PVP2008 61708
PVP2008 61708
PVP2008 61708
PVP2008-61708
Selecting the Optimum Bolt Assembly Stress: Influence of Flange Type on Flange Load Limit
Warren Brown
The Equity Engineering Group
Shaker Heights, OH, USA
[email protected]
ABSTRACT conservative. In this paper both the limits and results have been
In previous papers, practical limits on the maximum applied appropriately adjusted to represent the correct material that was
load for standard ASME B16.5 and B16.47 carbon steel, weld neck analyzed. In addition to the maximum stress limit, a gasket may have
pipe flanges were examined. A new code equation for the tangential a maximum flange rotation that it can accept prior to leakage. This
(hoop) stress at the small end of the hub for a weld neck flange was limit must also be assessed to ensure that the specified bolt load will
developed to facilitate calculation of the limits using elastic analysis. not cause excessive flange rotation, as outlined in the previous
The results were verified against elastic-plastic Finite Element papers.
Analysis (FEA). In this paper, the work is extended to include other
In the previous papers by this author on the topic, the concept
flange configurations, including loose ring flanges, slip-on flanges
of maximum allowable bolt load for both standard pipe flanges
and flat plate flanges. This paper is a continuation of the papers
presented during PVP 2006 and PVP 2007 (Brown [1,2]) and it (based on Elastic-Plastic FEA and code calculation) and limitations
extends the scope of the proposed methodology for determining for non-standard flanges (based on code calculation) were examined.
flange stress limits in determining the maximum allowable bolt load The FEA used to confirm the work included all standard ASME
for any given flange size and configuration. B16.5 flanges greater than 2 in. nominal bore and ASME B16.47,
Series A flanges up to 48 in. nominal bore. The goal of this analysis
INTRODUCTION was to determine the point of Gross Plastic Deformation (GPD) of
In the previous papers, the importance of knowing two basic each of the flanges, which is suggested as the point of maximum
values for the joint; minimum acceptable assembly bolt load and, allowable bolt load for flange assembly. GPD is defined as the point
more importantly, maximum acceptable assembly bolt load was where the rotation of the flange ring under applied bolt load becomes
highlighted. The reason that the maximum acceptable bolt stress is non-linear. This signifies that, at that point, the flange is taking on a
more important is that an optimal bolt load for joint assembly should permanent set and will, upon release of load, have residual flange
always be biased towards the maximum acceptable load, as this gives rotation. In addition, the onset of GPD results in a rather rapid
the largest buffer against joint leakage. It could even be argued that increase in flange rotation with applied load and so, therefore, it is
one need not know the minimum acceptable bolt load, because by likely that such rotation will cause joint leakage due to mal-
assembling to the maximum possible bolt load then we have given distribution of gasket stresses. This paper will focus on determining
ourselves the greatest chance of sealing the joint. The maximum the maximum acceptable bolt load for other standard (slip-on and
acceptable assembly bolt load is determined from examining the loose) and non-standard (flat plate) piping flanges based on both
maximum load that can be taken by any one of the three joint flange rotation and GPD limits. Only the assembly bolt load case is
components (bolts, gasket or flange). Unfortunately, the upper limit considered in this work, as this is generally considered sufficient due
for both gasket and flange are not well defined. A selection of to the fact that gasket relaxation will reduce the bolt load during
maximum gasket stress values were presented in a previous paper operation to a point below the flange or bolt material yield at
(Brown [1]), based on both laboratory test and field experience. This temperature (during operation). If gasket relaxation is less than the
original work was expanded on and new code equations and elastic reduction in material yield due to temperature then the specified
stress limits were proposed in a following paper (Brown [2]). In that assembly bolt load will need to be reduced by the ratio of yield at
paper, Elastic-Plastic (E-P) FEA results were presented for SA105 temperature divided by yield at ambient. This adjustment must also
flanges that were actually based on lower strength material. Due to be made if the joint is to be tightened while hot.
