principal place of Business with Cell No .and Correspondence address. Treasury Challan
&/CDR/FDR/BG
Valid GSTIN No. & PAN No.
Scanned Copy of GSTIN Registration and latest clearance certificate FORM GST-38 I.e.
latest clearance certificate FORMGST-38 of the preceding Month to the Issued of Nrr
The bidder at his own responsibility and risk should visit and examine the site of work and its
surroundings before submission of bid.
298
Non attendance of pre-bid meeting will not be cause of disqualification of the bidder. All
documents relating to the bid shall be in the English Language.
Bidder must ensure to upload scanned copies of all necessary documents including earnest money
and tender documents fee in terms of sop copies with technical bid. No document (s} which has
/have not been uploaded shall be entertained in the form of hard copy. However, in case of any
clarification the bidders shall have to produce original documents in support of sop copies if need
arises
General Conditions of Contract: -
The date of start of the work shall be reckoned within one week from the date of issuance of
LOI/Contract allotment as the case may be.
Penalty for delay in completion: - ln case of delay in completion of work beyond stipulated period
of completion, penalty upto maximum of 10% of the contract shall be imposed.
Time extension: -Suitable time extension shall be granted in case of increase in scope of work
CHAPTER - 20
and in the event of delay beyond control of contractor to be determined by the department.
Advance Payments:-No mobilization advance/equipment advance shall be paid unless otherwise
specified in the SBD.
Secured Advance:-No secured advance is admissible unless otherwise specified.
Schedule of Payment:-The payment schedule shall be fixed after award of contract in favour of
successful bidder, on the basis of availability of funds and value of work executed, shall be
determined by the Engineer. Amendment of bidding document:-Before the deadline for
submission of bids the employer may modify the bidding documents by issuing Addendum.
The tender receiving authority reserves the right to accept or reject any tender or all tenders
Restoration of work:- On completion of contract the contractor shall be responsible to remove all
un-used material and restore all work in its original position at his own cost.
Arbitration:- The arbitration shall be conducted in accordance with the arbitration procedure
stated in the J&K Conciliation and Arbitration Act No:-xxxv of 1997 issued vide SRO No:-403
vide Notification of J&K Govt.,
299
"Law Department" 11th December-I997.
Defect Liability period:- The DLP shall be Calculated from date of certified completion of
work and period shall be 36 months. The defects noticed in the work during execution or D.L.P.
shall be corrected by the Contractor within the length of time specified by the Engineer. If the
contractor does not correct the defects pertaining to D.L.P. to the satisfaction of the Engineer
within the time specified, the Engineer will assess the cost of having the defects corrected and
contractor will pay this amount on correction of defects.
The date of start of work shall be reckoned within seven days from the date of issuance of
allotment/ Letter of intent. In case the agency fails to execute the work, the deposits in the shape
of CDR/FDR/BG and Additional performance guarantee shall be liable for forfeiture besides
initiating other punitive actions against the defaulter without serving any notice.
ALL KEY CONSTRUCTION MATERIAL shall have to be strictly as per prescribed
specifications and approval of the Engineer In-charge.
The EMD shall be released after successful completion of DLP
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
Failure on part of the contractor to fulfill his obligations of maintenance schedules shall result in
forfeiture of the deposits held for this purpose as well as the CDRIFDR/BG for this work.
Safety:- The contractor shall be responsible for safety of all activities at site of work.
Tests:-The contractor shall be solely responsible for carrying out the mandatory tests required for
the quality control at his own cost.
Termination:- The employer may terminate the contract if the contractor causes a
fundamental breach of the contract.
Continuous stoppage of Work for a period of30 days without authorization of Engineer in-
charge. Contractor is declared bankrupt.
Any evidence of involvement of contractor in corrupt practices.
If the contractor indulges in willful disregard of the quality control measures put in place by the
department. Contractor delays the completion of work beyond stipulated time of completion.
Pursuant to the process of termination of defaulted contract, the employer reserves the right to
invite fresh tender for the balance work at the risk and cost of defaulting contractor.
If in case contractor failed to start /complete the work, within the stipulated time period, his Earnest
Money shall be forfeited after termination of the contract. Besides, defaulting contractor shall be
debarred from taking works in R&B Department at least for one year.
Major Labour Laws applicable to establishment
engaged in building and other construction Work:-
Workmen compensation act 1923.
Payment of Gratuity Act 1972.
Employees P.F. and Miscellaneous Provision Act
1952. Maternity Benefits Act 1951.
Contract Labour (Regulation & Abolition) Act
1970. Minimum Wages Act 1948.
Payment of Wages Act 1936.
Equal remuneration Act 1979.
Payment of bonus Act 1965.
300
Industrial disputes Act 1947.
Industrial employment standing orders Act 1946.
Trade Union Act 1926.
Child Labour (Prohibition & Regulation) Act 1986.
Inter State Migrant workmen's (Regulation of employment & Conditions of service)Act 1979.
The Building and other Construction workers (Regulation of employment and Condition of
service) Act 1996 and the Census Act of 1996.
Factories Act 1948.
Compliance with Labour Regulation Laws of J&K .
Specification/Quality Control:-All items of works shall conform to specifications as per IRC/
MORTH/ NBO/ CPWD/ SSRI Any other prescribed specifications.
CHAPTER - 20
the contractor shall be mandatory.
Laws Governing the Contract: -The contract shall be governed by Laws of the land.
Court's Jurisdiction:-In case of a disputes/differences between contractor and Department the
jurisdiction shall be J&K.
Time Extension: -
The work is to be completed within the time limit specified in the NIT and the time of
completion will also increase I decrease in proportion with additional I deleted quantum of
No. _
Executive Engineer
Dated: } }.2020 R&B Division _
Copv to the:-
301
NOTICE INVITING TENDER
MACADAM WORKS
For and on behalf of the President of India ,e-tenders (In single cover system) are invited on
CHAPTER - 20
Percentage basis from approved and eligible Contractors registered with J&K Govt., CPWD,
Railways and other State/Central Governments for the following works:-
Adv. Cost Cost of Eomest Time of
S.No Name of Work T/Doc. Money
(Rs.In Lacs} completion
(In Rupees) (inRs.)
2 3 4 5 6
improvement/upgradtion of road
1. Surface (Machine mix to Incl. C/o 1- 1- Days
be laid with Paver). Bitumen
PWD ENGINEERING MANUAL-2020
302
Failure of Successful bidder to execute the agreement within 28 days after fixation ofcontract.
Instruction to bidders regarding e-tendering process.
Bidders are advised to download bid submission manual from the "Downloads" option as well as from
"Bidders Manual Kit" on website www.jktenders.gov.into acquaint bid submission process.
To participate in bidding process, bidders have to get 'Digital Signature Certificate {DSC)' as per
Information Technology Act-2000. Bidders can get digital certificate from any approved Vendor.
The bidders have to submit their bids online in electronic format with digital Signature. No bid
will be accepted in physical orm.
Bids will be opened online as per time schedule mentioned in Para-1.
Bidders must ensure to upload scanned copy of all necessary documents with the bid. Besides,
original / photocopies of documents related to the bid be submitted physically / by registered post
/through courier before the date specified in Para-1.
Bidders must ensure to upload scanned copy of all necessary documents with the technical bid.
CHAPTER - 20
Note:- Scan all the documents on 100 dpi with black and white option.
The department will not be responsible for delay in online submission due to any reasons.
Scanned copy of cost of tender document in shape of Treasury Challan in favour of Executive Engineer
R&B Division and Earnest Money / Bid Security in shape of CDR/FOR. (The date of earnest
money/Bid security should be between the date of start of bid and Bid Submission End date) pledged to
Executive Engineer R&B Division must be uploaded with the documents of the bid. The original Treasury
Challan {cost of tender document), CDR/FDR/BG {earnest money/bid security) and relevant bid
documents shall be obtained from the lowest bidder before the fixation of contract.
Bidders are advised not to make any change in BOQ {Bill of Quantities) contents. In no case they should
attempt to create similar BOQ manually.
303
General Conditions of Contract:-
The date of start of the work shall be reckoned within one week from the date of issuance of
LOI/Contract allotment as the case may be.
Penalty for delay in completion: -ln case of delay in completion of work beyond stipulated
period of completion, penalty upto maximum of 10% of the contract shall be imposed.
Time extension:-Suitable time extension shall be granted in case of increase in scope of work
and in the event of delay beyond control of contractor to be determined by the department.
Advance Payments: -No mobilization advance/equipment advance shall be paid unless
otherwise specified in the SBD.
Secured Advance:- No secured advance is admissible unless otherwise specified.
Schedule of Payment:-The payment schedule shall be fixed after award of contract in favour of
successful bidder, on the basis of availability of funds and value of work executed, shall be
determined by the Engineer. Amendment of bidding document:-Before the deadline for
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
submission of bids the employer may modify the bidding documents by issuing Addendum.
The tender receiving authority reserves the right to accept or reject any tender or all tenders
without assigning any reason thereof.
Unbalanced Bid:- In case bid of the bidder Is unbalanced. The bidder has to upload additional
performance security In shape of CDR/FDR/BG as per the breakup given below. failling which
the tender shall be rejected. (The date of CDR/FDR/BG should be between the date of start of
bid and bid submission and date).
Percentage of unbalance bid
S.No Additional Performance Security
viz., advertised cost on account of Low rates
01. Upto and including 16% below Nil
02. >16% upto and including 20% below 6% of Advertised Cost
03. >20% upto and including 26% below 10% of Advertised Cost
04. >26% upto and including 30% below 15% of Advertised Cost
05. > 30% Balow 20% of Advertised Cost
The additional performance security shall be released only after successful completion of
work. The additional performance security unsuccessful bidder shall be released in a week's
time after technical evaluation.
Arbitration:- The arbitration shall be conducted in accordance with the arbitration procedure
stated in the J&K conciliation and Arbitration Act No:-xxxv of 1997 issued vide SRO No:-403
vide Notification of J&K Govt., "Law Department" 11th December-1997.
Defect Liability period:- The DLP shall be Calculated from date of certified completion of
work and
304
period shall be 36months. The defects noticed in the work during execution or D.L.P. shall be
corrected by the Contractor within the length of time specified by the Engineer. If the
contractor does not correct the defects pertaining to D.L.P. to the satisfaction of the Engineer
within the time specified, the Engineer will assess the cost of having the defects corrected and
contractor will pay this amount on correction of defects. The date of start of work shall be
reckoned within seven days from the date of issuance of allotment/ Letter of intent. In case
the agency fails to execute the work., The deposits in the shape of CDR/FDR/BG and
Additional performance guarantee shall be liable for forfeiture besides initiating other
punitive actions against the defaulter without serving any notice.
All Key Construction Material shall have to be strictly as per prescribed specifications and
approval of the Engineer In-charge.
Retention Money & Maintenance Liability:- An amount equal to 15% of the payments due shall
be retained and treated as a deposit on account of retention money and maintenance liability for a
CHAPTER - 20
period of (03) three years from the date of virtual completion of the work. The same shall be
released after successful completion of maintenance liability for the said period as per schedule
give below:-.
50% of such deposit after One year of maintenance to be counted from Virtual date of
completion.
25% of such deposit after two years of maintenance to be counted from Virtual date of
completion 25% of such deposit after three years of maintenance to be counted from Virtual date
of completion
Note:-
The maintenance liability will not include damages caused due to natural calamities like
Safety:- The contractor shall be responsible for safety of all activities at site of work.
Tests:-The contractor shall be solely responsible for carrying out the mandatory tests required for
the quality control at his own cost.
Termination:- The employer may terminate the contract if the contractor causes a
fundamental breach of the contract.
305
If the contractor indulges in willful disregard of the quality control measures put in place by
the department. Contractor delays the completion of work beyond stipulated time of
completion.
Pursuant to the process of termination of defaulted contract, the employer reserves the right to
invite fresh tender for the balance work at the risk and cost of defaulting contractor.
If in case contractor failed to start /complete the work, within the stipulated time period, his
Earnest Money shall be forfeited after termination of the contract. Besides, defaulting contractor
shall be debarred from taking works in R&B Department at least for one year.
31.0 Major Labour Laws applicable to establishment engaged in building and other
construction work:- Workmen compensation act 1923.
Payment of Gratuity Act 1972.
Employees P.F. and Miscellaneous Provision Act 1952.
Maternity Benefits Act 1951.
Contract Labour (Regulation & Abolition) Act 1970.
Minimum Wages Act 1948.
Payment of Wages Act 1936.
Equal remuneration Act 1979.
PWD ENGINEERING MANUAL-2020 CHAPTER - 20
33.0 Insurance:- Insurance cover to Labour / Machinery / Work / Plant material Equipment
by the contractor shall be mandatory.
Laws Governing the Contract:-The contract shall be governed by Laws of the land.
306
On contractor's representation based on the grounds as detailed above the time for
completion of the work may be extended by a period considered reasonable by the
Department.
Extension of time shall be also admissible in the event of temporary suspension of work.
Special Conditions regarding Specifications and Quality control for Machine laid B.T.
Works:-
All the components of the work shall be executed strictly as per specifications laid down in
the Ministry of Road transport and Highways publication "Specifications for road and
bridge Works" and I.R.C:SP:20 read with revised guidelines as per I.R.C:SP:72 and
amendments made till date of issuance of N.I.T.
All the road materials for use shall conform to the specifications laid down in "Rural Roads
manual" a publication of I.R.C.
For items not covered in Rural Roads manual the Ministry of Road Transport & Highways
(MORTH) Specifications for Road and Bridge works- Latest edition shall be followed.
Physical properties of aggregates for bituminous works i.e Shape, Strength, durability and
CHAPTER - 20
Stripping value should satisfy the requirements prescribed in I.R.C: SP: 20.
Periodic sieve analysis of each type of aggregate and periodic check of aggregates at the
gradation control unit shall be carried out to ensure that the proportion of the aggregates as
specified is complied with. Conducting of mandatory quality control tests for various
components of the advertised work like Thickness tests, tests for impact value, stripping,
307
308
309
310
Chapter 21
21.01.1. General
All officer s concerned with the supervision, management and control of contract works shall
thoroughly familiarize themselves with the general and special conditions of contract, the
technical details and specifications of the work. The officer who has executed a contract
agreement shall be responsible for the proper execution of the work as per specifications in
PWD ENGINEERING MANUAL-2020 CHAPTER - 21
accordance with the conditions of contract. There shall be advance planning of each item of
work to keep up the progress of work specified in the agreement. For this advanced methods in
planning and management techniques shall be adopted.
This planning shall be done in accordance with the schedule of work and the time frame fixed
for the project, by the Assistant Engineer or Assistant Executive Engineer in respect of contracts
entered into by them, or by the Executive Engineer in respect of other works. The contractor
shall abide by the planning schedule of the concerned authority and direction of the field
Engineers. All preliminaries such as removal of hindrances like underground cables, pipelines,
electric posts, etc., shall be completed before the award of contract. Difficulties if any shall be
brought to the notice of the head of departments concerned or to government. Where delay is
anticipated, the matter shall be brought to the notice of the authority who executed the
agreement so that the date of commencement may be fixed suitably in consultation with the
contractor.
311
21.02.2. Working Drawings
For all works except maintenance, it may be necessary to supply working drawings giving full
details of the work. Such working drawings may be prepared by the site Engineers of the contractor
and may be adopted with the approval of the officer who has executed the agreement. Where,
however, there is substantial variation contemplated from what is provided for in the original
design, modifications shall not be approved, except with the approval of the authority who gave
technical sanction to the estimate. Wherever necessary, approved working drawings may be made
to form part of thecontract.
CHAPTER - 21
21.02.3. Setting out of works
Before starting any work, the work shall be set out on the ground as per approved plans. The
responsibility for setting out a wo rk is that of the contractor as p er terms of contract. It is however
necessary that the setting out is checked and approved by the departmental Officers. This shall be
done bythe Assistant Executive Engineer in other cases. If in the course of checking, the J.E,
Assistant Engineer or the Assistant Executive Engineer feels that the advice of any higher authority
is necessary he shall refer the matter to such higher authority and abide by his instructions. The
Agreement Authority may in the case o f major works, direct that the setting out shall be got
checked and approved by an officer of rank higher than that of an Assistant Executive Engineer.
All benchmarks and setting out marks to be adopted for a work shall be of a permanent nature.
312
21.03. Quality Control
Every work has to be properly supervised to ensure that it is carried out in accordance with the
required specifications. Effective supervision shall be insisted for maintaining quality of all items
of work. Where there is no specification for a particular item described in the schedule, the
specification of the item in the MoRTH/ NBC as the case may be, or the Indian Standard
Specification shall be adopted. Every officer and subordinate controlling the construction of the
work shall be fully conversant with these specifications. Any deviation from the standards
prescribed shall be reported fourth-with by the Junior Engineer, Assistant Engineer to the Assistant
Executive Engineer. The Junior Engineer under the control of a work shall be responsible for
maintaining quality of all items of work. They are bound to act according to the duties and
responsibilities laid to them. It will also be the duty of the Junior Engineer/Assistant Engineer and
other inspecting officers to check the quality of works to see that the specifications are properly
followed. If any bad work is noticed even though passed by a subordinate officer, it shall be
ordered to be removed forth with, at the cost of the contractor. Important items like R.C.C. in
works shall be carried out only in the presence of the Assistant Executive Engineer. The Assistant
PWD ENGINEERING MANUAL-2020 CHAPTER - 21
Executive Engineer may delegate supervision of small items of R.C.C. work like lintels, coverings
lab, sunshade and other similar items to Assistant Engineer, in case he is unable to be present at the
time of concreting. Plain cement concrete works for levelling course, side drains and other similar
items shall be done in the presence of the Junior Engineer/Overseer in charge. However, plain
concrete works for major structures shall be done only in the presence of the Assistant Executive
Engineer. In all major works, the Executive Engineer shall decide, the items, which are to be done
in his presence. Quality control shall be effected as per the provisions of the chapter on Quality
Control. Certificates as required in this chapter shall also be
insisted.
● A list of mandatory tests should be prepared and attached with the tender documents
● Test Registers should be issued to all officers under the control of the work by Executive
Engineer.
● Test Reports of all mandatory tests should be submitted along with the final bill of the work.
313
for the safe custody and maintenance of the book issued to him for a particular work.
3. The Junior Engineer/Overseer at site shall record in the Work spot order book, the day-
today progress of the work; procurement of materials, inspecting officers shall record their remarks
and instructions in the work spot order book.
The work spot order book shall invariably be perused and initialed with date by the Junior
Engineer/Assistant Engineer in charge, during his inspection, irrespective of whether he has any
remarks to offer or not.
The work spot order book shall not be treated as a substitute for measurement book or field book.
The orders issued by the inspecting officers shall be recorded in the work spot order book. If such
orders are beyond his competence, the officer issuing the orders shall address the appropriate
authority and obtain ratification. The instructions and orders issued through the work spot order
CHAPTER - 21
book will be binding on the departmental subordinates at site. The Overseer shall submit copies of
the instructions to the Junior /Assistant Engineer. The Junior/Assistant Engineer shall communicate
copies of instructions to be complied with by the contractor to him in writing.
21.08. Labour
As per special conditions of contract (above) 20.6.1.4
314
case may be and duly checked by superior officers. The contractor or his authorised agent shall be
present at the time of recording of each set of measurements and shall sign the measurement book
and/or level field book in token of his acceptance. If the contractor fails to be present at the time of
taking measurements either in person or through his authorised agent or fails to accept the
measurements or file objections to the measurements with reasons before check measurement, the
measurements taken by the Engineer shall be deemed to be correct subject to check measurements.
The measurement book i n the form given in Appendix 2100E1 is the original record of actual
measurements. Except for quantities of work paid on level basis, all measurements are recorded in
the measurement book. The J.E shall record the measurements. The measurements shall be checked
by an officer higher in rank to the officer who has recorded the measurement, but not by an officer
below the rank of an Assistant Engineer. All measurements shall be recorded directly in the
measurement book or in the field book and the description shall be lucid to enable easy
identification and check. All the Measurement books and Field books belonging to each Division
shall be numbered serially and pages of each book shall be machine numbered and a register of
PWD ENGINEERING MANUAL-2020 CHAPTER - 21
them shall be maintained in JK.P.W. Form 84 in the Division Office, showing the serial number of
each book, names of sections to which issued, the date of issue and date of return so that its
eventual return to the Division Office may be watched. The completed measurement books shall be
sent to the Division Office for final record.
The above procedure shall be adopted for the maintenance of Standard Measurement books also. A
movement register shall be maintained in the Section, Sub Division and Division offices for noting
the receipt and return of measurement books and LF books.
As a general rule, earth work shall be measured by level section where the total quantity exceeds
300 cum. and where the site conditions are such that level sections, will give correct indications of
the quantity of work involved. If the site conditions are not suitable for working out the quantities
through level sections, orders of the officer who accorded technical sanction shall be obtained for
taking measurements otherwise, than by level sections in cases where the total quantity exceeds
300cum. Where level sections are taken for computing the quantity of earth work the initial levels
and final levels shall be entered in properly numbered field books (Appendix 2100E2) by the
concerned Junior/ Assistant Engineer. Computerized calculation methods shall be utilized for
earthwork computation wherever available. The agreement authority shall approve the proposals
for earthwork in the initial level sheets. The method of measurement as indicated in the standard
data book in metric system shall be followed. Where there is no specific direction in this matter in
the standard data book, the Indian standard method of measurement for building work shall be
followed (I.S. 1200 as amended from time to time).
Electronics device shall be utilized for earthwork computation as far as possible wherever available
in which case computerized printout duly signed by the contractor and verified by the Junior /
Assistant Engineer checked by the Assistant Executive Engineer shall be treated as records.
If an item of work is measured in incomplete stages, up to date measurements shall be recorded
each time and the quantity for payment at any stage shall be worked out by deducting the total
quantity already paid from the up to date quantity measured at that time.
In making interim payments, care shall be taken to see that no over payments are made. For this
purpose, if tape measurements are taken for earthwork, requiring level calculation a deduction of
not less than 10 percent shall be made in the quantity assessed for payment.
In case of works, which will be covered up, measurements shall be taken prior to such covering up
and got verified checked and accepted even though a bill may not be immediately due.
In case of works like demolition of an existing structure etc., which cannot be measured after
execution of the work, pre measurement of the work to be done shall be taken and got check
measured before the commencement of the work.
315
Payment for the works above the TS powers of the Superintending Engineers shall be based on
measurements / reduced level recorded and signed by the contractor in computer format at various
stages of the works duly verified by the Assistant Engineer and checked by the Assistant Executive
Engineer. The measurement shall be in computerized M-Book format. In quadruplicate the
measurements shall be verified by Assistant Engineer and checked the Assistant Executive
Engineers and two copies to be returned to the contractor. One copy of this approved measurement
shall be accompanied with the bills submitted by the contractor. The bill shall be prepared and
submitted by the contractor in quadruplicate supported by approved measurement with soft copy.
The contractor shall jointly be responsible for the correctness and completeness of the
measurements with the verifying and checking officers. Computerized level field books to be
issued and maintained in the same way as computerized measurement books as 5th para noted
above.
The items of test check by Executive Engineer should invariably include
CHAPTER - 21
R.C.C./Reinforcement/other high value item which will also ensure structural safety.
Interim bills may be paid at suitable intervals according to the stage of execution of the work subject
to availability of funds. Junior/Assistant Engineer shall prepare the bill on the basis of measurements
taken by him and deal with it after getting the bill accepted by the contractor. After verification and
check measurement, the Assistant Executive Engineer or Executive Engineer will pass the bill and
effect payments as per powers delegated to them.
Payment for deposit works shall be made by the concerned officers as per powers delegated for
passing and payments of bills.
The Contractor is bound to complete the work within the stipulated period as per the agreement.
When the contract period has to be extended wholly or partly due to default on the part of the
contractor, the Agreement Authority may sanction extension of time after imposing fine prescribed
in the bidding document.
It is also open to the agreement authority to refuse sanction to a modified program or extension of
time if such modification or extension is wholly or partly due to default on the part of the
contractor. The agreement authority may in such cases cancel the contract and arrange the balance
work following the procedure laid down in the General Conditions of contract/standard bidding
document and rearrange the work within ninety days from the date of order of termination.
Application for extension of time from the contractor shall in all cases be made before the expiry of
the time of completion as per agreement. The Junior/Assistant Engineer shall submit the
application received from the contactor to Assistant Executive Engineer with his remarks /
recommendations regarding the genuineness of the reasons stated by the contractor. If the
contractor fails to make such application in time as mentioned above the contract will stand
terminated on the expiry of the time of completion stipulated in the agreement including extension
already sanctioned. In case there is no default on the part of the contractor the termination will not
attract any penalty. When there is default on the part of the contractor, he shall he liable for
penalties as per general conditions of contract for termination.
The contractor shall not execute any work as per the agreement after the expiry of the time of
completion unless the agreement authority duly sanctions extension of time. If any work is carried
out by the contractor in contravention to this, the same shall be treated as unauthorized and no
payment will be made for such work. The department will also have the right to claims from the
contractor, cost of dismantling and removing such unauthorized works. Departmental officers shall
be responsible for the delay in completion of a project if the delay is attributed due to lapses on
their part
Fines for extension of time
Period Rate of fine
First Extension as per SBD
317
21.13. Date of Completion of Work
The date of completion of a work is the date of last measurements taken by the concerned
Assistant Engineer/contractor on completion of work. A completion certificate in the prescribed
proforma (Appendix 2100G) along with the as built drawings of the work shall be submitted to
the TS authority with copies to the superior officers. Final bill will be paid only after completion
is certified by the competent authority.
21.14. Suspension of Works
If, in the course of execution of work, circumstances arise necessitating the suspension of the
work in whole or part, the agreement authority may order suspension of the work in accordance
with the provisions in the general conditions of contract. However, before ordering such
suspension, the agreement authority shall consider all alternatives for different and speedy
CHAPTER - 21
execution of the work and order suspension only if it is inevitable. The period of suspension shall
PWD ENGINEERING MANUAL-2020 CHAPTER - 21
318
3) With holding of this amount on failure to achieve the completion of work or of milestones
shall be automatic without any notice to the contractor.
319
21.18. Settlement of Disputes and Differences
The agreement authority as well as the contractor shall follow the procedure contained in the
relevant clause in the general conditions of the contract for settling the disputes arising out of
the execution of the contract as per SBB.
CHAPTER - 21
when the work is intended for the use of any other Department or agency, the completed works
along with a s et of completion drawings to the concerned officer of that Department/ Agency. If
any land is excess of that required by the completed work had been taken over for the work and
if it is no longer required for the Department the Assistant Executive Engineer will take action
to hand over such land to the Revenue Department.
320
Chapter 22
All works shall be executed based on the specification of MoRTH for road works and National
Building Code for building works. The Assistant Engineer is the first responsible engineering
officer at the site of any construction work like buildings, bridge, roads, etc., who looks after
day to day king of the project. The efforts taken & the strict supervision on his part have direct
relation to the quality of work. He shall therefore get conversant with various aspects of
execution of work, to discharge the duties efficiently. The Assistant Engineer can depute one or
PWD ENGINEERING MANUAL-2020 CHAPTER - 22
more Overseers to a work site for the effective supervision and proper quality control.
1. Drawings
All drawings like plan, elevation, layout plan, sections, R.C.C. layout, alignment plan etc. shall
be maintained in site office. Such plans are required for daily reference and during the inspection
of higher officers. These drawings shall be properly preserved. Such drawings shall bear the
signatures of officers approving such drawings, to avoid use of any other drawing. Outdated or
superseded drawings shall be clearly marked as such and removed from the site. Also all
drawings in CD may be kept at the office.
2. Estimate &Tender
Copy of the technically sanctioned estimate shall be kept in site office under custody of
Assistant Engineer for correct reference. Similarly, the contract copy containing all documents
shall be kept at site for study and guidance
321
3. Other Registers
Some other registers are also required to be maintained like dewatering, record for foundation,
labour attendance/ wages register maintained by the contractor.
CHAPTER - 22
These are Auto level/Dumpy Level, Theodolite Vernier Caliper and Tapes. Tapes are required
to be carried always for checking measurements. Generally, following tapes shall be available.
i. Metallic tape 15 m &-30m.
ii. Steel tape lm, 15 m,30m.
iii. Cloth tape 15m, & 30m.
In addition each Asst. Engineer/Junior Engineer must carry a 3m. steel tape and a calculator in
his pocket at all times. The following tools are also helpful in execution.
• hammer and peg
• chisel
322
22.04.1 Green buildings
· A green building is one which uses less water, optimizes energy efficiency, conserves
natural resources, generates less waste and provides healthier spaces for occupants, as compared
to a conventional building. The Indian Green Building Council (IGBC) is the leading green
building movement in the country. India is witnessing tremendous growth in infrastructure and
construction development. The construction industry in India is one of the largest economic
activities and is growing at an average rate of 9.5% as compared to the global average of 5%. As
the sector is growing rapidly, preserving the environment poses a host of challenges. To enable
the construction industry environmentally sensitive, CII-Sohrabji Godrej Green Business Centre
has established the Indian Green Building Council (IGBC). IGBC, is a consensus driven not-
for-profit Council, represents the building industry, consisting of more than 1,923. committed
members. The Council encourages, builders, developers, owners, architects and consultants to
design & construct green buildings, thereby enhancing the economic and environmental
performance of buildings. The Green Building Movement in India has been spearheaded by
IGBC since 2001, by creating awareness amongst the stakeholders. Thus far, the Council has
PWD ENGINEERING MANUAL-2020 CHAPTER - 22
been instrumental in enabling 2.23. Billion sq.ft of green buildings in the country. The Council‘s
activities have enabled a market transformation with regard to green building materials and
technologies. IGBC continuously works to provide tools that facilitate the adoption of green
building practices in India. The development of IGBC Green New Buildings rating system is
another important step in this direction. Green building is the practice of creating structures and
using processes that are environmentally responsible and resource-efficient throughout a
building's life-cycle from sitting to design, construction, operation, maintenance, renovation and
deconstruction. This practice expands and complements the classical building design concerns
of economy, utility, durability, and comfort. Green building is also known as a sustainable or
high performance building.
· Benefits of Green New Buildings
Green New buildings can have tremendous benefits, both tangible and intangible. The most
tangible benefits are the reduction in water and energy consumption right from day one of
occupancy. The energy savings could range from 20 - 30 % and water savings around 30 - 50%.
The intangible benefits of green new buildings include enhanced air quality, excellent day
lighting, health & well-being of the occupants, safety benefits and conservation of scarce
national resources.
· National Priorities Addressed in the Rating System
The IGBC Green New Buildings rating system addresses the most important national priorities
which include water conservation, handling waste, energy efficiency, reduced use of fossil fuels,
lesser dependence on usage of virgin materials and health & well-being of occupants. The rating
system requires the application of National standards and codes such as t he NBC, ECBC,
MoEF guidelines, CPCB guidelines, and several others. The overarching objective is to be better
than the national standards so as to create new benchmarks. IGBC Green New Buildings Rating
System 5.
· Water Conservation
· Most of the Asian countries are water stressed and in countries like India, the water table
has reduced drastically over the last decade. IGBC Green New Buildings rating system
encourages use of water in a self-sustainable manner through reduce, recycle and reuse
strategies. By adopting this rating programme, green new buildings can save potable water to an
extent of 30 - 50%.
· Handling of Consumer Waste
Handling of waste in buildings is extremely difficult as most of the waste generated is not
segregated at source and has a high probability of going to landfills. This continues to be a
challenge to the municipalities which needs to be addressed. The rating system intends to
address this by encouraging buildings to segregate the building waste
323
· Energy Efficiency
The building sector is a large consumer of electrical energy. Through IGBC Green New
Buildings rating system, buildings can reduce energy consumption through energy efficient -
building envelope, lighting, air conditioning systems, etc., The energy savings that can be
realized by adopting this rating programme can be to the tune of 20 - 30%.
· Reduced Use of Fossil Fuels
Fossil fuel is a slowly depleting resource, the world over. The use of fossil fuel for
transportation has been a major source of pollution. The rating system encourages the use of
alternate fuel vehicles for transportation.
· Noise
324
Green buildings are designed to reduce the overall impact of the built environment on human
health and the natural environment by:
For example, green buildings may incorporate sustainable materials in their construction (e.g.,
reused, recycled-content, or made from renewable resources); create healthy indoor
environments with minimal pollutants (e.g., reduced product emissions); and/or feature
landscaping that reduces water usage (e.g., by using native plants that survive without extra
watering).
The built environment has a vast impact on the natural environment, human health, and the
economy. By adopting green building strategies, we can maximize both economic and
environmental performance. Green construction methods can be integrated into buildings at any
stage, from design and construction, to renovation and deconstruction. However, the most
significant benefits can be obtained if the design and construction team takes an integrated
approach from the earliest stages of a building project. Potential benefits of green building can
include:
· Environmental benefits
· Enhance and protect biodiversity and ecosystems
· Economic benefits
· Reduce operating costs
· Create, expand, and shape markets for green product and services
· Social benefits
325
22.05. Quality Assurance of works
For all construction activities the provisions of quality manual shall be followed.
CHAPTER - 22
The products of the clearing are to be stacked in such place and in such manner as may be ordered
by the Assistant Engineer and the ground shall be left in a perfectly clear condition. All products
of the clearing shall be the property of Government. These shall be disposed of as per existing
rules without damage to the environment.
22.06.2. Excavation for road work and drain and approval of foundation
All excavation shall be done as per section 300 of MoRTH specification. The Assistant Executive
Engineer shall approve all excavations.
326
22.06.4. Dewatering and protection
Normally, open foundations shall be laid dry. Where water is met with in excavation due to
stream flow, seepage, springs, rain or other reasons, the Contractor shall take adequate measures
to keep the foundation trenches dry when so required and to protect the green concrete/masonry
against damage by erosion or sudden rising of water level. The Contractor shall take all
precautions in diverting channels and in discharging the drained water as not to cause damage to
the works, crops or any other property.
of such proportions as decided by the Executive Engineer. No extra cost is payable to the
contractor on this account.
When rock or other hard strata is encountered, it shall be freed of all soft and loose material,
cleaned and cut to a firm surface either level and stepped as directed by the Junior
Engineer/Assistant Engineer. All seams shall be cleaned out and filled with cement mortar or
grout to the satisfaction of the Junior Engineer/ Assistant Engineer. When foundation piles are
used, the excavation of each pit shall be substantially completed before beginning pile-driving
operations therein.
22.06.7. Backfilling
Back filling shall be done with approved material after concrete or masonry is fully set and
carried out in such a way as not to cause undue thrust on any part of the structure. All space
between foundation masonry or concrete and the sides of excavation shall be refilled to the
original surface in layers not exceeding 150 mm compacted thicknesses. The compaction shall
be done with the help of suitable equipment such as mechanical tamper, rammer, plate vibrator
etc., after necessary watering, so as to achieve a density not less than the field density before
excavation.
327
a) affect the stability or safety of the highway, or any railway or other structures, which may be
present.
b) prevent natural or artificial drainage or irrigation.
c) damage adjacent property or future expansion plans for the highway.
After the correct layout is marked, cross checked and approved the excavation for
foundation starts. Before starting excavation, it is necessary that ground levels are taken
correctly and recorded in level book and the foundation plan. The levels at all junctions of
building shall be taken at a large number of points to give correct idea of ground occupied in
foundation.
Unauthorized entries to site of work shall be prohibited. The contractor shall obtain proper
license for explosives whenever explosives are required to be stored at site and proper
magazines as per rules must be insisted on.
CHAPTER - 22
22.07. Formwork
The concrete acquires exact shape of the mould in which it is placed. For good concrete work,
shuttering, centering and concreting operations are three important things. It is therefore
important that principle of sound design, erection of the shuttering is strictly followed. Any
negligence on this count may lead to mishaps resulting in loss of human life and Government
money.
The provisions of clause 11 of IS 456:2000 shall be followed for formwork. The plan of the
formwork proposed to be employed by contractor shall be obtained and examined by the Junior
Engineer Assistant Executive Engineer in respect of contracts entered into by him or higher
officers. In respect of contracts executed by the Assistant Engineer, the plans shall be obtained
22.07.1 Forms
In designing forms, concrete shall be treated as a fluid weighing 2400 Kg. per cubic metre and
in addition a live load of 700Kg. per square metre on horizontal projection of surfaces shall also
be allowed. Forms shall be so designed and constructed that they may be removed without
injury to the concrete. Blocks and bracings shall be removed with the forms and in no case shall
any portions of the wood forms be left in the concrete. The forms must be so constructed, set
and maintained that the finished concrete shall be of the form and dimensions shown on the
plans and true to line and grade. Allowance for the deflection of forms and for shrinkage and
settlement of staging or centering in addition to the allowance for dead loads, and camber, as
shown upon the plans shall be provided.
Forms used a second time shall be thoroughly cleaned and shall be free from bulge, splits or
warps. In case of compaction of concrete by vibration, the forms shall be so designed as to
withstand the effects of vibration. The formwork shall be coated with an approved release agent
that will effectively prevent sticking/ coating the reinforcement and will not stain the concrete
surface. Lubricating oil(machine oils) shall not be used for this purpose.
The forms shall remain in place for the period required as p er clause 11.3 of IS 456 2000. The
foregoing specification for forms shall also apply to steel forms. The sheets used shall be of
such thickness that the forms will remain true to shape. All bolt and rivet heads shall be
countersunk. Clamps, pins or other connecting devices shall be designed to hold the forms
rigidly together and to allow removal without injury to the concrete. Steel forms, which do not
present a smooth surface or line up properly, shall not be used. Special care shall be exercised to
keep steel forms
328
free from rust, grease or other foreign matter, which will discolor the concrete.
Broadly, the following steps shall be observed
i) Proper design of centering system for all dead & live loads that is approved by competent
officer.
ii) Proper use of shuttering & centering material. Centering shall be of steel props & beams
(telescopic), shuttering of waterproof ply board (preferably laminated on one side) & steel
centering plates.
iii) The erection shall be done carefully. The ground on which it is to be supported shall be firm and
unyielding even during rains. The supports shall be adequatelybraced.
iv) After erection, the Assistant Engineer and Assistant Executive Engineer shall check it for
dimension, line, level &safety.
v) The centering shall be removed only after the minimum prescribed curing period is over.
22.07.2 Scaffolding
PWD ENGINEERING MANUAL-2020 CHAPTER - 22
Scaffolding is the responsibility of contractors, but the departmental officer must ensure that the
scaffolding provided is adequate and properly fixed together and strengthened so that workmen
and others using them can carry on work safely.
22.08.2. Aggregate
It includes both fine and coarse aggregates and shall comply with the requirements of IS 383
329
or other deleterious material. Coarse aggregates having positive alkali-silica reaction shall not
be used. Coarse aggregate shall confirm IS 383 and tests for conformity shall be carried out as
per IS 23.86 Parts I to VIII.
22.08.4Fine Aggregates
It consists of natural sand or hard pieces of crushed stone or gravel or combination thereof.
They shall be clean and shall not contain mica or other deleterious material in such quantities as
to reduce the strength and durability of the concrete or to attack the embedded steel. It also
confirm to IS 383.
CHAPTER - 22
2208.5.Water
Water used for mixing and curing shall be clean and free from injurious amounts of oils, acids,
alkalis, salts, sugar, organic materials or other substances that may cause deterioration to
concrete or steel. It shall conform to requirements of clause 5.4 of IS 456:2000. Potable water is
generally considered satisfactory for mixing concrete. Mixing and curing with sea water shall
not be permitted.
22.08.6. Admixtures
The admixtures for concrete shall be as per clause 5.5 of IS 456:2000.
22.08.8. Bricks
Burnt clay bricks shall conform to the requirements of IS: 1077, except that the minimum
compressive strength when tested flat shall not be less than 8.4 Mega Pascal for individual brick
sand 10.5 MPa for average of 5 specimens. They shall be free from cracks and flaws and
nodules of free lime. The brick shall have smooth rectangular faces with sharp comers and emit
a clear ringing sound when struck. The size maybe according to local practice with
toleranceof±5percent.
22.08.9. Stones
Stones shall be of the type specified. It shall be hard, sound, and free from cracks, decay
and weathering and shall be freshly quarried from an approved quarry. Stone with round surface
shall not be used. IS 1127 shall be adopted for the dimensions of natural building stones. The
crushing
330
strength of building stones when tested as described in IS 1121 shall have a minimum value of
350 Kg/cm2
Following IS codes give specification for various stones used for construction.
331
No road material in excess of requirements shall be stacked in that stretch. Any excess quantity
shall be removed to where It is required, before the materials in that reach are measured.
If sufficient land with not available for stacking in the stretch and/or if safety consideration
demands, the stacking of materials can be permitted in suitable stacking yards with prior
permission from the Assistant Engineer.
All aggregates shall be measured by the J.E and check measured by Assistant Executive
Engineer before it is spread. After check measurement, each stack shall he marked by white
wash or otherwise to prevent the possibility of it being measured again. This shall be reported
to the Quality Cell for verification of quantities as per section 2213. As a rule, collecting and
spreading shall not be carried on at the same time in one and the same kilometer, or in two
adjoining kilometers.
CHAPTER - 22
During the time the aggregate is supplied and stacked, there shall be frequent inspections by the
Overseer as well as by J.E/ Assistant Engineer to guard against stacks being formed over
heaped up earth or debris.
22.09.1.1 Concreting
Concrete proportioning shall be as per clause 9 of IS 456:2000. Nominal mix concrete may be
Usedfor M15 or lower. Design mix is adopted for higher grades. Concreting under special
conditions shall be as per clause 14 of IS456:2006
332
iii) Concrete shall be well compacted, immediately on placing with vibrators. Over or under compaction
shall be avoided. Care shall be taken where reinforcement is heavy in narrow sections. The finished
surface shall be retro welled after initial set to avoid surface cracks.
iv) The curing must begin after the final set but not later than 24 Hrs. The date of concreting shall be
written by paint on column/ beam faces, after removal of shuttering for easy reference. Curing shall
continue for 14 days. When maintaining of proper curing is difficult, curing compounds shall be
used. To conserve water, fine sprayers shall be used for curing the sides & bottoms.
v) At least three cubes shall be taken from the working mix prescribed for day's concreting and their
record shall be maintained. These cubes shall be tested in the laboratory on due dates and proper
cognizance of results shall be taken. In case of abnormal results, the fact shall be immediately
brought to notice of the superior officers.
centering shall be removed only after the prescribed period. While removing centering, care shall
be taken to avoid injuries to the labourers or staff working there. Particular care shall be taken
while removing shuttering below cantilever slab/ beams etc. Unless sufficient counter weight for
the cantilever portion is developed the centering shall not be removed. If proper sequence of
removal of props is not followed, the beam or truss may collapse due to wrong support pattern.
22.10. Ladder
Necessary ladders must be provided in accordance with the clause 14.3 of part 7 of NBC for
supervision and inspection of the official during execution and safety of the workers.
22.11.1. Measurements
Measurement shall be as per section 2109. The Assistant Engineer /Junior Engineer / Contractor
shall take measurements in time so as to get the same checked and bills passed as per terms of
contract. The contractor may also furnish measurements, in which case these shall be checked by
Assistant Engineer and further checked by Assistant Executive Engineer. Any corrections shall be
brought to the notice of the contractor, to be effected accordingly.
333
1. Composite masonry of stone &brick.
2. Item of door, which includes frames, panels, fixtures etc.
3. Items of w/c. containing the pan, flushing cistern, with connections, valves P/Strapor urinals
stands consisting of urinal pot, connecting water supply pipe, flushing tank with overflow,
disposal pipe etc.
Recording of the measurements signifies that all the sub items are completed as p er the
specification. However, if it is necessary to release payments for such item, then proportionate
payments for work done & measured shall be recorded.
CHAPTER - 22
The basic document for effecting payment is the Measurement Book and all payments to
the contractors are governed by the measurements recorded there us & bill recorded. If false,
incorrect, or excess measurements are recorded, it leads to payment not due and Govt. money is
misappropriated. The punishment for such act/lapse is severe and the incumbent shall be
proceeded against as per rules.
334
report by e-mail or fax to Quality Cell in the proforma given in Appendix 2200B so as to verify
the reported quantity. Earth work and usage of stacked materials can be used only after the
verification or on completion of three working days from the date of sending the messages. In
case of urgency the Executive Engineer shall super-check the full quantity and give sanction to
proceed with the work.
In road works involving multi layer pavements powered by the level measurements initial
level with proposal for subsequent layers shall be reported to the Quality cell without resorting
to reporting of final levels of intermediate levels.
Preparation of Bill and payment for the work shall be done only with of the following
certificates:
The contractor has to produce the necessary certificates/test results for compliance to quality
procedures as per chapter on quality control. Environment certificate as per the chapter on
environmental aspects shall also be produced. In case of road and bridge works, Road Safety
Certificate as per the chapter on road safety shall be produced (refer clause 2110 also). This
shall be for works within the technical sanction powers of the Executive Engineer and above.
335
Chapter 23
23.1.1 General
The term "Electrical Works" is used to denote all works necessary for distributing
electrical energy from the supplier‘s service within particular premises. In addition, the
installation and maintenance of certain appliances operated by electricity may also be carried out
as part of electrical works e.g. lifts, air conditioners, water coolers, refrigerator, heaters, cooking
ranges, D.G sets, transformers, fire detection and protection systems, computer networking etc.
The responsibility for carrying out electrical works in all Government buildings is vested
336
23.2 Estimate for Electrification Works
The estimates are to be prepared by the Assistant Engineer of Electrical Wing of PWD based on
client requirements, but subject to prescribed norms. All estimates shall be accompanied by
dimensioned plans indicating the purpose for which each room is proposed to be used and a
circuit diagram and report with the following details.
i. Location of building
ii. Purpose of the building and nature of work conducted in the building.
iii. Details of light points, fan points, light fittings, fan fittings and plug points etc.
iv. Specification of working accessories and fittings.
v. Details of major appliances, fixed and portable.
vi. Cost of existing installation and fittings (in case of old buildings).
vii. Details of repairs and replacements of electrical installation last effected and approximate cost
(in case of old buildings)
viii. Proximity to electric supply lines and feasibility of service connection.
PWD ENGINEERING MANUAL-2020 CHAPTER - 23
ix. The authority that will look after the maintenance of the building.
No estimate for electrification shall be technically sanctioned unless scrutinised and approved
by the concerned officer of the Electrical Wing. Where lifts are to be provided, it shall be ensured
that the lift well and its approaches are in conformity with the relevant Indian Standard Codes, for
the type and size of lift proposed.
Sometimes it will be necessary to obtain sanction from the inspecting authorities such as
electric inspection division and the Fire Force Department for which necessary scrutiny and
inspection fee will have to be paid. Provision for the same shall be included in the estimate for
preparation of necessary drawings and to make necessary fees to the respective departments. The
charges for the preparation of drawings and connected documents shall be included in a realistic
manner so as to meet the actual expenses incurred for this purpose. The fees are to be paid by the
selected contractor to the concerned department and such amounts shall be reimbursed to
him/them on production of documentary evidence.
To ensure the quality of certain products as well as certain panel assemblies etc., such items
will have to be tested either in any of the CPRI Test Centres or any other institutions approved by
BIS to carry out such tests. In such a case, either the product or the panel assembly will have to be
conveyed to the test centres and necessary testing fees will also have to be paid. It will be the
responsibility of the selected contractor to convey the materials and to pay the required fees. The
department shall reimburse the expenses towards one-time to and fro conveyance to the nearest
Test Centre from the place of manufacture / fabrication, having the facility to conduct the
prescribed test and one-time remittance of fees. If the product or the panel assembly has to be
conveyed and tested further, the subsequent expenses to this effect will be on the contractors
account. If tests are proposed, necessary provision shall be made in the estimate to make
payments for such tests.
The estimate for electrification shall be scrutinised by the competent authority of the Electrical
wing as detailed in the Delegation of powers. In the case of existing buildings under construction
where electrification was not originally contemplated, the electrification estimate will require
both Administrative Sanction and Technical Sanction.
337
23.2.1 New Buildings
In the case of new buildings to be constructed by P.W.D. adequate provision shall be made in the
detailed estimate towards electrification works, subject-to the requirement of the concerned
department and in compliance with the standards and statutory rules mentioned above. The
competent authority in Electrical Wing shall sanction necessary working estimate against any lump
sum provisions made in the estimate. The electrical works shall be done along with the civil works
and completed simultaneously so as to occupy the buildings soon after construction.
CHAPTER - 23
23.2.2 Building of other departments
In the case of existing buildings under the control of other departments on request of the District
Officer of' the concerned department the Assistant Executive Engineer concerned shall arrange to
get the estimate for electrification work prepared and scrutinized by the competent officers of the
Electrical Wing after realizing the centage charges as per rules provided. It shall be ensured that
funds are available for the execution of the work. In the case of deposit works, the approved
estimate will be forwarded to the concerned department for Administrative Sanction and placement
of necessary funds on receipt of which, necessary technical sanction for the estimate will be issued
by the competent authority and the work arranged for execution.
