Funil
Funil
178
Main Brazilian Dams III
2. The concrete structures that include the spillway the powerhouse that houses three turbine/generator units.
and intake; the first has four gates and a 7.356 m3/s The intake adjoins the spillway at a 15° angle, and in
discharge capacity; the second is part of the hydraulic turn ends at the right rockfill dam.
power circuit, that includes, a short 50 m penstock and
179
Main Brazilian Dams III
3. GEOLOGY AND GEOTECHNICS OF brown when originating from amphibolite and biotite
THE FOUNDATIONS gneiss, and red silty clay when originating from diabase.
180
Main Brazilian Dams III
The alluvium layer on the right bank terrace was 8 m out along the right slope between the spillway and the
thick and on the left bank it was only 2 m and the coarse main dam and included various soils and rocks, such as
particles varied according to the following locations: colluvium, residual soil/saprolite, decomposed rock
• In the riverbed there could be found mainly clean medium (D3/D4) and sound to decomposed rock (D1/D2).
sand, lightly micaceous, with 1.0 m of pebbles and rock Excavations were up to 35 m deep and blasting
blocks at the base of the layer. heights in decomposed rock were around 20 m deep.
• In the riverbank terraces, alluvium was made up basically In the intake and powerhouse area there were some
of fine silty sand, light grey in colour and mixed with weak areas where the decomposed rock excavations
colluvium soil. and extreme fracturing had to be treated with gunite and
• In the left bank downstream from the diversion tunnel anchored wiremesh.
portal there was a layer of rock blocks of sizes varying The deepest excavations were in the powerhouse area
between centimeters and meters in a 25 by 40 m area. down to El. 747 and in sound rock they reached 33 m
The resistance of the soil, based on SPT tests, was deep along the axis of the units. The excavations of the
low along the river terraces and high in the riverbed. On right and left wall were done in 10 m vertical cuts with
the right terrace the tests required 1 to 2 blow counts 0.5 berms and where required, surface reinforcement was
down to 6.0 m deep. In the riverbed in general the tests with 6 cm thick gunite with fibers, anchored in a 2 x 2 m
required over 15 blow counts, with exception of the net with 1" rebars 2.5 m deep.
investigation SM-22 bore hole in the downstream cutoff In some places where the foundation rock surface of
trench where SPT tests required less than one blow these structures was very fractured or decomposed, the
count, with a high permeability between 10 -2 and weak area was removed and filled with dental concrete
10-4 cm/s. or grout and consolidation grouting was carried out.
181
Main Brazilian Dams III
slopes 1V:1,3H and 1V:1H, with 3 m berms in every layers. The top layers of colluvium had average thickness
10 m heights. Protection of these slopes was with planted of 2.0 m in area 1 and 2.9 m in area 2. In previous studies
grass and sometimes with gunite where grass could not it was classified as fine sand and secondarily as medium
take hold. to coarse sand with fractions of silt and clay, of medium
Excavations in saprolite between El. 785 and the to high plasticity, and considered as MH material by the
decomposed rock in an area subject to tailwater Unified Soil Classification System (USCS).
fluctuations has slopes of 1V:1.3H with berms of 5 m The underlying horizon is a residual soil with average
every 10 m of height and protected with transition and thicknesses of 7.5 m in area 1 and 6.2 in area 2. It was
rockfill. In the intake channel the area of the slopes mainly fine silty clay sand of medium plasticity, and
subject to the reservoir fluctuations were also protected. also classified as MH soils by the USCS.
In the same way as in the stilling basin, the slopes in The estimated volume of these soils was:
decomposed rock (D3) of the spillway were less inclined 1. Borrow Area 1
(1V:1H) and were treated in weak areas with the standard • Colluvium 247,600 m³
gunite, steel wiremesh or fiber and anchored to the rock • Residual Soil 784,300 m³
foundation. 2. Borrow Area 2
In sound rock excavations reached 17 m high with • Colluvium 459,600 m³
vertical cuts and 0.5 m berms, and the deeper cuts were • Residual Soil 549,100 m³
made in the stilling basin area.
The tailrace channel is in decomposed rock (D3) and 4.2. Coarse Grained Soils
at the end in saprolite. Where there was soil or very The prospection of sand and gravel deposits was
decomposed rock the channel was over excavated carried out in the river bed downstream from the dam
between 1 and 2 m below the bottom at El. 765 and filled axis. The depth of the deposits varied, reaching 12 m
in with rockfill for protection. deep as was the case of the one along the dam axis.