this, the subsequently developed code equation limits were overly
The pipe wall thicknesses and material yield properties used 6 78.5 86.0 91.4 78.8 87.7 77.6
8 105.0 89.0 95.3 67.1 83.5 80.8
in the analysis are listed in Brown [2]. The gasket type used in the
10 73.0 92.7 82.1 64.4 91.0 78.8
analysis was a spiral wound gasket in accordance with ASME 12 103.3 88.0 81.6 71.6 80.3 86.2
B16.20. For the weld-neck flanges, the elastic-plastic FEA models 14 84.5 65.9 74.4 76.3 70.3
were run for each case and the flange rotation (defined as the rotation 16 81.6 57.7 73.7 77.1 70.6
occurring at the mid-plane of the flange ring) versus bolt load 18 89.0 68.5 86.2 77.4 75.6
information from the FEA output was analysed to determine the bolt 20 82.4 65.4 69.9 79.1 72.7
load prior to the change in the slope of the load vs. deflection curve 24 69.4 53.0 65.3 79.2 69.7
26 31.6 35.1 52.1 65.0
becoming two times greater than the initial slope. This is a nominal
28 28.0 38.3 51.4 57.8
limit selected by the author that allows a standard determination of 30 33.0 42.0 64.8 67.4
the onset of GPD, although in many cases the accuracy of this 32 25.1 39.5 57.5 66.7
determination for the FEA was only within a 10ksi range, due to the 34 23.2 43.0 67.1 60.6
rather large increments chosen. The large FEA load step increments 36 30.0 37.8 58.6 63.2
were chosen in order to minimize the computer time required to 38 30.6 80.8 90.3 79.9
obtain the results. 40 28.9 77.7 91.9 77.2
42 31.6 84.2 90.8 84.9
44 32.0 98.0 92.6 82.6
The resulting maximum assembly bolt loads from the
46 34.5 105.0 99.6 81.6
elastic-plastic FEA prior to onset of GPD were used to develop 48 32.2 76.0 87.8 90.6
closed-form solutions to determine the maximum permissible Note: the shaded cells represent values that are lower than 50ksi bolt stress.
assembly bolt load limits for individual joint geometries (including
different gaskets, pipe wall thicknesses and flange materials). The Since the closed-form solution is based on standard code
closed-form solutions used the current code (ASME [3]) flange stress equations, it is a relatively simple step to apply these formulae to
equations and also included the development of an equation for alternative flange configurations, using the rules presently defined in
tangential (hoop) stress at the small end of the hub (ST0). The ASME [3]. It should be noted, that presently the code instructs the
development of the new equation followed the original approach used user to analyse optional type flanges (slip-on flanges) as integral
for development of the ASME code equations (Waters [4]), and flanges. This requirement is generally more stringent than allowing
resulted in a new “f” factor that relates tangential stress at the shell to them to be analysed as loose flanges and will result in a more robust
hub junction to longitudinal stress at the ring to hub junction, in the design. In addition, the code instructs the value of g0 to be equal to
same way that the existing “f” factor relates longitudinal stress at the the vessel wall thickness for slip-on type flanges, which is not
hub to shell junction to longitudinal stress at the ring to hub junction. appropriate, as this is the equivalent of specifying a weld-neck
(tapered) hub. In this paper, the code approach and the approach of
In order to determine the maximum permissible load on the using the actual dimension for the small end of the hub is used, which
flange, the value of ST0 was limited to material yield (Sy), since it is a means that for non-tapered hubs g0 equals g1. In order to verify the
(Fig. 15 and Fig. 16). It can be seen that in this case there was 2 0.6 0.9 0.9 0.8 1.0
significant difference between the partially inserted and fully inserted 2.5 1.1 0.9 0.9 1.0 1.0
pipe cases. However, by using the new factors, the stepped solution 3 1.0 0.9 1.0 1.0
4 1.1 0.9 1.1 0.9
predicts the point of GPD conservatively for the fully inserted case, 5 0.9 1.1 1.3 1.0
and therefore is sufficiently close to the partially inserted case that it 6 0.9 1.3 1.3 1.0
would be considered equally applicable. In the case where the wall 8 1.0 1.1 1.3 1.0
thickness gets significantly larger, the effect of partial versus full 10 1.1 1.4 1.3 1.0
