PRESENTATION SCHEDULE / AGENDA
1. INTRODUCTION ON DRAINAGE SYSTEM
DEFINITION OF DRAIN, THE HYDROLOGIC CYCLE, STORM WATER, PURPOSE & IMPORTANCE OF
DRAINAGE SYSTEM, DRAINAGE IN URBAN & RURAL AREA, ROAD DRAINAGE SYSTEM.
SECTION - 1
INTRODUCTION ON DRAINAGE SYSTEM
DRAIN
1. INTRODUCTION : TERMINOLOGY & DEFINITION
A storm drain, storm sewer (US), stormwater drain (Australia and New
Zealand) or drainage well system (UK) or simply a drain or drain system is
designed to drain excess rain and ground water from paved streets, parking
lots, sidewalks, and roofs. Storm drains vary in design from small residential
dry wells to large municipal systems. They are fed by street gutters on most
motorways, freeways and other busy roads, as well as towns in areas which
experience heavy rainfall, flooding and coastal towns which experience
regular storms. Many storm drainage systems are designed to drain the
storm water, untreated, into rivers or streams.
SEWER V.S. STORM DRAIN
1. INTRODUCTION : STORM WATER V.S. WASTE WATER
STORM WATER (RAINFALL)
1. INTRODUCTION : THE WATER CYCLE
STORM WATER (RAINFALL)
1. INTRODUCTION : THE HYDROLOGICAL CYCLE (MALAYSIA)
GEOGRAPHICAL POSITION OF SARAWAK
TRAFFIC
LOAD
SECTION – 2
DESIGN PRINCIPLES FOR ROAD DRAINAGE SYSTEM
REKABENTUK PERPARITAN DAN PEMBETUNG JALAN
DESIGN PRINCIPLES FOR ROAD DRAINAGE SYSTEM
ENGINEERING DESIGN OF THE ROAD COMPONENTS REQUIRED
FOR ROAD DEVELOPMENT PROJECTS IN SARAWAK
TRAFFIC SIGN DESIGN BRIDGE DESIGN RET. STRUCTURE DESIGN OTHER DESIGN
NEEDS TO COMPLY WITH AUTHORITY’S APPROVED STANDARD & CRITERIA
GENERAL CONSIDERATION
1. THE EROSIVE/DESTRUCTIVE POWER OF FLOWING WATER INCREASES EXPONENTIALLY AS ITS
VELOCITY INCREASES. THEREFORE, WATER MUST NOT ALLOWED TO DEVELOP SUFFICIENT
VOLUME OR VELOCITY SO AS TO CAUSE RAPIDLY DAMAGE A ROAD PAVEMENT AND
FORMATION, EXCESSIVE WEAR ALONG DRAINS OR ALONG EXPOSED RUNNING SURFACES,
CUTS OR FILLS.
3. THE PRESENCE OF EXCESS WATER OR MOISTURE WITHIN THE ROADWAY WILL ADVERSELY
AFFECT THE ENGINEERING PROPERTIES OF THE MATERIALS WITH WHICH IT WAS
CONSTRUCTED. CUT SLOPE OR EMBANKMENT FILL FAILURES, ROAD SURFACE EROSION,
AND WEAKENED SUBGRADES FOLLOWED BY A MASS FAILURE ARE ALL PRODUCTS OF
INADEQUATE OR POORLY DESIGNED DRAINAGE.