338
23.5. Materials fittings to be provided and stocked by the department for use
in electrification works
Supply of materials and labour shall be combined and work arranged. In unavoidable
circumstances some electrical materials and fittings can be procured directly by the department
with the approval of the Chief Engineer and arrange to have the same used in electrification
works.
The electrification works in Government buildings shall be arranged only through competent
PWD registered electrical contractors.
339
23.08. Maintenance
In an electrical installation, a defect which remains unnoticed, can cause serious and fatal
accidents. It is therefore very necessary that electrical installations in Government buildings are
periodically inspected and minor defects set right then and there. During such inspection, besides
attending to minor repairs, if major repairs are necessary details shall be collected and the
estimates prepared on the basis of such inspection.
The subordinate staff in the electrical wing shall examine the electrical installations in
340
Tool kit must be available with the field staff, which they shall carry with them while they visit a
centre either on routine inspection or on receipt of any notice.
The field staff shall maintain a diary of works attended and submit the same to the Assistant
Engineer periodically for review.
23.09.2. Accidents
In all Industrial establishments notices indicating how to treat persons who have suffered electric
shock shall be displayed at prominent places as per rule 44 of the Indian Electricity Rules.
When accidents are caused due to electricity, information shall be given to the Electrical
Inspector to Government as per Rule 44 A of the Indian Electricity Rules.
341
Chapter 24
24.01.1. General
Quality is an attribute to excellence. According to BSS 4778 (1) quality is totality of features and
characterization of a product or service that bears on its ability to satisfy, the stated or implied
needs. Quality in fact should be an ongoing process of getting the best continuously. Quality is
fundamental to reliability and durability of a product. The quest for quality calls for integrity,
commitment, dedication, knowledge, ethics and team work of persons involved in construction
activity. Quality upgrading is a continuous process of innovations of products, processing and
CHAPTER - 24
adapting control tools. The quality must be consistent. There are two types of quality control (1)
Process control includes control at every stage specifically; and (2) End Control based on end
results. Quality management covers management responsibilities, internal and external control,
tests, acceptance criteria, corrective actions, documentations, transparency etc.
24.02.1 Traffic Diversions and Other Disturbances include abetment of construction noise and
environmental hazards, (Refer EMP for the work).
e) Thorough compaction o the mix in the patch using a small vibratory roller or any other
suitable roller or compacting equipment (or even by the rear wheels of a loaded heavy truck if
none of these are available), soon after laying the mix and finishing to the same level as the
adjoining/surrounding area of the patch.
342
24.03. Bridge Works
To ensure construction of safe, serviceable, durable and economically viable bridges, it is
necessary to have a strategy for management of human skills by way of quality systems defining
quality policy, quality assurance and quality audit. Guidelines on quality systems for road bridges
have been evolved by IRC vide SP 47: 1998 to facilitate preparation of appropriate quality systems
for new bridge projects. Procedures laid down for roads and bridges as per Quality Manuals of the
department issued from time to time can also be followed. For all bridge works tests certificate
from the quality control wing shall be incorporated with the bill.
24.04. Building Works
Quality checks shall be performed at every stage from preparation of building layout,
construction, till the completion of the work. The provisions of part 0, 2 and 3 of National
PWD ENGINEERING MANUAL-2020 CHAPTER - 24
Building Code and the prevailing rules and regulation of the local bodies shall be followed in
preparation of architectural plans and layouts. Also the provisions contained in Section 5A(b) Part
6, Materials workmanship, inspection and testing for concrete works shall be followed. In case of
masonry construction, the details as per National building code Par t 6 Section 4 shall be
followed. Details in Part 7, 8 and 9 of National Building Code relating construction, safety and
building services shall be followed. For test on various building materials the relevant IS Codes
as listed in Part V of National Building Code shall be followed. The Executive Engineers in the
Division / Assistant Executive Engineer in Sub division shall furnish copy of the contract
documents to the Zonal Executive Engineers in the Quality Monitoring Cell. For all works
contractor shall set up field laboratory for conducting mandatory tests.
For all original building works except prequalification work tests results from approved lab/field
lab shall be incorporated in the bill. For the prequalification works certificate from the quality
control wing shall be incorporated with the bill. Procedures laid down for structures as per
Quality Manuals of the department issued from time to time can also be followed.
24.05. Physical requirement of aggregates and requirement of mix for surface wearing course refer
table 2400.
24.06. Technical Audit
The objective of Technical Audit on works is to encourage Departmental officers to pay adequate
level of attention to quality in works. All works shall be subjected to Technical Audit
immediately after physical completion of works through an expert agency. The Executive
Engineers shall report the details along with a copy of abstract of final bill direct to the DCW for
transmitting to the agency appointed for technical audit. Further details for verification by the
Technical Audit agency may be forwarded on demand. The Technical Audit agency shall conduct
detailed checks at every kilometer of road or as required at site including quality of materials
used, thickness of layers, workmanship etc by carrying out mandatory test as per IS, IRC
standards and specifications and quality manual. National building code and other standards and
specifications shall be in the case of building works. Copies of the audit details including findings
shall be forwarded to the DCW who shall promptly call for Action Taken Reports (ATR) from
the Executive Engineer and Superintending Engineer on the rectification works, if any suggested
by the Technical Auditor, under intimation to Govt. Incase there are defects in the quality of
materials, thickness in layers, or workmanship which cannot be rectified, suitable actions against
the contractor and the officers responsible may be initiated under intimation to Govt. However, the
technical audit shall not be linked to payment of contractor‘s regular and final claims as per rules.
343
24.07.1 High Performance Bituminous Materials
The issues related to handling of modified bitumen and mixes at sites are very important. It is
extremely important that modifier is thoroughly blended with bitumen before preparation of mix
so that modified bitumen retains its premium properties. The other precautions shall be as under:
344
i. Preferably be blended at refinery or proper mixing plant.
ii. Product supplied hot in tankers or if supplied in drums shall be agitated in melted conditions
with suitable device.
iii. Penetration, softening point, separation and elastic recovery test shall be conducted at site for a
lot of 10 tonnes.
iv. Multiple heating shall be avoided.
O
v. In case of NRMB, material shall be supplied at 130-150 C and shall be used within 24 hours
of its filling.
emulsions, latex of natural or synthetic origin having extremely fine particles are used for
modification in aqueous phase. The main property of this modifier is their elastic rubber behavior
of residue that allows them to accept and recover from large strains when they are exposed to
temperature. This property of residue from modified emulsion can be observed by elastic
recovery test. The merits of modified emulsions over normal emulsions are many but some are
listed below:
i. High cohesion at medium and high service temperature
ii. Improved performance at low temperature
iii. Improved theological behavior.
iv. Increased plasticity interval
v. Better resistance to ageing.
345
24.07.1.6 Production of Cubical Aggregates
The Indian Road aggregates industry is not so very well organized as in the west. In India, hand
breaking of stones is still continued in many Projects. The ideal is a hammer or a percussion
crusher which by giving an impact blow would shatter the rock boulder into smaller fragments
resulting in uniformly angular or cubical aggregates rather than flaky ones. Depending upon the
magnitude of work involved, an integrated crushing plant should be setup for each Project.
Further, introducing shaping unit after secondary crushing stage can control shape of aggregates.
Crusher type also has effect on shape of aggregates is well known. The shape of aggregates gives
strength to bituminous mixes. If the flakey particles are more, these are likely to be crushed under
traffic and the gradation will be changed which will affect the void sin the mix and subsequently
the strength properties of the mix. The reduced flakiness index, increase the mix strength and
reduces the binder consumption significantly.
CHAPTER - 24
24.07.1.7 Mastic Asphalt
Bitumen mastic, alternatively known as Mastic Asphalt, is a mixture of bitumen, mineral filler
and fine aggregates in suitable proportions designed to yield a void less compact mass. Its
consistency is such that it flows like a viscous fluid at temperatures of around 200 0C, but on
cooling to normal temperature; it solidifies into a dense mass. Thus, its construction required no
compacting effort. Mastic Asphalt is used as wearing course material for heavy- duty pavement,
city street carrying high volume of traffic, bus stops where heavy tangential forces are expected
due to deceleration and acceleration, junctions where cornering stresses are predominant and on
bridge decks. Thin mastics are also used for footpaths.
346
At intersections In car parks
On highways On air port runways
On gradients On unloading areas
24.07.1.10Porous Asphalt
Porous asphalt mix is a thin open graded mix, which has been found to eliminate the danger of
hydroplaning, enhance surface friction, reduces spray, and night glare during wet weather
conditions as porous mixes have inter connected voidsand high permeability. Porous asphalt mixes
are designed so as to form a surfacing with a voids ratio of about 18- 22% after laying and
compaction. With such a high percentage of voids, a network of channels is created in the layer,
capable of carrying off the water that has fallen on the pavement during a rain/shower and
penetrated the surface. The benefits from porous asphalt are:
i. Hydroplaning potential during rainstorm is minimized
ii. Skid resistance at high speeds during wet weather is improved
PWD ENGINEERING MANUAL-2020 CHAPTER - 24
24.07.2 Geosynthetics
Geosynthetic is a revolutionary material for various applications for road works to provide
advantages in the performance and level of service of the specification in which it is used. These
are available in various forms: geotextile, geogrid, geonet, geomembrane, geocomposite, etc for
appropriate applications. Each of these are produced in different forms; for example, the
geotextile can be woven or non-woven type with different gauge of the fabric to meet different
strength requirements in the two perpendicular directions. Geosyntehtics can be used in pavement
structure for various purposes: as separation layer, drainage layer, to enhance tensile strength, to
prevent reflection cracks in bituminous layers, to use in reinforced earth/fill, for consolidation of
clayey layer and many other such applications.
347
24.07.4 Slurry Seal
The slurry seal is a mixture of fine aggregates, Portland cement as filler, bitumen emulsion and
water. It is like a slurry of thick consistency to be laid in a l ayer of 1.5-5 mm thickness to seal
the cracks and to fill any voids left in the surface course. Emulsion of modified bitumen provides
better result. Slurry seal may be used on top of single coat surface dressing. The surface shall be
opened to traffic in about 2 hours.
CHAPTER - 24
specification as that of slurry seal. This can be laid in thickness of 4mm to 16 mm depending on
the present undulations of the surface.
Structurally adequate pavements having the bituminous surface oxidized and with micro- cracks
are most suited for this treatment as preventive maintenance intervention. Micro surfacing have
the following advantages over convention hot mixed techniques:
348
it is no longer popular for higher category of roads as well as city roads. WMM is a mix prepared
from clean crushed aggregates and fine aggregates with proper grading, premixed with water, to
form a dense mass, which is laid by pavers in the required thickness providing the needed camber
and compacted to the finished thickness. WMM so laid is popular nowadays for all types of road
and is a much better specification than WBM in many ways. WMM can be laid in thickness from
75mm to 200mm in one layer depending on the compacting equipment available. WMM
specifications given in clause 406 of MoRTH specification should be used directly.
and requiring no further treatment before placing in the position in which It is to set and harden.
By using RMC, there may be less chances of spillage of concrete and its constituents and the
concrete mix would be of better quality than conventionally mixed concrete, since better quality
control measures are adopted in making RMC is not only a ―quality material‖ but also a ―service‖.
349
is generally characterized by low water/cement ratio and may contain silica fume and fly ash as
mineral admixtures as replacement of cement. The cost of the production of HPC is higher (by16-
32percent) as compared to that of the normal concrete at equivalent mix proportion. However,
there is 20 to 50 percent increase in the compressive and flexural strength as compared to
conventional or normal concrete. Further, the benefits accrued from the use of HPC, such as low
maintenance cost. Longer life of the structure, higher strength, trouble free service etc, shall
compensate the high initial cost of the HPC. Possible benefits include:
i. Reduced construction times
ii. For rapid repair of distressed pavements and bridges
iii. Chloride resistance
iv. Reduced Permeability
v. Reduced corrosion of steel bars
CHAPTER - 24
vi. Improved durability, and service ability, and
vii. Enhancement of the life of concrete pavements and bridges.
350
equipped laboratory for that purpose to prove the efficacy of the same as per available
specification. If it is not used anywhere in India under similar conditions, it must be used first for
experimental purpose as test sections of the actual road for evaluation under normal traffic. For
such experimentation, the manufacturer of the material should also contribute to fund the study.
Such study shall comply to the following equipments.
i. The quality control and quality assurance for such experimental (construction) sites shall be
more stringent.
ii. The proper plan for monitoring the performance of the road be made and data recorded over
sufficiently long period to justify the use of such materials.
iii. The proper record of planning and design of the experimental section is also to be maintained
so as to replicate and to develop design methodology after the successful experimentation.
iv. The manufacturer of the material should provide minimum period (normal performance)
guarantee for the performance of the material under experimentation.
PWD ENGINEERING MANUAL-2020 CHAPTER - 24
351
24.07.14 Methods of Measuring Distress
The pavement performance is largely defined by evaluation in the following categories.
Roughness / Unevenness Surface distress
Skid resistance
Structural evaluation – Deflection
Roughness / Unevenness
Pavement roughness or unevenness is generally defined as an expression of irregularities in the
pavement surface that adversely affect the ride quality of a vehicle (and thus the user). Roughness is
an important pavement characteristic because it affects not only ride quality but also vehicle delay
costs, fuel consumption and maintenance costs.
CHAPTER - 24
set of road users can be asked to rate the riding quality on a 0-5 scale as shown below: Present
serviceability Rating (as suggested in AASHTO on a scale of 0-5) can be worked out from these
subjective ratings.
Dipstick Profiler
This instrument can record the pavement profile measurement very accurately. The device
records 10 to 15 readings per minute. Software analysis provides a profile accurate to 0.127 mm.
However, measurements by dipstick are time consuming and therefore, it is commonly used to
measure a profile for calibration of more complex instruments.
Profilographs
Profilographs have a sensing wheel, mounted to provide for free vertical movement at the center
of the frame. The deviation against a reference plane, established from the profilograph frame, is
recorded on graph paper from the motion of the sensing wheel. Profilographs can detect very
slight surface deviations or undulations up to about 6 m in length. However, they are not practical
for network condition surveys due to slow speed.
352
fifth when bump integrator that is normally used in India also falls in this category. The advantage
of these RTRRMs is that they can record the road roughness at speeds upto 80 km/hr. Since no
two RTRRMs are exactly alike, it is necessary to convert measures (unevenness index) to a
standard common international scale.
To provide a common quantitative basis on which the different measures of roughness can be
compared, the International Roughness Index (IRI) was developed by World Bank. The IRI
summarises the longitudinal surface profile in the wheel path and the computed from surface
elevation data collected by either topographic survey or a mechanical profilometer or a dipstick.
IRI is reported in units of m/km.
All the RTRRMs need to be calibrated by measuring the unevenness of a standard stretch for
which IRI value are known.
Profile devices
These devices very accurately can establish the longitudinal profile of a pavement by either using
contact or non-contact sensor systems. Then on-contact systems use laser/ultrasonic devices form
PWD ENGINEERING MANUAL-2020 CHAPTER - 24
aping the road profile. These profilometers are expensive and are normally used to calibrate
RTRRMs.
353
such as non-contact (laser) profilometers for mapping longitudinal as well as transverse pavement
profile, distance measuring instrument and computer workstations for processing the data are
fitted. Automatic Road Analyzer and Laser Road Surface Tester fall in this category.
Using integrated pavement analysis units one can obtain the following measurements.
● Roughness
● Distress(cracking, rut depth)
● Gradients, camber, curvature
● Pavement texture
The rating suggested by IRC in its guidelines or maintenance management of primary, a
secondary and urban road is given in the following table:
CHAPTER - 24
Defects Range of Distress
Rating 1 2 3 4 5
Condition Very Poor Fair Good Very
Poor Good
(Source: Guidelines for Maintenance Management of Primary, Secondary and Urban
Roads, IRC, 2004)
354
24.07.16 Skid Resistance
Skid resistance is the force developed when a tyre that is prevented from rotating slides along the
pavement surface (Highway Research Board, 1972). Skid resistance is an important pavement
evaluation parameter because inadequate skid resistance will lead to higher incidences of skid
related accidents. Skid resistance depends on pavement surface texture. Skid resistance changes
over time.
Typically it increases in the first two years following construction as the roadway is worn away
by traffic and rough aggregate surfaces become exposed, and then decreases over the remaining
pavement life as aggregates become more polished.
Skid resistance is generally quantified using some form of friction measurement such as a friction
factor or skid number.
Friction factor (like a coefficient of friction) : = F/L Skid number: SN = 100 (f)
PWD ENGINEERING MANUAL-2020 CHAPTER - 24
It is a dynamic pendulum impact type tester for measuring the resistance offered by a surface
under test. It is used for measuring spot value of surface friction at representative locations.
Though, it provides good information on the skid resistance of the pavement, it cannot provide
data with different speeds.
This method uses a locked wheel skidding along the tested surface to measure friction resistance.
It is possible to measure skid resistance at different speeds in this method. The spin up tester
A spin up tester has the same basic setup as a locked wheel tester but operates in an opposite
manner. For a sp in up tester, the vehicle (or trailer) is brought to the desired testing speed
(typically 64 km/hr) and a locked test wheel is lowered to the pavement surface. The test wheel
braking system is then released and the test wheel is allowed to ―spin up‖ to normal travelling
speed due to its contact with the pavement. The friction force can be computed by knowing the
test wheel‘s moment of inertia and its rotational acceleration. This avoids the use of costly force
measuring equipment.
In this method the pavement skid resistance is correlated with the pavement macro texture. By
measuring the pavement texture and using the established correlation between the macro texture
and the skid resistance, the skid resistance is obtained.
355
Deflection
Pavement surface deflection measurements are the primary means of evaluating a flexible
pavement structure. Although other measurements can be made that reflect (to some degree) a
pavements structural condition, surface deflection is an important pavement evaluation method
because the magnitude and shape of pavement deflection is a function of traffic (type and
volume), pavement structural section, temperature affecting the pavement structure and moisture
affecting the pavement structure. Deflection measurements can be used in back calculation
methods to determine pavement structural layer stiffness and the subgrade resilient modulus.
Furthermore, pavement deflection measurements are non-destructive destructive in nature which
adds on to the overall viability of usage.
Measurement Technique
CHAPTER - 24
The pavement surface deflections can be measured using either static deflection equipment or
impact load deflection devices. Static deflection equipment measure pavement deflection in
response to a static load. Benkelman Beam falls in this category. Impact load devices deliver a
transient impulse load to the pavement surface. The subsequent pavement response (deflection
basin) is measured by a series of sensors. The most common type of equipment is the falling
weight deflectometer (FWD)
Benkelman Beam
Is a simple device that operates on the lever arm principle. The Benkelman Beam is used with a
loaded truck – typically 80 KN on a single axle with dual tires inflated to 480 to 550 kPa. Placing
356
24.07.16 Intervention Criteria
Based on the objective/subjective rating of the pavement distress one can adopt a
maintenance strategy to bring back the distress ratings to an acceptable level. This kind of
maintenance termed, as pavement condition responsive maintenance is very effective when
compared to the traditional scheduled maintenance approach.
In order to determine the intervention criteria with respect to various distress indicators, it
is necessary to classify the roads. For the purpose of fixing the intervention criteria and for
determining the level of pavement evaluation to be adopted the following classification.
Category-I : All State Highways and City Roads Category-II : Major District Roads
Category-III: Other District Roads
lN City
o Roads
357
In the long run, the data on Roughness, surface distress, skid resistance and structural
evaluation should be collected using suitable instruments as explained in Annexure 12-A in an
objective manner. At a network level, as speed of collection of such data is also an important
factor, integrated analysis units may be used for collecting data on pavement distress and FWD
may be used for structural evaluation. Ultimately, an objective system of road performance
evaluation should be in place as a part of the Road Maintenance Management System. In the
mean time a qualitative approach of pavement performance evaluation could be attempted.
In the mean time- A detailed qualitative rating system on each and every parameter Table-2 may
be tried for State Highway & MDR.
This pavement performance evaluation when implemented in its full form should become
part of a road maintenance management system, which will guide in deciding the best
maintenance strategy.
The data on pavement performance evaluation could be used for arriving at workable
CHAPTER - 24
quality assurance and quality control criteria.
Table 2 : RATING OF PAVEMNT SURFACE
Name of Road: Rater:
Section: Date and Time:
Number of Traffic Lanes:
Distress Rating Scale
Cracking G OO D F AI R P OO R
5 4 3 2 1 0
Patching G O OD F A IR P O OR
5 4 3 2 1 0
Raveling G O OD F A IR P O OR
5 4 3 2 1 0
Bleeding G O OD F A IR P O OR
5 4 3 2 1 0
358
Potholes GOOD F A IR P O OR
5 4 3 2 1 0
Riding G OO D F AI R P OO R
Quality
5 4 3 2 1 0
Explanatory Notes
Cracking : Good: Generally un-cracked
PWD ENGINEERING MANUAL-2020 CHAPTER - 24
Fair: Single crack along the when path or localized very fine cracking.
Poor: Extensive cracking
Rutting Good: Deformation along wheel path up to10mm
Fair: Deformation along when path between 10 and 20mm Poor:
Deformation along wheel path above20mm
Patching : Good: No patching or potholes or localized depressions observed
Fair: Localized patching or potholes observed at some places
Poor: Extensive patching or potholes spread all along the section.
Raveling : Good: No raveling or stripping observed
Fair: Stripping confined to localized pockets but exposed aggregate
remain stable Poor: Aggregate surface is exposed extensively and
extensive raveling observed.
Bleeding: Good: No bleedingobserved
Fair: Bleeding confined to a few localized patches Poor: Extensive
bleeding spread all along the section
Riding Quality Good: Comfortable travel inside the vehicle
Fair: Generally comfortable with occasional bumps
Poor: Uncomfortable ride with frequent bumps.
Simple qualitative rating shown in tables below could be used for other roads.
359
:
CHAPTER - 24
The PCI then assessed for each kilometer based on normal driving speed as under:
Normal Driving Speed PCI
Over 50 km/hr 5
40 to 50 km/hr 4
30 to 40 km/hr 3
20 to 30 km/hr 2
Less than 20 km/hr 1
360
moving rubber tyres start grinding the surface. This grinding results in to further loosening of
other metal pieces in the pavement and with the sucking and churning effect of traffic the whole
surface starts raveling. Water accumulated in depressions and pot holes continuously supplies
moisture to lower layers weakening the whole structure for the pavement. Prolonged contact of
moisture affects all the components of the pavement.
361
2) Due to creep if the edges of the pavement are higher than the adjoining portion they
should either be chopped out or leveling courses should be so adjusted that the finished
surface is at desired camber.
3) Existing drainage system should be thoroughly checked by some experienced and
responsible person. Any deficiencies noted, modifications suggested etc should be duly
undertaken on priority, preferably before main work of pavement is taken up.
4) Leaking pipes, spring flows, chronic damage spots and cracked up portions should be
investigated and proper corrective measure should be taken before the main work.
5) If adjoining plots are higher than the main road they should be trimmed. Alternatively
a cattle trap type drain should be provided and joined to SWD system.
6) Edge gutter/gully, inlet etc should be examined for their levels and clearance.
7) Provision of shoulder drains should be made where soft shoulders exist. Similarly incase
CHAPTER - 24
of roads in cutting and at chronic spots provision of subsoil drains should be made.
(Appendix2407C&D)
8) At the end of the flyovers and ramps water flowing along the slopes should be arrested
and diverted to SWD system by providing aslotted/ cattle trap type drain at the foot of
the slope.
9) Water flowing through water spouts of the flyovers should be lead through suitable pipes
to the ground chambers and connected to SWD.
10) Wearing coat on the flyover and bridges should be 15 to 20 cm short from the Kerbs/
Devri stones. The notch formed will serve as a drainage gully. This will avoid stagnation
on the bridge decking and avoid damages to wearing coat.
362
24.07.23. Work Zone Traffic Management
24.07.23.1General
The purpose of any work zone Traffic Management Plan (TMP) is to ensure that the
impacts of road works on the public domain, in particular with respect to temporary
interruptions to vehicular and pedestrian traffic, are considered by the authority. The TMP must
ensure safety to the workers, pedestrians and vehicle users at all times, and that the delay due
to interruptions is minimized. The TMP should also ensure that the minimum required time is
made available to the roadwork before the road is opened for traffic.
are being under taken by the contractor. Flexible pavement maintenance works at present are
carried out during night time when the traffic volume levels are negligible. No specific traffic
management measures are being implemented for these road maintenance works. One of the
important problems observed in the case of road resurfacing works is that these works are
opened to traffic much earlier than the minimum required curing period. A proposer work zone
traffic management plan will ensure the availability of minimum required time for a roadwork
before it is opened to traffic, safety at the work zone and minimum delay to the road users.
Therefore, it is suggested the PWD should prepare and implement a traffic management plan
for all road works. Particularly attention should be paid to requirements for smooth and safe
pedestrian flow.
Transition Area
When traffic needs to be redirected from normal lanes, channelization devices are used
to move traffic to a new path. This redirection should occur at the beginning of the transition
area. Transition areas usually involve the use of roadway tapers. Tapers are created using a
series of channelizing devices or pavement markings placed out of or into the normal traffic
path. There are several types of tapers; merging, shifting, shoulder downstream, and one –lane
/ two–way.
Activity Area
Actual road works is conducted within the activity area. This area is made up of the
worm space, the traffic space, and optional buffer spaces. The works pace is that portion of the
roadway closed to traffic and set aside for workers, equipments, and material. The work space
can be stationery or move as work is conducted. The traffic space is the portion of the roadway
in which traffic is routed through the activity area. Buffer space is intended to provide an area
363
of separation and security between the work site and traffic. The buffer space can be placed
longitude in all y and/or laterally to the work area. Buffer spaces are optional.
Termination Area
The termination area is used to return traffic to the normal traffic path. In this area,
tapers can be used to achiever routing of the traffic back to the normal traffic lanes. The
termination area extends from the downstream end of the work area to an ―END OF ROAD
WORK‖ sign if posted.
All these four components are shown for a typical work zone in Fig. 18.1 wherein one
lane is closed for maintenance.
CHAPTER - 24
A suitable strategy from the ones mentioned below should be adopted for traffic
control at work zones after assessing the impact.
Lane Constriction ie., reducing the width of one or more lanes to retain the number of lanes
normally available. Lane constriction is usually the least disruptive to traffic but is applicable
only if the work area is predominantly outside the normal traffic lanes and if should are
available.
Lane Closure ie., one or more traffic lanes are closed after determining that serious
congestion will not result based on a capacity analysis.
Shared right – of –way ie., utilizing one lane for both directions of traffic flow with flaggers
or signals to coordinate the two directions of traffic or possibly traffic control signing alonefor
Use of the shoulder or median, ie., the existing shoulder or median acts as a temporary
traffic lane Where shoulder lane is used for diverting the traffic, shoulders should be
strengthened to take the regular traffic during the duration of closure. Earthen shoulders for
the purpose strengthening shoulder be provided with 150mm thick granular base covered with
bituminous surface dressing or carpet or mix seal surface.
Detour, ie, total closure of the roadway (one or both directions) and rerouting traffic to
existing alternate facilities.
364
implementation of the strategy. Capacity deficiency due to the road work is overcome by
implementing traffic management strategies. The impact of each strategy is worked out. Simple
speed flow curves could be used to work out the reduction in speed for each of the strategies.
The best strategy that has minimum adverse impacts could be selected.
The work zone traffic management plan should also identify any interruption to bus services or
bus stops and provide details of any measure to ensure continued access to public transport.
Existing bus routes will be maintained as far as is reasonably practicable and any diversions
necessary will be well publicized. The TMP should also ensure that satisfactory access for
emergency vehicles such as ambulances, fire fighting vehicles etc is not impeded.
Emergency vehicles require reasonable access to every property, along the construction route
all times.
Signs
Temporary traffic control zone signs are similar in their communication objectives to
all other traffic signs. Leathering‘s, temporary traffic control signs are categorized as
regulatory signs, warning signs, and informatory signs. Signs used at night need to be retro-
reflectorized or illuminated to achieve a night time visibility that is comparable to that in day
light. The illumination can be internal or external; street or highway lighting is not usually
adequate to satisfy this requirement. Signs used in temporary traffic control zones are often
relocated and subject to considerable wear and tear during handling. Therefore, they should be
routinely inspected for cleanliness, visibility, excess wear, and proper positioning and should
be replaced if necessary. Descriptions of specific signs are available in IRC: 67- 2001.
Arrow Displays
An arrow display is a sign with a matrix of elements. The matrix, capable of with either
flashing or sequential displays, provides the driver with additional warning or information. The
direction of movement of vehicle at diversions could be effectively indicated by these arrows.
Channelizing Devices
Channelizing devices warn and guide drivers through work activities in or near the
roadway and protect workers in the temporary traffic control zone. Types of channelizing
devices include: cones, tubular markers, vertical panels, drums, barricades, portable barriers,
and temporary raised islands. Each device is subject to specific requirements as to size, color,
stripe patterns and use of retro reflectorized material.
365
Pavement Markings
Pavement markings provided in a temporary traffic control zone must be comparable to
the markings maintained along adjacent roadways. Pre-existing markings need to be evaluated
for their potential to misguide vehicles Any such markings need to be thoroughly removed (black
spray paint is not satisfactory as in certain lighting it can appear to motorists as an existing
marking). All markings and devices used to delineate vehicle paths and pedestrian routes should
be evaluated in differing lighting and weather conditions to assess the risk of misguidance.
Descriptions of pavement markings are available in IRC: 35-1997.
Lighting Devices
It is often necessary to supplement retro reflectorized signs, barriers and channelizing devices
with lighting devices at night. Floodlights should be used to illuminate flagger stations,
CHAPTER - 24
equipments crossings, and other work areas where existing light is not adequate. The
floodlights should not be used where they may create a disabling glare for drivers. A flashing
beacon is a flashing yellow light used to alert drivers to special road conditions. Steady –
burning lamps placed in a line on channelizing devices are effective in delineating the proper
vehicle path through a temporary traffic control zone. Because warning lights attract a driver‘s
attention, they are used to help drivers identify road hazards.
Other Devices
Other devices include impact absorbing attenuators, portable barriers, temporary traffic
signals, rumble strips, screens and lane dividers. Impact attenuators, which may be stationary
366
same time.
10) In the event that sidewalks on both sides of the street are closed, pedestrians should be
guided around the construction site.
11) Reflectorized traffic control devices are of little value of pedestrians.
Warning lights should be used to delineate the pedestrians‘ pathway and to
mark hazards as appropriate.
12) Particular attention should be given to avoid inconvenience to senior citizens
and handicapped pedestrians.
efforts to reduce traffic through the temporary traffic control zone; and Closing
roads.
367
Quality Control Coordinator (SQCC), an officer of S E rank supported by two
executive engineers (Each for Jammu and Kashmir), two Assistant executive
engineers (Each for Jammu and Kashmir),and two Assistant engineers (Each for
Jammu and Kashmir). The post of which can be made available out of existing
sanctioned strength under deputation category. The system shall be conceived and
designed on the pattern of PMGSY deptt., where the pattern has been successfully
implemented and yielded encouraging results. The SQCC shall be independently
working under the direct control of Administrative Secretary/DCW/Chief Engineer
DIQC. He shall be deputing State Quality Monitors (SQM) while as State Quality
Auditors (SQA) shall be deputed by the Administrative Secretary/DCW to various
work sites for monitoring of quality control of works as per the guidelines. The SQAs
shall be drawn from retired CEs/SEs while as SQMs shall be drawn from retired
SEs/EEs and enrolled with SQCC whose performance shall also be audited
periodically as per the guidelines. The Honorarium for SQAs/SQMs will be met out
of the contingency component of the Capex Budget. The Honorarium pattern, present
in vogue in PMGSY is proposed to be adopted.
24.11. Three tier set up for quality management system
The three-tier quality management mechanism comprises:I
a. Tier I Quality control shall be conducted by the in-house departmental engineers
at various levels.
b. Tier II Quality control shall be conducted by a pool of retired SE/EE engineers of
the state/UT called as State Quality Monitors (SQM) and controlled by the State
Quality Control Coordinator (SQCC) of the rank of SE to be appointed under
DCW on the pattern of SQC in PMGSY deptt.
c. Tier III Quality control shall be conducted by a pool of retired Chief
Engineers/SE, called as State Quality Auditors (SQA) working under the
Development Commissioner Works who will be deputing the SQAs for tier three
supervision and audit of the works.
24.11.1 First tier
The Executive Engineer is envisaged as a first tier of quality management with the
primary function of construction supervision and quality control. The quality
management functions of the Executive Engineer shall include the following:
(i) Preparation of realistic detailed project report (DPR) on the basis of detailed drawings
and design, with adequate attention to investigations and pre-construction activities
which are essential for proper design and estimation of the project as per standard IS,
IRC codes of practice and guidelines issued by the state PW R&B department for time
to time.
(ii) Preparation of bid documents and effective selection process for procurement of
works, based on proven capacity and ability of the contractors in accordance with the
relevant guidelines.
(a) Contractors have brought the necessary machinery and equipment to site.
(c) A comprehensive CPM/PERT charts/Bar charts reflecting all the activities of the work
along with their critical time of completion shall be prepared by the contractor and
approved by the engineer incharge.
(d) The work programme has been approved.
368
(iv) Supervising Site/off Site, Quality Control arrangements including materials and
workmanship, primarily through testing.
(v) The following frequency of inspection visits to site by Executive Engineer staff is
recommended while the work is in progress:
(vi) Taking timely action to ensure replacement of defective material and rectification of
defective workmanship.
(vii) To ensure effective Quality Control on materials and workmanship, the following
standard procedure shall be followed:
(viii) A monthly return of the tests shall be submitted in the prescribed proforma
by the AEE to the EE in the first week of every month. The EE will review this return
regularly to see that the Quality Control tests are being performed at the desired
frequency and with the desired accuracy. The EE will also verify that the Non-
Conformance Reports (NCR) are being issued by the AEE whenever non-
conformance occurs and the Contractor is taking action promptly on the NCR.
Payment to the Contractor shall be regulated by the EE as per the returns of the
Quality Control tests. Any deviation will be the personal responsibility of the EE.
(ix) Quality Control Registers shall be maintained for all works issued by the
divisional office for recording of test results and Non conformity of quality in the
work. The NCR, (Non-Conformance Report) shall be submitted to the executive
engineer within 3 working days.
(x) The SE in charge of the circle and the Chief Engineer having jurisdiction are
responsible for the proper functioning of the Executive Engineer as part of their
normal administrative duties. Their inspection and quality testing supervision will
therefore be counted as part of effective supervision of the first tier of quality
management (and not as a second tier of quality management). The SE/CE shall:
a. During his visits to the work, oversee the operations of the quality control testing
procedure and record his observations in the Quality Control Register. The SE/ CE
will also verify that the Non-Conformance Reports are issued in time and action is
being taken by Contractor promptly.
b. Prepare Inspection Reports which shall be sent to the Executive Engineer for
taking remedial action.
The second tier of quality management shall be headed by the State Quality Control
Coordinator (SQCC). Who will be directly reporting to DCW.
The first tier of quality management has the primary function of quality control
through enforcement of technical standards and quality control requirements through
regular testing, close supervision and inspection. While as the function of the second
tier quality management is to inspect the works and ensure that the Quality
Management System at the site is functioning satisfactorily and suggest possible
improvements where required. For this, they may be required to carry out and report:
369
i) Independent quality tests in accordance with the standard codal requirements and to
verify that the quality management system is achieving its intended objectives.
ii) The State Quality Monitors shall carry out inspections at appropriate stages of work
under progress.
iii) SQMs shall also help the field engineers in developing a scientific working
environment in execution of the works.
iv) Observations of SQMs shall be placed on JKPWDOMS website so that these are
available for viewing by the stakeholders.
v) While deciding upon the stages of inspection by SQMs All Executive Engineers and
Assistant executive engineer shall be responsible for getting the works inspected at
critical stages of progress of work and ensure minimum no of inspection as per the
guidelines.
vi) All works shall be inspected by the SQM as per the prescribed table. However, the
inspections shall not be spaced beyond three working months. In addition, the
Executive Engineer can request for an out of plan inspection depending upon the
requirement of work at site.
24.11.2.1 Reporting Methodology and Performance Evaluation
Under the Second Tier of Quality Monitoring, the following guidelines for reporting
methodology and process of performance evaluation shall be adopted by the
Department.
(a) The SQCC shall draw up programmes for inspection by SQMs in such a way that
every work is inspected as per the schedule of visits as per the manual. The first two
inspections of every work should be carried out during the execution of work spaced
at least three months apart and the last inspection should be carried out on the
completion of work or at the finishing stage but in no case later than one month after
completion of work.
(b) The schedule should generally be drawn up every month for various works. However
every work shall be visited as per the above schedule not spaced more than three
months apart.
(c) The SQCC shall ensure inspection of works by the SQMs strictly as per provisions of
these guidelines.
The observations shall be recorded and reported by the SQMs in prescribed formats.
24.11.2.2 Grading of Works:
i) Upon inspection of work, the quality of every item and sub item of work would be
evaluated by the SQM on the basis of methods of observations prescribed in
Annexure 2. The grading of work would be done with an intention to quantify the
observations showing level of satisfaction in relation to prescribed specifications
of the work/item under observation. The grading would be recorded in every item and
abstracted at appropriate space provided in relevant format.
ii) The objective of the grading is to indicate to the Executive Engineer that whether the
material or workmanship is acceptable, or unacceptable. If the item is unacceptable,
the improvement could be done by either replacement of the entire material/portion of
work or by rectification in workmanship or material. Therefore, based on the type of
item and method of observation, each item/ sub-item of work would be graded in any
370
of the categories indicated as ‗Satisfactory (S)’, ‘Satisfactory Requiring
Improvement (SRI)’ or ‘Unsatisfactory (U)’ as prescribed in format.
iii) Based on grading, the Executive Engineer shall take action for rectification of defect,
therefore, it is very important to record the defect as well as the suggestive method by
which the rectification could be done. The SQM shall record, in the observation
sheet, the grade as well as clear and express reasons for grading the item of work
as ‗SRI‘ or ‗U‘ along with his suggestions for improvement. The reasons and
suggestions shall be recorded clearly in such a way that there are no ambiguities or
contradictions with observations in other items.
24.11.3 Third tier
The third tier of quality management shall compose of State Quality Auditors (SQAs)
who shall be working directly under the control of Administrative Secretary/DCW.
The objective of this tier is to monitor the quality of works executed by the
department to ensure that the works conform to standards and to see whether the
quality management mechanism in place is effective. The role of this tier shall be to
audit and inspect the works and provide guidance to the field engineers. SQAs shall
also help in developing a systemic and scientific working environment in the
department besides identifying the shortcomings in the system and provide a feedback
to the department for rectification of the same. The role of SQA shall be more of a
teacher than that of an examiner.
i) Conduct Independent quality tests in accordance with the standard codal requirements
and to verify that the quality management system is achieving its intended objectives.
ii) Carry out inspections at appropriate stages of work under progress.
iii) Help the field engineers in developing a scientific working environment in execution
of the works.
iv) Observations of SQAs shall be placed on JKPWDOMS website so that these are
available for viewing by the stakeholders.
v) While deciding upon the stages of inspection by SQAs all Executive Engineers and
Assistant executive engineer shall be responsible for getting the works inspected as
per the schedule during the progress of work.
vi) All works shall be inspected by the SQA as per the prescribed table. In addition, the
SQCC can request for an out of plan inspection depending upon the requirement of
work at site.
24.11.3.1 Reporting Methodology and Performance Evaluation
Under the Third Tier of Quality Monitoring, the following guidelines for reporting
methodology and process of performance evaluation shall be adopted by the
Department.
Organizing the Inspections:
The DWC shall take the following action for organizing inspections under this tier:
i) The DCW shall draw up programmes for inspection by SQAs in such a way that
works to be inspected by the SQAs shall be critically selected so that the quality of
works is randomly cross checked at a higher level.
ii) The schedule should generally be drawn up every month for various works to be
inspected by the SQAs. However, every work shall be visited as per the above
schedule.
371
iii) The DCW shall ensure inspection of works by the SQAs strictly as per provisions of
these guidelines.
24.12 Independent External Monitoring
24.12.1 Role and Duties of IEMs (Independent External Monitoring)
The IEMs appointed by the Competent Authority would have access to all contract
documents, whenever required, only for large scale works.
It would be desirable to have structured meetings of the IEMs with the Head of the
Department of the Organization on a quarterly basis including an annual meeting to discuss
/ review the information on tenders awarded during the previous quarter. Additional
sittings, however, can be held as per requirement.
The IEMs would examine all complaints received by them and give their
recommendations/views to the Head of the Department of the Organization, at the
earliest. They may also send their report directly to the Vigilance Organisation, in case
of suspicion of serious irregularities requiring legal/administrative action. IEMs are
expected to tender their advice on the complaints within 10 days as far as possible.
For ensuring the desired transparency and objectivity in dealing with the complaints
arising out of any tendering process, the matter should be examined by the full panel of
IEMs jointly as far as possible, who would look into the records, conduct an
investigation, and submit their joint recommendations to the Management.
IEM should examine the process integrity, they are not expected to concern themselves
with fixing of responsibility of officers. Complaints alleging mala-fide on the part of
any officer of the organization should be looked into by the VO of the concerned
organisation.
The role of IEMs is advisory, would not be legally binding and it is restricted to
resolving issues raised by an intending bidder regarding any aspect of the tender which
allegedly restricts competition or bias towards some bidders. At the same time, it must
be understood that IEMs are not consultants to the Management. Their role is
independent in nature and the advice once tendered would not be subject to review at
the request of the organization.
Issues like warranty / guarantee etc. should be outside the purview of IEMs.
All IEMs should sign no disclosure agreements with the organization in which they are
appointed. They would also be required to sign a declaration of absence of conflict of
interest.
A person acting as an IEM shall not be debarred from taking up other assignments such
as consultancy with other organizations or agencies subject to his declaring that his /
her additional assignment does not involve any conflict of interest with existing
assignment. In case of any conflict of interest arising at a later date from an entity
wherein he is or has been a consultant, the IEM should inform the Head of the
Department of the Organization and recluse himself/herself from that case.
All organizations may provide secretarial assistance to IEC for rendering his/her job as
IEM. In case of any misconduct by an IEM, the Head of the Department of the
Organization should bring it to the notice of the Competent Authority detailing the
specific misconduct for appropriate action at it‘s end.
372
The role of the VO of the organization shall remain unaffected by the presence of IEMs.
The choice of IEM should be restricted to officials from the government and public sector
undertakings who have retired from positions of the leveI of Additional Secretary to the
Government of India and above or equivalent pay scale, and for Public Sector Undertakings,
Board level officers in Schedule A Companies, Public Sector Banks, Insurance Companies and
Financial Institutions. Officers of the Armed Forces who have retired from the rank equivalent of
Lt. General and above may also be considered for appointment.
Prior appointment as IEM the Head of the Department of the Organization has to forward a panel
of suitable persons to the Competent Authority. This panel may include those who are in the
panel maintained by the Vigilance Organization or they may propose names of other suitable
persons for appointment as IEM. While forwarding the panel of suitable persons, the
Organization would enclose detailed bio-data in respect of all names proposed. The details would
include postings during the last ten years before superannuation, special achievements,
experience, etc., in Go vernment sector. It is desirable that the persons proposed possess domain
experience of the PSU activities or the relevant field with which they may be required to deal.
The Commission would not consider the name of an officer / executive who is either serving or
who has retired from the same organization to be an IEM in that organization, although they may
have served in the top management.
The appointment of IEM would be for an initial tenure of three years and could be extended for
another term of two years on a request received by the Competent Authority from the
organization appointing the IEM. An IEM can have a maximum tenure of 5 years in an
organization with an initial term of three years and another term of two years.
Age should not be wore than 70 years at the time of appointment / extension of tenure.
Remuneration payable to the IEMs by the organization concerned would be equivalent to that
admissible to an Independent Director in the organization and in any case should not exceed Rs.
20,000/- per sitting. Remuneration being paid to existing IEMs may not be changed till the
termination of their tenure.
The terms and conditions of appointment, including the remuneration payable to the IEMs,
should not be included in the Integrity Pact or the NIT. This may be communicated individually
to the IEMs concerned.
373
Chapter 25
25.1. Asset Management
25.1.1. Introduction
Maintenance of all the assets is far more important than continuous creation of new assets
without provision for proper upkeep. Currently the backlog of maintenance activities has caused
the deterioration of structures and most of them have to be reconstructed. It is vital to the
economy of the UT that timely maintenance is carried out.
The maintenance activities should be properly planned and implemented periodically. For
this all the assets shall be recorded in registers and regular inspection and verification done.
CHAPTER - 25
25.1.2. Land Plans & Land Records
The land plans & land records are the basic documents of property right of the Govt.
/Department. Therefore, land plan showing boundaries of the area etc. should be kept on record
& updated from time to time. Sometimes part of Govt. land is given on lease to some private
parties or corporations. In such cases lease proposals are approved at Govt. level & lease
agreements are signed at Executive engineer‘s level. The Ex. Engineer has no power to give any
piece of Govt. land to any party without permission from the competent authority. In all such
cases of leases of Govt. property a lease register & agreement copies of lease deed should be
maintained by the Executive Engineer for record, reference, renewal or termination of lease.
25.1.3. Encroachments
The encroachments generally occur on Government land of buildings or adjoining the
roads/ bridges. Such encroachments should be removed with the help of revenue and police
authorities then and there.
374
bridges etc. should be taken on record as per provisions in section.3019.3. Before dismantling
any old building, permission of the competent authority should be obtained for dismantling and
to write off the structure from Building Register as per section 2901.1.3. In case of culverts the
same shall be noted in the concerned register as per section 2702 and bridges as per section 2802.
to mobilise support of relief/ rescue from local police/ revenue officers. The detailed reporting
should follow later on. In case of major accidents, the matter is to be reported.
375
Chapter 26
26.1. Maintenance of Roads
26.1.1. General
The maintenance of road is an elaborate activity and includes maintenance of basic records,
maintenance of structures and tools & plants required including carrying out inspection of all the
structures at regular prescribed intervals. While maintenance of State Highways and Major District
Roads is the responsibility of PWD, the J&K Government acts as the agent of the Union
CHAPTER - 26
Government for carrying out maintenance works on National Highways. Remaining all roads are to
be maintained by the P. W D. if it does not belong to any organization/authority/private party. Even
when roads are constructed in highest quality, over a period of time, they will show signs of distress
due to the effects of increase in vehicular traffic, climatic effects and other reasons.
Traffic on most of the roads have exceeded their capacities, and do not cater to the needs of
modern multi axle heavily loaded vehicles. Moreover, reclassification to higher categories is done
without properly designed upgradations. Hence, this has resulted in deterioration of roads which in
turn causes loss to the economy by way of increased fuel consumption, wear and tear to vehicles,
accident costs and increased travel times. The need of the hour is to create a road network of desired
level of service for which upgradation of existing roads shall be done in a phased manner.
376
Chief Engineer shall finalize actual fund requirement based on output from Road Maintenance
Management System and this shall be transmitted to the Finance Department before 31stDecember
every year. Chief Engineer shall allocate the maintenance fund to each Division at the start of every
financial year.
The Executive Engineer shall arrange and execute the maintenance work based on fund
allocation as regular maintenance contract or as Fixed Term Maintenance Contract. To enable this,
the Assistant Executive Engineer shall prepare detailed maintenance estimate of the identified roads.
The specifications for maintenance shall be as per Section 3000 of specification for road and bridge
works of MoRTH and shall apply to all items of road maintenance works as required to carry out
under the contract or as directed by the Executive Engineer. The works shall be carried out in
conformity with the relevant specifications to the required level, grade and lines using approved
materials. The works shall be carried out using light duty machinery or manual means provided the
quality of the end product does not suffer. In execution of maintenance works, a reference is made to
the IRC publications Manual for Construction and Supervision of Bituminous works and Code of
PWD ENGINEERING MANUAL-2020 CHAPTER - 26
Practice for Maintenance for Bituminous Surfaces of Highways, IRC 82 for guidance and compliance
wherever applicable. Wherever the specification is not clear, good engineering practice shall be
adopted in the construction to the satisfaction of the Executive Engineer.
377
(a) Ordinary Repairs
(b) Renewal of Surface (periodic maintenance)
(c) Special repairs.
Maintenance of roads shall be as per section 3000 of Specification for Road and Bridge Works
Published by MoRTH. For specific treatment of surface distress, and other maintenance of bituminous
surface, the Manual for construction and supervision of Bituminous works by MoRTH and as per
relevant IRC publications shall be followed.
