Rate Analysis For Concrete Itms - Foundation Column Slab Beam Walls Works
Rate Analysis For Concrete Itms - Foundation Column Slab Beam Walls Works
Rate Analysis For Concrete Itms - Foundation Column Slab Beam Walls Works
SL No Description
Unit Total Qty Rate Amount REMARK
With common burnt clay F.P.S.(non modular) bricks of class (Black Bituminous paint detail not mentioned in item for C.I. cover &
2.1 EACH 2.00 #ERROR! #ERROR!
designation 7.5 Fixing / provision of sleeves details for water meter not clear.
MAKE
Providing and fixing cast iron double flanged butterfly - CONSIDERED:
3 valves conforming to IS 13095 PN 1.6 complete with bolts, - - ADVANCE/ mi
3.1 nuts,
100 MM3.0 DIA
mm thick compressed asbestos gasket. EACH - 1,650.00 - AUDCO/
Providing, fixing, jointing and testing in position the C.I. - ZOLOTO
MAKE
4 class LA pipe conforming to IS :1536 including all necessary - - CONSIDERED:
4.1 fittings
100 MM& DIA
Excavating specials such as
trenches of bends, junctions
requried width etc.,
for Lead
pipes,Joint RM 60.00 1,100.43 66,025.98 NICO
4.2 cables,etc
150 MM DIAincluding
For STP excavation for sockets and dressing of RM 140.00 1,742.48 243,947.03
sides ramming of bottoms depth upto 1.5 m including gtting -
out the excavated soil and then returning the soil as required
5 Pipes, cables etc. exceeding 80inmm dia.including
but not exceeding - -
in layers not exceeding 20 cm. depth
5.1 300 mm dia each deposited layer by ramming watering etc.
cosolidating RM 200.00 175.39 35,077.30
Providing and laying cement concrete 1:5:10 (1 cement : 5 -
and
coarse sand : 10 graded stone aggregateas
disposing of surplus excavated soils 40directed within a
mm nominal
6 lead - -
size) of 50 m CI- LA class pipes including bed concrete as
all-round
6.1 100 standard
per MM DIA design : RM 60.00 #ERROR! #ERROR! 150 mm bed concrete, 75 mm allaround
6.2 150 MM DIA RM 140.00 #ERROR! #ERROR!
-
Providing and making connection to EXT.water main
including cutting the existing C.I.L.A. line and fixing required
7 fitting with loose collars and lead joints including excavation, JOB 1.00 2,600.00 2,600.00
bailing out water, back filling, fixing strainer etc. complete in
all respects.
AUTH. SIGN.
BILL OF QUANTITIES & PRICE SCHEDULE
Civil &structural works for construction of __________________________-(Haryana)
(Rates for all cement concrete items plain and reinforced described below
shall include work from lowest Basement to top of last roof including roof of
machine room, mumty, overhead tanks and parapets above. This section
covers cast in situ structural and architectural as well as precast structural
and architectural concrete.) Note :- Contractor shall use Marble Powder
and Mechanical grinder in repairing joints and honeycombs if
required.
2.1.1 Providing and laying plain cement concrete of specified grade as bed
concrete under foundation, bases for rafts, underground water tank,
building machine equipments, column footing, under floor landings, below
road and pathways,cill, coping, screeding at roof to required slope and
other locations as called for laid, consolidated and cured etc. complete
including finishing the top surface to receive the next course / layer as per
specification and drawing excluding the cost of centering and shuttering.
a. 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm and cum 475 6,273.09
down gauge)
b. 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm and cum - 5,775.26
down gauge)
c. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 20 mm and cum 760 5,421.62
down gauge)
d. 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40mm and cum - 5,200.75
down gauge)
2.2 Damp proof course
Providing and laying damp proof course 40mm thick with cement concrete sqm. - 376.40
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggreate 20mm nominal
size) including providing and mixing of water proofing compound @ 2% of
cement content and providing and applying two layers of bitumen of grade
85/25 and as directed by the Project Manager.
2.3.1 Foundation, raft slab, raft beams, plinth beam, lift pits, sump pits, cum 11,900 7,158.65
pedestals / bases of coloum, wall foundations grade slab etc.