THE DESTRUCTIVE POWER OF WATER
THE DESTRUCTIVE POWER OF WATER
THE DESTRUCTIVE POWER OF WATER
TEMUDOK TEMUDOK
SEMUKOI SEMUKOI
ENGINEERING CHALLENGES IN DEVELOPMENT OF ROADS IN SARAWAK
GENERAL REQUIREMENTS
MAIN CRITERIA FOR DESIGNING ROAD DRAINAGE SYSTEM :
A ROAD DRAINAGE SYSTEM MUST SATISFY CERTAIN MAIN CRITERIA IF IT IS TO
BE EFFECTIVE THROUGHOUT ITS DESIGN LIFE :
Table - 1
EXISTING & FUTURE MAJOR RURAL ROAD NETWORK IN SARAWAK (HNDP STUDY PHASE-2)
R5
A
3D VIEW
PROPOSED ROAD
PROPOSED CULVERT
A CATCHMENT AREA
EXISTING ROAD
95
ARI 20 Years
80
Time Concentration (Minutes)
RUNOFF COEFFICIENT
4. FACTORS IN DESIGN :
DESIGN PARAMETERS (C, I,A), GROUND
HYDRAULIC ANALYSIS
CONDITIONS, TOPOGRAPHY, DRAIN TYPE,
(TO ESTIMATE CAPACITY OF THE DRAIN)
MATERIAL, CROSS SECTION, DRAIN SLOPE.
CATCHMENT AREA FOR VARIOUS SURFACE DRAIN DESIGN IN RURAL AREA
SURFACE DRAINAGE DESIGN
SURFACE DRAINAGE DESIGN
SURFACE DRAINAGE DESIGN
DESIGN PRINCIPLES FOR ROAD DRAINAGE SYSTEM
CULVERT DESIGN
CULVERT DESIGN
INTRODUCTION ON CULVERT
1. PRIMARY PURPOSE :
TO CONVEY WATER UNDER A ROADWAY (AS
A FACILITY OF DRAINAGE CHANNEL
CROSSING ROADWAYS).
3. CULVERT COMPONENT :
MAIN CULVERT, INLET/OUTLET HEADWALLS
& WINGWALLS, INLET/OUTLET APRONS,
BEDDING SLABS, FOUNDATION, SCOURING
PROTECTIONS.
4. CULVERT TYPE & MATERIAL :
RC (PRECAST) PIPE, CORRUGATED METAL/
STEEL PIPE (ARMCO), 3-W HDPE PIPE, RC
(CAST IN-SITU) BOX, RC (PRECAST) BOX.
CULVERT CONFIGURATION : SINGLE, TWIN
OR TRIPLE CULVERTS.
CONDITIONS AND REQUIREMENTS OF A CULVERT
3D VIEW
A
PROPOSED ROAD
PROPOSED CULVERT
A CATCHMENT AREA
EXISTING ROAD
RURAL AREA
URBAN AREA
EXAMPLE OF CATCHMENT AREA FOR HYDROLOGICAL ANALYSIS OF A CULVERT DESIGN
EXAMPLE ESTIMATION OF PEAK DISCHARGE FOR INDIVIDUAL CATHCMENT
IDF CURVES
GUIDANCE FOR CULVERT TYPE SELECTION
CAPACITY OF VARIOUS TYPE & SIZE OF CULVERTS FOR A TRIAL ON HYDRAULIC ANALYSIS
SELECTION OF A TRIAL CULVERT FOR HYDRAULIC ANALYSIS
FLOW CHART OF HYDRAULIC ANALYSIS FOR CULVERT DESIGN
CULVERT DESIGN : HYDRAULIC ANALYSIS
CULVERT DESIGN : HYDRAULIC ANALYSIS
Figure 5.9
CULVERT DESIGN : HYDRAULIC ANALYSIS
CULVERT DESIGN CHART – ENTRANCE LOSS COEFFICIENTS (Ke)
CULVERT DESIGN : HYDRAULIC ANALYSIS
CULVERT DESIGN : HYDRAULIC ANALYSIS
CULVERT DESIGN : HYDRAULIC ANALYSIS
CULVERT DESIGN : HYDRAULIC ANALYSIS
CULVERT DESIGN CHART – CRITICAL DEPTH (hc)
CULVERT DESIGN CHART – OUTLET CONTROL NOMOGRAPH
CULVERT DESIGN : HYDRAULIC ANALYSIS
CULVERT DESIGN : HYDRAULIC ANALYSIS
CULVERT DESIGN SUMMARY FORM
FACTOR IN HYDRAULIC DESIGN OF CULVERT
FACTOR IN HYDRAULIC DESIGN OF CULVERT
FACTOR IN HYDRAULIC DESIGN OF CULVERT
KURSUS REKABENTUK PERPARITAN DAN PEMBETUNG JALAN
(ROAD SURFACE DRAIN & CULVERT DESIGN)