CHAPTER - 26
(i) Filling up potholes and patchwork to black topped surface.
(ii) Thorough repairs including clearing of jungle growth, sectioning and forming of
berms, clearing side drains
(iii) Clearing of culvert and opening outlets.
(iv) Filling up erosions and removal of slips.
(v) Repairs to pitching, retaining walls, masonry works, culverts.
(vi) Painting Signboards, Kilometer stones, Hectometer stones, Guard stones, Boundary
stones, road markings etc.
(vii) Planting avenue trees and maintaining the same.
378
26.2.4.3. Special Repairs
Special repairs are such items of repairs, reconstruction, or additional construction found
occasionally necessary to keep the road in good condition. These may be divided into Special
repairs to roads, such as construction or reconstruction of retaining walls, raising a portion of
the road, widening of pavements, maintenance of shaller, construction of drains etc.
a. Special repairs to culverts up to 6mts span, construction and maintenance of road
side drains these may include reconstruction as well as construction of new culverts
if found necessary.
b. Emergency works related to VVIP visit.
c. Repairs to flood damages/ damages due to snow clearances.
d. Repairs to frost damages and other natural calamities.
The nature of repairs consequent of floods, drought and other natural calamities may fall under
one or other of the above categories or may be a new type of work such as training of a river
PWD ENGINEERING MANUAL-2020 CHAPTER - 26
course etc. Even when a flood damage work comes under the category of special repairs to roads
or to culverts, this is kept distinct from original repairs mentioned in (a) and (b) above since the
financing is from an allocation specially earmarked for this purpose.
Adequate signboards and road markings, not provided as per requirements, shall also be included
in special repairs.
Necessary provisions shall be made in the estimate for carrying out periodical maintenance
including clearing of drains, jungles, painting of sign boards, road markings and shaller maintenance
etc. during the defect and maintenance liability period.
For renewal coat, the defect and maintenance liability period shall be 3 years. All the periodical
maintenance including clearing of drains, jungles, and shaller maintenance etc. in the defect and
maintenance liability period shall be done by the contractor for the up keep of the road. After the
end of 3 years (defect and maintenance liability period), ordinary repairs (annual maintenance) shall
be done for next 2 years. After end of 5 years, surface renewal shall be done.
The table on the Schedule of maintenance operations given in Appendix 2600I may be
used as a guidance in preparing the timetable over a two year period.
379
Periodicity of Routine Maintenance Activities
N Name of item Frequency of operation in
o the year
.
1 Clearing of road side gutters Twice
.
2 Pothole filling (WBM & BT) Once
.
3 Filling up edges of asphalt surface of (i) Single lane
. excavating borrow pit. T. I*.0-1000 Twice
T.I. 1000-5000 Four
times
CHAPTER - 26
(ii) One and Half lane
T.I.0-1000 Once
T.I.1000-5000 Twice
T.1.Over5000 Four
times
(iii) Two lane
T.I.1000- Once
5000 Twice
T.I.
380
.
1 White washing parapets of C.D. Works Once
4
.
1 Earthwork in berms, de-silting of drains, etc. As per actual requirement
5
.
repairs. All unauthorized advertisement boards, banners and arches across and along
the roads shall be removed. In the case of masonry works, if any jungle growth is observed, the
same shall be rooted out. The site or work spot shall be cleared by the contractor after
construction by removing waste material like aggregate wastes, dust, timber woods, ashes etc
and disposed according to the environmental guide lines.
381
26.3.2. Fog Spray
Fog spray is a very light application of low viscosity bitumen emulsion for purposes of
sealing cracks less than 3mm wide or incipient fretting or disintegration in an existing
bituminous surfacing, and to help reduce loosening of chips by traffic on newly finished surface
dressing.
The materials to be used, construction operations, surface finish, quality checks and
opening to traffic shall be as per the specifications of MoRTH clause 518.
CHAPTER - 26
major treatment is carried out. SAM can be laid as a single coat or a double coat. A SAMI is a
layer which is applied to a cracked pavement surface but which is followed (within 12 months)
by the application of an overlay course. A SAMI may be a material similar to that used for a
SAM. It may alternatively consist of a bitumen-impregnated geotextile.
The materials to be used, construction operations, surface finish, quality checks and
opening to traffic shall be as per the specifications of MoRTH clause 522.
382
Branches of avenue trees shall have to be cut to maintain sight distances form Road safety point
of view. It may also happen that branches be cut for maintenance of or extension of electric lines,
telegraph lines or telephone lines. In the case of maintenance of existing lines, the authorities
under the control, can cut the obstructing branches in order to restore service quickly without
prior intimation to P.W.D. In the case of extension, the Executive Engineer under the control of
the concerned road shall be informed of the proposal by the authority concerned. Even here the
authority under the control may arrange the actual cutting of branches, after intimating the
Executive Engineer P.W.D. All branches, leaves etc. cut during such process shall however be
disposed by the P.W.D. For this purpose, the Overseer/ Supervisors shall arrange to collect the
branches etc., in suitable places and help in disposal as directed by the Junior Engineer/Assistant
Engineer. Roadside arboriculture could be a separate contract to the maintenance works.
planted on all the roads as per IRC 8 and IRC 26 for 200-meter stones. They shall be placed
clear of the shallers of the road so as not to obstruct traffic but shall be in such a position as to
be quite visible. They shall be maintained clean and legible always. The provision of kilometer
stones and 200 meter stones, wherever absent, shall be taken up as part of renewal coating or
special repairs.
383
(b) WheretheplantingofsuchboardsislikelytoobstructthevisionoftheDriver.
(c) At hairpin bends of curves, approaches of bridges.
(d) Near prestigious buildings, hospitals, educational institutions etc.
(e) Within 50 metres of any of the signboard erected.
(f) In such a manner as may obstruct the vision or distract the attention of the driver of a
vehicle on the road.
(g) To mar the aesthetic appearance of this background especially in localities which are
predominantly residential or where the national scenery is likely to be spoiled by such
display. National Building Code Part 10 Section 2 also provides the guidelines fordisplay
boards.
The highway authority may permit the display of advertisements in the typical formats on the
railings fences and bus bays built under private sector participation after levying the prescribed
fees/ rent, which shall be deposited to State Treasuries. This agreement shall be renewed
annually or a new agreement executed. The Highway Authority has the power to order removal
of all unauthorised display of advertisements and other encroachments.
CHAPTER - 26
26.7. Cutting roads/ overhead crossing
For any work involving the opening of the PWD roads, the road cutting protocol as per
Appendix 2600K shall be followed. It shall be unlawful for anyperson or authority or agency
intending to construct, place, maintain or carry any cable, wire, pipe, drain, sewer, channel of
any kind through, across, along, under, in or over any PWD road to make an excavation/
Crossing in or disturb the surface of any road to make an excavation/ Crossing in or disturb the
surface of any PWD road without written permission from the concern Authority, whose
decision shall be final and binding.
26.8. Encroachments
J&K Service rules empowers the officers of the department i.e. Executive Engineer and
his subordinate officers to take action for removal of encroachments with the help of district/
municipal and Police administration.
384
Chapter 27
27.1.1. General
Bridges are vital links in the highway network and if a bridge goes out of commission
for any reason, the resultant disruption of traffic seriously affects the capacity and efficiency of
the network. Highway structures, both old and new have to be maintained in a traffic-worthy
condition to facilitate uninterrupted flow of traffic. For this, regular and systematic inspection
of the structures shall be made by responsible officers to find out defects or deterioration of the
various parts and urgent action taken to remedy the defects.
PWD ENGINEERING MANUAL-2020 CHAPTER - 27
27.3. Inspection
Periodical inspection shall be conducted for all bridges as per IRC guidelines. Weak
bridges shall be inspected more often according to necessity and appropriate steps shall be
taken to remedy defects if any noticed.
27.3.1. Routine inspection
This involves visual assessment using conventional standard tools to determine obvious
deficiencies in the bridge structure, which might lead to traffic accidents or cause high
maintenance and repairs cost, if not attended promptly. The frequency of routine inspection shall
be at least once a year but preferably twice a year before and after monsoon. However, bridges
located in high altitude terrain prone to effects of landslides and bridges in severe exposure
conditions shall be inspected twice a year, i.e. before and after monsoon. In general, the
designation of the inspecting officer may be as per table 2700.1, but the same can be altered
depending upon the importance of the work.
385
Table 2700.1 Minimum Yearly Inspections by Engineers
Designation Type of Structure Test Check
Junior/Assistant All culverts and bridges of span less
Engineer than 30 m
CHAPTER - 27
Executive All major bridges of span greater Bridges and culverts inspected by the
Engineers than 60 m and less than 200m subordinate officers especially all minor
bridges marked weak and dangerous.
Superintending Allbridgesofspangreaterthan200mand Above cases especially those marked as
Engineers all pre-stressed concrete, continuous weak and dangerous.
structures, suspension bridges, cable
Stayed bridges and special structures
Chief Bridges above 500m in length Any Bridges
Engineer
386
27.3.2. Waterway:
Conditions in the stream bed shall be noted as to adequacy of channel afforded by the existing
structure, risk of scour that may endanger the foundation, presence of obstructions such as
drift, logs, undergrowth, stumps of old piers etc. that may be diverting the current so as to
cause undermining of the foundation and need for any bank protection to keep the channel
properly confined.
reduced to 15 cm or less shall be marked for replacement. Sills, bottom of posts and mud sills
for trestle piers shall be similarly tested. Steel or CI tubular piers shall be carefully examined
for corrosion in rivet or bolt head connecting the cylinder sections. Examination shall also be
made to note whether there has been appreciable movement or sink age of the tubes due to
impact of heavy loads on the structure; if so additional footing sor bracings may be needed. If
the tubes are out of plumb, it shall be checked whether this is due to undermining or the lack
of proper bracing or inadequate support below.
(b) Concrete or masonry piers or Abutments-These shall be examined for damages if any
arising from impact of floating matter or undermining or cracks. Further, they shall be examined
whether they are plumb. If cracks exist, the cause shall be properly investigated so as to choose
appropriate remedial measures. In the case of masonry abutments any tendency of bulge shall he
particularly noted as this will indicate excessive lateral pressure. When any such defect is noticed,
corrective steps shall be taken to relieve suchpressure.
27.3.4. Superstructure:
Where flooring is provided as in culverts and small bridges, any upheaval or sink age in
the flooring shall also be carefully noted and corrected. Where the deck is of reinforced
or pre-stressed concrete, the examination shall cover the following:
(i) Expansion joints and bearing plates examined to ensure that they are functioningproperly
and that their lubricating arrangements are satisfactory.
(ii) Drainage facilities verified to see that there is no collection of water in any part of the
structure and that water is drained easily.
(iii) Roadway surface checked to see whether there is excessive scaling or unevenness.
(iv) The bottom and sides of girders of slabs checked to note whether there is any honeycomb
area exposing reinforcement and further whether any cracks appear on such parts.
(v) Kerbs /Devri Stones and handrails to be checked for any spalling and exposed
reinforcements. The inspection of Steel trusses shall include the following points.-
(i) General alignment of the span to see whether in the case of ―through Bridges ‗the end posts
and top chords are straight and in line. Any buckling would indicate that the structure has
been overloaded.
(ii) Whether any of the structural members is kinked or rusted or has in any other manner
suffered deterioration.
(iii) Where there is excessive deflection of any member.
(iv) Whether any of the rivets and bolts in important junctions has worked loose.
(v) Whether the conditions of end shoes and rollers are good. The examination of Timber
387
Trusses shall cover the following: -
(i) Whether there is any noticeable sag. If sag is present, note whether it is due to failure of
splices. Improper adjustment of vertical rods or crushing or diagonal members.
(ii) The condition of the bearing and the caps over the pier piling.
(iii) Whether all bolts through splices packing blocks and cross bracing are tight and in good
order.
(iv) The condition of the stringers.
(v) The condition of the stringers as seen from the bottom particularly with regard to full bearing
on pier caps and indications if any, of crushing.
(vi) Examination of the deck and hand rails from roadway.
(vii) Whether all bolts in the deck are properly tightened or have become loose due to shrinkage of
the timber.
(viii) The condition of the underside of the decking.
CHAPTER - 27
27.3.5. Culverts: The waterway shall be examined whether it is obstructed by jungle growth, or
silting etc. In the case of pipe culverts, examine whether the pipes have gone out of alignment
either vertically or laterally and also whether any of the pipes has cracked The condition of the
headwalls shall also be noted particularly to see whether they are plumb and free from cracks.
To facilitate proper routine inspection reporting, a simple check-list as suggested in IRC:SP: 35
shall also be used.
Underwater inspection: Visual examination of the surface may be done after removing marine
growth like coral deposits, algae, etc. Detailed inspection for obtaining more information of
deteriorated areas shall be done after clearing the surface growth as to enable closer inspection.
Underwater inspection is a highly specialized activity and as such shall be be entrusted only to
competent agencies experienced in underwater inspection. Such agencies shall be carefully
briefed on the components to be inspected and the nature of defects to be inspected. Close circuit
television may be used where the water is reasonably clear. Where visibility is poor, portable
echo sounding equipment can be used to provide a reasonably accurate profile.
388
388
detailed involvement of design organizations and experts in the relevant fields, who shall be
senior level engineers.
scour effects,
maximum flood level, etc.
(b) High structures During and after season of high
velocity wind.
(c) Bearings and expansion joints During extreme seasons and after
floods.
(d) Bridges in hilly terrain Before and after monsoons.
27.3.9.1 Guidelines
Detailed guidelines for highway bridge inspection and maintenance are contained in the
following and the same should be invariably followed.
i) IRC SP 35 "Guidelines for Inspection and Maintenance of Bridges",
ii) IRC Special Publication No 18 "Manual for Highway Bridge Maintenance Inspection"
iii) IRC: 52-1998 "Bridge Inspection's Reference Manual".
389
389
27.3.9.1. Inspection Report
The inspection report shall be in the prescribed formats. Properly referenced sketches
or photographs shall be used to illustrate the defects and condition of the bridge. Free hand
sketches shall be made during the inspection at the site itself. The size and location of the
defects shall be dimensioned though the sketch itself need not be to scale. For taking
photographs, reference number of the bridge and the location of the defects may be written in
colour at the appropriate place on the bridge. Apart from reporting defects and deficiencies any
proposals or recommendations for strengthening and repairs of the affected components shall
also be included.
CHAPTER - 27
shortcoming / distress noticed either during routine inspection or principal inspection, the matter
shall be reported to the senior level Engineer and the latter shall decide further line of action in
consultation with the Design Wing/ Consultants, if he considers it necessary and give detailed
instructions as to whether special inspection is called for.
If during the inspections any bridge is found to indicate distress of serious nature leading
to doubt about structural adequacy, the bridge will have to be evaluated for its load carrying
capacity.
If the assessment shows the bridge to be inadequate for the design loads, one or more of the
following actions shall be taken:
• The load on bridge shall be restricted to its assessed capacity. The condition of thebridge
390
390
27.4. Repair and Rehabilitation of Bridges
All bridges are to be kept in good condition and their rehabilitation and strengthening
needs shall be attended to as and when they arise. It is now well recognized that bridges not only
require systematic maintenance but also strengthening or rehabilitation during their service life.
IRC: SP-40 "Guidelines on Techniques for Strengthening and Rehabilitation of Bridges"
provides guidance on basic approach to repair and rehabilitation, identification, assessment and
diagnosis of distress, repair materials and repair and strengthening techniques to be adopted in
respect of concrete bridges. These guidelines may be followed while undertaking rehabilitation
or strengthening of concrete bridges.
391
iv. Epoxy injection: Epoxy injection for sealing fine cracks as small as O.05mm shall be applied.
The epoxy is injected under pressure to penetrate the very fine and tortuous cracks that may
exist. Ensure good quality of epoxy resin, correct selection of equipment and experienced
operating personnel for the application.
v. External pre-stressing: External pre- stressing consists of adding cables placed externally
to the girders with new anchorages at suitable locations. It can be used to compensate the
loss of pre-stress in the cables and partly/ fully restore the bridge deck to its original
service ability level.
vi. As the external cables are fully exposed and do not have concrete cover, they shall be
encased in either a strong High Density Poly Ethylene (HDPE) tubing or rigid metallic pipe
protected against corrosion by special coating. Pressure grouting of external pre- stressing
cables after tensioning is essential. Special care shall be taken while drilling holes or cutting
recesses in the structure for fixing anchorage assemblies to ensure that the existing pre-
CHAPTER - 27
stressing tendons are not damaged.
vii. Epoxy bonded steel plates: Steel plates bonded to concrete surface with epoxy structural
adhesive can strengthen RCC members in flexure and shear.
viii. Full depth concrete overlay/deck slab replacement: Where deterioration of large areas of
concrete surface of bridge decks has occurred, it may not be possible to repair it by crack
repair or patching. In such cases, a full depth concrete overlay may be required. Similarly,
where the deck slab has become structurally weak due to loss of cross pre-tress or other
reasons, complete replacement of the deck slab may have to be resorted to. The overlays can
be of dense Portland cement concrete with special quick setting admixtures of latex modified
cement concrete. They shall be bonded structurally to the underlying old concrete and shall
392
392
restricted, and will, in most cases be the cause of new damage to the intrados as experienced on
many bridges even where the headroom/clearance satisfies legal limits. Extra material may be
placed by shuttering and pumping concrete (which is difficult to compact at the crown) or by
fixing a mesh to the intrados and spraying concrete. In both cases, any shrinkage of the new
concrete will tend to make the old and the new material separate radically. Also these impervious
rings prevent natural drainage between the stones or brickwork of the arch so that special
provision must be made to deal with water or under severe climatic conditions. Sprayed-on
concrete will in any case change the appearance of an arch constructed of stone, brick or a
combination of the two.
A more effective, but at times a more expensive, treatment is to remove the fill and cast
the extra required thickness on the extrados of the arch. Usually, a full ring is cast but
occasionally only the end quarters are strengthened to act as cantilevers and reduce the effective
span of the arch. Normal concrete placing techniques are satisfactory. Replacement backfill may
be with normal or lightweight concrete. The latter will reduce dead load on the foundations but
PWD ENGINEERING MANUAL-2020 CHAPTER - 27
393
changing the structural action so that loads are supported in a way that prevents high stress
range from developing.
CHAPTER - 27
27.5.6. Excessive vibrations
Suitable structural alterations and increased damping for which a specialist in dynamic
behavior of structures may have to be consulted can overcome these.
27.6. Monitoring
After the rehabilitation/strengthening of the structure is completed, it is essential that the
bridge structure is kept under observation and its condition monitored regularly so as to ascertain
its performance and the efficacy of the measures adopted. The monitoring may involve
inspections at more frequent intervals, carrying out of certain laboratory and field-tests as well
394
Chapter 28
28.1. MAINTENANCE OF BUILDINGS
28.1.1 General
All Government buildings are to be maintained properly. As a matter of convenience, heads
of various departments of the State are authorized to arrange and carry out maintenance works
of buildings under their administrative control provided the annual maintenance cost of any
building or group of building in one campus does not exceed the estimate does not exceed 10%
of the capital cost of building. This shall be intimated to the PWD. In addition, departments
other than P.W.D, which are having engineering wings under them such as Rural Engineering
Department, are allowed to carry out maintenance works of all the buildings under their
administrative control. Quasi Government Organizations and local bodies and Government
owned corporations attend to maintenance of their buildings even if the buildings were originally
PWD ENGINEERING MANUAL-2020 CHAPTER - 28
put up at Government cost. Subject to these and other exceptions ordered by Government from
time to time, the P.W. D. has the responsibility to maintain all Government buildings.
Maintenance includes white washing, coloring, painting, repairs to doors, windows, roofs,
sanitary & water supply fittings, structural repairs, internal roads, fencing, compound walls etc.,
However, expenditure towards day to day cleaning, sweeping, watch & ward, gardening,
payment of rent, water and electricity charges, taxes & tariffs etc. shall be borne by the user
department.
395
increased or decreased by acquisition, transfer or otherwise, the fact shall be noted in the
register. The intention is that the register shall give full and up-to-date information about the
buildings under the maintenance charge of every building division. Possession
Certificate showing property rights of the land /building shall be obtained from concerned
authorities and maintained in proper order.
CHAPTER - 28
28.2. Maintenance of Government Buildings
DesignatedPWDCivilEngineersandElectricalEngineersunderthecontrolofeachGovernent
building shall be responsible for its upkeep and maintenance. All maintenance and construction
shall be done under their supervision and direction. Other quasi government agencies or private
agencies shall not carry out any modification, minor or major works in such government
buildings.
396
sanctioned by Government as per rules in force.
In the case of certain classes of buildings like Tourist Bungalows, Rest Houses etc. Linen
curtains, crockery etc. originally provided at Government cost and responsibility for renewal is
with the P.W. D, shall be dealt with as part of special repair. The cost on account of these need
not be included as part of the ordinary maintenance grant of the concerned building. In all other
cases such charges shall not be incurred by the P.W.D. except under special orders of
Government
The grant fixed for ordinary repairs for every building shall be revised once in every five
years or as often as found necessary. In all cases where the existing grant is altered, the alteration
shall be on the basis of the standard estimate and the then current schedule of rates. The ceiling
of grant of capital cost will not apply in such cases. Revisions shall also be noted in the typical
maintenance register.
Maintenance grant do not include expenditure. Like –
a) Municipal taxes,
b) Service charges,
PWD ENGINEERING MANUAL-2020 CHAPTER - 28
c) Water charges,
d) Telephone,
e) Electricity,
f) Internal roads etc.
397
maintenance work to be carried out.
(a) That the standards prescribed for the class of buildings are not increased.
CHAPTER - 28
(b) That the estimate does not include items which shall be provided by the occupant or
occupying department
(c) That the works include major repairs, which strengthens the building, prolongs, its life,
improves its hygienic condition & safety of the building.
Further, the occupant or occupying department shall not make any structural alterations or
put up additional structures, or dismantle any portion of the building. Such construction work,
if required shall be done by the Building wing of PWD, who is responsible for the safety and
maintenance of the building. The Electrical wing of PWD shall attend to any alterations to
398
the electric circuits.
In case any damage in the structure or the internal electrification or water supply or sanitary
installation is noticed the same shall forthwith be intimated by the occupant or occupying
departments to the concerned PWD officers for necessary action. On receipt of any such
complaint it is the responsibility of the P.W.D. officers concerned to arrange to inspect the
building and rectify the damage as early as possible. If such rectification is likely to take time
the fact shall be intimated to the occupant or occupying department and where possible,
necessary temporary arrangements may be made to enable the building being occupied and put
to use before permanent rectification is done. Such temporary arrangements shall be treated as
special repairs.
28.4. Inspection
It is essential that buildings under the maintenance of the P.W.D. are periodically inspected
so that damage, if any noted, is attended to then and there and not allowed to cause deterioration
of the structure. The Assistant Engineer shall inspect all the buildings (whose maintenance is
under his/her charge).
PWD ENGINEERING MANUAL-2020 CHAPTER - 28
399
28.1. Maintenance of Heritage Structures
Buildings maintained by PWD also include many heritage structures of prestigious nature.
While attending to repairs of such buildings it shall be ensured that the original characteristics
and aesthetics of these structures are preserved.
CHAPTER - 28
28.4.3. Cracks in Buildings
Cracks if any noticed in any part of the building needs to be investigated thoroughly and
cause ascertained before taking remedial measures.
400
under use are spoiled by debris, spots of paint, whitewash etc. such portions shall be cleaned up
then and there without waiting for the whole work to be completed. This is in addition to the
contractor's responsibility for removal of debris on completion of work.
401
building is handed over for occupation, the occupant shall sign and acknowledge the various
items included in the inventory. When the occupant vacates the house he shall give prior
intimation to the Assistant Engineer and handover all the items in the inventory list as well as
any additional items subsequently fitted, in good condition. The occupant shall also produce
necessary no due certificates from the Jal Shakti Dept. etc. at the time of handing over the
quarters. The Assistant engineer shall intimate the vacancy of the quarters to the Executive
Engineer on the same day when the occupant handover the key.
28.9.1. General
All major public buildings and government quarters shall have provision for waste
CHAPTER - 28
disposal. Solid wastes shall be disposed in an incinerator. Non-biodegradable waste materials
shall be, segregated and suitably disposed.
Public buildings shall be provided with sufficient urinals and latrines, as per norms and
shall be properly maintained. Their location must be clearly exhibited with name boards.
Electrical installations such as lifts, escalators, AC etc. shall be periodically inspected
and maintenance arranged as per specification of the manufacturer. Backup electric power shall
be provided for such installations with staff posted for operation.
28.9.2. Furniture
402
The Executive Engineer, Buildings Division will act as the Estate Officer of all
government buildings.
Once the building is decided to be taken on rent the head of the occupying office will
forward the following documents to the Assistant Engineer/ Assistant Executive Engineer
concern for fixing rent of the building.
1) Consent document in original with dated counter signature.
2) Land value certificate indicating the market value of land on the date of
occupation/proposed date occupation issued by the Thasildar.
3) Age certificate of the building issued by the local authority.
4) A list of officers and staff of the office with a note on special request of space if any..
5) The prescribed proforma duly filled up and signed.
The Assistant Engineer/ Assistant Executive Engineer is responsible for taking exact
measurements and working out rent as per the guidelines prescribed in the specific proforma.
The construction material, construction method etc. shall be properly verified on site and the
PWD ENGINEERING MANUAL-2020 CHAPTER - 28
rent worked-out The Assistant Engineer shall prepare the rent calculation on the basis of clause
28.9.5 and approve the same and issue rent certificate if the rent calculated is within his powers
of sanction and if not forward it to the superior officer to approve the rent calculation as per
delegation of powers.
The rent calculation and processing shall be completed within 20 days in the section office and
10 days in each higher office/ as per valuation schedule . The competent authority of the
occupying department, who shall get the administrative sanction from the competent authority
of their department and pay the rent from their funds, shall forward the rent certificate. On receipt
of the administrative sanction the concerned officer of the occupying department shall execute
a lease deed with the owner of the building and pay the rent to the parties from the date of
occupation or date of agreement whichever is earlier. The occupying department or the
occupant shall pay the electricity and water charges for the building during the period of
occupation. Once a building is occupied and rent fixed for the same, revision of rent will be
permissible only after the expiry of a period of 3 years from the date of agreement or date of
occupation whichever is earlier. Any revision of rent shall be made only on specific request
from the owner of the building and shall be effective only from the date mentioned above or from
the date of application for revision of rent whichever is later. Notwithstanding the above if any
alterations or additions are made to the rented building by the owner at the request of the
occupying department rent may be revised to allow for the above alteration or additions from
the date of completion of the same.
If the rent demanded by the owner is higher than the P.W.D. rate of rent the same has to be
treated as special rent. In case of special rent approval of the Government Rent Committee
constituted for this purpose shall be obtained before the administrative department passes orders.
Government will fix the procedure for this from time to time through technical circulars or
orders. If special rent is sanctioned the same shall be valid for five years and the owner can
demand revision only after this period. The lease deed shall be executed specifying this period
403
maintenance work as also to pay the taxes due to the building and premises. The details of rent
calculation for partially occupied building etc., will be worked out based on the technical circular
issued by the Chief Engineer from time to time.
28.10. Valuation
CHAPTER - 28
R.C. work, in the absence of any other data, the minimum of steel necessary for the particular
item may be assumed as having been used. With regard to foundations a few examination pits
shall be taken to find out dept. hand nature of foundations.
For attic floor, an allowance equal to 30% (Thirty percent) of the difference of rates assessed
for the floor comprising Attic and the floor immediately under it may be allowed. However
Attic floor over 5th story shall not be accounted for.
Explanation for valuation of Attic (For example,03 storied with Attic) 30% of
(Assessment of Attic as 4th floor minus assessment of 3rd floor).
1. Sanitary fittings @Rs.1.70 Lacs/point (Rupees One Lac Seventy Thousand per
point) (One sanitary point shall mean one W.0 with flushing cistern, one wash basin with
mirror, one bath / shower point, water storage tank, wafer supply system and disposal
system including septic tank and soakage pit).
For additional points having common disposal and water supply system @Rs.0.35
Lacs / point (Rupees Thirty Five Thousand per point) shall be accounted for.
404
2. Extra water point @Rs.10,000/point (Rupees Ten Thousand per point) which shall
Include steel sink, Of 01 bib cock, 01 stop cock, 01 gully chamber & necessary fittings) (Not
applicable for toilet and bathrooms).
3. Electric fittings:-
I. Lighting point @ Rs.995/point (Rupees Nine Hundred and Ninety Five per point)
One Lighting point shall Ind. wiring for lighting points in 1.5 Sq.mm PVC insulated Copper
wire 8 2.5 Sq.mm PVC insulated multi-strand Copper wire for lighting Sub-mains, 6 Amp one
way switch, 2 mm thick PVC conduit I Channel with bends, Junction boxes etc, 6 Amp S Pole
MCB , 10 Amp DP MCB , 2 way DB for Housing MCB and Hylem Sheet with wooden box
accessed in wells with accessories.
II. Heating points @Rs.1900/Point (Rupees One Thousand Nine Hundred per point)
PWD ENGINEERING MANUAL-2020 CHAPTER - 28
One Heating point shall incl. wiring for heating points in 2.5 Sq.mm PVC insulated Multl-
Strand Copper wire & 4 Sq.mm PVC insulated multi-strand Copper wire for heating Sub-
mains, 16 Amp switch socket combined, 2 mm thick PVC conduit / Channel with bends,
Junction boxes etc. 10 Amp S Pole MCB 2 way DB for Housing MCB and Hylem Sheet with
wooden box recessed in walls with accessories.
III. Fan points @Rs.3400/Point (Rupees Three Thousand and Four Hundred per
point) One Fan point shall include wiring for Lighting points in 1.5 Sq.mm PVC insulated
Multi-Strand Cooper wire, 1200 mm ceiling fan / 225 mm exhaust an with ceiling roses & PVC
Square block, 350 Watts electronic fan dimmer, 2 mm thick PVC conduit / Channel with
bends. Junction boxes etc. 6 Amp S Pole MCB . 10 Amp DP MCB , 2 way DB for Housing
MCB for lighting circuits and Hylem Sheet with wooden box recessed in walls with
accessories.
4. Extra for wardrobes / Almirahs made of Budloo planks / block boards having
paneled / (Flush shutters with teak wood / $(117117iC0 facing incl. all furnitures complete
shall be assessed as under:-
Block
Board Budloo board
a) In built Almirahs 9"
deep Rs.398/Sft Rs.462/Sft
b) in built
wardrobes 24" deep
Rs.513/Sft Rs.602/Sft
5.Extra for Marble store flooring @Rs.130/Sft
6.Extra for Marble chips flooring @.48/Sft
7.Extra for Kota stone flooring @Rs.87/Sft
8.Extra for Vitrified tile flooring @Rs.108/Sft
9.Extra for Ceramic galazed tiles @Rs.82/Sft
10. Extra for Mild steel grills for windows @Rs.80/Kg
11. Miscellaneous items not covered under this schedule shall be loaded as per
prevailing market rates.
405
The rates are applicable for the base year 2018 and for successive years rates be
determined on the basis of yearly appreciation as per All India whole sale price index
which shell be issued by this office on yearly basis.
CHAPTER - 28
storeyed
1. Foundation and 10% 9% 8.75% 8.50% 8.00%
underground work
2. Plinth 6% 4% 3% 3.% 2.%
3. Superstructure 15% 21% 25% 27% 29%
(Brick / stone work
only).
4. Doors & Windows 13% 16.75% 18% 19% 20%
(Frames and _
406
CATEGORY "A‘ CATEGORY
CATEGORY "B‖ CATEGORY "C‖ "D‖
Maas concrete / Random rubble
Random rubbe1 Random rubble /pot/penal stone
polygonal Stone /pot/penal stone meson/yin Random rubble
masonry In cement mason/yin swear are swear ere stone masonry
Foundation
over ROC strip / mortar over mortar over dry or In mud
cement conc. bed cement/lime concrete cement/lime mortar.
block or RCC Bed Block. concrete Bed
footing Block.
Mass concrete / R Polygons? /
Random rubble
class random rubble Polygons / Coursed Ceased I Random
atone masonry
/ polygonal/ /Random rubble stone rubble stone
In mud mortar
Plinth Conned stone masonry in cement masonry in cement
with brick bond
masonry in concrete /lime with face dressed /time mlh face
or Devdar wood
With lace dressed stones end DPC dressed stones
Dasa
stones and DPC end DPC
CHAPTER - 28
407
28.10.2. Cost Estimation
An estimate shall be prepared for the construction of the structure using the current PWD
schedule of rates. Where non-standard items of work are done, special data for the same shall be
worked out on the basis of prevailing market rates. In case the building is electrified, the estimated
cost of electrification shall be worked out in consultation with the Assistant Engineer, Electrical
Wing of PWD. For leveling site, only the minimum quantity necessary for construction of a
building of the size shall be assumed unless there is evidence at site that extra quantity of work
was involved and it is possible to measure such extra quantity. Leads and lifts for materials shall
be worked out as if the structure is being constructed by the department at that site. If any item of
work done is sub- standard as compared to the same item as per P. W.D. specifications, suitable
percentage reduction may be made for the same. Similarly, if any item of work is of especially
superior standard as compared with the corresponding item of P.W. D specification, a suitable
extra percent on the rate of the concerned item due to such superior work may be allowed.
CHAPTER - 28
28.10.2.1. Depreciation
From the estimated cost of the building worked out on the above basis, depreciation shall
be deducted for the period, which had elapsed after the building was constructed. The age of the
building shall be ascertained by l ocal enquiries including enquiries from local bodies like
Municipalities, etc., having jurisdiction over the area. The facts ascertained through such local
enquiries shall also be verified by examination of the condition of the building and its component
parts.
Depreciationisaffectedfromtheestimatedcapitalvalueworkedoutandabove.Thedepreciati on
is applied successively for each year, i.e., by compounding the depreciation annually. The
408
Chapter 29
29.00. Maintenance –Movable Assets
29.00.1. General
This chapter includes the maintenance of articles, which are necessary for carrying out
the various works of the Department. It includes items like vehicles, office accessories like
furniture and communication systems, survey instruments and other tools and plants, reference
books and codes, appliances, etc., which are not consumed in the course of execution of works.
This invariably includes the replacement/procurement of obsolete/requisite items also. This
chapter also includes materials and other stores that get consumed in due course.
Most of the works in the P. W. D. are carried out through contract agencies and the
selected contractor is to supply all the materials required for the complete work, including special
items as in the case of projects. However, for departmental execution, supply of certain materials
for the construction is necessary and these shall be procured as per section.
PWD ENGINEERING MANUAL-2020 CHAPTER - 29
29.01. Registers
A Register of movable assets shall be maintained in each office. Every item acquired by
purchase, transfer or through any other way shall be included in the appropriate groups in the
register kept in the concerned Division Office. Similarly every item, which is disposed of
finally by transfer to other divisions or by sale or in any other manner shall be noted in the
appropriate register. Each division will have an up to date register of all the assets like vehicles,
office furniture, survey instruments and other tools and plants, reference books and codes, all
appliances and spares including those in subordinate offices grouped under proper heads as
above.
To ensure that all acquisitions and final disposals are posted in the register, the vouchers
dealing with the acquisition or final disposal shall contain a certificate from the Accountant
under the control of work in the division that the transactions have been posted in the Register
giving also the page and item number of the entry. The certificate shall be checked and initialed
by the Divisional Accountant after verifying the concernedregister.
Cases may arise where the transactions regarding acquisitions or final disposal are dealt
in the subdivision office. Before the concerned vouchers or other documents dealing with these
are finally accepted, the same shall be got pre-checked and passed by the Executive Engineer so
that appropriate entries are made in the register of the division.
Each item of tools and plants, scientific and mathematical instruments and furniture shall
be given an identification number when first received in the division and this number shall be
quoted in all transactions relating to the same. The identification numbers will be preceded by a
n initial representing the name of the Division and followed by initials
409
representing the group and sub group to which the item belongs. The number itself will be based
on the serial number of the item in its subgroup or groups in the concerned register.
Spares shall also be entered in the register and treated as stock items and when used for
replacement or in repairs shall be shown as issue on the register and concerned repair estimate.
Accessories however are additional equipments to improve its performance. If these are kept
separate, these shall be numbered and accounted in the register. If fitted, the accessory need
not be separately accounted but the descriptions of the Plants shall indicate the fact of the
accessory being fitted in it.
All movements of tools and plants, scientific instruments etc., which are given separate
identification numbers shall be watched through a movement register so that at any time the
location of any item is easily known. To enable the movement register kept in the Division
Office being posted up-to-date, all movements of such Tools and Plants shall be accompanied
by a transfer note, a copy of which shall he sent to the Division Office.
29.04. Instruments
Regarding, mathematical and drawing instruments each Draftsman. Junior Engineer,
Tracer and Assistant Engineer shall have one set of drawing instruments consisting of-
(a) One Mathematical Instrument Box
(b) One tee square/ Mini drafter
(c) Two setsquares
(d) One parallel ruler
(e) Box of scales including plotting scales and architectural scales.
(f) Field instruments like total station, DGPS, auto level with level and staff.
In addition in each Division Office there shall be one set of French curves, Pantograph and
Planimeter and computers with drafting software‘s like AutoCAD and a printer/ plotter. If in any
Division, Subdivision, or Section the normal standard as specified above is found inadequate
then additional instruments and/or Superintending Engineer or Chief Engineer may sanction
additional quantities of the listed items according to necessity.
410
29.05. Tools and Plants
Tools and plants required for the general use of the department will be held as part of
stock and will be accounted for as such. The Executive Engineer shall annually review the
existing stock of the Tools and Plants available in the Division.
Existing hand tools like mammatties, pickaxes, shovels etc. not in use shall be accounted
and survey report prepared. These shall be disposed off in public auction after getting sanction
to the survey reports from the competent officer.
Machineryrequiredforworksdonebycontractorshallbeprovidedbythecontractorhimselfan
d shall not be provided by the department on hire. The department shall hire all machinery
required for departmental execution of works.
Existing road rollers, bitumen rollers asphalt hot mix plants, sprayers and accessories of
the above f or road surfacing work, which are not in use, shall be accounted and survey reports
prepared. These shall be disposed off in public auction after obtaining sanction from the
competent authority
PWD ENGINEERING MANUAL-2020 CHAPTER - 29
411
cash chest as per Government rules. Computer tables and chairs shall also be provided.
29.08. Bitumen
The Executive Engineer shall procure the bitumen for works up to TS powers of
Executive Engineer, from approved sources.
CHAPTER - 29
a. If any tools & plants and vehicles are required, the concerned Chief Engineer shall
sanction a proposal with an estimate for the same. This will form the basis for
procurement.
b. Office accessories like furniture, small tools, survey instruments and reference booksand
codes shall be procured by an officer not below the rank of an Executive Engineer based
on the sanctioned estimate
c. All purchases shall be against specific provision in sanctioned estimates. As an exception
to the above, spares/ replacements may be purchased against L. S. provision provided in
the annual maintenance estimate.
412
equipment, maintenance schedules, dates of repairs, type of repair, cost of repair, replacements,
transfer from Division/ offices and any other special remarks.
If any plants or equipment needs repairs, the custodian shall report the fact to the
Executive Engineer through his official superior. The custodian shall also arrange a competent
mechanic or Engineer/ government approved workshop to inspect the plants and report on the
nature of repairs to be done, the time required and the probable cost. If the plants is beyond the
stage of economical repair this fact also shall be reported by the inspecting mechanic or
Engineer. Executive Engineer may then propose to dispose off the plants at the place where it is
or transferred to a suitable place and may then be auctioned as per sanction received from
competent authority.
ThecustodianshallarrangetherepairsaftergettingsanctionfromthecompetentEngineer.Wh
ere operators or drivers are under the control of a vehicle or plants, they shall notify the
custodian immediately of any special requirements or replacements needed for safe
functioning of the vehicle or plants.
Scientific instruments like levels, theodolites, Total stations etc., shall be handled and
used only by technical hands having the requisite training in the use of these instruments. When
they are not in use, these instruments shall be kept properly in their boxes or containers. When
transported, the boxes or containers shall be carefully supported in cushions without the chance
of getting jolted, during the journey. Necessary skilled labour shall be employed for conveyance
and carrying out the work.
29.12.1. Calibration
Prolonged use may stretch tapes and chains, and the Legal Metrology department as per rules
shall do standardization. Measuring and weighing apparatus shall be calibrated at least once in
6 months. Other scientific measuring instruments and lab equipments shall be calibrated
periodically as per rules. Calibration and validity certification shall be the responsibility of the
custodian.
29.12.2. Operation
Operation of plants and machinery shall been trusted only to operators competent to
handle them. For this purpose the required training shall be given to persons selected to work as
operators. Such training may be given in special training establishments or by a period of
apprenticeship under a skilled operator. Wherever the manufacturers of the equipment issue
operating instructions, the same shall be translated to local language and the operator asked to
get fully conversant with it. A copy of such operating instructions shall be kept along with the
equipment and exhibited in such a manner that the operator can at all times refer to it easily.
Where the manufacturers issue no operating instructions, the Assistant Engineers shall write out
the important operating instructions for the guidance of operator.
Road vehicles as well as plants that require the operators and crew to have licenses issued
by certain statutory authorities shall have Operators who shall possess the required licenses,
which shall be periodically renewed and kept current at their own expenses.
All-important items of equipment such as vehicles, road rollers, plants, pile driving plants, U
compressors, mixers, pumps etc., shall have log books maintained for each such equipment. The
log book shall be written by the operator-in-charge of the equipment and frequently checked by
the Junior Engineer/ Assistant Engineer, and reviewed by Assistant Executive Engineer
concerned. In the case of vehicles, the log book shall be written by the officer in- charge of the
vehicle or the officer assigned to use the vehicles.
In the case of plants consuming fuel, lubricants etc., the standard rate of consumption
of these per hour of operation or for a certain unit of work done shall be prescribed after
413
carefully watching the performance of each such plants. When reviewing the logbook, a check
shall be made whether the actual consumption is reasonable as compared with the prescribed
standard. If any abnormality is noticed, the plant‘s performance shall be tested and if
necessary repairs or tuning as are required shall he carried out. The standard of consumption
shall be re fixed once a y ear or as often as found necessary by the Junior Engineer/Assistant
Executive Engineer.
Remittance of Motor vehicle tax, insurance premia, pollution control tests, obtaining
vehicle fitness certificate, etc. shall be the responsibility of the operator/ driver and custodian
officer.
29.13. Stores
Each store will have a custodian /A. E(stores) who will be responsible for the
verification, receipt, custody and issue of the stock materials and maintenance of initial accounts
of all store transactions. The administrative control over such custodians will be exercised by
CHAPTER - 29
stores officers (Assistant Executive Engineer) who will be stationed in suitable places. The
Stores controlling Officer (concerned Executive Engineer) shall render compiled accounts to the
Accountant General monthly.
The Stores officers and custodians of Stores shall be provided with ministerial and field
staff if required to assist them in the discharge of their duties.
Periodical verification of stores is a matter of great importance and a regular systematic
verification of all the stores has to be carried out at least once a y ear under control of concerned
Superintending Engineer.
414
reason for such entry in the remarks column.
different
articles.
Type of Material
n
c
e
This register shall be up to date at all times for verification by higher officers.
The store and the yard around it shall be properly protected with only one gate, controlled
by a gateman who shall have a shelter put up near the gate.
415
the custodian shall obtain a receipt from the contactor / contractor's agent
/representative along with the requisition and the issue shall be intimated to all concerned.
The quantity shall be entered in standard units prescribed for each item either in full or part both
in words and in figures. All articles issued shall be counted, measured or weighed as the case
may be before they are issued. There shall be proper measuring and weighing apparatus in each
store for this purpose. The stores officer shall make it a point to test these measuring and
weighing apparatus and keep it accurate.
Counting, measuring or weighing of articles particularly heavy articles may need the
assistance of some labour. This shall be legitimately charged to work. Loading of articles into
lorry or other conveyance for removal from the store is the responsibility of the custodian of
the store. For this purpose, the messenger who arrives with the Indent may be allowed to bring
in his own labour, lorry or other conveyance to the stores for removal of articles from the store
and arrange the loading work.
In the case of issue of stationery items, the custodian shall collect requests for issue and
CHAPTER - 29
get it sanctioned by the store controlling Officer. Each issue shall be entered in the indexed
register shown below then and there and the receiving officer shall sign in the Signature column
as a token of receipt.
Name of article
Sl. Opening Receipts Issue Balance as Remarks
No Balance on
date
of
Issue
416
cleaning of oil and fuel filters, tightening of loose joints, etc. shall normally be done by the
operating crew when the equipment is in operation. When the equipment is laid off, certain
preventive maintenance items may still have to be done occasionally and this shall be arranged
through any other suitable approved agency.
Checking and correcting contacts in electrical system and works of a similar nature can
be considered as preventive maintenance.
Such preventive maintenance items shall be properly listed out for each equipment and
charts of the same written in English or the language known to the operator and kept with the
equipment and displayed whenever it is in operation.
The cost of preventive maintenance works for the above items shall be included in the
general maintenance estimate for the division concerned. The Executive Engineer shall arrange
such works immediately.
PWD ENGINEERING MANUAL-2020 CHAPTER - 29
417
29.16. Workshops
P. W. D. shall make use of the Government approved workshops for all repairs in the
case of vehicles and tools and plants. For electronic and other equipments, the authorized service
centers of the manufacturer shall be utilized.
CHAPTER - 29
initiated regarding erroneous postings and other irregularities if any detected during verification.
An officer designated by the Store Control Officer shall do verification.
418
will be the basis for regulating future balances, the differences being taken up separately
through the concerned Chief Engineer. Wherever differences are observed between the book
(ledger) balances and the counted balances, the postings shall be checked, the case for the
differences investigated and instructions recorded in the ledger maintained by the Verifier.
8. The result of such verification shall be recorded in the progress reports to be submitted to
the Chief Engineer. Each article counted shall be carefully examined and its condition shall
be noted in the progress report. Also materials, which have not been operated upon for more
than one year noted and explanation called for. There port must be handed over to the
Stores Officer for record.
9. The Verifiers will also see that orders of the concerned Chief Engineer passed on the
different statements are given effect to promptly and action is taken to adjust all shortages
and surpluses in balances.
10. They shall verify whether list of surplus, obsolete and unserviceable articles are promptly
submitted and disposed off.
PWD ENGINEERING MANUAL-2020 CHAPTER - 29
11. The Verifier shall furnish a certificate in the progress reports to the effect that the accounts
prescribed in the Public Works Department Manuals are properly maintained.
12. The progress reports will he prepared in triplicate, with original copy submitted to
the Stores Officer who will record his remarks and submit it to the concerned Chief
Engineer through the Executive Engineer. The duplicate copy submitted directly to the
concerned Chief Engineer. The Verifier will retain the triplicate copy for his reference.
13. The Verifier shall also furnish his remarks in the progress reports about the
adequacy of arrangements made for the custody of materials.
14. The Verifier has also to verify whether reports are periodically sent to the Executive
Engineer.
29.19. Disposal
419
suitable place where these unserviceable articles can be retained till disposal. The Stores Officer shall
conduct necessary enquiries as to the reason for the article having become unserviceable and obtain
sanction from competent authority to dispose of the unserviceable articles through a survey report giving
a clear history of the matter. After such sanction is received, the articles shall be disposed off in public
Auction.
CHAPTER - 29
public auction after preparing necessary survey report and sanctioning it by the competent authority.
All unserviceable dismantled materials obtained shall also be disposed off.
420
GOVERNMENT OF J&K
J&K Public Works Department
Engineering Manual Edition 2020
PART – III
APPENDICES
The Appendices Part III Edition 2020 are General Guidelines for reference only and
shall be subject to change as and when felt necessary by the PW(R&B) Department.
The Department shall not be held responsible for any Errors and omissions. In case
of difference of opinion on any part/s of the manual the decision of the Development
Commissioner Works shall be final and binding upon the parties in such matters.
421
List of Appendices
APPENDICES
18C SO 15 dated:- 09.01.2020 (Finance Department) 429-435
report
422
S.No. Particulars Page No.
alignment of Roads/Bridges
Roads/Bridges
A3 roads/buildings/bridges.
construction of works
423
S.No. Particulars Page No.
Road Construction
to start work
424
425
426
Annexure – 2600 N
Page-2
ADVISORY:
It has been observed in umpteen cases that the DPRs (Detailed Project Reports) do not contain all the
required information/documents mandatory for accord of Technical Vetting, causing unnecessary delay
in processing of these DPRs in this office.
