02 Determination of Quantities
02 Determination of Quantities
of Work
SR
ESTIMATION AND COSTING
Determination of Quantities of different Items of
Work in Construction
AN
KIRAN S R
Lecturer in Civil Engineering
Government Polytechnic College
KIR
DEPARTMENT OF TECHNICAL EDUCATION
Government of Kerala
Contents
SR
1 Introduction
2 IS 1200
AN
3 Items & its Units
Introduction
Why do we determine Quantities?
SR
AN
KIR
Introduction
Why do we determine Quantities?
SR
We know that, Cost of an item of work is determined from:
Quantity x Rate = Cost
Quantity:
the amount or number of a material estimated by spatial
measurement.
expressed in Length, Area or Volume, determined by standard
AN
mensuration procedures/formula.
Rate:
Cost of unit quantity of an item.
KIR
Referenced from Delhi Schedule of Rates (DSR) or Local Market
Rates (LMR).
Therefore, it is mandatory to determine quantites, for estimation of
cost.
For preparing Detailed Estimate, it is a necessity for the Estimator
to determine the quantities of each item of work involved in the
project.
KIRAN S R, Lecturer, Dept. of Civil Engineering 3/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
Introduction
SR
Basic Steps involved in Quantification of Items:
1 All items relevant to the work shall be identified from following
sources:
building plans, detailed architectural & structural drawings,
preliminary lay-out drawings of the various services,
AN
detailed specifications etc.
2 Further, each item of the project should be broken down into its
parts and its dimensions (Length, Breadth, Height, Diameter etc.)
KIR
measured.
3 Quantities (in terms of running metres, area or volume) are then
determined using standard formulas of mensuration, in tabular
form, as shown below.
Introduction
SR
AN
KIR
In booking dimensions, the order shall be consistent and in the
sequence of Length (L), Width (B) and Height/depth/thickness (H).
IS 1200
SR
IS 1200 (Indian Standard Methods of Measurement of Building and
Civil Engineering Works) was published by Bureau of Indian
Standards, with the intend to bring uniformity in the methods of
AN
measurement of Civil Engineering works and to standardize the
same.
Therefore, the methods of measurement and determination of
quantities shall strictly adhere to IS 1200.
KIR
IS 1200 has 28 parts – one for each item of work. A list of all parts
is given herewith.
Parts of IS 1200
Part 1: Earthwork
SR
Part 2: Concrete works
Part 3: Brickwork
Part 4: stone masonry
Part 5: Form work
Part 6: Refractory work
AN
Part 7: Hardware
Part 8: Steel work and iron work
Part 9: Roof covering (including cladding)
KIR
Part 10: Ceiling and linings
Part 11: Paving, floor finishes dado and skirting
Part 12: Plastering and Pointing
Part 13: Whitewashing, colour washing, distempering and painting
of building surfaces
Part 14: Glazing
KIRAN S R, Lecturer, Dept. of Civil Engineering 7/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
Parts of IS 1200
SR
Part 15: painting, polishing, varnishing etc
Part 16: laying of water and sewer lines including appurtenant items
Part 18: demolition and dismantling
Part 19: Water Supply, Plumbing and Drains
Part 20: laying of gas and oil pipelines
AN
Part 21: wood-work and joinery
Part 22: materials
Part 23: piling
KIR
Part 24: well foundations
Part 25: tunneling
Part 26: Acid resistant lining
Part 27: Earthwork done by mechanical appliances
Part 28: Sound insulation works
SR
structure). Study the figure carefully. Identify all relevant items of
work and units of measurement.
