CLJ - 2010 - 1 - 309 - BC01034 (Extra Case) - Maxim of Equity
CLJ - 2010 - 1 - 309 - BC01034 (Extra Case) - Maxim of Equity
CLJ - 2010 - 1 - 309 - BC01034 (Extra Case) - Maxim of Equity
v.
(2) The argument that the plaintiff was estopped from rescinding
the agreement because the plaintiff had chosen not to I
terminate or rescind the agreement immediately after the
alleged breach but had made progressive payments was
Berjaya Times Square Sdn Bhd
[2010] 1 CLJ v. M-Concept Sdn Bhd 311
(1) Time was the essence of the contract, and there was delay
on the part of the defendant to deliver vacant possession of
the property. The delay was far too excessive and could not
C
be tolerated. (para 59)
For the appellants - R Thayalan (VK Lashmi with him); M/s VK Lashmi & A
Co
For the 1st respondent - Rosli Dahlan (SC Cheah & TM Liew with him);
M/s Lee Hishammuddin Allen & Gledhill
[Appeal from High Court, Kuala Lumpur; Originating Summons No: S3-24-
473-2003] B
[Editor’s note: For the High Court judgment, please see M-Concept Sdn Bhd
v. Berjaya Times Square Sdn Bhd [2004] 4 CLJ 852.]
JUDGMENT
[4] Under cl. 22(1) of the agreement, the completion date for
the property was 36 months from the date of agreement
(completion date). Under the same clause, there was an automatic
extension of three months from the expiry of the completion date. H
The completion date of 36 months expired on 23 August 1998.
The extended period of three months expired on 23 November
1998. However, the construction of the property was not
completed and delivered to the plaintiff within the extended period
or on or before 23 November 1998 as according to the I
agreement.
Berjaya Times Square Sdn Bhd
[2010] 1 CLJ v. M-Concept Sdn Bhd 315
(iv) the defendant shall pay the plaintiff all financing costs, legal
expenses and others incurred by the plaintiff for the purpose
C
of purchasing the property from 27 December 2001 till the
date of the order where the damages would be assessed by
the Senior Assistant Registrar;
(v) the defendant shall pay the plaintiff damages as a result of the
defendant’s breach of the agreement for a sum to be assessed D
by the Senior Assistant Registrar;
(vi) the defendant shall pay the plaintiff interest at the rate of 8%
per annum on all sums to be paid from the date of the order
to the date of full settlement; E
[12] The learned High Court judge granted the orders as prayed F
by the plaintiff. The main issue before the High Court as well as
before us is whether the failure by the defendant to deliver vacant
possession of the property on or before the completion date
constitutes a fundamental breach of the contract which entitles the
plaintiff to rescind the agreement. The learned High Court judge G
answered the question in the affirmative. He reasoned as follows:
The failure of the defendant to deliver vacant possession of the
property after 23 November 1998, as agreed under clause 22(1)
of the agreement, for nearly 4 years and 4 months until the H
present originating summons was filed, amounts to a fundamental
breach of the agreement by the defendant. The delay on the part
of the defendant is excessive and unreasonable given the fact that
the defendant was required to deliver vacant possession of the
property to the plaintiff within 36 months from the date of signing
of the agreement. As under the agreement time is essential, the I
failure on the part of the defendant to deliver vacant possession
at the stipulated time renders the agreement voidable at the option
of the plaintiff (see section 56(1) of the Contract Act 1950).
Berjaya Times Square Sdn Bhd
[2010] 1 CLJ v. M-Concept Sdn Bhd 317
In that case, it was argued by the developer that the only remedy
available is a claim for liquidated damages instead of the
termination of the agreement, but it was rejected by the court.
G
[15] Again, a similar issue was decided by Sibu High Court in
favour of the purchaser in the case of Law Ngei Ung & Anor v.
Tamansuri Sdn. Bhd. [1989] 2 CLJ 181; [1989] 2 CLJ (Rep) 44.
In that case, it was held by Chong Siew Fai J (as he then was)
that:
H
... the defendant had in fact failed to complete the premises within
the time stipulated in the agreement which made time of the
essence of the agreement and the defendant’s failure to complete
the premises amounted to a renunciation or abandonment of the
I agreement and that the defendant had evinced an intention not to
be bound by the agreement.