As is seen during examination/technical scrutiny of the DPRs, concerned departments adopt casual
approach in the preparation of a project irrespective of its size and magnitude thereby missing important
components/items, giving rise to revision of the project cost which could have been otherwise avoided.
This practice contributes to time over-run and subsequent cost over-run of projects and has to be
essentially stopped to save time and money.
APPENDICES
Accordingly, this is in the interest of smooth execution of a project that all the pre-requisites obligatory
for obtaining technical vetting are completed well in advance to ensure its timely processing in this
office.
Rate Reasonability Certificate (issued by an officer not below the rank of Executive Engineer or
equivalent) for the items not covered in the relevant schedule of Rates but being imperative for
execution needs to be supported with detailed analysis of rate on correct inputs.
DPRs for CD (Cross drainage like bridges etc) works need to be supported with all relevant Hydraulic
data, including HFL, scour depth behaviour/morphology of river/stream/Nallah with catchment area
etc. The cost of proposal should be based on detailed estimates and not on per meter basis.
For building structures, the DPR should carry Soil Test Report so that soil bearing capacity is known
to justify inclusion of components like Raft foundation, pile foundation, etc. in the DPR.
In case of road projects, pavement design should be supported with important details like CBR
(California Bearing Ratio), daily/yearly traffic details, However, wherever applicable additional details
like habitation/number of souls to be benefitted, layout plan/index man indicating the neighbourhood
and existing road network should also be given.
With a view that above highlighted issues and other requirement are fully taken care of while
forwarding the DPRs to the office of Development Commissioner for Technical Vetting, a check list
has been devised forming Annexure A to this Advisory for information and necessary action by all the
concerned departments, so that Technical Vetting of a DPR is carried out smoothly without delay. Any
DRR is not conforming to the checklist shall not be entertained in future.
427
Annexure – 2600 N
Page-3
6. The DPR should be framed on uniform rates as per J&K SSR (with detail wise estimates) or CPWD
Plinth area rates and where the rates are taken in LMR, reasonability of rate should be given by way
of proper rate analysis as per price index.
7. Approval regarding the overhead charges/agency charges/corporation charges from the
concerned authority.
8. A certificate duly authenticated by the competent authority that project does not fall in any other
scheme or in any other department plan.
9. Revised DPR, if any, should be enclosed with original copy of the DRP of comparison along with
justification for such revision.
10. Source of funding/flow of funds and name of funding agency should be mentioned.
All the above documents need to be kept in original duly countersigned by the Project Authority.
428
GOVERNMENT OF JAMMU AND KASHMIR
FINANCE DEPARTMENT
Civil Secretariat, Jammu/ Srinagar
Notification,
Jammu, the 9th of January, 2020.
S.O 15 :- In exercise of the powers conferred under section 67 of the Jammu and Kashmir
Reorganisation Act, 20 19,the Lieutenant Governor, Union Tenitory of Jammu and Kashmir is
pleased to delegate his financial powers to accord Administrative Approval, Technical sanctions and
Sanction of contracts, to the Administrative Departments, Major Heads of Departments, Class-I
Officers (Other Officers) and Class-I1 Officers, to the extent as indicated in Annexure-I, to this
Notification.
The financial powers delegated are subject to the condition that all Codal Formalities shall
be followed as per the provisions laid down in General Financial Rules 2017, Manual for
Procurement of Goods and Services, 2017, Manual for Procurement of Works 2019, Manual for
Procurement of Consultancy and Other Services 2017, issued by Ministry of Finance, Department of
Expenditure, GoI, and, other instructions/ orders/ guidelines issued by Government of Jammu and
Kashmir.
By Order of the Lieutenant Governor.
Sd/ -
(Dr. A. K. Mehta), IAS,
Financial Commissioner,
Finance Department.
429
Annexure-I to Notification S.0. 15 Dated 09.01.2020
430
B) Powers to accord Technical Sanction.-
1. To accord technical Chief Engineer Full powers. Subject to
sanction to detailed Chief Hospital condition that: (a)
estimates of cost of Full powers. estimated cost
original works or Engineers technically
sanctioned does not
parts thereof (SKIMS) exceed the
including special corresponding
repairs, Superintending Upto Rs. 1.00 Crore. administratively
renovations, Engineer approved cost by
additions and more than 10%
alterations and Ex. Engineer Upto Rs. 40.00 lakh subject to a
improvements not Assistant Upto Rs. 1.00 lakh monetary limit of
Rs.5.00 lakhs for
chargeable to Executive estimates upto Rs.
maintenance. 100.00 lakhs and
Engineer 5% of the cost
administratively
approved subject to
a monetary limit of
Rs.10.00 lakhs for
estimates above
Rs. 100.00 lakhs.
b) plans and designs
for individual
works costing over
Rs. 2.50 lakhs and
Rs.10.00 lakhs
are approved by
S.E and C.Es
respectively before
technical sanction
is accorded by
Executive Engineer,
Superintending
Engineer
respectively.
c) post of Chief
Hospital Engineer,
SKIMS is held by a
regular
deputationist Chief
Engineer from
PWD.
431
C) Powers to sanction/ award contracts:
1. To sanction contracts Administrative Full powers within Subject to the
for purchase of Departments budgetary limits. condition that 100%
Stores, Supplies, funding has been
Major Head of accorded/ committed.
Services on the Department
recommendations of
Class I Officers
Purchase Committee.
(Other Officers)
Class II Officers
2. To grant contracts Contract Committee Full Powers. Subject to the
for individual works. Departmental Upto Rs. 40.00 Crore Condition that AA
Contract Committee has already been
accorded and 100%
Chief Engineer Upto Rs. 20.00 Crore funding has been
Superintendent Upto Rs. 7.00 Crore accorded/ committed.
Engineer
Executive Engineer Upto Rs. 1.50 Crore
3 To form Purchase All Departments Provided that senior and experienced
Committee in the officers in the Department are selected as its
Departments, under members, Director Finance/ Financial
them. Advisor or an Accounts Officer, if any,
available in the Department and a
representative from Industries and
Commerce Deptt. should also be selected as
two of its members. In respect of rate
contract the rates fixed will remain valid for
a period as may be specified by the
Committee but not beyond one year from
the date of issue of orders determining the
contract. Where the period of validity of
rates has not been mentioned by the
Committee the same will be valid for one
year from the date of issue of the order. For
individual contracts the rates will be valid
till completion of the contract, as per the
terms of the agreement and/or supply order.
4 To form Contract General The Contract Committee shall comprise the
Committee. Administration foilowing members:-
Department, on the 1. Administrative Secretary concerned.
2. Representative from Finance Department.
proposal of
3. Secretary, (Technical) PW (R&B)/
the
Development Commissioner (Works).
Administrative
4. Chief Engineer PW (R&B) Department /
Departments. PHE (I&FC) Department/PDD.
5. Chief Engineer, of Inspections, Quality
Control and Designs.
6. Chief Engineer (Mech.) for such works as
432
involves purchase of Mechanical
Equipments.
8. Director/Joint Director PD&M
Department.
9. Director Finance /Financial Advisor.
10. Representative from Industries &
Commerce Department, not below the
rank of Addl. Secretary.
5 To constitute General The Departmental contract committee shall
Departmental Administration have the following constitution:-
contract Department, on 1. Development Commissioner, Public
committee. Works Department.
the proposal of
the Administrative 2. Chief Engineer PW (R&B) Department
Departments. 3. Chief Engineer (Mech.) for such works
as involves purchase of Mechanical
Equipments.
4. Chief Engineer of Inspections,
Quality Control and Designs.
5. Director Finance / Financial Advisor.
6. Director/Joint Director PD&M Deptt.
7. Spl. Secretary/Addl. Secretary of the
Deptt.
8. Representative from Industries &
Commerce Department, not below the
rank of Addl. Secretary.
6 To constitute an General The Empowered Committee shall comprise
Empowered Administration of the following:-
Committee for i) Chief Secretary.
high value and Department.
ii)Administrative Secretary,
prestigious projects Finance Department.
for supervision and iii)Administrative Secretary,
monitoring. Planning, Development & Monitoring
Department.
iv) Principal Secretary to Lieutenant
Governor.
v) Administrative Secretary,
PWD/PHE/PDD.
vi) Administrative Secretary, Housing &
Urban Dev. Department.
vii) Administrative Secretary concerned.
The Committee shall co-opt a Chief
Engineer as and when necessary.
The selection of the projects as would be
monitored by the above Committee shall
be approved by the Hon‘ble Lieutenant
Governor.
435
GOVERNMENT OF JAMMU AND KASHMIR
CIVIL SECRETARIAT—FINANCE DEPARTMENT
Notification
Jammu, the 31st of December, 2019.
Financial Commissioner,
Finance Department.
436
ANNEXURE-I TO NOTIFICATION S.O.-58 DATED 31-12-2019
437
2. Unspecified items Administrative Up to Rs. 5.00 lakhs Subject to rules laid down in
Departments per annum in each case GFR 2017.
Major Heads of Up to Rs. 2.50 lakhs
departments per annum in each case
Class-I Officers Up to Rs. 30,000
(Other officers) per annum in each case
Class-II and Class-III Up to Rs. 30,000
Officer per annum in each case
3. Purchase of bicycle Administrative Full powers within
for use of their Departments budgetary limit
own office as well Major Heads of
as for their departments
subordinate offices Class-I Officers
(Other officers)
4. Repairs of bicycle Administrative Full powers within
Departments budgetary limit
Major Heads of
departments
Class-I Officers
(Other officers)
438
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
5. Conveyance Hire Administrative Full powers within
Departments budgetary limit
Major Heads of Up to Rs. 50,000
departments per month
Class-I Officers Up to Rs. 40,000
(Other officers) per month
Class-II Officer Up to Rs. 20,000
per month
Class-III Officer Up to Rs. 10,000
per month
6. Reimbursement of Administrative Up to Rs. 4,000 per
conveyance charges Department month per person
Major Heads of Up to Rs. 2,000 per
departments month per person
Class-I Officers Up to Rs. 1,000 per
(Other officers) month per person
Class-II Officer & Up to Rs. 500 per
Class-III Officer month per person
7. Electricity, water Major Heads of Full powers within
charges, Gas other departments budgetary limit
439
than LPG Class-I Officers
(Other officers)
Class-II Officer
Class-III Officer
8. Purchase of Major Heads of Full powers within Subject to rules laid down
furniture departments budgetary limit in Chapter 6 Procurement
Class-I Officers of Goods and Services in
(Other officers) GFR 2017.
Class-II Officer
Class-III Officer
9. Repair of Major Heads of Full powers within
furniture departments budgetary limit
Class-I Officers
(Other officers)
Class-II O fficer
Class-III Officer
10. Freight and Major Heads of Full powers within
demurrage/ departments budgetary limit
wharfage charges Class-I Officers
(Other officers)
Class-II Officer
Class-III Officer
440
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
11. Hiring of office Major Heads of Full powers within
furniture, electric departments budgetary limit
fans, heaters, Class-I Officers
coolers, clocks (Other Officers)
etc. Class-II Officer
Class-III Officer
12. Legal charges Major Heads of Full powers within Subject to the principles and
departments budgetary limit rates laid down by Law
Class-I Officers Department.
(Other officers)
Class-II Officer
Class-III Officer
13. Maintenance upkeep Administrative Full powers within
and repair of Department budgetary limit
vehicles Major Heads of
departments
Class-I Officers Up to Rs. 15,000 per
(Other officers) annum per vehicle
Class-II Officer Up to Rs. 15000 per
annum per vehicle
441
Class-III Officer Up to Rs. 15000 per
annum per vehicle
14. Condemnation of Administrative Full powers Subject to the fulfilment of
vehicle Department norms.
15. Municipal rates and Major Heads of Full powers within
taxes departments budgetary limit
Class-I Officers
(Other officers)
Class-II Officer
Class-III Officer
16. Execution of repairs Administrative Full powers within In exercising these powers, the
and day to day Departments budgetary limit, if the provision of rules 132 and 140
maintenance of work is executed of the General Financial Rules,
Govt. buildings through Public Works 2017 shall be observed.
Department.
Major Heads of Full powers within
departments budgetary limit, if the
Class-I Officers work is executed
(Other officers) through Public Works
Department.
442
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
17. Postal and telegraph Administrative Full powers within
charges Departments budgetary limit
Major Heads of
departments
Class-I Officers
(Other officers)
Class-II Officer
Class-III Officer
18. Printing and Binding Administrative Full powers within
through Government Departments budgetary limit
Press Major Heads of
departments
Class-I Officers
(Other officers)
Class-II Officer
Class-III Officer
19. Printing and Binding Administrative Up to Rs. 20,00,000 Subject to rules laid down in
through Local Departments per annum Chapter 6 Procurement of
Private Agencies Major Heads of Up to Rs. 5,00,000 Goods and Services in GFR,
departments per annum 2017.
443
Class-I Officers Up to Rs. 2,00,000
(Other officers) per annum
Class-II Officer Up to Rs. 1,00,000
per annum
Class-III Officer Up to Rs. 50,000
per annum
20. Publication Administrative Full powers within Subject to rules laid down in
(i) Official Departments budgetary limit Chapter 6 Procurement of
publication Major Heads of Goods and Services in GFR,
departments 2017.
Class-I Officers
(Other officers)
Class-II Officer
Class-III Officer
(ii) Non-Official Administrative Full powers within Subject to rules laid down in
publication Departments budgetary limit Chapter 6 Procurement of
including books Major Heads of Goods and Services in GFR,
also departments 2017.
Class-I Officers
(Other officers)
Class-II Officer
Class-III Officer
444
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
(iii) Advertisements Administrative Full powers within Through Information
in Newspaper Departments budgetary limit Department only.
Major Heads of
departments
Class-I Officers
(Other officers)
Class-II Officer
Class-III Officer
21. To sanction rent for Administrative Full powers Rent is recommended to be
accommodation of Department reasonable by Executive
Offices and other Engineer of the concerned
public institutions in locality in which accommodation
private Buildings has been hired and the
required for non- agreement of the Finance
residential purposes Department has been obtained.
outside J&K when
no Govt. accommo-
dation is available
22. To sanction rent for Major Heads of the Full powers Subject to the condition that the
accommodation of Department rent is recommended by District
445
Offices and other Level Rent Assessment
public institutions in Committee.
private buildings
required for non-
residential purpose Class-I & Class-II
Officers
23. To sanction rent for General Administration Full powers within Subject to the following
private accommodation Department (Estates) budgetary limit conditions :—
hired for residential (1) Rent is recommended
purpose when suitable by Rent Assessment
Govt. building is not Committee.
available (2) Hiring of accommodation
at the rent recommended
by committee is approved
by LG in coordination.
24. Repair to and removal Administrative Full powers within
of Machinery (Where Departments budgetary limit
the expenditure is not
of capital nature)
Major Heads of
departments
Class-I Officers
(Other officers)
446
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
25. To grant rewards Administrative Full powers within As per the guidelines issued by
Departments budgetary limit the F. D. from time to time.
26. To sanction fluctuating Administrative Full powers within Subject to the rates approved
expenditure in meeting Departments budgetary limit by the Government from time
allowances of Major Heads of to time.
sweepers for part time departments
service. Class-I Officers
(Other officers)
Class-II Officers &
Class-III Officers
27. Purchase of Administrative Full powers within Subject to rules laid down in
stationery articles Departments budgetary limit Chapter 6 Procurement of
Major Heads of Goods and Services in GFR,
departments 2017.
Class-I Officers
(Other officers)
Class-II Officer &
Class-III Officer
447
28. Local purchase of Administrative Full powers within Subject to rules as laid down
petty stationery stores Departments budgetary limit in Chapter 6 Procurement
Major Heads of of Goods and Services in
departments GFR, 2017.
Class-I Officers Up to Rs. 50,000
(Other officers) per annum
Class-II Officer Up to Rs. 50,000
per annum
Class-III Officer Up to Rs. 50,000
per annum
29. Stores required for Administrative Full powers within Subject to the following
petty works Departments budgetary limit conditions that :
(repairs etc.) (i) Sanction of competent
Major Heads of authority for executing
departments the work carries with it,
sanction for incurring
necessary expenditure on
the purchase of stores
required for the work.
(ii) Rules as laid down in
Chapter 6 Procurement
of Goods and Services
in GFR, 2017.
448
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
30. Other Stores i. e. Administrative Full powers within Subject to rulesas laid down
stores required for Departments budgetary limit in Chapter 6 Procurement of
working of an Major Heads of Goods and Services in GFR,
establishment, departments 2017.
instruments, Class-I Officers Up to Rs. 50,000
equipments and (Other officers) per annum
apparatus Class-II Officer Up to Rs. 30,000
per annum
31. Purchase of Dietary Administrative Full powers within Subject to rules laid down in
articles/clothing and Departments budgetary limit Chapter 6 Procurement of
other items for day- Major Heads of Goods and Services in GFR,
to-day use of departments 2017.
Government Class-I Officers
hospitals (Other officers)
Class-II Officer Up to Rs. 10,000
at a time
32. Supply of uniforms Administrative Full powers within As per the guidelines issued by
Departments budgetary limit the F. D. from time to time.
449
Major Heads of
departments
Class-I Officers
(Other officers)
Class-II Officers &
Class-III Officers
33. To sanction Telephone General Administration As per sanction of
connections for public Department (Estates) Telephone sanctioning
offices and institutions committee
and residences of
Govt. Officers.
34. To sanction telephone Administrative Full powers within
charges Departments budgetary limit
Major Heads of
departments
Class-I Officers
(Other officers)
Class-II Officers &
Class-III Officers
35. Tents and camp Major Heads of the Full powers within
furniture Department budgetary limit
Class-I Officers
450
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
(Other officers)
Class-II Officers
36. Purchase of office Administrative Full powers within Subject to rules as laid down
automation equipment Departments budgetary limit in Chapter 6 Procurement
like photocopier, fax of Goods and Services in
machine, telephone GFR, 2017, and obtaining of
apparatus, computer, concurrence from F. D. if
laptop, printer etc. the expenditure exceeds
Rs. 20,00,000 ;
Major Heads of Subject to rules as laid down
departments in Chapter 6 Procurement of
Goods and Services in GFR,
2017, and obtaining of
concurrence from F. D. if
the expenditure exceeds
Rs. 10,00,000 ; and
Class-I Officers Up to Rs. 2.00 lakhs
(Other officers) per annum
Class-II Officers & Up to Rs. 2.00 lakhs
Class-III Officers per annum
451
37. Hire and maintenance Administrative Full powers The expenditure on the
of all kinds of Departments maintenance (including repairs),
computers/office Major Heads of upkeep when the work is
equipments departments entrusted to a ‗Public Sector
Class-I Officers Undertakings‘ and hire for block
(Other officers) time in case of exigency faced
Class-II & Class-III by breakdowns, erratic power
Officers supply, non-availability of
computer spares of special
nature at short notice, etc.,
when time bound work has to
be completed, shall be incurred
subject to general or special
instructions issued by the
Department of Finance/
Information Technology
Department from time to time
in this behalf.
38. Sanction of G. P. Fund Administrative Full powers (Ordinary, As per provision laid down in
Advance Departments Special and non- ―General Provident Fund
refundable GPF (Central Services) Rules, 1960.
withdrawal)
Major Heads of Full powers (Ordinary,
departments Special and non-
452
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
refundable GPF
withdrawal)
Class-I Officers Full powers
(Other officers)
Class-II Officers & (Ordinary, GPF
Class-III Officers Advance)
39. To sanction House Administrative Full powers As per the guidelines issued by
Building Advance Departments the F. D. from time to time.
40. To sanction an Administrative Full powers within As per the guidelines issued by
allowance to Departments budgetary limit the F. D. from time to time.
Orderlies who handle
Gestetner Machines Major Heads of
in addition to their Departments
own duties
41. To incur expenditure Administrative Full powers within
on service postage Departments budgetary limit
stamps for use in
office Major Heads of
Departments
Class-I Officers
453
Other officers
Class-II & Class-III
Officers
42. Cost of Petrol, Oil Administrative Full powers within
and Lubricant for Departments budgetary limit
Departmental vehicle Major Heads of
Departments
Class-I Officers
(Other officers)
Class-II & III
Officers
43. To sanction expenditure Administrative Full powers within As per the guidelines issued by
on account of Departments budgetary limit the F. D. from time to time.
refreshment charges in
favour of Government Major Heads of
employees participating Departments
in All India Service
Tournaments
44. To grant compensation Administrative Full powers In accordance with the rules
to Govt. employees Departments framed by Government from
under the Workmen‘s time to time.
Compensation Act
454
1 2 3 4 5
–––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––––
45. To sanction expenditure Information Full powers within As per the guidelines issued by
on entertainment under Departments budgetary limit the F. D. from time to time.
the unit, ‗News Service
and Briefing of
Correspondents‘
46. To sanction reimburse- Labour Full powers within
ment of expenses Departments budgetary limit
incurred under
Employees State
Insurance Scheme
(ESI Corporation
of India)
47. To sanction refresh- Administrative Full powers within As per the guidelines issued by
ment charges in favour Departments budgetary limit the F. D. from time to time.
of employees on
following occassions :— Major Heads of
(i) During sessions of departments
Legislature Class-I Officers
(ii) Budget Formation (Other officers)
(iii) Plan formulation
455
(iv) Conduct of
elections
(v) During Cabinet
meeting
48. To sanction the grant Education Departments In respect of the As per the guidelines issued by
of scholarship in Govt. Head of the Institution students in Colleges the F. D. from time to time.
Colleges and Schools
Provincial Joint In respect of the
Directors of School students in High/
Education Higher Secondary
schools.
Chief Education In respect of the
Officer students in Middle
Classes studying
in schools other
than High/Higher
Secondary
49. Outsourcing of staff Administrative Full powers within Subject to obtaining of
(Cook, Driver, etc.) Departments budgetary limit concurrence from Finance
Department.
Major Heads of
departments
––––––
456
ANNEXURE-II TO NOTIFICATION. S. O.-58 DATED 31-12-2019
CLASSIFICATION OF OFFICERS
Major Heads of Departments
1. Chief Secretary.
2. Advocate General.
3. Financial Commissioner.
4. Principal Secretary to Government.
5. Principal Secretary to Lt. Governor.
6. Principal Secretary to Chief Minister.
457
21. Director General, Accounts and Treasuries
458
44. Director Institutional Finance and Resources, Finance Department.
45. Secretary Legislative Assembly.
46. Director Accounts and Treasuries Kashmir/Jammu
47. Director Industries and Commerce.
48. Director Geology and Mining.
49. Director Handicrafts.
50. Director Handlooms Development Department.
51. Director Sericulture.
52. Registrar Co-operative Societies.
53. Director Agriculture.
54. Director Horticulture.
55. Director Soil Conservation.
56. Director Animal Husbandry.
57. Director Sheep Husbandry.
58. Financial Commissioner (Revenue).
59. Divisional Commissioner.
60. Relief Commissioner (Migrant).
61. District Development Commissioner.
62. Custodian General.
63. Commissioner Agrarian Reforms.
64. Director Food and Supplies.
459
67. Development Commissioner Works.
68. Director Stores and Procurement Department.
69. Chief Architect.
70. Director Health Services.
71. Drugs Controller.
72. Principal Medical College, Jammu/Srinagar.
73. Director Institute of Medical Sciences, Srinagar (SKIMS).
74. Principal SKIMS Medical College, Srinagar.
75. Principal Dental College, Srinagar.
76. Principal Government Dental College, Jammu.
77. Administrator, Associated Hospitals, Srinagar/Jammu.
78. Director Indian System of Medicines.
79. Director Family Welfare, MCH and Immunisation.
80. Director Social Welfare.
81. Director Tourism, Kashmir/Jammu.
83. Director Gardens and Parks/Floriculture.
84. Director Motor Garages.
85. Principal Chief Conservator of Forests/Addl. PCCF.
86. Chief Conservator of Forests.
87. Chief Wildlife Warden.
88. Director Environment and Remote Sensing.
89. Director Forest Institute.
90. Project Director Social Forestry Project.
91. Chairman Pollution Control Board.
92. Director Hospitality and Protocol.
460
93. Labour Commissioner.
94. Director Stationery and Civil Supplies.
95. Director Employment.
96. General Managers, Govt. Presses, Jammu/Srinagar.
97. Development Commissioner Fisheries.
98. Director Fisheries.
99. Transport Commissioner.
100. Director Local Bodies.
101. Settlement Commissioner
102. Chief Executive Officer, Pahalgam Development Authority.
103. Chief Executive Officer, Gulmarg Development Authority.
104. Chief Executive Officer, Patnitop Development Authority.
105. Director Horticulture (Planning and Marketing).
106. Director Estates.
107. Director Local Fund Audit and Pensions.
108. Chief Executive Officer, Sonamarg.
109. Chief Executive Officer, Kokernag.
110. Chief Executive Officer, Lakhanpur-Sarthal.
111. Chief Executive Officer, Bhaderwah.
112. Chief Executive Officer, Kishtwar.
113. Chief Executive Officer, Poonch.
114. Chief Executive Officer, Verinag.
115. Chief Executive Officer, Aharbal.
116. Chief Executive Officer, Yousmarg.
117. Chief Executive Officer, Wullar-Manasbal.
461
118. Chief Executive Officer, Surinsar-Mansar.
119. Chief Executive Officer, Lohlab-Bangus-Drangyari.
120. Chief Executive Officer, Tosa-Maidan.
121. Director Command Area Development, Kashmir.
122. Director Command Area Development, Jammu.
123. Director Rural Development, Kashmir.
125. Director Rural Development, Jammu.
126. Director Rural Sanitation, J&K.
127. Commissioner, Food Safety, J&K.
128. Director Libraries and Research, J&K.
129. Director Archives, Archeology & Museums, J&K.
462
CLASS-I OFFICERS
(OTHER OFFICERS)
1. Secretary to Govt. (not being independently incharge of a
Department).
2. Special Secretary and Additional Secretary to Govt.
4. Secretary, Trade Commission.
5. Secretary, J&K Public Service Commission.
6. Registrar, Special Tribunal.
7. Secretary, Service Selection Recruitment Board.
8. Director-cum-Pilot, Civil Aviation Wing.
9. Deputy Inspector General of Police.
10. Deputy Inspector General of Prisons.
11. NCC Group Commander.
12. DIG (Ranges).
13. Director, Defence Labour Procurement Department.
14. Director, Forensic Science Laboratory.
15. Joint Director J&K Fire Services.
16. Zilla Sainik Welfare Officer.
17. Director Sher-i-Kashmir Police Academy, Udhampur.
18. Joint Director Evaluation and Statistics.
19. Director Audio Visual Division.
20. Joint Director Press and Publication, Information Department.
21. Joint Director Audio Visual Division, Information Department.
22. Joint Director Planning and Administration, Information Deptt.
463
24. Principal, Polytechnic.
25. Joint Director, Education.
26. Principal, J&K Institute of Education.
27. Editor, Gazetteers Unit.
28. Principal, College of Physical Education.
29. Principal, Northern Zonal Accountancy Training Institute, Jammu.
30. Principal, Accountancy Training School, Srinagar
31. Examiner, Local Fund Audit.
32. Deputy Sales Tax Commissioner (Appeals).
33. Deputy Director Funds Organisation.
464
47. Joint Director Handlooms.
48. Joint Director Geology and Mining.
49. Deputy Director Geology and Mining.
50. Additional Registrar Co-operatives.
51. Joint Director, Agriculture.
52. Director, Rakh and Farms.
53. Maize Breeder.
54. Joint Registrar Co-operative Societies.
55. Joint Director Agriculture Multiple Cropping.
56. Deputy Director Horticulture.
57. Agriculture Research Engineers.
58. Rice Specialist.
59. Soil Survey Officer.
60. Agriculture Chemist.
61. Entomologist.
62. Vegetable Specialist.
63. Agronomist.
64. Agriculture Botanist.
65. Geneticist.
66. Deputy Director Training.
67. Wheat Breeder.
68. Deputy Director, Agriculture.
69. Agrostologist.
70. Superintending Engineer, Engineering Wing, Agriculture Deptt.
465
72. Mushroom Specialists.
73. Director (Provincial), Fire and Emergency Services.
74. Plant Pathologist (Apple Scab).
75. Deputy Director, Animal Husbandry.
76. Manager, Cattle Breeding Farm.
77. Poultry Project Officer.
78. Deputy Director, Sheep Husbandry.
79. Deputy Director, Animal Husbandry.
80. Deputy Director, Poultry.
81. Deputy Director, Research Animal Husbandry Department.
82. Project Officer, Intensive Cattle Development.
83. Deputy Director, Poultry Marketing Jammu/Kashmir.
84. Poultry Geneticist, Jammu/Kashmir.
85. Poultry Nutritionist.
86. Manager, Exotic Cattle Breeding Farm Mansbal.
87. Joint Director, Sheep Husbandry Department.
88. Joint Director, Animal Husbandry Department.
466
97. Deputy Development Commissioner (Works), Jammu/Srinagar.
98. Senior Architect.
99. Superintendents of Hospitals.
100. Deputy Director, Health Services.
101. Superintendents of Nursing Homes.
102. Principal, Ayurvedic College.
103. J&K T. B. Officer.
104. Joint Director Health Services.
467
122. Joint Director Field Survey Organisation.
123. Joint Director Town Planning Organisation.
124. Director Urdu Co-ordination Cell.
–––––
468
ANNEXURE-II TO NOTIFICATION, S.O.-58 DATED 31-12-2019
CLASS-II OFFICERS
469
21. Divisional Youth Welfare Officer.
22. Principal Industrial Training Institute.
23. Chief Education Officers.
470
46. Manager-cum-Chemist (Horticulture Deptt.).
47. District Horticulture Officers.
48. Project Officer, Multiple Cropping.
471
69. Manager, Poultry Farm, Srinagar.
70. Animal Husbandry Extension Officer, Publicity Wing, Jammu.
71. Poultry Marketing Officer, Jammu/Srinagar.
72. Manager, Rearing Space, Jammu/Srinagar.
73. Dairy Development Officer.
472
93. Town Planner.
94. Assistant Executive Engineer.
95. Joint Director (Works).
473
(iv) B.C.G. Programme ;
(v) Trachoma Pilot Project ;
(vi) Health Education Bureau ; and
(vii) Anti V. D. Programme.
112. Deputy Superintendents of City Hospitals and C. D. Hospitals.
113. Deputy Superintendent, SKIMS Hospital, Srinagar.
114. Malariologist.
115. District Medical Officers.
116. Assistant Director, Health Services (Indian Medicines).
117. Special Officer for Special Programme for Nutrition for Children.
118. Programme Officer/Deputy Director, Social Welfare Department.
119. Executive Engineer, UEED.
220. Deputy Director, Tourism.
221. Garden Keepers, Parks and Gardens.
122. Deputy Director, Botanist, Parks and Gardens.
123. Regional Wildlife Warden.
124. Joint Director, Integrated Water Shed Project.
125. Deputy Director IWDP.
126. Chief Executive Officer.
127. Regional Director, Pollution Control Board.
128. Member-Secretary, Pollution Control Board.
129. Deputy Director, Pollution Control Board.
130. Joint Director, Forest Protection Force.
131. Deputy Director, Forest Protection Force.
132. Divisional Forest Officer.
474
133. Deputy Conservator of Forests.
134. Executive Engineers, Irrigation.
135. Executive Engineers, Flood Control, Designs and Planning.
136. Executive Engineers, Public Health.
137. Deputy Director, Hospitality and Protocol.
138. District Employment Officer.
139. Deputy Director, Central Employment Department.
475
ANNEXURE-II TO NOTIFICATION S. O.-58 DATED 31-12-2019
CLASS-III OFFICERS
1. Under Secretary to Govt.
2. Administrative Officer.
3. Superintendent of District Jails (other than Srinagar and Jammu).
4. Assistant Directors, Fire Services.
5. Deputy Superintendent of Police.
6. Assistant Director, Statistics.
7. Revenue Officer, Power Development Department.
8. Assistant Director, Physical Education.
9. Officer Incharge Industrial Training Institute.
10. Principals, Higher Secondary Schools (10+2).
11. Assistant Director Archives, Archaeology and Museum.
12. District Youth Welfare Officers.
13. Accounts Officer.
14. Excise and Taxation Officers.
15. Public Prosecutors/Addl. Public Prosecutors.
16. Sub-Registrars.
17. Munsiffs.
18. Manager, Govt. Central Market, Srinagar.
19. Manager, Industrial Estates.
20. Factory Chemists.
22. Inspectors of Factories.
23. Assistant Director, Handlooms.
24. Assistant Director, Handicrafts.
476
25. Sr. Manager, Massive Craft Scheme.
26. Deputy Director of Sericulture Dev. Department.
27. Manager, Industries Centres.
28. Manager, Seed Sericulture Dev. Department.
29. Geologist Grade-II.
30. Manager, Plant Protection Workshop and Stores (Distt. Level).
31. Garden Assistant.
32. Economists, Horticulture, Planning and Marketing.
33. Assistant Soil Chemist, Soil Testing Laboratory.
34. Information Publicity Officer (Horticulture Department).
35. Principal, Malies Training Class.
36. Officer Incharge, Tea Cultivation.
37. Assistant Horticulturists.
38. Zonal Education Officer/Headmaster.
39. Zonal Agriculture Production Officer.
40. Superintendent Gardens, Agriculture Department.
41. Assistant Registrar, Co-operatives.
42. Field Manuring Officer.
43. Assistant Plant Protection Officer.
44. Officer Incharge, Mechanised Farm, Nandpur.
45. Crop Botanist.
46. Mycologist.
47. Veterinary Inspectors.
48. Liver Fluke Control Officers, Agriculture Department.
49. Livestock Dev. Officers, Animal Husbandry Department.
477
50. Hill Cattle Development Officer.
51. Chief Executive Officer, Emergency Relief Organisation.
52. Consolidation Officers.
53. Tehsildars.
54. Provincial Assistant Controllers of Weights and Measures.
55. Officer Incharge Border Area Land Reclamation.
56. Assistant Director, Food and Supplies.
57. Assistant Architect.
58. Assistant Town Planner.
59. Assistant Engineers.
60. Chief B. C. G. Officer.
61. Epidemiologists.
62. Veneriologists.
63. Asstt. Director, Health Services (Small Pox Project Scheme).
64. Nutrition Survey Officer.
65. Malaria Officer.
478
73. Tourist Officer, Katra.
74. Assistant Director, Gardens and Parks.
75. Assistant Director, Tourism.
76. Officer Incharge, Floriculture.
77. Assistant Wildlife Warden.
78. Assistant Director, Forest Protection Force.
79. Assistant Soil Conservation Officer.
APPENDICES
80. Assistant Research Officer, Irrigation, Research Laboratories.
479
Appendix 200 A
QUESTIONNAIRE (Under duties of Superintending Engineer)
steps been taken to regularize works started without adequate funds? Give details.
Are there works started without Administrative Sanction or Technical Sanction? If so give
details and reasons.
Has a Review of expenditure vis-à-vis budget provision been made with regard to works
under various head? If so where performance budget has been introduced, has the review of
the performance been made in accordance with the performance budget?
Have estimates been prepared and sanctioned for all budgeted works? If not, indicate the
present position regarding estimates as given below:
No. of works not yet investigated,
No. of works investigated and in the design stage.
No. of works where estimate is under preparation or scrutiny.
No. of works where investigation design or estimate is held up on account of some special
reasons. Has a test check of the designs approved by the Executive Engineer been made? If
so, are these in accordance with standards followed in the Department?
Where type designs are available are these being adopted?
Are there cases where the actual cost of work has exceeded or is likely to exceed the
Sanctioned Estimate by more than 50%? If so, make a case study and indicate the principal
reasons for the excess and how such large excess can be avoided in future.
Have all safety precautions been taken in the works under execution?
Have the various registers like Revenue Register Tender Register, Building maintenance
register, Acquittance roll been examined? What are the general conclusions after a review of
the register?
Are service books kept up-to-date?
Has a test check of overtime allowances paid been made? If so, does this disclose any
abnormalities or irregularities?
Has a test check been made regarding wages of workers to whom Factory Act is applicable?
If so does this disclose any irregularity?
Has the Executive Engineer inspected the Subdivision office and Stores if any under his
control during the year? If so review any one of the inspection registers of the Executive
Engineer and indicate the findings. Are labour gangs in different sections of roads adequate?
Is sufficient number of quarries available?
Is road traffic statistics conducted and details kept in proper form?
Are there pending replies to remarks of Audit reports, inspection reports and public accounts,
committee estimates committee etc? If so give details.
Have sufficient computers installed in Divisions and are they operational? If not, action
taken.
480
Appendix 200 C
Space Standards : Standards of space allotment for various types of Buildings :
School Buildings
For Primary Schools.
Class Room : Minimum of 1 sq.m per student
For Secondary Schools.
Class Room : Minimum of 1 sq.m per student
For Colleges (Arts & Science)
Lecture Hall : Minimum of 1.2 sq.m per student Laboratory : Minimum of 2.5 sq.m per student
The requirement for Professional Colleges will be suggested by the authorities concerned.
Standards for student hostels
For Dormitories : Minimum of 4.5 sq.m per student
For triple occupancy : Minimum of 6.5 sq.m per student
For Double occupancy: Minimum of 7.5 sq.m per student
For Single Occupancy: Minimum of 9.0 sq.m per student
Standards For sanitary requirements:
Relevant Rules in JKMBR shall be followed.
For Office buildings, officers above rank of executive engineer and above are eligible for separate
toilet.
Space standards for tourist Bunglows
3.1. Economic Class :
Area for Single Room: 12 sq.m. excluding toilets Area for Double Room: 18 sq.m.excluding toilets
481
Appendix 400 A
Roads Information Inventory/ Assets Contracts Contractor Computer Aided General Ledger Personal Files PWD eMail
system (with GIS) Management Contracts Profile Design Tools Accounts Payables Service records Website / P Messaging
Roads Maintenance Procurement and Administration Projects in Modeling and Accounts Salary Records WINGS Workflow
Management Tender Planning progress Simulation Tools Receivables Seniority, Secure automation
Roads Safety Management Tendering /completed Structural Assets Valuation Promotions and Department Group ware
Management/Accide Revenue: Billing Planning EMD &BG Analysis Funds Flow Transfers Intranet / WAN MS Office
nt Info System & Collection Costing Bills Raised Tools Management Training and for employees equivalent
Funding Stage- wise Satellite Imagery Cash Management Career &internal tools Files
Bridges Budget Planning stakeholders
& Monitoring Resource payment s made Interpretation/ Cheque Books Development Tracking
Management Secure Extranet
Management Recoveries Due editing tools Management Performance Library
Pavement Contracts Aerial Photography Treasury for external
Billing Performance Appraisals Information
Management Management stakeholders
Progress Report / Other Integration Management Skills Inventory Management
Traffic Management Contractors Tools Budgeting Capability Profile and agencies Legislative
System Management GIS Financial Controls Employee Payroll Public Assembly &
Toll ways Projects environment Financial Expense and Access Parliament
Management System Management Technical Travel portal Q&A
Reporting
Real-time Traffic HW, SW& Litigation
Stores Accounting Pay Roll
482
APPENDICES
desires to undertake any project is required to submitBoard
a detailed project report, which shall inter-alia include
an Environmental Impact Assessment (EIA).
483
projects. Control Board
3. The Public An Act to provide for public liability insurance for theJ&K State Pollution Control
Liability purpose of providing immediate relief to the personsBoard
Insurance Act, affected by accident occurring while handling any
1991 hazardous substance (defined under the Environment
(Protection) Act 1986 and exceeding such quantity as
may be specified by notification by
the central Government and for matters connected
there with or incidental thereto.
4. The National An Act to provide for strict liability for damagesMinistry of Environment &
Environment arising out of any accident occurring while handlingForests
Tribunal Act, any hazardous substance and for the establishment of
1995 a National Environment Tribunal for effective and
expeditious disposal of cases arising from such
PWD ENGINEERING MANUAL-2020 APPENDICES
7. The WildlifeEstablish a number of National Parks and Sanctuaries Ministry of Environment &
(Protection) Actto protect and conserve the flora and fauna. Forests
1972
484
8. The BiologicalAn Act to provide for conservation of biologicalMinistry of Environment &
Diversity Actdiversity, sustainable use of its components and fairForests
2002 and equitable sharing of the benefits arising out of the
use of biological resources, knowledge and for
matters connected there with or incidental thereto.
To develop national strategies, plans, programmes for
the conservation and promotion and sustainable use
of biological diversity including measures for
identification and monitoring of areas rich in
biological resources, promotion of insitu, and exsitu,
conservation of biological resources, incentives for
research, training and public education to increase
awareness with respect to biodiversity.
9. The LAWA Act Establishment of No construction Zones to protect Lakes
APPENDICES
and waterways
and conserve the flora and fauna. Department
10. The Motor Enforce standards for prevention and control ofState Transport Authority /
Vehicles Act, vehicular pollution . The authority also checksPCB
1988 emission standards of registered vehicles, collect road
485
Petroleum Rules, and blending of petroleum.
2002
15. The Mines and An Act and rules to provide for the regulation ofState Government
Minerals mines and the development of minerals to be followed
(Regulations and for the extraction of the sand and aggregates through
Development) mining.
Act, 1957 and
rules thereunder
PWD ENGINEERING MANUAL-2020 APPENDICES
486
Appendix 1100.2 Standard EMP for Projects / Works
Environmental
S. Management Measures
Issue
No.
APPENDICES
documents reasons shall be maintained in all such cases where deviation from the original EMPis
proposed.
Relocation of All community utilities and properties i.e., water supply lines, sewer lines, bank buildings,
W.A. Community health centers, schools, health clinics and veterinary hospitals will be relocated before
2 Utilities & construction starts, on any section of the project corridor. The PWD will relocate these
Common properties in consultation and written agreement with the agency/ owner/community. The
Property schools and health centers will be constructed as per the relevant state norms.
Resources. All other community property resources within the corridor of impact such as handpumps,
ponds, grazing lands etc. will be relocated.
The relocation sites for these schools will be identified in accordance with the choice of
The contractor shall take necessary care to ensure no impact on cultural properties such as
(i) historic sites and remains, (ii) places of worship including, mosques, churches, shrines
W.A. Cultural and temples (iii) graveyards and monuments and other important structures as identified
3 properties during the design.
As per design, if there are works that impact these cultural properties, the contractor shall
execute the works in close co-ordination with the PWD and the local community.
B. FLORA & FAUNA
487
Environmental
S. No. Management Measures
Issue
All efforts will be made to preserve trees including evaluation of minor design
adjustments / alternatives (as applicable) to save trees. Specific attention will be given
for protecting giant trees, green tunnels and locally important trees (religiously
Preservation of important, etc.).
W.B.1
Trees Tree cutting is to proceed only after all the legal requirements including attaining of
In-principle and Formal Clearances from the Forest Dept. / DoEF / MoEF are
completed and subsequently a written order is issued to the Contractor.
Particular species declared as „protected‟ by the State‟s Forest Dept. in the private
land will be felled only after due clearance from the Forest Dept. is obtained.
Contractor shall acquire material only from approved and licensed quarries. If
PWD ENGINEERING MANUAL-2020 APPENDICES
W.C.2 Quarrying contractor intends to develop a new quarry, then all the approvals and licenses must
be obtained prior to withdrawing material from the quarry. Contractor shall adhere to
the separate Guidelines on quarry management as per PCB /DA
D. CONSTRUCTION CAMP
Arrangements forThe contractor as per prevalent rules will carry out negotiations with the landowners
W.D.1 Temporary Landfor obtaining their consent for temporary use of lands for construction sites/hot mix
Requirement plants / traffic detours / borrow areas etc. The PWD will be required to ensure that the
clearing up of the site prior to handing over to the owner(after
construction or completion of the activity) is included in the contract.
Hot mix plants and batching plants will be sited sufficiently away from settlements and
agricultural operations or any commercial establishments. Such plants will be located
atleast 150m away from the nearest village/settlement preferably in the downwind
direction.
The Contractor shall submit a detailed lay-out plan for all such sites and approval of
Crushers, hot-mix
PWD shall be necessary prior to their establishment.
W.D. 2 plants and Batching
Arrangements to control dust pollution through provision of windscreens, sprinklers,
Plants Location
dust encapsulation will have to be provided at all such sites.
Specifications of crushers, hot mix plants and batching plants will comply with the
requirements of the relevant current emission control legislations and Consent / NOC
for all such plants shall be submitted to the PWD.
The Contractor shall not initiate plant/s operation till the required legal clearances are
obtained and submitted.
488
S. No. Environmental Issue Management Measures
APPENDICES
will not exceed 75 d B (A), measured at one meter from the edge of the
equipment in freefield, as specified in the Environment (Protection)
Rules,1986.
The Contractor shall maintain a record of PUC for all vehicles and machinery
used during the contract period.
The contractor will use ground water as a source of water for the construction
and will setup the own bore-well facility for construction work. Contractor
can use the ponds, which are not in use by community or identified to fill up
for the project, but in that case, before using any pond water contractor will
obtain written consent from the owner and submit to PWD.
The Contractor will also provide potable water facilities within the precincts
Potable water for of every work place in an accessible place, as per standards set by the Building
W.D.5
labour and other ConstructionWorkers (Regulation of Employment and Conditions
of Service) Act,1996.
The contractor will also guarantee the supply of sufficient quantity of
potable water (as per IS) in every work place / labor camp site at suitable and
easily accessible places and regular maintenance of such facilities.
489
Environmental Issue Management Measures
S. No.
E. CONSTRUCTION WASTES
Debris generated due to the dismantling of the existing road will be suitably
reused in the proposed construction, subject to the suitability of the materials
and approval of the PWD as follows:
The sub grade of the existing pavement shall be used as embankment fill
material.
PWD ENGINEERING MANUAL-2020 APPENDICES
490
S. No. Environmental Issue Management Measures
APPENDICES
Contractor will ensure that any spoils of material unsuitable for embankment
fill will not be disposed off near any water course, agricultural land, and
natural habitat like grasslands or pastures. Such spoils from excavation can
be used to reclaim borrow pits and low-lying areas located in barren lands
along the project corridors (is so desired by the owner / community). All waste
materials will be completely disposed and the site will be fully cleaned and
certified by PWD before handing over.
The contractor at its cost shall resolve any claim, arising out of waste
disposal or any non-compliance that may arise on account of lack of action
on his part.
491
S. No. Environmental Issue Management Measures
W.F.2 Landslides Along landslide prone areas in hilly terrain, the slopes need to be
stablised. As drainage is most critical at these locations, proper drainage
needs to be constructed at these locations.
Contractor will ensure that no construction materials like earth, stone, ash
or appendage disposed off so as not to block the flow of water of any water
Drainage and Flood course and cross drainage channels.
W.F.3
Control Contractor will take all necessary measures to prevent the blockage of
PWD ENGINEERING MANUAL-2020 APPENDICES
492
operation, maintenance and refueling will be carried out in such a fashion
that spillage of fuels and lubricants does not contaminate the ground. Oil
interceptors will be provided for vehicle parking, washdown and refueling
areas as per the design provided. In all, fuel storage and refueling areas, if
located on agricultural land or areas supporting vegetation,the top soil will
be stripped, stockpiled and returned after cessation of such storage.
Contractor will arrange for collection, storing and disposal of oily wastes
to the pre-identified disposal sites (list to be submitted to PWD) and
approved by the PWD. All spills and collected petroleum products will be
disposed off in accordance with MoEF and state PCB guidelines.
PWD will certify that all arrangements comply with the guidelines of PCB/
MoEF or any other relevant laws.
APPENDICES
H. AIR POLLUTION
All vehicles delivering materials to the site shall be adequately covered.
The contractor will take every precaution to reduce the level of dust
emissions from crushers / hotmix plants / batching plant / WMM plant,
construction sites involving earthwork by sprinkling of water,
encapsulation of dust source and by erection of screen/barriers.
W.H.1 Dust Pollution
The contractor shall obtain the necessary consent-to-establish and consent-
to-operate for all its plants from the JKSPCB.
The contractor will provide necessary monitoring reports to confirm that
r Emission from Contractor will ensure that all vehicles, equipment and machinery used for
Construction Vehicles, construction are regularly maintained and confirm that pollution emission levels
W.H.2 Equipment and comply with the relevant requirements of PCB. The Contractor will submit PUC
chineries certificates for all vehicles / equipment / machinery used for the project.
Monitoring results will also be submitted to PWD as per the monitoring plan.
493
S. No. Environmental Issue Management Measures
I. NOISE
494
S. No. Environmental Management Measures
Issue
J. TRANSPORTING MATERIALS
Contractor will maintain all roads (existing or built for the project), which are used for
transporting construction materials, equipment and machineries. All vehicles
delivering fine materials to the site will be covered to avoid spillage of materials.
Transporting
W.J.1 All existing highways and roads used by vehicles of the contractor or any of his sub-
Construction
contractor or suppliers of materials and similarly roads, which are part of the works,
APPENDICES
Materials and
will be kept clear of all dust/mud or other extraneous materials dropped by such
Haul Road
vehicles.