SECTION – 2 (Additional)
DESIGN EXAMPLE FOR ROAD SURFACE DRAIN
ROAD DRAINAGE SYSTEM
2. DESIGN EXAMPLE FOR ROAD SURFACE DRAIN & CULVERT
(L.H.S. DIRECTION)
CULVERT C-5
CULVERT C-1
HYDROLOGICAL ANALYSIS
(TO ESTIMATE DESIGNED FLOOD DISCHARGE)
HYDRAULIC ANALYSIS
(TO ESTIMATE CAPACITY OF THE DRAIN)
DESIGN EXAMPLE FOR ROAD SURFACE DRAIN
KURSUS REKABENTUK PERPARITAN DAN PEMBETUNG JALAN
(ROAD SURFACE DRAIN & CULVERT DESIGN)
SECTION – 2 (Additional)
DESIGN EXAMPLE FOR CULVERT
ROAD DRAINAGE SYSTEM
DESIGN EXAMPLE FOR CULVERT C-1
CULVERT C-1
DESIGN EXAMPLE FOR CULVERT C-1
DESIGN EXAMPLE FOR CULVERT C-1
DESIGN EXAMPLE FOR CULVERT C-1
DESIGN EXAMPLE FOR CULVERT C-1
DESIGN EXAMPLE FOR CULVERT C-1
ROAD DRAINAGE SYSTEM
DESIGN EXAMPLE FOR CULVERT C-5
CULVERT C-5
DESIGN EXAMPLE FOR CULVERT C-5
DESIGN EXAMPLE FOR CULVERT C-5
DESIGN EXAMPLE FOR CULVERT C-5
DESIGN EXAMPLE FOR CULVERT C-5
KURSUS REKABENTUK PERPARITAN DAN PEMBETUNG JALAN
(ROAD SURFACE DRAIN & CULVERT DESIGN)
SECTION – 3
ROAD DRAINAGE DESIGN DRAWINGS (EXAMPLE)
ROAD DRAINAGE
ROAD DRAINAGE DESIGN DRAWINGS : SURFACE DRAINS & CULVERTS
SECTION – 4
SPECIFICATION FOR ROAD DRAINAGE WORKS
COMPARISON OF THE STANDARD SPECIFICATION FOR ROAD
WORKS (SSRW) - SECTION 3: DRAINAGE WORKS
CONTENT OF SECTION 3: DRAINAGE WORKS
JKR/SPJ/1988 JKR/SPJ/2013-S3
EXCAVATION AND BACKFILLING FOR DRAINAGE EXCAVATION AND BACKFILLING FOR DRAINAGE
3.2 3.2
WORKS WORKS
3.10 CORRUGATED METAL PIPE CULVERTS NO MORE USED FOR NEW ROAD IN MALAYSIA
JKR/SPJ/1988 JKR/SPJ/2013-S3
ITEM DESCRIPTION ITEM DESCRIPTION
3.4 SURFACE DRAINAGE 3.4 SURFACE DRAINAGE
3.4.1 Surface Drainage Types 3.4.1 Surface Drainage Types
3.4.2 Surface Drain Construction 3.4.2 Surface Drain Construction
3.4.2.1 Unlined Drains 3.4.2.1 Unlined Drains
3.4.2.2 Cast In Situ Concrete Drains 3.4.2.2 Cast In Situ Concrete Drains
3.4.2.3 Precast Concrete Drain Sections 3.4.2.3 Precast Concrete Drain Sections
3.4.2.4 Stone Pitching Drains
3.4.2.5 Sumps ADDITIONAL
3.4.2.6 Half Round Glazed Earthenware Drains
JKR/SPJ/1988 JKR/SPJ/2013-S3
ITEM DESCRIPTION ITEM DESCRIPTION
3.2 EXCAVATION AND BACKFILLING FOR 3.2 EXCAVATION AND BACKFILLING FOR
DRAINAGE WORKS DRAINAGE WORKS
3.2.1 Description 3.2.1 Description
This work shall… This work shall…
Excavation and backfill for pipe culverts… Excavation and backfill for pipe culverts… (deleted)
JKR/SPJ/1988 JKR/SPJ/2013-S3
ITEM DESCRIPTION ITEM DESCRIPTION
3.4.2 Surface Drain Construction 3.4.2 Surface Drain Construction
3.4.2.3 Precast Concrete Drain Sections 3.4.2.3 Precast Concrete Drain Sections
… …
… All precast drain units shall be of a dense and
Porous concrete… impermeable type (additional spec.)