12 1.1 1.3 1.3 1.1
insertion could be studied by using the stepped solutions with a 14 1.3 1.6 1.5 1.0
flange ID equal to the pipe ID for the fully inserted case and equal to 16 1.2 1.2 1.4 1.0
the flange ID for the partially inserted case. 18 1.1 1.3 1.1 1.0
20 1.2 1.1 1.0 1.0
24 0.9 0.9 0.9 1.0
The closed-form GPD results for the welded slip-on, SA105
flanges are in general lower than the weldneck flanges (Table 2). It
can be seen that the majority of them are still above the nominal CONCLUSIONS
value of 50ksi (shaded yellow). The associated flange rotation at the Allowing a 45 degree hub in ASME B16.5 does not appear to
calculated GPD bolt load is shown in Table 3, in order that these may be a good idea, as it results in a much weaker flange. Luckily (or by
be used in determining if the maximum assembly bolt load should be design), most flange manufacturers use the full hub height when
Improved joint leakage performance can be expected if the [2] Brown, W., Reeves, D.., 2007, “An Update on Selecting the
bolt assembly stress is set by calculation of the actual gasket stress, Optimum Bolt Assembly Stress For Piping Flanges”, Proceedings of
with an upper limit that avoids damage to the joint components. The the ASME PVP 2007, ASME, San Antonio, Texas, PVP2007-26649
newly introduced calculation of the stepped flange factors, coupled [3] ASME. 2007, ASME VIII, Div 1, Boiler and Pressure Vessel
with limits on the magnitude of the existing code calculated stresses, Code, Appendix 2, American Society of Mechanical Engineers, NY,
have been shown to accurately predict the actual maximum USA
acceptable assembly bolt load for several standard flange
[4] Waters, E.O., Rossheim, D.B., Wesstrom, D.B., Williams, F.S.G.,
configurations. The same methodology and stress limits have been
1949, “Development of General Formulas For Bolted Flanges”,
shown to be applicable to both connected (weld-neck, slip-on and flat Taylor-Forge & Pipe Works, Southfield, Michigan, Reprinted by the
plate) flanges and loose (lap joint) flanges. PVRC in 1979.
Stress (MPa)
set an upper limit on acceptable assembly bolt load for standard 300
SA105, ASME B16.5 slip-on flanges. The only risk with using these 250
values would be if the actual wall thickness was significantly less
200 SA182 F304
than the values presented in Brown [2] or if the gasket dimensions SA105
150
were significantly different from the values used, resulting in a
significantly larger value of hg. Alternatively, for a given piping 100
specification or, based on the minimum wall thickness across all 50
piping specifications on a individual sites, more accurate maximum 0
allowable bolt loads may be calculated using the equations presented 0.00E+00 2.00E-02 4.00E-02 6.00E-02 8.00E-02 1.00E-01
in ASME [3] and this paper and using the stress limits outlined in this Strain
paper. In specifying these values, it is implicit that the load be
Figure 1 – SA105 and SA182-F304 Elastic-Plastic Curve
accurately applied, otherwise flange GPD may occur if the actual
achieved bolt load is significantly above the specified value. An 1
FEA - Full Hub
example of this would be the use of an incorrect nut factor when 0.9
FEA - 45deg. Hub
determining the assembly bolt torque. 0.8 Code Equations - Full Hub
Flange Rotation (degrees)
1.5
0.5
0
0 0.2 0.4 0.6 0.8 1 1.2
Fraction of Bolt Yield (105ksi) Figure 7 – 20in., cl.150 Flat Plate Hoop Stress Results
Figure 3 – 20in., cl.150 45deg. Weldneck Results
NPS 20, cl.150, Slip-On Flange, 4.78mm w.t.
3
2.5
0
0 0.2 0.4 0.6 0.8 1
Fraction of Bolt Yield (105ksi)
Figure 4 – 4in., cl.600 Hoop Stress
Figure 8 – 20in., cl.150, 4.78mm w.t. Slip-On Flange GPD
84ksi Bolt 53ksi Bolt NPS 20, cl.150, Slip-On Flange, 7.62mm w.t.
Stress Stress 3
2.5
Flange Rotation (°)
2 Fully Inserted
Partially Inserted
1.5 Non-Welded
Code - Integral
1.8
Figure 9 – 20in., cl.150, 7.62mm w.t. Slip-On Flange GPD
1.6
Flange Rotation (°)
1.4
Welded (7.62mm wt)
1.2
Welded (4.78mm wt)
1 Not Welded
0.2
0
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5
Figure 13 – Graph of FS
0.1 g2/g0 1
1000
h/(sqrt(B.g 0)
0.005
0.05
100
0.1
0.2
0.3
VS
10 0.35
0.4
0.5
1 0.6
0.7
0.8
0.9
0.1 1
Figure 14 – Graph of VS