Management
Contractor will arrange for regular water sprinkling as necessary for dust suppression
of all such roads and surfaces.
The unloading of materials at construction sites in/close to settlements will be
restricted to day time only.
K. TRAFFIC MANAGEMENT
The contractor will provide safe and convenient passage for vehicles, pedestrians and
livestock to and from roadsides and property accesses connecting the project road,
495
construction and provide,
W.K.3
Informatory Si approaching or passing through the section of any existing cross roads.
andHoardings
PWD ENGINEERING MANUAL-2020 APPENDICES
PWD.
L. LABOUR
W.L.1 Labor The contractor preferably will use unskilled labor drawn from local communities to
Requirements give the maximum benefit to the local community.
W.L.2 Personal Contractor will provide:
Measures fo Protective footwear and protective goggles to all workers employed on mixing
Labour asphalt materials, cement, and lime mortars, concrete etc.
Welder's protective eye-shields to workers who are engaged in welding works
Protective goggles and clothing to workers engaged in Factories Act, 1948 stone
breaking activities and workers will be seated at sufficiently safe intervals
Ear plugs to workers exposed to loudnoise, and workers working in crushing,
compaction, or concrete mixing operation.
High visibility overalls particularly when working along the ROW.
496
form of spray or a surface having lead paint dry is rubbed and scrapped.
The Contractor will mark „hard hat‟ and „no smoking‟ and other „high risk‟ areas an
en force non-
the Construction Safety Plant to be prepared by the Contractor during mobilization
and will be approved by PWD.
APPENDICES
W.L.3 First Aid The contractor will arrange for:
A readily available first aid unit including an adequate supply of sterilized dressing
materials and appliances as per the Factories Rules in every workzone
Availability of suitable transport at all times to take injured or sick person(s) to the
nearest hospital Equipment and trained nursing staff at construction camp.
The contractor will take all reasonable precautions to prevent danger to the workers
and public from fire, flood etc. resulting due to construction activities.
W.M.1 Risk Forc The contractor will make required arrangements so that in case of any mishap all
497
App 1100.3 Guidance on Oxbow Lands
General
In rural areas with the realignment of roads, land acquisition is required and ―Oxbow‖ lands can result
from this process.This is the land in between the existing road and the new alignment.
The Government of J&K owns the land and the PWD Chief Engineer have delegated authority to use and
manage this land in the public interest provided proper Mutation of documents
This land can be an opportunity to provide benefits for the road corridor and the community. Oxbow lands
can vary in length ranging from a few metres to a few kilometers with a variable width of a few
metres,which is unlikely to exceed 20 metres. As land is scarce in J&K, the remaining Oxbow lands provide
an opportunity for public and private investment to ultimately provide public benefit.
Each parcel of land will differ in size and context and the area suitable for only certain types of activities.
A preliminary needs analysis should be undertaken initially to identify and establish the feasibility of
options. A detailed plan can then be prepared.
PWD ENGINEERING MANUAL-2020 APPENDICES
Traffic and transport related infrastructure – such as vehicle parking bays, lay-byes, safety bill
boards, bus bays, taxi ranks, bus shelters.
Compensatory habitat – to replace trees that may have been removed during construction.
Rest Area Facilities primarily for travelers and include basic facilities such as seating, play area, signage
and information.
Comfort stops – these could be larger facilities to provide for recreation, rest, toilet and food facilities.
Commercial Facilities.These would be for primary use by commercial travelers and include petrol.
Local Park land, Sport and Recreation and Entertainment spaces.
Visual Amenity Improvement – by providing seating, landscaping, lighting, community art and signage.
Public utility purposes including Waste management facilities for collection.
Tourism related activities - such as interpretation centres.
Expand or complement existing adjoining property activities.
Key Issues and Opportunities
Potential Income Generation: There is potential to generate economic benefit for PWD through the lease,
use or disposal of the land. The local municipality may also have an interest in the land for purchase or
lease.
Capital Expenditure: The type of facilities provided will require capital investment. Options to share in
costs or for generating income to provide facilities should be explored with relevant authorities and non-
government organisations.
Maintenance Costs: Depending upon the type of activity and the land tenure, the areas may require
ongoing expenditure for maintenance by PWD. Self-financing options or income generating activities
should be explored where appropriate.
Liaison with other Stake holders: Consultation with the relevant stakeholders would assist in the decision-
making process for the planning, design and operation of the land. This includes community representatives,
concerned authorities such as the panchayet and non- government organizations.
Encroachments: Signs should clearly state the use of the site and the penalties for encroachment.
Encroachment enforcement should be carried out as per the J&K road Protection Act.
498
Guidelines
The development and use of this land should be considered by PWD in road planning, design,
construction and operation phases.
Each oxbow land area is to be considered on its merit. A Concept Plan should be prepared at the same time
as planning for the overall road project. Each site should be assessed before a detailed design is prepared.
The Concept Plan can show:
Environmental characteristics of the land including its topography and significant vegetation or
environmental values that should be retained.
Social characteristics of the land including any cultural values associated with the land, the need for
APPENDICES
community facilities and services in that specific location.
The relationship of the area land to adjoining areas and the type of uses adjoining the area.
The size of the land.
Access control and sight distance. Consider other factors in developing options.
The size of the area and the demand or need for rest stops or facilities in the area identified
(Refer: Tables 1 and 2).
The need to provide compensatory habitat as a result of the roadworks.
Any impact on personal or property safety for any activities proposed on the site.
The need for tourism facilities, rest stops, local facilities such as parking, bus shelters and lay-byes.
Funding Sustainability.
Stage 2: Analysis
Based on the information from Stage1, identify arrange options for the use of the area. Identify Criteria and
weight the criteria according to their importance to the area and the outcomes to be achieved. Each option
can then be evaluated against the specified criteria to select a preferred option. Criteria can include:
Road Safety
Pedestrian Amenity
Public transport use
Transport efficiency
Land use / Resource efficiency
Cultural and Social Values
Environmental Values
Viability Sustainable funding or ongoing income generating economic returns.
Prepare detailed design for the selected option on a site plan / Landscape Plan / Strip Plan for the area.
Species should be planted in accordance with the Guidance for Landscaping Species unless the land is used
for agricultural purposes.
Buildings and structures must comply with relevant IRC Codes, building specifications or relevant
499
Safe access and egress should be provided generally using the existing road, which may require
reconfiguration to enhance safety.
Any proposal for facilities will require the preparation of a Planning Report, which considers the
implications of the proposal and also a site map this should include the following:
Table 1: Typical type of Infrastructure and size for use of oxbow lands
500
App 1100.4. Guidance on Quarry and Borrow Area Management
Purpose
To avoid and manage the impact of activities associated with quarry and borrow areas on the environment
and affected community.
Some of the impacts of borrow areas and quarrying activities can include:
APPENDICES
vegetation.
Changes to the natural drainage pattern of the area.
Loss of agricultural / productive soils especially paddy field areas due to borrow areas / Quarry.
Digging of borrow areas within and along the proposedroadway.
Improper management of the quarry/borrow area top soil.
Over quarrying shall be avoided because of adverse impact on the ecology
These activities can have an affect on ecologically sensitive areas, the visual appearance of an area
and also impact on the health and well being of communities living nearby. Management measures
should be used to avoid and minimize any impacts from quarry relatedactivities.
Guidelines
All works to be undertaken in accordance with relevant rules and legislation including IRC guidelines and
MORT&H specification.
Quarry activities cannot commence until consent has been given in writing by the Forest Department or
other concerned authorities.
The Contractor will provide the Employer / Engineer with details of the location, size and shape of
borrow areas / quarry areas for written approval prior to opening the area.
Where specific borrow areas are not designated by the Employer / the Engineer, the Contractor will be
solely responsible for ensuring that the source of supply of material for embankment and subgrade is carried
out in accordance with environmental requirements for excavation and borrow areas as stipulated, from
time to time by the Ministry of Environment and Forests, Government of India and the local bodies, as
applicable
.
501
Top soil shall not be unnecessarily trafficked either before stripping or when in a stockpile. Stockpiles
shall not be surcharged or otherwise loaded and multiple handling shall be kept to a minimum.
Following excavation, the sides of excavated area shall be trimmed and the area contoured to minimize
erosion, subsidence and pounding, allowing for natural drainage to take place.
If trees were removed, new trees shall be planted, as directed by the Engineer. Additional borrow pits
should not be opened without the restoration of those areas no longer in use.
Borrow areas are not permitted to be located in the paddy fields or other agricultural areas.
The contractor is to prepare a Borrow and Quarry Area Management Plan and include the following
details:
Name.
PWD ENGINEERING MANUAL-2020 APPENDICES
Location.
Size of the Quarry or Borrow area.
Ownership of the borrow or Quarry area. Whether purchased or leased. Include a signed
statement of approval from the owner giving approval for the works.
State the proposed Activities including:
Approximate quantity and type of the material available.
Approximate depth of excavation required to obtain the material. Whether the depth and cutslope
areas per IRC guidelines?
The number, species type, location and maturity of trees to be removed. Quantities of top soil
removed.
Location of storage of top soil. Estimated daily truck movements.
Existing land use of the area (including the access road to be developed) to bequarried.
The relationship to adjoining areas including whether it is located near to ecologically sensitive
area, proximity to residential areas? Specify the nature and approximate distance from the proposed
quarry or borrow area.
Include details of the safety precautions to be used during quarry operation to protect workers, the
environment and the public.
Proposed plan for the reuse of top soil.
Methods used to reduce air (e.g. Dust from trucks) and noise pollution duringoperation.
Methods for the proper drainage of water.
Offset form the TOE of the Roadway.
Distance from the adjacent borrow area.
A Restoration Plan indicating the location, type and number of trees that will be planted, the method
to rehabilitate the access road, the landscaping plans for the borrow or quarry area and the
maintenance program that will be implemented to ensure the proposed works are properly
maintained following completion of the project.
The action plan for leveling and landscaping in order to bring the area in conformity to the
neighboring land uses.
The quality of the proposed borrow materials shall be determined and approved prior to use.
502
Format 1
Pre-Construction Stage Report- Date ... ... ... ... ... .. Month ... ... ... ... .. Year... ………..
Site Layout of Borrow Area and Proposed Borrow Area Rehabilitation Plan are required to be attached
with format. Format to be submitted before target date as (decided by PWD) for establishing Quarries Area
No. BA.
APPENDICES
Location of Borrow Area (KM) ... ... ... ...(RHS/LHS) Package ... ... ... ... ... ...
S. No. ITEM UNIT DETAILS REMARKS
1 Date of Borrow Area becoming
Operational dd/mm/yy
2 Current Land use
3 No of settlements within 500m of Nos
Borrow Area
4 Distance from the ecologically Km
sensitive Area (River,
503
Format 2
Site Layout of Quarry and Proposed Quarry Re-habilitation Plan to be attached with format. Format to be
submitted before target date quarries as (decided by the PWD) for establishing Quarry No.Q
3 License No.
4 License Valid till Date
5 Size of Quarry mxm
6 Quantity Available Cum
7 Proposed depth M
8 Total Capacity Cum
9 No of Settlements within 500m of Nos
Quarry
10 Width of Haul road M
11 Type of Haul Road Metalled/dirt
12 Length of Haul Road Sqkm
13 No. of Settlements within 500m of Haul Name
14 Road
15 Distance from Nearest Water Source Type/Distance
16 Whether Crusher Plant located on Site Yes/No
17 Details of the safety precautions during
blasting.
18 Whether local people are aware of the Yes/No
proposed quarry ?
19 Quantity of top soil removed
20 Details of the storage of top soil
21 Plan for the reuse of top soil
22 Details of the arrangement for proper
Drainage
Certified that the furnished information is correct and all relevant information as required is attached.
504
App 1100.5. Guidance on Landscaping & Tree Species
General
Purpose: The purpose of this policy is to provide a list of species that can be used in landscaping for road
purposes. Planting is an important part of the road network and can be used as a tool to improve road side
appearance and also to moderate driver behaviour.
APPENDICES
Modify vehicle speeds and driver and pedestrian behaviour
The PWD prefers species that have some or all of the following attributes:
Are indigenous to the area and can be sourced and grown locally
Provide weather protection
Require low maintenance and low water consuming
Are low hazard to people and property
Enhance the quality of the environment or streetscape
Will not interfere with utility services
The Process
A Landscape Plan should be prepared for projects either as a separate document or as part of an ESAMP.
A Concept Plan may be prepared initially, based on a preliminary analysis of the site conditions and the
future use of the site. A more detailed Landscape Plan is required when the concept is finalised and should
include relevant supporting information. The Landscape Plan should include a Title block with details
including date, scale and revision number, dimensioned plan of the site, the proposed location and type of
species and the relationship of the site to adjoining areas and the species within those areas. Supporting
documentation is to include a site analysis, species selection analysis, detailed species list, proposed
maintenance management plan and any other information necessary to justify that the use of landscaping,
tree planting and rehabilitation options have been selected to best meet the needs of the specific project.
(Suggest that PWD draft A Guide line on how to prepare a Landscape Plan for inclusion in the Code and
Manual. Until then, it is recommended to retain this clause).
Removal of any vegetation should comply with relevant statutory requirements including the J&K
Preservation of Trees Act which lists species that are not to be removed without first securing permission.
505
Tree plantation guidelines
safety.
Select species that integrate and complement existing indigenous species and could improve vegetation
corridors. Reason: Visual integration and Enhance Habitat Corridor
Where theme planting is required, select a few dominant species and replicate their use through the
streetscape to create a visual rhythm. Reason: Visual enhancement
In urban areas, due to narrow carriageway widths, roadside planting may not be appropriate.
Planting for Medians, traffic islands, traffic management measures, roundabout planting with fencing can
be promoted where it does not obscure sight distance or create a traffic hazard.
Reason: Pedestrian safety and Capacity
For median planting, shrubs should generally not exceed 60 cm in height and should be spaced in
accordance with plant specifications. Reason:Visibility
Plant species should be selected that avoid impacts on utility services and the roadway. For example
potential root damage to underground pipes and pavements and interference with above ground services
such as power lines due to height. Reason: Avoiding Disruption to Services
The potential impact on human health and well being such as respiratory ailments caused by flowering
species, is to be considered in species selection. Reason: Human Health
The propagation and use of native seeds collected from the local site or district is to be promoted.
Reason: Species Health
The type, location and spacing of species is appropriate for the road speed environment. For example shrubs
and small trees could be used in a village area as a tool to reduce driver speeds, manage parking allocation
and alter pedestrian behaviour. Reason: Modify road user behaviour
For large tracts of land consultation is recommended with the Forestry Department regarding the
opportunities associated with mass planting. Reason: Compensatory habitat and Carbon Sequestration.
The planting of productive food producing plants, such as coconut palms or herbs is promoted in appropriate
locations such as certain oxbow lands only if effective management measures can be implemented. Reason:
Food Supply
Adequate watering shall be made available during the contract and maintenance period
Specific Landscaping contracts for routine maintenance and watering of medians / islands / oxbow lands
may be implemented.
Species List
Table A includes a List of Species Indigenous to J&K. Examples of species that can be considered are listed
below by their Scientific Name, Common Name and Kashmiri name. Other species may also be suitable
and the reasons for their use justified in the supporting information accompanying the Landscape Plan.
506
Other Considerations
Aspects to consider in the selection of species also includes:
whether fruit or limbs will impact on pedestrians or vehicles
size at maturity and ultimate girth size
life span of the species and replacement
attraction of fauna
shade and shelter potential
visual interest
potential interference with drainage or services or other structures
irrigation requirements
personal safety and security
impact on human health e.g. respiratory
potential carbon sequestration
APPENDICES
dust and pollution tolerance
Longer Term Suggestions:
Develop Policy Guidelines for Landscape Planning if they don‘t already exist with reference to more
detailed landscape and planting elements including:
Standard work items
Payment for landscaping
Landscape establishment time frame
Material type and requirements
Plant Supply – suppliers, plant specifications, ordering
507
Table A: SpeciesList
S. No. Kashmiri
Botanical Name Name Trade/Popular Habit/Nature Sutability Character
Name
1 Acalipha Acalipha Evergreen Bet.1200-1800 above SeaOr namental Shrub (2-5m tall)
brachystachya level
2 Acalipha ciliate " Temperate Ornamental Shrub (2-5m tall)
3 Acalipha dalzillii " Tropical Ornamental Shrub (2-5m tall)
4 Acalipha hispida " Sub-tropical Ornamental Shrub (2-5m tall)
5 Araucaria cookie Araucaria Evergreen Sea coast to mid-hills Ornamental,Shade, Landscape
6 Azadirachta Indica Neem Evergreen All over J&K Multi purpose (Tree)
7 Alstonia Scholaris Shaitan wood / Devils ropical Shade, Ornamental Tree
Tree
PWD ENGINEERING MANUAL-2020 APPENDICES
508
33 Garcinia morella Indian Gamboge Avenue,Ornamental,Road
sideTree
34 Helicters isora East Ind Screw Tree Shrub,Ornamental, Landscape
APPENDICES
40 Jacaranda Jacaranda Evergreen Valleys,Low hills Avenue,Ornamental,Road
mimosaefolia sideTree
41 Largestroemia Queen's Flower All over J&K Landscape, Road side tree
reginae
42 Largestroemia Naked maiden of All over J&K Road side tree
microcarpa forest
43 Melia azedarach Malabar neem Central and Northern J&K Road side tree
54 Populus ciliata Poplar Deciduous All over J&K Road side, soil conservation etc
wall.
55 Pongamia pinnata Evergreen All over J&K Ornamental tree
56 Peltrophorum Yellow flame Evergreen All over J&K Roadside shade tree
pterocarpum
57 Pisonia alba Lettuce tree Coastal areas Ornamental shrub
58 Pandanus All over J&K Landscape (20 feet)
odoratissimus
59 Robinia Black Locust Deciduous All over J&K Avenue, Wood is decay resistant
psuedoacacia
60 Rawolfia Evergreen All over J&K Road side, good foliage
macropylla
61 Saraca indica Linn. Asok Evergreen Mild climatic conditions Ornamental and avenue
62
63 Spathodia Tulip Tree Evergreen All over J&K Shade, Avenue, Landscape tree
campanulata
509
64 Swietenia Mahogany All over J&K Shade Tree
Mahogani
65 Swietenia Mahogany All over J&K Shade Tree
macrophylla
66 Syzygium jambos Evergreen All over J&K Avenue, Road side planting
67 Syzygium Evergreen Valleys,Low hills Roadside planting
wightianum
68 Stereospermum Padri Evergreen All over J&K Avenue, Ornamental
suaveolens
69 Salix tetrasperma Indain Willow Deciduous Tropical, Valley areas Riverside, Wind break,
70 Thespesia Bhendi/Portia tree Deciduous Coastal/All over J&K Road side planting
populnia.Soland
71 Terminalia Catappa Badam All over J&K Road side, Shade tree
72 Terminalia Kindal All over J&K Road side, Shade tree
Crenulata
73 Tectona grandis Teak All over J&K Road side, Avenue
PWD ENGINEERING MANUAL-2020 APPENDICES
510
App 1100.6.
Guidance on Public Consultations
General principles
APPENDICES
consultation (e.g. respect the views of all
people even if you don‟t agree, only one
person to talk at a time, max)
Explain the project / issue
Outline of the role of the stake holders in
the overall decision-making process
Identify the key stakeholder issues
Outline the proposed consultation process
Approve the consultation schedule
511
Consider the following:
How accessible it is for stakeholders to
participate, e.g. district or panchayat
will the time of day and day of the week
affect participation e.g. Sunday
any cultural activities, holiday periods or
public events
Advise stakeholders of any changes to
the proposed schedule.
The process should facilitate participation Identify all relevant stakeholders who are
by all relevant stakeholders genuinely interested in or affected by the proposed
project.
This could include:
Affected property owners; occupants; business,
PWD ENGINEERING MANUAL-2020 APPENDICES
512
Respond to all comments and document Respond to each comment and state if and how it
is to be addressed by the decision maker. This
information should be made available for
participants to provide for transparency in
decision-making.
APPENDICES
community and is important for maintaining the
profile of PWD. Similar methods can be used to
feedback to the community as it was to get their
input.
513
Appendix 1100.7.
Guidance for preparing management measures where project-specific EMP are
required
-
The acquisition of land and private properties will be carried out in accordance with the
PS.P.1 Resettlement Action Plan (RAP) and entitlement framework for the project.
of land shall be addressed and integrated into the EMP and other relevant documents.
All Resettlement & Rehabilitation (R&R) activities will be undertaken in
accordance with the RAP document. It will be ensured that all R&R activities
Sites including environmental management plan preparation are completed before the
PS.P.2
construction activity starts, on any section of ROW of existing road and/or
proposed new bypasses.
EMPs for the Resettlement Site will be prepared in consultation with the concerned
community. Plans will include specific actions in relation to health, hygiene and
plantation
relevant norms.
514
Environmental
S. No. Management Measures
Issue
APPENDICES
resources.
515
Environmental
S. No. Management Measures
Issue
The Contractor shall not initiate plant/s operation till the required legal clearances
obtained and submitted from PCB.
All vehicles, equipment and machinery to be procured for construction will confirm to the
relevant Bureau of India Standard (BIS) norms. The discharge standards promulgated
Other Constru under the Environment Protection Act, 1986 will be strictly adhered to.
Noise limits for construction equipments to be procured such as compactors, rollers, front
PS.P.9
and Machinery loaders concrete mixers, cranes (moveable), vibrators and saws will not exceed 75 dB (A),
measured at one meter from the edge of the equipment in free field, as specified in the
Environment (Protection) Rules,1986.
The Contractor shall maintain a record of PUC for all vehicles and machinery used
during the contract period.
Finalizing borrow areas for borr
of the contractor.
agreeme
and the PWD.
Locations finalized by the contractor shall be reported to the Environmental Expert of SC
PS.P.10 Borrow Areas / Environment Cell of PWD and who will in turn report to PWD. Format for reporting
will be as per the Reporting Format for Borrow Area and will include a reference map.
stage. The haul roads shall be routed to avoid agricultural areas as far
Rehabilitation Guidelines) and will use the existing village roads wherever available.
In addition to testing for the quality of borrow materials by the S
516
Environmental
S. No. Management Measures
Issue
APPENDICES
PS.P.11Fly Ash The haul road will avoid
SC and PWD.
517
Environmental
S. No. Management Measures
Issue
PS.P.14 Labour The contractor preferably will use unskilled labor drawn from local communities to give
Requirements the maximum benefit to the local community.
518
Environmental
S. No. Management Measures
Aspect/Issue
APPENDICES
PS.C.1
Cell of PWD.
The contractor, under any circumstances will not cut or damage trees. Trees identified under the
project will be cut only after receiving clearance from the Forest Dept. / DoEF / MoEF (as
applicable) and after the receipt of PWD‟s written permission in this regard.
Debris generated due to the dismantling of the existing road will be suitably reused in the
proposed construction, subject to the suitability of the materials and approval of the SC and
Environmental Expert of SC / Environment Cell of PWD as follows:
The sub grade of the existing pavement shall be used as embankment fill material.
The existing base and sub-base material shall be recycled as sub-base of the haul road or access
The pre-designed disposal locations will be a part of Comprehensive Solid Waste Management
Plan to be prepared by Contractor in consultation and with approval of Enviro nmental Expert of
SC / Environment Cell of PWD.
519
Environmental
S. No. Management Measures
Aspect/Issue
into the surface water bodies or form mud puddles in the area.
-lying areas
dors (is so desired by the owner/community).
Non-bituminous wastes other than fly ash may be dumped in borrow pits (preferably located in
shall be created as part of
520
Environmental
S. No. Management Measures
Aspect/Issue
The top soil from all areas of cutting and all areas to be permanently covered will be stripped to
a specified depth of 150 mm and stored in stockpiles. A portion of the temporarily acquired
area and / or Right of Way will be earmarked for storing top soil. The locations for stock piling
will be pre-identified in consultation and with approval of Environmental Expert of SC /
Environment Cell of PWD. The following precautionary measures will be taken to preserve them
till they are used:
APPENDICES
a. Stockpile will be designed such that the slope doesnot exceed 1:2 (vertical to horizontal),
and height of the pile is restricted to 2 m. To retain soil and to allow percolation of water, the
Stripping, edges of the pile will be protected by silt fencing.
stocking and b. Stockpiles will not be surcharged or otherwise loaded and multiple handling will be kept to
PS.C.4 preservation of a minimum to ensure that no compaction will occur. The stockpiles shall be covered with
top soil gunny bags or vegetation.
c. It will be ensured by the contractor that the top soil will not be unnecessarily trafficked either
before stripping or when in stockpiles.
Such stockpiled top soil will be utilized for -
Covering all disturbed areas including borrow areas (not those in barren areas)
521
Environmental
S. No. Management Measures
Aspect/Issue
Temporary diversions will be constructed with the approval of the SC and Environmental Expert
of SC / Environment Cell / Engineer Incharge of PWD.
Detailed Traffic Control Plans will be prepared and submitted to the Environmental Expert of SC
/ Environment Cell of PWD for approval, five days prior to commencement of works on any section
for of road. The traffic control plans shall contain details of temporary diversions, traffic safety
PWD ENGINEERING MANUAL-2020 APPENDICES
Planning
Traffic arrangements for construction under traffic, details of traffic arrangement after cessation of work
PS.C.6 Diversions and each day, safety measures undertaken for transport of hazardous materials and arrangement of flag
Detours men.
The Contractor will provide specific measures for safety of pedestrians and workers at night as a
part of traffic control plans. The Contractor will ensure that the diversion / detour is always
maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow.
The contractor will also inform local community of changes to traffic routes, conditions and
pedestrian access arrangements with assistance from SC and PWD. The temporary traffic detours
will be kept free of dust by sprinkling of water three times a day and as required under specific
conditions (depending on weather conditions, construction in the settlement areas and volume of
traffic).
522
Environmental
S. No. Management Measures
Aspect/Issue
Contractor will ensure that they will strictly follow the specification given in IRC:SP 58 for
flyash embankment construction. Further, Contractor will also ensure that-
Flyash will be transported in covered dump truck to the project site and is directly dumped on
the embankment. This will not be stockpiled at project site.
Weathered (at least not freshly generated) flyash will be collected from the fly ash pond to
reduce the possibility of water contamination due to leaching of heavy metals.
Flyash surface will be graded and sloped at the end of each working day to provide drainage and
to prevent the ponding of water or the formation of run-off channel.
APPENDICES
The side slope will be properly benched and covered with soil and later vegetation will be grown
to prevent the erosion.
Run-off from the fly ash embankment / stockpile will be collected and discharged into proper
PS.C.8 Fly Ash drainage system.
Further handling, if any will be restricted within ROW. During such handling and also after placing
on embankment, if the flyash surface dries up completely, contractor will arrange for frequent
sprinkling of water for dust suppression. Otherwise, surface of the flyash will be covered with
tarpaulin or polyethylene sheets or other suitable material.
The flyash will be placed on an aggregate drainage blanket to prevent water from rising into the
flyash by way of capillary action. Contractor will ensure that flyash layer is separated from the
The contractor shall obtain materials for quarries only after consent of the Department of
Mining and District Administration.
Quarry
PS.C.9 Operations The contractor will develop a Comprehensive Quarry Redevelopment plan, as per the Mining
Rules of the state and submit a copy to PWD and SC prior to opening of the quarry site.
The quarry operations will be undertaken within the rules and regulations in force.
PS.C.10 Transporting Contractor will maintain all roads (existing or built for the project), which are used for transporting
Construction Construction materials, equipment and machineries as précised. All vehicles delivering fine
Materials and materials to the site will be covered to avoid spillage of materials.
Haul Road All existing highways and roads used by vehicles of the contractor or any of his sub-contractor o
Management suppliers of materials and similarly roads, which are part of the works, will be kept clear of all
dust/mud or other extraneous materials dropped by such vehicles.
Contractor will arrange for regular water sprinkling as necessary for dust suppression of all such
roads and surfaces.
The unloading of materials at construction sites in/close to settlements will be restricted to daytime
only.
523
Environmental
S. No. Management Measures
Aspect/Issue
Contractor will arrange adequate supply and storage of water for the whole construction period at
his own costs. The Contractor will submit a list of source/s from where water will be used for the
project to SC and PWD.
Construction The contractor will source the requirement of water preferentially from ground water but with prior
PS.C.11
Water permission from Jal Shakti. A copy of the permission will be submitted to SC and PWD prior to
initiation of construction.
The contractor will take all precaution to minimize the wastage of water in the construction
PWD ENGINEERING MANUAL-2020 APPENDICES
process/ operation.
While working across or close to any perennial water bodies, contractor will not obstruct / prevent
the flow of water.
Construction over and close to the non-perennial streams shall be undertaken in the dry season. If
River Trainingconstruction work is expected to disrupt users of community waterbodies, notice shall be served
and Disruptionwell in advance to the affected community.
The contractor will serve notice to the downstream users well in advance to divert the flow of water
PS.C.12 to Other Users
ofWater of any surface water body. Wherever excavation for diverting water flow will take place, contractor
will ensure that the slopes are not steeper than1:2 (vertical:horizontal) otherwise proper slope
protection measures will be taken as approved by the Environmental Expert of SC / Environment
Cell of PWD.
The contractor will take prior approval of the River Authority or Irrigation Department or SC for
any such activity. The PWD will ensure that contractor has served the notice to the downstream
users of water well in advance.
PS.C.13 Drainage and Contractor will ensure that no construction materials like earth, stone, ash or appendage disposed
Flood Control off so as not to block the flow of water of any water course and cross drainage channels.
524
Environmental
S. No. Management Measures
Aspect/Issue
Contractor will take all necessary measures to prevent the blockage of waterflow. In addition to the
design requirements, the contractor will take all required measures as directed by the Environmental
Expert of SC / Environment Cell of PWD to prevent temporary or permanent
flooding of the site or any adjacent area.
The Contract or will not excavate beds of any stream / canals / any other water body for borrowing
earth for embankment construction.
APPENDICES
Contractor will construct silt fencing at the base of the embankment construction for the entire
Siltation of perimeter of any water body (including wells) adjacent to the RoW and around the stockpiles at the
PS.C.14 Water Bodies an construction sites close to water bodies. The fencing will be provided prior to commencement of
Degradation o earthwork and continue till the stabilization of the embankment slopes, on the particular sub- section
Water Quality of the road.
The contractor will also put up sedimentation cum grease traps at the outer mouth of the drains located
in truck laybyes and busbays which are ultimately entering into any surface water bodies / water
channels with a fall exceeding 1.5m.
Contractor will ensure that construction materials containing fine particles are stored in an enclosure
such that sediment-laden water does not drain into nearby water course.
The contractor will take slope protection measures as per design, or as directed by the
PS.C.16 Water PollutionT he Contractor will take all precautionary measures to prevent the wastewater generated during
from Construction from entering into streams, water bodies or the irrigation system. Contractor will avoid
Construction construction works close to the streams or water bodies during monsoon.
Wastes All waste arising from the project is to be disposed off in the manner that is acceptable to the State
Pollution Control Board or as directed by Environmental Expert of SC / Environment Cell of PWD.
The Environmental Expert of SC / Environment Cell of PWD will certify that all liquid wastes
disposed off from the sites meet the discharge standards.
525
Environmental
S. No. Management Measures
Aspect/Issue
The contractor will ensure that all construction vehicle parking location, fuel / lubricants storage
sites, vehicle, machinery and equipment maintenance and refueling sites will be located atleast
500m from rivers and irrigation canal/ponds.
All location and lay-out plans of such sites will be submitted by the Contractor prior to their
PWD ENGINEERING MANUAL-2020 APPENDICES
526
Environmental
S. No. Management Measures
Aspect/Issue
Emission from Contractor will ensure that all vehicles, equipment and machinery used for construction are
Construction regularly maintained and confirm that pollution emission levels comply with the relevan
PS.C.19 Vehicles, requirements of PCB. The Contractor will submit PUC certificates for all vehicles / equipment
Equipment and machinery used for the project. Monitoring results will also be submitted to SC and PWD as pe
Machineries the monitoring plan.
The Contractor will confirm the following:
All plants and equipment used in construction shall strictly conform to the MoEF / CPCB noise
APPENDICES
standards. All vehicles and equipment used in construction will be fitted with exhaust silencers.
Servicing of all construction vehicles and machinery will be done regularly and during routine
servicing operations, the effectiveness of exhaust silencers will be checked and if found defective
will be replaced. Limits for construction equipment used in the project such as compactors
rollers, front loaders, concrete mixers, cranes (moveable), vibrators and saws shall not exceed 75
Db (A) (measured at one meter from the edge of equipment in the free field), as specified in the
Noise PollutionEnvironment (Protection) rules, 1986.
Noise from Maintenance of vehicles, equipment and machinery shall be regular and upto the satisfaction of th
PS.C.20
Vehicles, PlantEnvironmental Expert of SC / Environment Cell of PWD to keep noise levels at the minimum.
and Equipments At the construction sites within 150m of the nearest habitation, noisy construction work such a
crushing, concrete mixing, batching will be stopped during the night time between 9.00 pm to
527
Environmental
S. No. Management Measures
Aspect/Issue
528
Environmental
S. No. Management Measures
Aspect/Issue
The Contractor will take all required precautions to prevent danger from electrical equipment and
ensure that-
No material will be so stacked or placed as to cause danger or inconvenience to any person or the
Risk from
public.
PS.C.23 Electrical
All necessary fencing and lights will be provided to protect the public in construction zones.
Equipment (s)
All machines to be used in the construction will conform to the relevant Indian Standards (IS)
codes, will be free from patent defect, will be kept in good working order, will be regularly
inspected and properly maintained as per IS provision and to the satisfaction of the
APPENDICES
Environmental Expert of SC / Environment Cell of PWD.
The contractor will take all reasonable precautions to prevent danger to the workers and public from
Risk Force fire, flood etc. resulting due to construction activities.
PS.C.24 The contractor will make required arrangements so that in case of any mishap all necessary steps can
Measure
be taken for prompt first aid treatment. Construction Safety Plan prepared by the Contractor wil
identify necessary actions in the event of an emergency.
The contractor will arrange for:
A readily available first aid unit including an adequate supply of sterilized dressing materials and
PS.C.25 First Aid appliances as per the Factories Rules in every work zone
Availability of suitable transport at all times to take injured or sick person (s) to the nearest
hospital.
The contractor will do the plantation at median and / or turfing at embankment slopes as per the tree
plantation strategy prepared for the project.
Road side Minimum 80 per cent survival rate of the saplings will be acceptable otherwise the contractor will
PS.C.27 Plantation replace dead plants at his own cost. The contractor will maintain the plantation till they handover the
Strategy project site to PWD.
The Environmental Expert of SC / Environment Cell of PWD will inspect regularly the survival rate
of the plants and compliance of tree plantation guidelines.
The contractor will take reasonable precaution to prevent his workmen or any other persons from
removing and damaging any flora (plant/vegetation) and fauna (animal) including fishing in any water
body and hunting of any animal.
PS.C.28 Flora and If any wild animal is found near the construction site at any point of time, the contractor will
Chance found immediately upon discovery there of acquaint the Environmental Expert of SC / Environment Cel
Fauna of PWD and carryout the SC's instructions for dealing with the same.
The Environmental Expert of SC / Environment Cell of PWD will report to the nearby forest office
(range office or divisional office) and will take appropriate steps/ measures, if required in consultation
with the forest official etc.
529
Environmental
S. No. Management Measures
Aspect/Issue
All fossils, coins, articles of value of antiquity, structures and other remains or things of geologica
or archaeological interest discovered on the site shall be the property of the Government and shal
be dealt with as per provisions of the relevant legislation.
PS.C.29 Chance Found The contractor will take reasonable precautions to prevent his workmen or any other persons from
Archaeological removing and damaging any such article or thing. He will, immediately upon discovery thereof and
Property before removal acquaint the Environmental Expert of SC / Environment Cell of PWD of such
discovery and carry out the SC's instructions for dealing with the same, waiting which all work shal
PWD ENGINEERING MANUAL-2020 APPENDICES
be stopped.
The SC will seek direction from the Archaeological Survey of India (ASI) before instructing the
Contractor to recommence the work in the site.
Labour camp Contractor will follow all relevant provisions of the Factories Act, 1948 and the Building and the
PS.C.30 management - other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 for
Accommodatio construction and maintenance of labour camp.
n The location, layout and basic facility provision of each labour camp will be submitted to SC and
PWD prior to their construction.
The construction will commence only upon the written approval of the Environmental Expert of
SC / Environment Cell of PWD.
The contractor will maintain necessary living accommodation and ancillary facilities in
functional and hygienic manner and as approved by the SC & Engineer Incharge.
530
Environmental
S. No. Management Measures
Aspect/Issue
The Contractor will construct and maintain all labour accommodation in such a fashion that
uncontaminated water is available for drinking, cooking and washing.
The Contractor will also provide potable water facilities within the precincts of every work
place in an accessible place, as per standards set by the Building and other Construction
Workers (Regulation of Employment and Conditions of Service) Act,1996.
The contractor will also guarantee the following:
APPENDICES
Supply of sufficient quantity of potable water (as per IS) in every workplace / labor camp
site at suitable and easily accessible places and regular maintenance of such facilities.
Labour campIf any water storage tank is provided that will be kept such that the bottom of the tank at
management -least 1mt. from the surrounding ground level.
PS.C.31
Potable Water If water is drawn from any existing well, which is within 30 mt. proximity of any toilet, drain
or other source of pollution, the well will be disinfected before water is used for drinking.
All such wells will be entirely covered and provided with a trap door, which will be dustproof
and waterproof.
A reliable pump will be fitted to each covered well. The trap door will be kept locked and
opened only for cleaning or inspection, which will be done at least once in a month.
531
Environmental
S. No. Management Measures
Aspect/Issue
The contractor will provide garbage bins in the camps and ensure that these are regularly emptie
Labour campand disposed off in a hygienic manner as per the Comprehensive Solid Waste Management Pla
approved by the Environmental Expert of SC / Environment Cell of PWD.
PS.C.33 management
Waste Disposal Unless otherwise arranged by local sanitary authority, arrangements for disposal of night soil
(human excreta) suitably approved by the local medical health or municipal authorities or as
PWD ENGINEERING MANUAL-2020 APPENDICES
532
Environmental
S. No. Management Measures
Issue
APPENDICES
Performance enhancement provision for relocated temples, schools and other relocated structures;
status of rehabilitation of borrow areas; and utility of noise barriers.
PWD will ensure that all drains (side drains, median drain and all cross drainages) are
Maintenance of periodically cleared especially before monsoon season to facilitate the quick passage of
PS.O.2
Drainage rainwater and avoid flooding.
PWD will ensure that all the sediment and oil and grease traps setup at the water bodies
are cleared once in every three months.
The periodic monitoring of the ambient air quality, noise level, water (both ground and
surface water) quality, soil pollution /contamination in the selected locations as suggested
Pollution
MA. O.3 in pollution monitoring plan will be responsibility of PWD. PWD will appoint PCB
Monitoring
Atmospheric Ambient air concentrations of various pollutants shall be monitored as envisaged in the
MA. O.4 Pollution pollution- monitoring plan.
Roadside tree plantation will be maintained.
Noise pollution will be monitored as per monitoring plan at sensitive locations. Noise
control programs are to be enforced strictly.
PS.O.5 Noise Pollution
Monitoring the effectiveness of the pollution attenuation barriers, if there is any, will be
taken up thrice in the operation period.
Soil Erosion and Visual monitoring and inspection of soil erosion at borrow areas, quarries (if closed and
PS.O.6 Monitoring of rehabilitated), embankments and other places expected to be affected,will be carried out
Borrow Areas once in every three months as suggested in monitoring plan.
PS.O.7 Changes in Land PWD shall take initiative and act as facilitator to prepare an action plan for balanced
Use Pattern regional development in consultation with Local Development Authority and State
Government to control the ribbon development along the project road including new
bypasses. A land use regulation control, if applicable need to be adopted.
A land use-zoning map may be developed, under which upto a particular distance from
the ROW of the alignment especially in new bypass stretches, no development will be
allowed.
Necessary hoardings will be erected indicating the availability of ROW and legal charges
for encroachment of ROW. Budgetary provisions are to be made to control the ribbon
development along project road.
533
Annexure 1202B: Social Screening Format for Categorization of Social Impact
Part A
Name of theDepartment:
Name of theCircle:
Name ofDivision:
Districts covered by the Project:_
Name of Sub divisionResponsible:
Name & Address of the Officers Responsible
SuperintendingEngineer:
ExecutiveEngineer:
Sub DivisionalEngineer:
PWD ENGINEERING MANUAL-2020 APPENDICES
Category ofProject:
Part B
(Please tick mark (√) in the appropriate column and provide relevant information in Col.6)
3
Will there be loss of agricultural plots?
4
Will there be loss of seasonal crops?
5
Will there be loss perennial crops (yielding
and/or fruit bearing and other trees?
6 Will the project displace residential structures
(Houses)?
7 Will the project displace commercial structures
(shops workshops, factory and
other establishments)?
8 Will there be loss of structures other than
buildings? (Compound wall/gate/water tanks/
slabs/ wells/ septic tanks, etc
9 Are any cultural properties (place of worship,
religious structure,memorial,
monument, cemetery, etc) affectedor
displaced?
10 Are any community properties affected or
displaced?
11 Are any tenants running enterprises or
operating from the structures that would be
displaced?
12 Are there any tenants residing in the
structures that would be displaced?
Are there residential squatters within the
right of way?
534
13 Are there commercial squatters within the right
of way?
14 Are there residential and commercial squatters
within the right of way?
1. Social Screening sheet must be completed by all projects at Investigation Stage and forwarded to social
APPENDICES
cell for review, verification and records
535
Annexure 1202C: Social Impacts Data Sheet– to be attached with investigation Report
Residential properties
Commercial Properties
Residential & Commercial Properties
Agricultural Land
PWD ENGINEERING MANUAL-2020 APPENDICES
Land only
Land with minor structure
Land and building
F Community Properties
Land only
Land with minor structure
Land and building
Land and some public utility (specify eg. well)
G Squatters (Non-titleholders)
Residential
Commercial
536
Annexure1202D: Budget Estimate to be attached with Detailed Project Report
2 (a)
3 Compensation towards other immovable properties
APPENDICES
R and R Assistance and Activities
1 Shifting assistance
Executive Summary
537
Institutional Mechanism for Implementation andMonitoring
Criteria for Inclusion on PAP List
Methods for determining compensation
Appeal Procedures and Grievance Redressal Mechanism
Procedure and Mode of delivery of compensation and assistances
Monitoring and Evaluation System
The SIA report for S-2 Category Project shall pride the following:
Screening
Transect walk proceedings,
Analysis of alternatives
Consultation proceedings,
Impact Statement,
PWD ENGINEERING MANUAL-2020 APPENDICES
Explain the purpose and objectives of land acquisition and resettlement. Describe relevant national and state
policy pertaining to resettlement and rehabilitation applicable to the project and the relevant portion of the
LA act
Prepare entitlement matrix for all categories of loss including compensation rates and eligibility criteria.
If the project is financed by any bilateral agency, their policy requirements should be accommodated and
explained in thischapter.
CHAPTER IV: PUBLIC CONSULTATION, PARTICIPATION AND GRIEVANCE REDRESS
Identify project stakeholders, describe mechanisms used to ensure active participation of the primary,
secondary and tertiary, etc. of stakeholders in the planning, implementation, management, monitoring and
evaluation of the development project and the resettlement and rehabilitationcomponent.
Identify local organizations and institutions and suggest ways and means to support the affected population
Establish procedures for public consultation and redress of grievances of the affected population.
538
CHAPTER V: RELOCATION OF HOUSING AND SETTLEMENTS
Identify relocation options for all structures including housing, commercial establishments, cultural and
community properties including cash compensation and self-relocation. Specify measures to assist with
transfer and establishment at newsites
In extreme cases specify measures to include resettlement sites in land acquisition.
Specify means to safeguard livelihoods of the affected population.
Identify and suggest concrete measures to address gender issues and others related to vulnerable groups
Identify cultural and environmental risks precipitated by land acquisition and displacement and measures
to manage and monitor.
APPENDICES
Specify job opportunities and job creation plan; provision for compensating loss of livelihood, retraining
and skill up gradation forself-employment.
Prepare plan to relocate and restore business including income substitution.
Describe alternative options considered to minimize land acquisition and displacement. Explain why the
remaining effects (land acquisition and displacement if any) are unavoidable. Give a summarized version
of the key effects, the extent of land acquired, the assets people would lose and the people displaced from
homes or from their livelihoods oroccupations.
Describe the resettlement policy of the State which provides resettlement benefits to mitigate the negative
impact and the details of entitlements of the project affected persons and families
539
Chapter 3: Public Consultation, People‘s Participation and Grievance Redress
Describe consultation process and procedures, how the project will ensure participation of the affected
people in the awareness programs on the proposed project, the processes of land acquisition and
resettlement and how their grievances will beredressed.
Describe arrangement for valuing and disbursing compensation. Explain the arrangements that would be
made for relocation of housing and shifting of establishments. Describe livelihood restoration measures to
be implemented, as to how, when, where and by whom, and the mechanism to monitor the processes and
time-boundprogress.
Identify main tasks and responsibilities related to planning, implementing and monitoring land acquisition
and resettlement.
540
1500
All major PWD roads shall be designed in accordance with the relevant IS/IRC codes and practices. For
this purpose the following list of codes may be made referred.
IRC:32-1969 Standard for Vertical and Horizontal Clearances of Overhead Electric Powerand Tele
communication Lines as Related toRoads
IRC:38-1988 Guidelines for Design of Horizontal Curves for Highways and Design Tables (First
Revision)
IRC:39-1986 Standards for Road-Rail Level Crossings(FirstRevision)
IRC:41-1997 Type Designs for Check Barriers (FirstRevision)
IRC:54-1974 Lateral and Vertical Clearances at Underpasses forVehicularTraffic
APPENDICES
IRC:65-1976 Recommended Practice for TrafficRotaries
IRC:66-1976 Recommended Practice for Sight Distance onRuralHighways
IRC:69-1977 Space Standards for Roads in UrbanAreas
IRC:73-1980 Geometric Design Standards for Rural (Non-Urban)Highways
IRC:80-1981 TypeDesignsforPick-upBusStopsonRural(i.e.,Non-Urban)Highways
IRC:86-1983 Geometric Design Standards for Urban Roads inPlains
IRC:92-1985 Guidelines for the Design of Interchanges in UrbanAreas
IRC:98-1997 Guidelineson Accommodation of Underground Utility Services Along and Across
Roadsin Urban Areas (FirstRevision)
IRC:99-1988 Tentative Guidelines on the Provision of Speed Breakers for Control of Vehicular
IRC: SP: 12- 1973 Tentative Recommendations on the Provision of Parking Spaces for Urban Areas
IRC: SP: 23- 1983 Vertical Curves for Highways
IRC: SP: 41- 1994 Guidelines on Design of At-Grade Intersections in Rural & Urban Areas
541
1501. Classification of roads
The roads under PWD are classified as Expressways, National Highways (NH), State Highways (SH), and
Major District Roads (MDR), other District Roads as detailed below,
Expressways: The function of Expressways is to cater for movement of heavy volumes of motor traffic at
high speed. They connect major points of traffic generation and are intended to serve trips of medium and
long length between large residential areas, industrial or commercial concentration and the central business
districts.
National Highways (NH): These are main highways running through the length and breadth of the country
connecting major ports, highways of neighbouring countries, state capitals. These are the highways
connecting majorports, industrial and tourist centres with in the state and neighbouring states.
(c) State Highways (SH): These are arterial routs of a state linking district head quarters and important
cities within the state and connecting them with National Highways to the neighbouring state.
Major District Roads (MDR): These are important roads within a district serving areas of
production/markets and connecting these with each other or with the main highways.
Main Link roads (MRL): These are important roads within a district serving areas of
PWD ENGINEERING MANUAL-2020 APPENDICES
production/marketsandconnectingthesewithMDRs/SHs.
Other Village/muncipal roads: These are important roads within a district serving areas of
production/markets and connecting these with MDRs/SHs.
1502. Design Parameters
The main parameters involved in the design of any road is the traffic volume it has to cater to, the speed at
which the traffic flows, and the safety of vehicles in terms of sight distance considerations.
1502.1.Speed: Thedesignspeedistheexpected95thpercentilespeedofthemotorisedtrafficonthenew road in the
design year. The 95th percentile speed is the speed, which only 5% of vehicles will exceed. The choice of
design speed has a big influence on key aspects of highway design, especiallycurvature
In practice it is rarely possible to adopt a uniform design speed for the whole road - design speeds need to
vary from section to section to reflect differences in the road environment, terrain, etc. IRC SP 73 specifies
the design speeds for different types ofterrain.