AN
KIR
SR
AN
KIR
SR
1 Earthwork in excavation (m3 )
AN
KIR
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN
KIR
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN
KIR
3 RR masonry in CM 1:6 in foundation and
basement (m3 )
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN
KIR
3 RR masonry in CM 1:6 in foundation and
basement (m3 )
4 Damp-proof Course (m2 )
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN
KIR
3 RR masonry in CM 1:6 in foundation and
basement (m3 )
4 Damp-proof Course (m2 )
5 Brickmasonry in CM 1:6 (m3 )
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN
KIR
3 RR masonry in CM 1:6 in foundation and
basement (m3 )
4 Damp-proof Course (m2 )
5 Brickmasonry in CM 1:6 (m3 )
6 Centering & Shuttering for RCC works
(m2 )
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN
KIR
3 RR masonry in CM 1:6 in foundation and
basement (m3 )
4 Damp-proof Course (m2 )
5 Brickmasonry in CM 1:6 (m3 )
6 Centering & Shuttering for RCC works
(m2 )
7 TMT bars (Fe500 grade) (kg)
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN
KIR
3 RR masonry in CM 1:6 in foundation and
basement (m3 )
4 Damp-proof Course (m2 )
5 Brickmasonry in CM 1:6 (m3 )
6 Centering & Shuttering for RCC works
(m2 )
7 TMT bars (Fe500 grade) (kg)
8 RCC 1:1.5:3 (m3 )
KIRAN S R, Lecturer, Dept. of Civil Engineering 10/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN 9 Cement Plaster 12mm thick on walls (m2 )
KIR
3 RR masonry in CM 1:6 in foundation and
basement (m3 )
4 Damp-proof Course (m2 )
5 Brickmasonry in CM 1:6 (m3 )
6 Centering & Shuttering for RCC works
(m2 )
7 TMT bars (Fe500 grade) (kg)
8 RCC 1:1.5:3 (m3 )
KIRAN S R, Lecturer, Dept. of Civil Engineering 10/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN 9
10
Cement Plaster 12mm thick on walls (m2 )
Cement Plaster 6mm thick on ceiling (m2 )
KIR
3 RR masonry in CM 1:6 in foundation and
basement (m3 )
4 Damp-proof Course (m2 )
5 Brickmasonry in CM 1:6 (m3 )
6 Centering & Shuttering for RCC works
(m2 )
7 TMT bars (Fe500 grade) (kg)
8 RCC 1:1.5:3 (m3 )
KIRAN S R, Lecturer, Dept. of Civil Engineering 10/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN 9
10
Cement Plaster 12mm thick on walls (m2 )
Cement Plaster 6mm thick on ceiling (m2 )
KIR
3 RR masonry in CM 1:6 in foundation and 11 PCC 1:2:4 on floors (m3 )
basement (m3 )
4 Damp-proof Course (m2 )
5 Brickmasonry in CM 1:6 (m3 )
6 Centering & Shuttering for RCC works
(m2 )
7 TMT bars (Fe500 grade) (kg)
8 RCC 1:1.5:3 (m3 )
KIRAN S R, Lecturer, Dept. of Civil Engineering 10/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN 9
10
Cement Plaster 12mm thick on walls (m2 )
Cement Plaster 6mm thick on ceiling (m2 )
KIR
3 RR masonry in CM 1:6 in foundation and 11 PCC 1:2:4 on floors (m3 )
basement (m3 ) 12 Flooring (tiles etc.) (m2 )
4 Damp-proof Course (m2 )
5 Brickmasonry in CM 1:6 (m3 )
6 Centering & Shuttering for RCC works
(m2 )
7 TMT bars (Fe500 grade) (kg)
8 RCC 1:1.5:3 (m3 )
KIRAN S R, Lecturer, Dept. of Civil Engineering 10/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN 9
10
Cement Plaster 12mm thick on walls (m2 )
Cement Plaster 6mm thick on ceiling (m2 )
KIR
3 RR masonry in CM 1:6 in foundation and 11 PCC 1:2:4 on floors (m3 )
basement (m3 ) 12 Flooring (tiles etc.) (m2 )
4 Damp-proof Course (m2 ) 13 Woodwork in frames of Doors, Windows,
5 Brickmasonry in CM 1:6 (m3 ) etc. (m3 )
6 Centering & Shuttering for RCC works
(m2 )
7 TMT bars (Fe500 grade) (kg)
8 RCC 1:1.5:3 (m3 )
KIRAN S R, Lecturer, Dept. of Civil Engineering 10/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN 9
10
Cement Plaster 12mm thick on walls (m2 )
Cement Plaster 6mm thick on ceiling (m2 )
KIR
3 RR masonry in CM 1:6 in foundation and 11 PCC 1:2:4 on floors (m3 )
basement (m3 ) 12 Flooring (tiles etc.) (m2 )
4 Damp-proof Course (m2 ) 13 Woodwork in frames of Doors, Windows,
5 Brickmasonry in CM 1:6 (m3 ) etc. (m3 )
6 Centering & Shuttering for RCC works 14 White washing / Cement Primer /
(m2 ) Emulsion paints on walls (m2 )
7 TMT bars (Fe500 grade) (kg)
8 RCC 1:1.5:3 (m3 )
KIRAN S R, Lecturer, Dept. of Civil Engineering 10/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
1
2
Earthwork in excavation (m3 )
PCC 1:4:8 in foundation (m3 ) AN 9
10
Cement Plaster 12mm thick on walls (m2 )
Cement Plaster 6mm thick on ceiling (m2 )
KIR
3 RR masonry in CM 1:6 in foundation and 11 PCC 1:2:4 on floors (m3 )
basement (m3 ) 12 Flooring (tiles etc.) (m2 )
4 Damp-proof Course (m2 ) 13 Woodwork in frames of Doors, Windows,
5 Brickmasonry in CM 1:6 (m3 ) etc. (m3 )
6 Centering & Shuttering for RCC works 14 White washing / Cement Primer /
(m2 ) Emulsion paints on walls (m2 )
7 TMT bars (Fe500 grade) (kg) 15Priming coat / Synthetic Enamel Paint on
3 woodwork (m2 )
8 RCC 1:1.5:3 (m ) Etc.....
KIRAN S R, Lecturer, Dept. of Civil Engineering 10/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
Note that the following items of AN 1 Earthwork in excavation
KIR
2 PCC 1:4:8 in foundation
work are distributed along the
Centreline of walls of the 3 RR masonry in CM 1:6 in
building. foundation and basement.
