Mos T&C Earthing
Mos T&C Earthing
Mos T&C Earthing
Method Statement for Testing and Commissioning for Earthling and Lightning Protection System
(ESE)
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
STATEMENT TITLE
REVIEW STATUS
01
Pa
ge
1
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
Contents List
1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITION
5. RESPONSIBILITIES
6. EQUIPMENTS
7. PROCEDURES
8. ATTACHMENT
Page 2
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
1. PURPOSE
2. SCOPE
This method statement is applicable for the testing & commissioning of earthing
system and lightning protection system to ensure that the work is installed and
conforms to the requirements of contract documents & project specifications for
the project ANANTARA MINA AL ARAB RAS AL KHAIMAH RESORT
3. REFERENCES
Page 3
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
4. DEFINITION
PQP : Project Quality Plan
MS : Method Statement
SK : Store Keeper.
5. RESPONSIBILITIES
Responsibilities for ensuring that the steps in this procedure shall be carried out
are specified at relevant steps in the procedure: LPS Specialist shall supervise
the testing & commissioning of Earthing / LPS and ensure the practice is in line
with accepted standards.
- Approved Specialist
- Project Manager
- Construction manager
- QA/QC Engineer
- Site Engineer
- HSE officer
- SK
Page 4
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
- Project Manager is the overall responsible for the project in terms of work
execution, safety, planning & quality. The Project Manager will maintain the
planning progress and coordination of works with the main contractor.
- The work progress shall be carried out as per planned program and all the
equipment’s required to execute the works shall be available and in good
condition as per project planned.
- Specific attention is paid to all safety measures and quality control in
coordination with Safety Engineer and QA/QC Engineer and in line with
PSP and PQP.
Page 5
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
- The constant coordination with the Safety Engineer to ensure that the
works are carried out in safe working atmosphere.
- The constant coordination with the QA/QC Engineer for any works to be
carried out and initiate for the Inspection for the finished works.
- He will ensure the implementation of any request that might be raised by
the Consultant.
- Efficient daily progress shall be obtained for all the equipment and
manpower.
- He will engage in the work and check the same against the daily report
received from the Foremen.
- The passage of all the revised information to the Foremen and ensure that
it’s being carried out properly.
- The carrying-out of work and the proper distribution of all the available
resources in coordination with the Site Engineer on a daily basis.
- Daily reports of the works are achieved and coordinated for the future
planning with the Site Engineer.
Page 6
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
- The monitoring of all safety measures in compliance with the HSE plan and
as per approved method statement and risk assessment.
- The monitoring of safety measures is adequate to maintain a safe working
environment on the work activity.
- Inspection of all the site activities and ensure safety induction to personnel
and its proper reporting to the Construction Manager and the Project
Manager.
- HSE is responsible to monitor safety compliances as per project health and
safety plans and approved method statement and risk assessment.
- Responsible for overall Store operations in making sure to store the material
delivery to the site and keep it in suitable area that will keep the material in
safe from rusty and damage.
- One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
6. EQUIPMENT
Tool box
Earth Resistance Tester (Fall of Potential Meter)
Continuity Tester with precision 0.000 Ohm
Ladder / Scaffolding
Measuring Tape
Earth Meggering Instrument.
Page 7
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
7. PROCEDURES
7.2 Installation
Page 8
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
Mark the location of the copper tape, ESE terminals, down conductor and
test points on the floor/slab/walls/roof/column structure as per approved
layout drawing.
Fix the proprietary clips and clamps conforming to BSEN62561 – Part 2 to firmly
fix the air termination network of copper tapes on the roof as per the
approved LPS Drawings
Fix bare copper tape / PVC Cover Copper Tape to the clamps with the help
of countersunk
The network of approved size bare tape or covered tapes shall be installed
across the roof area and interconnected with the down conductors placed
at appropriate intervals as per the LPS drawings
Install the DC outside the building (for Exposed DC) or through the column
clamped to rebar.
No of DCs should be as per the LPS drawings given as in line with NFC 17 102
standards.
Install the Ring conductor at respective floors and bond the same with the
DC and to the Al Cladding as detailed in the LPS drawings
Install the Test points at all DCs 600 mm to 1 Mtr above GF / BF level. Suitable
test box should be provided test links
Install Strike Counter in the DC as per the LPS drawings given. Each ESE
terminal should have one Strike counter. Install a suitable box for the same.
ESE terminal is the component of the system that is intended to intercept the
lightning strokes
Page 9
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
The position of the E.S.E. air terminal, including height of above structure shall
be determined in accordance with the level of protection required & as per
the LPS drawings furnished.