Mass concrete for bases shall be of grade 10/15 Notwithstanding any approval given by the S.O.,
concrete… any defective or broken drain section shall be
replaced by the Contractor at his own expense
before or after laying in position (additional spec.)
Porous concrete… (deleted)
Mass concrete for bases shall be of grade 15
concrete…
3.4.2.4 Stone Pitching Drains
Excavation shall be carried out to the lines and
levels as specified in the Drawings
The constituent materials and construction
methods of stone pitching shall comply with the
appropriate requirements of Section 3.5
Weep holes shall be installed as shown in the
Drawings or as directed by the S.O.
3.4.2.5 Sumps
Sumps shall be constructed of brickwork or stone
pitching in accordance with Section 3.6 and
Section 3.5 or in-situ concrete accordance with
Section 9-Concrete of this Specisication
Foundation to sumps shall be of concrete of a
quality and dimensions indicated in the Drawings
3.4.2.6 Half Round Glazed Earthenware Drains
HRGE for surface drain shall comply with MS 1061
COMPARISON OF CONTENT (DETAIL OF SPECIFICATION)
JKR/SPJ/1988 JKR/SPJ/2013-S3
ITEM DESCRIPTION ITEM DESCRIPTION
3.8 SUBSOIL DRAINS 3.7 SUBSOIL DRAINS
3.8.2 Materials 3.7.2 Materials
3.8.2.3 Filter Cloth 3.7.2.3 Filter Cloth
The synthetic filter cloth shall be a non-woven type The synthetic filter cloth shall be a non-woven type
of approved manufacture… of approved manufacture…
(a) Chemical Composition Requirements (a) Chemical Composition Requirements
(b) Physical Property Requirements refer to (b) Physical Property Requirements refer to
TABLE 3.5(c) Filtration Requirements NEW TABLE 3.5
JKR/SPJ/1988 JKR/SPJ/2013-S3
ITEM DESCRIPTION ITEM DESCRIPTION
3.8 SUBSOIL DRAINS 3.7 SUBSOIL DRAINS
3.8.2 Materials 3.7.2 Materials
3.8.2.4 Cement Mortar 3.7.2.4 Cement Mortar
1:3 cement mortar for use in pipe joints shall Cement mortar shall comply with Sub-Section
comply with Sub-Section 3.5.2.2 3.5.2.2
3.8.2.5 Construction Methods 3.7.2.5 Construction Methods
Excavation for subsoil drains… Excavation for subsoil drains…
Backfill shall then be placed… Trench shall be lined with filter cloth of 500mm
ninimum overlapping (additional spec.)
