Weekly Report 45

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

ASHTART

03/11/2014

Weekly report N°43: 27/10 To 02/11

1 Highlights

 TEG unit: complete overhaul ongoing.


 Z2700: start of compressor after maintenance
 Z700C: preparation for lifting of crank shaft
 GIII: end of electrical check in the new electrical room.
 IFRII: preparation of crude loading

2 HSSE

2.1 Incidents & High Potential Incidents

2.2 HSSE status


 IFRII: safety equipment test in case of crude loading preparation
 IFRII: HARC study of crude loading
 Induction for the new electrical Engineers on site.
 NDT control of the deluge lines on PF2 (pipe out of tolerance to be replaced
urgently)
 HSE committee meeting was organized on PFC
 Investigation of the incident N°9 of crane operator in PF3 on 17/10/2014.
 EBOLA awarness session organized on PFC by site Doctor
3 Operations (TOA)

3.1 Production (TOA-A)


a. Realizations
The realization of ASHTART field during this week is shown in the next table and
graph.

Reporting week YTD


KPI
m3 bbls m3 bbls

Oil Production 6627 41704 265716 1671391


Water
31100 195712 1427712 8981270
Injection
Flared Gas 136278 SCM 4,8 MMSCF 5875100 SCM 207,46 MMSCF
Page 1 / 3
ASHTART
03/11/2014

Weekly report N°43: 27/10 To 02/11

Gas Lift 3541000 SCM 125 MMSCF        


Diesel
337,3 2156    
Consumption

30000

25000

20000

Injected water (m3)


15000
Produced oil (m3)
Flared gas (sm3)
10000

5000

0
27-Oct 28-Oct 29-Oct 30-Oct 31-Oct 01-Nov 02-Nov

b. Wells
 ASH15: exchange of gas line ongoing
 Wells test :
o ASH42BST (oil = 50m3 -8 m3, water = 78 m3 -9 m3 , gas=8100 sm3 )
o ASH50 (oil = 44 m3 -6 m3, water = 4 m3 -3m3 , gas=29100 sm3 )

c. Process
 V120: visit of capacity to prevent leakage between oil and water compartment.
 V4930: instrumentation preventive visit.
 E3960 : preventive visit of electrical equipments and reinstallation of
instruments
 TEG unit: remove of all equipments and instruments ongoing.
 IFRII: preparation of crude loading

Page 2 / 3
ASHTART
03/11/2014

Weekly report N°43: 27/10 To 02/11

d. Water injection

3.2 Maintenance Operations (TOA-M)

 Z2700: Standard exchange of burners n°7 and n°3, standard exchange of diesel
pump. start up of compressor and control of parameters
 Z700B: exchange of engine oil filter, exchange of burners
 Z700C: preparation for lifting and exchange of crank shaft ongoing
 GIII: end of electrical check in the new electrical room and start of generator at
low charge. Regulation of parameters ongoing
 IFRII: preparation of crude loading

3.3 Workover & Drilling (TOA-D)


NTM.