1502.2. Volume: Traffic data is critically important in the design of roads. Traffic surveys must cover
motorised as well as non-motorised traffic. For new roads on completely new alignments it will be
necessary to assign traffic to them from existing roads and then make an allowance for generated traffic.
Usually mixed traffic volumes are expressed in PCU. The PCU factor for various vehicle types are available
in IRC 73 and the PCU ranges for various class of roads are in IRC 86
1502.3. Sight distance: The need to achieve minimum sight distance standards sets limits on how sharp
the curves can be. The details of sight distance for horizontal curves and vertical curves are given in IRC
73 and IRC SP 23 respectively. In the case of Rural Highways, IRC 66:1976 may be referred. There are
threemaintypesofsightdistancetoconsider:StoppingSightDistance(SSD),OvertakingSightDistance (OSD)
Intermediate Sight Distance(ISD).
1502.4. Stopping Sight Distance. This is the visibility necessary for a driver to be able to see an
obstructionintimetobringthevehicletoahaltwithout acollision.Thisisabasicminimumstandardfor two-lane
single carriageway roads. It is assumed that the driver‟s eye height is 1.2m and the height ofthe obstruction
is at least 0.15m above the roadsurface.
1502.5.Overtaking Sight Distance: This is the visibility necessary for a driver to be able to see whether
the road ahead is sufficiently clear to enable him to overtake a vehicle in front – even if an oncoming vehicle
appears after he has started the overtaking manoeuvre. It is a very long distance, especially at the higher
speeds, and it can be difficult toachieve.
1502.6. Intermediate Sight Distance: This is the visibility necessary for a driver to be able to see whether
the road ahead is sufficiently clear to enable him to overtake, assuming that he will abort the manoeuvre if
an oncoming vehicle appears before he has got level with the slower vehicle. ISD is much less than OSD
yet it permits reasonably safe overtaking. ISD is about twice SSD. It is assumed that the observer and the
obstruction are at eye height (1.2m).
1502.7. Geometric Design Standards: Geometric Design Standards for Urban Roads in Plains shall be as
per IRC: 86-1983 and for Rural (Non-Urban) Highways as per IRC: 73-1980. The space standards for Roads
in Urban Areas shall be IRC: 69-1977. In the case of Hill Roads Recommendations About the
542
Alignment Survey and Geometric Design of Hill Roads IRC: 52-2001 may be followed. Appendix 3.4
gives the standards for roads inJ&K.
1503. Cross Sectional Elements
1503.1. Building lines, Control lines, Land width, ROW
Desirable land width in metre for different classes of roads is indicated in Appendix 3.4. The same is also
shown in Figure 3.1
APPENDICES
Roadway
Carriageway
543
1503.4. Medians
Medians segregate traffic, provides protection from out-of-control vehicles, reduce glare at nighttime, and
acts as pedestrian refuge in urban intersections. For details the chapter on road safety may be referred.
1503.5 Culverts
Culverts must be designed for the entire carriageway width. IRC SP 13 may be referred for details of Culvert
design. Typical drawings are also given. IRC SP 20:2002 also details the different type of culverts.
1503.6. Utilities
Provision for Underground Utility Services Along and Across Roads in Urban Areas shall be as per IRC:
98-1997
1503.7. Bus Bays
In the case of highways, bus bays are to be provided to ensure that the other vehicles in the stream are not
obstructed due to stoppage of buses. The bus bays are usually of one lane width and the length varies
depending on number of buses that stop simultaneously. Details are included in the chapter on Road Safety.
1503.8. Footpath:
Roads passing through urban locales with considerable pedestrian traffic must be provided with footpaths.
PWD ENGINEERING MANUAL-2020 APPENDICES
From safety considerations, fencing may be appropriate. IRC 103 shall be referred for pedestrian facilities
Details are also included in the chapter on Road Safety.`
1503.9. Truck Lay byes
Highways usually cater to long distance truck traffic and facilities shall be provided for their parking. These
laybyes shall offer resting facilities for the drivers also. Length of lay bye shall be adequate to cater to peak
parking demand estimated on volume projections and average delay expected.
1503.10. Passing places
On hill roads, passing places are required to facilitate crossing of vehicles. These shall be provided at the
rate of 2 to 3 per km and each shall be of 20 to 30 m length and of 5.5m widths.
1503.11. Lateral and vertical clearances
Lateral clearance is the distance between the extreme edges of the carriageway to the face of the nearest
support, whether it is a solid abutment, pier or column.
Vertical clearance stands for the height above the highest point of the travelled way i.e. the carriageway and
part of the shallers meant for vehicular use (crown/ super elevated edge) to the lowest point of the overhead
structure/ overhangs. For details refer IRC 54. Standard for Vertical and Horizontal Clearances of Overhead
Electric Power and Telecommunication Lines as Related to Roads shall be as per IRC:32- 1969
1503.12.Emb
1503.12.Embankments
The details of embankment design are given in IRC 36 and IRC SP 20, and the Guidelines for the Design
of High Embankments as per IRC: 75-1979
1503.13. Drains
Drains are an integral part of road and must be provided for all roads. These must be permanent structures,
considering the heavy monsoons that the state is subjected to. Moreover, these must be properly maintained,
as otherwise, the entire road gets damaged. The main objective of drainage is to prevent early damage of
the pavement due to entry of excess of water and preventing saturation up to a dept of 1 m below the top of
the sub grade. This can be achieved by providing proper drainage. The two types are surface drains and
subsurface drains.
Details may be referred in IRC SP 42 and IRC SP 50.
1504. Horizontal Alignment
The alignment shall be as directional, fluent and matching well with the surrounding topography as
possible and also to avoid abruptchanges. On new roads, the curve shall be designed to have the large
practical radius, generally not less than the ruling value corresponding to ruling design speed given in
IRC:38-1988. Absolute minimum values based on minimum design speed may be used where economics
of construction and sight conditions so dictates. The radii below absolute minimum shall not be provided
Straight section exceeding 3 km length must beavoided
544
A curvilinear alignment with long curve is better from point of safety and aesthetics. Sharp curve shall not
be introduced at the end of long tangents, since this can be extremely hazardous. Curve shall be sufficiently
long and shall have transition curves at either end to eliminate shock due to application of centrifugal force.
Deflection angle less than 1 no curve is required to be designed. Reverse curves may be needed in difficult
terrain. Sufficient length between 2 curves shall be provided for introduction of requisite transition curve.
To avoid distortion, in appearance, the alignment shall coordinate with longitudinal profile
1504.1. Horizontal curves
The radius of curvature in horizontal curves is decided by the design speed of the road, side friction. In
general Horizontal curves shall consist of a circular portion flanked by spiral transition at both ends. Refer
IRC 38 and IRC 73 for details of horizontal curves, extra-widening super-elevation and setbackdistances.
1505.Vertical Alignment
The general alignment of the road shall follow the terrain as far as possible. Economy and aesthetics are
also of importance is choosing the longitudinal profile.
1505.1.Gradient
APPENDICES
The rate of rise or fall with respect to the horizontal along the length of road expressed as ratio or a
percentage is termed as gradient. Recommended gradients for different terrain conditions are given in IRC
73 and IRC SP 23
1505.2.Vertical Curves
Formula and length of Summit curves and Valley curves are as per IRC SP 23.
1506. Coordination of Horizontal and vertical alignment
Vertical and horizontal curves shall coincide and result in a smooth flowing appearance. If not possible, the
horizontal curve shall be somewhat longer than the vertical curve. Sharp horizontal curve shall be avoided.
If the horizontal scale is large and the vertical scale is relatively small, it may be satisfactory to include two
At grade intersections(Junctions)
The different types of at grade intersections are given in IRC SP 41. Recommended Practice for Traffic
Rotaries are as per IRC: 65-1976V
545
Grade Separate dintersections
An intersection layout that permits crossing manoeuvres at different levels is known as grade separated
intersection or an interchange. These are provided when the traffic volumes on the intersecting arms are too
heavy and results in long queues is being formed. Usually these are required in urban intersections where
both the roads are equally important. Also from a safety point, those intersections with high accident records
may be converted into grade separated intersections. IRC 92 gives the details for interchanges in urban
areas.
1509. Sub grade and Pavement
The road structure may be divided into four major components, Viz. Land, Earthwork, pavement and cross
drainage works. The types of pavement are
✓ Flexible Pavement
✓ Rigid Pavement
✓ Composite Pavement (Semi rigid and Roller Compacted Concrete) In case of rural roads, in view of the
stage development strategy and the initial cost advantage, the flexible pavement may be the appropriate
choice. Generally, the choice of pavement will be further guided by several other factors such as
PWD ENGINEERING MANUAL-2020 APPENDICES
1510.1. Pavement Thickness: The thickness of pavement is designed on the basis of projected number of
commercial vehicles, for the design life using the current commercial vehicles per day and its growth rate.
Based on the strength of granular materials that are used, the total design thickness is divided into base and
sub-base thickness.The principle criteria for determining the thickness of a flexible pavement with a thin
bituminous surfacing is the vertical compressive strain on top of the subgrade imposed by standard axle
load of magnitude 8.17 KN (870 Kg) Excessive vertical Subgrade strain causes permanent deformation in
the subgrade, which is manifested in the form of rutting on the pavement surface. The minimum recommend
pavement thickness is 450 mm for frost prone zones. For rigid and semi rigid pavements, tensile stress is
taken as design criteria. The detail design for flexible pavement may be as per IRC: 37 & IRC SP 72-2015
1512.1. Introduction
The design of Bridges shall be carried out as per the provisions and recommendations IRC/IS codes as per
list below. In case of IRC codes being silent about any design aspect, provisions in IS/ International codes
or general practice adopted in DESIGN WING (DIQC) may be followed.
546
1512.1.1. List of Codes to be referred for Design of Bridges
1. IRC: 5-1998 Standard Specifications and Code of Practice for Road Bridges, Section I –
General
Features of Design (Seventh Revision)
2. IRC: 6-2000 Standard Specifications and Code of Practice for Road Bridges, Section II – Loads
and
Stresses (Fourth Revision)
3. IRC:18-2000 Design Criteria for Prestressed Concrete Road Bridges (Post-Tensioned Concrete)
(Third Revision)
4. IRC:21-2000 Standard Specifications and Code of Practice for Road Bridges, Section III –
Cement
Concrete (Plain and Reinforced) (Third Revision)
5. IRC:22-1986 Standard Specifications and Code of Practice for Road Bridges, Section VI –
APPENDICES
Composite Construction (First Revision)
6. IRC:24-2001 StandardSpecificationsandCodeofPracticeforRoadBridges,SectionV–SteelRoad
Bridges (Second Revision)
7. IRC:40-2002 Standard Specifications and Code of Practice for Road Bridges, Section IV –
Brick,
Stone and Block Masonry (Second Revision)
8. IRC:78-2000 Standard Specifications and Code of Practice for Road Bridges, Section VII –
Foundations and Substructure (Second Revision)
547
1512.2. Design Data Required for Design of Bridges
For all bridges to be designed in the make a complete investigation of the site and the design data and
required drawings shall be prepared and submitted along with the proforma given in Appendix1500A.
The other documents required to be submitted along with the investigation report are alignment plan
approved by the Design wing and checklist given in Appendix 1500B & 1500C
1513. Design Procedure for Bridges
1513.1. Preliminary Design: The ARO shall study the investigation details and alignment particular bridge
and shall make note on any modification required for the above alignment plan considering the various
design aspects. The ARO shall also make preliminary design of the bridge in the form of a proposal drawing
and submitted to the superior officers, if the modifications required in the alignment plan are of trivial
nature. If any major alterations are required in the alignment plan, the same may be intimated to the Chief
Engineer with specific recommendations for revision and approval. After receipt of the revised approved
alignment, a proposal drawing shall be prepared on the basis of the same and forwarded the Chief Engineer
who shall subsequently furnish a feasibility report considering the various construction and economic
aspects of the proposed bridge at the site.
PWD ENGINEERING MANUAL-2020 APPENDICES
1513.2. Detailed Design: Based on the feasibility report furnished and the alignment plan approved by the
DCW, the Assistant Director shall do a general and detailed design of the bridge. The design shall be done
by manually or by using approved computer software. In both cases a design volume shall be maintained
and approved by the CE. The DRO shall check the general arrangement and detailed design drawing
designed by the ARO. The D.R.O shall review the same and the R.O shall recommend the drawings to
DCW for approval. The CE may entrust the whole design to outside consultant also if found necessary.
1514. Geometrical Criteria
1514.1. Width of Carriageway, Footpath, Median and Kerb; This shall be as per the provisions of IRC
5.
1514.2. Longitudinal Gradient: The Engineer in charge of design has to consider all aspects such as
construction costs, practical problems in construction at the site and the vehicle operation cost, before
finalizing the gradients. Based on the topography of site, IRC has recommended the following categories
of gradients for roads which shall be applicable to bridges also.
Terrain Ruling Limiting Exceptional
gradient Gradient Gradient
a) Plain or rolling 3.3 % (1 in 30) 5 % (1 in 20) 6.7 % (1 in 15)
b) Mountainous terrain 5 % (1 in 20) 6 % (1 in 16.7) 7 % (1 in 14.5%)
c) Steep terrain 6 % (1 in 16.7) 7 % (1 in 14.5%) 8 % (1 in 12.5%)
Where non-motorised vehicle are likely to use the structure more appropriate lower gradients shall be
utilized, but may need to a balance against cost and other environmental issues.
1514.3. Cross gradient
The deck cross gradient shall be adopted with a view that in localities with lower rainfall, a flatter camber
and in places with high rainfall, a steeper camber. The values of cross gradient recommended by IRC for
different types of road surfaces are as follows, which shall be applicable to bridges also.
Range of cross gradient in areas of rainfall
Type of surface coat Heavy to Light
Cementconcrete 2.0%(1in50)to1.7%(1in60)
Bituminous 2.5%(1in40)to2.0%(1in50)
1514.4.Gradients, Super Elevation
If there is a change of gradient on the bridge deck, suitable vertical curve shall be introduced conforming
to the stipulations contained in IRC: SP-23. The super elevation on the deck of a bridge on a horizontal
curve shall be provided in accordance with the relevant IRC Road Standards.
1514.5. Clearances
The minimum vertical and horizontal clearance (clear height and width respectively available for passage
of traffic) to be provided on bridges shall be as specified in IRC:5. For vertical and horizontal clearances at
under passes and / rail over bridges the essential provisions of the code has to be followed.
548
1516. Hydraulic Criteria
1516.1.DesignDischarge: The design discharge, for which the waterway of the bridge is to be designed,
shall be based on maximum flood discharge of 50 years return cycle. In case where the requisite information
is not available, the design discharge shall be the maximum estimated discharge determined by the methods
suggested in IRC:5 or any other rational method. The investigation report shall contain the discharges
obtained by the different methods suggested in IRC: 6.
1516.2. Effective Linear waterway, Afflux and Scour depth
The effective linear waterway may be compared with that provided under other bridges in the vicinity over
the same river after duly considering their performance. IRC 5 may also be referred.
For calculation of afflux IRC SP: 13 may be referred to. To calculate the maximum scour depth, IRC: 5 and
IRC SP: 13 shall be followed.
1516.3. Loading Criteria
The Loading criteria to be adopted for all the bridges are as per IRC: 6.
1517. Selection of Type of Bridge and Span Arrangement
APPENDICES
1517.1.General Considerations: Specific site characteristics like width of crossing, nature of stream, depth
of flow, depth of flow during different seasons, subsoil characteristics, and the capabilities of contracting
agencies, who would be interested in building the structure including the availability of skilled and
unskilled labour are mostly the major considerations in selecting the type of structure and span
arrangements in specialized structures like long span bridges. The attempt of the engineers shall be towards
minimising the overall cost of the total structure including approaches within the site-specific constraints
as obtained. For normal simply supported structures, it has been observed that the total cost of the bridge
proper tends to be the minimum, when the cost of superstructure approaches to that of foundation and
substructure put together which may be applied as a thumb rule for initialtrial.
549
However,wheneveraneconomicalspanarrangementandtypeofstructureisdecided,ithastobeensured that
the required infrastructure facilities, design and construction capabilities, specified materials etc. are
available.
1518. Superstructure
It is the superstructure of a bridge that directly supports the traffic and facilitates its smooth
uninterrupted passage over natural/man made barriers like rivers, creeks, railways, roads, etc. by
transmitting the loads and forces coming over it to the foundation through the bearings and substructure.
The minimum functional requirement of superstructure is mentioned in section 1617.2. Consistent with
economy and local availability of the materials, labour and technology for a particular type of
superstructure selection may have to be made out of the following: i) Reinforced cement concrete
superstructure: These are the most poplar type of superstructure in the present day which may take the
form of solid slab, voided slab, T-beam and slab, box girder, rigid frame, arch, balanced cantilever or
bow-string girder. ii) Pre-stressed concrete superstructure: This may also take any of the above forms
PWD ENGINEERING MANUAL-2020 APPENDICES
referred in the previous paragraph. Care shall be taken about the provision of future pre- stressing to the
extent of 20 per cent of total pre-stress force. For this purpose, dummy cables may be laid in the
structure, which can be used for further pre-stressing if the need arises afterwards. iii) Steel
superstructure: With increasing availability of quality steel at international prices in recent years the use
of steel for superstructure is becoming attractive option. The forms, these may take are steel beam, plate
girder, box girder, steel truss, arch, cantilever suspension bridges and cable stayed bridges. Any
combination of above materials considering their distinct advantages for particular elements may be
adopted. Most common types of composite construction are cast in situ or pre-cast girder in prestressed
concrete with RCC deck or steel beam/plate girders with RCC deck or cable stayed bridges with RCC
or PSC deck.
1518.1.Design
Relevant IRC Codes which have to be complied in the design of superstructure are IRC: 40, IRC: 21,
IRC: 18, IRC: 24, IRC: 22 for Masonry, RCC, PSC, Steel and Composite Structures respectively. Other
codes applicable for all types of superstructures are IRC: 5 and IRC: 6. Other major guidelines also
include IRC: 85. In case of IRC codes silent about some design aspects, provisions in the
IS/International Codes may be followed.
1518.2. Standard Plans (Type designs)
Wherever possible the adoption of standard plans prepared by the MoRTH shall be followed for
superstructure. These will obviate detailed individual designs for bridge decks and ensure that drawings
are available on time and also maintain accuracy in design.
550
Ministry of Road Transport & Highways have brought out various standard plans which include
standard plan for:
No. Type of Deck Skew Overall Effective span (m)
Angle width of
deck(m)
1.a. RCC Solid Slab without 0° 8.45 3.37, 4.37, 5.37, 6.37, 7.37, 8.37, 9.37,
footpath 10.37
1.b. RCC Solid Slab with footpath 0° 11.05 3.37, 4.37, 5.37, 6.37, 7.37, 8.37, 9.37,
10.37
1.c. RCC Solid Slab without 15°,30° 8.45 5.37, 6.37, 8.37
footpath 45°,60°
1.d. RCC Solid Slab with footpath 15°,30° 11.05 4.37, 6.37 & 8.37
45°,60°
APPENDICES
1.e. RCC Solid Slab with and 0° 12.00 3.00, 4.00, 5.00, 6.00, 7.00, 8.00, 9.00,
without 10.00
Footpath
1.f. RCC Solid Slab without 15°, 12.00 4.00, 6.00, 8.00, 10.00
footpath
22.5°, 35°
2.a. RCC T-beam and slab without 0° 8.45 10.5, 12.5, 14.5, 16.5, 18.75, 21.75, 24.75
footpath (3 girders)
2.b. RCC T-beam and slab with 0° 11.05 10.5, 12.5, 14.5, 16.5, 18.75, 21.75, 24.75
1519.Bearings
The design of metallic bearings and neoprene bearings shall be in conformity with IRC: 83 Parts I &II.
and clause 2000 of Specifications for Road and Bridge Works published by Ministry of Road Transport
and Highways (MoRTH)
(MoRTH) carries out pre-qualification of the manufacturers of bearings from time to time. The pre-
qualification is valid for a certain period. Bearings have to be procured from such manufacturers only.
1520. Sub-structure
Substructure include those portions of a bridge which are above the foundation which include piers,
abutments, abutment and pier caps, dirt wall, returns, wing wall etc. but excludes bearings and
superstructure. It can be built of brick/stone masonry, plain/reinforced/pre-stressed concrete, steel.
Selection of a particular type of sub structure depends upon the span and type of superstructure, the
height of substructure, availability of construction material and construction equipments, period and
time of construction and above all on overall economy. The shape of piers and abutments in general,
shall be such as to cause minimum obstruction to flow of water.
1520.1.General Considerations:
The following general conditions are to be followed for the construction of substructures: i) On all
exposed faces of concrete member a minimum reinforcement equivalent to 2.5 kg/sq.m. shall be
provided to withstand stresses due to temperature and shrinkage with maximum spacing limited to 200
mm. ii) The width of abutment and pier cap shall be fixed on the basis of design and construction
requirement. Further it shall be sufficient to accommodate not only the bearings but also an offset of
150 mm beyond the edges of the bearings and also facilitate inspection and repairs of bearings. The
thickness of such caps shall not be less than 225m1m19 up to a span of 25 m. iii) In skew bridges, where
551
bearings are placed at right angles to the longitudinal axis of the bridge, the top width of the
piers/abutment has to be more compared to right bridges in order to have a clear distance of 150 mm
beyond the edges of bearings. iv) It is desirable to lay the abutment caps and the dirt walls over
abutments with the same concrete and in one operation, and make them monolithic by detailing the
reinforcement properly, to avoid cracking at the junction of the two components. v) The top of wing
return walls shall be carried 100 mm above the top of the slope of embankment to prevent any soil from
being blown or washed away by rain. vi) Length of cantilever returns where adopted, shall not be more
than 3.5 metres. vii) All abutments shall be designed for a live load surcharge equivalent to
1.2 m height of earth fill. viii) All wing walls or return walls provided for full height of approaches shall
be designed to withstand a live load surcharge equivalent to 0.6 m height of earth fill. ix) The fill behind
abutments, wing walls, and return walls shall conform to specifications given in IRC:78. x) Suitably
designed cut and ease waters shall be provided in piers up to affluxes High Flood Level or higher from
consideration of waves, etc. xi) If the height of pier exceeds 6 metres, R.C.C. piers may be preferred.
1520.2. Design: Sub-structure shall be designed to withstand the loads and forces as specified in IRC:6,
the worst combination of forces and factors of safety shall be as specified in IRC:78. For allowable 108
PWD ENGINEERING MANUAL-2020 APPENDICES
stresses and other design requirements, IRC Codes depending upon the type of construction material
shall be followed.
1521. Bridge Foundations
The foundations for piers and abutments shall be at such depths that they are safe against scour and
large impacts where necessary and are protected against it. They shall be taken down to a level sufficient
to secure firm foundation from consideration of bearing capacity, overall stability and suitability of the
strata at founding level and sufficient depth below it. The subsoil characteristics obtained at a particular
site and consequently the type of foundations feasible is one of the major considerations in selection of
type of structure and span arrangement.
It is necessary to evaluate, in advance, at the preliminary design stage, the pros and cons of choice of a
particular type of foundation. The selection of wrong type of foundation may lead to delay in
construction, increase in cost, and distress during construction and sometimes impossibilities of
realizing technical requirement. In order to avoid such difficulties that may arise during execution stage,
alternative foundation types shall be suggested in the Proposal Drawing. The concerned authority in the
field office shall study the pros and cons of constructing the suggested types of foundations and shall
record a note about the same in the feasibility report. Based on the above report,
the type of foundation shall be fixed by the engineer responsible for the design. R efer IRC 78 for
different types of foundations.
1522. General Considerations and Design
All Bridges within 20 km of the Saline/Alkline water shall be given anti corrosive treatment for
reinforcements as per specifications for Road and Bridge Works published by (MoRTH) and IS 13260.
Epoxy painting may be given to all exposed surface of RCC structural elements in such area; similar
treatment may also be done in areas prone to industrial/environmentalpollution.
1522.1. Open foundations:
The design aspects of open foundations can be obtained from IRC: 21 and IRC: 78. Excavation on open
foundations shall be done after taking necessary safety precautions for which guidance may be taken
from IS: 3764.
1522.2. Well foundations:
Well foundation shall be designed to withstand the loads and forces as specified in IRC: 6, the stability
and design of well foundations shall be done under the most critical combination of loads and forces as
specified in IRC: 78. The pressure on foundations shall also satisfy the provisions of IRC:
78. For allowable stresses and other design requirements, IRC: 21 shall be followed.
1522.3. Pile foundations:
Piles shall be designed to carry uplift and lateral loads besides direct vertical load. The worst
combination of forces and factors of safety shall be as specified in IRC: 78. For design of piles guidance
may be taken from IS: 2911 subject to limitations/stipulations given in IRC: 78. For allowable stresses
and other design requirements, IRC: 21 shall be followed.
552
1522.4. Expansion Joints
Expansion joints are provided at the end of deck and cater for movement of deck due to temperature,
shrinkage, creep etc. Expansion joints make the deck joint leak proof, protect the edges of slab/girder
and allow smooth passage of loads from one span to other by bridging the gap. Depending upon the gap
width to be bridged, there are various types of expansion joints in use at present. IRC 83- part Part II
and I may be referred for details regarding expansion joints. Specifications for Road and Bridge Works
published by (MoRTH) have issued interim specifications for expansion joints and subsequent
modifications in the list of manufacturers/suppliers, which may be followed. Further, a warranty of 10
years of trouble free performance may be insisted upon from the contractors/suppliers for all type of
joints except for buried joints and filler joints.
1522.5. Railings, Parapets or Guide Posts and Crash Barriers
The forces to be considered in design of Railings, Parapets or Guide Posts and Crash Barriers shall be
shall be as per relevant stipulations of IRC:6. For R.O.Bs across railway lines, those for railway‟s safety
shall govern these requirements.
APPENDICES
1522.6. Surface Finishes and Drainage of Carriageway
All carriageway and footpath surfaces shall have anti-skid characteristics. Average 75 mm thick M20
cement concrete with temperature steel shall be provided for wearing coat with necessary camber and
over it a uniform treatment of 25mm mastic asphalt top layer for waterproofing. Alternately wearing
coat as specified in Specifications for Road and Bridge Works published by (MoRTH) may be provided
depending on site condition. 109 The deck has camber or super elevation, which guides rainwater
towards Kerbs/Devri stones, and waterspouts located near the kerb further disposes the water out. One
waterspout per 20 sq.m. of the deck area is considered adequate and the spacing shall not exceed 10 m.
The spout shall have diameter not less than 100 mm and shall be of corrosion resistant material such as
553
difficult situations, the Engineer responsible for the design may at his discretion permit a reduction in
the minimum straight length of approaches, provided reasons for making a departure from the Code are
clearly recorded in the proforma for Design Data submitted along with the Investigation Report. The
investigation reports shall be accompanied by land plan clearly marking the land to be acquired from
private and public bodies and the extend of each category along with the duly completed social impact
check list. Where horizontal curves have to be provided on the approaches beyond the straight portion
on either side, the minimum radius of curvature, the super elevation and transition length for various
speed and the curve radii shall be provided in accordance with relevant stipulations contained in IRC:
38. If there is a change of gradient, suitable vertical curves shall be introduced conforming to relevant
stipulations contained in IRC: 23. Minimum surfaced width of these straight lengths of approaches shall
be equal to the carriageway width on the bridge. Reinforced concrete approach slab covering the entire
width of roadway shall be provided as per the details given in the Detailed Design Drawing of the
particular bridge. The minimum length of approach slab shall be 3.5 meters and the minimum thickness
as 150 mm. If the approaches is in filling, borrow pits shall not be dug close to the embankment to avoid
risk of parallel flow being developed which may endanger safety of the embankment. In this connection,
PWD ENGINEERING MANUAL-2020 APPENDICES
554
Set of original Architectural drawings and CD from DIQC or through website/ webportal.
Copy of Administrative approval to the estimate of the structure, (based on approved Architectural
drawings.)
Soil investigation details.
Proposed construction programme i.e. proposed dates of start of different stages of construction and
scope of different phases of construction in case of phased construction from the Executive Engineers
office.
After the Executive Engineer submits the required documents and architects design on a CD or through
web Portal to the Design Wing (Signed copies also to be forwarded), the Final design shall be prepared
and forwarded to the EE/SE/ CE as per TS issuing powers by the Executive Engineer
/concern officer. The Architects plan shall also be forwarded to Electrical wing simultaneously,
forpreparing layout of electric installations and concerned Executive Engineer for preparing sanitary
and water supply details.
1524.2.Design Philosophy
APPENDICES
design of buildings is being carried out mainly by three methods of design. They are namely: (1)
Workingstressmethod,(2)Ultimateloadmethodand(3)Limitstatemethod.
The Limit state method is now in vogue in all government design offices and premier private consulting
firms .The B.I.S. have published I.S.: 456-2000 incorporating the use of Limit state Method of design.
Working Stress Method: Used over decades, this method is now practically outdated in many advanced
countries of the world, because of its inherent limitations
The I.S: 456-2000 code gives emphasis on Limit State Method which is the modified form of Ultimate
Load Method .
Besides analytical part of structural design, following factors shall also be kept in mind while designing
555
14. I.S.: 1893-1984 Criteria for earthquake resistant design of structures.
15. I.S: 1904-1986 Code of practice for design & construction of pile foundation in soil structural
safety of building foundation.
16. I.S. 2911-1990 Code of practice for design and construction of pile (Part I to IV) foundation.
17. I.S. 2950-1981 Code of practice for design and construction of raft foundation.
18. I.S. 3370-1965 Code of Practice for water retaining structures.
19. I.S. 3414-1987 Code of Practice for Design and Installation of joints in buildings.
20. I.S. 4326-1993 Code of practice for earthquake resistant design of structure.
21. I.S. 6403-1981 Code of practice for Determination of bearing pressure of shallow foundation . 112
22. I.S.13920-1993 Code of practice for ductility detailing of reinforced concrete structures subjected
to seismic forces .
Latest revisions of above code shall be followed
I.S. Codes are also available for design of special types of structures like folded plate, shell structures
etc. Refer publication list of BIS for the same.
Similarly there are special publications of I.S., which are useful for design of buildings such as.
PWD ENGINEERING MANUAL-2020 APPENDICES
For aspects, which are not covered by any other I.S. codes available, relevant International Standard
Codes may be referred to. While designing R.C.C. structures, important provisions (as detailed below)
of I.S. 456 must be borne in mind.
General Provisions
Clause No. 20 Deals with stability of the structure against overturning and sliding.
Clause No. 26.2.1: Development length of bars.
Clause No. 26.3.2: Minimum distance between individual bars.
Clause No.26.3.3: Maximum distance between bars in tension.
Clause No.26.4: Cover to reinforcement.
Clause No.27: Expansion joints.
Provision regarding slabs
Clause No.22.2: Effective span.
Clause No.22.4.1: Arrangement of live load.
ClauseNo.22.5:Momentandshearco-efficientforcontinuousbeams.
Clause No.23.2: Control ofdeflection.
Clause No.24.1: Provisions regarding solid slabs.
Clause No. 26.5.2.1: Minimum reinforcement.
Clause No.26.5.2.2: Maximum diameter.
Provisions regarding beams
Clause No.22.2: Effective span
Clause No.22.4.1: Arrangement of live load.
Clause No. 22.5: Moment and shear co-efficient for continuous beams.
Clause No. 23.2: Control of deflection.
Clause No. 23.3: Slenderness limits for beams.
Clause No. 26.5.1.1: Tension Reinforcement.
Clause No. 26.5.1.2: Compression reinforcement.
Clause No. 26.5.1.3: Side face reinforcement.
Clause No.26.5.1.5: Maximum spacing of shear reinforcement.
Clause No.26.5.1.6: Minimum shear reinforcement.
556
Clause No.26.5.1.7: Distribution of torsion reinforcement.
APPENDICES
Clause No.34.4: Transfer of load at the base of column.
557
Appendix- 1500 A
DESIGN DATA FOR MAJOR AND MINOR BRIDGES
A. General
1. Name of Road :
2. Classification of Road : SH / MDR / ODR
3. Road chainage at centre :
4. Land width of road :
5. Formation width of road :
6. Width of Roadway :
PWD ENGINEERING MANUAL-2020 APPENDICES
C. Nature of Stream/Canal:
15. Is the stream
a) alluvial with erodable banks :
b) quasi-alluvial with fixed bed but erodable banks :
c) rigid with inerodable bed and banks :
16. Is the stream
a) perennial : Yes/No
b) seasonal : Yes/No
c) tidal : Yes/No if so
i) High Tide Level (HTL) :
ii)Low Tide Level (LTL) :
d) saline : Yes/No e) polluted with any industrial waste : Yes/No if so, specify thepredominant
chemicals in the waste:
17. Hydraulic particulars at low water level
a) Low Water Level (LWL) :
b) observed water surface velocity :
c) water surface slope :
d) bed slope :
18. Hydraulic particulars at high flood level :
a) High Flood Level (HFL)
i) at site :
ii) at u/s cross section :
iii) at d/s cross section : (specify distance of u/s & d/s from site)
b) estimated water surface velocity :
c) water surface slope :
558
d) area of cross section
i) at site :watersurfaceslope :
area of crosssection at site :
D. Ventway Parameters:
APPENDICES
22. Vertical clearance above HFL required for navigation:
23. Horizontal clearance required for navigation:
24. Does the stream carry drifting matter in floods? :
25. Details of training works, if needed:
Alignment andapproaches:
26. Whether the bridge proposed is right or skew? : if skew, give the angle of skew :
27. Whether the approaches straight? : if not
i) straight reach and radius of curve at side-1 :
Superstructure:
31. Loading to be done for (Class A / 70R):
31. Proposed clear roadway over the bridge:
32. Width of footpath, if any:
33. Formation level
i) at centre of bridge:
ii) at abutment points:
34. Number and size of span recommended:
Foundations:
Foundations recommended: Open / Well /Pile
559
H. ExistingStructures
Details of each of the existing bridges on the stream/canal in thevicinity
No. Details Upstream Downstream
a) Distance from site
b) Number and size of spans
c) Year of construction
d) Type of structure
e) Width of roadway
f) Provision of footpath
g) Vertical clearance
h) Horizontal clearance
i) Type & depth of foundations
j) Whether the existing structure
PWD ENGINEERING MANUAL-2020 APPENDICES
is trouble free
k) Any other information
I. Miscellaneous
Name of town nearest to the bridge:
Nearest Railway station and its distance from bridge site:
Is the site located in an industrially or otherwise polluted area:
(If so, specify the predominant air and water pollutant):
Nature of terrain: Plain/Rolling/Hilly
560
Appendix 1500B
CHECK LIST OF DETAILS REQUIRED FOR APPROVAL OF ALIGNMENT
Road/ Bridge
Name of Work:
S.E.‟s Authentication in all drawings and data: Yes/No
Investigation report: Yes/No
Form D.A. Completely filled up: Yes/No
Design Data form completely filled up: Yes/No
Index map (Districtmap): Yes/No
Key map (siteplan): Yes/No
Two copies of Alignment plan with the following details: Yes/No
Names of stations connected: Yes/No
North direction: Yes/No
Name of River: Yes/No
APPENDICES
Direction of flow: Yes/No
Skew angle(ifany): Yes/No
Width of riveratHFL: Yes/No
Proposed Land width(available/tobeacquired): Yes/No
Continuous chainages ofapproachroads: Yes/No
Bore hole locations with chainages: Yes/No
Strip plan for affected properties: Yes/No
Social impact assessment (SIA) reports. If theimpactfall
within category AorB Yes/No
561
Appendix 1500C
CHECK LIST OF DETAILS REQUIRED FOR DESIGN OF ROADS/ BRIDGE
Name of Work:
S.E.‟s Authentication in all drawings and data: Yes/No
Copy of Administrative Sanction obtained: Yes/No
Investigation report: Yes/No
Design Data form completely filledup: Yes/No
Index map (Districtmap): Yes/No
Key map (siteplan): Yes/No
Catchmentareamap: Yes/No
Two copies of approved Alignment plan with the following details: Yes/No
Names of stations connected: Yes/No
North direction: Yes/No
Name of River: Yes/No
PWD ENGINEERING MANUAL-2020 APPENDICES
If any of the above items is marked as „No‟, the reasons for the same shall be indicated along with
this.
2 Italicised details not required for roads.
562
APPENDIX 1600 A1
Model Preliminary estimate for Road Works
Name of Project Name of Division, subdivision, section. (Constituency also)
Part I. Acquisition of site.
(a) Land acquisition.
(b) Acquisition of structures and R& R cost.
(c) Shifting of electrical lines, Telephone/Telegraph lines, Pipe lines etc.
Part II. General improvements.
(a) Felling trees.
(b) Earthwork-widening, raising and/or forming embankments.
(c) Blasting rock.
(d) Conveyance of materials.
Part III. Masonry works.
APPENDICES
(a) Retaining walls.
(b) Construction of culverts.
(c) Construction of small bridges.
Part IV. Surfacing
(a) Gravelling or soling and/or metalling.
(i) Supply of materials.
(ii) Spreading & consolidation of materials to form the road.
(iii) Forming the sides.
(b) Remetalling.
(i) Supply of materials.
563
APPENDIX 1600 A2
Model Preliminary Estimate for Bridge Works
Name of Project Name of Division, subdivision, section. (Constituency also) Part I. Acquisition of
site,
(a) Land Acquisition.
(b) Acquisition of structures and R & R cost.
(c) Shifting of electrical lines, Telephone lines, Telegraph lines, Pipe lines etc.
(d) Felling trees.
Part 11. Construction of temporary site office and working yard when necessary.
Part III Foundation.
Part IV. Sub-structure.
Part V. Super-structure.
Part VI. Approaches.
(a) Earth work filling/Cutting including conveyance if any.
(b) Blasting rock.
PWD ENGINEERING MANUAL-2020 APPENDICES
564
APPENDIX 1600 A3
Ill. Model Preliminary Estimate for Building Works
Name of Project
Name of Division, subdivision, section. (Constituency also)
Part I. Acquisition of site-. .
(a) Land acquisition.
(b) Acquisition of structures, if any.
(c ) Resettlement and Rehabilitation cost
(d) Shifting of Electrical lines/ telephone/Telegraph lines and Drainage Sewer Pipe lines.
Part II. Preparation of site.
(a) Clearing and levelling site.
(b) Demolishing existing structures, felling trees etc., if any.
Part III. Earth work.
(a) Earth work for foundation.
(b) Filling basement.
APPENDICES
Part IV. Sub-structure and super-structure.
(a) Foundation.
(b) Basement.
(c) Superstructure.
(d) Wood work for doors and windows etc.
(e) Roof timber/trusses.
(f) M. P. tiled/A. C. Sheet/RCC/Roof.
Part V. Finishing items.
(a) Flooring.
(b) Ceiling.
Part VII
(a) Compound wall/Enclosures. (b)
Approach roads.Part VIII. Tools and Plant.
Part IX. Value of departmental materials such as rubble credited, if any
Part X. Miscellaneous
a) Lift
b) Firefighting
c) HVAC
d) Storm water storage
Part XI. Other items.
(a) Contingency.
(b) Difference in value between recovery rate and issue rate of materialsetc.
(c) Cost for project preparation including investigation and design.
565
Appendix 1600 B Docket Sheet
ISSUE OF TECHNICAL SANCTION
Name of Division
Name of Sub Division
PWD ENGINEERING MANUAL-2020 APPENDICES
Name of Work
Amount of Estimate
Reference to Administrative Sanction
Register Number and date of estimate
Source of funds
Duration in which work has to be executed
Signature of Engineer
566
Appendix 1600 B1
PreliminaryEstimateReport
1. Name of Work and Scope
2. Authority and Plan Provision
3. Climatic, Geographic and Historic details
4. Necessity/Justification (with traffic counts): Reasons for justifying the work, based on traffic
intensity, proximity and location in relation to important town and industrial and commercial centres,
educational institutions, hospitals etc., which will be served by the road.
5. Existing facilities
i) Road way
ii) Transport
iii) Pavement and Shaller Condition
iv) Cross drainage facilities
6. Engineering facilities required for transport
APPENDICES
i. Classification as per standards.
ii. Alignment with respect of topographical features, bridge sites, important town etc.
iii. Gradient
iv. Type of pavement and surfacing
v. Geometries with reference to the general standards for different classifications.
vi. Protective works required
vii. Drainage facilities and cross drainage works with location and type of each work
viii. Any other technical features as may be found necessary
7. Timeframe to complete proposed project
8. Plans including an index map, location map showing alternative proposals, LS and typical CS.
567
PWD ENGINEERING MANUAL-2020 APPENDICES
Appendix 1600B2
(Details to be incorporated in Preliminary Project Reports for Bridges)
1. Name of Work and Scope
2. Authority and Plan Provision
3. Climatic, Geographic and Historic details
4. Necessity/Justification (with traffic): Reasons for justifying the work, based on traffic intensity,
details of the bridges crossing the river within a reasonable distance of the proposed bridge.
5. Existing facilities
6. Engineering features giving:
i. Class of road in which bridge is proposed and Technical standards for bridge. ii.
Flood characteristics and maximum flood discharge in the stream.
iii. Periods of high flood levels for a number of years.
iv. Soil and sub soil particulars at the site v.
Type of foundation
vi. Type of superstructure suggested.
vii. Angle and direction of skew if any.
viii. Number of spans
ix. Any other technical details as may be necessary
7. Plans viz, index plan, site plan, LS of stream, cross section of stream at site of bridge and at 30
metres upstream and downstream etc.
8. Cross sections of the stream within 250 M. upstream and down stream where the stream is
appreciably narrower than the proposed site (if any)
9. Rough cost estimate with break up of cost under major heads viz, land acquisition, EW,
pavement, surfacing, protective works, cross drainage works as per Appendix 3.13 b.
10. Timeframe to complete proposed project
568
Appendix 1600 B3
(Details to be incorporated in Preliminary Project Reports for Buildings)
1. Name of Work and Scope
2. Authority and Plan Provision
3. Climatic, Geographic and Historic details
4. Necessity/Justification for the building
5. Details of Existing Facilities and Structures
6. Engineering aspects giving i.
Site condition
ii. Accessibility viz. approaches roads and internal roads within colonies. iii.
Nature of terrain
APPENDICES
iv. Sub soil particulars v.
Prevailing winds
vi. Type of buildings proposed vii.
Type of foundation suggested
viii. Proximity to water and power supply
7. Plans viz, Index map, site plan with layout and line plan of the buildings.
8. Rough cost estimate as per Appendix 3.13 c
Note: i. The sites for buildings shall be chosen in consultation with the Department for which it is
constructed.
569
Appendix 1600 C
Docket sheet (preliminary report / detailed report)
J&K Public Works Department
Circle.. Division..
SubDivision. ………………………….
Section..
Name ofwork:
Amount of Administrative Sanction*:
Reference to Administrative Sanction*:
Source offunds:
Head of classification as per viz. major head, minorhead, departmental headand
PWD ENGINEERING MANUAL-2020 APPENDICES
570
Appendix 1600 D
Checklist for Detailed Estimate Report
APPENDICES
8. Details of land acquisition, demolition, Resettlement and Rehabilitation etc.
9. Timeframe to complete proposed project
10. Detailed drawings and designs
11. Itemised detailed estimate
* Note :
(1) An estimate report explaining the location, length of roads and other salient features of the works proposed,
and a site plan shall be furnished.
(2) All the items indicated in the model estimates may not be required in all cases. Where an item is not
required, it may be indicated as 'Nil'.
571
PWD ENGINEERING MANUAL-2020 APPENDICES
APPENDIX 1600 E
APPENDIX 1600 F
APPENDIX 1800 A
(Vide Para
G. W. D. 156
Register of sanction to estimates for ................................
Technical Name of work Amount of Reference to Administrative sanction Source of funds
Sanction No. estimate
Authority No. Date
APPENDIX 2100B
Sample Form of Work spot Order Book ( )
Name of Division………………………….
Book No…………………………………..
INSTRUCTIONS
1. The work spot order book is to be maintained at site of construction works of all types.
2. This Book will be maintained by the Work Superintendent/J.E posted for supervision of the work and
he will be responsible for its proper maintenance and safe custody.
APPENDICES
PWD ENGINEERING MANUAL-2020 APPENDICES
3. After completion of the work, the book will be recorded in the office of the authority who gives
technical sanction to the work.
4. Each book will be numbered serially and an account of the books maintained in the Division Office.
5. The orders issued by the inspecting officers shall be recorded in the work spot order book. If such orders are
beyond his competence, the officer issuing the orders shall address the appropriate authority and obtain
ratification. The instructions and orders issued through the work spot order book will be binding on the
departmental subordinates at site. The J.E/Supervisor shall submit copies of the instructions to the Assistant
Engineer. The Assistant Engineer shall communicate copies of instructions to be complied with by the
contractor to him in writing.
PROGRESS OF WORK
Month Progress
TOOLS AND PLANT AT SITE
INSPECTING OFFICERS ORDERS AND INSTRUCTIONS
Date and time of inspection
573
APPENDIX 2100D
SAFFTY CODE (As per para)
1. Suitable scaffolds shall be provided for workmen for all work that cannot safely be done from the ground, or from
solid construction except such short period work as can be done safely from ladders. When a ladder is used an extra
mazdoor shall be engaged for holding the ladder and if the ladder is used for carrying materials as well, suitable
footholds and hand- holds shall be provided on the ladder and the ladder shall be given an inclination not steeper than ¼
to 1 ( ¼ horizontal and
1 vertical).
2. Scaffolding or staging more than 3.25 metres above the ground or floor, swung or suspended from an overhead support
or erected with stationery support, shall have a guard rail properly attached, bolted, braced and otherwise secured at least
1 meter high above the floor or platform of such scaffolding or staging and extending along the entire length of the outside
and ends thereof with only such openings as may be necessary for the delivery of materials. Such scaffolding or staging
shall be so fastened as to prevent it from swaying from the building or structures.
3. Working platform, gangways, and stairways shall be so constructed that they do not sag unduly or unequally, and if
height of a platform or gangway or stairway is more than 3.25 meters above ground level or floor level, it shall be closely
PWD ENGINEERING MANUAL-2020 APPENDICES
574
(b) Those engaged in handling any material which is injurious to eyes shall be provided with protective goggles.
(c) Those engaged in welding works shall be provided with welder's protective eye shields.
(d) Stone breakers shall be provided with protective goggles and protective clothing and seated at sufficiently safe intervals.
(e) When workers are employed in sewers and manholes, which are in use, the Contractor shall ensure that manhole
covers are opened and manholes are ventilated at least for an hour before workers are allowed to get into them. Manholes
so opened shall be cordoned off with suitable railing and provided with warning signals or boards to prevent accident to
public.
(f) The Contractor shall not employment below the age of 18 and women on the work of painting with products containing
lead in any form. Whenever men above the age of 18 are employed on the work of lead painting, the following precautions
shall be taken:
(i) No paint containing lead or lead products shall be used except in the form of paste or readymade pain.
(ii) Suitable face marks shall be supplied for use by workers when paint is applied in the form of spray or a surface having
lead paint dry rubbed and scraped.
APPENDICES
(iii) Overalls shall be supplied by the Contractor to workmen and adequate facilities shall be provided to enable
working painters to wash during and on cessation of work.
9 When work is done near any place where there is risk of drowning all necessary equipment shall be provided and kept
ready for use and all necessary steps taken for prompt rescue of any person in danger and adequate provision made for
prompt first aid treatment of all injuries likely a be sustained during the course of the work.
10. Use of hoisting machines and tackle including their attachments, anchorage and supports shall conform to the
following:-
(a) (i) These shall be of good mechanical construction, sound material and adequate strength and free from patent defects
and shall be kept in good repair and in good working order.
575
13. These safety provisions shall be brought to the notice of all concerned by display on a notice board
at a prominent place at the workspot. Persons responsible for ensuring compliance with the safety code
shall be named therein by the Contractor.
14. To ensure elective enforcement of' the rules and regulations relating to safety precautions,
arrangements made by the Contractor shall be open to inspection by the Engineer-in-charge, or his
representatives and the Inspecting Officers.*
15. Notwithstanding the above conditions 1 to 14 the Contractor is not exempted from the operation of
any other Act or Rules in force.
*‟Inspecting Officer‟ means any Labour Enforcement Officer or Assistant Labour Commissioner of the
Chief Labour Commissioner's Organisation
PWD ENGINEERING MANUAL-2020 APPENDICES
576
Appendix 2100E1
MEASUREMENT BOOK ( )
Circle/Division ...............................................................
Subdivision/Section.......................................................
Measurement Book No ...............................................