This is because, the building is a 4 Damp-proof Course
load bearing structure. 5 Brickmasonry in CM 1:6
6 RCC 1:1.5:3 in Lintel band
KIRAN S R, Lecturer, Dept. of Civil Engineering 11/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
AN
KIR
Such items of work, which are distributed along the Centreline of walls
of a Load-bearing Structure, can be quantified by any on the following
methods:
1 Long wall–Short wall method
2 Centreline method
Definition:
SR
This method identifies the walls of the building as Long Walls & Short
Walls, such that:
Long Walls refer to all walls of that building in a single direction,
and are predominantly longer;
Short Walls refer to all other walls of that building, which are
AN
perpendicular to the direction of Long Walls.
KIR
SR
Definition (Contd..):
Here the term ”wall” refers to the legs/sides of any the following
items and not just by its literal meaning.
1 Earthwork in excavation
AN
2 PCC 1:4:8 in foundation
3 RR masonry in CM 1:6 in foundation and basement.
4 Damp-proof Course
5 Brickmasonry in CM 1:6
KIR
6 RCC 1:1.5:3 in Lintel band
This is because, all these items have same shape in plan, but
differ only in their width (see next slide).
SR
AN
KIR
SR
Definition (Contd..):
AN
Also note that, all these items have the same Centreline length,
irrespective of their difference in width (see next slide).
KIR
SR
AN
KIR
Since the length of Centrelines of all these items are same, it shall
SR
suffice to compute its magnitude from the Plan of BRICKWALL
as shown here.
AN
KIR
SR
Definition (Contd..):
AN
Long Walls are expressed in terms of its out-to-out length;
Short Walls are expressed in terms of its in-to-in length.
(See next slide)
KIR
SR
AN
KIR
Therefore, the Out-to-out Length of Long walls and the In-to-in Length
of short walls for each of the item may be computed as follows:
SR
1 Earthwork in excavation and PCC 1:4:8 in foundation:
Longwalls:
ABC: 7.00 + 0.80 = 7.80m
DEF: 7.00 + 0.80 = 7.80m
AN
GH: 3.10 + 0.80 = 3.90m
Total = 19.50m
Shortwalls:
AD: 4.10 - 0.80 = 3.30m
KIR
BE: 4.10 - 0.80 = 3.30m
CF: 4.10 - 0.80 = 3.30m
DG: 2.10 - 0.80 = 1.30m
Centreline Length of:
EH: 2.10 - 0.80 = 1.30m ABC = DEF = 7.00m
Total = 12.50m GH = 3.10m
AD = BE = CF = 4.10m
Total Length = 32.00m DG = EH = 2.10m
KIRAN S R, Lecturer, Dept. of Civil Engineering 21/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
Longwalls:
ABC: 7.00 + 0.60 = 7.60m
DEF: 7.00 + 0.60 = 7.60m
GH: 3.10 + 0.60 = 3.70m
AN
Total = 18.90m
Shortwalls:
AD: 4.10 - 0.60 = 3.50m
BE: 4.10 - 0.60 = 3.50m
KIR
CF: 4.10 - 0.60 = 3.50m
DG: 2.10 - 0.60 = 1.50m Centreline Length of:
ABC = DEF = 7.00m
EH: 2.10 - 0.60 = 1.50m GH = 3.10m
Total = 13.50m AD = BE = CF = 4.10m
DG = EH = 2.10m
Total Length = 32.40m
KIRAN S R, Lecturer, Dept. of Civil Engineering 22/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
Longwalls:
ABC: 7.00 + 0.45 = 7.45m
DEF: 7.00 + 0.45 = 7.45m
GH: 3.10 + 0.45 = 3.55m
AN
Total = 18.45m
Shortwalls:
AD: 4.10 - 0.45 = 3.65m
BE: 4.10 - 0.45 = 3.65m
KIR
CF: 4.10 - 0.45 = 3.65m
DG: 2.10 - 0.45 = 1.65m Centreline Length of:
ABC = DEF = 7.00m