318 Current Law Journal [2010] 1 CLJ
[20] On the facts of this case, we are unable to hold that the
defendant came to the court with clean hands to rely on the
doctrine. The defendant had clearly breached its contractual H
obligation by failing to complete the construction of the property
by 23 November 1998 or any other promised dates. Even, as at
the date of filing of the originating summons on 20 March 2003,
the defendant had still failed to deliver vacant possession of the
property. I
Berjaya Times Square Sdn Bhd
[2010] 1 CLJ v. M-Concept Sdn Bhd 319
[27] The property was not completed nor delivered to the plaintiff
by the extended period. In fact, on 20 March 2003 when the
plaintiff filed the originating summons seeking for the principal relief B
of a declaration that the plaintiff had rescinded the agreement
together with the other reliefs, the defendant had still failed to
deliver vacant possession of the property.
Analysis A
[45] Secondly, the defendant held the views that the plaintiff was
not entitled to rescind the agreement for late delivery of the C
property but rather the plaintiff was entitled to claim liquidated
damages calculated from day to day at the rate of 12% per annum
of the purchase price from the date of the expiry of the extended
period up to the date of delivery of vacant possession of the
property under cl. 22(2) of the agreement. D
A [49] The High Court judge granted the declaratory reliefs sought
by the plaintiff and this court would only interfere if it can be
shown that the learned High Court judge has exercised his
discretion wrongly. Here, nothing was shown to us to merit our
interference with the exercise of discretion by the learned High
B Court judge. Reasons were given by the learned High Court judge
and those reasons showed that the discretion was not exercised
in a selective and discretionary manner, and neither was it done
arbitrarily or decided upon his own judicial whim (see the speech
of Lord Diplock in Cookson (Widow And Administratrix of the Estate
C of Frank Cookson, Decd) v. Knowles [1979] AC 556, 565 HL). And
Viscount Kilmuir LC in Vine v. National Dock Labour Board [1957]
AC 488 at 500 rightly said that, “the discretion should not be
exercised save for good reason”.
D [50] Here, the crucial issue for determination was whether the
failure by the defendant to deliver vacant possession of the
property on the completion date or on the extended period or on
or before any other date as promised by the defendant constitutes
a fundamental breach of the contract which entitles the plaintiff
E to rescind the agreement. In considering this crucial issue, it must
be borne in mind that time has been made the essence of the
contract. That being the case, s. 56(1) of the Contracts Act 1950
should be invoked and that section provides that failure to
perform within a fixed time in a contract, where time is essential,
F would render the contract voidable.
Their Lordships do not think that this section lays down any A
principle which differs from those which obtain under the law of
England as regards contracts to sell land. Under that law equity,
which governs the rights of the parties in cases of specific
performance of contracts to sell real estate, looks not at the letter
but at the substance of the agreement in order to ascertain
B
whether the parties, notwithstanding that they named a specific
time within which completion was to take place, really and in
substance intended more than that it should take place within a
reasonable time. The principle is well expressed in what Lord
Redesdale said in his well-known judgment in Lennon v. Napper
[1802] 2 Sch. & Lef. 682, which was adopted by Knight-Bruce C
L.J. in Roberts v. Berry 3 D.M. & G. 284, at p. 289. The doctrine
laid down in these cases was again formulated by Lord Cairns in
Tilley v. Thomas L.R. 3 Ch. 61 and by the House of Lords in
the recent case of Stickney v. Keeble [1915] A.C. 386. Their
Lordships are of opinion that this is the doctrine which the
D
section of the Indian statute adopts and embodies in reference to
sales of land. It may be stated concisely in the language used by
Lord Cairns in Tilley v. Thomas L.R. 3 Ch. 61: ‘The construction
is and must be in equity the same as in a Court of Law’.
[52] Continuing at the same page and spilling over to p. 33, this E
was what Viscount Haldane said:
Their Lordships will add to the statement just quoted these
observations. The special jurisdiction of equity to disregard the
letter of the contract in ascertaining what the parties to the
contract are to be taken as having really and in substance F
intended as regards the time of its performance may be excluded
by any plainly expressed stipulation. But to have this effect the
language of the stipulation must show that the intention was to
make the rights of the parties depend on the observance of the
time limits prescribed in a fashion which is unmistakable. The G
language will have this effect if it plainly excludes the notion that
these time limits were of merely secondary importance in the
bargain, and that to disregard them would be to disregard nothing
that lay at its foundation. Prima facie, equity treats the importance
of such time limits as being subordinate to the main purpose of
the parties, and it will enjoin specific performance notwithstanding H
that from the point of view of a Court of law the contract has
not been literally performed by the plaintiff as regards the time
limit specified. This is merely an illustration of the general
principle of disregarding the letter for the substance which Courts
of Equity apply, when, for instance, they decree specific I
performance with compensation for a non-essential deficiency in
subject-matter.