Backfill shall then be placed…
JKR/SPJ/1988 JKR/SPJ/2013-S3
ITEM DESCRIPTION ITEM DESCRIPTION
3.9 R.C. PIPE CULVERTS 3.8 R.C. PIPE CULVERTS
3.9.2 Materials 3.8.2 Materials
3.9.2.3 Bedding Material 3.8.2.3 Bedding Material
Type A bedding… Type A bedding…
Type B bedding… Type B bedding…
Bedding material shall have a gradation
conforming to the envelope shown in Table 3.1 for
sand and Table 3.2 (Envelope C) for granular of this
Specification (additional spec.)
3.9.3 Excavation and Backfilling for R.C. Pipe 3.8.3 Excavation and Backfilling for R.C. Pipe
Culverts Culverts
3.9.3.1 Excavation 3.8.3.1 Excavation
(a) General (a) General
(b) Trench Method (b) Trench Method
(c) Open Ground Method Where rock or other hard material foundation is
encountered in the trench, it shall be excavated to
a depth below the bottom of pipe design levels of at
least 300mm or 12.5mm per 300mm of fill to be
placed over the top of the pipe, whichever is
greater, up to a maximum of 75% of the internal of
the pipe. The hard material so excavated shall be
replaced with suitable material uniformly
compacted in layers of not more than 150mm
compacted thickness to provide satisfactory
support for the pipe, all to the satisfaction of the
S.O. (additional spec.)
(c) Open Ground Method
COMPARISON OF CONTENT (DETAIL OF SPECIFICATION)
JKR/SPJ/1988 JKR/SPJ/2013-S3
ITEM DESCRIPTION ITEM DESCRIPTION
3.11 PRECAST BOX CULVERTS 3.9 PRECAST BOX CULVERTS
3.11.2 Materials 3.9.2 Materials
3.11.2.1 Precast Boc Culverts 3.9.2.1 Precast Boc Culverts
Precast box culverts shall be of approved Precast box culverts shall be of approved
manufacture complying with Australian Standard manufacture complying with M.S. 1293, or any
Specification 1597 Part 1, or any equivalent equivalent alternative
alternative standard acceptable and approved by
the S.O.
3.11.2.3 Bedding Material 3.9.2.3 Bedding Material
Precast box culverts shall be bedded on Type B Precast box culverts shall be laid on Type A or
bedding as specified in Sub-Section 3.9.2.3 Type B bedding as specified in the Drawings and
as per Sub-Section 3.8.2.3
SECTION – 4 (Additional)
SPECIFICATION FOR PARTICULAR APPLICATION
(EXAMPLE FOR ROAD DRAINAGE WORKS)
SPECIFICATION FOR PARTICULAR APPLICATION (D R A I N A G E)
EXAMPLE SPECIAL REQUIREMENT FOR PRECAST BOX CULVERT
1.24 PRECAST BOX CULVERTS
1.24.1 Culvert Type
Precast reinforced concrete box culverts shall preferably be obtained from the SCIB Concrete
Manufacturing Sdn. Bhd. or approved equivalent. The precast box culverts type shall use
Standard Size Box Culverts with Dry Weather Flow with details of all dimensions to comply
with the details shown on the Drawings.
The Standard Size Box Culverts shall be designed to cater for backfill superimposed dead
load not exceeding 4 m depth (inclusive of pavement) plus 45 units of HB vehicle live loads.
1.25.4 Butt Ended Pipe Culverts with Cast In-Situ Concrete Collars
Cast in-situ concrete collars shall be grade 25/20 concrete and shall be suitably reinforced all
in accordance with Section 9 of the SSRW. The collar dimensions shall comply with the details
shown on the Drawings. The method of construction shall follow that described in Sub-Section
3.8.4.2 of the SSRW for butt ended pipe culverts except for the exclusion of precast concrete
collars.
SPECIFICATION FOR PARTICULAR APPLICATION (D R A I N A G E)
EXAMPLE SPECIAL REQUIREMENT FOR R.C. SPUN PIPE CULVERT
1.26 PILING WORKS
1.26.1 General
Piles shall be of R.C. Square Piles for R.C. cast in-situ box culverts, R.C. pipe culverts, R.C.
crossing and R.C. open drains as specified on the Drawings.