EH: 2.10 - 0.45 = 1.65m GH = 3.10m
AD = BE = CF = 4.10m
Total = 14.25m DG = EH = 2.10m
Total Length = 32.70m
KIRAN S R, Lecturer, Dept. of Civil Engineering 23/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
Longwalls:
ABC: 7.00 + 0.30 = 7.30m
DEF: 7.00 + 0.30 = 7.30m
GH: 3.10 + 0.30 = 3.40m
AN
Total = 18.00m
Shortwalls:
AD: 4.10 - 0.30 = 3.80m
BE: 4.10 - 0.30 = 3.80m
KIR
CF: 4.10 - 0.30 = 3.80m
DG: 2.10 - 0.30 = 1.80m Centreline Length of:
ABC = DEF = 7.00m
EH: 2.10 - 0.30 = 1.80m GH = 3.10m
AD = BE = CF = 4.10m
Total = 15.00m DG = EH = 2.10m
Total Length = 33.00m
KIRAN S R, Lecturer, Dept. of Civil Engineering 24/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
Sl. Details of Item No. L B H Quantity
No. (m) (m) (m)
1 Earthwork in 1 32.00 0.80 0.80 20.48m3
excavation
AN
2 PCC 1:4:8 in 1 32.00 0.80 0.20 5.12m3
foundation
3 RR masonry in
CM 1:6 in
KIR
(a) foundation 1 32.40 0.60 0.60 11.66m3
(b) basement 1 32.70 0.45 0.45 6.62m3
Total 18.28m3
4 D.P.C 1 32.70 1.35 44.15m2
B=0.45+0.45+0.45=1.35m
SR
No. (m) (m) (m)
5 Brickmasonry 1 33.00 0.30 2.85 28.22m3
in CM 1:6
H=2.00+0.85=2.85m
Deductions:
AN
D 1 1.00 0.30 2.00 -0.60m3
D1 2 0.80 0.30 2.00 -0.96m3
W1 4 1.00 0.30 1.50 -1.80m3
W2 2 1.50 0.30 1.50 -1.35m3
KIR
Total 23.51m3
6 RCC 1:1.5:3 1 33.00 0.30 0.15 1.49m3
in Lintel band
Note: The Item No. 5 referred to as Brickmasonry in superstructure has few sub-items with
negative quantities, to account for wall openings (such as Doors, Windows, Ventilators, etc.) and hence,
whose volumes are duly deducted from the gross volume (computed without considering the effect of wall openings)
of Brickwork.
KIRAN S R, Lecturer, Dept. of Civil Engineering 26/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
Centreline Method
SR
Definition:
This method involves determination of Centreline length of all
walls of a building.
As in the previous method, this method also bases itself to the fact
AN
that the Centreline length of all the following items remain the
same.
1 Earthwork in excavation
2 PCC 1:4:8 in foundation
KIR
3 RR masonry in CM 1:6 in foundation and basement.
4 Damp-proof Course
5 Brickmasonry in CM 1:6
6 RCC 1:1.5:3 in Lintel band
Centreline Method
Procedure:
SR
1 Here, the walls of the building are identified as Outer Walls and
Inner Walls.
AN
KIR
Centreline Method
Procedure:
SR
3 If CLouter and CLinner are known, then Net Length of item is
computed as follows:
Case Type of Building Net Length of the Item
1 Single Roomed Building CLouter +CLinner
(with only 2-wall intersections)
W idth of Item
2 Building with 3-wall CLouter +CLinner – (No. of T-junctions x 2 )
intersections (T-junctions)
AN
W idth of Item
3 Building with 4-wall CLouter +CLinner – (No. of T-junctions x 2 )
intersections (cross-junctions)
in addition to T-junctions – (No. of cross-junctions x Width of Item)
KIR
Centreline Method
SR
Procedure:
Therefore, Centreline Method can be easily used to determine the Net
Length (L) of any of the following items.
Earthwork in excavation
AN
PCC 1:4:8 in foundation
RR masonry in CM 1:6 in foundation and basement.