2.3.2 Suspended floors, roofs, balconies, shelves/ counters, stair waist slabs, cum 32,300 8,144.68
folded plate stairs and landings, lintel and floor beams, girders (deep
beams), RCC bands, cantilever projections, slab of tank, arches, other non-
structural elements etc.
2.3.3 Columns, pillars, piers, abutments, posts and struts,wall, offset and cum 3,460 8,280.47
projection of columns, etc.
2.3.4 Retaining Walls, water tank wall, shear wall, lift wall (any thickness) cum 26,290 7,900.81
2.3.5 Parapets, planters, facias, fins, vertical projection of balconies, pergolas, cum 1,241 8,600.34
copings, cills etc. (for all heights as shown in the drawing)
2.4 Extra for add or deduct for using Richer or leaner mix in place of M-25
Concrete.
2.4.1 M-30 instead of M-25 cum 44,200.0 252.45
2.4.2 M-35 instead of M-25 cum
2.4.3 M-40 instead of M-25 cum 33,352.0 463.39
2.4.4 M-45 instead of M-25 cum
2.4.5 M-50 instead of M-25 ( WITH SILICA CONTENT) cum
2.4.6 (a) M-50 instead of M-25 ( WITHOUT SILICA CONTENT) cum 1,658.0 1,818.76
2.4.6 (b) M-60 instead of M-25 ( WITH SILICA CONTENT) cum 5,260.0 3,803.58
Total : 2 : -
3 of
BILL OF QUANTITIES & PRICE SCHEDULE
tion of __________________________-(Haryana)
Amount
Estimated Value Appx. 180 Cr.
2,979,716
4,120,434
85,187,889
263,073,052
28,650,443
207,712,230
10,673,344
11,158,290
15,454,850
3,015,507
20,006,831
652,032,586
4 of
SUMMARY OF CONCRETE (Example for 10 Lac Sqft High Rise Buildings)
Total Super Built Up Area 1000000 Basement 350000
Coffecient of Concrete 0.085
Total Quatity of Concrete 85000 Cum (Including PCC & RCC) 180
PCC Cum 1700 2% 67 35% 35-40%
Raft & Foundation Concrete Cum 11900 14% 32 18% 18-20%
Tower Area Columns & Shear Walls Cum 29750 35% 40 22% 22-24%
Slab & Beam Concrete (Basement & Typical Floors) Cum 32300 38%
Lintals & Counters Slab Cum 850 1%
Basement Retaining Walls, Water Tanks, STP, UG Tanks Cum 4250 5%
VDF & Tremix Flooring, External Road Works Cum 4250 5%
Total Quantity of Concrete Cum 85000 100%
Machinaries & Equipments Unit Qty Price Months Weightahe Amount Salvage Value Recovered Amount
Concrete Equipments
Batching Plant CP 30 / CP 40 Nos 1 4,400,000 4,400,000 40% 1,760,000
Tansit Mixer - 3 Nos Nos 3 2,600,000 7,800,000 55% 4,290,000 3,510,000
Concrete Pump with Line upto 200 Metre Nos 2 2,600,000 5,200,000 50% 2,600,000
JCB Nos 1 2,800,000 2,800,000 60% 1,680,000
(Rates for all cement concrete items plain and reinforced described below shall
include work from lowest Basement to top of last roof including roof of machine
room, mumty, overhead tanks and parapets above. This section covers cast in situ
structural and architectural as well as precast structural and architectural
concrete.) Note :- Contractor shall use Marble Powder and Mechanical grinder in
repairing joints and honeycombs if required.
Providing and laying plain cement concrete of specified grade as bed concrete
under foundation, bases for rafts, underground water tank, building machine
equipments, column footing, under floor landings, below road and pathways,cill,
coping, screeding at roof to required slope and other locations as called for laid,
consolidated and cured etc. complete including finishing the top surface to
receive the next course / layer as per specification and drawing excluding the
cost of centering and shuttering.
1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40mm and down
gauge)
Details of Cost for 1 cum.