The deposits were mainly of medium sand and
4. CONSTRUCTION MATERIALS secondarily of coarse sand and gravel that were tested
in the laboratory. The estimated volume of the deposits
4.1. Soils was 400,000 m³
Based on studies before the preliminary design that
indicated two potential areas for materials for the dam 4.3. Rock Materials
construction and denominated borrow areas 1 and 2, a Bedrock materials were used as coarse aggregate
program for investigations was elaborated to sample soils for concrete, rockfill for the dam and transitions and drains
for laboratory tests. Both borrow areas were located on and were obtained from the excavations for the foundation
the right bank of the Grande river at a distance of about of the structures, the diversion tunnel and channels. Two
1100 m from the dam axis. types of rock were found: sound rock and decomposed
The borrow areas had the same geological to medium decomposed rock, and were used in the dam,
characteristics differing only by the thickness of the cofferdams and various fills.
182
Main Brazilian Dams III
5. DESCRIPTION OF THE MAIN being carried out. The compacted earthfill was raised up
STRUCTURES to the level of the cofferdam crests and the whole structure
was overlayed with a blanket of rockfill for protection. In
5.1. River Diversion and Tunnel the flood season the high river flows were discharged
The construction of the civil works was done in two through the diversion tunnel and overflowed the main dam.
stages. In the first the Grande river was kept in its natural During the dry season of 2002 the protection blanket
riverbed while the diversion tunnel was being excavated of rockfill was removed to complete the construction of
in the left bank and the concrete structures on the right the main earth dam, with the river flowing again only
bank. In the second stage with the upstream and through the tunnel. The design flow for this stage was
downstream cofferdams damming the river bed, the river 1,094 m3/s
was diverted through the tunnel.
The diversion tunnel structure was divided in the 5.2. Main Dam
approach channel, the control structure, the tunnel and The construction of the main dam was planned to
the outlet channel. The approach channel was 164.0 m use the maximum amount of material from the
long, 20.0 wide and narrowing at the end to 14.6 m, excavations of the concrete structures and the diversion
excavations were in soil and rock. The control structure tunnel. Because of the geological-geotechnical conditions
at the upstream portal has two openings for the closure of the foundation, the dam was divided in three typical
gates 5.0 x 11.6 m. The actual tunnel is 211.0 m long sections:one is rockfill with an impervious core, the
with a bottom rectangular cross section 11.6 m wide and second a mixed section of earth and rockfill and the third
semi-circular at the top. The outlet channel is 142.5 m a homogeneous earthfill. The crest of the main dam is at
long and 13.0 to 20.0 m wide from the tunnel to the end El. 811.3.
of the outlet. The diversion tunnel excavations were done The first section on the right bank, adjoining the intake,
in sound and lightly decomposed gneiss. with a length of 25.0 m, is rockfill with an earth core and
The upstream cofferdam was built by dumping rockfill transitions; the upstream and downstream slopes are
across the river flow at about 1 m above the water level. the same: 1V:1.3H; this section of the dam had its
After dumping transition material and sealing, the foundation on decomposed rock.
cofferdam was raised with compacted soil up to The second section toward the riverbed, about 80 m
El. 776.20, which is the diversion elevation for a recurrence in length, has a mixed section with rockfill on the
river flow of 20 years for the dry period of the year. To downstream slope with an inclination of 1V:1.8H and an
prevent a backflow of water through the tunnel from the earth slope on the upstream side, sand drains and
downstream channel outlet, a downstream cofferdam was transitions (Figure 2). This section was founded on
built similar to the upstream one with a crest at El. 773.00. decomposed rock and residual soil. Where the foundation
The cofferdams were built with material from the was on residual soil a cut-off trench 8.0 m wide was
excavations for the foundations of the structures. excavated into the decomposed rock below.
The following diversion scheme with the overtopping The third section is about 270 m long, from the riverbed
of the partially constructed main dam was tested in the to the left bank, and has a typical homogeneous earth
hydraulic models and used for the river diversion: section, founded on an alluvium layer in the riverbed and
gneissic saprolite on the left bank. The upstream slope
First Stage Diversion is 1V:2.1H and the downstream is 1V:1.9H from the crest
The first stage river diversion of the Grande river was down to El. 785.0. From there on and until the
made with the use of two natural septa that were left on incorporated cofferdam crest 12.0 m below, at El. 773.0
the left bank to protect the excavations of the diversion the slope is 1V: 2.0H. In the riverbed a cut-off trench
tunnel and the tunnel's intake and discharge channels. 25.0 m wide had to be excavated through the 9.0 m
The leftover septa heights were derived from the rating alluvium layer and the slopes of the trench were 1V:2H
curves made by CEMIG, based on two river water level in decomposed rock. The dam section has an internal
gauges installed nearby. vertical sand drain with a horizontal base.
The maximum diversion design flow of 2,442 m3/s led For slope protection on the upstream side of the whole
to water levels of El. 778.4 and El. 777.3 at the upstream main earth dam, where the reservoir water level varies, a
and downstream septa, and determined that both should protection layer of graded sound rockfill was placed. On
be left 1.0 m above these elevations: El. 779.4 and 778.3. the downstream side protection of the slope from rain
was made with rockfill and transitions.