Damp-proof Course
KIR
Brickmasonry in CM 1:6
RCC 1:1.5:3 in Lintel band
Centreline Method
Centreline method can be used to determine quantities of such
items as follows:
SR
AN
KIR
Centreline Method
SR
No. of T-junctions in plan = 2
No. of cross-junctions in plan = 1 AN
KIR
Net length of:
Earthwork in excavation
L= 26.40 + 7.20 - (2 x 0.80
2
) - (1 x 0.80) = 32.00m
PCC 1:4:8 in foundation
L= 26.40 + 7.20 - (2 x 0.80
2
) - (1 x 0.80) = 32.00m
RR masonry in CM 1:6 in foundation
L= 26.40 + 7.20 - (2 x 0.60
2
) - (1 x 0.60) = 32.40m
KIRAN S R, Lecturer, Dept. of Civil Engineering 32/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
Centreline Method
SR
Net length of:
RR masonry in CM 1:6 in basement AN
KIR
L= 26.40 + 7.20 - (2 x 0.45
2
) - (1 x 0.45) = 32.70m
Damp-proof Course
L= 26.40 + 7.20 - (2 x 0.45
2
) - (1 x 0.45) = 32.70m
Brickmasonry in CM 1:6
L= 26.40 + 7.20 - (2 x 0.30
2
) - (1 x 0.30) = 33.00m
RCC 1:1.5:3 in Lintel band
L= 26.40 + 7.20 - (2 x 0.30
2
) - (1 x 0.30) = 33.00m
KIRAN S R, Lecturer, Dept. of Civil Engineering 33/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
Centreline Method
SR
Sl. Details of Item No. L B H Quantity
No. (m) (m) (m)
1 Earthwork in 1 32.00 0.80 0.80 20.48m3
excavation
AN
2 PCC 1:4:8 in 1 32.00 0.80 0.20 5.12m3
foundation
3 RR masonry in
CM 1:6 in
KIR
(a) foundation 1 32.40 0.60 0.60 11.66m3
(b) basement 1 32.70 0.45 0.45 6.62m3
Total 18.28m3
4 D.P.C 1 32.70 1.35 44.15m2
B=0.45+0.45+0.45=1.35m
Centreline Method
SR
Sl. Details of Item No. L B H Quantity
No. (m) (m) (m)
5 Brickmasonry 1 33.00 0.30 2.85 28.22m3
in CM 1:6
H=2.00+0.85=2.85m
Deductions:
AN
D 1 1.00 0.30 2.00 -0.60m3
D1 2 0.80 0.30 2.00 -0.96m3
W1 4 1.00 0.30 1.50 -1.80m3
W2 2 1.50 0.30 1.50 -1.35m3
KIR
Total 23.51m3
6 RCC 1:1.5:3 1 33.00 0.30 0.15 1.49m3
in Lintel band
SR
Quantity: Generally, measured in Volume (m3 )
Measurement:
Each dimension shall be measured to the nearest 0.01m.
Volumes shall be worked out to the nearest 0.01m3 .
AN
KIR
For the above cases, Volume is determined by:
Volume = Length x Width x Depth
where, for wall foundation, the Length of earthwork in excavation is
determined by Longwall–Shortwall/ Centreline Method.
KIRAN S R, Lecturer, Dept. of Civil Engineering 36/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
Concrete Work:
SR
2
AN
Dimensions shall be measured to nearest 0.01m, except for the
thickness of slab which shall be measured to nearest 0.005 m.
Volumes shall be worked out to the nearest 0.01m3 .
Exemptions: No deduction shall be made for the following cases:
KIR
for openings ≤0.1m2 .
for the volume occupied by the steel reinforcements.
for volume occupied by pipes, conduits, etc of cross-sectional area
≤100cm2 for PCC and ≤25cm2 for RCC.
for volume occupied by ends of disssimilar materials (eg. steel
beams, posts, etc) of cross-sectional area ≤500cm2 .
SR
AN
KIR
SR
3
AN
surfaces in contact with concrete.
Measurement:
Dimensions shall be measured to nearest 0.01m.
Areas shall be worked out to the nearest 0.01m2 .
KIR
Exemptions:
If there are any openings in formwork, no deductions shall be made
for openings ≤0.4m2 .
In grid beam system, where Secondary beams intersect Main
beams, no deduction shall be made from the formwork of the Main
beam, where secondary beams intersect it.
SR
AN
KIR
SR
4 Stone Masonry:
Quantity: Generally, measured in Volume (m3 )
Measurement:
AN
Dimensions shall be measured to nearest 0.01m.
Volumes shall be worked out to the nearest 0.01m3 .
Exemptions: No deduction shall be made for the following cases:
for openings ≤0.1m2 .
KIR
for volume occupied by ends of disssimilar materials (eg. steel
beams, posts, etc) of cross-sectional area ≤0.1m2 .
Cement concrete blocks for holdfasts, holding-down bolts etc.
SR
Bricks are of following types.
AN
Dimensions shall be measured to nearest 0.01m.
Volumes shall be worked out to the nearest 0.01m3 .
Walls of thickness ≤ half brick shall each be measured separately in
square metres (m2 ) stating thickness.
KIR
Half brick thickness = 100mm (for modular bricks) ; 115 mm (for
non-modular bricks).
Walls of thickness > half brick, as usual, are measured in m3 .
Exemptions: No deduction shall be made for the following cases:
for openings ≤0.1m2 .
for volume occupied by ends of disssimilar materials (eg. steel
beams, posts, etc) of cross-sectional area ≤0.1m2 .
