DOC : IMSR /EOM

PGP CONTRACTING
REV 0
TIME SHEET
ISSUE DATE: 31.1.2022
SUBSTATION East Sitra ACTIVITY DATE 22.2.2023

ACTIVITY TYPE Maintenance STARTING TIME 7.00 Am


NO OF MANPOWER 3 ENDING TIME 4.00Pm

CLIENT HYUNDAI EQUIPMENT ID T611

CLIENT REPRESENTATIVE Mr NAGENDRA KUMAR REPORT NO PGP-HE-EOM

MANPOWER DETAILS
SNO NAME OCCUPATION START TIME END TIME OVERTIME
1 Faiez Khan Supervisor 7.00 Am 4.00pm _
2 Aurangzeb Technician 7.00 Am 4.00pm _
3 Mohd Wahid Labour 7.00 Am 4.00pm _
ACTIVITY
SNO DESCRIPTION REMARKS
East Sitra T611
1 Washing of Transformer completed

2 Replacement of old labels with new one completed

3 Testing of oil Break down voltage completed


4 Red panting and stencil work on T611 transformer . completed
5 Replacement of Flexible hoses in Bucholz relay . completed
6 Transformer Meggering Test conducted . completed

7 Oil Sampling for laboratary test (full)- 4 nos completed


8 stencil work onTransformer completed

PGP RESOURCES USED


BDV KIT MEGGER KIT

PGP CLIENT
DOC : IMSR /EOM
PGP CONTRACTING
REV 0
TIME SHEET
ISSUE DATE: 31.1.2022
SUBSTATION East Sitra ACTIVITY DATE 23.2.2023

ACTIVITY TYPE Maintenance STARTING TIME 7.00 Am


NO OF MANPOWER 3 ENDING TIME 4.00Pm

CLIENT HYUNDAI EQUIPMENT ID T611

CLIENT REPRESENTATIVE Mr NAGENDRA KUMAR REPORT NO PGP-HE-EOM

MANPOWER DETAILS
SNO NAME OCCUPATION START TIME END TIME OVERTIME
1 Faiez Khan Supervisor 7.00 Am 4.00pm _
2 Aurangzeb Technician 7.00 Am 4.00pm _
3 Mohd Wahid Labour 7.00 Am 4.00pm _
ACTIVITY
SNO DESCRIPTION REMARKS
East Sitra T611
1 Yellow touch paint work on Transformer completed

2 Labelling of Transformer completed

3 Marking work and cleaning of LCP and OLTC panel completed


4 cleaning of Transformer using blower completed

PGP RESOURCES USED

PGP CLIENT
DOC : IMSR /EOM
PGP CONTRACTING
REV 0
TIME SHEET
ISSUE DATE: 31.1.2022
SUBSTATION East Sitra ACTIVITY DATE 26.2.2023

ACTIVITY TYPE Maintenance STARTING TIME 9.00 Am


NO OF MANPOWER 3 ENDING TIME 4.00Pm

CLIENT HYUNDAI EQUIPMENT ID T611 & T612

CLIENT REPRESENTATIVE Mr NAGENDRA KUMAR REPORT NO PGP-HE-EOM

MANPOWER DETAILS
SNO NAME OCCUPATION START TIME END TIME OVERTIME
1 Faiez Khan Supervisor 9.00 Am 4.00pm _
2 Aurangzeb Technician 9.00 Am 4.00pm _
3 Mohd Wahid Labour 9.00 Am 4.00pm _
ACTIVITY
SNO DESCRIPTION REMARKS
East Sitra T611
1 Trip Test conducted before Energization completed

East Sitra T612


1 Washing of Transformer completed
2 label work on transformer necessary areas. in Progress

PGP RESOURCES USED

PGP CLIENT
DOC : IMSR /EOM
PGP CONTRACTING
REV 0
TIME SHEET
ISSUE DATE: 31.1.2022
SUBSTATION East Sitra ACTIVITY DATE 27.2.2023

ACTIVITY TYPE Maintenance STARTING TIME 7.00 Am


NO OF MANPOWER 3 ENDING TIME 4.00Pm

CLIENT HYUNDAI EQUIPMENT ID T612

CLIENT REPRESENTATIVE Mr NAGENDRA KUMAR REPORT NO PGP-HE-EOM

MANPOWER DETAILS
SNO NAME OCCUPATION START TIME END TIME OVERTIME
1 Faiez Khan Supervisor 7.00 Am 4.00pm _
2 Aurangzeb Technician 7.00 Am 4.00pm _
3 Mohd Wahid Labour 7.00 Am 4.00pm _
ACTIVITY
SNO DESCRIPTION REMARKS
East Sitra T612
1 Yellow touch paint work on Transformer completed

2 stencil work on Transformer completed

3 Red paint work on Transformer completed


4 label work on transformer necessary areas. completed
5 Red Marking in LCP and OLTC panel completed
6 Testing of Oil Breakdown voltage completed

7 Transformer Meggering Test conducted . completed

8 Fixing of covers on LCP heaters . completed

9 cleaning of local control panel and oltc panel completed

10 Oil Sampling for laboratary test (full)- 4 nos completed


PGP RESOURCES USED
BDV KIT MEGGER KIT

PGP CLIENT
DOC : IMSR /EOM
PGP CONTRACTING
REV 0
TIME SHEET
ISSUE DATE: 31.1.2022
SUBSTATION East Sitra ACTIVITY DATE 28.2.2023

ACTIVITY TYPE Maintenance STARTING TIME 7.00 Am


NO OF MANPOWER 3 ENDING TIME 3.00pm

CLIENT HYUNDAI EQUIPMENT ID T612

CLIENT REPRESENTATIVE Mr NAGENDRA KUMAR REPORT NO PGP-HE-EOM

MANPOWER DETAILS
SNO NAME OCCUPATION START TIME END TIME OVERTIME
1 Faiez Khan Supervisor 7.00 Am 3.00pm _
2 Aurangzeb Technician 7.00 Am 3.00pm _
3 Mohd Wahid Labour 7.00 Am 3.00pm _
ACTIVITY
SNO DESCRIPTION REMARKS
East Sitra T612
1 Trip test conducted before Energization . completed

PGP RESOURCES USED

PGP CLIENT