1.1 SCOPE
1.2 PURPOSE
The objective of this work instruction is to give a guideline to the QC Inspector and
Workshop’s Foremen/Supervisor to ensure hydrostatic testing is conducted in a safe and
efficient manner and in accordance to specification/codes for piping which subject to
internal test.
Client’s specifications
Chloride content in water shall be less than 250 ppm for carbon steel components.
Chloride content in water shall be less than 50 ppm for stainless steel components.
1.6 RESPONSIBILITIES
Mark the test limits on the isometric drawing of latest revision and perform the line
check.
Locate the pressure gauges, test blinds, vent and drains.
Confirm with relevant QC personnel whether NDEs has been completed and accepted.
Complete the relevant documents as required by the test package.