Berjaya Times Square Sdn Bhd
[2010] 1 CLJ v. M-Concept Sdn Bhd 325
A But equity will not assist where there has been undue delay on
the part of one party to the contract, and the other has given him
reasonable notice that he must complete within a definite time.
Nor will it exercise its jurisdiction when the character of the
property or other circumstances would render such exercise likely
to result in injustice. In such cases the circumstances themselves,
B
apart from any question of expressed intention, exclude the
jurisdiction. Equity will further infer an intention that time should
be of the essence from what has passed between the parties prior
to the signing of the contract.
[57] Salleh Abas FJ speaking for the then Federal Court in Sim
Chio Huat v. Wong Ted Fui [1983] 1 CLJ 178; [1983] CLJ (Rep)
363 had this to say of s. 56 of the Contracts Act 1950:
C
However, the rules contained in section 56 of the Contracts Act
are not different from the position arrived at in common law.
Yeow Kim Pong Realty Ltd. v. Ng Kim Pong [1962] M.L.J. 118,
126. The position is this: If in a contract in which time is of the
essence, a party fails to perform it by the stipulated time, the
innocent party has the right either to rescind the contract, or to D
treat it as still subsisting. If he treats it either expressly or by
conduct as still continuing, the contract exists but time ceases to
be of the essence and becomes at large. Consequently he cannot
claim the liquidated damages under the contract unless there is a
provision as to the extension of time. However, this cessation can
E
be revived and so time can be restored to be of the essence by
the innocent party serving a notice to the party in default giving
a new date of completion.
[58] Seah FJ, delivering the judgment of the then Federal Court
had this to say in Ganam Rajamany v. Somoo Sinnah [1984] 2 CLJ F
268; [1984] 1 CLJ (Rep) 123 in regard to time being the essence
of the contract:
In a contract for the sale of land the time fixed by the parties for
completion or performance is not to be strictly construed unless
it is the intention of the parties that time should be of the essence G
of the contract (see Jamshed v. Burjorji A.I.R. 1915 P.C. 83,
Stickney v. Keeble [1915] A.C. 386, Warren v. Tay Say Geok & Ors
[1965] 1 M.L.J. 44, and section 56(1) of the Contracts Act
1950]. Intention may either be express or implied and there are
three cases in which time is of the essence of the contract. H
(a) where the contract expressly states that time shall be of the
essence of the contract (Steedman v. Drinkle [1916] 1 A.C.
275 and Brickles v. Snell [1916] 2 A.C. 599).
(b) where time was not originally of the essence of the contract I
but has been made so by one party giving a notice to the
other. Such notice can only be given after the other party
Berjaya Times Square Sdn Bhd
[2010] 1 CLJ v. M-Concept Sdn Bhd 327
[64] The net result of finding that there has been either a breach
of a fundamental term or a fundamental breach is this. That the
innocent party or the party who is not in default may put an end
to the contract - in the sense that any obligations then
G
outstanding need no longer be performed by either party, and the
innocent party too may sue for damages for any loss suffered as a
result of the defaulting party’s non-performance. The plaintiff here
has done just that. Having rescinded the agreement, the plaintiff
filed the originating summons and sought for all those reliefs and
H
the learned High Court judge rightly granted those reliefs.
G
At this stage of the proceedings, this court was not asked to
determine whether the rescission would result in the plaintiffs not
being able to receive the liquidated damages but in passing I
would say that, as provided by s. 76 of the Contracts Act 1950,
a party who rightly rescinds a contract is entitled to compensation
for any damage which he has sustained through the non-fulfilment
H of the contract. I had in fact made it clear in my ruling that the
plaintiffs’ entitlement to liquidated damages if the developer failed
to complete within 24 months did not in any way take away the
rights of the purchaser to rescind the contract.
[69] While sitting on the High Court bench, in the case of Xavier
I
Kang Yoon Mook v. Insun Development Sdn Bhd (supra), I had a rare
opportunity to consider the same matter. In that case, by a sale
and purchase agreement (“agreement”), the purchaser purchased
330 Current Law Journal [2010] 1 CLJ
[70] I too spoke of the rights of the purchaser in this way (see G
p. 96 of the report):
Applying the above principles to the present case, as time was
provided to be of the essence of the S & P agreement, the
stipulated time period within which the said house had to be
delivered to the plaintiff became an essential condition of the S & H
P agreement. The failure of the defendant to fulfil this condition
would entitle the plaintiff to have an option of treating the S & P
agreement either: (a) as having been repudiated and sue for
damages; or (b) as still continuing. The plaintiff rightly exercised
his option to proceed under (a). I
Berjaya Times Square Sdn Bhd
[2010] 1 CLJ v. M-Concept Sdn Bhd 331