The document provides quotations for labour rates for various construction items for a boundary wall project. It lists 7 items with their respective unit, labour rate and remarks. It notes that the rates provided are only for labour and do not include costs for materials, machinery, taxes or contractor profit. It also provides breakdowns of the cost components to calculate the rate per cubic meter of concrete for 3000 PSI, 4000 PSI and 1500 PSI, including quantities of materials, their individual rates and costs, overhead and profit amounts. The final section updates the cement rate for a date of March 15th, 2022.
The document provides quotations for labour rates for various construction items for a boundary wall project. It lists 7 items with their respective unit, labour rate and remarks. It notes that the rates provided are only for labour and do not include costs for materials, machinery, taxes or contractor profit. It also provides breakdowns of the cost components to calculate the rate per cubic meter of concrete for 3000 PSI, 4000 PSI and 1500 PSI, including quantities of materials, their individual rates and costs, overhead and profit amounts. The final section updates the cement rate for a date of March 15th, 2022.
The document provides quotations for labour rates for various construction items for a boundary wall project. It lists 7 items with their respective unit, labour rate and remarks. It notes that the rates provided are only for labour and do not include costs for materials, machinery, taxes or contractor profit. It also provides breakdowns of the cost components to calculate the rate per cubic meter of concrete for 3000 PSI, 4000 PSI and 1500 PSI, including quantities of materials, their individual rates and costs, overhead and profit amounts. The final section updates the cement rate for a date of March 15th, 2022.
The document provides quotations for labour rates for various construction items for a boundary wall project. It lists 7 items with their respective unit, labour rate and remarks. It notes that the rates provided are only for labour and do not include costs for materials, machinery, taxes or contractor profit. It also provides breakdowns of the cost components to calculate the rate per cubic meter of concrete for 3000 PSI, 4000 PSI and 1500 PSI, including quantities of materials, their individual rates and costs, overhead and profit amounts. The final section updates the cement rate for a date of March 15th, 2022.
Download as XLSX, PDF, TXT or read online from Scribd
Download as xlsx, pdf, or txt
You are on page 1of 5
Date: 12/11/2017
Boundary Wall Labour Rate Quotation
Sr# Item Unit Labour Rate Remarks
1 Brick Works C.M 2040
2 Plaster Works Sq.M 330
3 Concrete Pouring C.M 980
4 Form Work Sq.M 950
5 Steel Fixing Ton 15000
6 Barbid Wire Fixing R.m 420
7 Backfilling(without C.M 550
Material) NOTES 1 These Rates are only labour rate(No Material & Machinery included). 2 Contractor's profit and labour costs etc are included. 3 No Tax included in our rates. 4 Payment will be made as per actual executed quantities 5 Electricity & water is respensbilty of clinte. 3000 Psi Concrete Rate Breakdown Per C.M Sr# Description Qty Rate Cost Accumulative Remarks 1 Cement 320 17.4 5568 5568 2 Crush 28 60 1680 7248 3 Sand 17.6 34 598.4 7846.4 4 Admixer 3.1 75 232.5 8078.9 7 Water 190 0.37 70.3 8149.2 8 Profit+ Over Head 1 12% 977.904 9127.104 9127.104