Cement concrete blocks for holdfasts,
KIRAN S R, Lecturer, Dept. of Civil Engineering 42/89
holding-down bolts etc.
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
for Concrete Reinforcement)
To quantify Reinforcing steel, Bar Bending Schedule shall be
prepared.
It is a tabular representation showing details of reinforcement bars
used for a given RCC work.
AN
It is prepared after the design of an RCC structural element.
It helps to estimate the quantity of reinforcing steel required for
construction.
Further, it enables one to bend Bars in accordance with the
appropriate dimensions shown in the schedule.
KIR
SR
Quantity: Generally, measured in Mass (kg)
Measurement:
Reinforcement (including bends, hooks and laps) shall be measured
in Length, measured to nearest 0.01m, separately for different
diametres.
Then, their weight (in kg) is calculated on the basis of standard unit
AN
weight, given below (IS 1786).
KIR
SR
Bends & Hooks in bars: Generally, Bends and Hooks in bars are
designated by Diameter of bar (d), Internal Radius (R), Hook
allowance (H) and Bend allowance (B).
AN
KIR
Properties For MS bars For HYSD bars
d≤25mm d>25mm d≤25mm d>25mm
Internal Radius (R) 2d 3d 4d 6d
Hook Allowance (H) 9d 11d 13d 17d
Bend Allowance (B) 5d 5.5d 6d 7d
Minimum value of H and B shall be 75mm.
1
H and B values determined as above, shall be rounded off to the nearest 5mm.
2
KIRAN S R, Lecturer, Dept. of Civil Engineering 45/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
6 Steel Reinforcement:
SR
Lap Splicing of Bars:
The standard length of
bars available from mills
is generally 12 m.
Due to non-availability
AN
of longer bars, splicing
of bars is required.
According to IS 456, Lap
splices may be used for
KIR
bar dia ϕ ≤ 36 mm.
Lap length should at
least be equal to the
development length
(Ld ).
From table,
Lap Length ≈ 50d
SR
bars for different cases.
AN
KIR
SR
7 Plastering:
Quantity: Generally measured in Area (m2 )
Measurement:
Length and breadth shall be measured correct to 0.01m.
AN
Area shall be calculated correct to 0.01m2 .
Plastering on roofs, ceilings and walls shall be measured separately.
Wall plaster is computed as:
Quantity = Length of Wall surface x Height of Wall surface.
KIR
Length is measured between the walls or partitions (the dimensions
before the plaster shall be taken).
Height is measured between top of floor surface/skirting to the
ceiling.
SR
7 Plastering:
Deductions in measurement for Openings:
For openings of area ≤0.5m2 :
(i) No deductions shall be made.
(ii) No additions shall be made for jambs/soffit/sill of that opening.
AN
KIR
Plastering:
SR
7
AN
KIR
SR
Deductions in measurement for Openings:
For openings of area >0.5m2 and ≤3m2 :
Subcase 2: If two faces of wall are plastered with different types of
plaster,
(i) deduction shall be made only from the plaster on that side of wall
on which width of reveal is less than that on the other side,
AN
(ii) no deduction shall be made on the other side with greater width
of reveal.
(iii) If widths of reveals on both faces of wall are equal, deduction of
50 % of area of opening shall be made on each face of wall.
KIR
(iv) No additions shall be made for jambs/soffit/sill of that opening.
SR
Deductions in measurement for Openings:
For openings of area >0.5m2 and ≤3m2 :
Subcase 3: If only one face is plastered and the other face is not,
(i) deduction shall be made from plaster, if width of reveal on
plastered side is less than that on unplastered side
(ii) if widths of reveal on both sides are equal or width of reveal on
AN
plastered side is more, no deduction shall be made.
(iii) No additions shall be made for jambs/soffit/sill of that opening.
KIR
7 Plastering:
SR
Deductions in measurement for Openings:
For openings of area >3m2 :
(i) deduction shall be made for opening on each face
(ii) Addition of area of jambs, soffits and sills shall be made. Note
that, deduction shall not be made for the area of jambs/soffit/sill in
AN
contact with the frames of doors, windows etc.
KIR
Painting:
SR
8
AN
Painting, except the priming coat, shall generally be taken in hand
after practically finishing all other building work.
The primer for wood work, iron work or plastered surface shall be as
specified below (also measured in Area (m2 )).
KIR
SR
8 Painting:
Deductions in measurement for Wall Openings:
For openings of area ≤0.5m2 :
(i) No deductions shall be made.
(ii) No additions shall be made for jambs/soffit/sill of that opening.