Materials :
Stone Aggregate 20mm (Single Size) Cum 0.700 1,871 1,310
Stone Aggregate 10 mm (Single Size) Cum 0.240 1,942 466
Coarse Sand (Zone III) Cum 0.470 1,766 830
OPC Cement @ 300/- Bag Bag 2.79 300 837 1.55 16
Labour 0.096875
Mason Nos 0.10 550 55 139.5
Beldar Only for Laying Nos 0.82 400 326 2.79
Bhisti For Curing Nos 0.70 400 280
Misc. for Viberator, Curing, Motor Etc. @ 2% 82
Indirect Costs
Transportation of Concrete & Materials Nos 1.00 30 30
Tools & Machinaries, Plant, Pump, TM, Tower Crane etc. Nos 1.00 309 309
Total Cost - A 4,525
Water & Electricity Charges 2% 2% 91
EPF 12.5% & ESI 4.5% = 17% 17% 112
Total Amount - B 4,728
Other Heads, Salary, Safety, & Site Management @ 2.5% 2.50% 118
Add Contractor Profit @ 7.5% 7.50% 355
Rate for 1 Cum 5,201
Providing and laying damp proof course 40mm thick with cement concrete 1:2:4
(1 cement : 2 coarse sand : 4 graded stone aggreate 20mm nominal size) including
providing and mixing of water proofing compound @ 2% of cement content and
providing and applying two layers of bitumen of grade 85/25 and as directed by
the Project Manager.
Providing & laying cast - in - place structural controlled design mix cement
concrete of M25 grade using pump with 20mm down gauge coarse aggregates
excluding cost of centering, shuttering and steel reinforcement but including cost
of making shear keys and provision of construction / control joints in various
locations, laid, consolidated and cured, item to include all structural items like
base raft, ramp, column, column capitals, wall, footings, equipment foundations,
fins, mullions, beams, lintels, pergola, chajja, facia, parapet, railing, slab, trenches,
drains and sumps etc. of any shape and sizes. The rates of concrete to include the
cost of Fly ash /admixtures / plasticisers/superplasticers/ bonding agent to
achieve specified strength and to facilitate pumpable concrete etc complete for
all height and level.
Foundation, raft slab, raft beams, plinth beam, lift pits, sump pits, pedestals /
2.3.1 bases of coloum, wall foundations grade slab etc.
Details of Cost for 1 cum.
Materials :
Stone Aggregate 20mm (Single Size) Cum 0.570 1,871 1,067
Stone Aggregate 10 mm (Single Size) Cum 0.280 1,942 544
Coarse Sand (Zone III) Cum 0.425 1,766 750
OPC Cement Bag 6.80 300 2,040 340
Flyash @ 20% replacement of Cementecious Content Kg 68.00 2 136
Admixture Normal (1.5 to 2%) of Cement Content Kg 6.80 55 374
Labour
Mason Nos 0.17 550 94
Beldar Only for Laying Nos 1.00 400 400
Bhisti For Curing Nos 0.90 400 360
Misc. for Viberator, Curing, Motor Etc. @ 2% 115
Indirect Costs
Transportation of Concrete & Materials Nos 1.00 30 30
Tools & Machinaries, Plant, Pump, TM, Tower Crane etc. Nos 1.00 309 309
Total Cost - A 6,219
Water & Electricity Charges 2% 2% 124
EPF 12.5% & ESI 4.5% = 17% 17% 165
Total Amount - B 6,508
Other Heads, Salary, Safety, & Site Management @ 2.5% 2.50% 163
Add Contractor Profit @ 7.5% 7.50% 488
Rate for 1 Cum 7,159
Suspended floors, roofs, balconies, shelves/ counters, stair waist slabs, folded
plate stairs and landings, lintel and floor beams, girders (deep beams), RCC
2.3.2 bands, cantilever projections, slab of tank, arches, other non-structural elements
etc.
2.3.3 Columns, pillars, piers, abutments, posts and struts,wall, offset and projection of
columns, etc.
2.3.4 Retaining Walls, water tank wall, shear wall, lift wall (any thickness)
2.4 Extra for add or deduct for using Richer or leaner mix in place of M-25 Concrete.