Second Stage Diversion
In the dry season of 2001, the second stage diversion 5.3. Intake
started after May, with the river flowing only through the The intake is located between the dividing wall and
tunnel. In the meantime the foundation treatment of the the main earthfill dam. It is a concrete gravity structure
riverbed section and cutoff of the main earth dam were 44.7 m long and 34.0 m high, divided in three blocks.
The upstream side has a 1V:0.1H slope and each block
183
Main Brazilian Dams III
184
Main Brazilian Dams III
185
Main Brazilian Dams III
186
Main Brazilian Dams III
187
Main Brazilian Dams III
The ogee has a Creager profile with the sill at reduce these instabilities a guide wall with a crest at
El. 793.5. The crest is 5,5 m above the approach channel El. 811.0 was included in the design.
and discharges into a stilling basin that is 83.4 m long
from the spillway toe to the basin end and 59.0 m wide.
After the end of the spillway, the rock excavation surface
is overlayed with a concrete slab 0.5 m thick, that
increases to 1.0 m by the time it reaches the channel
bottom at El. 758.0, and maintains this thickness until
the basin end. The slabs are all anchored to the rock
foundation. The basin has an upward slope at the basin
end 12.12 m in length and 7.0 m in height (1V:1.73H)
and the lip is at El. 765.0.
The spillway crest is at El. 811.0 where there is a
roadway to cross the river and the runway rails of the
gantry crane. There is only one gantry crane for the
spillway and intake and it travels all along the concrete
crest structures up to the right gravity wall where the
stoplogs of both structures are stored. The crane has a Photo 3 - View of the Spillway and Powerhouse
capacity of 200 kN on the main hook and 45 kN on the
auxiliary monorail winch. 5.8. Right Rockfill Dam
The reservoir load of the radial gates on the vertical Closing the dam on the right side by the spillway is
spillway piers are absorbed by the concrete post- the small right rockfill dam that abuts against the concrete
tensioned trunnion beams that are also post tensioned gravity dam that extends on the right side of the spillway.
and anchored into the upstream side of the piers. The It is made of rockfill and has an earth compacted core.
cables were laid in a horizontal direction and the upstream
side has a tensioning chamber 3.0 m long at El. 797.5, 6. CONSTRUCTION SEQUENCE
the same elevation of the trunnion beams.
There are four 2,40 x 5,50 x 3,50 m rooms, one for The basis for determining the construction sequence
each gate, on the crest of each pier, that houses the considered the following important aspects:
hydraulic equipment to operate the gates. • Compliance with the project schedule and all
The drainage gallery is at El. 787.0, and 2.0 m above construction phases.
the foundation, runs along the length of the structure with • Coordination of excavations with the production of rock
an access through the dividing wall. The gallery has a aggregate and earthfill for dam construction, to minimize
3.0 x 2.5 m section and the grout curtain was drilled on transport distances.
the upstream side and vertical drains on the downstream • Concrete construction schedules not to interfere with
side. To certify that the uplift would be always low, there the electro-mechanical work and cause erection and
is a top/bottom circular/rectangular 0.8 m drain parallel installation delays.
to the gallery and 8.5 downstream on the horizontal rock • Control of production volumes to reduce peaks and
surface, and another drain along the toe, 5.0 below. There optimize the use of manpower and equipment.
are two drains under slope of the concrete basin surface,
3.0 and 11.0 m below the spillway toe with 2% slopes First Phase: The Grande River Flowing in the
from the center to the basin side walls, to prevent uplift. Riverbed
The approach channel was excavated in soil and The following activities were carried out:
rock at El. 788.0. The channel width diminishes from • Stakeout of the jobsite.
70 m to 40 m. Along the right spillway side wall which • Construction of the campsite and lodgings.
contains the first gate trunnion beam, the upstream part • Construction of access roads.
is designed with a curve to direct the approach flow and • Excavation of the diversion tunnel approach and
has an "L" section to withstand the right rockfill dam discharge channels, except the rock septa for cofferdams.
lateral loads. Adjoining the spillway and the right side • Tunnel excavation.
wall is the concrete gravity dam that joins the concrete • Excavation of the main structures on the right bank,
structures to the right rockfill dam. This concrete structure except the rock septum at El. 780 along the riverbed
is 22.0 m long at the base and 20.0 at the crest, 10.0 m that was used as a cofferdam.
wide and contains the stoplog storage shaft, • Start of concrete works, except the spillway.
7.5 x 14.0 m x 10.5 m deep.
Results from the hydraulic model tests showed that Second Phase: Diversion Through the Tunnel
instabilities were noticed on the right side of the approach • Removal of the septa located at the channel ends.
channel that reached up to gate 4 of the spillway. To • Construction of the cofferdams: upstream (El. 776.2)
188
Main Brazilian Dams III
189
Main Brazilian Dams III
190