QCP - Buildings
QCP - Buildings
QCP - Buildings
Project Description Main Contractor Contract No. Sub WBS Facility No. QCP Revision
Contract Description Sub-Contractor Contract No. WBS Name SANS 1200 & KCSA Specifications
1.3 Approved Construction and Layout Drawings Latest Updated Drawings and Register H H H H H
1.6 Approved Brick Compressive Strength Test Results SANS 227, SANS 2285, SANS 1215 H V V S V
Controlled Activities
2 Foundation
2.1 Survey and setting out to Points (Performed by Contractor) Setting Out Certificate H W V H V
2.2 Survey and setting out Points (Verification by KCSA) KC-CON-FOR-SURV-REQ & REPORTS H W V H V
2.9 Setting up Gauge Rods / building lines for laying brick layers Visual H W V S V
3 Brickwork
649403639.xlsx Page 1 of 4
Install roof trusses - (welded roof trusses to be inspected and
3.7 KCSA-CIV-CL-01 H V V S V
approved by KCSA prior to installation)
3.8 Paving Building Plan / Drawings / Spec H V V S V
4 Plastering
4.3 Ensure walls are clean and ready to receive plaster. Visual H V V S S
5 Roof Installation
6 Electrical Installation
6.3 Install earth rods and earthing cables Electrical Drawing / KC-CON-EL-CL-02 W V V S V
6.5 Pull all electrical cables and terminate Electrical Drawing / KC-CON-EL-CL-04 W V V S S
6.7 Install electrical plugs & light switches Electrical Drawing / KC-CON-EL-CL-05 W V V S V
7 Additional Work
8 Painting
9 Punch Inspection
10 Hand Over
649403639.xlsx Page 3 of 4
10.4 Review Data Dossier Data Book H R R R R
Approvals
Contractor Supervisor Contractor QC Inspector KCSA Supervisor KCSA Surveyor KCSA QMS Inspector / Manager
Name:
Signed :
Date :
DEFINITION OF INTERVENTION POINTS: A point of inspection in the QCP that requires the presence of the inspection organisation:-
H - where the next stage of the production/construction process cannot proceed beyond this point until an inspection has been performed by the inspection organisation and the required conditions indicated as met/achieved.
W - where production cannot proceed beyond this point if the inspection organisation has not attended, provided due notice of the activity has been given to the inspection organisation in terms of the relevant contract.
S - where surveillance may be performed by the inspection organisation.
R - where a review of the records developed by the supplier to ensure that the relevant activity has been performed satisfactory and that contractual requirements have been met.
V - where a verification by the inspection organisation to ensure that the relevant activity has been performed satisfactory and that contractual requirements have been met.
A - where the organisation needs to execute an operation prior to intervention and inspection.