Weekly Report 45
Weekly Report 45
Weekly Report 45
03/11/2014
1 Highlights
2 HSSE
30000
25000
20000
5000
0
27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov
b. Wells
ASH15: exchange of gas line ongoing
Wells test :
o ASH42BST (oil = 50m3 -8 m3, water = 78 m3 -9 m3 , gas=8100 sm3 )
o ASH50 (oil = 44 m3 -6 m3, water = 4 m3 -3m3 , gas=29100 sm3 )
c. Process
V120: visit of capacity to prevent leakage between oil and water compartment.
V4930: instrumentation preventive visit.
E3960 : preventive visit of electrical equipments and reinstallation of
instruments
TEG unit: remove of all equipments and instruments ongoing.
IFRII: preparation of crude loading
Page 2 / 3
ASHTART
03/11/2014
d. Water injection
Z2700: Standard exchange of burners n°7 and n°3, standard exchange of diesel
pump. start up of compressor and control of parameters
Z700B: exchange of engine oil filter, exchange of burners
Z700C: preparation for lifting and exchange of crank shaft ongoing
GIII: end of electrical check in the new electrical room and start of generator at
low charge. Regulation of parameters ongoing
IFRII: preparation of crude loading