AN
KIR
Painting:
SR
8
AN
KIR
SR
Deductions in measurement for Wall Openings:
For openings of area >0.5m2 and ≤3m2 :
Subcase 2: If two faces of wall are provided with different types of
finish,
(i) deduction shall be made only from the finish on that side of wall
on which width of reveal is less than that on the other side,
AN
(ii) no deduction shall be made on the other side with greater width
of reveal.
(iii) If widths of reveals on both faces of wall are equal, deduction of
50 % of area of opening shall be made on each face of wall.
KIR
(iv) No additions shall be made for jambs/soffit/sill of that opening.
SR
Deductions in measurement for Wall Openings:
For openings of area >0.5m2 and ≤3m2 :
Subcase 3: If only one face is treated and the other face is not,
(i) deduction shall be made from finish, if width of reveal on treated
side is less than that on untreated side
(ii) if widths of reveal on both sides are equal or width of reveal on
AN
treated side is more, no deduction shall be made.
(iii) No additions shall be made for jambs/soffit/sill of that opening.
KIR
8 Painting:
SR
Deductions in measurement for Wall Openings:
For openings of area >3m2 :
(i) deduction shall be made for opening on each face
(ii) Addition of area of jambs, soffits and sills shall be made. Note
that, deduction shall not be made for the area of jambs/soffit/sill in
AN
contact with the frames of doors, windows etc.
KIR
SR
In measuring areas of uneven surfaces of painting, varnishing, etc.
of woodwork, steel work etc., the following coefficients shall be
used to obtain the actual area payable. The coefficients shall be
applied to the areas measured flat and not girthed. (Contd...)
AN
KIR
8 Painting:
SR
In measuring areas of uneven surfaces of painting, varnishing, etc.
of woodwork, steel work etc., the following coefficients shall be
used to obtain the actual area payable. The coefficients shall be
applied to the areas measured flat and not girthed.(Contd...)
AN
KIR
8 Painting:
SR
In measuring areas of uneven surfaces of painting, varnishing, etc.
of woodwork, steel work etc., the following coefficients shall be
used to obtain the actual area payable. The coefficients shall be
applied to the areas measured flat and not girthed.
AN
KIR
SR
9 Woodwork:
(a)In Frames of Doors, Window & Ventilators
Quantity: Generally, measured in Volume (m3 )
Measurement:
AN
Length shall be measured to nearest 0.01m. Width & thickness shall
be measured to nearest 0.001m.
Volumes shall be worked out to the nearest 0.001m3 .
Wooden members of uniform rectangular cross-section shall be
KIR
measured for finished dimension without any allowance for the
wastage.
For such members having mouldings, roundings, rebates, varying
sections, etc., finished dimensions shall be taken as the sides of the
smallest rectangle from which such a section can be cut.
Woodwork:
SR
9
AN
Dimensions shall be measured to nearest 0.01m.
Area shall be worked out to the nearest 0.01m2 .
Framework:
Overall length and width of the framework of the shutters shall be
KIR
measured.
No deduction shall be made to account the effect of panel openings.
Panelling:
Length and width of opening for panels/ glazed panels is measured.
The portions of the panel/ glazed panel inside the grooves or rebates
shall not be measured.
SR
AN
KIR
SR
AN
KIR
SR
10 Land Levelling (Part of Earthwork):
Land leveling is the process of modifying the surface relief by
smoothening it.
AN
It is the process of flattening or modifying existing (natural) slopes
or undulations and thereby creating a level surface.
Normally land leveling requires excavation and movement of earth
from higher elevations to lower elevations.
KIR
Land grading is modifying the slope of land to a planned grade
(slope) and specifications for different purposes (e.g. irrigation
planning).
SR
AN
KIR
Consider a natural terrain that needs to be converted into a level
1-1’ for a construction project, as shown in Figure.
For this, some portions of the terrain need cutting, while some
portion demands filling.
In certain situations, the earth from cutting is loaded to fill a
depression or a dipping area as shown. This process is hauling.
KIRAN S R, Lecturer, Dept. of Civil Engineering 68/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
This may be idealized as follows for the purpose of study:
AN
KIR
There arise the necessity to define two important terms – Lead & Lift
SR
carried from the source to the place of deposit or filling.
It is not necessarily the route actually followed.
Measured in units/multiples of:
(i) 50m (for distances ≤250m)
(ii) 250m (for distances >250m and ≤500m)
(iii) 500m (for distances >500m and ≤5km)
AN
(iv) 1km (for distances >5km)
Items shall include loading and unloading.
Carriage by manual labour shall be reckoned in units of 50 metres.
Carriage by animal and mechanical transport shall be reckoned in 1
KIR
km unit.
2 Lift:
SR
Average straight vertical distance through which the earth can be
lifted from the source to the place of deposit or filling.
