JCF-C010 - Installation of Doors - Windows Request

The document is a request form for the installation of doors and windows that checks compliance with approved construction drawings and technical specifications. It contains sections to check that materials have passed required testing, tools are on site, openings are properly aligned and located, dimensions are correct, and safety requirements like scaffolding and PPE are met. The form requires signatures from the contractor, QC engineer, inspector, contractor witness, and project engineer to approve the work.

Uploaded by

katy lee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views1 page

JCF-C010 - Installation of Doors - Windows Request

The document is a request form for the installation of doors and windows that checks compliance with approved construction drawings and technical specifications. It contains sections to check that materials have passed required testing, tools are on site, openings are properly aligned and located, dimensions are correct, and safety requirements like scaffolding and PPE are met. The form requires signatures from the contractor, QC engineer, inspector, contractor witness, and project engineer to approve the work.

Uploaded by

katy lee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Doc.

Code: DPWH – JCF-C-010


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Revision No. 0
INSTALLATION OF
Date 31MAY2017
DOORS & WINDOWS Page No. 1 of 1
REQUEST

CONTRACT ID
CONTRACT NAME:
LOCATION:
DATE REQUESTED: RFI No.:
STRUCTURE AREA/FLOOR ACTUAL INSPECTION DATE/TIME:
LEVEL:
GRIDLINE:
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS FOR CONSTRUCTION DRAWINGS AND TECHNICAL SPECIFICATIONS.
COMPLIED ACTIONS
COMPONENTS REMARKS
DFC YES NO N/A REQUIRED
A. GENERAL
1. Materials passed the required testing or necessary   
inspection (with attached test result or EC)
2. Required tools and equipment are on site   
B. ALIGNMENTS
3. Vertical and horizontal alignment control   
4. Squareness and plumbness of the opening   
C. LOCATION AND DIMENSION
5. Openings are in correct location as per plan   
6. Openings have correct dimensions to fit dimensions of   
jambs/frames
D. CONSTRUCTION SAFETY REQUIREMENTS
7. Stable scaffoldings for safe access of workers on the   
work area particularly on elevated areas
8. Personal Protective Equipment (PPE)   
REMARKS: DFC = Dimension for Compliance

WORK APPROVAL: ☐ Accepted ☐ Rejected


PREPARED BY: CONFIRMED BY: INSPECTED BY: WITNESSED BY: APPROVED BY:
QA
QC

________________________ _______________________ _______________________ ____________________ __________________________


Contractor QC Engineer DPWH Inspector Contractor DPWH Project Engineer

DISTRIBUTION: Contractor QC Engineer Inspector Project Engineer