Notes
1. The measurement book is the basis of all accounts of quantities, whether for work done by piece work for by
contract, or of materials received for specific works which have to be measured, and should be so kept that the
transaction may be readily traceable into the accounts.
2. (a) Measurements shall invariably and neatly be recorded direct in the measurement books at site, and not copied
into them later on at leisure, from measurement sheets.
(b) Erasures and over writings in the measurement books are strictly prohibited and will be seriously noticed. If
mistakes are made, they should be corrected by neatly scoring off the incorrect entries and inserting the correct
APPENDICES
once between the lines. Dated initials of the recording officer shall be insisted on, on each page of the
measurement book in the case of original entries, and initials, in the case of each and every correction. In the case of
contract work, the contractor's signature should be taken in the measurement book in token of the contractor's
acceptance of the measurements recorded either at the time of measurement or in any case, before payment, to avoid
complaints of omissions, incorrectness, etc.
3. (a) No officer below the rank of a Supervisor in responsible charge of a work, is empowered to measure a
work and make either an entry or a correction in the measurement books in respect of particulars, measurements
or rails. Measurements relating to all supplies and services shall also be recorded by the J.E/ Supervisor. No member
of the clerical staff except the account section responsible for the preparation and checking of the bills, is allowed
to make arithmetical corrections. Such corrections noticed in the preparation of bills, shall be invariably attested by
577
later stage of work should not be lost sight of , while closing or checking interim bills or at the time of
final payment.
6. The measuring officer shall be responsible for closing the bills in the measurement books and taking
care to enter therein correctly, all references previous measurements and all receipts and issues of materials
utodate and effect all recoveries, they shall be observed as an orthodox rule, as the measuring officer is primarily
and wholly responsible for all entries made by him in the measurement book and for the bills as corrected and
finally passed by on for audit on the basis of those measurements. In fact the bill will be an exact copy of the
closing abstract as made out by the measuring officer, in the measurement book.
7. From the measurement book all quantities should be clearly traceable to the documents on which payments are
made reference to voucher in which the quantities are entered for payment as well as date of entry should be
given by endorsement upon the original entries in the measurement book. No contract certificate or bill should be
signed without crossing out the connected entry in the measurement book and the document on which the
payment is made should invariably bear a reference number and page of the book in which detailed
measurements are recorded.
8. The measurement books are thus one of the most important initial records relating to the execution and
payment of works, they should be carefully checked by Divisional/ Sub divisional officer to see that they are kept
as per complete records of each kind of work done for which certificates have been granted. The eventual return
PWD ENGINEERING MANUAL-2020 APPENDICES
of all books to the division office for record should be insisted upon.
9. Name of officer and check measuring officer shall be noted below the signature.
578
Appendix 2100E2
Level Field Book (As para )
Rules to be observed in leveling and survey operations
Rules to be observed in leveling and survey
operations
1. In all surveys the survey line should be shown with a fine red line that it may
be at once apparent with what degree of accuracy a plan has been made.
2. it is also directed that on every convenient occasion tie lines shall be
introduced to check the general accuracy of the work
Though the features of the ground may not need these tie lines for filling in detail, they
must not be omitted,
as the general accuracy of survey is the chief
point to be ensured
3. It is further directed that all levels should be checked either by returning to the
point originally started upon or by closing on a bench mark known to be accurately
APPENDICES
determined. Under no circumstances shall levels be run from one point to another without
the accuracy of the work being inconsistently proved.
4. The adjustments of instruments including chains and tapes, should be checked
and if necessary adjusted before using. Field book level or survey must be carefully
preserved records. Under no circumstances shall nay page or part of a page be torn from
the book. Entries shall invariably and neatly be recorded direct in the field book in ink
at site. Pencil entries should be avoided but if unavoidable these shall be in indelible pencil
and shall not be inked in, but left untouched. Erasures and overwriting s in the field book
are strictly prohibited. And will be seriously noticed. Any mistakes made should be
neatly scored off and corrected in red ink between lines. Dated initials of the recording
Propose:
Locality
Date: Name of officer
579
PWD ENGINEERING MANUAL-2020 APPENDICES
Appendix 2100F
Proforma to Accompany Recommendation for Extension of Time of
Completion ( )
1. Name of work withestimateamount :
2. Agreement numberanddate :
3. Nameofcontractor :
4. Date of commencement as per agreement :
5. Date of completion asperagreement :
6. (a) 1st extension :
(b)2ndextension:
7. Date upto which extension is nowappliedfor :
8. Whether ground for extension applied is default by the
contractor. If not, specify the grounds on which extension is
Applied
9. Present stage of work with percentage of progress so far
Achieved
10. Whether fine has been realised for previous extension. If so
furnish details
11. Period of extensionnowrecommended :
12.Fineproposed :
13.Recommendations :
Assistant Engineer
Assistant Executive Engineer Executive Engineer
580
APPENDICES
Appendix 2100G
CERTIFICATE OF COMPLETION OF WORK ( )
Name of Work :
Name of contractor :
...................................................... Engineer
581
APPENDIX - 2200
2217. EXECUTION – ROADS
This section provides a guide to the correct construction practices and procedures for use on
road contracts. Throughout the site (the area where the works are being constructed) the
contractor is responsible for supplying all the necessary signs and other equipment to ensure
the smooth and safe flow of traffic. The construction shall be carried out in a safe and
controlled manner to prevent damage to vehicles and the general public from construction
equipment, site materials and activities.
2218. General
2218.1. Key Points
Before any construction the roadway must be cleared of all vegetation and trees, including
their roots removed.
• Cross sections shall be taken prior to any excavation works.
• Finalize cross section of the alignment and levels prior to excavation.
• All construction works must be carried out in as safe a manner as possible.
PWD ENGINEERING MANUAL-2020 APPENDICES
582
lines, grades and cross- sections shown in the drawings or as indicated by the Engineer.
Excavation for road works shall conform to the specifications of Section 300 of MoRTH. It
shall include the hauling and stacking of or hauling to sites of embankment and subgrade
construction, suitable cut materials as required, as also the disposal of unsuitable cut materials
in specified manner, trimming and finishing of the road to specified dimensions or as directed
by the Assistant Engineer.
APPENDICES
excavation shall be done with due consideration of the stability of slopes. Benching may be
resorted to wherever necessary and other suitable slope protection provided. In case of rocks
the provisions of clause 301.3.5 and 301.6 of MoRTH shall apply.
2223.Embankment construction
2223.1.Key Points
• All fill materials must be free from vegetable matter and the material must be approved as
suitable.
• The material shall be of an appropriate nature and at moisture content that permits
compaction to form a stable layer.
• Generally embankments shall be constructed in 150 mm compacted layers parallel to the
583
2223.2. Sub grade
The sub grade is the layer of embankment immediately below the pavement. This may be undisturbed
local material or may be soil excavated elsewhere and placed as fill. In either case it has to be prepared
to give added strength. All subgrade material must be free of vegetable matter. The material also needs
to be of a type and moisture content that it can be compacted to form a stable layer. If the material in
the subgrade level is found to be unsuitable, this must be excavated and replaced with suitable material,
which shall then be compacted. The subgrade must be prepared over the full width of the embankment,
including the shallers. This is generally carried out in lengths of greater than 100 metres. In some cases
to maintain traffic, part width working may be necessary. If this is the case it is vital that the full width
of the embankment meets the subgrade material and compaction requirements. When the road is to be
placed on existing material, this shall be fully loosened to a depth of 150 mm below the subgrade level.
Any lumps shall be removed or broken up to be less than 50 mm in size. The subgrade must be
compacted uniformly by use of adequate and appropriate compaction equipment. The material shall be
at moisture content close to optimum throughout the layer so that it can be compacted to produce a
dense compacted layer. Generally the compaction shall begin at the outer edges of the embankment
and by rolling in a longitudinal direction gradually progress towards the centre so that each section
PWD ENGINEERING MANUAL-2020 APPENDICES
receives equalcompaction.
Laboratory tests shall be performed as specified in the chapter on Quality control.
2223.3.Drainage
The surface of the embankment/subgrade at all times during construction shall be maintained at such
a cross fall (not flatter than that required for effective drainage of an earthen surface) as will shed water
and prevent ponding. For this surface drains and subgrade drains shall be provided.
2223.4. Surface drains
Drains shall follow the slope of embankment. Surface drains shall be excavated to the specified lines,
grades, levels and dimensions to the requirements of Clause 309 of MoRTH Specifications for Road
and Bridge works.
2223.5. Sub grade Drains
Sub grade drains are constructed to ensure that water in the pavement, which would weaken the road,
is allowed to drain way. Subgrade drains shall be extended to the edge of the embankment with drains
on opposite sides of the road being staggered. In case of roads with minimal longitudinal fall it is often
better to install subgrade drains longitudinally at the edge of the road pavement, see Figure 4.1
Subgrade drains shall be excavated by hand in the prepared subgrade. The excavation shall be filled
with clean sand or gravel, which contains no vegetable matter, silt or clay. The backfill must be
compactedbyhandrammingandstruckofflevelwith,orslightlyabove,thefinishedsubgradelevel.The
finished backfill must be immediately covered with an approved separator material. The separator
material is normally specified and will be woven rot proof fabric, geo-textile membrane or perforated
heavy duty polythene sheeting. The separator material shall extend 150mm beyond the edges of the
drain on all exposed faces. Any joints in the fabric shall overlap by at least 150mm. Materials over
the drain shall be placed by hand for at least 100mm above the separator membrane prior to rolling
either the pavement or the shallermaterials.
2223.6.Finishing operations
Finishing operations shall include the work of shaping and dressing the shallers /verge/road bed and
side slopes to conform to the alignment, level, cross-sections and dimensions shown on the drawings
or as directed by the Engineer. Both the upper and lower ends of the side slopes shall be rounded off
to improve appearance and to merge the embankment with the adjacent terrain. When earthwork
operations have been substantially completed, the road area shall be cleared of all debris, and ugly
scars in the construction area responsible for objectionable appearance eliminated.
2224. Sub Base
2224.1. Granular Sub Base
This work shall consist of laying and compacting well-graded material on prepared subgrade in
accordance with the specifications. The material shall be laid in one or more layers as sub-base or
lower sub-base and upper sub-base (termed as sub-base hereinafter) as necessary according to lines,
grades and cross -sections shown on the drawings or as directed by the Assistant Engineer.
584
The materials to be used, construction operations, surface finish and Quality checks and opening to
traffic shall be as per the specifications of MORTH clause 401.
2224.2.Cement treated Soil Sub-Base/Base
This work shall consist of laying and compacting a sub-base/base course of soil treated with cement
on prepared subgrade/sub-base, in accordance with the requirements of these Specifications and in
conformity with the lines, grades and cross-sections shown on the drawings or as directed by the
Engineer.
The materials to be used, construction operations, surface finish and Quality checks and opening to
traffic shall be as per the specifications of MORTH clause 403.
2225. Base Course (Non Bituminous)
• Water Bound Macadam Sub –Base / Base
• Sub Base Course: Normally consists of at least one layer of grading I or II materials.
• Base course: Base course is done using Grade III material.
• Crusher-Run Macadam Base
• Crushed Cement Concrete Sub-Base/Base
APPENDICES
• Wet Mix Macadam Sub -Base/Base
2225.1.Water Bound Macadam Sub –Base / Base
WBM may be used as Sub Base as well as Base course and also surface course of rural roads. This
work shall consist of clean, crushed aggregates mechanically interlocked by rolling and bonding
together with screening, binding material where necessary and water laid on a properly prepared
subgrade/ sub- base/ base or existing pavement, as the case may be and finished in accordance with
the requirements of these Specifications and in close conformity with the lines, grades, cross-sections
and thickness as per approved plans or as directed by the Engineer. It is, however, not desirable to
lay water bound macadam on an existing thin black topped surface without providing adequate
585
may be referred.
2226.2. Laying Trials
Once the plant trials have been successfully completed as per MoRTH, and approved, the Contractor
shall carry out laying trials, to demonstrate that the proposed mix can be successfully laid, and
compacted all in accordance with the MoRTH Specifications. The laying trial shall be carried out as
per MoRTH Specifications for road and Bridge works.
2226.2.1.Key Points
• Samples of the material along with laboratory test results shall be submitted to the Engineer at
least 14 days in advance of a proposed material‟s use. If approved, the contractor shall then carry out
trial mixes. This shall also be tested and approved. No dense bituminous surfacing can occur until both
the job mix formula and the trial sections have been approved.
• Thereafter all asphalt work is required to follow the approved Job Mix formula and the
procedures established by the approved trials.
• The surface upon which the bitumen or bituminous mixture is to be placed must be thoroughly
cleaned immediately before the bitumen or mixture is placed.
PWD ENGINEERING MANUAL-2020 APPENDICES
• Bituminous materials shall be placed only when the surface is dry, when rain does not appear
imminent and when the prepared road bed is in a satisfactory condition.
• The entire surface to be primed must be covered evenly. The distributor shall be cleaned and
calibrated to ensure the required rate of spray is achieved. Depending on the nature of the surface to
be primed a light application of water just prior to priming may be beneficial to aid penetration of the
bituminous material.
• No bituminous mixtures shall be placed until the prime coat has dried.
• Tack coat may need to be applied to make the road surface sticky prior to the bituminous
carpeting layer being placed.
• For Primer Seals and Bitumen Surface Treatments the aggregate must be spread and rolled
into bitumen immediately after spraying, preferably rolling shall be by multi tyrerollers.
• Each day dense bituminous surfacing is laid, three Marshall specimens shall be prepared and
tested as ASTM D 2041 or relevant IS code.
• Samples to be collected from either the plant or the laid mat, as directed by the Engineer.
Samples shall also be taken each day to determine the mix composition (Extraction of bitumen test and
grading),
• All equipment proposed to be used by the Contractor are in good condition and operated by
competent and experienced operators
• Dense bituminous surfacing must be thoroughly compacted as soon as the material will
support the roller without undue displacement or cracking. Excess use of water on the roller drums is
to be avoided as this cools the asphalt mat.
• The surface of the mixture after compaction must be close and tight, and free from dragging
cracks. Any mixture that is defective shall be removed and replaced with fresh hot material, which
shall be compacted immediately.
• After final rolling, samples shall be cut from areas of bituminous surfacing for density and
thickness at specified intervals. Where samples have been taken, fresh material must be placed and
thoroughly compacted.
586
2227.1. Bituminous Macadam
This work shall consist of construction in a single course having 50mm to 100mm thickness or in
multiple courses of compacted crushed aggregates premixed with a bituminous binder on a previously
prepared base to the requirements of these specifications. Bituminous macadam is more open graded
than the dense graded bituminous materials.
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH clause 504.
2227.2. Bituminous Penetration Macadam
A penetration Macadam is a compacted layer of coarse aggregates into which bituminous binder is
introduced. The binder penetrates in to the layer through the voids and binds the stone aggregates. A
layer of small aggregates, called key aggregates, is spread on the surface and rolled so as to fill in the
surface voids in the coarse aggregate layer. A seal coat is provided to make the surface more
impervious to water. This type is commonly used in remote areas where it is difficult to transport
mixing and laying equipment. It can also be used as a temporary emergency material to repair a
APPENDICES
pavementdamaged by rains andfloods.
The materials to be used, construction operations, surface finish and quality checks and opening
totraffic shall be as per the specifications of MoRTH clause505.
2227.3.Built-up Spray Grout
This work shall consist of a two-layer composite construction of compacted crushed coarse aggregates
with application of bituminous binder after each layer, and with key aggregates placed on top of the
second layer, in accordance with the Specifications of MoRTH, to serve as a base course and in
conformity with the lines, grades and cross-sections shown on the drawings or as directed by the
Engineer. The thickness of the course shall be 75 mm. Built-up spray grout shall be used in a single
course in a pavementstructure.
587
2227.7. Semi dense Bituminous Concrete
This clause specifies the construction of Semi Dense Bituminous Concrete, for use in wearing/binder
and profile corrective courses. This work shall consist of construction in a single or multiple layers of
semi dense bituminous concrete on a previously prepared bituminous bound surface.A single layer
shall be 25mm to 100mm in thickness.
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH clause 508.
2227.8. Bituminous Concrete
This clause specifies the construction of Bituminous Concrete, for use in wearing (also used as profile
corrective courses) especially for heavily trafficked highways. This work shall consist of construction
in a single layer (25mm to 100mm in thickness) of bituminous concrete on a previously prepared
bituminous bound surface.
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH clause 509.
2227.9 Surface Dressing
This work shall consist of the application of one coat or two coats of surface dressing, each coat
PWD ENGINEERING MANUAL-2020 APPENDICES
consisting of a layer of bituminous binder sprayed on a previously prepared base, followed by a cover
of stone chips rolled in to form a wearing course to the requirements of these Specifications. Surface
Dressing is used in the case of relatively lightly trafficked roads over gravel or other untreated road
bases. It shall be noted that surface dressing is a thin treatment and does not enhance the structural
strength of the pavement. If the existing road is full of irregularities and undulations, it does nothing
to improve riding quality. Design of Surface Dressing may be referred to in the Manual for
Construction and Supervision of Bituminous Works.
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH clause 510.
2227.10.Open grade premix carpet
2227.10.1.Open-graded Premix Surfacing using Penetration Bitumen or Cutback.
This work shall consist of the preparation, laying and compaction of an open-graded premix surfacing
material of 20 mm thickness composed of small-sized aggregate premixed with a bituminous binder
on a previously prepared base, in accordance with the requirements of these Specifications, to serve as
a wearing course.
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH clause 511.1.
2227.10.2.Open graded premix surfacing using cationic bitumen emulsion
This work shall consist of the preparation, laying and compaction of an open graded premix surfacing
of 20 mm thickness composed of small-sized aggregate premixed with a cationic bitumen emulsion on
a previously prepared surface, in accordance with the requirements of the relevant Specifications of
MoRTH, to serve as a wearing course.
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH clause 511.2.
2227.11 Mixed Seal Surfacing
This work shall consist of the preparation, laying and compaction of a close-graded premix surfacing
material of 20 mm thickness composed of graded aggregates premixed with a bituminous binder on a
previously prepared surface, in accordance with the requirements of these Specifications, to serve as a
wearing course. Close graded premix surfacing shall be of Type A or Type B as specified in the
Contract documents.
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH clause 512.
2227.12 Mastic Asphalt
This work shall consist of constructing a single layer of mastic asphalt wearing course for road
pavements and bridge decks. Mastic asphalt is an intimate homogeneous mixture of selected well
graded aggregates, filler and bitumen in such proportions as to yield a plastic and void less mass, which
when applied hot can be trowelled and floated to form a very dense impermeable surfacing. Its
consistency is such that it flows like a viscous fluid at temperatures of around 1750 C to 2100 C but,
588
on cooling to normal temperatures; it solidifies in to a dense mass. Thus its construction requires no
compacting effort. Because of its superior properties, it is used as a wearing course material for heavy
duty pavements, city streets carrying high volume of traffic, bus stops where heavy tangential forces
are expected, junctions where cornering stresses are predominant.
The materials to be used, construction operations, surface finish and Quality checks and opening to
traffic shall be as per the specifications of MoRTH clause 515.
2227.13. Seal Coat
This work shall consist of the application of a seal coat for sealing the voids in a bituminous surface
laid to the specified levels, grade and cross fall (camber). Seal coat shall be of either of the two types
specified below:
• Liquid seal coat comprising of an application of a layer of bituminous binder followed by a
cover of stone chips.
• Premixed seal coat comprising of a thin application of fine aggregate premixed with
bituminous binder.
APPENDICES
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH 513.
2227.14. Bituminous Cold Mix (Including Gravel Emulsion)
Bituminous Cold Mix consists of a mixture of unheated mineral aggregate and emulsified or cutback
bitumen. This Specification deals only with plant mix (as opposed to mixed- in-place). Bituminous
cold mixes are used in situations where hot mix plants are not readily available, including for work in
remote areas and maintenance operations. Two types of mix are considered, namely,
• Designed Cold Mix
• Recipe Cold Mix.
The Design Mix procedure shall be used unless the Engineer specifically approves the Recipe
589
The materials to be used, construction operations, surface finish and quality checks and opening to
traffic shall be as per the specifications of MoRTH 602.
2229.Shallers 2229.1. General
Shaller gives adequate side support to the pavement and also drains off surface water from the
carriageway to the roadside drain. The work shall consist of constructing shaller on either side of the
pavement in accordance with the requirements of these Specifications and in conformity with the lines,
grades and cross-sections shown on the drawings.
Shaller may be of selected earth/ granular material/ paved conforming to the requirements of MoRT&H
Clause 305/407. Paved shallers shall consist of sub-base, base and surfacing courses, as shown in the
drawings and materials for the same shall conform to relevant Specifications of the corresponding
items. Where paved or hard shallers are not provided, the pavement shall be provided with brick/stone
block edgings as shown in the drawings. The bricks shall conform to Clause 1003 of these
Specifications. Stone blocks shall conform to Clause 1004 of these Specifications and shall be of size
225 mm x 110 mm x 75 mm.
2229.2.Shoulder width
Width of the shoulder shall vary from 1 m to 2.5 m be as shown on the drawings or as directed by the
PWD ENGINEERING MANUAL-2020 APPENDICES
Assistant Engineer..
2229.2.1Construction Method
The sequence of operations shall be such that the construction of paved shaller is done in layers each
matching the thickness of adjoining pavement layer. Only after a layer of pavement and corresponding
layers in paved and earth shaller portion have been laid and compacted, the construction of next layer
of pavement and shaller shall be taken up.
Where the materials in adjacent layers are different, these shall be laid together and the pavement layer
shall be compacted first. The corresponding layer in paved shaller portion shall be compacted
thereafter, which shall be followed by compaction of earth shaller layer. The adjacent layers having
same material shall be laid and compacted together.
During all stages of shaller (earthen/ hard/ paved) construction, the required cross fall shall be
maintained to drain off surface water.
2229.3Culverts
Culverts are mainly of two types, Pipe Culverts and Slab Culverts. The width of culvert shall be equal
to the formation width of the road. It shall be generally situated on the straight alignment of the road.
If the road has a gradient the same shall be maintained for deck slab of theculvert.
2229.3.1Pipe Culverts:
2229.3.2NP 4 pipes for national highways conforming to IS 458:1988 shall be used.
Bedding: The bedding must be even and uniform, projecting rock faces and boulders must be removed
before forming the bedding. The thickness of bedding layer shall be minimum 75 mm. The bedding
material shall be well graded sand or granular material passing 75 mm sieve.
For heights of fill greater than 4 m, continuous concrete cradle bedding may be used. The mix shall
not be leaner than M150 concrete and the pipes shall be laid in position before the concrete has set.
Laying: Start Laying from the outlet and proceed towards the inlet ensuring the specified lines and
grade. The minimum longitudinal slope shall be 1 in 1000.
Where two or more lines of pipes are to be laid adjacent to each other, they shall be separated by a
distance equal to at least half the diameter of the pipe subject to a minimum of 450 mm. Ensure that
the pipe has a cushion of at least 0.60 m excluding crust thickness at the top.
2229.3.2.RCC Slab Culverts:
Depending on the scour characteristics of the bed material, open foundations with or without erosion
proof bed flooring is generally adopted. In general, concrete footing shall rest over good stratum at a
depth of about 1.5m below the lowest bed level. Bed flooring where provided shall consist of stone
pitching set in cement mortar 1:3 or two layers of brick on edge set in cement mortar 1:3. These shall
be laid over 150 mm thick foundation concrete M15.
2229.3.3.RCC Box culverts
These are economical in such cases where either the depth of foundation is more than 4 m below bed
level or where the total embankment is very high and are suitable for a situation where the catchment
area is more than 40 hectares. Box section of height less than 2m X 2m is not practicable to implement.
590
2230.Dimensions of abutment and wing wall:
Dimensions of abutment for RCC Slab Culvert
Span 1m to 4 m 5m to 6 m
H 2 3 4 2 3 4
b1 0.2 0.3 0.4 0.2 0.3 0.4
b2 0.7 1.1 1.4 0.6 1 1.4
b3 0.3 0.3 0.3 0.4 0.4 0.4
b4 - 0.2 0.5 - 0.2 0.6
B1 1.5 2.0 2.4 1.5 2.0 2.5
APPENDICES
B2 2.7 3.6 4.6 2.7 3.6 4.9
Dimensions of wing wall
Span upto 2 m 3m 4m 5m 6m
H 2 3 4 2 3 4 2 3 4 2 3 4 2 3
b1 0.23 0.33 0. 0.24 0. 0.44 0.24 0.34 0.44 0.25 0.3 0.45 0.25 0.35
43 34 5
B1 1.3 1.65 2. 1.33 1. 2.03 1.34 1.69 2.04 1.37 1.7 2.08 1.38 1.72
0 68 2
B2 2.1 2.45 2. 2.13 2. 2.83 2.14 2.49 2.84 2.17 2.5 2.88 2.18 2.53
8 48 2
0.3 0.3
b3
591
Figure 4.2 Abutment and wing wall section for height more than 4.5m
Road
End Pillar
Parapet CC Bed Construction
Premix
Carpet Joint
40 30 Deck 150
Slab 210 Masonry / mm
mm CCAbutment WBM
Slope 1: 3
H
CC/ RR Packing
PWD ENGINEERING MANUAL-2020 APPENDICES
0
Masonry /
10 CC
CC 1:4:8 , 20mm
Figure 4.3 Typical Details of Abutment and wing wall section for height upto
The following points are to be followed for construction of culverts.
1. The design shall be based on 2lane IRC Class A loading.
2. The length of wing walls shall be sufficient to eliminate any tendency of the embankment slope
to slip into the stream.
3. Construction joint between abutment and wing wall shall be provided to avoid overstressing at
the junction due to differential settlement.
4. The bearing shall be of reinforced bitumen laminated Kraft paper conforming to IS 1938.
While concreting the slabs, care shall be taken to prevent the bearing material from being displaced.
5. All space between foundation, masonry or concrete and the sides of excavation shall be refilled
to the original surface in layers not exceeding 150 mm compactedthickness.
6. The backfill material around the structure shall be of granular type having plasticity index and
liquid limit not exceeding 20 and 40 respectively. The fill material shall be deposited in horizontal
layers not exceeding 200 mm compacted thickness.
7. If the height and abutment and return over bed level is more than 2 m weep hole shall be
provided
150 mm above low water level or ground level whichever is higher. In case of concrete/ masonry,
weep holes of 150 mm dia or 80 X 150 mm size in 1:20 slope shall be provided at 1 metre interval
both horizontally and vertically. Refer IRC 40
8. Water Spout shall be provided for large span culverts. For 5 and 6 m span, one water spout of
100 mm diameter shall be provided in the centre of slab on either side of thedeck.
9. All culverts shall be numbered on the end pillars as per IRC SP 20 with year ofconstruction.
10. In case of stone masonry, coarse rubble masonry is stipulated.
11. Face stones shall be hammer dressed on all beds and joints so as to give them approximately
rectangular shapes.
12. The hearting or interior filling of the wall shall consist of flat bedded stone carefully laid on
their proper beds in mortar. While the use of chips shall be restricted to the filling of interstices
between the adjacent stones in hearting and these shall not exceed 15 % of the quantity of masonry.
13. Bond stones or headers shall be at 1.5 m or 1.8 m apart clears in every course. The headers shall
overlap at least by 150 mm
14. Face stone shall tail into the work for not less than their heights and at least one third of the
stones shall tail into the work for a length not less than twice the height
592
15. The face joint shall not be more than 20 mm thick.
2231.Causeways and Submersible Bridges.
A causeway is a small submersible structure, which allows flood to pass over it.
2231.1.Flush causeway: It is a paved dip built to cross a shallow water course. The top level shall
be at the same level as that of the bed of the water course.
2231.2. A low level or vented causeway: This is a structure provided with a few openings
comprising of pipes, small span slabs or small arches etc. with a raised road top level to a moderate
height upto 1.5 m height.
2231.3. A high-level causeway: This is a submersible structure provided with larger openings
comprising of a simply supported /continuous RCC slab or multiple arches or boxes and a raised
road top level to a reasonable height 1.5 m to 3 m. The RCC Slab may be supported over a series
of short piers (Masonry/
CC)
To avoid the heading up of water on the upstream side which results in producing high velocities
APPENDICES
leading to structural failure and out flanking, the top level of the causeway shall be kept as low as
possible. The water way provided in the causeway shall not be less than 30 % of the area of the
stream, measured between the stream bed level and the proposed top level of the road.
The details for culvert and causeway design shall be referred to in IRC SP 20-2002.
2232.Side drains
Side drain must be provided to collect surface water from the roadway and lead to an outlet. It also
acts as an outlet for the subsurface drains thereby protecting the base course of the roadway structure
from getting saturated/ lost its load bearing capacity. Side drains are designed for open channel flow
and generally provided on both sides of the road. Road drains in hilly terrain are constructed to
parabolic, trapezoidal, triangular, V-shaped, Kerb and channel or U- shaped cross sections.
593
2234. Execution – Bridges
2234.1.General
Before starting the construction work, the procedure mentioned in section 2200 must be
followed and care must be taken to ensure that the following documents are available at
site.
1. Sanction letter and technical note, if any
2. Bill of Quantities
3. Copy of contract document
4. Copy of approved set of plans, estimates and detailed working drawings
5. Standards, specifications, guidelines, codes of practices etc., according to which the
work must be executed as per contract
6. Survey, investigation and subsoil test reports
2235. Excavation
Before starting excavation, it is necessary that initial site levels are taken. Protective
works, if any, shall be completed before monsoon so that foundations do not get
undermined. Excavations for laying foundations shall be carried out in accordance with
PWD ENGINEERING MANUAL-2020 APPENDICES
Section 300 of MoRTH Specification for Road and Bridge works. The last 300 mm of
excavation shall be done just before laying of lean concrete below foundation.
Where there is any doubt regarding the bearing capacity or suitability of the foundation
soil the matter shall be reported to the Executive Engineer. In the case of small works up
to TS power of Executive Engineer, if any variation on the width, depth and type of
foundation is found necessary the Assistant Executive Engineer himself may decide the
matter after reporting to the authority sanctioning the estimate.
Load tests shall be conducted in the foundation soil if found necessary. If the contractor
has over excavated the foundation, he shall not be allowed to refill this with earth but, the
additional excavation shall be filled up by concrete. No extra cost is payable to the
contractor on this account. In some cases, it may be possible to reduce the depth or width
of foundation due to existence of harder type of soil or rock in particular localities but the
Assistant Executive Engineer may decide on the alteration necessary and instruct the
contractor accordingly. A report shall be sent to the Executive Engineer clearly indicating
the change effected and the reasons therefore.
The useful materials obtained from excavation like moorum sand stone etc. shall be
stacked separately and properly measured and accounted for. It shall be reused for
backfilling of foundations and other useful works. All spaces excavated and not occupied
by the foundation shall be refilled upto surrounding level in accordance with section 300
MoRTH Specification for Road and Bridge works. All safety measures shall be observed
at site to avoid accidents. Unauthorized entries to site of work shall be prohibited. The
contractor shall obtain proper license for explosives whenever these are to be stored.
The excavation for foundation shall be checked and got approved by the Executive
Engineer
2236. Concreting
All the materials used in concreting must be tested for relative properties before hand.
2236.1. Key Points
• The minimum cement content is based on 20 mm aggregate.
• For 40 mm and larger sized aggregates, cement content may be reduced suitably,
but the reduction shall not be more than 10%
• For underwater concreting, the cement content shall be increased by 10 %.
• Prior to start of construction, the contractor shall design the mix and submit to
the Executive
Engineer for approval of the mix, proportions of materials, including admixtures used.
• Trial mixes: Test cubes shall be taken, from trial mixes. For each mix, set of six
cubes shall be made from each of three consecutive batches. Three cubes from each set of
mix shall be tested at
594
an age of 28 days and three at an earlier date (7 days) approved by the Executive Engineer.
The cubes shall be made, cured, stored, transported and tested in conformity with the
MoRTH specifications.
• The average strength of the nine cubes at 28 days shall exceed the specified
characteristic strength.
• Concrete shall be mixed either in a concrete mixer or in a batching and mixing
plant approved by the Executive Engineer. Hand mixing shall not be permitted.
• Mixers, which have been out of use for more than 30 minutes, shall be
thoroughly cleaned before putting in a new batch.
• The first batch of concrete from the mixer shall contain only two thirds of the
normal quantity of coarse aggregate.
• The compacted thickness of each layer shall not be more than 0.45 m when
internal vibrators are used and shall not exceed 0.3 m in all othercases.
•
APPENDICES
Do not allow dropping of concrete from a height exceeding 2 m.
• When concreting is to be received on a surface, which has hardened, it shall be
roughened, swept clean, wetted and covered with a 13 mm thick mortar layer composed
of cement and sand in the same ratio as in the concrete mix.
• Do not apply vibration through the reinforcement.
• Keep the compacted concrete continuously wet for a period not less than 14 days
Transporting, placing and compaction of Concrete shall be as per clause 1709 of MoRTH
Specification for Road and Bridge works. For formwork and staging clause 1500 of
MoRTH Specification for Road and Bridge works shall be followed. The contractor shall
furnish the design and drawings of complete formwork as well as their supports for
595
Table123.4 Maximum nominal size of Coarseaggregates
Sl Components Maximum nominal size of Coarse
no: aggregates
1 RCC Well kerb 20
2 RCC/ PCC Well steining 40
3 Well cap or pile cap, solid type piers and 20
abutment
4 RCC work in Girders, slabs, wearing coat, curb 20
approach slab, hollow piers and abutments,
piers.
5 Pre stressed concrete (PSC) work 20
6 Any other item. As specified by the Executive
Engineer
The time of removal of formwork and staging shall be as per Table 4.3.2.
Table4.3.2 Time of Removal of Formwork
PWD ENGINEERING MANUAL-2020 APPENDICES
596
2237.Foundations 2237.1.
Open foundation:
The plan dimensions of the foundation shall be set out at the bottom of foundation trench and
checked with respect to original reference line and axis. It shall be ensured that at no point the
bearing surface is higher than the founding level shown on the drawing.
Open foundation shall be constructed in dry conditions and the contractor shall provide for adequate
dewatering arrangements to the satisfaction of the Assistant Executive Engineer. Measures such as
bailing out, pumping, constructing diversion channels etc. shall be taken to keep the foundation
trenches dry and to protect the green concrete against damage. Where the bearing surface is earth, a
layer of M15 concrete shall be provided below foundation concrete. The thickness of lean concrete
layer shall be 100 mm minimum unless otherwise specified. All spaces excavated and not occupied
by the foundation shall be refilled and compacted with earth up to the surface of surrounding ground.
In case of excavation in rock, the annular space around foundation shall be filled with M 15 concrete
up to the top of rock.
APPENDICES
The construction procedure shall conform to provisions contained in Section 2100 of MoRTH
Specification for Road and Bridge works.
2237.2. Well foundation:
This work consists of construction of well foundation, taking it down to the founding level through
all kinds of sub-strata, plugging the bottom, filling the inside of the well, plugging the top and
providing a well cap in accordance with the details shown on the drawing and as per the
specifications of MoRTH Specification for Road and Bridge works section 1200.
Key points:
• Fix up reference points, away from the zone of blowups/ settlements resulting from well sinking
and mark centre lines of the individual wells in longitudinal and transverse directionsaccurately.
597
2237.3. Pile Foundation
Sub-surface investigation shall be carried out by in-situ pile tests. At least one bore- hole for every
foundation of the bridge shall be executed. Depth of boring shall not be less than
• 1.5 times estimated length of pile in soil but not less than 15 m beyond the probable length of pile
• 15 times diameter of pile in weak/jointed rock but minimum 15 m in such rock
• 4 times diameter of pile in sound, hard rock but minimum 3 m in such rock
2237.3.1. Type of piles
The piles may be of reinforced concrete, pre stressed concrete, steel or timber. The piles may be of
solid or hollow sections or steel cased piles filled with concrete. Concrete piles may be driven cast-
in- situ or pre-cast or bored cast- in-situ or pre-cast piles driven into preformed bores. The shape of
piles may be circular, square, hexagonal, octagonal, "H" or "I" Section.
Construction of pile foundations shall be as per the MoRTH Specification for Road and Bridge
works clause 1100 and IS: 2911. The construction of pile foundations requires a careful choice of
the piling system depending upon sub-soil conditions and loading characteristics and type of
structure. The method of installing the piles, including details of the equipment shall be submitted
by the Contractor and got approved by the Executive Engineer
PWD ENGINEERING MANUAL-2020 APPENDICES
598
2238 SubStructure
The construction procedure shall conform to provisions contained in Section 2200 of MoRTH
Specifications for Road and Bridge Works.
2238.1. Piers and Abutments
In case of concrete piers, the number of horizontal construction joints shall be kept minimum.
• Construction joints shall be avoided in splash zones.
• No vertical construction joint shall be provided.
• In case of tall piers and abutments, use of slip form shall be preferred.
• The surface of foundation/well cap/pile cap shall be scrapped with wire brush and all loose
materials removed.
• In case reinforcing bars projecting from foundations are coated with cement slurry, tapping,
hammering or wire brushing shall remove the same.
• Before commencing masonry or concrete work, the surface shall be thoroughlywetted.
• In case of solid (non-spill through type) abutments, weep holes as shown on the drawings shall be
APPENDICES
provided.
• The surface finish shall be smooth, except the earth face of abutments, which shall be rough,
finished.
• In case of abutments likely to experience considerable movement on account of backfill of
approaches and settlement of foundations, the construction of the abutment shall be followed by
filling up of embankment in layers to, the full height to allow for the anticipated movement during
construction period before casting of superstructure.
Specific requirements of piers and abutments shall be as per Clauses 2204 of MoRTH
Specification for Road and Bridge works.
599
• The finish of the surface on the earth side shall be rough while the front face shall be
smooth finished.
• Architectural coping for wing wall/return wall in brick masonry shall conform tosection
1300 of MoRTH Specifications.
Specific requirements of Dirt/ Ballast Wall, Return Wall and Wing Wall shall be as per Clause
2206 of
MoRTH Specification for Road and Bridge works.
2239. Bearings
Bearings are the part of the bridge structures, which bears directly all the forces from the structure
above and transmits the same to the supporting structure. The different types of bearings currently
in use are Steel bearings, Elastomeric Bearings, Pot Bearings and Special bearings. Bearings shall
conform to the provisions contained under section 2000 of MoRTH Specifications for Road and
Bridge Works.
2240. Super Structure
2240.1. Reinforced Concrete Construction
Construction of Solid Slabs and RCC T-Beam & Slab are carried out as per the clause 2300 set
PWD ENGINEERING MANUAL-2020 APPENDICES
600
2243.1.Brick and Stone Masonry
Where the design suggests the use of Brick or Stone masonry, these shall conform to the
specifications in section 1300 and 1400 of MORTH respectively.
2245.1. General
Before start of the construction work, care must be taken to ensure that the documents as specified
in section 2200 are readily available. The site shall be handed over to the contractor within the
stipulated time and acknowledgement in prescribed form forwarded to all concerned officials.
APPENDICES
2245.1.1. Professional Services and Responsibilities
The responsibility and competence of the team of professionals with regard to planning designing
and supervision of building construction work shall be in accordance with Part 2 'Administration' of
National Building Code 2005. The provisions in Part 2 „Administration‟ of National Building Code
2005 shall also govern all applications for permits and issuance of certificates, etc. Employment of
trained workers shall be encouraged for building construction activity.
i) The Contractor shall mark the Layout of Building on the ground in the form of centre lines of
walls and columns. These centre lines shall be guided by brick pillars made along the centre line at
a distance of 1.2 m from the outer walls and columns with the centre marked on these reference
pillars with fresh plaster. Excavation is done to the prescribed basement floorlevel.
ii) Balance excavation to be done after remarking the position of columns on excavated ground
and also making temporary markings of centre lines on excavated sides. Marking the foundation/
beams sizes and then doing the balance excavation giving shape to the raft foundation / column
foundations as per the design.
iii) In case external waterproofing is to be done, it is to be done on the PCC and if internal it shall
be done after completing the RCC of the basement. Then the final Layout of walls, columns and
beams on the PCC shall be made and got verified by the Assistant Executive Engineer.
iv) Contractor shall prepare and submit the bar bending schedule as per drawings and get it
approved by the Assistant Executive Engineer. Cover blocks to be made by contractor in PCC at the
time of laying PCC in the thicknesses stipulated and placed below or around reinforcement so as to
provide proper cover. After laying of the Steel reinforcement it is to be checked and measured by
the Assistant Executive Engineer for accuracy and cover to reinforcement. This shall be check
measured by AEE
v) Concrete for columns (or in walls) shall be as per design mix and vibrated properly. Cement
601
additives can be added for generating proper flow and compaction of concrete as per clause 5.5 of
IS 456: 2000. Single lift shall not be more than 1.2 m
vi) Contractor is to cast the balance height of column after proper shuttering up to beambottom.
vii) Contractor is to provide and do shuttering of the roof as per structural drawings and check its
level. It shall be ensured that proper amount of supports are provided and also that the shuttering is
not uneven or done with very old planks or bent plates. The shuttering of wareproof ply or of steel
sections made to the size required shall be used. Steel shuttering of various column sizes and also
steel plates for roof shuttering shall be used. Assistant Engineer shall check the shuttering for levels
and design aspect he shall also check the supports for any loose ends.
viii) The primary responsibility of ensuring the correctness of the reinforcement details as per
design is vested with the Assistant Engineer. But the contractor‟s Engineer shall certify that the
reinforcement is provided as per structural drawings and bar bending schedule. The J.E/Overseer in
charge shall report the matter to the Assistant Engineer.
ix) In normal course concreting shall be done at a stretch. In the case of emergency, the work shall
be stopped only at supports or at the point of contra flexure.
PWD ENGINEERING MANUAL-2020 APPENDICES
x) Time shall be given to the electrical contractor and the plumbing contractor for laying the pipes,
fan and light boxes properly. Thus a gap of one day shall be provided after the bending of steel
reinforcement so that both the electrical and sanitary contractors can execute this work properly and
also for the Assistant Executive Engineer to check the reinforcement, shuttering, electrical and
sanitary work.
xi) Assistant Engineer shall depute one of his Supervisors/ Overseers to keep a check at the point
of mixing for volumes of cement, coarse sand, coarse aggregate. Additives for concrete available in
the market for increasing the workability of concrete shall be used as perrequirement.
602
2248. Foundation
Foundation shall be done as per the design drawings. The forms and materials of building
foundations vary according to ground conditions, structural material, structural type, and other
factors. Types of foundation and details shall be referred to in Part VI Section 2 of National
Building Code 2005 (Clause 6 to 13)
2249. Plain Cement Concrete.
Plain Cement Concrete shall be done as per the thickness given in the drawing. The minimum
thickness of PCC must be 100 mm. The bottom of the foundation shall be leveled both
longitudinally and transversely or stepped as directed by the Assistant Engineer. Before footing is
laid, the surface shall be slightly watered and rammed. In the event of excavation having been
made deeper than that shown on the drawings or as otherwise ordered by the Assistant Engineer,
APPENDICES
the extra depth shall be made up with concrete of same grade as that of PCC of the foundation at
the cost of the Contractor. Earth filling shall not be used for the purpose to bring the foundation to
level. When rock or other hard strata is encountered, it shall be freed of all soft and loose material,
cleaned and cut to a firm surface either level and stepped as directed by the Assistant Engineer. In
the case of open foundation dewatering shall not be permitted from the time of placing of concrete
up to 24 hours after placement.
603
The following methods can be adopted:
a. A base slab of weak cement concrete with a smooth surface finish is constructed on the floor of
the excavation. This shall project at least 15 cm. beyond the outer walls. The damp proof course is
laid over the entire slab.
b.A protective flooring of flat brick or cement concrete 1:3:6 is constructed over the damp proofing
course to protect it. The structural walls and floor are then constructed. They shall be suitably
designed to withstand the anticipated water pressure. The outside faces are plastered and finished
smooth.
c. The damp proof course is then applied to the outside face of the wall, joining at the base to the
projecting damp proof course originally laid over the base slab, taking care to ensure a perfect bond.
A thin protective brick wall, half brick thick, is then constructed over the projecting base slab. The
gap between the walls shall be grouted with cement.
Alternately, where sufficient working space is not available after the base concrete is laid, the outer
protective wall is first constructed. The damp proof course is then laid over the floor and sides. A
protective layer of brick is laid over the floor and a thin inner protective wall is constructed to protect
PWD ENGINEERING MANUAL-2020 APPENDICES
the damp proof course laid over the sides. The structural walls are then constructed.
2253. Formwork
Most structural concrete is made by placing (also called CASTING) plastic concrete into spaces
enclosed by previously constructed Forms. These forms are usually removed once the plastic
concrete hardens into the shape outlined by the forms. Forms for concrete structures must be tight,
rigid, and strong. The forms must be strong enough to resist the high pressure exerted by the
concrete.
2253.1.Form Materials
Wood, plywood, steel, fiberglass, and other approved materials are commonly used as form
materials.
604
2253.1.1.Foundation Forms
Foundation forms may include forms or parts of forms for column footings, pier footings, and wall footings.
Whenever possible, the earth shall be excavated and the hole used to contain the foundation of footing forms.
Footings are cast directly against the earth, and only the sides are molded in forms. Where there is a firm
natural earth surface, which is capable of supporting and molding the concrete, there is no need of additional
formwork.
Wall forms are made up of five basic parts. They are as follows: Wall forms are made up of five basic
parts. They are as follows:
(1) Sheathing, to shape and retain the concrete until it sets;
(2) Studs, to form a framework and support the sheathing;
(3) Wales, to keep the form aligned and support the studs;
APPENDICES
(4) Braces, to hold the forms erect under lateral pressure; and
(5) Ties and spreaders or tie-spreader units, to hold the sides of the forms at the correct spacing. Wall forms
may be built in place or pre- fabricated, depending on the shape and the desirability
for reuse. Wall forms are usually reinforced against displacement by the use of TIES. Small
605
2253.3. Beam and Girder Forms
The type of construction to be used for beam forms depends upon whether the form is to be
removed in one piece or whether the sides are to be stripped and the bottom left in place until
such time as the concrete has developed enough strength to permit removal of the shoring. Beam
forms are subjected to very little bursting pressure but must be shored up at frequent intervals to
prevent sagging
under the weight of the fresh concrete. The vertical side members are placed to assist in transmitting
slab loads to the supporting shores.
2253.4. Scaffoldings
Properly designed and constructed scaffolding built by competent workmen shall be provided
during the construction in the building site to ensure the safety of workers. Joining the members of
scaffolds only with nails shall be prohibited, as they are likely to get loose under normal weathering
conditions. In the erection or maintenance of tall buildings, scaffoldings shall be of noncombustible
material especially when the work is being done on any building in occupation. Frequent
inspections of scaffolding shall be done after initial construction of thescaffolding.
PWD ENGINEERING MANUAL-2020 APPENDICES
2254. Column
Concrete columns shall be executed as per approved structural drawings/ designs. For any change
proposed at site, in the size of column section and reinforcement/or their orientation, etc., approval
of Executive Engineer shall be obtained before execution.
2255. Walls
Walls are differentiated into two types: load bearing and non-load bearing. Load-bearing walls not
only separate spaces, but also provide structural support for whatever is above them. Non- load
bearing walls function solely as partitions between spaces. Partition walls, curtain wall, panel wall
and shear wall come under this category.
Common burnt clay bricks, Burnt clay fly ash bricks, pulverized fuel ash lime bricks, Stones, Sand
lime bricks, Concrete blocks (Solid & Hollow), Lime based blocks, Burnt clay hollow blocks,
Gypsum Partition blocks, Autoclaved cellular concrete blocks and Concrete stone masonry blocks
are used with cement mortar for the construction. The materials used in masonry construction shall
be in accordance with the Part 5 Building Materials and construction shall conform to the accepted
standards of Part 6 Section Masonry of NBC. Height and length of masonry walls shall be restricted
as per clause 4.6 and clause 8 ofSection 4 of part 6 of National Building Code.
Depending on the type of wall to be constructed height of the wall per day shall be restricted to
ensure that the newly constructed wall does not come down due to lack of strength in lower
layers. In long walls adequate expansion/crumple joints shall be provided to ensure safety. If an
opening is necessary in the existing wall then adequate support against the collapse or cracking of
the wall portion above or roof or adjoining walls shall be provided. Whenever projections
cantilever out of the walls temporary form work shall be provided for such projections and the
same shall not be removed till wall over the projecting slabs providing stability load against over
turning are completely constructed.
606
openings. Pre-cast concrete sills can be used.
Pre-cast concrete lintels can be used with an offset on the underside to fit the modular openings.