Install the air terminal base on roof surface with steel bolts install the air rod
shaft on the terminal base firmly
Cu tape connections to the Air terminal should be wrapped with Denso tape
to prevent corrosion
Make sure that the down Conductor resistance from Roof to GF / BF should
be less than 0.2 Ohm
Material shall be stored in a covered/ dry space at all the time to avoid
corrosion.
Earth Pits used as lightning protection system electrode & its locations are
indicated in the GF – LPS Drawings.
Down conductor Test link locations are shown in the approved LPS typical
floor Layouts. Remove the face plate cover; clean the connections to
eliminate the dust / contaminations from the test link.
Page 10
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
Identify the Equipment earth pits and its Earth Bar Location. Labeling should
be done at pits and at respective earth bars for easy identification.
Remove the Earth pit cover, clean inside the pits and its connections.
Check the installation of Strike counters, ESE Terminal & its guy wires.
Make sure all the installation is tight and the guy wires without any sag.
1. Lightning ESE Terminal (Air terminal) of 5 Mtr height as per the given
coverage radius (NFC 17 102) should be installed to protect the structure
against lightning strikes.
2. Detailed ESE terminal final with accessories is shown in the Fig ..(guy kit
assembly drawing)
3. Place the base of the ESE terminal on flat roof as per the approved LPS
drawings. Fix the base plate to the roof with nuts and bolts.
4. Fix the ESE device on top of the steel terminal, tight the screws with the
given allen keys.
Page 11
1 2 3 4 5 6 7 8
Item N.o. Part Name Part type Part code Qty Unit
3 Screw and fixing Kit for MAT3503 and for flat conductor KFP0035 2CTH050027R0000 1 pcs
A A
4 Screw and fixing kit for stainless steel Extension mast Ø 42 KFR3542 2CTH050026R0000 1 pcs
5 Guying kit: 3-direction clamp, 3x ring fasteners, 3x anchoring clips FHF0001 2CTH050022R0000 1 pcs
17 Guying kit: 3x anchoring clips, 3x stay tighteners, 3x ring fasteners FHF0001 2CTH050022R0000 1 pcs
Notice
Manual snap tool Ø 20 (2CTH0BMA0020) for use with Cu bond earth rod assembly / hammering
Flat conductor delivered by 50m coil. Coil should be cutted for suitable lenghts.
One guying kit includes 6 anchoring clips, 3 stay tighteners, 3 ring fasteners, 1
D D
3‐directional clamp and 1 base, 2CTHCHPP4523
Foundation details from
drawing 17-10979-PV-CE-LA-FND
E E
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 0 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
o) Connect the two given rods with nuts & bolts. Install the guy wires
and anchor to the roof floor as shown in drawings.
Page 13
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
cable arm, over the full length of the wire as shown in Figure 3.
Finish setting up the end of the wire with a rapping.
iv) After the assembly, the assembly must have the appearance
shown in Figure 4.
Note: There is no need to worry if during the assembly part of the abrasive
paste that is deposited inside the wire of the clamp disintegrates: During
manufacturing, this paste was deposited sufficient and allows several
successive assembly and disassembly.
Page 14.
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
6. PREPARATION OF GUY WIRES – Unroll the fiberglass and cut the lengths
required for each guy wire according to the guying radius.
Page 15
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
- Ensure the proper installation as per the standards and drawings. Make
sure the pits are clean, dry and without any contamination. Ensure the top
seal is fully tighten and no water ingression. Remove the connections from
the rod & make connections to the rod needs to be tested and the
auxiliary connections as per the below diagram.
7.3.1 Measurement of Earth Electrode Resistance (For Equipment & For LPS):
Page 16
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE)
- Make sure the resistance readings are less than 1 Ohm as per authority
standards.
- Minimum permissible earth resistance value for lightning protection is to
<10 ohms.
- Submit the readings for approval / keep the same for future
reference.
Page 17
PROJECT : ANANTARA MINA AL ARAB RAS AL
KHAIMAH RESORT
MEP CONTRACTOR : M/S. DELTA ELECTRICAL & Rev. No: 00 Date: 05-03-23
SANITARY CONTRACTING AND SAFETY EQUIPMENTS
LLC
Description: Method Statement for Testing and Commissioning for Earthling and Lightning Protection
System (ESE))
8. Appendix
Test Sheets
Page 18
TEST REPORT – PILE/PIT RESISTANCE USING FALL OF POTENTIAL METHOD
PROJECT NAME :
CLIENT NAME :
CONSULTANT :
MAIN CONTRACTOR :
MEP CONTRACTOR :
CALIBRATION DATE :
TEST RESULT
10
11
COMPANY :
SIGNATURE :