All the R.C. square piles shall be driven until the length or set specified by the S.O. has been
achieved, whichever come first. If the pile achieves the specified set before reaching the
contract length or if the pile reaches the contract length without achieving the specified set, the
Contractor shall refer the matter immediately to the S.O. and shall carry out any further driving
required by the S.O. until the specified set is finally obtained.
The whole of the works and materials are to be in accordance with the MS 1314 Part 3 : 2004
- Precast Concrete Piles : Part 3 : Precast Reinforced Concrete Square Piles (RC Piles) –
Class M, Class J and Class S; and MS 1314 Part 6 : 2004 - Precast Concrete Piles : Part 6 :
Small Reinforced Concrete Square Piles – Small Piles Class RCS-1 and Class RCS-2.
The Contractor shall install 1 no. of 200 mm x 200 mm R.C. test pile at each location of R.C.
box culverts and R.C. pipe culverts, all as specified by the S.O.. Furthermore all the test piles
shall be used as working piles.
KURSUS REKABENTUK PERPARITAN DAN PEMBETUNG JALAN
(ROAD SURFACE DRAIN & CULVERT DESIGN)
SECTION – 5
ROAD DRAINAGE CONSTRUCTION WORKS
ROAD DRAINAGE
4. CONSTRUCTION : ROAD DRAINAGE WORKS
CONSTRUCTION OF CULVERT
CONSTRUCTION OF CULVERT
SECTION – 6
OTHER MATTERS RELATED TO ROAD DRAINAGE:
1. EXAMPLE SUMMARY OF TENDER (SOT) & BILL OF QUANTITY
(BQ) FOR ROAD DRAINAGE WORKS
2. EXAMPLE SCHEDULE OF RATES (YEAR 2018) FOR ROAD
DRAINAGE WORKS
3. EXAMPLE TECHNICAL INSPECTION AND QUALITY CONTROL
DURING CONSTRUCTION OF THE ROAD DRAINAGE WORKS
ROAD DRAINAGE
6. QUALITY CONTROL FOR ROAD DRAINAGE WORKS
QUALITY CONTROL
FOR DRAINAGE CONSTRUCTION WORKS
The QUALITY CONTROL for Road Drainage Works is drawn up to ensure that the
material used and the work carried out are in accordance with the specification
and to establish good and acceptable practice.
The Quality Control System serves as guidelines for both technical inspection
and quality control testing to be carried out for each item of works. This will
assist in the detection of the faulty or substandard materials in the works, and to
enable unsatisfactory workmanship to be detected and rectified.
ROAD DRAINAGE
CONSTRUCTION MATERIAL SPECIFICATION AND QA/QC REQUIREMENTS
CONRETE ROAD SIDE DRAIN CONCRETING FOR RC PIPE CONCRETE WORKS FOR RC BOX
ROAD DRAINAGE
ROAD DRAINAGE SYSTEM
ROAD DRAINAGE
6. QUALITY CONTROL : CULVERT VERIFICATION
ROAD DRAINAGE
6. QUALITY CONTROL : CULVERT VERIFICATION
ROAD DRAINAGE
6. QUALITY CONTROL : CULVERT VERIFICATION
ROAD DRAINAGE
6. QUALITY CONTROL : CULVERT VERIFICATION
ROAD DRAINAGE
6. QUALITY CONTROL : CULVERT VERIFICATION
ROAD DRAINAGE
6. QUALITY CONTROL : CONCRETE CUBE TEST
ROAD DRAINAGE
6. QUALITY CONTROL : CONCRETE CUBE TEST
ROAD DRAINAGE
6. QUALITY CONTROL : CONCRETE CUBE TEST
ROAD DRAINAGE
6. QUALITY CONTROL : CONCRETING WORKS
ROAD DRAINAGE
6. QUALITY CONTROL : CONCRETE CUBE TEST (SUPPLIER)