57.1. Sunshade: This is provided for protection of doors windows, ventilators and other openings
from the effect of rain and sunlight. This may be provided as per the provisions of the code IS
456. It must be cast monolithically with the lintel and care must be given to ensure sufficient slope
to aid runoff. Lintel must be raised above the sunshade to a minimum 5 cm so that water seepage
is avoided.
2257. Beam
Beams are the principal load-carrying horizontal members. They take the load directly from the floor
above and carry it to the columns. The beams shall be constructed in accordance with the structural
drawings.
APPENDICES
2258. Slabs
Slabs shall be constructed as per the structural drawings. Top surface of Roof slab shall have
necessary slope to drain off rainwater. In case of sloping roof, the slabs shall rest on RCC beams
over masonry walls, so that crack development can be avoided.
2259. Pre-stressed concrete
For this method of concreting Refer IS 1343: 1980
2260. Ready mixed concrete
For this method of concreting Refer IS 4926: 2003
2261. Doors
607
materials installed to cover the surfaces of the floors, the walls, and the ceilings.
2263.1. Flooring and Floor Finishes
Floor materials found in shore establishment buildings and structures for various occupancies
include wood, concrete, terrazzo, and clay tile. Common floor coverings include asphalt, vinyl tile,
and linoleum. Common tiles in use are ceramic tiles, stone tiles, granite tile, marble and slate etc
Clean the surface. Roughen the concrete under-bed to provide a good bond for the new setting
cement. Dampen the under-bed and place the setting mortar mixed in the proportion of 1 part cement
to 3 parts sand. Set the tile, tamping it to the level of the required finished floor. Fill the joints with
grout or pointing mortar, matching the color and finish of floor as closely as possible. Grout joints
3 mm or less in width with neat cement grout of the consistency of thick cream. Point joints one-
3mm to 6mm in width with pointing mortar, consisting of one-part cement to one-part screened
sand. Point joints wider than 6 mm with pointing mortar consisting of one-part cement to two-parts
PWD ENGINEERING MANUAL-2020 APPENDICES
screened sand. I n locations, such as galleys and food-preparation areas, where the floor is directly
exposed to the effects of corrosion agents,
acid-resistant joint material is used to fill the joints. The acid-resistant mortars areproprietary
products and shall be mixed according to the manufacturer‟s recommendations.
608
be used. In case of large halls and auditoriums, for acoustics, special acoustical tiles and acoustical
plaster of approved quality and specifications shall be used. Acoustical tiles are available in various
materials, such as wood, vegetable or mineral fibre, perforated metal, or cemented shavings in
different thicknesses, shapes, and dimensions and with varying textures, perforations, and joint
treatment.
2265. Painting
2265.1.Surface Preparation
The most essential part of any painting job is proper surface preparation and repair. Each type of
surface requires specific cleaning procedures. Before painting suitable priming coat shall be applied
as per specifications and maximum possible time gap shall be allowed before painting is done. Paint
will not adhere well, provide the protection necessary, or have the desired appearance unless the
surface is in proper condition for painting. Exterior surface preparation is especially important
because hostile environments can accelerate deterioration.
2265.1.1.Application of Paint
APPENDICES
Painting shall be done to different types of surfaces, such as metal, wood, and concrete/ masonry.
The common methods of applying paint are brushing, rolling, and spraying. The choice of method
is based on several factors, such as speed of application, environment, type and area of surface, type
of coating to be applied, desired appearance of finish, and training and experience of painters.
Brushing is ideal for small surfaces and odd shapes or for cutting in corners and edges. Rolling and
spraying are efficient on large, flat surfaces. Spraying can also be used for round or irregular shapes.
While spraying, adjacent areas not to be coated must be covered. Lacquer products, which dry
rapidly, shall be sprayed.It should be stored as per relevant claus of IS Code.
2265.2.Interior Painting
2265.3.White washing
The interior wall of ordinary buildings and all ceilings shall be whitewashed
2265.4.Colour washing
The interior wall of residential buildings and office buildings shall also be colour washed.
609
and the prescribed number of coats, each conforming to the requirements of the specifications, is
applied. Nonferrous metal is usually not painted.
2265.9. Woodwork
Make sure that surfaces are thoroughly dry and clean and are otherwise suitably prepared for painting
before permitting work to proceed. Ensure that the priming coat is intact and is of suitable
PWD ENGINEERING MANUAL-2020 APPENDICES
consistency to protect the wood, but not so tight that moisture in the wood is prevented from
evaporating. Make sure that the wood is smooth enough to assure the continuity and adherence of
the paint film; that holes and cracks are puttied or filled with wood filler; and that knots and pitch
streaks are sealed with shellac, varnish, or other sealer, as prescribed. Make certain that the paints
are of approved quality and color; and are applied by brushing, using high-quality brushes, until the
coat is smooth, even, free from brush marks, and of uniform thickness, texture, and color. Also be
sure that the paint is not brushed too thin to assure satisfactory hiding power; that each coat is
allowed to dry thoroughly to a firm film before permitting application of the next coat; and that the
specified number of coats is applied.
610
. List of relevant codes for painting
IS 144: 1950 Ready mixed paint, brushing, petrol resisting, air-drying, for
interior painting of tanks and container, red oxide (colour unspecified)
IS 145: 1950 Ready mixed paint, slushing, petrol resisting, air-drying forinterior
painting of tanks and containers, red oxide (colour unspecified)
IS 146: 1950 Specification for ready mixed paint, brushing, petrol resisting,
stoving, or interior painting of tanks and containers, red oxide
IS 147: 1950 Specification for ready mixed paint, slushing, petrol resisting,
stoving, for interior painting of tanks and containers, red oxide
IS 1200: Part 13: Method of measurement of building and civil engineering works:
Part 13 Whitewashing,
1994 colour washing, distampering and painting of building surfaces
APPENDICES
IS 1200: Part 15: Method of measurement of building and civil engineering works:
Part 15 painting, 1987 polishing, varnishing etc
IS 1477: Part I: Code of Practice for Painting of Ferrous Metals in Buildings - Part I
: Pretreatment
2000
IS 1477: Part 2: Code of practice for painting of ferrous metals in buildings: Part2
Painting
1971
611
2266.1. Lighting and Ventilation
Refer National Building Code 2016, Part8Sec
tions 1
2266.2.Electrical and Allied Installations
Refer National Building Code 2005 Part 8 Section 2
Insulation and Noise control Refer National Building Code 2005 Part 8 Section 4
2266.5. Lift and Escalators
2266.6.Stairs, passages
This shall be constructed as per the architectural and structural drawings.
2266.7.Water supply
Refer National Building Code 2005 Part 9 Section 1 clause 4
2266.10.Gas Supply
Refer National Building Code 2005 Part 9 Section 2
2266.11.Fire fighting
Refer National Building Code 2005 Part 4 2266.12.
Landscaping, Signs and Outdoor Display Structures Refer National Building Code 2005
Part 10 Section 2. Latest codes shall be followed
612
APPENDIX 2200A
Inspection Note ( )
Inspection Notes of ............
Date of Inspection .................. Estimate amount ..................
Name of work ...................... Date of contract ..................
Name of contractor ................. Date of completion as per agreement…………..
3. Are there any special difficulties affecting the progress of the work
APPENDICES
4. Is the supply of departmental materials satisfactory
5 Are there any designs, working drawings or special instructions required fromthe
Department which might hold up progress. If so what action has been taken
7. Do you find any need for deviation from sanctioned estimate of any particular item. If so
briefly indicate measures of the nature of deviation
.General remarks:
613
Appendix 2200B
Material Collection Repor
Material Collection/ Initial LevelReportNoDate ofReporting
NameofWork Name ofSection
Name of Subdivision
If part supply reference to earlier report and clearance
Estimated PAC Agreed PAC
Name of Contractor Agreement no. and date Tender Excess
Date of handing over of Site Scheduled date of Completion
Sl Descriptio Name of Quantity Quantity Reference to Date of Date of Quantity Upto Remar ks
no. n of item / Locality, Km as per measured M.book/ measurem check as per date
supplied and chainage agreemen Field Book ent measure check quanti
ofroad t me nt measurem ty
ent
PWD ENGINEERING MANUAL-2020 APPENDICES
614
APPENDIX 2200C
MACHINERY FOR EXCAVATION OF DIFFERENT OPERATION OF ROAD
CONSTRUCTION ( )
Sl. Type of Soil Choice of Roller/Plant Remarks
No.
A Compaction of Embankment and Sub-grade
A.1 Granular and dry cohesive i 8-10 Ton three smooth
soil wheeled roller
ii 80-100 kN vibratory
compactor
iii Pneumatic tyred roller Load per wheel 20 kN
A.2 Uniformly graded soil i 8-10 Ton three smooth
wheeled roller
APPENDICES
ii Pneumatic tyred roller Load per wheel 15 kN
iii 8-10 Ton vibratory roller
A.3 Cohesive soil Sheep foot roller
A.4 Cohesionless soil Vibratory roller
B Earth Moving Operations
B.1 Clearing and grubbing i Dozer
clearing light scrub,
grass, etc.
ii Motor Grader Can easily be used if scrub is very
615
Sl. No. Type of Soil Choice of Roller/Plant Remarks
B.4 Spreading : Distributing fill in i Scraper, tractor towed Best machine for
layers of uniform thickness ormotorised hauling and spreading
thin layers of material
ii MotorGrader Used for spreading and
withdrawing
materialsof
workable nature
iii TippingTrucks Can spread their loads
to a limited extent
iv CrawlerDozer Best machine for initial
PWD ENGINEERING MANUAL-2020 APPENDICES
spreading of workable
material
B.5 Cambering i MotorGrader Best machine for
providing final camber
ii CrawlerDozer Can provide camber
during initial
excavation for road
formation
iii Scraper, tractor towed Can provide camber
ormotorized during initial
excavation for road
formation
B.6 Scarifying and shaping earth roads Grader with scarifier Best machine for
loosening for shaping
top layer of
earth
B.7 Maintenance of earth haul roads i Motor grader/ wheelcrawler Best machine for this
work
ii Wheel / Crawlerdozer Should be used only if
grader not available
B.8 Watering i
Truckortrailermountedwatertank
erwitha
sprinkler and water pump
C Compaction
C.1 Soil Stabilisation i 8-10 ton three smooth
wheeledroller
ii Vibratingroller
C.2 Granular base/ Sub Base i 8-10 ton three smooth
wheeledroller
ii Vibratingroller
C.3 Macadam and other coarse i 8-10 ton three smooth
aggregate base wheeledroller
Courses
ii Steel wheeled Vibratoryroller
C.4 Mix-in-place Asphalt base course i 8-10 ton three smooth
wheeledroller
616
ii Vibratory compactor tandem8-
10ton
iii Pneumatic Tyreroller
C.5 Plant-mix base leveling or surface i 8-10 ton three smooth For break-down rolling
courses wheeledroller
ii Steel wheeled tandemroller For break-down rolling
iii Pneumatic tyred For intermediate rolling
roller(Selfpropelled)
iv TandomRoller For intermediate rolling
v Rubber tyred roller For final rolling
APPENDICES
Sl. No. Type of Soil Choice of Roller/Plant Remarks
D Bituminous Pavement
D.1 Surface dressing i Bitumen For uniform application of binder
pressure distributor,
if bulkbitumen
supply is available
ii For even spreading of chips to correct thickness
Chipspread
er
D.2 Bituminous grouting i Bitumen
617
ii Bitumen For tack coat
boilers withsprayers
iii Bitumen
pressuredistributors
iv Hot mix Batch or continuous type
plant 40-060 ton or
more/hr
v Electronic To match the capacity of hot
paver finisher mix plant
withsensor
vi 6-8 nos depending on the distance from the plant
TippingTru
cks
vii Front For cold feed loading
PWD ENGINEERING MANUAL-2020 APPENDICES
endloaders
viii Generators if For electrical hot mix plants
required
ix 8-10 ton
three smooth
wheeledroller
x Vibratory
tandemroller
xi Rubber
tyred roller
E Sub base/ base course
E.1 Soil Stabilisation i SoilStabiliser
ii Rotavater
iii Vibratory roadroller
iv 8-10 ton three
smooth wheeledroller
v Water Sprinkler
E.2 Water Bound Macadam i Aggregatespreader
(WBM)
ii Water Sprinkler
618
Sl. Type of Soil Choice of Roller/Plant Remarks
No.
iii 8-10 ton three smooth
wheeledroller
iv TippingTrucks
E.3 Wet Mix i Multi-stage stone
Macadam crushingplant
(WMM)
ii Concretemixer Suitable for small quantity of works
iii Wet Mixplant Plant should have tin shaft pug mill
APPENDICES
iv Paver Finisher It has better control of thickness and profile
v TippingTrucks
vi 8-10 ton three smooth
wheeledroller
vii Vibratory roadroller
E.4 Granular Sub base i MotorGrader
(GSB)
ii TippingTrucks
iii 10 ton three smooth
wheeledroller
619
APPENDIX 2200D
Tentative Output of Road Machinery ( )
Machine/ Tool Output
1 Scraper (Motorised)towed 160 cum/day
2 Dozer 200 cum/day
3 MotorGrader 600 cum/day
4 Excavator 1 m3capacity 400 cum/day
5 Three smooth wheeled roadroller
5.1 Earth work 450 cum/day
5.2 Moorum/Gravel 450 cum/day
5.3 Pavement
5.3.1 WBM Stone basecourse 45 cum/day
5.3.2 WBM/ WMM wearingcourse 40 cum/day
5.3.3 DBM 40 cum/day
5.4 Surface Dressing
PWD ENGINEERING MANUAL-2020 APPENDICES
620
APPENDIX 2200E
Details to be submitted for Approval from Engineer to start work (As per para 2218.1)
(i) Source and location of all materials;
(ii) Proportions of all materials expressed as follows where each is applicable: (a) Binder type, as
percentage by weight of total mixture;
(b) Coarse aggregate/Fine aggregate/Mineral filler as percentage by weight of total aggregate including
mineral filler;
(iii) A single definite percentage passing each sieve for the mixed aggregate;
(iv)The individual gradings of the individual aggregate fractions, and the proportion of each in the
combined grading.
(v) Physical properties of the mix detailed in the relevant sections as obtained by theContractor;
(vi) Where the mixer is a batch mixer, the individual weights of each type of aggregate, and binder per
batch,
(vii) Test results of physical characteristics of aggregates to be used;
APPENDICES
(viii) Mixing temperature and compacting temperature.
APPENDIX 2200F
PROFORMA OF PROGRESS OF WELL STEINING AND SINKING ( 2237.2)
Note: Give the number plan of the wells on the first page.
*Heading of columns shall be as given below:
1. Date
2. Time of observation
3. Well No.
621
APPENDIX 2200G
PROFORMA FOR RECORDING TILTS AND SHIFTS OF WELLS
Note: Give the numbering plan of the wells on the first page.
*Heading of columns shall be as given below:
1. Date
2. Time of observation
3. Well No.
4. Total steining done in the well up-to-date (vide column 5(iv) of proforma of progress ofsinking)
5. Total sinking done up-to-date (vide column 6 of proforma of progress of sinking).
6. Reduced levels at the gauge marks on the tilted plane: (i) Along X axis (traffic axis)
Side
(say north side) (say south side)
(ii) Along Y axis (perpendicular to traffic axis) On downstream side On upstream side
7. Difference in levels taken on the tilted plane: (i) Along X-axis.
(ii) Along Y-axis
PWD ENGINEERING MANUAL-2020 APPENDICES
8. Extent of tilt:
(i) Along X-axis
(ii) Along Y-axis
9. Shifts:
(i) Along X-axis
(ii) Along Y-axis
10. Action being taken in case tilt has exceeded 1/80 and shift 150 mm
11. Remarks.
12. Signature of the official taking observation
13. Signature of Assistant Engineer in token of check
14. Signature of Executive Engineer/Superintending Engineer in token of having seen the register
APPENDIX 2200H
STATEMENT SHOWING PARTICULARS OF DIFFERENT METHODS ADOPTED AND
PHENOMENON ENCOUNTERED DURING WELL SINKING ON DIFFERENT WELLS (As per
para 2337.2)
12. Whether dewatering was done after bottom plugging and if so how much below river water
level
13. Rate of rise of water inside the well in dewatering testRemarks
14. Signature of person recording the information
622
PWD ENGINEERING MANUAL-2020 APPENDICES
623
Appendix 2600A
Type of distress, Symptoms, Probable causes and possible types of treatment ( )
Sl Type of Symptoms Probable causes Possible types of
no distress treatment
A Surface
defects
1 Fatty surface Collection of binder on the Excessive binder in premix, spray or tackSand blinding; open-graded
surface coat, loss of cover to aggregates;premix;
excessively heavy axle loads liquid seal coat; burning of
excess binder; removal of
affected area
2 Smooth Slippery Polishing of aggregates under traffic, Resurfacing with surface
surface excessive binder dressing or
premix carpet
3 Streaking Presence of alternate lean and Non-uniform application of bitumen or Application of a new
PWD ENGINEERING MANUAL-2020 APPENDICES
624
or heavy bullock cart traffic
2. Corrugations Formation of spots regularLack of stability in mix, oscillations setScarification and relaying of
undulations up by vehicles, springs, or faulty layingsurfacings, of cutting of high
of surface course spots
and filling of low spots
3. Shoving Localised bulging of pavement Unstable mix, lack of bond betweenRemoving the material to
surface along the crescentlayers, or stop type movements and thosefirm base and relaying a
shaped cracks involving negotiation of stable mix
curves and gradients
4. Shallow Localised shallow depressions Presence of inadequately compactedFilling with premix
depressions pockets materials
APPENDICES
5. Settlement Large deformation of pavement Poor compaction of fills poor drainage,Where fill is weak, the
and upheaval inadequate pavement or frost heave defective fill should be
excavated and re-done.
Where inadequate pavement
is the
cause, the pavement should
be strengthened.
D Disintegratio
n
1 Stripping Separation of bitumen fromUse of hydrophilic aggregate, inadequateSpreading and compacting
aggregate in the presence ofmix composition, continuous contactheated sand over the
625
Appendix 2600B Maintenance criteria (2601.1)
Features Criteria Action Priority
A Features concerned with safety
of
Traffic
A1 Major breaches in the road way Any type of breach which Steps to be taken as Urgent
endangers safety of per clause 14.7 of
traffic and causes obstructions MoRTH
to flow of traffic Handbook
A2 Minor cuts or blockades Cuts or blockades which do Get blockades Urgent
not completely obstruct traffic removed and get the
but endanger safety of traffic cuts repaired
A.3 Branches of trees at height less Any kind Get them cut in Special
than 4.5 m over the roadway order of lower ones attention
first
B. Carriageway and crust conditions
B-1 Cracking not accompanied by a) Cracking in local areas a) Local sealing or Routine
PWD ENGINEERING MANUAL-2020 APPENDICES
626
avinganexcessthick
nessof about one-
third the depth of
rut. Compacttill
surfaceislevelledan
dlocalsealingofcrac
ks.
b)More than 50 mm With surface Work of
accompanied by cracking dressing over original
cracks, overlay nature
required
B-5 Potholes Potholes, as soon as they occur required Local Special
restoration by attention
APPENDICES
patching preferable
B-6 Reflection cracks a) Widely spaced cracks Slurry for fog seal Recurrent
b) Closely spaced Apply surface Special
dressing use of attention
geotextiles
627
Features Criteria Action Priority
B-7 Edge subsidence Any extent Patch road edge and repair Recurrent
and rutting shoulder
B-8 Defective camber Any extent Check and correct by Special attention
reconstructing to proper
camber profile
B-9 Undulations Any extent Investigate the cause and rectify Special attention
B-10 Loss of material Any extent Investigate the cause and rectify Special attention
from unpaved
road
C Shoulders-side-
drains
C-I Deformation or Any extent Fill and compact and bring its Routine
PWD ENGINEERING MANUAL-2020 APPENDICES
628
Appendix 2600J
Register of avenue trees As on.
Division…………………………. Subdivision………………………
Section…………………………...
Sl. No. Name of Proceeding in the Species Girth at 1 metre Whether Revenue Remarks
of trees road direction of above ground level yielding ornot
Kilometre Kilometerage
Left Right
1 2 3 4 5 6 7 8
Note: - 1. Numbering should be done serially in every road in each kilometer in the direction of
increasing kilometerage first on the left side and then on the right side.
2. The number should be written or stenciled in black with figures 7 ½ cm. height after painting the
background in white.
PWD ENGINEERING MANUAL-2020 APPENDICES
Appendix 2600K
ROAD CUTTING AND RESTORATION PROTOCOL (As per Para 2607)
1.1 A road-opening permit is required for any digging, excavation or construction of any kind within a
public right of way or that has an effect on the right of way. The road excavations by any person or authority
or agency and its reinstatements there after shall strictly follow thisProtocol.
1.2 A separate permit shall be required for each and every road opening. Excavation for appurtenances
such as manholes, small head walls, cutoff walls, small vaults, valve boxes, catch basins, wall footings, etc.
APPENDICES
4 Issuance of Permit
4.1 The Road authority should verify the proposal, conduct a joint inspection if necessary, and prepare a
detailed estimate for restoration works as per the standards. The work should not include any uprooting
of trees.
4.2 The Highway Authority should direct the utilities to make use of any available ducts or channels
provided for this purpose, especially along bridges and across roads orjunctions.
4.3 Validity of permit
4.3.1 Permit shall be in effect for thirty (30) days from date of issue, however any opening should not
be left unfilled for a period exceeding 48 hours. In case the work needs more than 30 days, it shall be at the
630
necessary precautions and shall be liable for any damage caused by the construction.
5.4 The contractor will be required to repair the permanent trench for a period of one(1) year.
5.5 The contractor will be responsible for all miscellaneous expenses. For no reason shall the
Department be responsible for any costs incurred from any of the conditions of the road opening permit,
including but not limited to, any costs related to any litigation related to thispermit.
this is to be properly backfilled before the other half is opened, so as to permit the free flow of traffic. In
some cases it may be possible to open on each side of the road and jack or drive a pipe from one opening
to the other. This should be done whenever possible.
6.1.4 Tunneling or mechanical methods of boring under the road for service installations may be
permitted only on written approval of the Highway Authority, or his representatives.
6.1.5 Excavated material suitable for backfilling shall be stockpiled in an orderly manner and unsuitable
/ excess mteral shall be disposed off suitably by the contractor. Excavated material will only be placed on
the traveled way when it will not impede the flow of traffic.
7 Pipe/ cable laying:
7.1 The bottom of the trench shall be accurately graded to provide uniform bearing and support for each
section of the pipe. Foundation and bedding for these underground facilities shall be native material, or
sand or quarry dust, which conforms to the grading requirement of MoRTH for fineaggregate.
7.2 When backfill material consists of aggregate base course, crushed stone, or other material containing
stones, only sand/ Quarry dust will be used for foundation and bedding. In case of PVC and other plastic
type pipes the bedding shall invariably be of sand. The foundation depth below the pipe shall be 15cms and
bedding depth shall be 30cms above the top of the facility.
7.3 Alternately a concrete rectangular open section of maximum width 45 cm could be used as bed and
pipes/ cables placed over it. It shall be continuous true to lines and levels so as to form a channel. This
shall then be sand filled and over it backfilling done. Semi circular concrete sections may also be usedto
cover these pipes before sand filling. Each cast block shall be about 60cms length.
30 cm
7.4 If any utilities are exposed during excavation, i.e. Sewer, Water, Electric, etc., the appropriate
department will be notified for the opportunity for an inspection prior to backfilling. In any case an
inspection by the highway authority is mandatory.
8 Procedure for Backfilling
8.1 Backfilling will be done with excavated material unless otherwise directed by the Highway
Authority. It shall be done, with flowable fill or mechanically compacted materials in 15cms lifts or jetted
with water to within 5cms of pavement grade.
8.2 When material is placed on the traveled way, suitable arrangement shall be in place to sweep and
keep the pavement clean and free of dust after backfilling each day.
8.3 Acceptable backfill material shall conform to clause 305 of MORTH. This does not preclude theuse
of excavated material which may meet these specifications. The Department reserves the right to test any
and all backfill material prior to its use.
631
8.4 Backfill shall be deposited in layers not to exceed 20 cm in depth before compaction. Equipment to
be used for compaction may include vibrating tampers of the mechanical or pneumatic type, impact type
rammers or trench rollers or any other type of equipment, which will produce therequired
degree of compaction. Rolling and compaction shall be done in the longitudinal direction of the trench.
8.5 If the moisture content of the soil is outside of the limits required for achieving 95 percent of
maximum compaction the the addition of water or the use of drier soil so that the required degree of
compaction will be achieved. Water consolidation by jetting of these layers shall be resorted towithout
causing any flooding, when compaction methods are not possible.
8.6 Exceptional cases In case of excavation greater than 1.5m, the in situ densities shall be taken and
compaction done to achieve the same while backfilling upto 1.5 m depth. Top 1.5 m shall be done as per
above specifications.
APPENDICES
8.7 Temporary Pavement
8.7.1 The last 10 cm shall be a temporary bituminous/ concrete patch in case of trenches across or on
the pavement. If pavement restoration is not to be made immediately, backfill shall be carried to the
finished grade of the pavement, the final 10cm to consist of shoulder stone or approvedequal.
8.7.2 In case of trenches for domestic/ residential use, the top 10cm shall be of concrete afterrefilling
and consolidation as specified earlier.
8.8 Driveways, sidewalks, street intersections, shoulders, lawns, shrubs, trees, signs and pavement
markings shall be restored to conditions prior to construction, at no extra cost. No tree limbs, or brushwill
be cut without prior approval of the Highway Authority.
8.9 Reference markers
35 cm
25 cm
25 cm
(Not to scale)
632
8.10 At this stage the road shall be inspected by the highway authority and a certificate issued to the
effect that the backfilling has been done as per specifications. Based on thiscertificate, the permittee may
accord sanction for final payment.
9 Final Pavement
9.1 After completion of the work covered by this permit, there will be a surface overlay of bituminous
concrete in case of pavements and shoulder restoration in case of side trenches..
9.2 The temporary bituminous patch as specified above is to be maintained for a minimum of thirty (30)
days. Then the temporary patch shall be removed and a permanent patch shall be applied in
accordance with MoRTH Specification for patch working.
9.2.1 In case of trenches along the road allow sub-grade to dry sufficiently, scarify, digout up to 30cm
on each side of the original cut, so that the patch is placed on undisturbed material when the permanent
patch is applied. Wherever necessary, an additional base course has to be provided.
9.2.2 In case of trenches across roads, bituminous concrete laid to full width of the traveled way, and 3
meters both sides of the excavation at a minimum depth of 2-4 cm or at the discretion of the Highway
PWD ENGINEERING MANUAL-2020 APPENDICES
11.1.3 Backfilling- material should conform to specified standards, and compaction shouldachieve
required density.
11.1.4 Pavement layer- should merge with the adjacent surface without causingbumps.
AppendixA (TeStingFrequencieS)
Embankment/Subgrade
633
Maximum Dry IS 2720 2 tests per 1.52gm/cc(min) for To check at least15% of the
Density Part 8 3000 m³ embankment tests during execution.
(Proctor) 1.75gm/cc(min)
for subgrade
CBR Value IS 2720 1 tests per >5% for To check at least 15% of
Part16 3000 m³ embankment the tests during execution.
>8%for
subgrade
Field Density IS 2720 2 tests per 97%for subgrade To check at least 15% of
Part 8 3000 m³ 95%for embankment the tests during execution.
APPENDICES
GranularSub-Base
Liquid Limit IS 2720 1 tests per <25% To check at least 15% of the
Part 5 200 m³ tests during execution
634
Maximum IS 2720 2 tests per - To check at least 15% of the
Dry Density Part 8 1000 m³ tests during execution.
CBR Value IS 2720 1 tests per As per Grading To check at least 15% of the
Part16 3000 m³ tests during execution.
Sieve Analysis IS 2386 1 tests per As shown in To check at least 15% of the
Part 1 100 m³ table A.3 below tests during execution.
635
Temperature
For binder at the time of mixing : 150-163 Degrees For aggregate at thetimeof mixing : 155-163
Degrees For mix attheplant : 130-160Degrees
For layingat site: 120-160Degrees
Rolling operation shall be completed before temperature of mix falls below 100 degrees/ Units.
APPENDICES
IS Sieve Designation Per cent by weight passing sieve
For 50 mm compacted For 75mm compacted
Thickness thickness
Coarse Key aggregate Coarse Key aggregate
Aggregate aggregate
63 mm 100
53 mm
45 mm 100 58-82
Quantities of materials required for 10 sq.m area for bituminous penetration macadam is givenbelow.
TABLE –B.5.2
636
Dry and clean coarse aggregate shall be spread uniformly and evenly at the rate specified by the above
table. After the coarse aggregate has been rolled and checked, the bituminous binder shall be applied at
specified temperature, the rate of application given in the abovetable.
Immediately after the first penetration of bitumen, key aggregate in a clean and dry state shall be spread
uniformly over the surface by means of an approved mechanical spreader at the rate specified in the above
table and rolled in accordance with the specification.
Seal Coat
Seal coat of two types (see MORT&H clause 513)
Type-A- Chip Sealing seal coat comprising of an application of a layer of bituminous binder followed by
a cover of stone chippings.
PWD ENGINEERING MANUAL-2020 APPENDICES
Type-B- Premixed seal coat comprising of thin application fineaggregate premixed with
bituminousbinder.
Physical requirement of aggregate
Type-A- the aggregate shall satisfy all the physical requirements ofaggregate
for bituminous macadam except for water absorption which shall be less than 1%. Stone chippings shall be
of 6.7 mm size defined as 100% passing through 11.2 mm sieve and retained on 2.36 mm sieve. The quantity
used for spreading shall be0.09cum/10sq.m.
NOTE : The contractor is responsible to ensure that the surface seal coat does not strip, ravel, flush or
bleed. Spray rates for bitumen & spread rates for aggregate chips must be adjusted to allow for the effects
of traffic and size and quality of aggregate chip etc.
Type-B- The aggregate shall pass through 2.36 mm sieve and be retained on 180-micron sieve
. Type-B- The aggregate shall pass through 2.36 mm sieve and be retained on 180-micron sieve
.The quantity used for premixing shall be 0.06 cum/10sq.m.
B.7. The spray rate of bitumen for bituminous works is detailed below
Note : There is no need for tack coat on freshly laid bituminous surfaces if overlaid on same day without
opening to traffic.
637
Appendix B (RoadWorkS)
Specification – General requirements (Refer to relevant clauses of latest edition of MORT&H
Specifications for Roads and Bridges for full descriptions)
List of typical equipment that needs to be checked/calibrated
APPENDICES
Graders Blades are straight
Pavers Boards are flat segments are
aligned and angle of attack
correct hydraulics smooth
Trucks Mechanically sound, tyres at
correct pressure
Thermometers Checked against standard
Weigh-Scales Calibrated with standard
638
The physical requirements of the materials for sub-base are (a) 10 per cent fines value in soaked condition:
min 50 KN (b) water absorption: max 2%.
BaseCourse
Physical Requirements of Aggregates (WBM)
The requirements for aggregates used are (a) Los Angeles abrasion value :max 40% (b)Aggregate
impact value max 30% (c) combined Flakiness and Elongation index : max 30%.
TABLE – B.3.1
Aggregates with bricks, kankar, laterite, etc. which get softened in presence of water shall be tested
for impact value under hot conditions in accordance with IS 5640. Flakiness index and elongation
index shall be enforced only in case of crushed broken stone and crushed slag and the combined
flakiness and elongation shall not exceed 30%.
The screenings used to fill the voids have to satisfy gradation given below. When gravel is used
the liquid limit should be less than 20 and the plasticity index less than 6%. Percent passing 75-
micron sieve should not be morethan10%.
639
TABLE –B.3.2
APPENDICES
BituminousMacadam
The physical requirement of aggregate used for bituminous macadam are (a)Los Angeles abrasion value
max 40% (b) aggregate impact value : max 30% (c) flakiness and elongation (total):max 30% (d) water
absorption : max 2% (e) soundness : max loss of weight 12% for sodium sulphate and 18% for magnesium
sulphate.
TABLE –B.4.1
Bitumen content for pre mixing shall be 3 to 3.5 per cent by weight of total mix. The maximum
compacted layer thickness shall be 100 mm. Bituminous macadam mix shall be prepared in a hot
mix plant of adequatecapacity.
640
Temperature
For binder at the time of mixing : 150-163 Degrees For aggregate at thetimeof mixing : 155-163
Degrees For mix attheplant : 130-160Degrees
For layingat site: 120-160Degrees
Rolling operation shall be completed before temperature of mix falls below 100 degrees/ Units.
Quantities of materials required for 10 sq.m area for bituminous penetration macadam is givenbelow.
TABLE –B.5.2
641
Dry and clean coarse aggregate shall be spread uniformly and evenly at the rate specified by the above
table. After the coarse aggregate has been rolled and checked, the bituminous binder shall be applied at
specified temperature, the rate of application given in the abovetable.
Immediately after the first penetration of bitumen, key aggregate in a clean and dry state shall be spread
uniformly over the surface by means of an approved mechanical spreader at the rate specified in the above
table and rolled in accordance with the specification.
Seal Coat
Seal coat of two types (see MORT&H clause 513)
Type-A- Chip Sealing seal coat comprising of an application of a layer of bituminous binder followed by
APPENDICES
a cover of stone chippings.
Type-B- Premixed seal coat comprising of thin application fineaggregate premixed with
bituminousbinder.
Physical requirement of aggregate
Type-A- the aggregate shall satisfy all the physical requirements ofaggregate
for bituminous macadam except for water absorption which shall be less than 1%. Stone chippings shall be
of 6.7 mm size defined as 100% passing through 11.2 mm sieve and retained on 2.36 mm sieve. The quantity
used for spreading shall be0.09cum/10sq.m.
B.7. The spray rate of bitumen for bituminous works is detailed below
Note : There is no need for tack coat on freshly laid bituminous surfaces if overlaid on same day without
opening to traffic.
642
Requirement of sprayed bituminous chip sealing for surface dressing
Spray rates for bitumen and spread rates for aggregate chips depends on traffic, aggregate chip size,
bitumen temperature, and penetration etc and shall be checked with the Engineer before sprayed chip
sealing is attempted
B. 8. Built Up Spray Grout (See IRC47)
The grading requirement is given below are percentage by weight passing the sieve.
TABLE –B-7.1
PWD ENGINEERING MANUAL-2020 APPENDICES
: 15kg/10sq.m
Second : 15kg/10sq.m
Coarse aggregate is spread uniformly at the rate of 0.5-cum/10sq.m areas over a tack coat and inder is
applied at 15kg/10sq.m area. Immediately after key aggregate is spread uniformly at 0.13 cum/10sq.m area
and rolled, brooming. whenever required for uniformity. Then the final surface has to be provided without
delay .If there is delay, a seal coat should be provided as an intermediate step.
643
Binder content: Minimum 4% of mix by weight. Gradation requirements are given below
TABLE –B.8.1
Grading 1 2
Nominal aggregate size 13mm 10mm
Layer Thickness 35 – 40mm 25 -30mm
+
IS Sieve (mm) Cumulative % by weight of total aggregate passing
19 100
13.2 90 – 100 100
9.5 70 – 90 90 - 100
4.75 35 – 51 35 - 51
APPENDICES
2.36 24 – 39 24 - 39
1.18 15 – 30 15 - 30
0.3 9 – 19 9 - 19
0.075 3–8 3-8
Bitumen content % by mass Min. 4.5 Min 5.0
of total Mix #
Bitumen grade 65* 65*
+ The combined aggregate grading shall not vary from the low limit on one sieve to the high limit on the
adjacent sieve.
# Determined by the Marshall method.
* Only in exceptional circumstances, 80/100 penetration grade may be used, as approved by the Engineer.
Requirement of mix
644
Minimum temperature fo rrolling : 90 oC
Field Tests for Bituminousworks
No bituminous work shall be carried out when the atmospheric temperature is less than 16 degree and when
the base or the construction materials are damp. The thickness of the layer can be checked at frequent
intervals after compaction by using pre decided depth blocks. Rolling should continue till the roller marks
are eliminated. Rolling temperature should not fall below 100degree.
It is necessary to conduct tests at frequent intervals during the work to find out whether the prescribed
bitumen quantity is being used in the work. For this a simple field solubility test can be conducted (for field
control) as follows.
About 1 kg of the mix is collected and weighted accurately. The sample is immersed and flushed in either
carbon di-sulphide or carbon tetra chloride liquids (both chemicals are highly toxic and should only be used
in a fully vented fume cupboard). Kerosene can also be used for the purpose. Since the bitumen is
PWD ENGINEERING MANUAL-2020 APPENDICES
completely soluble in these solvents except for negligible quantities of impurities like carbon, salts, etc. the
weight of aggregates without the bitumen can be obtained to arrive at the difference in weight, which
represents the weight of bitumen used in themix.
Marshall StabilityTest
The Marshall stability test shall be used to determine bituminous concrete mix proportions and to test the
product delivered to the job. Mix shall be approved by the Engineer prior to use in theworks.
Other ControlMeasures
The camber of the laid surface should be checked by means of camber board and spirit level. Triangular
wedges may be used for finding out depressions under a 3 metre straight edge. Maximum allowable
depression is 6mm. Templates may also be prepared to check the cambers at different locations. The
longitudinal alignment should be checked by a straight edge and triangular wedge.
Traffic on the fresh surface should not be allowed until the mix has become cool enough to prevent wheel-
marking by traffic.
Standards of surfaceevenness
The surface unevenness should be controlled during construction so that both longitudinal and cross profiles
are simultaneously satisfied. The maximum number of undulations permitted in any stretch of 300 meters
length is 30 and in the cross profile, it is 6 only. The details of the permitted tolerance of surface regularity
of pavement courses are given as under.
645
Permitted tolerances of surface regularity for pavement courses
TABLE –B.10.1
APPENDICES
1 Earth subgrade 24 30 15
2 Sub base 15 30 12
3 WBM with 15 30 12
40mm 90mm
rolled
4 WBM with 20- 12 30 8
50mm of 40-
63mm size BPM
5 Surface dressing 12 20 8
6 Open graded 10 30 6
premix carpet mix
seal
surfacing
7 Bituminous 10 20 6
macadam
8 Semi dense 10 20 6
carpet
9 Asphalt 8 10 4
concrete
Surface level even-ness shall be in accordance with table 900-1 of MORT&H Specification for Roads and
Bridges. Surface even-ness may be measured by 3m straight edge and wedges or by other acceptable means
approved by the Engineer
Depending on the standards of original construction, change in traffic intensity, climatic conditions etc.,
maintenance of roads presents problems of different nature. A systematic approach involving sequential
operations is necessary.
646
The different items of maintenance works being carried out fall under three headings
Routine maintenance: including filling up potholes, patches, repairs to side berms, improving surface
drainage, cleaning choked culverts, painting sign boardsetc.
Periodical maintenance: including surface renewals (ie re-gravelling) and
trengthening by way of providing overlaysand Rectification/upgradation: including widening of
roads, improvement of CD works, improved drainage measures, providing new sign boardsetc.
RoutineMaintenance
Potholes
The occurrence of potholes is the most common phenomenon observed especially after rains. These can be
the result of but not limited to:
PWD ENGINEERING MANUAL-2020 APPENDICES
ingress of water into the pavement throughcracks, ingress of water by surface ponding because of
insufficient surface camber or super-elevation. lack of bond between the surfacing and the base course and
(d)use of insufficient bitumen in the surfacing etc.
Patching of these potholes has to be executed with care to make it successful.
The potholes should be cut as nearly as possible to the shape of a rectangle, sides being vertical.
All loose material shall be cleaned out. If there are deep pot holes as a result of improper drainage
or existence of soft pocket in the subgrade, these should be dug out down to solid subgrade, and
made good with well-graded aggregate. In WBM roads, the potholes should be filled with
aggregates and screenings as specified for WBM and compacted with heavy hand rammers. In
asphalt roads, the bottom and sides of the potholes duly trimmed to a rectangular shape should be
coated with bitumen emulsion (using a sprayer or by brushing) and filled with premix. The premix
should be compacted in layers of 25mm at a time, the hand rammers being dipped in water often
so that the coated metal may not stick to it. The finished surface should be compacted level with
(not below, but in any case no more than 5mm above) the surrounding roadsurface.
ShoulderGrading
Shoulders must be graded to slope away from the carriageway such that water can flow across the shoulder
and not run along the pavement adjacent to the carriageway.
647
Grass Cutting-JungleClearance
Grass shall be cut as per the specified interval debri removed from thesite
Repairs To HeadwallsEtc
Headwalls to culverts and masonry to side drains etc shall be repaired using the same techniques as used in
the original structure. Materials used shall be of sound quality according to the specification and
construction shall be in accordance with the best practice techniques
PeriodicMaintenance
Periodic maintenance such as BT overlays or Bitumen Chip Sealing surface dressing, or re-gravelling shall
APPENDICES
be carried out in accordance with the schedules prepared by the RMMS system. Materials and workmanship
shall be in accordance with the Contract andSpecification.
Where the maximum profile corrective course thickness works out to not more than 40 mm, it shall be done
as an integral part of the average course. In other cases, the profile corrective courses shall be provided as
a separate layer.
Potholes have to be filled before profile corrective course is laid.
BT Carpeting shall be in accordance with the specification and must be manufactured at 150º C and laid
in accordance with clauses B9 toB13.
BituminousTesting:
The control tests to be conducted on bituminous works are listed below for ready reference.
e) Binder content
f) Temperature
d) Grading of aggregates
f) Rate of spread
g) Temperature
5. Bitumimous Macadam:
a) Quality of binder
d) Stability of mix – Marshall test for stability, flow value, Density and void content
649
Appendix C (Structural WorkS)
Concrete Works
Aggregate
a) Coarse aggregate
For plain and reinforced cement concrete works, coarse aggregate shall consist of clean, hard,
strong, dense. non-porous and durable pieces of crushed stone, crushed gravel or a suitable
combination thereof or other approved inert materials.
APPENDICES
For every new source the following tests are to be conducted.
b) Fine aggregate
The fineness modulus of fine aggregate shall neither be than 2.0 nor greater than 3.5.
The grading requirement are given below
TABLE C-1.2
650
10 mm 100 100 100
Cement
The manufacture‟s test certificate can be accepted. The Contractor must produce the
manufacture‟s certificate for the relevant bill. If it is not available contractor must do tests at his
own cost and submit the result to the Engineer.
Steel
The steel used for structural work shall confirm to Table 1000-3 of MORT&H
specifications.
The manufacture‟s test certificate can be accepted. If it is not available contractor must do tests at
his own cost and submit the result to theEngineer.
Prior to construction, the contractor shall prepare a design mix in the case of „Design Mix Concrete‟ or
prepare a nominal mix in the case of „Nominal Mix Concrete‟ and obtain approval from the Engineer before
use. For PCC and small RCC works nominal mix design can be adopted, but for major RCC works and for
the concreting of load bearing structures a design mix must be followed based on the criteria in clause 1704
of MORT&H Roads and Bridges Specifications. For the testing and characteristic strength refer Table1700
MORT&H specification.
651
One set of sample (6nos of cube) shall be taken for every 50m3or for the day‟s work.
Formwork
All formwork and the reinforcement contained in it shall be cleaned and made free from standing water,
dust, snow or ice immediately before placing concrete.
Concrete shall be mixed either in a concrete mixer or in batching plant as mentioned in the contract or
approved by the Engineer. Hand mixing shall not be permitted. The mixer or plant shall be at an approved
location considering the properties of the mixers and transportation arrangement available with contractor.
The mixer plant shall be approved by the Engineer.
Curing
Exposed surfaces of concrete shall be kept continuously in a damp or wet condition or by covering a layer
of sacks, canvas, hessian or similar materials and shall be kept constantly wet for a period not less than 14
days from the date of placing ofconcrete.
Finishing
Immediately after the removal of forms, exposed bars or bolts if any shall be cut inside the concrete and
resulting holes filled with cement mortar.
.
Shifting ofUtilities
Pavement Shoulder
Length of Cut
Size of Opening
Type of (Material composition )
Bituminous layer
Metalled layer
Whenever Telephone/Electric posts/pipe lines are to be shifted to facilitate widening of roads, the
Executive Engineer concerned should forward a request to the concerned District Officer of the
department for shifting.
12.2 District Officers of the department/organisation concerned should shift the utilities within four weeks
of receipt of requisition and inform the Executive Engineer concerned about the completion of the work.
After the lapse of prescribed time, Highway Authority may initiate necessary steps for removal
of the same and the expenses incurred shall be levied from the concerned department.
12.3 Shifting of these utilities shall be done at the locations specified and directed by thehighway
Authority at the cost of concerned departments.
13 Penalty
13.1 Highway Protection Act clause 26 sub section (1) specifies the necessity for a permit and sub section
652
(3) describes the fine to be collected for such trespassing.
13.2 Failure to obtain a permit or comply with the regulations in force shall be subject to a fine of 10(ten)
times the estimated restoration charges plus the permit fee or the penalty specified under Clause 26
Sub section (3) of Highway Protection Act, whichever is greater.
PWD ENGINEERING MANUAL-2020 APPENDICES
653
Bibliography:
Bridges:
1 IRC: 5- 1998 Standard Specifications and Code of Practice for Road Bridges, Section I – General
. Features of Design (Seventh Revision)
2 IRC: 6 -2000 Standard Specifications and Code of Practice for Road Bridges, Section II – Loads and
. Stresses (Fourth Revision)
3 IRC:18- Design Criteria for Pre-stressed Concrete Road Bridges (Post-Tensioned Concrete)
. 2000 (Third Revision)
4 IRC:21- Standard Specifications and Code of Practice for Road Bridges, Section III – Cement
. 2000 Concrete (Plain and Reinforced) (Third Revision)
5 IRC:22- Standard Specifications and Code of Practice for Road Bridges, Section VI –
. 1986 Composite Construction (First Revision)
6 IRC:24- Standard Specifications and Code of Practice for Road Bridges, SectionV–SteelRoad
. 2001 Bridges (Second Revision)
7 IRC:40- Standard Specifications and Code of Practice for Road Bridges, Section IV – Brick,
PWD ENGINEERING MANUAL-2020 APPENDICES
11 IRC:83- Standard Specifications and Code of Practice for Road Bridges, Section IX – Bearings,
2002 Part III: POT, POT-CUM-PTFE, PIN AND METALLIC GUIDE BEARINGS
. (Part III)
12 IRC:87- Guidelines for the Design and Erection of False work for Road Bridges
1984
.
13 IRC:89- Guidelines for Design and Construction of River Training & Control Works for Road
15 IRC: SP: 33 Guidelines on Supplemental Measures for Design, Detailing & Durability of Important
Bridge Structures
. 1989
16 IS 456-2000 Plain and Reinforced Concrete - Code of Practice
Roads:
1. IRC:32-1969 StandardforVerticalandHorizontalClearancesofOverheadElectricPowerand
Telecommunication Lines as Related to Roads
2. IRC:38-1988 Guidelines for Design of Horizontal Curves for Highways and Design Tables
3. IRC:39-1986 Standards for Road-Rail Level Crossings
4. IRC:41-1997 Type Designs for Check Barriers
5. IRC:54-1974 Lateral and Vertical Clearances at Underpasses for Vehicular Traffic
6. IRC:65-1976 Recommended Practice for Traffic Rotaries
7. IRC:66-1976 Recommended Practice for Sight Distance on Rural Highways
8. IRC:69-1977 Space Standards for Roads in Urban Areas
9. IRC:73-1980 Geometric Design Standards for Rural (Non-Urban)Highways
10. IRC:80-1981 Type Designs for Pick-up Bus Stops on Rural(i.e., Non-Urban)Highways
11. IRC:86-1983 Geometric Design Standards for Urban Roads in Plains
12. IRC:92-1985 Guidelines for the Design of Interchanges in Urban Areas
654
13. IRC:98-1997 Guidelines on Accommodation of Underground Utility Services Along and Across
Roads in Urban Areas (First Revision)
14. IRC:99-1988 Tentative Guidelines on the Provision of Speed Breakers for Control of Vehicular Speeds on
-Minor Roads
15. IRC:103-1988 Guidelines for Pedestrian Facilities
16. IRC: SP: 12- 1973 Recommendations on the Provision of Parking Spaces for Urban Areas
17. IRC: 58-2002 Guidelines for the Design of Plain Jointed Rigid Pavements for Highways
18. IRC:SP: 72- 2015 Design of flexible Pavements
Buildings
655
ACKNOWLEDGEMENT
The Engineering Manual 2020 has been framed after many decades and the
compilation of the same was not possible without the relentless efforts of the
technical advisory team who worked consistently to accomplish this task in a very
short span of time.
The technical advisory team was all along guided by Er. Sami Arif Yasvi,
Development Commissioner Works, J&K PWD who supported the team at every step
during the process of framing this manual.
656