The vertical distance for removal with reference to the ground level.
Excavation up to 1.5 m depth below ground level and depositing
excavated material on the ground shall be included in the item of
earthwork for various kinds of soil.
AN
Extra lift shall be measured in unit of 1.5 m or part thereof.
Obvious lifts shall only be measured; i.e., lifts inherent in the lead
due to ground slope shall not be measured.
KIR
SR
Generally, for the construction of pavements, there involves earthwork in
cutting or filling, which shall have cross-sections of the shape of
trapezium. Such a solid may be called ”Prismoid”, as shown.
AN
KIR
SR
Roads are generally constructed at the desired gradient, the level
corresponding to which is called Formation level.
To obtain this level, it may sometimes require to raise the original
ground (by filling) or depress the original ground (by cutting).
AN
KIR
SR
The dimensions of the cut and fill are shown here.
AN
KIR
B = top (crest) width of fill / bottom (trough) width of cut
= Formation Width
d = depth of fill / cut, which may vary along the longitudinal axis
N:1 = side slope, expressed as horizontal : vertical
SR
Since the depth of the prismoid varies along its longitudinal axis,
inorder to determine the volume of earthwork,
we consider intermediate sections along the longitudinal axis, as shown.
AN
KIR
SR
all the cross-sections, including the end-sections, are truly vertical.
Formation Level has only longitudinal slope and no transverse
slope.
Ground surface has only longitudinal slope and no transverse
slope.
AN
KIR
SR
For prismoidal earth in filling,
every section is trapezoidal shape with the trough width a
function of formation width (B) and depth (d).
For prismoidal earth in cutting,
every section is trapezoidal shape with the crest width a
AN
function of formation width (B) and depth (d).
KIR
SR
width of the side opposite to Formation level B is obtained as:
= B + 2Nd
Hence, the area of the cross-section becomes:
A = Bd + Nd2
AN
KIR
Since Formation width (B) and side slope (N) are constants, as
the depth of the section increases, the width of the opposite side of
the prismoid (i.e., trough in fill and crest in cut) also increases.
KIRAN S R, Lecturer, Dept. of Civil Engineering 78/89
Introduction IS 1200 Items & its Units Long wall–Short wall Method Centreline Method More about Items of Work
SR
As we divided the prismoidal earth into several equally-spaced sections,
we shall now consider each segments of prismoid separately.
AN
KIR
SR
Case 1: Formation level parallel to Original Ground
=⇒ d= constant, for all sections
AN
KIR
If k = number of prismoidal segments
= number of sections – 1
then, total volume of earthwork = kL(Bd + Nd2 )
SR
Here, d varies linearly between adjacent sections, as shown.
AN
KIR
SR
Volume of Earthwork may be determined by any of the following
methods.
1 Mid-section Formula
2 Average End-area formula (Trapezoidal Formula)
3 Prismoidal Formula
AN
KIR
SR
1 Mid-section Formula: based on mean depth of the segment,
determined by averaging the depth of preceding and succeeding
sections of that segment.
d1 + d2
Mean depth of 1st segment = dm1 =
AN
2
=⇒ Volume of 1st KIR segment = V1 = L(Bdm1 + Ndm1 2 )
SR
1 Mid-section Formula
d2 + d3
Mean depth of 2nd segment = dm2 =
2
=⇒ Volume of 2nd segment = V2 = L(Bdm2 + Ndm2 2 )
........................can be determined upto k th segment.
AN
Volume of earthwork V = V1 + V2 + V3 + ..... + Vk
KIR
SR
2 Average End-Area Formula (Trapezoidal Formula): based on
mean area of the segment, determined by averaging the area of
preceding and succeeding sections of that segment.
A1 + A2
Mean area of 1st segment = Am1 =
2
=⇒ Volume of 1st segment = V1 = L Am1
AN
Volume of 2nd segment = V2 = L Am2
........................can be determined upto k th segment.
Volume of earthwork V = V1 + V2 + V3 + ..... + Vk
KIR
SR
direction
2 Average End-Area Formula (Trapezoidal Formula):
If there are ′ k ′ segments, the above equation may be simplified to
obtain:
L
V = (A1 +Ak+1 +2(A2 +A3 +.......Ak ))
AN
2
KIR
SR
3 Prismoidal Formula:
This is applicable only in cases of odd number of sections or even
number of segments.
In case of even number of sections, the end segment shall be treated
separately.
AN
According to this, if there are ′ k ′ segments, volume of earthwork:
L
V = (A1 +Ak+1 +4(A2 +A4 +.......Ak )+2(A3 +A5 +.......Ak−1 ))
3
KIR
SR
remaining items of work, based on the recent discussions.
AN
KIR
SR
THANK YOU
AN
KIR